pw and wfi storage and distribution systems design and...
TRANSCRIPT
PW and WFI STORAGE and DISTRIBUTION
SYSTEMS DESIGN and OPERATION
A PRACTICAL COMPARISON
Scope and Purpose
Discussion on the Basis of Design of PW and WFI systems
Requirements: Uses of water
Quality
Design
Construction
Critical parameters
Sampling
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 2
Disclaimer All information is widely available:
On Internet
Regulatory publications
Standards
Guides
Professional publications
Other sources
There is “regulation” “interpretation” “current practice” “best practice”
There is no one way of doing things
Everyone has to decide for himself
This presentation is about GMP related engineering aspects
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 3
Clarification
The following are not in the scope of this discussion: User Requirement Specification (URS) and a Functional Design Specification (FDS)
Detailed specifications for the equipment design, construction and
Detailed specifications for pipeline installation, slope measurement, cleaning and passivation
Detailed engineering design, commissioning and operation of the critical system
Inspection and Verification / Qualification / Validation requirements
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 4
Definition The storage and distribution system has the role to provide a buffer by
holding the required quantity of water, based on the daily water usage and the water generation capacity, and supply it to the users at the points of use (POU), while maintaining the chemical and microbial quality of water, according to the specifications, defined in the company’s relevant SOPs.
It is relatively easy to maintain the chemical quality of the water
Maintaining the microbial quality is more of a challenge
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 5
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 6
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 7
◦ US Food and Drug Administration (FDA) ◦ 21 CFR Part 210
◦ 21 CFR Part 211
◦ 21 CFR Part 11
◦ Pharmacopeias of US, Europe, Japan (USP, EP, JP)
◦ Various GMPs from European countries ◦ EudraLex Volume 4, GMP Guidelines Part 1, Basic Requirements for Medicinal products
◦ Annex 1 Manufacture of Sterile products
◦ Annex 5 Manufacture of Immunological Veterinary Medicinal Products
◦ Annex 9 Manufacture of Liquids, Creams and Ointments
◦ Annex 10 Manufacture of Pressurized Metered Dose Aerosol Preparations for Inhalation
◦ Annex 11 Computerized Systems
◦ Annex 15 Qualification and Validation
◦ Other source of guidance: ◦ International Society of Pharmaceutical Engineers (ISPE), Baseline Guides
◦ American Society of Mechanical Engineers (ASME) Bioprocessing Equipment (BPE-2012)
Applicable standards
Use of Water
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 8
Uses PW WFI
Feed water √ -
Washing √ √
Final rinse √ √
Formulation √ √
Humidification √ Pure Steam
Others (e.g. USP 1231)
Quality requirements
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 9
PW WFI USP EU USP EU
Conductivity ≤ 1.3 µS/cm @25°C ≤ 4.3 µS/cm @20°C ≤ 1.3 µS/cm @25°C ≤ 1.1 µS/cm @20°C
TOC < 500 ppb < 500 ppb < 500 ppb < 500 ppb
Nitrate NO3 - ≤ 0.2 ppm - ≤ 0.2 ppm
Bacteria ≤ 100 CFU/ml ≤ 100 CFU/ml ≤ 10 CFU/100 ml ≤ 10 CFU/100 ml
Endotoxin - - ≤ 0.25 EU/ml ≤ 0.25 I.U./ml
pH 5-7
System boundaries To be in control one must define where does the system start and where does it end
Divide et impera
The scope of the System starts at the generation system inlet / fill valve to
the Storage Tank The scope of the System starts at the inlet valve of any required utility
service, such as Pure Steam, plant steam, cooling water or compressed air The scope of the System terminates at the distribution system outlet valve of
any manual use point. Hoses used in the manufacturing process are considered the responsibility of the production department
The scope of the System terminates at the inlet valve of any directly connected equipment, and includes any piping and components between the loop outlet valve and the equipment inlet valve
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 10
Materials of construction
All wetted parts should be type 316L stainless steel
Type 316 stainless steel may be used if the component is fully annealed and is not to be welded in the field
The first component welded to the outside of any equipment should be of the same material as the wetted component.
Seals are EPDM, Viton, Teflon
Thermal insulation should be of low chloride material
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 11
Surface finish The surface finish for all equipment and components in contact with the water
should be mechanically polished (PW) and then electropolished (WFI)
There is a trend towards smoother and smoother surfaces and there are questions as to what is too much
ASME-BPE suggests 25 µinch (0.65 µm) and this may be sufficient
It is important that the surface be electropolished for inspection purposes
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 12
Storage tank
Proper sizing
Rupture disk
Double jacket
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 13
Vent filter The vent filter is prevented from getting wet by heating to a temperature
above the storage tank content, either electrically or by low pressure steam in the filter housing jacket
Filters should be equipped with an independent temperature monitor with high and low temperature alarms
For WFI the vent filter is integrity tested and steam sanitized
For PW is a question of interpretation and decision
The vent filter cartridge is of the membrane type, 0.2 μ absolute pore size, of the hydrophobic type, suitable for pharmaceutical applications
The vent filter housing is installed with sanitary clamp type fittings, to permit easy removal of the housing
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 14
Pump All pumps should utilize the water being pumped, as a seal lubricant
This may be by using a single mechanical seal or by using a double mechanical seal with the pumped liquid being supplied to the seal chamber
Redundancy (dual pumps)
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 15
Heat exchangers Shell and tube type heat exchangers should be of the double tube-sheet
design
Heat transfer tubing should be full finish seamless construction
Heat exchangers should be designed to be self-venting and self-draining on both the tube and shell sides
All liquid heating / cooling media or product should enter the bottom of the heat exchanger and exit at the top
Heating steam should enter the top of the heat exchanger and condensate should be removed from the bottom
The integrity of heat exchangers should be periodically verified by pressure tested using a suitable test media
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 16
Piping Pipes are of sanitary tube type
All piping shall be sloped to drain
Pipelines are to be suitably identified as to contents and direction of flow
No pipelines are permitted above open containers containing liquids that are subject to microbial or chemical purity requirements
Pipeline connections should be sanitary clamp type connections or welded
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 17
Valves Valves in water contact are to be of the sanitary diaphragm seal type
Valve design should ensure that any leak is detected and does not permit liquid to accumulate above the diaphragm
Use of “zero dead leg” valves
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 18
Dead legs Dead legs are not allowed
In the past the FDA has recommended that no dead-leg be longer than 6 times the diameter of the branch line. The source of this value is unknown, but believed to be from a different industry such as paint, for mixing of paint colors or possible for line cleaning
Some practices suggest reducing this to 3 or 4 diameters or as low as 2 diameters, however the aim should be to minimize the concern by use of components that have minimum dead-leg, such as zero dead-leg valves and short outlet tees.
This is especially true for water systems operating at ambient temperatures.
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 19
Drainability and Slopes All parts of the equipment and piping are to be fully drainable
Especially in WFI and PS systems
Components that could have limited drainability, such as orifice discs, check valves and small diameter valves and piping should be confirmed as being properly installed or operated in a manner to ensure complete drainage.
In systems that are not intended for steaming (PW systems), some dismantling may be acceptable for full drainage.
All pipelines must be sloped to drain
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 20
Backflow prevention Air-gaps are to be provided at all drain lines. Suitable air gaps are two times
the diameter of the drain pipe or 50mm, whichever is greater
Air gaps are to be measured above the “flood level rim”, such as the top of any area enclosed by a curb
Air-gaps are required before the drain connection to any other liquid system
At all locations where there is cross-connection with other systems there shall be suitable means of backflow prevention
At all water inlet connections to storage tanks dip pipes should not be used and the upper liquid level should be below the bottom of any spray ball
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 21
Welds and weld inspection All pipeline welding should be of the automatic autogenous type gas tungsten
arc welding in accordance with the applicable Welding /Inspection Procedures
Weld inspection should be 100% visual inspection by borescope and video documenting
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 22
Cleaning and passivation After construction, changes to the system, and routinely the system is cleaned
and passivated according to the relevant SOP
The system must have suitable vent and drain connections to permit field cleaning and passivation
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 23
Operating parameters that are subject to interpretation Some of the parameter values that were adopted many years ago have
become accepted practice, and while they may be desirable they may not have a scientific basis for the accepted value Temperature
Velocity of liquid flow in pipelines
Pressure
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 24
Temperature It is accepted that elevated temperatures can prevent microbial growth, and it
is usual practice for hot WFI systems to operate at 80⁰C
The value of 80⁰C has been accepted for many years, but lower temperatures are also effective in preventing microbial growth
Temperature should be measured at key locations within the storage and distribution system and at the storage tank vent filter
Temperature monitoring should cover normal operations and sanitization / steaming verification
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 25
Pressure Except during times of shut down for maintenance, critical pipeline systems
should be maintained under continuous (positive) pressure, to prevent the intrusion of any contaminants
There is no minimum pressure stated in the regulatory guidelines, however the pressure should be sufficient to: Prevent back siphonage from any use point in the system
Provide adequate pressure for the use points that require a minimum pressure for consistent operation
Pressure should be monitored at appropriate locations in the WFI distribution piping system such as the start and end of the distribution loop
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 26
Velocity of liquid flow in pipelines Flow should be maintained in all portions of the water system at all times, or
provision should be made for automatic flushing of water to drain.
The actual velocity of the liquid flow is subject to discussion. The currently accepted velocity of say 5 feet/second (1.5 m/sec) has its basis in being a practical flow rate for the economic sizing of pipelines, and has little relationship to the prevention of microbial growth or the formation of biofilm on the pipeline walls
In piping systems that continually operate hot, any flow rate that is sufficient to keep the pipeline full and at the required minimum temperature should be acceptable
The flow rate should also be sufficient to displace air from the high points of the piping distribution system
In systems that operate at temperatures where microbial growth can occur, a specific rate of flow will not ensure low microbial levels and other actions, such as periodic sanitization, are required to provide a suitable operation
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 27
Conductivity and TOC Total Organic Carbon (TOC) and conductivity should be measured at
representative locations in the distribution piping
TOC monitoring may use a single TOC analyzer for several sample sites with the samples taken in rotation
TOC and Conductivity should be measured in accordance with the applicable compendial requirements Temperature compensation in conductivity measuring
Suitability testing and calibration
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 28
Controls and Instrumentation Critical parameters must be defined
For critical parameters the monitoring and alarm instrumentation should be completely separate from the control instrumentation, using different sensors
Time delays on alarms should only be provided to eliminate alarms caused by short-term transient conditions. Time delays should not be so long that they permit significant or intermittent cGMP concerns to be undetected
Controls and computer systems and PLCs should be GAMP CFR 21 - Part 11 compliant
Alarm monitoring and reporting should provide for local and remote reporting, recording and trending capability
Critical monitoring, recording and alarm components should be on battery back-up power
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 29
Sampling Water is sampled at the user points for chemical and microbiological quality according to the
relevant SOP
Sample valves should be provided upstream and downstream of all equipment /components that can have an effect on the microbial of chemical quality of the critical fluid
Not all sample points are tested on a routine basis
Sampling valves must be installed in an easily accessible location
Sample valve should not be located where the local environment can affect the integrity of the sample
Sample valves should be of a design that is suitable for sampling; similar type and size of valve should be used throughout the system being sampled
Sampling at locations where hoses are used should be conducted through those hoses, to replicate actual usage conditions
Loop outlet valve sample, where the sample valve is upstream of the loop outlet valve, is not representative of the water supplied to the final point of use
Sampling at connected equipment should be conducted as close to the final point of use as practical
Any flushing performed prior to sampling should use the same procedure that is used for production use of the water
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 30
Operational considerations Operating temperature Cold Ambient Hot Hot storage – Ambient distribution
Vent Filter Heating Replacement Integrity testing
Sanitization - Water systems should be designed to be sanitized PW Heat
Ozone
Chemical ?
WFI – on the next slide
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 31
Sanitization WFI Sanitization is performed by admitting Pure Steam into the tank and into the
return circulation line to the tank. The isolation valves between the return line to the tank and the tank outlet to the recirculation line are closed so that the sanitization steam flows into the tank and around the distribution loop in parallel separate directions. The steam displaces air and condensate is removed through condensate traps located at all low points of the pipework.
At the end of the sanitization process, nitrogen is admitted through the vent filter to the system so as create a positive pressure during the cooling stage
The vent filter is sanitized with Pure Steam independently of the rest of the system. Pure Steam is admitted on the atmospheric side of the filter and passed through the filter media to the tank side. After sanitization, passing nitrogen through the filter in the same direction as the steam dries the filter
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 32
The end of this presentation
March 1-2, 2017 PW AND WFI DESIGN AND OPERATION 33