put title here - pushing beyond what's been done · 9/14/2018 · ryan drew –senior project...
TRANSCRIPT
Put Title Here
Put date or other info here
September 14, 2018
Owner and Design Team
Grinnell College HSSC Project
Leadership Team:
Mike Latham
Jim Swartz
Erik Simpson
Keith Brouhle
Rick Whitney
Dave Robinson
Larry Gleason
Keith Archer
Nancy Combs
Christi Baker
Jane Taylor
EYP Architects
Jennifer Amster
Eric Kern
Eric Petersen
Angela Wilson
OPN Architects
Bill Catrenich
Pylar Eaton
McGough Project Team
Dustin Schwake – Project Executive
Matt Schroeder – Senior Project Manager
Josh Miltenberger – Senior Project Manager
Ryan Drew – Senior Project Manager
Alex Maass – Assistant Project Manager
Amy Robinson – Project Coordinator
Chuck Carpenter – Senior Superintendent
Patrick Woodson – Assistant Superintendent
Subcontractors
1st Interiors
Advance Equipment Co.
All-American Scaffold
American Fence Co.
American Structural Metals
Architectural Wall Systems
Baker Electric
Bartley Sales
Bolander
CGA
DA Bunch
Danny’s Construction
Des Moines Marble
Floors by Beckers
Forman Ford
Heartland Finishes
J&M Roofing
Johnson Specialty Sales
KONE Elevator
Navetta
PAC-VAN
Pella Tree Service
Peterson Contractors, Inc.
Premier Edge
Pro-Bel
S&F Underground
Seedorff Masonry
Skold Companies
Soil-Tek
Summit Fire Protection
Superior Painting
Swanson & Youngdale
Waldinger Mechanical
Walsh Door & Security
Wilkie Sanderson
Wynn O. Jones
Current Highlights
High ceiling work progresses in the atrium
Finishes continue in south pavilion
Carpet, Tile, Millwork, Lab casework, Doors & hardware, Interior glass
Drywall and finishing nearly complete in north pavilion
Interior granite continues
South pavilion window wells are finished at skylights
Mechanical, electrical, fire protection trim continues
Chilled beams, light fixtures, fire alarm devices, electrical trim, fire sprinkler
heads
View from commencement
South elevation
View of main courtyard / atrium
View at northwest elevation
Window well – south end of south pavilion
Window well – 2nd floor – final details complete
Rough-in for A/V at S1310 – 1st floor south pavilion
Interior granite at main entrance to atrium
Louver install – 1st floor at north end of atrium hallway
Ceiling framing & trim for bridges in atrium
South atrium wall – louvers being set
2nd floor main street corridor looking north
Millwork set and protected – 2nd floor south
Raised flooring installation – 3rd floor south
Chilled beam install – 2nd floor north pavilion
Upcoming Highlights
Tile flooring to start in south pavilion – main corridors
Exterior finish complete on overhangs – direct applied finish system
High ceiling work to continue in atrium – wood look ceiling/lights/fire sprinkler
Flooring to start in north pavilion
Equipment start-up and testing for AFA project
Interior finishes continue in south and north pavilions