qra for overall project risk - dr david hillson
TRANSCRIPT
© Copyright 2015-16, The Risk Doctor Partnership, Slide 1
Assessing overall project risk with quantitative risk analysis
Presented by
Dr David Hillson
HonFAPM, PMI Fellow, FIRM, FCMI
The Risk Doctor The Risk Doctor Partnership [email protected] www.risk-doctor.com
11 February 2016, London, UK
© Copyright 2015-16, The Risk Doctor Partnership, Slide 2
Two key questions
1. How risky is
your project?
2. How do you
know?
© Copyright 2015-16, The Risk Doctor Partnership, Slide 3
How to answer these questions?
Two levels of question & answer:
1. Project Manager:
Q: What are the risks in my project?
A: Individual risks (see Risk Register & risk reports)
2. Project sponsor/project owner/customer:
Q: What is the riskiness of this project?
A: Overall project risk (????)
© Copyright 2015-16, The Risk Doctor Partnership, Slide 4
What is “individual risk”?
APM PRAM Guide (2004), BoK6 (2012)
an uncertain event or set of circumstances that, should it occur, will have an effect on achievement of one or more of the project’s objectives.
PMI Practice Standard for Project Risk Management (2009), PMBoK® Guide (2013)
an uncertain event or condition that, if it occurs, has a positive or negative effect on a project’s objectives.
© Copyright 2015-16, The Risk Doctor Partnership, Slide 5
What is “overall project risk”?
APM PRAM Guide (2004), BoK6 (2012)
Overall risk is the exposure of stakeholders to the consequences of variation in outcome, arising from an accumulation of individual risks together with other sources of uncertainty.
PMI Practice Standard for Project Risk Management (2009), PMBoK® Guide (2013)
Overall project risk represents the effect of uncertainty on the project as a whole. It is more than the sum of individual risks on a project.
© Copyright 2015-16, The Risk Doctor Partnership, Slide 6
Is this in scope for project managers?
Project Manager is responsible for identifying, assessing and managing specific uncertainties within the project (individual risks)
Project Manager is accountable to Project Sponsor and stakeholders for overall risk exposure of the project (overall project risk)
Yes, but how?
© Copyright 2015-16, The Risk Doctor Partnership, Slide 7
Managing overall project risk
Identifying sources of overall project risk
Quantifying overall project risk
Responding to overall project risk
Reporting & monitoring overall project risk
© Copyright 2015-16, The Risk Doctor Partnership, Slide 8
“Exposure of stakeholders to variation in outcome”
“Effect of uncertainty on the project as a whole”
Key questions with quantitative answers:
How likely is this project to succeed (or fail)?
What is potential range of variation in outcome?
Standard Monte Carlo simulation answers these
Quantifying overall project risk
© Copyright 2015-16, The Risk Doctor Partnership, Slide 9
Quantifying overall project risk
Cum
ula
tive p
robabili
ty (
%)
TARGET
£2.2M
23% CHANCE OF MEETING TARGET
EXPECTED
VALUE
£2.35M
85% CHANCE OF COSTING £2.45M
RANGE OF UNCERTAINTY (5:95) = £0.5M
0
10
20
30
40
50
60
70
80
90
100
Cum
ula
tive p
robability
(%)
0
10
20
30
40
50
60
70
80
90
100
Predicted total project cost
£2.0M £2.2M £2.4M £2.6M £2.1M £2.7M £2.8M £2.5M £2.3M
An example Monte Carlo output (cost)
© Copyright 2015-16, The Risk Doctor Partnership, Slide 10
“How risky is this project?”
Quantitative answers:
How likely is this project to succeed?
Probability of meeting £2.2M target = 23%
Expected value = £2.35M (+7%)
What is potential range of variation in outcome?
Total potential range = £0.5M (= 22% of project value)
Realistic best case (5th percentile) = £2.1M (– 4%)
Realistic worst case (95th percentile) = £2.6M (+18%)
Quantifying overall project risk An example Monte Carlo output (cost)
© Copyright 2015-16, The Risk Doctor Partnership, Slide 11
Time
Co
st
PLANNED
PROJECT
START
ZERO
MAXIMUM
TOTAL
COST
LATEST
PROJECT
END
WORST CASE:
MAXIMUM COST &
LATEST END
MINIMUM
TOTAL
COST
EARLIEST
PROJECT
END
BEST CASE:
MINIMUM COST &
EARLIEST END
INDIVIDUAL
COST-TIME
RESULT
EXPECTED
PROJECT
END
EXPECTED
TOTAL
COST
EXPECTED CASE MEAN COST & TIME
Quantifying overall project risk Another example Monte Carlo output (cost/time)
© Copyright 2015-16, The Risk Doctor Partnership, Slide 12
Reporting overall project risk
Update at key milestones, tell stakeholders:
Current level of overall project risk
Major causes of overall project risk
Key responses underway or planned
Trend in overall project risk since project started
Predicted level at next reporting point
Monitor changes and trends
No common practice formats
Suggested dashboard components
© Copyright 2015-16, The Risk Doctor Partnership, Slide 13
Overall Project Risk Barometer
PR
OB
AB
ILIT
Y O
F P
RO
JE
CT
SU
CC
ES
S
0%
50%
100%
80%
PROJECT START
PROJECT END
REVIEW 1 R2 R3 R4 MILESTONE 1
R5 R6 MS2 R7 R8 MS3 R9 R10 R11
TIME NOW
PR
OB
AB
ILIT
Y O
F P
RO
JE
CT
SU
CC
ES
S
0%
50%
100%
80% TREND LINE
© Copyright 2015-16, The Risk Doctor Partnership, Slide 14
Overall Project Risk Barometer + variability
PR
OB
AB
ILIT
Y O
F P
RO
JE
CT
SU
CC
ES
S
0%
50%
100%
80%
REVIEW 1 R2 R3 R4 MILESTONE 1
R5 R6 MS2 R7 R8 MS3 R9 R10 R11
TIME NOW
TREND LINE
PR
OB
AB
ILIT
Y O
F P
RO
JE
CT
SU
CC
ES
S
0%
50%
100%
80%
PROJECT START
PROJECT END
REVIEW 1 R2 R3 R4 MILESTONE 1
R5 R6 MS2 R7 R8 MS3 R9 R10 R11
VA
RIA
BIL
ITY
VA
RIA
BIL
ITY
TARGET
UNDER
TARGET
OVER
TARGET
TARGET
UNDER
TARGET
OVER
TARGET
TREND LINE
MIN
EXP
MAX
© Copyright 2015-16, The Risk Doctor Partnership, Slide 15
Cost/time variability from “eyeball/football plot”
Time
Co
st
TARGET COST
TARGET
DATE
REVIEW 1
REVIEW 3
REVIEW 2
© Copyright 2015-16, The Risk Doctor Partnership, Slide 16
“Eyeball/football” orientation indicates risk type
Cost & time risk are positively correlated and equally balanced
Time
Co
st
EARLY LATE
UN
DE
RS
PE
ND
O
VE
RS
PE
ND
© Copyright 2015-16, The Risk Doctor Partnership, Slide 17
Cost & time risk are positively correlated,
equally balanced
Cost & time risk are negatively
correlated, equally balanced
Major risk is to time, cost not
affected significantly
Major risk is to cost, time not
affected significantly
Time
Co
st
EARLY LATE
UN
DE
RS
PE
ND
O
VE
RS
PE
ND
Time
Co
st
EARLY LATE
UN
DE
RS
PE
ND
O
VE
RS
PE
ND
Time
Co
st
EARLY LATE
UN
DE
RS
PE
ND
O
VE
RS
PE
ND
Time
Co
st
EARLY LATE
UN
DE
RS
PE
ND
O
VE
RS
PE
ND
“Eyeball/football” orientation indicates risk type
© Copyright 2015-16, The Risk Doctor Partnership, Slide 18
Final thoughts
© Copyright 2015-16, The Risk Doctor Partnership, Slide 19
Next steps for practitioners and the profession
Risk matters, including both individual risks and overall project risk
Both need to be managed proactively
Best-practice needs to evolve to cover both
PM standards must provide guidance for both
We must deal equally with the risks in the project and the riskiness of the project
© Copyright 2015-16, The Risk Doctor Partnership, Slide 20
Final questions
How risky is your project?!
How do you know??!!
Do you include overall project risk
in your thinking & practice?
If not, why not?
Would it be possible?
What changes are required?
© Copyright 2015-16, The Risk Doctor Partnership, Slide 21
Thank you Any questions?
© Copyright 2015-16, The Risk Doctor Partnership, Slide 22
For further information
Dr David Hillson The Risk Doctor Partnership
+44(0)7717.665222
www.risk-doctor.com
YouTube.com/RiskDoctorVideo
11 February 2016, London, UK
This presentation was delivered
at an APM event
To find out more about
upcoming events please visit our
website www.apm.org.uk/events