qty take off presentation-hvac
TRANSCRIPT
1.1 WATER SIDE
1.1.1 Countable Items
Count qty of items by tag no wise/capacity wise/size wise from the drawing and schedule.
Record the qty in hard copy and xls sheet as floor/zone wise.
Compare the takeoff qty with BOQ qty.
Find out difference in items qty.
If any deviation in items qty,RFI to be raised.
Basic unit of measurement – nos, set
3
1.1 WATER SIDE
1.1.2 Measurable Items
Measure qty of items size wise from the drawing.
Record the qty in hard copy and xls sheet as floor/zone wise.
Compare the takeoff qty with BOQ qty.
Note down the Scale of drawing and use particular scale/conversion.
Find out difference in qty.
If any deviation in items qty,RFI to be raised.
Basic unit of measurement – meters
4
1.1 WATER SIDE
1.1.3 Assumable Items
List of out the assumable items.
Connect these items to primary measure/Count items qty.
Calculate the qty from primary items qty respectively.
Record the qty in hard copy and xls sheet as floor/zone wise.
Compare the takeoff qty with BOQ qty (if avail)
Finalize the qty
Basic unit of measurement – nos,liters,meters,sq.m
5
1.1 WATER SIDE
1.1.3.1 Assumable Items-Pipe Insulation
List out dia wise pipes take off qty.
Note down the thickness of insulation as per specification ,drawing ,BOQ.
Arrive and Segregate the pipes insulation qty based on locations.(exposed or conditioned)
Compare the takeoff qty with BOQ qty and finalize the qty.
Application(in general)Conditioned locationExposed location
6
Example
S.No ItemsPipe dia in
mmPipe qty in mtr Pipe Insulation qty in mtr
Conditioned area -25 mm thick
1 Chilled Water Pipes 25 25 25
Roof/Exposed area-50mm thick
2 Chilled Water Pipes 25 53 53
noteConditioned location -25 mm insulation thickExposed location -50 mm insulation thick
1.1.3.1 Assumable Items-Pipe Insulation
7
1.1 WATER SIDE
1.1.3.2 Assumable Items-Pipe Cladding
Indentify the requirement of cladding on pipe insulation as per speciation.
Arrive the qty of cladding(sq.m) over pipe insulation.
Record the qty in hard copy and xls sheet as floor/zone wise.
Compare the takeoff qty Compare the takeoff qty with BOQ qty if available and finalize the qty.
Application In generalCladding in Exposed area Pipe insulation thick 50mm
8
Pipe
nominal
dia in mm
Pipe outer dia
in mm
Ins thick both
side in mm
Pipe dia with
ins in mm
Pipe ins qty in
mtr
Perimeter m
(3.14 x D)
Surface Area
Cladding(Sq.m)
a a' b c=a*b d e=c*3.14 f=d*e
20 26.7 100 126.7 50 0.40 19.9
25 33.4 100 133.4 50 0.42 20.9
32 42.2 100 142.2 50 0.45 22.3
notePipe outer dia as per ASTM sch 40Exposed location 50mm insulation thick
1.1.3.2 Assumable Items-Pipe Cladding
Perimeter calculationPerimeter = 3.14 * D
Where D- Diameter of pipe with insulation
Assume 50mm insulation thickness
Exposed location 50mm insulation thick
9
1.1 WATER SIDE
1.1.3.3 Assumable Items-Pipe Supports(Chilled water)
List out pipes qty size wise “with insulation” from the take off qty.
Find the supports distance by specification and drawing.
Arrive the supports qty size wise from the support distance.
Compare the takeoff qty with BOQ qty (if available.)
Finalize the qty
10
Pipe
nominal dia
in mm
Pipe outer dia
in mm
Ins thick both
side in mm
Pipe dia with
ins in mm
Pipe qty in
mtr
Support
spacing in
mtr
Support
(hangers)
qty in nos
a a' b c=a*b d e f=d/e
20 26.7 100 126.7 50 2 25
25 33.4 100 133.4 50 2 25
32 42.2 100 142.2 50 2 25
Pipe
nominal dia
in mm
Pipe outer dia
in mm
Ins thick both
side in mm
Pipe dia with
ins in mm
Pipe qty in
mtr
Support
spacing in
mtr
Riser Clamps
qty in nos
Riser
support(angle/
channel)qty in
mtr
Ceiling suspended supports
Riser supports
1.1.3.3 Assumable Items-Pipe Supports(Chilled water)
in mm mtrmtr
a a' b c=a*b d e f=d/e g=0.4*f
20 26.7 100 126.7 50 2 25 10
25 33.4 100 133.4 50 2 25 10
32 42.2 100 142.2 50 2 25 10
Pipe
nominal dia
in mm
Pipe outer
dia in mm
Ins thick both
side in mm
Pipe dia with
ins in mm
Pipe qty in
mtr
Support
spacing in
mtr
Support
clamps
qty in nos
Support(angle
/channel)qty
in mtr
Support MS
plate qty in
no
a a' b c=a*b d e f=d/e g=(0.4+0.4)*f h=f
20 26.7 100 126.7 50 2.5 20 16 20
25 33.4 100 133.4 50 2.5 20 16 20
32 42.2 100 142.2 50 2.5 20 16 20
note:
per support 0.4m length assumesd
per support 0.4m height assumesd
MS plate size 200x200x5 mm
50mm thick pipe insulation
Roof supports
11
1.1 WATER SIDE1.1.3.4 Assumable Items-Insulation vapor barrier
List out pipes qty size wise “with insulation” from the take off qty.
Find out pipes surface area
Arrive the qty of vapor barrier from the surface area.
Record in xls or hard copy .
Finalize the qty
12
Pipe nominal
dia in mm
Pipe outer dia
in mm
Ins thick both
side in mm
Pipe dia with
ins in mm
Pipe qty in
mtr
Perimeter in
m
(3.14 x D)
Surface Area
(Sq.m)
Vapor Barrier-
ltr(2sq/ltr/coat)
a a' b c=a*b d e=c*3.14 f=d*e g=f/2*2coat
20 26.7 100 126.7200 0.40 79.6 79.6
2533.4 100 133.4
200 0.42 83.8 83.8
32 42.2 100 142.2200 0.45 89.3
89.3
note pip insulation thick 50mm
1.1.3.4 Assumable Items-Insulation vapor barrier
note pip insulation thick 50mm
13
1.1 WATER SIDE1.1.3.5 Assumable Items-Insulation Adhesive Glue
List out pipes qty size wise “with insulation” from the take off qty.
Find out pipes surface area
Arrive the qty of Glue from the surface area.
Record in xls or hard copy .
Finalize the qty
14
Pipe nominal
dia in mm
Pipe outer dia
in mm
Ins thick both
side in mm
Pipe dia with
ins in mm
Pipe qty in
mtr
Perimeter in
m
(3.14 x D)
Surface Area
(Sq.m)
Glue-
ltr(5sqm/ltr)
a a' b c=a*b d e=c*3.14 f=d*e h=f/5
20 26.7 100 126.7 200 0.40 79.6 15.9
25 33.4 100 133.4 200 0.42 83.8 16.8
32 42.2 100 142.2 200 0.45 89.3 17.9
1.1.3.5 Assumable Items-Insulation Adhesive Glue
note pip insulation thick 50mm
15
1.1 WATER SIDE1.1.3.6 Assumable Items-Self adhesive tape
List out pipes qty size wise “with insulation” from the take off qty.
Find out pipes surface area
Arrive the qty of self adhesive tape from the surface area & length of pipe.
Record in xls or hard copy .
Finalize the qty
16
Pipe nominal
dia in mm
Pipe outer dia
in mm
Ins thick both
side in mm
Pipe dia with
ins in mm
Pipe qty in
mtr
Perimeter in
m
(3.14 x D)
Surface Area
(Sq.m)
Al foil 3" in
roll(50 mtr/roll)
a a' b c=a*b d e=c*3.14 f=d*e j=d/1.2*e+d /50
20 26.7 100 126.7 200 0.40 79.6 5
25 33.4 100 133.4 200 0.42 83.8 5
32 42.2 100 142.2 200 0.45 89.3 5
1.1.3.6 Assumable Items-Self adhesive tape
note pip insulation thick 50mm
17
1.1 WATER SIDE1.1.3.7 Assumable Items-Insulation Canvas cloth
List out pipes qty size wise “with insulation” from the take off qty.
Find out pipes surface area
Arrive the qty of Canvas cloth from the surface area.
Record in xls or hard copy .
Finalize the qty
18
Pipe nominal
dia in mm
Pipe outer dia
in mm
Ins thick both
side in mm
Pipe dia with
ins in mm
Pipe qty in
mtr
Perimeter in
m
(3.14 x D)
Surface Area
(Sq.m)
Canvas cloth
30 yard roll(70
sq.m/roll)
a a' b c=a*b d e=c*3.14 f=d*e i=f/70
20 26.7 100 126.7 200 0.40 79.6 1.1
25 33.4 100 133.4 200 0.42 83.8 1.2
32 42.2 100 142.2 200 0.45 89.3 1.3
note pip insulation thick 50mm
1.1.3.7 Assumable Items-Insulation Canvas cloth
note pip insulation thick 50mm
19
1.1 WATER SIDE1.1.3.8 Assumable Items-Vibration pad/Inertia base
List out main equipments qty from the take off qty.
Find vibration pad and inertia base /unit
Arrive the total qty
Record in xls or hard copy .
Finalize the qty
20
1.1.3.8 Assumable Items-Vibration pad/Inertia base
Item Qty in nosVibration Pad
qty/Unit in no
Toltal Vibration
Pad qty/Unit in
no
Inertia base
qty/Unit in no
Total Inertia
base qty/Unit in
no
a b c=a*b d e=a*d
Chiller 2 12 14
Pump5
1 5 Pump5
1 5
note per chiller 12 no assumed
per pump1 no assumed
21
1.1 WATER SIDE
1.1.3.9 Assumable Items-Pipe Painting
Indentify the requirement of painting on pipe as per speciation.
Arrive the qty of paint(ltrs) over pipe
Record the qty in hard copy and xls sheet as floor/zone wise.
Finalize the qty
22
1.1.3.9 Assumable Items-Pipe Painting
Pipe nominal
dia in mm
Pipe outer dia
in mm
Pipe qty in
mtr
Perimeter m
(3.14 x D)
Surface Area
pipe(Sq.m) No of Coat
Paint qty in
ltrs
a a' b c=a*3.14 d=c*b e f=c/14*e
20 26.7100 0.08 8.4 2.0 1.2
2533.4
100 0.10 10.5 2.0 1.5
32 42.2100 0.13 13.3 2.0 1.9
4.6 4.6
note assume 14 sq.m per ltr
assume 2 coat
23
1.1 WATER SIDE
1.1.3.10 Assumable Items-BMS System I/O Point
List out main equipments from all service take off qty.
Identify the BMS control equipments from drawing/specification/schedule
Arrive the I/O point of equipments as per specification.
Finalize the qtyRecord the total I/O qty in hard/xls copy
24
S.No Item DescriptionNo Of Item in
NosDI DO AI AO
No of I/O
pointsNo Of Unit
Total No of
I/O points
1 Chiller 4 3 8 3 14 4 56
2 SCHWP 4 3 1 7 1 12 4 48
3 PCHWP 4 3 1 5 9 4 36
4 CHW Prs 1 3 1 4 1 4
5 Parking Fresh fans 25 7 2 9 25 225
6 Parking Exh fans 10 7 2 9 10 90
1.1.3.10 Assumable Items-BMS System I/O Point
6 Parking Exh fans 10 7 2 9 10 90
7 FCU 33 2 4 1 7 33 231
8 Waste pump 2 4 4 2 8
9 Water Pumps 6 3 3 6 18
10 Fire pumps 1 4 1 5 1 5
11 FM200 1 2 2 1 2
12 Water Tanks 4 2 2 4 8
13 MV panel 2 5 5 2 10
14 Transforemer Room 1 3 3 1 3
25
1.2 AIR SIDE
1.2.1 Countable Items
Count qty of items by tag no wise/capacity wise from the drawing and schedule.
Record the qty in hard copy and xls sheet as floor/zone wise.
Compare the takeoff qty with BOQ qty.
Find out difference in qty.
If any deviation in items qty,RFI to be raised.
Basic unit of measurement – nos
26
1.2 AIR SIDE
1.2.2 Measurable Items
Measure qty of items size wise from the drawing.
Record the qty in hard copy and xls sheet as floor/zone wise.
Compare the takeoff qty with BOQ qty.
Note down the Scale of drawing and use particular scale/conversion.
Find out difference in items qty.
If any deviation in items qty,RFI to be raised.
Basic unit of measurement – meters,sq.m
27
1.2 AIR SIDE
1.2.2.1 Measurable Items- GI/Pre insulated Ducting
Measure qty of items size wise and duct type wise from the drawing.
Record the qty in hard copy and xls sheet as floor/zone wise.
Find out Surface area of duct from the perimeter of duct.
Note down the Scale of drawing and use particular scale/conversion.
Compare the takeoff qty with BOQ qty.
Find out difference in items qty.
If any deviation in items qty,RFI to be raised.
28
Duct Size in mm
Gauge
thick in
mm
Duct Length
in m
Perimeter
in m
Duct
Area(Sq.m)
W H a b=2*(w+h)/1000
c=a*b
200 400 0.6 100 1.20 120.0
250 300 0.6 150 1.10 165.0
1.2.2.1 Measurable Items- GI/Pre insulated Ducting
300 300 0.6 200 1.20 240.0
29
1.2 AIR SIDE
1.2.3 Assumable Items
List of out the assumable items.
Connect these items to primary measure/Count items qty.
Calculate the qty from primary items qty respectively.
Record the qty in hard copy and xls sheet as floor/zone wise.
Compare the takeoff qty with BOQ qty(if avail)
Finalize the qty
Basic unit of measurement – nos,liters,meters,sq.m
30
1.2 AIR SIDE
1.2.3 .1Assumable Items-Duct Thermal Insulation
List out size wise duct take off qty.
Note down the thickness of insulation as per specification ,drawing ,BOQ.
Arrive and Segregate the duct insulation qty based on locations.(exposed or conditioned)
Record the qty in hard copy and xls sheet as floor/zone wise.
Compare the takeoff qty with BOQ qty(if avail)
Finalize the qty
31
1.2.3 .1Assumable Items-Duct Thermal Insulation
Duct Size in mm Type Of Duct Insulation
Thick in mm
Duct Length
in m Perimeter in m
Duct
insulation
Area(Sq.m)
W H a b=2*(w+h)/1000 c=a*b
200 400 SAD 50 100 1.2 120.0
250 300 RAD 50 100 1.1 110.0
300 300 EAD 25 100 1.2 120.0
500 600 RAD 25 100 2.2 220.0
500 550 EAD 25 100 2.1 210.0
note assume condition area 25 mm thick
assume exposed area 50 mm thick
32
1.2 AIR SIDE
1.2.3.2 Assumable Items-Duct Acoustic Insulation
List out equipment qty with size of duct connected to equipment.
Note down the thickness of insulation as per specification ,drawing ,BOQ.
Arrive the duct insulation qty based.
Record the qty in hard copy and xls sheet as floor/zone wise.
Compare the takeoff qty with BOQ qty(if avail)
Finalize the qty
33
1.2.3.2 Assumable Items-Duct Acoustic Insulation
Duct Size in mm Type Of
Equipment No of side
Qty of
equipment in
no
Insulation Thick
in mm
Duct Length
in m
Perimeter in
m
Area of
insulation Sq.m
W H a b c d=2*(w+h)/1
000
e=a*b*c*d
500 500 AHU 2 10 25 3 2 120.0
450 300 FAHU 2 5 25 3 1.5 45.0
300 300 FCU 1 15 25 3 1.2 54.0
250 250 Fan 2 5 25 3 1 30.0
note assume condition area 25 mm thick
assume insulation lengtho 3 mtr
34
1.2 AIR SIDE
1.2.3.3 Assumable Items-Duct Cladding
Indentify the requirement of cladding on duct insulation as per speciation.
Arrive the qty of cladding(sq.m) over duct insulation.
Record the qty in hard copy and xls sheet as floor/zone wise.
Compare the takeoff qty Compare the takeoff qty with BOQ qty if available and finalize the qty.
Application In generalCladding in Exposed area duct insulation thick 50mm
35
Duct Size in mm Insulation
thick in mm
Duct Size with insulation in
mm Duct Length in m Perimeter in m
Area
of
claddin
g Sq.m
W H a W' H' b c=2*(w'+h')/1000 d=c*b
500 500 50 550 550 25 2.2 55.0
450 300 50 500 350 50 1.7 85.0
1.2.3.3 Assumable Items-Duct Cladding
450 300 50 500 350 50 1.7 85.0
300 300 50 350 350 30 1.4 42.0
250 250 50 300 300 45 1.2 54.0
note assume insulation thick exposed 50 mm
36
1.2 AIR SIDE1.2.3.4 Assumable Items-Insulation vapor barrier
List out Duct qty size wise “with insulation” from the take off qty.
Find out duct surface area
Arrive the qty of vapor barrier from the surface area.
Record in xls or hard copy .
Finalize the qty
37
1.2.3.4 Assumable Items-Insulation vapor barrier
Duct Size in mm Insulation
Thick in mm
Duct Size with insulation in
mm
Duct Length in
m Perimeter in m
Surface
Area(Sq.
m)
Vapour Barrier-
ltr(2sq/ltr/coat)
W H W' H' a b=2*(w’+h’)/1000 c=a*b d=c/2*2 coat
200 400 50 250 450 100 1.40 140.0 140.0
250 300 50 300 350 150 1.30 195.0 195.0
300 300 50 350 350 200 1.40 280.0 280.0
assume thick of insulation 50mmNote
38
1.2 AIR SIDE1.2.3.5 Assumable Items-Insulation Adhesive Glue
List out Duct qty size wise “with insulation” from the take off qty.
Find out Duct surface area
Arrive the qty of Glue from the surface area.
Record in xls or hard copy .
Finalize the qty
39
1.2.3.5 Assumable Items-Insulation Adhesive Glue
Duct Size in mm Insulation
Thick in mm
Duct Size with insulation in
mm
Duct Length in
m
Perimeter in
m
Surface
Area(Sq.m)
Glue-
ltr(5sqm/ltr)
W H W' H' a b=2*(w+h)/100
0
c=a*b h=f/5
200 400 50 250 450 100 1.40 140.0 28.0
250 300 50 300 350 150 1.30 195.0 39.0 250 300 50 300 350 150 1.30 195.0 39.0
300 300 50 350 350 200 1.40 280.0 56.0
assume thick of insulation 50mmNote
40
1.2 AIR SIDE1.2.3.6 Assumable Items-Self adhesive tape
List out duct qty size wise “with insulation” from the take off qty.
Find out duct surface area
Arrive the qty of self adhesive tape from the surface area & length of pipe.
Record in xls or hard copy .
Finalize the qty
41
1.2.3.6 Assumable Items-Self adhesive tape
Duct Size in mm Insulation
Thick in mm
Duct Size with insulation in
mm
Duct Length in
m
Perimeter in
m
Surface
Area(Sq.m)
Al foil 3"
in roll(50
mtr/roll)
W H W' H' a b=2*(w+h)/100
0
c=a*b j=(a/1.2*b)+(
a*4))/50
200 400 50 250 450 100 1.40 140.0 10
250 300 50 300 350 150 1.30 195.0 15
300 300 350 350 200 21 300 300 50 350 350 200 1.40 280.0 21
assume thick of insulation 50mmNote
42
1.2 AIR SIDE1.2.3.7 Assumable Items-Insulation Canvas cloth
List out duct qty size wise “with insulation” from the take off qty.
Find out duct surface area
Arrive the qty of Canvas cloth from the surface area.
Record in xls or hard copy .
Finalize the qty
43
1.2.3.7 Assumable Items-Insulation Canvas cloth
Duct Size in mm Insulation
Thick in mm
Duct Size with insulation in
mm
Duct Length in
m
Perimeter in
m
Surface
Area(Sq.m)
Oven cloth
30 yard
roll(70
sq.m/roll)
W H W' H' a b=2*(w+h)/100
0
c=a*b i=f/70
200 400 50 250 450 100 1.40 140.0 2.0 200 400 50 250 450 100 1.40 140.0 2.0
250 300 50 300 350 150 1.30 195.0 2.8
300 300 50 350 350 200 1.40 280.0 4.0
assume thick of insulation 50mmNote
44
1.2 AIR SIDE1.2.3.8 Assumable Items-Vibration pad/Vibration hanger
List out main equipments qty by type of installation from the take off .
Find vibration pad and hanger qty/unit
Arrive the total qty
Record in xls or hard copy .
Finalize the qty
45
ItemCeilng mount
qty in nos
Floor mount
qty in nos
Vibration Pad
qty/unit in no
Toltal
Vibration Pad
qty/Unit in
no
Hanger qty/Unit
in no
Total hanger
qty/Unit in no
a a b c=a*b d e=a*d
Fans 5 10 0 4 20
1.2.3.8 Assumable Items-Vibration pad/Vibration hanger
Fans 5 10 0 4 20
FCU 5 10 0 4 20
AHU 5 15 10 150 4 20
note per unit 4 hanger
per unit 10 vibration pad
46
1.2 AIR SIDE
1.2.3.9 Assumable Items-Duct Flexible Connector
List out equipment qty with size of duct connected to the equipment.
Note down the size of flexible connector as per specification ,drawing ,BOQ.
Arrive the duct flexible connector.
Record the qty in hard copy and xls sheet as floor/zone wise.
Compare the takeoff qty with BOQ qty(if avail)
Finalize the qty
47
Duct Size in mm Type Of
Equipment No of side
Qty of
equipment in
no
Perimeter in m
Length of
flexible
connector in m
W H a b d=2*(w+h)/1000 e=d
500 500 AHU 2 10 2 2
450 300 FAHU 2 5 1.5 1.5
300 300 FCU 1 15 1.2 1.2
250 250 Fan 2 5 1 1
1.2.3.9 Assumable Items-Duct Flexible Connector
note assume size of flexible connector 4"x6"4"
48
1.2 AIR SIDE
1.2.3.9 Assumable Items-Duct Supports
List out duct qty size wise “with insulation” from the take off qty.
Find the supports distance by specification and drawing.
Arrive the supports qty size wise from the support distance.
Compare the takeoff qty with BOQ qty (if available.)
Finalize the qty
49
Duct size in mm
length
except roof
mtr
Roof Length
in mtr
No of floor
support in
no
No of roof
support in no
Angle/support
- 40x4xx3mm
in mtr
Angle-
40x40x3mm
in mtr
C-channel
75x40x5mm/
support in
mtr
C-channel
75x40x5m
m/support
in mtr
Ms Plate
/support
in no
W H a b c d e f=c*e g h=d*g i=d*2
500 500 100 25 50 12.5 0.7 35 1.15 14.38 25
600 450 75 15 37.5 7.5 0.8 30 1.3 9.75 15
400 450 65 10 32.5 5 0.6 19.5 1 5.00 10
note assume roof duct support spacing 2m
assume other than roof duct support spacing 2m
assume 2 MS plate/support
1.2.3.9 Assumable Items-Duct Supports
50