quality assurance & accountability project · routinely and systematically monitored and...
TRANSCRIPT
Date: 25th April, 0930-1600 | 26th April; 09:30-1430 CEST
Location: Solidarites International, 89 Rue de Paris, 92110 Clichy, France
Attendees: Oxfam: Eva Niederberger, James Brown
SI: Aude Lazzarini, Laurène Barlet
GWC: Franck Bouvet
UNICEF: Carla Daher, Masumi Yamashita
Groupe URD: Lisa Daoud
ACF: Tom Heath
Objectives:
• Review progress made to date, identify challenges and ways forward
• Discuss conceptual models and agree how they should be applied in practice
• Agree how the project can be communicated to external stakeholders
• Develop project roadmap based on new timescale
• Agree planning for South Sudan, Colombia and key outputs
Day 1:
For overview, see p.3
Day 2: Project planning
MA
Y
GBV Stocktaking Workshop
First ro
un
d o
f co
un
try
vis
its
Mo
nth
ly Q
AA
P T
WG
Ca
lls /
Up
date
s
South Sudan Visit 1
Guidance note table of contents
Literature review final draft
JU
N
Colombia visit
JU
L
Re
mo
te
su
pp
ort
AU
G
Guidance note draft 1
SE
PT
Phase II concept note
Se
con
d r
oun
d o
f
co
un
try v
isits
OC
T
Guidance note draft 2
Communications strategy
NO
V
DE
C
Guidance final draft
Quality Assurance & ACCOUNTABILITY PROJECT:
TEAM REVIEW MEETING NOTES
GBV Stocktaking workshop:
The QAAP will be presented at the Stocktaking workshop: Lessons on promoting the dignity, safety,
health and privacy in humanitarian action organised by the GBV AoR, the IASC GBV Guidelines
Implementation Team, IOM and UNICEF. This will be an opportunity to raise awareness of the QAAP
project amongst participants (including shelter, CCCM and WASH sector coordinators in Bangladesh,
Iraq, Nigeria, Somalia and South Sudan) and to learn from existing GBV risk mitigation projects and
good practice.
South Sudan Visit 1:
The visit to South Sudan will be conducted by James and Helen from 20-31st May. The team will visit
field locations in Malakal, Mingkaman and Mangateen and further develop the quality analytical
framework.
Guidance note:
The QAAP Guidance note is a key output of the project and will be drafted progressively between
May and December 2019. An initial table of contents (ToC)will be proposed at the end of May,
followed by a first draft in August, a second draft in October and a final draft in December. The QAAP
TWG will have the opportunity to review and comment on these drafts as they are developed.
Colombia visit:
The Colombia visit will take place between 2-9 June.
Literature review:
The literature review will be circulated to the QAAP Team and TWG in mid-June for comment.
Phase II concept note:
Achieving the long-term behaviour change amongst NHWCPs and partners to ensure that quality is
routinely and systematically monitored and improved will require ongoing efforts. In order to secure
funding to continue the QAAP beyond 2019, a concept note setting the direction and objectives for a
QAAP Phase 2 will be drafted in September.
Communications strategy:
Ensuring that the findings, guidance and recommendations of the QAAP are effectively disseminated
to different stakeholders will be an important driver of the overall project impact. The communications
strategy developed by October will ma key stakeholders and identify communications and
engagement channels for each. The communications strategy will be used to plan dissemination and
engagement opportunities over the final quarter of the project. The QAAP TWG will be engaged
through monthly calls and updates from June.
PARIS MEETING PRESENTATION
QUALITY ASSURANCE &
ACCOUNTABILITY PROJECTREVIEW MEETING: PARIS
25th April 2019
Page 2
SESSION PLAN: THURSDAY
MORNING
0930 Introduction:
• Objectives setting
• Progress overview
1000 Conceptual models of quality
• Presentation of literature review
• Discussion around different models
1100 Break
1130 Presentation and discussion of the two field visits
• Bangladesh
• Myanmar
1230 Lunch
AFTERNOON
1330 Presentation and review of quality frameworks
• Process centred (Bangladesh)
• Outcome monitoring (Myanmar)
1430 Break
1500 Communication, dissemination
• Engagement of TWG
• Working with other initiatives
• Wider communications
Page 3
SESSION PLAN: FRIDAY
MORNING
0930 Day 1 review
1000 Project road map
• Guidance and advocacy
• Second round of visits
• Remote support to countries
1100 Break
1130 Planning for South Sudan, Colombia
1230 Lunch
AFTERNOON
1330 Wrap-up
1430 Break
1500 Flexible time
Page 4
OBJECTIVES
THURSDAY
• Review progress made to date, identify challenges and ways forward
• Discuss conceptual models and agree how they can be applied in practice
• Review quality analytical frameworks and agree way forward
• Agree how the project can be communicated to external stakeholders
FRIDAY
• Project roadmap
• Planning next steps
Page 5
PROGRESS REVIEW
DESK REVIEW
• Draft to be shared after this meeting
FIELD VISITS
• Bangladesh, Myanmar completed
• South Sudan (May)
• Colombia (June)
QUALITY FRAMEWORK
• 2 approaches developed
Page 6
ACTIVITY REVIEW
• Pre-visit phase• Inception meeting
• Literature review
• Develop concept sketch protocol
• Pre-visit preparation
• Visit each country – Visit 1• Initial meetings
• Make protocol specific
• Perhaps do an assessment
• Between visits• Provide external support on quality monitoring
process in contexts
• Provide tools for the contexts to monitor the process
• Visit each country – Visit 2• Review activities and monitoring data
• Continue to support protocol for quality monitoring
• Do assessment (if not completed during first visit)
• Post-visit phase• Final meeting
• Reports, guidance and Advocacy
CONCEPTUAL MODELS
Page 8
DMAIC
DEFINE: Objectives and processes (WHAT & HOW)
• Strategic operational framework (SOF)
• Humanitarian Response Plan (HRP)
• Contextualised standards document
MEASURE:
• Data collection, sharing
ANALYSE:
• Response level, identify priority issues and root causes,
control/influence/accept
IMPROVE:
• Jointly agree corrective action to control / influence
• Implement improvements
• Continue to MEASURE changes
CONTROL:
• Continue to monitor
• Capture lessons, adaptations to response documents
The Define – Measure – Analyse – Improve – Control (DMAIC) methodology is a structured
problem-solving technique that builds upon the PDCA cycle. It is one of the core tools used
in the Six Sigma quality management approach developed by Motorola in 1980 and widely
used in manufacturing and business processes. The slide shows how this process could be
adapted to the humanitarian WASH sector as the basis of a Quality Assurance System.
Page 9
THE DONABEDIAN MODEL
Structure Coordination Resourcing EvidenceOrganisational
capacity
Process Needs assessment
Analysis Project design Implementation
Outcomes Activities Outputs Outcomes Impact
Avedis Donabedian was a physician and founder of the study of quality in health care and
medical outcomes research. His approach for evaluating the quality of care is widely used
and conceptualises the measurement of quality into three components: structure, process
and outcomes. In this model, outcome measures are the ultimate validators of quality,
however they are affected by both process factors and structural factors in a causal chain
(examples given in the slide are not exhaustive).
Page 10
THE SERVQUAL MODEL
The SERVQUAL Model is an approach to measuring quality in the service sector, from the
perspective of customers or service users. The model comprises of a conceptual model and
a questionnaire which is administered to users to quantify their expectations and experience
of a service along different dimensions. The model has been applied and adapted widely in
a variety of contexts to measure the quality of services.
The five dimensions of service quality were derived from a systematic analysis of over 100
aspects of quality initially proposed in literature. The model was eventually reduced to five
dimensions found to be independent, stable and robust. They are defined as:
Reliability: the firm’s ability to perform the promise service accurately and dependably
Assurance: knowledge and courtesy of employees and their ability to inspire trust and
confidence
Tangibles: physical facilities, equipment and appearance of personnel
Empathy: caring and individualized attention paid to customers
Responsiveness: the firm’s willingness to help customer and provide prompt service
Page 11
THE “QUALITY CHAIN”
Links the processes in the project cycle with the results chain
The quality of what we do it throughout the project cycle influences what is
achieved throughout the results chain
Impact is the “ultimate validator of quality” but…
The further down the results chain, the more difficult to measure
Measuring outcomes doesn’t diagnose the causes of low quality
The level of process monitoring we do of the project cycle affects our
confidence in the assumptions made in the results chain
The quality chain can be proposed as a way to link ‘quality of process’ with ‘quality of results’
and shows that outcomes are somewhat dependant on the quality of assessment, analysis,
design and implementation.
Page 12
EA
SIE
R T
O M
EA
SU
RE
HIG
HE
R C
ON
FID
EN
CE
ASSUMPTIONS MADE AT
EACH STAGE:
(POTENTIAL ‘QUALITY
GAPS’)
If impact is the ultimate measure of quality, the further down the quality chain we can
measure the more confident we can be in our understanding, because there are fewer
assumptions needed (the measure is more direct). Monitoring results further down the
quality chain, however, becomes more challenging as output-level results typically rely on
making measurements of behaviours and perceptions. Attribution of outcomes to response
activities may also be difficult to demonstrate.
Page 13
THE ‘ENABLING ENVIRONMENT’:
• Resources
• Coordination
• Organisational capacity
• Evidence / Learning
The above diagram illustrates how the enabling environment, project cycle and results
causal chain are related, and how measuring of processes and measuring of results fit into
the system. Process monitoring of the project cycle (right hand side) can be carried out
through the use of checklists as proposed by URD 2018 in the COMPAS handbook (other
process checklists have been developed for example ACF’s Project Quality Management
Tool). These checklists measure to what degree each process in the project cycle has
followed a list of important actions or considerations.
Results are monitored at different stages along the causal chain, from activity monitoring
(e.g. construction supervision) through to impact evaluations.
Information from each level of monitoring should be fed-back to inform and improve different
stages in the project cycle. For example:
Supervision of activities, quality control and output monitoring is fed back to improve
implementation and provide progress updates e.g. if latrines are being constructed poorly,
additional capacity building of daily labour may be required
Outcome monitoring feeds back to inform changes in project design e.g. if latrines
constructed are not being used, changes may need to be made to the siting or design of
superstructures.
Impact monitoring feeds back to inform an understanding of needs e.g. increasing incidence
of diarrhoea may change our prioritisation of public health risks in a particular location
Monitoring of results alone does not necessarily provide sufficient information to design
corrective action but combined with process monitoring using agreed checklists they can
guide the first steps in diagnosing problems.
FIELD VISITS
Page 16
BANGLADESH: COX’s BAZAR
• Visited 9 camps in Kutupalong
• Interviewed 26 KIs (16 orgs)
• Workshop with 40 participants (25
orgs)
DRAFT ACTION PLAN
ADAPTED QUALITY FRAMEWORK
• Limited follow-up from country
THE HUMAN LENS
PARTICIPATION,
INCLUSION,PROTECTION
THE RESOURCE LENS
EFFICIENT, PRIORITISED, SUSTAINABLE
THE TECHNICAL LENS
APPROPRIATE,EFFECTIVE, RESPONSIBLE
SUPPORTING ENVIRONMENT
COORDINATED, SUPPORTED, RESOURCED,
INFORMED
Page 18
Principle Criteria Example practices from Bangladesh Example indicators for Bangladesh
Participation: The WASH response is based upon meaningful participation
with persons of all gender identities, ages, disabilities and backgrounds
Sector-standard designs for WASH facilities are based on the results
of consultation
% Communities express satisfaction that WASH actors have listened to their feedback
and made changes in programme where possible; % of WASH Committees fulfilling
requirements of minimum representation by people from different groups; # of people
who have been involved in community consultations (disaggregated by gender, age,
disability
Feedback: The WASH stakeholders seek and act upon where necessary ,
feedback and complaints from persons of all gender identities, ages,
disabilities and backgroundsFeedback and complaints collected by different agencies are
summarised at the sector level to inform sector approaches
Time between complaint - action - feedback; Number of complaints by theme and
gender/age/disability; # blocks / camps covered by complaints mechanisms; % people
who can identify an appropriate feedback mechanism;
Communication: The WASH stakeholders communicate clearly and
respectfully with affected people, including those with physical, sensory and
intellectual disabilities, persons with mental health disabilities and older
people WASH field workers are able to receive and refer feedback and
answer frequently asked questions in an appropriate language
# beneficiaries per community volunteer / field staff; % field staff speaking
Rohingya/Chittagonian; % Communities report that key information is clearly
communicated in appropriate languages and reaches all sections of the community using
context specific channelsAccess: The WASH stakeholders provide equitable access to information,
services and resources to all affected persons
Access to WASH services is monitered and results disaggregated by
sex, age, disability so that gaps may be identified Latrine use by gender, age, disability; People per latrine by gender, age, disability;
Safety: The WASH stakeholders prioritise do no harm; actively monitor and
addresse the safety of affected persons
Safety risks and mitigation measures in place are monitered and
results disaggregated by sex, age, disability
Safety perception; use of facilities by day/night; 'safe' standard designs (safety audit
using latrine checklist); % of women and girls who feel safe using a water facility
Adapted: The WASH response is based upon a systematic, objective and
ongoing analysis of the context and an impartial assessment of needs, risks,
vulnerabilities and capacities of different groups
The WASH sector collects and shares needs assessments
conducted by partners;
The WASH response plan includes strategies for responding to the
different needs of vulnerable groups
Vulnerable groups are identified and used to disaggregate data collection; Where access
for some groups is insufficient, or inequitable, action is taken to address specific needs /
barriers; % of women, girls, elderly or mobility impaired people who cannot safely
access latrines, provided with alternative safe sanitation options (adult potties, container-
based sanitation)
Prepared: The WASH response identifies future hazards and acts to mitigate
risks Preparedness plans have been developed at a sector / inter-sector
level for the priority risks identified
WASH sector has identified key hazards (monsoon, cyclone, AWD outbreak etc.) and has
developed plans for preparedness and immediate response, either as part of inter-sector
preparedness planning or individuallyTimely: The WASH stakeholders are responsive to changing needs,
capacities and contexts and make decisions and act without unnecessary
delay.
Alerts (full latrines, lack of water etc.) are addressed quickly;
Decommissioning of latrines is conducted without delay; Time between alert and action for desludging; water point repair; decommissioningStandards: The WASH response meets agreed technical humanitarian
standards based upon relevant evidence, guidance and best practice
(Sphere, national standards, or as appropriate)
Key Sphere / national WASH minimum standards have been
defined for the response, along with standard options for meeting
them and a monitoring framework to measure compliance; Relevant Sphere standardsIntegration: The WASH response appropriately integrates with different
sectors and approaches (health, cash, community engagement...) in order to
achieve programme objectives
Data from health sector is used to monitor WASH disease and
integrated actions are taken in the case of an outbreak; Market-
based approaches are considered for WASH NFIs;
Environmental: The WASH response identifies, communicates and mitigates
the risk of negative impacts to the environment from WASH interventions
Aquifer monitoring - water levels and water quality (F.Coli / chemical)
FSM effluent monitoring - BOD/COD of effluent discharged above
ground
BOD/COD of FSM effluent discharged above ground; Presence of OD 'hotspots'; Static /
dynamic water level at tubewell / borehole; Water quality at deep and shallow aquifer; Controlled: The WASH response includes sufficient quality control
mechanisms to identify deficiencies in design and implementation of WASH
services Supervision of construction activities; Infrastructure audit; % of latrines that pass inspection before being opened to use;
Transition: The WASH response transitions as early as possible away from
emergency approaches towards those that are more efficient based on an
analysis of the life-cycle costs
Identify indicators and define indicators for phasing of approaches
depending on emergency phase in master plans; Ensure key
transition activities (e.g. decommissioning of emergency tube wells
and latrines) is done in consultation with the local community. % of new facilities constructed that meet guidance on transitional approaches
Collaboration: The WASH response is developed and run in collaboration with
local communities and local actors, building capacity where required
Identify government and community stakeholders and ensure they
are included in sector strategy and decision making; Jointly identify
and plan for capacity building of local actors; % of new facilities constructed with a handover plan agreed with local service providersIndependence: The WASH response is designed to reduce dependence on
imported equipment, chemicals and spare parts, fuel supplies, or staff with
specialised skills not available locally
Carry out a market assessment to identify what is available at local /
national level; Identify any key items required for O&M that are not
available locally;
% of water supply systems (boreholes, treatment, pumping, distribution) where O&M
can be handed over to local service providers / authorities
HU
MA
N L
EN
ST
EC
HN
ICA
L L
EN
SR
ES
OU
RC
E L
EN
S
Page 23
MYANMAR: RAKHINE
• Visited 4 camps in Sittwe and
Pauktaw
• Interviewed 36 KIs
• Workshop with 14 participants (11
orgs)
DRAFT ACTION PLAN
COMMITMENT FROM CLUSTER
ADAPTED QUALITY FRAMEWORK
During the Myanmar mission an action plan was developed jointly with the Myanmar WASH Cluster to begin using the framework for Rakhine level reporting from the beginning of the Q3 period. Remote support will be provided to enable the cluster to achieve this.
Page 24
MODULAR APPROACH
CoordinationPublic Health
ProtectionCommunity
Engagement
x y z
Page 25
FRAMEWORK COMPONENTS
During the Myanmar visit an alternative framework was developed to reduce the number of indicators and to focus measurements on core outcomes. The objective of this framework is to:
• SIMPLIFY getting key information from the field level to coordination
• FOCUS on tracking the most important indicators of success
• CLARIFY the minimum expectations for each stage of the programme cycle This framework will be tested and further developed during the South Sudan and Colombia missions.
Page 26
FRAMEWORK COMPONENTS
• Focus area objective
• Key Performance Indicators (KPI):
• What are the most important measures of success?
• What information do we need to design programmes, trigger alerts, take
corrective actions?
• What is useful to track over time?
Page 27
FRAMEWORK COMPONENTS
• Expectations for “good quality” processes, actions:
• Programme phase Assessment Planning Implementation Monitoring
• Based on existing guidance
• Aim to be practical to carry out
• Critical questions to support the KPIs
Page 28
GENERAL FINDINGS
• 'Quality’ is already being measured to some degree
• Limited harmonisation of approaches
• Limited sharing response-level analysis
• Call for strengthened compliance role for cluster / sector
• Different levels of engagement with coordination platform
• Good knowledge of standards, but limited use in monitoring