purchaser: cesu of odisha central electricity supply...
TRANSCRIPT
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 1
CESU, Odisha Page 1 Release Date: 27th February 2016
An initiative of
Ministry of Power,
Government of
India
Restructured Accelerated Power Development and Reforms
Program (R-APDRP) of Govt. of India
REQUEST FOR PROPOSAL (RFP)
for Selection of ‘IT Implementation Agency’ to assist the
Central Electricity Supply Utility of Odisha for
implementation of IT infrastructure
For further details, please visit the website:
www.cesuodisha.com / www.cescoorissa.com
Purchaser: CESU of Odisha
Central Electricity Supply Utility of Odisha
RFP Identification No: CESU/ITCC/R-APDRP/07
Single Stage – Double Envelope Selection Procedure
The last date for submission of RFP is 28th March 2016 (Up to 13:00 Hrs)
(This document is meant for the exclusive purpose of RFP and shall not be transferred, reproduced or otherwise used for purposes other than that for which it is specifically issued.)
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 2
CESU, Odisha Page 2 Release Date: 27th February 2016
NOTIFICATION INVITING TENDER (NIT) / REQUEST FOR PROPOSAL
CENTRAL ELECTRICITY SUPPLY UTILITY OF ODISHA Head Office: IDCO TOWER, 2
nd Floor, Janpath, Bhubaneswar-751022
TELEPHONE: 0674-2545685, FAX: 0674–2543125
Website: www.cescoorissa.com OR www.cesuodisha.com
Tender Notice No.: CESU/IT-406/ Vol-III /2016/ 4677 Dt. 26/02/2016
For and on behalf of CESU, the undersigned invites sealed bids from qualified and eligible bidders to Implement IT infrastructure at CESU as per R-APDRP Part-A norms.
BRIEF DESCRIPTION: Event / Particulars Date and Time Location
Download of RFP / Bid Document
27th February 2016
from 13:00 Hrs onwards
www.cesuodisha.com / www.cescoorissa.com
Date of Pre-Bid Conference 10
th March 2016
from 12:00 Hrs to 14:00 Hrs.
Conference Hall, Central Electricity Supply Utility of Odisha, 3
rd
Floor, IDCO Tower, Janpath, Bhubaneswar – 751022 Odisha
Tender Participation Cost
Indian Rupees 25,000/- (Twenty Five Thousand) +
VAT 5%
Rs. 25,000/- (Twenty Five Thousand) Plus VAT 5%, by Demand Draft payable to CESU of Odisha, Bhubaneswar, Odisha. The interested empanelled SIs may download the tender document from website (www.cesuodisha.com / www.cescoorissa.com) and the cost may be submitted along with the bid.
Bid Security (EMD) Indian Rupees 1.00
Crore
Bid Security (EMD) to be submitted as Bank Guarantee in the prescribed format for a period of 150 days from the date of Bid Opening.
Final Bid Submission 28
th March 2016
(Up to 13:00 Hrs)
IT Center, Central Electricity Supply Utility of Odisha, 8
th Floor, IDCO Towers, Janpath,
Bhubaneswar -751022 Odisha
Technical Bid Opening 28
th March 2016 15:00 Hrs
Conference Hall, Central Electricity Supply Utility of Odisha, 3
rd
Floor, IDCO Tower, Janpath, Bhubaneswar – 751022 Odisha
Financial Bid Opening Will be Notified Later
The aforesaid dates are firm and will not be extended.
CESU reserves the rights to cancel the RfP without assigning any reason thereof.
Sd/- Sr. GM (IT)
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 3
CESU, Odisha Page 3 Release Date: 27th February 2016
General Instructions to bidders:
A. CESU invites PFC Empanelled companies to purchase the Request for Proposal (this “RFP”) to participate in the bidding and selection process for the appointment of IT Implementing Agency to implement R-APDRP PART-A.
B. This RFP can be downloaded from www.cesuodisha.com / www.cescoorissa.com on or after 27th February 2016, 13:00 Hrs Indian Standard Time by meeting the criteria and following the procedure indicated herein.
C. This RFP comprises of following documents, wherein the bidders are expected to inform themselves of the content fully:-
a. This RFP Document b. SRS Document issued by Nodal Agency (PFC) c. Amendments to the RFP and SRS documents issued by Nodal Agency (PFC) till
the date of bid submission
D. All interested parties are requested to strictly abide by ALL terms prescribed in this RFP and provide accurate information to the best of their knowledge without misleading CESU to be considered for participation in this Project.
E. CESU reserves the rights to reject any or all offers without assigning any reasons thereof.
F. The nodal person for all enquiries, correspondence and clarifications with respect to the
RFP and submission of the bid shall be Sr.GM(IT), CESU; e-Mail: part-
[email protected] Phone: 0674-2545685.
No tender shall be accepted /opened after the due date and time of receipt of tender irrespective of delay due to postal services or any other reasons and CESU shall not assume any responsibility for late receipt of the tender. In case the due date happens to be a holiday, the bids shall be received/ opened on the next working day at the same time & place.
G. It should be clearly understood that CESU will not reimburse any cost incurred by you for the preparation of offer, site visit, collection of information, or, if you are selected, for contract or negotiations.
H. Maximum of two members per empanelled System Integrator are permitted for attending the pre-bid conference. OEMs or other Partners shall raise their queries through respective SIs. All the queries / clarifications are to be sent in format given below. All queries / clarifications should be sent in advance, any query sent after the closing of bid query acceptance timeline i.e. 24 Hours before the pre bid conference shall not be entertained:
Name and Address of the Organization submitting
Request Name, Position and Contact details of person submitting
request
Sr. No Section No / Clause No.
Page No. RFP / SRS Sentence
Query / Clarification Sentence
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 4
CESU, Odisha Page 4 Release Date: 27th February 2016
I. Bidders should observe a high standard of ethic during the selection process and in the execution of this contract.
J. Any bid i.e. Technical, price or Bid Security cover received after the due date and time will not be accepted and the offer will be categorically ignored without any communication.
K. The bid, even though fulfilling the specified qualifying requirements/criteria as specified in the RFP bid document, are liable to be disqualified in case of non-compliance to the followings by the bidders :-
a. Not made misleading or false representations in the forms statements and
attachments submitted in proof of the qualification requirements. b. Has not been blacklisted by any company, Board, organization or government
body.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 5
CESU, Odisha Page 5 Release Date: 27th February 2016
1.0 Power Sector overview
From modest beginnings at the time of Independence, the Indian power sector has grown a
hundredfold – and is targeting a further doubling of capacity within the next decade or so. No
doubt, a tremendous achievement and there is no escaping the fact that the sustained growth
of the power sector has been one of the major drivers for the success story that is the Indian
economy, certain pain areas notwithstanding.
Starting from the opening up of the generation sector to private sector in October 1991 to the
1998 Act through which the regulatory agencies were sought to be set up and culminating in
the integrated Electricity Act, 2003, a remarkable continuity of vision and thought process has
been demonstrated by the highest level of planners, changes in government and other factors
notwithstanding. From the distribution utilities’ point of view, the two most significant
programmes taken up by the Ministry of Power, Government of India are the two versions of
the Accelerated Power Development Reforms Program i.e. APDRP-I and APDRP-II.
The thinking and policy directions that have now been decided on by the Ministry of Power,
Government of India in consultation with the leading power utilities in the fields of generation,
transmission and distribution can be summarized as follows:
� Protection of the interests of economically weaker sections of society; in particular those
living Below the Poverty Line (BPL) and whose daily energy consumption does not exceed
30 kWh per month
� Centers of excellence across the country to show the way
� 11 kV feeder will be treated as a profit center, with the concerned Junior Engineer playing
the role of a Feeder Manager (for one or more feeders as necessary)
� Committed and sustained movement towards improving the financial viability of the power
distribution utility
� Identification of Key Result Areas to help in prioritizing the various organizational initiatives
� Preparing all the market players to play an active, responsible but commercially-oriented
role in an ABT environment; both at the inter-State as well at the intra-State level when the
necessary communication infrastructure is in place and organizational capabilities have
been suitably enhanced
� Move towards rational tariff structures and reduce, if not eliminate, subsidies and cross-
subsidies to within 20% of properly ascertained cost of supply for all categories of
consumers
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 6
CESU, Odisha Page 6 Release Date: 27th February 2016
2.0 Overview of CESU of Odisha CESU has come into effect from 08.09.2006 after restructuring of erstwhile CESCO in compliance of Electricity Act 2003. CESU is a major power utility of the state with consumer strength over 20 Lacs approximately. 5 Circles, 20 distribution divisions, 65 Sub divisions and 250 electric supply offices make up the backbone to the power CESU, Odisha distribution system of the CESU area of operation. At present database of all IT activities of CESU is being maintained at Divisional Computer Centre (DCC) under the control of Divisional Manager of respective Divisions. At present, CESU is having 20 nos of such DCCs located all over CESU area. In its corporate Headquarters, CESU has a central Data Centre with 4 Mbps & 8 Mbps dedicated leased ISPs for connectivity with all the DCCs. Electric Supplies under the control of Distribution Divisions are mainly dealing with all consumers except EHT consumers. Most of the Subdivision offices in urban area are facilitated with Broadband connectivity. CESU has two categories of bulk consumers namely, Division billed and Spot Billed consumers. CESU has taken steps towards reduction of ATC loss by appointing Distribution Franchisees in 14 out of 20 divisions in BOT model. In order to provide better service to the customers of CESU and meet various stakeholders like Regulators, State Government, the CESU proposes to implement various IT infrastructure across its core business functions so that IT enabled process automation can be achieved without human intervention or manual work. MoP, GoI sanctioned the R-APDRP Scheme for 12 towns of CESU area in Odisha on 1st March 2014 and accordingly CESU has initiated various activities for the implementation of the scheme. Considering the objectives of the R-APDRP scheme, CESU proposes that a GPRS based Energy Audit & Accounting system will be implemented across its project areas covering network as well as high value consumers which be based on open protocol rather than vendor specific protocols. CESU will also move from the current decentralized billing database to adopt a centralized approach. As CESU Head Office is located in Bhubaneswar and also it is centrally located and has access to better communication as well as infrastructure. Hence, it is proposed that CESU's data centre will be located in Bhubaneswar which is under Bhubaneswar UA. Similarly, CESU also proposes that a Disaster Recovery Site will be located at the Berhampur Town or any other town to be selected by CESU for business continuity.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 7
CESU, Odisha Page 7 Release Date: 27th February 2016
Electricity Sector organizations in Odisha
OERC Odisha Electricity Regulatory Commission http://www.orierc.org
OHPC Odisha Hydro Power Corporation Limited http://www.ohpcltd.com
OPGC Odisha Power Generation Corporation Limited http://www.opgc.co.in
NTPC
(TTPS) Talcher Thermal Power Station http://www.ttps.com
OPTCL Odisha Power Transmission Corporation
Limited http://www.optcl.co.in
GRIDCO Grid Corporation of Odisha Limited http://www.gridco.co.in
CESU Central Electricity Supply Utility of Odisha http://www.cescoorissa.com
http://www.cesuodisha.com
3.0 CESU Vision
• To ensure uninterrupted quality and reliable power supply to its consumers.
• To be the best distribution utility of India.
• To make every work place a safe working place.
• To be socially responsible for employees and society.
3.1 CESU Area Covered in R-APDRP Scheme
Under R-APDRP scheme, The Ministry of Power, Govt. of India has sanctioned Detailed
Project Reports (DPRs) of 12 towns of Central Electricity Supply Utility of Odisha.
Details of approved towns are as follows:
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 8
CESU, Odisha Page 8 Release Date: 27th February 2016
Details of
CESU
towns for
R-APDRP
ProjectSr.
No
Town Name Connections
Area
(Sq.
Km.)
No. of Sub
Division &
Division
Offices
No. of Other
Offices
Total
No. of
Offices
1 Cuttack 90,252 64 7* 16* 23*
2 Bhubaneswar (HQ) 2,21,595 135 8* 37* 45*
3 Puri 37,496 17 3 16 19
4 Khordha 8,547 26 2 3 5
5 Jatni 7,138 25 1 3 4
6 Dhenkanal 14,878 31 1 8 9
7 Angul 13,669 19 1 5 6
8 Talcher 6,375 26 1 2 3
9 Kendrapara 9,008 11 2 3 5
10 Pattamundai 6,137 24 1 5 6
11 Jagatsinghpur 6,385 18 1 7 8
12 Paradeep 3,654 32 1 1 2
CESU Total 425,134 428 29 106 135
Note: * Number of offices may change during the period of R-APDRP Project.
The data provided above is as on 1st April 2013 for the area and consumer base covered
under R-APDRP. Bidder has to assume per annum growth of 7.5% in asset and consumer
base. However, consumer for entire CESU as on date is 20 Lacs approximately.
While Power distribution in Bhubaneswar & Cuttack is directly under CESU, two different Distribution Franchisees are managing 33kV and below electrical network, power distribution, billing and collection in remaining ten towns. Power distribution in Puri, Khordha & Jatni is handled by M/s FEDCO whereas M/s Enzen Global Solution is entrusted for handling the same in Dhenkanal, Angul, Talcher, Kendrapara, Pattamundai, Jagatsinghpur & Paradeep. These ten towns would be collectively referred as Franchisee Towns for the purpose of this document.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 9
CESU, Odisha Page 9 Release Date: 27th February 2016
3.2 Scope of Work for ITIA in R-APDRP Area
Under the R-APDRP (Part-A) Scheme, the following IT Infrastructure Setup has been
envisaged:
1. Establishment of Data Center at Bhubaneswar
2. Establishment of Disaster Recovery Center at Berhampur or any other town to be
selected by CESU.
3. Establishment of Customer Care Call Center at Bhubaneswar for seating capacity of 5
with a Toll Free No.
4. Providing all of the following modules and systems for the towns of Bhubaneswar and
Cuttack
i. Meter Data Acquisition System
ii. Energy Audit
iii. New Connection
iv. Disconnection & Dismantling
v. GIS based Customer Indexing and Asset Mapping
vi. GIS based integrated Network Analysis Module
vii. Centralized Customer Care Services
viii. Management Information System (MIS)
ix. Web Self Service
x. Identity and Access Management System
xi. System Security Requirement
xii. Development of Commercial Database of Consumers
xiii. Metering
xiv. Billing
xv. Collection
xvi. Asset Management
xvii. Maintenance Management
xviii. Document Management System
xix. Mail / Messaging System
xx. Enterprise Management System and Network Management System
xxi. Antivirus & Firewall System
xxii. Data Warehouse System with MIS application
5. AMR Implementation, including installation of meter modems and data concentrator
6. DGPS based GIS Survey
7. Establishment of LAN, MPLS-VPN and other networking in all the identified towns of
the CESU. Number of offices mentioned in Appendix – S.
8. Facility Management Services for 5 years from the “Go-Live” Date of Project
a. Integration, as envisaged in G1 section under 3.10 paragraph of SRS
Document, with existing applications
9. Data Migration for following applications as envisaged in section G1 under 3.9
paragraph of SRS, but not limited to
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 10
CESU, Odisha Page 10 Release Date: 27th February 2016
a. Metering
b. Billing
c. Collection
d. New Connection
e. Disconnection and Dismantling
f. Asset Management
g. Maintenance Management
h. GIS field survey data
10. Following modules are to be implemented in franchisee towns as well.
a. Energy Audit
b. GIS based Asset Mapping
c. GIS based integrated Network Analysis Module
d. Incremental Asset Data Import in GIS
e. Incremental data imports for Energy Audit
11. The software shall be centralised with customised requirements of the town. CESU
users shall have access to the system based on their roles and responsibilities.
For Towns Other than Bhubaneswar & Cuttack
a. DF (Distribution Franchisee) shall create non-GIS based Consumer Indexing
(CI) and Asset Mapping (AM) database and shall carry-out MBC activities
along with AMR data capture and changes related to meters / consumers
b. CESU will ensure that required infrastructure and processes are established in
Franchisee Towns for making live and sustenance of applications mentioned in
point 10- above. Some of these requirements are mentioned below.
i. Installation, maintenance and replacement of energy audit meters
before go-live as well as after go-live
ii. Regular reading download of energy audit meters and making these
available at DC and upload of same
iii. Mapping of Assets and its regular updates for changes on GIS map
iv. Process for incremental assets, meters and reading upload
v. IT infrastructure, network bandwidth and resources with requisite skills
for franchisee towns
c. CESU shall ensure that the data from the above mentioned activities are being
available in the server at DC on regular basis along with the CI and AM data
updation / upgradation.
d. ITIA shall import and process the above mentioned data into the newly build
Integrated system and shall ensure the Energy Audit & Accounting processing
including report preparation.
Note:
Energy audit meters are installed up to LT feeder level in all 12 towns. Since only
Bhubaneswar and Cuttack are under direct control of CESU, following approach would
be followed.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 11
CESU, Odisha Page 11 Release Date: 27th February 2016
Bhubaneswar and Cuttack:
With the help of correct consumer indexing and billing data, system should
automatically link the feeder level billed units and corresponding data from respective
energy audit meters at feeder to arrive at feeder level energy audit report. Same would
get linked to audit reports at DT/HT/EHT level. Consumption data is to be extrapolated
on pro-rata basis for any difference in duration of reading period.
Franchisee Towns:
Provision should be there to upload en-mass or enter feeder wise billed consumption
for specific dates (data to be provided by respective franchisees). Subsequent process
/ logic would remain same as defined for Bhubaneswar and Cuttack.
Since there is distinct possibility of conversion of any Franchisee town to non-
franchisee town, provision should also be made for conversion of Franchisee Town to
non-Franchisee town for all the applications
Exclusive Features
For the purpose of Software licenses and scalability of IT Hardware & networking equipment
in datacenter & disaster recovery center of this project, ‘Enterprise’ is to be considered as all
entities (or legal heir) authorized to distribute electricity in the State of Odisha whereas utility
would mean CESU and its current license area.
CESU of Odisha plans to build integrated IT solution for the entire enterprise. Through this
bidding process, CESU intends to select IT implementation Agency (ITIA) to build IT
Infrastructure for Data Centre for entire area of CESU of Odisha and implement all
applications of R-APDRP scheme as specified in the scope of work for Bhubaneswar &
Cuttack. In addition to these, for remaining ten towns (specified in the scope of work) selected
bidder is required to roll out GIS, GIS based asset survey and mapping, GIS based integrated
network analysis, energy audit, MDAS and integrated MIS for CESU. For this purpose, ITIA is
expected to build the required interfaces for data upload of incremental changes in assets,
electrical network, consumer indexing, MBC (metering, billing and collection) and other
modules of Franchisee Towns. The technical specifications for the scoped items would be
same as elaborated in this section and as mentioned in SRS and subsequent corrigenda
issued by PFC or CESU till the time of Bid Submission.
ITIA is also required to build interfaces for migration of base data from existing systems,
transit (incremental change) data during roll out and interfaces for existing applications, which
CESU would like to retain. Some of these applications are mentioned below.
1. Spot billing: Presently SBMs are of M/s Analogic and M/s Linkwell (Visiontek) make
and billing code for these machines are provided and maintained by the respective
vendors. For ease of maintenance and support, ITIA is to build its own billing code
for these machines. Hardware specs of SBMs are mentioned in Appendix – O.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 12
CESU, Odisha Page 12 Release Date: 27th February 2016
2. ECS registration module: To register and get collection information for consumers
opting for payment through ECS.
3. Existing Payment Gateway with Odisha e-Governance Services Limited (OeSL) is to
be integrated with ITIA’s system along with any other future payment gateway.
4. A scheme is proposed specifying the responsibilities of ITIA, CESU and Distribution
Franchises for GIS Implementation in the franchised towns as mentioned in
Appendix – R.
5. The Bidder has to provide the network connectivity to CESU offices and the meters
only in Bhubaneswar and Cuttack. Number of offices mentioned in Appendix – S.
Till the roll out of the entire system in proposed R-APDRP applicable towns, the R-APDRP
application will go live one after another town. The data from Go live town should be made
available to old CESU system through computerized automated interface as per the CESU’s
required specification. The ITIA should develop such an interface in the delivered system.
The detailed interface requirements document shall be provided to the Selected ITIA during
the ‘To-Be’ document phase.
It may be noted that above listed applications are only illustrative for the purpose of building
interfaces and hence it is advised that the intended bidders should study and carry-out
necessary due-diligence prior to quoting in the bid process.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 13
CESU, Odisha Page 13 Release Date: 27th February 2016
4.0 Bid Highlights
1. The requirement of the hardware and other units mentioned in BOM Appendix L are as
per the CESU’s approved DPRs. However, the payment will be made as per the actual
quantity consumed during the execution as per the site and solution requirements.
2. The evaluation shall be made on the overall cost of the items and quantities quoted in the
bid in compliance to RFP. However, while placing the order, or during the execution, the
utility reserves the right to modify the quantities of individual items to the extent of +/- 20%
of the mentioned BOQ subject to within a range of 10% of the value of the overall project
cost.
3. Accordingly the selected bidder, after the award of contract, will finalize the actual
quantities to be deployed after approval of the CESU, before initiating the purchase
process of such items.
4. The bidder is expected to complete the pilot implementation at Sub Division-3 area under
BCDD-1 division of Bhubaneswar Town of CESU including the Centralized Call Center,
Data Centre at Bhubaneswar and Disaster Recovery Centre at Berhampur (or any other
place as finalized by CESU) within 12 months from the date of LOI and complete rollout in
all the approved towns in next 6 months.
5. All application software, hardware, data, plans, drawings, specifications, designs, reports
and other documents procured or developed by the selected vendor in the execution of the
contract shall remain the property of the CESU, right from the beginning of the contract,
during the whole duration of the project and after the expiry or termination of the contract.
The CESU shall also remain the sole owner of the property (Hardware / Software) in case
the contract is terminated for any other reasons. This should be handed over to CESU
before go-live. Bidder would also hand over to CESU the code, documentation and version
details for any changes/ customization/ configuration/ modification done on bought out
applications or indigenously developed applications (for CESU) before the same is moved
from development/ test/ quality to production servers.
6. The source code of the customized part of the application software will remain the
exclusive property of the CESU, even after the termination or expiry of the contract. The
ownership shall also remain with the CESU in case the selected vendor fails to execute
tasks to the satisfaction of the CESU.
7. If the MoP or PFC issues any amendment to the SRS or Model RFP document till the date
of opening of this bid document, those amendments will become an integral part of this bid
document, for which no separate intimation will be given to the empanelled SIs.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 14
CESU, Odisha Page 14 Release Date: 27th February 2016
8. The bidder shall give self-declaration in the technical proposal that the FMS Cost has been
taken as minimum 20% of the total project cost (excluding FMS and bandwidth cost) and if
it is less than 20%, its bid may be declared as non-responsive.
9. The Bid Security mentioned in this document is for the entire bid.
10. The Performance Security will be 10% of the total bid amount as per SCC of this bid
document. However, an additional FMS Performance Bank Guarantee (FMS-PBG) equal
to 20% of the total FMS value for a period of 5 years starting from beginning of FMS
period is required to be submitted by the bidder.
11. Bidders to provide power point presentation in soft copy and hard copy with the Technical
proposal, to detail the functionality of below listed modules. The major Modules to be
covered are as under:
a. Metering
b. Billing
c. Collection
d. New Connection
e. Meter Data Acquisition System
f. CRM for Call Center
g. Energy Audit
h. Asset Management
12. During the course of evaluation of technical bid, the purchaser reserves the right to verify
the availability of various functionalities mentioned by the bidder in Appendix-B as
“available without modification” in a live demo of the system. . However, no bid shall be
rejected on the basis of Demo.
13. Since the execution of R-APDRAP scheme within the stipulated time is a pre-requisite to
convert the amount sanctioned by Ministry of Power (MoP) from loan to grant, the vendor
is required to plan project execution activities strictly as per the timelines.
14. Meter data captured through GPRS/CDMA Modem will be transmitted directly to Data
Centre / DRC for which appropriate connectivity bandwidth will be provided along with SIM
Cards in the name of CESU and enable it to pay directly to the service provider
15. Architecture Designs: The Software Application architecture should be designed in a way
that it should be possible to integrate the application and database of additional towns, if
the need be. The integration mechanism should be flexible and implemented at no cost to
the CESU.
16. The bidder should give a declaration on its Letterhead that its bid DOES NOT DEVIATE
from the RFP, SRS and their amendment/corrigendum issued till the date of bid
submission.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 15
CESU, Odisha Page 15 Release Date: 27th February 2016
17. The proposed solution should have the provision for integration with near future systems
like Automated Metering Infrastructure (AMI), SCADA, etc. System Integrator would be
solely responsible for providing the necessary touch points in required technology for
integrating future solutions with proposed systems during the complete contract period.
18. Data Center and Disaster Recovery Center:
The following will be considered and factored for sizing Data Center and Disaster
Recovery Centre and all its hardware, network components and their operating
systems.
i. Total consumer base and entire asset base of the CESU of Odisha will need to
be considered along with the scalability of 7.5 per annum to factor future growth
for sizing of servers and network bandwidth.
ii. For all software, licenses (except operating systems) in datacenter (and DR
centre) like database, applications, exchange, AD, monitoring, backup,
middleware, GIS, MDAS, access control, etc are to be sourced for entire
enterprise.
iii. For this purpose current consumer base for the utility is to be taken as 20 Lacs
approximately.
iv. The increase in consumer base and electrical asset base may be assumed at
the rate of 7.5 per annum compounding as specified by PFC on the base data
provided as on 1st April 2013 in the RFP up-to the date of Go- live and five
year support after go-live.
v. The bidder will have to size the system keeping in mind the contingencies such
as change in business process and business logic from the date of
commencement of work up-to the end of 5 years from date of Go-live of total
project.
vi. The sizing of applications and database servers, storage, network, operating
systems, Anti-virus etc. shall be done to comply with and maintain the SLAs
defined in SRS document and the scalability factors.
vii. In case of performance issues (non-compliance of SLA) for CESU area
requiring additional hardware or need for additional software license in Data
Centre or Disaster Recovery Centre for roll out of applications within state of
Odisha, ITIA to procure, install and configure these without any additional cost
to CESU up to 5 years from Go-Live.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 16
CESU, Odisha Page 16 Release Date: 27th February 2016
viii. The system must comply with the SLAs defined in SRS and included here-in
from the date of commencement of work up-to the end of 5 years from date of
complete live roll out of total project.
ix. In case bidder assumes any data or works out sizing in the absence of required
data, it should inform in writing to CESU so that necessary input can be
provided.
19. The quantities / capacity given in respect of servers for DC / DRC/CCC are only
indicative but the bidder shall quote as per the quantity required for its proposed
solution.
20. The DRC will be an exact replica of DC i.e. all the software, hardware and network
equipment and other items etc. provided at DC will also be installed and commissioned
at DRC along with relevant licenses to support all operations from DRC during DR drill
and in event of disaster.
21. It is mandatory requirement to provide the details of the basis for sizing of servers,
storage and network bandwidth in the technical proposal.
22. SAN cable is to be quoted as lot irrespective of its length. Bidders to provide minimum
usable SAN Capacity of 75 TB each at DC and DR.
23. Each database server shall be enterprise level SMP RISC / EPIC / CISC / x-86 64-
Bit processor based system and should be capable of minimum TPM-C rating of
14,00,000 (14 Lacs) or higher for fully populated configuration. OEM should certify this
on its letterhead with the estimated benchmark.
24. Application and other Servers shall be enterprise level SMP RISC / EPIC / CISC / x86
64-bit processing based system and each should be capable of minimum SPEC JBB
2005 rating of 800,000 bops (business operations per second) for fully populated
configuration. OEM should certify on its letterhead the estimated benchmark, in case it
is not published. The bidder shall offer the suitable servers considering the SRS
document along with its amendment and the benchmark parameters as mentioned
above as a referral point.
25. All Servers should be offered with latest CPU with highest clock speed available on the
server model being offered by the bidder at the time of bidding
26. All operating systems, databases and applications should be of latest version as
supported by OEM.
27. Each Server shall be configured with even number of CPUs.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 17
CESU, Odisha Page 17 Release Date: 27th February 2016
28. Server OEMs must be member of Transaction Processing Council (TPC) or Standard
Performance Evaluation Council (SPEC).
29. The Centralized Data Centre will be at Bhubaneswar. The Centralized DRC at
Berhampur town or any other town to be selected by CESU.
30. The successful bidder shall provide the DC requirements relating to all relevant
components, layouts, air conditioning requirements, detailed requirements of Civil and
Electrical work like earth pit, Electric Connection to UPS, DG set, Change over switch,
Cooling arrangement, Harmonic filter, Fire system, Access control and CCTV, Smart
cards, Cage construction, False ceiling, False Flooring, Interiors, furniture, etc. which
are in Scope of the Purchaser.
31. Facility Management Services: FMS Charges are required to be mentioned town wise
for 5 years from the date of Project “GO-LIVE”.
32. Licensing
a. All the licenses shall be procured in the name of “Central Electricity Supply Utility of
Odisha”.
b. The bidder shall provide enterprise wide license without constraint of number of
CPU / Core / Number of Users / Number of Consumers for all applications and
system software.
c. The GIS licensing should cover viewing rights to all users and edit/deletion/addition
rights to one Authorized User per Sub Division in the CESU.
d. All the licenses shall be owned by CESU of Odisha even after the end of period of
5 years from the date of “GO- LIVE” of the Project. CESU and any new power
distribution entity that emerges in CESU shall have complete right to use these
licenses.
e. The purchaser shall be at liberty to deploy the solution anywhere within the CESU
of Odisha.
33. Messaging Server: Utilities of Odisha intend to opt for messaging server and it is
required that the ITIA to provide this facility to the utilities with following highlights in
addition to requirements envisaged in SRS
a. The utilities will be having mail messaging facility which they can access by using
either Internet or Intranet.
b. CESU will have its own unique email extensions. For example CESU utility may
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 18
CESU, Odisha Page 18 Release Date: 27th February 2016
34. Performance Parameters for Switches: Type Port Densities
Support MAC Address Support
VLAN Support
Core Switch 200+ (10/100/1000) 64K 4000
Distribution Switch 100+ (10/100/1000) 32K 2000
Layer III Switch 48 (10/100) 8K 255
Access Switch (DMZ) 48 (10/100/1000) 8K 255
Core Switch & MPLS router packet forwarding rate should be minimum 200 Mpps
35. The ITIA will propose bandwidth sizing requirements for all offices and for GPRS modems
to meet the requirements of the proposed solution to achieve performance level and SLA
level during the entire period of engagement. The ITIA will resource Bandwidth from a
Network Bandwidth Service Provider (NBSP). The Utility shall pay the bandwidth charges
directly to the Bandwidth Provider. The ITIA would be required to enter into Tripartite
Agreement with the Utility and Network bandwidth service provider to manage and
oversee the network bandwidth service provider to ensure performance levels meeting
SLAs.
The minimum bandwidth requirements are given below:
No. Office/
Location Type of Connectivity Minimum Bandwidth
Requirement
1 Data Centre
Internet – Primary
Linkage
10 Mbps
Bidder to reassess for proposed solution
Internet – Secondary
Linkage (In H/A load
balancing Mode)
4 Mbps
Bidder to reassess for proposed solution
MPLS VPN – Primary
8 Mbps
Bidder to reassess for proposed solution
Secondary Linkage
2 Mbps
Bidder to reassess for proposed solution
2 DRC Internet – Primary
Linkage 8 Mbps
Bidder to reassess for proposed
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 19
CESU, Odisha Page 19 Release Date: 27th February 2016
solution
Internet – Secondary
Linkage (In H/A load
balancing Mode)
4 Mbps
Bidder to reassess for proposed solution
MPLS VPN – Primary
8 Mbps
Bidder to reassess for proposed solution
Secondary Linkage
2 Mbps
Bidder to reassess for proposed solution
3 DC / DR
Replication
Primary Linkage Bidder will size to meet the RPO & RTO-Refer SRS (Section 22.6 of G3)
Secondary Linkage (In
H/A load balancing
Mode)
Bidder will size to meet the RPO & RTO-Refer SRS (Section 22.6 of G3)
4 Customer Care
Centre
MPLS VPN – Primary
4 Mbps
Bidder to reassess for proposed solution
Secondary Bandwidth
2 Mbps
Bidder to reassess for proposed solution
5
Division and
Subdivision
Office
MPLS VPN – Primary
Linkage
Min 2 Mbps
Bidder to reassess for proposed solution
Secondary Linkage
Minimum 512Kbps
Bidder to reassess for proposed solution
6 Other Offices
MPLS VPN – Primary
Linkage
512 Kbps
Bidder to reassess for proposed solution
Secondary Linkage Not required
7
From GPRS
Modem to
DC/DRC
Should be assessed by bidder
Note:
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 20
CESU, Odisha Page 20 Release Date: 27th February 2016
� Mentioned bandwidths are minimum requirement and in case bidder requires higher
bandwidth for meeting the required SLA, the same shall be proposed by the bidder in
bid response.
� All the connectivity terminating at DC and DRC should be on fiber, the bidder should
provide sizing documents.
� The CESU reserves the right to ascertain the actual bandwidth usage pattern of the
different offices and if required the bandwidth may be revised accordingly on mutually
agreed terms and condition.
� Primary & secondary connectivity for DC/DRC/CCC and internet connectivity should
be sourced from two different ISPs.
36. Trainings: In addition to the scope envisaged in SRS document for trainings and
documentation, followings will be part of ITIA scope:
a. The selected vendor will provide the training on the various applications to application
users of CESU as per client requirements.
b. The training shall be conducted by experienced instructors of ITIA and OEM.
The System Integrator in consultation and convenience of the CESU shall workout the
training program and all the other modalities of the training, which should be delivered
by OEM certified and SI.
c. The training shall be conducted at sites to be specified by CESU.
d. System Integrator to conduct a training need analysis to determine the training and
development needs for all the job roles that will be affected by the CESU technology
initiatives. This will result in Training and Development plan including
i. The training requirements per user group
ii. Recommendations on the most appropriate training delivery methods and
channels.
iii. Identification of the criteria for training success along with any challenges and
risks.
iv. Knowledge sharing strategy to enable to perform future customizations
internally.
v. Content Development: Development of customized, modular training materials
based upon user roles and business processes and customized application.
OEM consultant along with ITIA will work together with CESUs resources to
enable knowledge transfer. The following material will be developed
o Paper Based Class room Participant guides,
o Paper Based Class room Instructor guides,
o Media Based training simulations for pre-class preparation
e. ITIA to provide the separate training delivery plan for the CESU in the Technical Bid
proposal.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 21
CESU, Odisha Page 21 Release Date: 27th February 2016
37. Electronic data migration is required from the existing applications to the new application
systems. Also digitization of assets and consumer records etc, as appropriate (serviced
over last three years) will be needed by data entry / document scanning to create
electronic data for use in various applications and document management system etc. by
the ITIA at the respective Division & Sub-Division offices.
38. ITIA shall integrate all R-APDRP applications with the SCADA system to be installed
separately. Also it will be required to integrate all such future applications deployed by the
Utility (during the contract period) with the applications provided under R-APDRP without
any extra cost.
39. The following elaboration is the requirements of SRS item “MIS 9: Provision of Business
Intelligence Tools. This module should provide Business Intelligence Tools for data
mining, analysis, trending, simulation etc”.
a. Provision of Business Intelligence Tools in the SRS and the specifications “Data stores
for transaction processing shall be kept separate from data stores for decision support”
given in System Functionalities section of SRS.
b. It is clarified that the Business Intelligence tools like Query and Report, On Line
Analytical Processing (OLAP) and Data Mining etc. will be configured and data stores
created in the framework of Data Warehouse. The data on which BI Tools will be used
will require data from disparate source applications and systems. The Extraction,
Transformation and Loading Tools (ETL) will be used to extract, transform data to
establish a common format, scrub and homogenize data, summarize and aggregate
data before loading into Data Warehouse. The data stores for Decision Support
System will form the Data Warehouse. The number of reports will be unlimited for
Utility.
40. If the MoP, PFC or Utility issue any amendment to the SRS or RfP till the date of
submission of this bid document, those amendments will become a part of this BID
document and no separate intimation shall be given to empanelled ITIAs. This, however,
will be no reason for any extension of bid submission/ opening date. The bidders are
advised to remain updated with the latest amendments issued by MoP, PFC & Utilities.
The SIs are also advised to check websites of MoP (www.apdrp.gov.in), PFC
(www.pfcindia.com) & Utility (www.cescoorissa.com / www.cesuodisha.com) regularly for
any amendment or addendum. For any amendments to this tender, the same shall be
updated in CESU’s website and no separate notifications shall be issued in the news
media or letters to the empanelled firms.
41. Clarification on User acceptance Testing(UAT): Acceptance testing has been defined in
the clause 3.6 (Testing and Acceptance procedure) in SRS section–G1, General Technical
specification and it is clarified that the performance testing will be part of Acceptance
testing as already defined in this clause of SRS document.
The term ”User Acceptance Testing” as used in RfP, as referred above and “Acceptance
Testing” as defined in the SRS document shall mean the same and vice versa”
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 22
CESU, Odisha Page 22 Release Date: 27th February 2016
42. Clarification on Go Live of a Project area; Pilot is the first project area that goes live in the
utility (CESU) along with the Data Center. The Go–Live of the pilot area may be
considered complete provided -
i. The Data Center has been completed in all respects including installation,
commissioning of all hardware and networking devices, installation, configuration and
customization of all RAPDRP application software as per requirement of utility and
their integration, integration with legacy applications (limited to applications defined in
SRS), if any, completion of functionality and other tests required as per specification,
availability of network connectivity etc.
ii. All the works in pilot area have been completed including installation, commissioning
of all Hardware and networking devices, completion of GIS survey activities and its
approval by utility, GIS data migration into GIS application, availability of meter data
from all system and HT consumer meters in MDAS system, operational connectivity
with data center and access of all the R-APDRP application at data center by the end
user in pilot area as per utility defined access rights.
iii. The Go live of the other project areas (towns) shall be completed progressively similar
to pilot area as clarified in para (ii) under this clause mentioned above.
43. The Bid Submission Sheets and Price Schedules given in RFP Section V. ‘Price Bid
Forms’ should be submitted on Company Letter Head and signed by an officially
authorized representative to sign the bid and stamp it with company seal. All other pages
of the documents – the RFP, the SRS and any addendum to SRS issued by PFC as also
any modification / elaboration or deviation taken by Utilities to SRS or RFP shall be signed
on each page with stamp of company seal by the authorized representative.
44. Technical proposal should have detailed Un-priced BOM with Make, Model and
Quantities of all the items for the proposed solution as per the annexure “Un-Priced
Technical Bid Form”. It should not have cost of any item.
45. The bidder should, if it feels necessary, study on its own, at its own cost, the existing
status, data, consumer base, geographical spread of the Utility. The bidder shall structure
the proposal as per the requirement of the system/solution being envisaged. Utility under
no circumstances shall accept any disclaimers from Successful Bidder on this account.
The ‘out of scope’, ‘exclusions’ and ‘assumptions’ having cost implications will not be
entertained and will be treated as deviations.
46. All update/upgrades and maintenance of all software and hardware should be provided as
per SRS Section G-1 Clause 9(D)-Annual Technical Support at no extra cost.
47. All equipment shall have onsite warranty from OEM and in accordance with SRS. OEM
certificate needs to be enclosed for after sale support. Successful bidder should maintain
adequate spare parts/hardware to support SLAs throughout contract period.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 23
CESU, Odisha Page 23 Release Date: 27th February 2016
48. The unit prices mentioned for various components should be the same for all Project
Areas. In case of any variance in unit prices for different Project Areas, the lowest unit
price of equipment mentioned for any Project Area shall be applicable and payable across
all the project areas.
49. All queries relating to this bid document that the prospective bidder wants to be clarified
during Pre-Bid Conference should be emailed to [email protected] at
least 24 hours before the pre-bid meeting date. No queries about the G3 section of SRS
will be entertained.
50. The source code of the customized part of the application software will remain the
exclusive property of Utility, even after termination or expiry of the contract.
51. Utility will define own archiving and data / document retention policy. The ITIA will
implement and observe these policies during the FMS period.
52. ITIA shall implement the Odisha IT security policy (currently under development) and any
modifications thereto during the period of its engagement.
Utility will have a defined enterprise wide Information Security Policy. The ITIA will be
responsible to incorporate all such security policies and modifications thereto during
implementation and FMS periods in the solution without any additional cost to CESU.
53. The vendor needs to incorporate all changes and additions in the applications suggested
by CESU during the implementation phase.
54. ITIA need to carry out the study of Business Processes, requirements and the
modifications to as being followed till Go-live and the same shall be implemented by the
ITIA.
55. Web pages will be developed for CESU of Odisha as per their requirements. The
necessary web pages will be designed irrespective of number of pages. Any updation /
addition / deletion in the web pages during the implementation and 5 years after the date
of “GO-LIVE” will be responsibility of ITIA without any additional cost to the utilities.
56. The bidders shall furnish the details of their quality assurance plan and test set up along
with the bid. A detailed quality assurance program shall be finalized with the successful
bidder during the award stage. However, the Quality Assurance plan shall conform to the
following standards and the bidder shall provide undertaking regarding the same.
a. IS / ISO / IEC 27001 - ISMS
b. IT Security, IT Services (10 Standards) – All harmonized with ISO / IEC
c. LITD 16 – Standards on computer hardware
d. IS 13252 : 2003 / IEC 60950
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 24
CESU, Odisha Page 24 Release Date: 27th February 2016
57. CESU of Odisha will provide necessary authorization to ITIA for obtaining meter protocol
and memory map from meter manufacturers. ITIA and Meter manufacturer will sign Non-
Disclosure Agreement with CESU.
58. Meter data captured through GPRS/CDMA Modem will be transmitted directly to Data
Centre for which appropriate connectivity bandwidth will be provided by bidders.
59. Procurement, supply and installation of SIMs for AMR solution will be under the scope of
ITIA.
60. All workstations should be provided with TFT Monitor having 15” or more size with
Resolution of 1024 x 768). It is mandatory that all the PCs need to be supplied with UPS
as specified in the SRS.
61. The Operating System on desktop machines will be latest Microsoft Windows with free
updates for the period of 5 years at no extra cost to CESU. There will be an enterprise
wide license for Operating System for the total PCs under this bid.
62. ITIA to do the following activities for the Data Health Assessment on legacy data
a. Identification of data cleansing requirements and submission of detailed report
b. Correction of data in production source systems
63. The ITIA to set up Project Management Offices at head quarter (Bhubaneswar), CESU
and propose the organizational structure for project execution and management with
details of personnel and their period of deployment and keep the Utility updated. The
Curriculum Vitae (CV) of the proposed resource personnel should clearly indicate the
position of the resource for this project as well as the proposed period of engagement on
this project. The relevant entries would be included in the format of the CV to be
submitted. The CV to be submitted shall duly have the signature of the authorized
representative of the bidder for verification of the details.
64. The successful bidder shall give presentation to CESU on project initiation and periodically
about the status of the project implementation on periodical basis or as desired by the
CESU.
65. Recovery Time Objective (RTO) and Recovery Point objective (RPO) shall be as per the
SRS document.
66. Bidders to provide 5KVA Online UPS at all division and sub division Offices and 2 KVA
Ups in all other offices in the areas under the scopes.
67. All FMS services as specified for DC will also be performed at DRC
68. All SLAs defined and applicable for DC will also be applicable and measured at DRC,
When DRC is live.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 25
CESU, Odisha Page 25 Release Date: 27th February 2016
69. The ITIA will conduct a DRC drill before DRC acceptance test.
The utility may conduct an annual DRC Drill for which ITIA shall fully provide support for
switch over of operations to DRC and back to DC. The RTO and RPO shall be complied
with.
70. The ITIA shall define the procedure for the DR drill and demonstrate the same during UAT
phase. During the FMS period the department intends to carry out annual DR drill for all
services covered under this project and ITIA to support. The ITIA shall perform the FMS
activities during the DR drill both at DC and DR sites. The level of services during this
period will be part of SLA measurement as defined in Appendix C of RFP.
71. The measurement of the SLAs mentioned above shall cover for both Data Center and
Disaster Recovery center as applicable. For example: SLA 5.10 above shall be measured
for both Data Center and Disaster Recovery Center.
72. Handholding support for application related operations at Division and Sub Division level
shall be provided by the selected vendor for which at least one person per Division and
Sub Division shall be deputed for the period till the complete rollout.
73. CVC Guidelines may be followed regarding the issue of price negotiations with L1 bidder.
74. At least Quad Core Desktops are to be quoted instead of Dual Core.
75. Bids are liable to be rejected in case bidder engages any of CESU's existing franchisee
agencies or their sister concerns / subsidiaries as its partner during implementation and
support of the project.
76. Except for the Enterprise Applications (as per the model SRS and RFP), user counts are
as below:
a) Total count of users who will be accessing mailing solution – 1200 approx.
b) Total count of users who will be accessing R-APDRP applications – 2000 approx.
c) Total count of GIS users who will perform editing – 100 approx.
d) Total count of locations from which digitization/ scanning of documents are to happen –
10 approx.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 26
CESU, Odisha Page 26 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
Meter data Acquisition
Meter data Acquisition
The above objective under this specification is achieved by providing an Automatic Meter Reading (AMR) based Data Logging System using any of the available Communication Technologies available like GSM, GPRS, EDGE, CDMA, PSTN or Low Power Radio covering all the Feeder Meter, DT Meters and select Consumer Meters in the entire Utility area.
The above objective under this specification is achieved by providing an Automatic Meter Reading (AMR) based Data Logging System using any of the available Communication Technologies available like GPRS, EDGE, CDMA covering all the Feeder Meter, DT Meters and select Consumer Meters in the entire Utility area.
Meter data Acquisition
The substation Data logger PC will acquire data from Feeder Meters and will transmit the same to Sub division office server through a GSM/GPRS/EDGE/CDMA/PSTN/LPR Modem, whereas the Sub division office Data Acquisition server will acquire data directly from all Distribution Transformers as well as HT/select LT Consumers through GSM/GPRS/EDGE/CDMA/LPR Modems. The Data acquisition servers at all sub division offices shall push the entire meter data to central data center on incremental basis during off-peak period on daily basis through MPLS/VPN based WAN network for data aggregation, analysis and generation of MIS report as per requirement of the utility.
- - deleted --
Meter data Acquisition
The meter data from all distribution transformers as well as HT consumers will be transmitted to the central data centre server(s) through GPRS/EDGE/CDMA. A PC will be installed at each substation with a purpose for local viewing and monitoring of feeders by substation staff.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 27
CESU, Odisha Page 27 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
Das1.2 Remote capturing of meter data from system & select consumer meters
A system that captures the meter data remotely from all the meters at 33 KV & 11 KV Feeders, Distribution Transformers and HT/select LT Consumers for sending it directly to the remote collection center i.e. sub division office and data center.
Remote capturing of meter data from system & select consumer meters
A system that captures the meter data remotely from all the meters at 33 KV & 11 KV Feeders, Distribution Transformers and HT Consumers for sending it directly to the remote collection center i.e. Central data center.
Das1.3 Provision of communication media
The system provides for GSM /GPRS/EDGE/CDMA/PSTN/Low Power radio or any other suitable Communication technology between Meters located at Distribution transformer/HT/LT consumers and Sub division office. The system also provides for above mentioned or any other suitable communication technology from Data Logger PC located at substation to the Sub division Office.
Provision of communication media
The system provides for GPRS/EDGE/CDMA Communication technology between Meters located at Distribution transformer/HT consumers and central data centre. The system also provides for above mentioned communication technology from Data Logger located at substation to the Central Data Centre.
Das2.1 Supply /installation of Hardware
Supply and installation of Server, Work station/HMI with Printer and all other hardware system for data logging system at required locations.
Supply /installation of Hardware
Supply and installation of Server, Work station/HMI with Printer and all other hardware system for data logging system at Central Data Centre and at required locations.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 28
CESU, Odisha Page 28 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
Das2.2 Application software for capturing, validating and analyzing the Meter data
Application software for capturing, validating, scheduling and analyzing the Meter data at the electrical Substation and Sub division offices scalable for a size of Network as defined in Annexure-A of Section: G6.
Application software for capturing, validating and analyzing the Meter data
Web based Application software for capturing, validating, scheduling and analyzing the Meter data at any of the Utility Offices scalable for a size of Network as defined in Annexure-A of Section: G6.
Das2.3 Application software at data center
Application software for acquiring incremental meter data from Data logging system of all the sub division offices under the utility area for aggregation, analysis and generation of various MIS report through appending of the Metering module.
Application software at data center
Application software for acquiring incremental meter data from all the metering points under the utility area for aggregation, analysis and generation of various MIS report through appending of the Metering module.
Das2.4 Daisy Chaining, Supply/ installation of data converters at sub stations
Supply and installation of RS 485 to RS 232 Converter at Sub stations along with field wiring/cabling from Feeder Meters to Data Converter unit and from data converter unit to the Computer system at Sub station
Daisy Chaining. Supply / installation of Data Concentrator Unit at sub stations
Supply and installation of data Concentrator Unit and Daisy Chaining of all Substations meter along with field wiring / cabling from feeder meter to Data Concentrator Unit and from Data Concentrator Unit to the computer system at sub-station (Data Acquisition Unit).
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 29
CESU, Odisha Page 29 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
Das2.5 Supply/ installation of Modems at sub stations
Supply and installation of suitable Modem (GSM/GPRS/ EDGE/ CDMA/ PSTN/ LPR) at sub stations for communication between data logging unit located at substation and the same at Sub division office.
Supply/ installation of Modems at sub stations
Supply and installation of Modem (GPRS/EDGE/CDMA) at sub stations for communication between the Data Acquisition Unit at Sub-station and Data Centre
Das2.6 Supply/ installation of Modems at DTs and HT consumers
Supply and installation of suitable Modem (GSM/GPRS/ EDGE/CDMA/PSTN/LPR) at meter ends for communication between Meters located at Distribution transformer and HT/select LT consumers and Sub division office server. If required necessary, the Modem may be retrofitted on optical port of the meter.
Supply/ installation of Modems at DTs and HT consumers
Supply and installation of suitable Modem (GPRS/ EDGE/CDMA) at meter ends for communication between Meters located at Distribution transformer and HT consumers and Data Centre Server(s).
Das3.2 Flexible deployment / implementation of software system
The software system deployment/ implementation should be flexible. The deployment may include installing the software at various locations like substations, sub divisions and data center. The system architecture will be modular so that only the required modules need to be installed at any given location. (e.g. installation at substation computer may have modules like data acquisition or network
Flexible deployment / implementation of software system
The software system deployment/ implementation should be flexible. The deployment should be web based and there should be no need for any installation / licensing at client end.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 30
CESU, Odisha Page 30 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
topology management. But data aggregation/analysis modules may be installed at sub division offices, data center etc. as per the requirement of utility)
Das3.3 Menu driven software system
The software shall be menu driven functions for automatic data capturing, periodic data uploading etc.
Web based software system
The software shall be web based system for automatic data display and reporting
Das3.6 Provision for data validation at both ends
The software shall ensure data validation at both ends e.g. at the substation end before transmission and Sub division office after reception to eliminate possibility of garbage data. The system at Sub division office should apply comprehensive data validation before accepting and using meter data.
Provision for data validation.
The software shall ensure data validation at Central Data Centre after reception to eliminate possibility of garbage data. The system at Central Data Centre should apply comprehensive data validation before accepting and using meter data.
Das4.0 Features of Data logging system at Substation:-
Features for Data logging system at Substation:-
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 31
CESU, Odisha Page 31 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
Das4.2
Data Collection at substation via RS 485/ RS 232 data converters
The software at substation will have the ability to perform remote data acquisition from Meters using RS 485/ RS 232 port converters
Data Collection at substation via Data Concentrator Unit.
The software at substation will have the ability to perform remote data acquisition from substation meters via Data Concentrator Unit.
Das4.4 Typical list of data acquisition from the Meters
A typical list of data acquisition from the Meters has been mentioned below: Acquire real time instantaneous data like voltage, current frequency, power factor, active power, reactive power etc. at the specified regular intervals (15 minutes- 30 minutes as per meter specification) for online local monitoring substation level. Acquire stored historical values of data at regular interval with power consumptions, accumulated energy, accumulated power, maximum demand and other parameters. Acquire real values of specified parameters on demand. Synchronize date and time of all meters.
Typical list of data acquisition from the Meters
A typical list of data acquisition from the Meters has been mentioned below : Acquire real time instantaneous data like voltage, current frequency, power factor, active power, reactive power etc. at the specified regular intervals ( 15 minutes-30 minutes as per meter specification) for online monitoring anywhere across Utility. Acquire stored historical values of data at regular interval with power consumptions, accumulated energy, accumulated power, maximum demand and other parameters. Acquire real values of specified parameters on demand. Synchronize date and time of all meters.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 32
CESU, Odisha Page 32 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
Das4.9 Mode of data transfer from substation to Sub division office
Normally the data transfer from Substation data logging system to sub division office will be over GSM/GPRS/ EDGE/CDMA/ PSTN/LPR by dialing from either end at some specified interval of time.
Mode of data transfer from substation to Central Data Centre
Normally the data transfer from Substation data logging system to Central Data Centre will be over GPRS/ EDGE/CDMA by Pushing the data from the substation device at some specified interval of time (15-30 minutes).
Das4.10 Facility for back up and restoration of data
Facility for taking backup & restore of data collected at substation shall be provided in software.
Facility for back up and restoration of data
Facility for taking backup & restore of data collected at Data Centre shall be provided in software.
Das5.0 Features of Data logging system at sub division office :-
Features of Data logging system for Central Data Centre :-
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 33
CESU, Odisha Page 33 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
Das5.1 Periodicity of data collection
System shall be capable of collecting data from all the HT consumers at least every one Hour and from all the Distribution Transformers at least once in 24 Hours. The substation data shall also be polled at least once in 24 Hours. The number of HT consumers and number of DTs have been furnished in the enclosed Annexure-A of Section: G6. However, the bidder may visit the area and collect the exact details about the number of HT consumers and number of DTs at site and design and supply the system as per actual availability at site. Further, the system shall be designed and shall have provisions for inclusion of new Consumers and Assets in future and shall provide additional spare capacity to cater 10% per annum growth over and above the actual requirement at site on account of the future provisions.
Periodicity of data collection
System shall be capable of collecting data from all the HT consumers at least every half Hour and from all the Distribution Transformers at least once in 24 Hour. The substation meter data from the substation data loggers shall also be captured at least once in 24 Hours. The number of HT consumers and number of DTs have been furnished in the enclosed Annexure-A of Section: G6. However, the bidder may visit the area and collect the exact details about the number of HT consumers and number of DTs at site and design and supply the system as per actual availability at site. Further, the system shall be designed and shall have provisions for inclusion of new Consumers and Assets in future and shall provide additional spare capacity to cater 10% per annum growth over and above the actual requirement at site on account of the future provisions.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 34
CESU, Odisha Page 34 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
Das5.2 Functionality of Sub division office Data acquisition software
The Data acquisition software at Central Data Centre Sub division office must have the following functions : a) Data Collection: It shall collect data from the remote Data logger systems installed at the substations and store in its local Database. It shall also collect Meter data directly from DTs and HT/select LT consumers through GSM/GPRS/ EDGE/CDMA/PSTN/LPR Modems and store in its local database. b) Data Processing: It shall use data from the database to create reports, charts and spread sheets. c) Data transfer to data center : It shall be able to transmit entire incremental meter data to data center and shall reside in the Metering module for further aggregation, analysis and MIS generation as per request from various utility offices d) Messaging : Via GSM/GPRS/EDGE/CDMA e) Program Generator : It shall have editors and configuration
Mode of Data Transfer from DTs/HT/Select LT consumers
The Data acquisition software at central data centre must have the following functions : a) Data Collection: It shall collect data from the remote Data logger systems installed at the substations and store in its local Database. It shall also collect Meter data directly from DTs and HT consumers through GPRS/EDGE/CDMA Modems and store in the database. b) Data Processing: It shall use data from the database to create reports, charts and spread sheets. c) Data transfer to data center : All the modems should be able to transmit the meter data to central data centre which shall reside in the Metering module for further aggregation, analysis and MIS generation as per request from various utility offices d) Messaging : Via GPRS/EDGE/CDMA e) Program Generator : It shall have editors and configuration software. f) Facility to communicate with multiple clients simultaneously through multiple communication lines. g) The communication shall be scalable and configurable to various media like CDMA, GPRS and EDGE.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 35
CESU, Odisha Page 35 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
software. f) Facility to communicate with multiple clients simultaneously through multiple communication lines. g) The communication shall be scalable and configurable to various media like PSTN, CDMA, GSM, GPRS, EDGE or LPR Modem etc.
Das5.6 Manual/ automatic mode of data transmission
There should be provision for manually dialing the modems connected to the DT and Consumer meters and feeder meters/data loggers or by configuring the software to collect the data from meters automatically with the help of Scheduler feature provided for auto dialing.
Manual/ automatic mode of data transmission
The modems (remote devices) should automatically push the data at pre configured interval of time. There should be option for changing the frequency of data transfer from the central server. There should also be a provision to get the data on manual request under special circumstances. There should be provision for manually dialing the modems connected to the DT, Consumer meters and feeder meters/data loggers or by configuring the software to collect the data from meters automatically with the help of Scheduler feature provided for auto dialing.
Das5.8 Mode of transfer of Meter data
The data file will be transferred from the sub-stations to sub division office server in one of the following possible methods
Mode of transfer of Meter data
The data will be transferred from various AMR devices/data loggers to the data centre server in one of the
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 36
CESU, Odisha Page 36 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
following possible methods :-
a) Data retrieval by sub division office from sub-station
Data acquisition software at sub division office may dial up the substation software over PSTN/GSM/GPRS/EDGE/ CDMA/Low power radio at some specified intervals and retrieve the data file.
Automatic Data Transfer By default data shall be automatically sent in push mode by the AMR devices/data loggers to the Data Centre at preconfigured time interval.
b) Data transfer from sub-station to sub division office
Substation software may dial up sub division office data logger system over PSTN/ GSM/GPRS/EDGE/CDMA or Low power radio at some specified interval and transfer the data file.
Manual Request for Data
Under special circumstances there should also be a provision to get the data on manual request from AMR devices/data loggers.
Das5.9 Facility for archiving, deletion, backup & restoration of the data
Facility for archiving, deletion and taking backup & restore of entire or part of the data collected at Sub division office shall be provided in Software.
Facility for archiving, deletion, backup & restoration of the data
Facility for archiving, deletion and taking backup & restore of entire or part of the data collected at Central Server shall be provided in Software.
Das6.3 Enabling of data acquisition over any communication media
The software will enable data acquisition over any of the locally and reliably available communication media : GSM/GPRS, EDGE, CDMA, PSTN, Low power radio etc.
Enabling of data acquisition over any communication media
The software will enable data acquisition over any of the locally and reliably available communication media: GPRS, EDGE, and CDMA.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 37
CESU, Odisha Page 37 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
Das6.5 Provision of remote reading & collection in both scheduled batch mode
Remote reading collection will be possible in both scheduled batch mode (automated) as well as in the on-demand (real-time) mode.
Provision of remote reading & collection in both automated and manual mode.
Remote reading collection will be possible in both data push from the field devices in automated as well as in the on-demand (real-time) mode.
Das6.6 Features of scheduled mode of data collection
In the In the scheduled mode of data collection, the software will allow reading cycles to be configured for either individual meters or groups of meters. Appropriate time windows for data collection from different meters based on location/type can be set. The data collection could be at any one of the pre-defined monthly, daily, hourly or quarter-hourly frequencies or at any user-defined frequency greater than 15 minutes.
Features of data collection
Data from remote AMR devices will be acquired automatically. Software will allow reading cycles to be configured for either individual meters or groups of meters. Appropriate time windows for data collection from different meters at pre-configured interval of time to the Data Collection Server at the Data Centre can be set. The data collection could be at any one of the pre-defined daily, hourly or quarter-hourly frequencies or at any user-defined frequency greater than 15 minutes.
Das6.7 Support for both inbound and outbound communication
The software will support both inbound and outbound communication, i.e. data transfer could be initiated by either the remote meter or the central software
Support for both inbound and outbound communication
The software will support both inbound and outbound communication, i.e. data transfer could be initiated by either the remote meter in general or the central software in case of special requirements
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 38
CESU, Odisha Page 38 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
Das6.12 Synchronization of all meters to a common fixed reference
The software will be able to synchronize the date and time of all meters to a common fixed reference. All the raw meter data entering the system via AMR or any external means is time-stamped and stored for audit and further analysis.
Synchronization of all meters to a common fixed reference
The software will be able to synchronize the date and time of all remote devices to a common fixed reference. All the raw meter data entering the system via AMR or any external means is time-stamped and stored for audit and further analysis.
Das 8.1 Supporting of automated rule- based validation
Software will support automated rule-based validation and estimation of raw metered data.
Supporting of automated rule- based validation
Software will support automated rule-based validation and estimation of raw metered data. The system should trigger The validation process automatically as and when the data is received from Meter data collection system built in validation routines: The system should have pre-defined validation rules that can be adjusted by user inputs. System should also have ability to define new validation and estimation rules Detail requirements need to be finalized by ITIA along with utility.
Das 8.6 Provision of meter data estimation routine
The software will have a meter data estimation routine that will be triggered on occurrence of validation failures.
Provision of meter data estimation routine
The software will have a meter data estimation routine that will be triggered on occurrence of validation failures. System should also have facility to define, add and revise estimation methods.
Das11.6 Reports at Sub stations : Reports for Sub stations :
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 39
CESU, Odisha Page 39 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
Das11.7 Reports at Sub Division Office: Reports for Sub Division Office:
Das11.7.1 Provision for comprehensive reporting and MIS facility
Software at Sub division office shall provide comprehensive reporting & MIS facility and it should provide fixed format as well as query based reports in tabular & graphic format as required by user.
Provision for comprehensive reporting and MIS facility
Software for Sub division office shall provide comprehensive reporting & MIS facility and it should provide fixed format as well as query based reports in tabular & graphic format as required by user.
Das11.8 Reports at various Utility offices, such as Division, Circle, Head Quarter etc. :
Reports for various Utility offices, such as Division, Circle, Head Quarter etc. :
Das11.8.1 Reporting facility at various utility offices
Various utility offices, which can interact with Metering/ Billing database at Data center to provide extensive analysis & reporting facility. It shall also have extensive search options and should provide fixed format as well as query based reports in tabular & graphic format as per the requirement of the utility and described in detail at para Das.11.7 above (i.e. Reports at Sub division offices).
Reporting facility at various utility offices
Web based Reporting Software shall be available through web browser to various utility offices, which can interact with Metering/ Billing database at Data center to provide extensive analysis & reporting facility. It shall also have extensive search options and should provide fixed format as well as query based reports in tabular & graphic format as per the requirement of the utility and described in detail at para Das.11.7 above (i.e. Reports at Sub division offices).
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 40
CESU, Odisha Page 40 Release Date: 27th February 2016
Elaborations Regarding MDAS System
Section Original Changes
Functionality Description Functionality Description
Das 13.0 Time synchronization
Time synchronization : The time synchronization shall be possible from the Work Station/ HMI through built-in function. An accuracy of ±1 milli- second within the station is required. However provision is to be made available for time stamping through GPS.
Time synchronization Time synchronization : The time synchronization shall be possible from the Work Station/ HMI through built-in function. An accuracy of ±1 milli-second within the station is required. However provision is to be made available for time stamping through GPS. System should allow configuring the frequency of the synchronisation.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 41
CESU, Odisha Page 41 Release Date: 27th February 2016
Sections in the RFP Document
Section Content
Section I Preface
Section II Instructions to Bidders
Section III Bid Data Sheet
Section IV Eligibility Criteria
Section V Bidding Forms
Section VI Scope of Work
Section VII General Conditions of Contract
Section VIII Special Conditions of Contract
Section IX Contract Forms
Appendix A Mandatory technical specifications
Appendix B Technical specifications
Appendix C Service level agreement
Appendix D Supplier response format
Appendix E Evaluation methodology
Appendix F Geographical and administrative information
Appendix G List of offices for WAN connectivity
Appendix H Review of current IT systems
Appendix I List of manual/business processes to be converted to electronic
form
Appendix J Review of current business processes
Appendix K Website
Appendix L List of goods and related services
Appendix M Estimated manpower requirement
Appendix N Expected implementation schedule
Appendix O Spot Billing Machines Specification
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 42
CESU, Odisha Page 42 Release Date: 27th February 2016
Appendix P Map of CESU of Odisha
Appendix Q Formats for Price Bids
Appendix R Proposed Interface Scheme v2.4
Appendix S CESU Offices Locations for Network Connectivity
Appendix T Additional Clarifications
Appendix U No Deviation Certificate
Appendix V Abbreviations
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 43
CESU, Odisha Page 43 Release Date: 27th February 2016
Section I. Preface
About this Document
The purpose of this document is selection of IT Implementation Agency (ITIA) for the
Restructured Accelerated Power Development and Reforms Programme (R-APDRP) - An
Initiative of Ministry of Power, Govt. of India.
Bidders are advised to study this document carefully. Submission of RFP shall be deemed to
have been done after careful study and examination of this document with full understanding
of its implications. This RFP document is not transferable. This document must be read in its
entirety. Please verify that you have a complete copy.
The Opportunity
Ministry of Power, Govt. of India, has launched the Restructured Accelerated Power
Development and Reforms Programme (R-APDRP) in the XI Five year Plan. Power Finance
Corporation Limited (PFCL) has been designated by GoI as the Nodal Agency for the
programme. The programme spans from data acquisition at distribution level till monitoring of
results of steps taken to provide an IT backbone and strengthening of the Electricity
Distribution system across the Country under the programme. The objective of the programme
is reduction of AT&C losses to 15% in project areas. The program is divided into 2 parts Part-
A and Part-B. Part-A will include projects for establishment of baseline data and IT
applications like Meter Data Acquisition, Meter Reading, Billing, Collections, GIS, MIS,
Energy Audit, New Connection, Disconnection, Customer Care Services, Web self service,
etc. to get verified baseline AT&C losses. Part-B will include distribution strengthening
projects.
The ITIA would supply, install and commission one integrated solution within the broad
framework provided in the SRS (System Requirement Specification) document. SRS
Committee under the guidance of Ministry of Power has finalized a detailed SRS document
which covers all the components of the project including hardware, software, networking; GIS
among others which shall help the utilities improve their performance.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 44
CESU, Odisha Page 44 Release Date: 27th February 2016
The Programme
The size of the programme is to the tune of Rs. 500 billion. The programme consists of Part-A
(to the tune of around Rs. 10,000 crore) covering Information Technology application in the
electricity distribution system and Part B (to the tune of around Rs. 40,000 crore) covering the
System strengthening, Improvement and augmentation of distribution system capacity. Both
parts entail planning of measures to be taken under the programme, implementation of such
measures to be taken and monitoring / evaluation of results / impact of the programme as a
whole and of its various components across the Country. The focus of the programme shall be
on actual, demonstrable performance in terms of loss reduction. Establishment of reliable and
automated systems for sustained collection of accurate base line data, and the adoption of
Information Technology in the areas of energy accounting will be essential for the success of
the R-APDRP.
• The Programme is proposed to be implemented on all India basis covering Towns and
Cities with a population of more than 30,000 (10,000 in case of Special Category States)
as per population data of 2001 Census. In addition, in certain high-load density rural areas
with significant loads, works of separation of agricultural feeders from domestic and
industrial ones, and of High Voltage Distribution System (11kV) will also be taken up.
• Towns / areas for which projects have been sanctioned in X Plan APDRP shall be
considered for the XI Plan only after either completion or short closure of the earlier
sanctioned projects. Projects under the scheme shall be taken up in Two Parts. Part-A
shall include the projects for establishment of baseline data and IT applications for energy
accounting/auditing & IT based consumer service centers. Part-B shall include regular
distribution strengthening projects. The activities to be covered under each part are as
follows:
Part – A: Preparation of Base-line Data System for the project area covering Consumer
Indexing, GIS Mapping, Automatic Metering (AMR) on Distribution Transformers and
Feeders, and Automatic Data Logging for all Distribution Transformers & Feeders and
SCADA / DMS system for big cities only. It would include Asset Mapping of the entire
distribution network at and below the 11kV transformers and include the Distribution
Transformers and Feeders, Low Tension lines, poles and other distribution network
equipment. It will also include adoption of IT applications for meter reading, billing &
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 45
CESU, Odisha Page 45 Release Date: 27th February 2016
collection; energy accounting & auditing; MIS; redressal of consumer grievances and
establishment of IT enabled consumer service centers etc.
Part – B: Renovation, modernization and strengthening of 11 kV level Substations,
Transformers/Transformer Centers, Re-conductoring of lines at 11kV level and below,
Load Bifurcation, Feeder segregation, Load Balancing, Aerial Bunched Conductoring
in thickly populated areas, HVDS, installation of capacitor banks and mobile service
centers etc. In exceptional cases, where sub-transmission system is weak,
strengthening at 33 kV or 66 kV levels may also be considered.
Calendar of Events
Event / Particulars Date and Time Location
Download of RFP / Bid Document
27th February 2016
from 13:00 Hrs onwards
www.cesuodisha.com / www.cescoorissa.com
Date of Pre-Bid Conference 10
th March 2016
from 12:00 Hrs to 14:00 Hrs.
Conference Hall, Central Electricity Supply Utility of Odisha, 3
rd
Floor, IDCO Tower, Janpath, Bhubaneswar – 751022 Odisha
Tender Participation Cost
Indian Rupees 25,000/- (Twenty Five Thousand) +
VAT 5%
Rs. 25,000/- (Twenty Five Thousand) Plus VAT 5%, by Demand Draft payable to CESU of Odisha, Bhubaneswar, Odisha. The interested empanelled SIs may download the tender document from website (www.cesuodisha.com / www.cescoorissa.com) and the cost may be submitted along with the bid.
Bid Security (EMD) Indian Rupees 1.00
Crore
Bid Security (EMD) to be submitted as Bank Guarantee in the prescribed format for a period of 150 days from the date of Bid Opening.
Final Bid Submission 28
th March 2016
(Up to 13:00 Hrs)
IT Center, Central Electricity Supply Utility of Odisha, 8
th Floor, IDCO Towers, Janpath,
Bhubaneswar -751022 Odisha
Technical Bid Opening 28
th March 2016 15:00 Hrs
Conference Hall, Central Electricity Supply Utility of Odisha, 3
rd
Floor, IDCO Tower, Janpath, Bhubaneswar – 751022 Odisha
Financial Bid Opening Will be Notified Later
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 46
CESU, Odisha Page 46 Release Date: 27th February 2016
Section II. Instructions to Bidders
Table of Clauses
A. GENERAL ................................................................................................................................... 48
1. SCOPE OF BID ............................................................................................................................................ 48
2. SOURCE OF FUNDS .................................................................................................................................... 48
3. CORRUPT PRACTICES ................................................................................................................................ 48
4. ELIGIBLE BIDDERS ..................................................................................................................................... 50
5. ELIGIBLE GOODS AND RELATED SERVICES............................................................................................... 53
B. CONTENTS OF BIDDING DOCUMENT ....................................................................................... 54
6. SECTIONS OF THE BIDDING DOCUMENT ................................................................................................... 54
7. CLARIFICATION OF BIDDING DOCUMENT ................................................................................................... 54
8. AMENDMENT OF BIDDING DOCUMENT ....................................................................................................... 55
C. PREPARATION OF BIDS ............................................................................................................ 56
9. COST OF BIDDING ...................................................................................................................................... 56
10. LANGUAGE OF BID ................................................................................................................................. 56
11. DOCUMENTS COMPRISING THE BID ...................................................................................................... 56
12. BID SUBMISSION SHEETS AND PRICE SCHEDULES .............................................................................. 58
13. ALTERNATIVE BIDS ................................................................................................................................ 59
14. BID PRICES AND DISCOUNTS ................................................................................................................ 59
15. CURRENCIES OF BID .............................................................................................................................. 60
16. DOCUMENTS ESTABLISHING THE ELIGIBILITY OF THE BIDDER ............................................................. 60
17. DOCUMENTS ESTABLISHING THE CONFORMITY OF THE GOODS AND RELATED SERVICES TO THE
BIDDING DOCUMENT ........................................................................................................................................... 60
18. DOCUMENTS ESTABLISHING THE QUALIFICATIONS OF THE BIDDER ..................................................... 60
19. PERIOD OF VALIDITY OF BIDS ................................................................................................................ 61
20. BID SECURITY ........................................................................................................................................ 61
21. FORMAT AND SIGNING OF BID ............................................................................................................... 62
D. SUBMISSION AND OPENING OF BIDS ...................................................................................... 63
22. SEALING AND MARKING OF BIDS ........................................................................................................... 63
23. DEADLINE FOR SUBMISSION OF BIDS .................................................................................................... 64
24. LATE BIDS .............................................................................................................................................. 64
25. WITHDRAWAL, SUBSTITUTION, AND MODIFICATION OF BIDS ............................................................... 65
26. BID OPENING ......................................................................................................................................... 65
E. EVALUATION AND COMPARISON OF BIDS ............................................................................. 68
27. CONFIDENTIALITY .................................................................................................................................. 68
28. CLARIFICATION OF BIDS ........................................................................................................................ 69
29. RESPONSIVENESS OF TECHNICAL PROPOSAL ..................................................................................... 69
30. NON CONFORMITES, ERRORS, AND OMISSIONS .................................................................................. 70
31. PRELIMINARY EXAMINATION OF BIDS ................................................................................................... 71
32. EXAMINATION OF TERMS AND CONDITIONS; TECHNICAL EVALUATION ................................................ 72
33. MARGIN OF PREFERENCE ..................................................................................................................... 73
34. EVALUATION OF BIDS ............................................................................................................................ 73
35. COMPARISON OF BIDS ........................................................................................................................... 74
36. POST-QUALIFICATION OF THE BIDDER .................................................................................................. 74
37. PURCHASER’S RIGHT TO ACCEPT ANY BID, AND TO REJECT ANY OR ALL BIDS ................................. 74
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 47
CESU, Odisha Page 47 Release Date: 27th February 2016
F. AWARD OF CONTRACT ............................................................................................................. 74
38. AWARD CRITERIA ................................................................................................................................... 75
39. PURCHASER’S RIGHT TO VARY QUANTITIES AT TIME OF AWARD ........................................................ 75
40. NOTIFICATION OF AWARD ...................................................................................................................... 75
41. SIGNING OF CONTRACT ......................................................................................................................... 75
42. PERFORMANCE SECURITY ..................................................................................................................... 76
43. LOCAL CONDITIONS ............................................................................................................................... 76
G. INTERPRETATION ...................................................................................................................... 76
44. INTERPRETATION OF THE SRS AND THE RFP DOCUMENT ................................................................... 76
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 48
CESU, Odisha Page 48 Release Date: 27th February 2016
A. General
1. Scope of Bid 1.1 In support of the Invitation for Bids indicated in the Bid Data
Sheet (BDS), the Purchaser, as indicated in the BDS, issues
this Bidding Document for the supply of Goods and Related
Services incidental thereto as specified in the Scope of Work
at Section VI. The name and identification number of the
International competitive Bidding (ICB) are provided in the
BDS.
2. Source of
Funds
2.1 The Purchaser has received sanction from Nodal Agency
(Power Finance Corporation Limited (PFC) under the aegis of
Ministry of Power (MoP), Government of India (GoI)) under
Part-A of R-APDRP towards the implementation cost of the
project named in the BDS (hereinafter called “funds”). The GoI
has agreed to convert the sanctioned loan into grant after
successful completion of project and meeting the guidelines of
R-APDRP. The Purchaser intends to apply a portion of funds
to eligible payments under the contract for which this bidding
document is issued.
2.2 Payments made under the Contract shall be in accordance
with the terms and conditions of the financing agreement
between the Purchaser and the Nodal Agency (hereinafter
called the Loan Agreement), and will be subject in all respects
to the terms and conditions of that Agreement. No party other
than the Purchaser shall derive any rights from the Loan
Agreement or have any claim to the funds.
3. Corrupt
Practices
3.1 Purchaser requires bidders to observe the highest standard of
ethics during the procurement and execution of such
contracts.
3.2 The following definitions apply:
o “Corrupt practice” means the offering, giving receiving, or
soliciting, directly or indirectly, of anything of value to influence
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 49
CESU, Odisha Page 49 Release Date: 27th February 2016
the action of any party in the procurement process or the
execution of a contract;
o “Fraudulent practice” means a misrepresentation or omission
of facts in order to influence a procurement process or the
execution of a contract;
o “collusive practices” means a scheme or arrangement
between two or more bidders, with or without the knowledge
of the Purchaser, designed to influence the action of any party
in a procurement process or the execution of a contract;
o “coercive practices” means harming or threatening to harm,
directly or indirectly, persons, or their property to influence
their participation in a procurement process, or affect the
execution of a contract;
o Purchaser will reject a proposal for the award of Contract if it
determines that the bidder recommended for award has,
directly or through an agent, engaged in corrupt, fraudulent,
collusive, or coercive practices in competing for the Contract
o the Nodal Agency will declare a firm ineligible, either
indefinitely or for a stated period of time, for awarding a R-
APDRP funded contract if it at any time determines that the
firm has engaged in corrupt of fraudulent practices in
competing for, or in executing, a RAPDRP funded contract.
3.2 In continuance of ITB clause 3.1 above, the Nodal Agency will
cancel the portion of the fund allocated to a contract for goods,
works or services if it at any time determines that corrupt or
fraudulent practices were engaged in by representatives of the
purchaser or a beneficiary of the fund, during the procurement
or the execution of that contract, without the Purchaser having
taken timely and appropriate remedial action satisfactory to
the Nodal Agency.
3.3 Any communication between the bidder and the purchaser
related to matters of alleged fraud or corruption must be made
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 50
CESU, Odisha Page 50 Release Date: 27th February 2016
in writing.
By signing the contract, the bidder shall represent that it is
either the owner of the Intellectual Property Rights (IPR) in the
hardware, software or materials offered, or that it has proper
authorization and/or license to offer them from the owner of
such rights. For the purpose of this clause, IPR shall be
defined in the GCC Clause 17. Willful misrepresentation of
these facts shall be considered a fraudulent practice subject to
the provisions of Clauses 3.1 to 3.3 above, without prejudice
to other remedies that the Purchaser may take.
Furthermore, Bidders shall also note the provision stated in Sub-
Clause 2 and Sub-Clause 33.1.1 (ii) of the General Conditions of
Contract.
4. Eligible
Bidders
4.1 Bidders empanelled as System Integrator (SI) by Nodal
Agency shall be eligible to bid
(a) SI shall have flexibility to subcontract Meter Data
Acquisition Solution Provider (MDASP) services, as per
requirement. In case SI decides to subcontract Meter
Data Acquisition Solution Provider services, the Meter
Data Acquisition Solution Provider shall only be selected
from the empanelled list of MDASPs. The SI shall
necessarily subcontract other ITIA roles of GIS Solution
Provider (GSP) and Network Solution Provider (NSP)
from the empanelled list of GSP and MDASP.
(b) The SI (Lead member in case of a consortium for SI
Role) shall have the authority to conduct all businesses
for and on behalf of any and all the parties during the
bidding process and, in the event the SI is awarded the
Contract, during contract execution.
(c) The SI (Lead member in case of a consortium for SI
Role) shall be wholly responsible for execution of the
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 51
CESU, Odisha Page 51 Release Date: 27th February 2016
contract.
(d) In case of non-performance (slippage in milestones,
scope & quality of work, discipline, etc. as assessed by
utility) and/or bankruptcy of any of the subcontracted ITIA
roles (GSP, NSP, MDASP), the SI (Lead member in case
of a consortium for SI Role) shall take necessary
remedial action through addition/change of subcontractor
for the concerned ITIA role. The addition/change of
subcontractor for concerned ITIA role (GSP, NSP,
MDASP) shall be with necessary prior approval of the
utility and shall be at no additional cost to the project cost
already quoted at the time of bidding for the project. The
addition/change of subcontractor for concerned ITIA role
(GSP, NSP, MDASP) shall only be from the list of
empanelled members for ITIA roles
(e) In case of exceptional circumstance of continued non-
performance, even subsequent to exercising of remedies
provided under clause 4.1.d above, as assessed and
reported by the utility, the empanelment is liable to be
cancelled by the Nodal Agency.
4.2 Bidder or the Lead Member in case of a Consortium shall not
have a conflict of interest with one or more parties in this bidding
process. Participation by Bidder(s) with a conflict of interest
situation will result in the disqualification of all Bids in which it is
involved. Purchaser considers a conflict of interest to be a
situation in which a party has interests that could improperly
influence that party’s performance of official duties or
responsibilities, contractual obligations, or compliance with
applicable laws and regulations, and that such conflict of interest
may contribute to or constitute a prohibited corrupt practice. A
Bidder may be considered to be in a conflict of interest with one
or more parties in this bidding process if, including but not
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 52
CESU, Odisha Page 52 Release Date: 27th February 2016
limited to:
(a) receive or have received any direct or indirect subsidy
from any of them; or
(b) have the same legal representative for purposes of this
Bid; or
(c) have a relationship with each other, directly or through
common third parties, that puts them in a position to
have access to information about or influence on the Bid
of another Bidder, or influence the decisions of the
Purchaser regarding this bidding process; or
(d) a Bidder (the SI/Lead member in case of a consortium
for SI Role) participates in more than one bid in this
bidding process. Participation by a Bidder or Lead
Member in more than one Bid will result in the
disqualification of all Bids in which it is involved.
However, this does not limit the inclusion of the same
product (commercially available hardware, software or
network product manufactured or produced by the firm),
as well as purely incidental services such as installation,
configuration, routine training and ongoing
maintenance/support, in more than one bid; or
(e) a Bidder or any of its sub-contractors or consortium
member(s) participated as a consultant in the preparation
of the design or technical specifications of the goods and
services that are the subject of the bid.
(f) if the SI (single bidder or consortium) or any of its sub-
contractors is/are part of IT Consultant appointed by that
utility
(g) if the SI or any of its sub-contractors get associated as
Consultant / Advisor / Third party independent evaluating
agency with any of the agencies taking part in the bid
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 53
CESU, Odisha Page 53 Release Date: 27th February 2016
process of the concerned utility under R-APDRP
(h) For any given project area, the IT consultant and the IT
implementation agency cannot be the same. An IT
Consultant and IT implementation agency (SI and/or its
subcontractors if any) agency may be considered to be in
a conflict of interest with one or more parties in this
process if they have controlling shareholders in common;
(i) Participation by Bidder(s) with a conflict of interest
situation will result in the disqualification. Furthermore,
the Nodal Agency reserves the right to debar/bar bidders
from all other process of empanelment including
cancellation of existing panels under R-APDRP.
Except SI, empanelled NSP, GSP and MDASP may provide
sub-contractual services to more than one bidder for the same
bid.
4.3 Government-owned enterprises who have been empanelled
shall be eligible
4.4 Bidders shall provide such evidence of their continued eligibility
satisfactory to the Purchaser, as the Purchaser shall reasonably
request.
5. Eligible
Goods and
Related
Services
5.1 For the purpose of this Clause, the term “Goods” includes
hardware, software, networking equipments and cables; and
“Related services” includes services such as insurance,
transportation, associated documentation, installation,
customization, integration, field survey, testing and
commissioning, training, technical support, maintenance, repair
and other necessary services to be provided by the selected
bidder and necessary for successful implementation of the
project as specified in the contract.
5.2 In case Bidder that does not manufacture or produce the Goods
it offers to supply shall submit the Manufacturer’s Authorization
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 54
CESU, Odisha Page 54 Release Date: 27th February 2016
using the form included in Section V, Bidding Forms to
demonstrate that it has been duly authorized by the
manufacturer or producer of the Goods to supply these Goods.
B. Contents of Bidding Document
6. Sections of
the Bidding
Document
6.1 The Bidding Document consists of the sections as indicated
below and should be read in conjunction with any Addenda
issued in accordance with ITB Clause 8.
• Section I. Preface
• Section II. Instructions to Bidders (ITB)
• Section III. Bid Data Sheet (BDS)
• Section IV. Eligibility Criteria
• Section V. Bidding Forms
• Section VI. Scope of Work
• Section VII. General Conditions of Contract (GCC)
• Section VIII. Special Conditions of Contract (SCC)
• Section IX. Contract Forms
• Appendix A to U
6.2 The Invitation for Bids issued by the Purchaser is a part of the
Bidding Document.
6.3 The Purchaser is not responsible for the completeness of the
Bidding Document and its addenda, if they were not obtained
directly from the Purchaser.
6.4 The Bidder is expected to examine all instructions, forms, terms,
and specifications in the Bidding Document. Failure to furnish all
information or documentation required by the Bidding Document
may result in the rejection of the Bid.
7. Clarification 7.1 A prospective Bidder requiring any clarification of the Bidding
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 55
CESU, Odisha Page 55 Release Date: 27th February 2016
of Bidding
Document
Document shall contact the Purchaser in writing at the
Purchaser’s address indicated in the BDS. The Purchaser shall
forward copies of its response to all Bidders who have acquired
the Bidding Document directly from it, including a description of
the inquiry but without identifying its source. Should the
Purchaser deem it necessary to amend the Bidding Document
as a result of a clarification, it shall do so following the
procedure under ITB Clause 8 and Sub-Clause 23.2.
7.2 The Purchaser will organize a pre-bid conference at the time
and place indicated in BDS. The purpose of the conference will
be to clarify issues and answer queries that the bidders might
have. Bidders are requested to submit the queries in writing to
reach the purchaser not later than 5 days before the conference.
Queries and responses shall be communicated in accordance
with ITB Clause 7.1. Any modifications to the Bidding document
listed in ITB Clause 6.1 which may become necessary as a
result of pre-bid conference shall be made by the Purchaser
exclusively by issuing Addendum and not through the
clarifications of the pre-bid conference.
8. Amendment
of Bidding
Document
8.1 At any time prior to the deadline for submission of the Bids or
the award of the contract, the Purchaser may amend the
Bidding Document by issuing addenda.
8.2 The Purchaser, at its discretion for any reason whether at its
own initiative or in response to a clarification requested by a
bidder may add, modify or remove any element of the Goods
(including hardware, software, networking, etc) or any
component of Related Service entirely or any part thereof from
the bid document till the time of award of contract. All bidders
will be notified of any such change.
8.3 In order to provide prospective Bidders reasonable time in which
to take the amendment into account in preparing their bids, the
Purchaser may, at its discretion, extend the last date for the
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 56
CESU, Odisha Page 56 Release Date: 27th February 2016
receipt of Bids.
8.4 Any addendum issued shall be part of the Bidding Document
and shall be communicated in writing to all who have obtained
the Bidding Document directly from the Purchaser.
8.5 To give prospective Bidders reasonable time in which to take an
addendum into account in preparing their Bids, the Purchaser
may, at its discretion, extend the deadline for the submission of
the Bids, pursuant to ITB Sub-Clause 23.2.
C. Preparation of Bids
9. Cost of
Bidding
9.1 The Bidder shall bear all costs associated with the preparation
and submission of its Bid, and the Purchaser shall not be
responsible or liable for those costs, regardless of the conduct
or outcome of the bidding process.
10. Language of
Bid
10.1 The Bid, as well as all correspondence and documents relating
to the Bid exchanged by the Bidder and the Purchaser, shall be
written in the English. Supporting documents and printed
literature that are part of the Bid may be in another language
provided they are accompanied by an accurate translation of the
relevant passages in English, in which case, for purposes of
interpretation of the Bid, such translation shall govern.
11. Documents
Comprising
the Bid
11.1 The Bid shall comprise two envelopes submitted simultaneously,
one containing the Technical Proposal and the other the Price
Proposal, enclosed together in an outer single envelope.
11.2 Initially, only the Technical Proposals opened at the address,
date and time specified in ITB Sub-Clause 26.1. The Price
Proposals remain sealed and held in custody by the Purchaser.
The Technical Proposals shall be evaluated by the Purchaser as
per Evaluation Methodology mentioned in Appendix-E. No
amendments or changes to the Technical Proposals are
permitted. Bids with Technical Proposals which do not conform
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 57
CESU, Odisha Page 57 Release Date: 27th February 2016
to the mandatory requirements (as specified in Appendix-A) will
be termed as non-responsive and will not be evaluated further.
11.3 Price Proposals of technically responsive Bids shall be opened
in public at the date and time to be advised by the Purchaser.
The Price Proposals shall be evaluated as per Evaluation
Methodology mentioned in Appendix-E.
11.4 Contract shall be awarded to the Bidder whose Proposal
(Technical and Financial) obtains the maximum score
11.5 The Technical Proposal shall contain the following:
(a) Technical Proposal Submission Sheet;
(b) Bid Security, in accordance with ITB Clause 20;
(c) written confirmation authorizing the signatory of the Bid
to commit the Bidder, in accordance with ITB Clause 21;
(d) documentary evidence in accordance with ITB Clause 16
establishing the Bidder’s eligibility to bid;
(e) documentary evidence in accordance with ITB Clauses
17 and 29, that the Goods and Related Services conform
to the Bidding Document;
(f) documentary evidence in accordance with ITB Clause 18
establishing the Bidder’s qualifications to perform the
contract if its Bid is accepted; and
(g) any other document required in the BDS.
11.6 The Price Proposal shall contain the following:
(a) Price Proposal Submission Sheet and the applicable
Price Schedules, in accordance with ITB Clauses 12, 14,
and 15;
(b) any other document required in the BDS.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 58
CESU, Odisha Page 58 Release Date: 27th February 2016
12. Bid
Submission
Sheets and
Price
Schedules
12.1 The Bidder shall submit the Technical Proposal and the Price
Proposal using the appropriate Submission Sheets provided in
Section V, Bidding Forms and Supplier response format,
Appendix D. These forms must be completed without any
alterations to their format, and no substitutes shall be accepted.
All blank spaces shall be filled in with the information requested.
12.2 The Bidder shall submit, as part of the Price Proposal, the Price
Schedules for Goods and Related Services, using the forms
furnished in Section V, Bidding Forms and Supplier response
format, Appendix D.
12.3 The Bidders should take note of following points while submitting
the Price Proposal:-
(a) Price Proposal should clearly indicate the price to be
charged without any qualifications whatsoever and should
include all taxes (sales, service, etc.), duties (excise &
customs, etc), octroi, fees, levies, works contract tax, Entry
tax and other charges as may be applicable, to be paid pre-
or post-delivery or to be deducted by the purchaser at
source, in relation to the Goods and Related Services. Such
taxes, duties, cess, charges etc, if not explicitly mentioned in
the Price bid tables in Appendix D.3, but applicable under
law, should be included in the Quote under “Any other
levies” column.
(b) The Purchaser will provide Central sales tax Form C,
whenever applicable.
(c) The Bidder will provide Tax rates assumed for the
calculation at the time of proposal for each item in notes to
respective table in Appendix D.3.
(d) Please refer to GCC Clause [13.2] and the SCC for Price
adjustments due to change in Tax rates (including local
taxes), duties, levies, cess, charges etc.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 59
CESU, Odisha Page 59 Release Date: 27th February 2016
13. Alternative
Bids
13.1 Alternative (alternate technology/architecture/design/functionality
or proposals with multiple options) bids shall be rejected.
14. Bid Prices
and
Discounts
14.1 The prices quoted by the Bidder in the Price Proposal
Submission Sheet and in the Price Proposal shall conform to the
requirements specified below.
14.2 All items in the Appendix L must be listed and priced separately
in the Price Schedules. If an item listed in Price Schedule is not
priced, their prices shall be assumed to be included by the
bidder in the prices of other items.
14.3 If an item is not listed in the Price Schedule, it shall be assumed
not to be included in the Bid. In such event, if the bid is
otherwise substantially responsive, Bid Price shall be adjusted
during evaluation of Price Proposals, for comparison purposes
only, to reflect the price of the missing or non-conforming item or
component. The price of the missing or non-conforming item or
component for this purpose shall be the highest of the prices
quoted by the other bidders for such missing item or component.
14.4 The terms EXW, CIF, CIP, and other similar terms shall be
governed by the rules prescribed in the current edition of
Incoterms, published by The International Chamber of
Commerce, at the date of the Invitation for Bids or as specified
in the BDS.
14.5 Prices quoted by the Bidder must be firm and final and shall
remain constant throughout the period of the contract and shall
not be subject to any upward modifications, except as specified
in the GCC Clause 14.2
14.6 The bidders are advised not to indicate any separate discount.
Discount, if any, should be merged with the quoted prices.
Discount of any type, indicated separately, will not be taken into
account for evaluation purpose. However, in the event of such
an offer, without considering the separate discount, is found to
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 60
CESU, Odisha Page 60 Release Date: 27th February 2016
be the lowest, the Purchaser shall avail such discount at the
time of award of contract.
15. Currencies of
Bid
15.1 Bidders may express their bid price in Indian Rupees only.
16. Documents
Establishing
the Eligibility
of the Bidder
16.1 To establish their eligibility in accordance with ITB Clause 4,
Bidders shall:
(a) complete the eligibility declarations in the Bid Submission
Sheet, included in Section V, Bidding Forms
17. Documents
Establishing
the
Conformity of
the Goods
and Related
Services to
the Bidding
Document
17.1 To establish the conformity of the Goods and Related Services
to the Bidding Document, the Bidder shall furnish as part of its
Technical Proposal the documentary evidence against Goods
and related Services provided in Appendix L.
17.2 The documentary evidence may be in the form of literature,
drawings or data, and shall consist of a detailed description of
the essential technical and performance characteristics of the
Goods and Related Services, demonstrating substantial
responsiveness of the Goods and Related Services to those
requirements, and if applicable, a statement of deviations and
exceptions to the provisions of Appendix D;
17.3 Standards for workmanship, process, material, and equipment,
as well as references to brand names or catalogue numbers
specified by the Purchaser in the Scope of Work, are intended
to be descriptive only and not restrictive. The Bidder may offer
other standards of quality, brand names, and/or catalogue
numbers, provided that it demonstrates, to the Purchaser’s
satisfaction, that the substitutions ensure substantial
equivalence or are superior to those specified in the Scope of
Work
18. Documents
Establishing
the
18.1 To establish its qualifications to perform the Contract, the Bidder
shall submit as part of its Technical Proposal the evidence
indicated for each qualification criteria specified in Section IV,
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 61
CESU, Odisha Page 61 Release Date: 27th February 2016
Qualifications
of the Bidder
Eligibility Criteria. However, only those bidders which have been
empanelled by Nodal Agency shall be eligible to bid.
19. Period of
Validity of
Bids
19.1 Bids shall remain valid for the period of 90 days after the bid
submission deadline date prescribed by the Purchaser. A Bid
valid for a shorter period shall be rejected by the Purchaser as
non responsive.
19.2 In exceptional circumstances, prior to the expiration of the bid
validity period, the Purchaser may request Bidders to extend the
period of validity of their Bids. The request and the responses
shall be made in writing. The Bid Security furnished in
accordance with ITB Clause 20, it shall also be extended for a
corresponding period. A Bidder may refuse the request without
forfeiting its Bid Security. A Bidder granting the request shall not
be required or permitted to modify its Bid.
20. Bid Security 20.1 The Bidder shall furnish as part of its Technical Proposal, a Bid
Security in original form and in the amount and currency
specified in the BDS
20.2 The Bid Security shall be in the form of a bank guarantee from a
Scheduled bank as notified by Reserve Bank of India. In case of
a bank guarantee, the Bid Security shall be submitted using the
Bid Security Form included in the Bidding Forms at Section V.
The form must include the complete name of the Bidder. The
Bid Security shall be valid for sixty (60) days beyond the end of
the validity period of the bid. This shall also apply if the period
for bid validity is extended
20.3 Any Bid not accompanied by a substantially responsive Bid
Security in accordance with ITB Sub-Clause 20.2, shall be
rejected by the Purchaser as non responsive.
20.4 The Bid Security of unsuccessful Bidders shall be returned as
promptly as possible upon the signing of the Contract with the
successful Bidder pursuant to ITB Clause 41 and 42
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 62
CESU, Odisha Page 62 Release Date: 27th February 2016
20.5 The Bid Security of the successful Bidder shall be returned as
promptly as possible once the successful Bidder has furnished
the required Performance Security and signed the Contract.
20.6 The Bid Security may be forfeited:
(a) if a Bidder withdraws its Bid during the period of bid
validity as specified in ITB Clause 19.1, except as
provided in ITB Sub-Clause 19.2 or 25 ; or
(b) if the successful Bidder fails to :
o sign the Contract in accordance with ITB Clause 41; or
o furnish a Performance Security in accordance with ITB Clause
42; or
o accept the correction of its Bid Price pursuant to ITB Sub-
Clause 30.5
o If the bidder is found to have submitted false particulars / fake
documents; or
o If the IT Implementation Agency (SI and its sub-contractors)
refuses to execute the job at his agreed scope/quoted rates
after the utilities issue the letter of intent (LoI)
o incidents of manipulation of rates by cartelization
20.7 The Bid Security must be in the name of the system integrator
(Lead Member in case of consortium for system integrator role)
21. Format and
Signing of Bid
21.1 The Bidder shall prepare one original of the Technical Proposal
and one original of the Price Proposal as described in ITB
Clause 11 and clearly mark each “ORIGINAL - TECHNICAL
PROPOSAL” and “ORIGINAL - PRICE PROPOSAL”. In
addition, the Bidder shall submit 1 (One) copy of the Technical
Proposal and the Price Proposal, and clearly mark them “COPY
- TECHNICAL PROPOSAL”. And five soft copies in separate
compact discs(CD)/DVD. In the event of any discrepancy
between the original and the copies, the original shall prevail.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 63
CESU, Odisha Page 63 Release Date: 27th February 2016
21.2 The original and all copies of the Bid shall be typed or written in
indelible ink and shall be signed by a person duly authorized to
sign on behalf of the Bidder. This authorization shall consist of
a written confirmation as specified in the BDS and shall be
attached to the Bid. The name and position held by each person
signing the authorization must be typed or printed below the
signature. All pages of the Bid, except for un-amended printed
literature, shall be signed or initialled by the person signing the
Bid. Response Formats duly filled along with supporting
documents shall be page numbered and stitched, book bound
as one volume. Each page of the bid (along with the supporting
documents including CVs) should be signed by the authorised
signatory. Spiral/Spico bound documents with end sealed may
also be accepted. The documents submitted in any other way is
liable to be rejected.
21.3 Any interlineations, erasures, or overwriting shall be valid only if
they are signed or initialled by the person signing the Bid.
D. Submission and Opening of Bids
22. Sealing and
Marking of
Bids
22.1 The Bidder shall enclose the original of the Technical Proposal,
the original of the Price Proposal, and one copy of the
Technical Proposal and one copy of the Price Proposal, , in
separate sealed envelopes, duly marking the envelopes as
“ORIGINAL - TECHNICAL PROPOSAL”, “ORIGINAL - PRICE
PROPOSAL” and “COPY - TECHNICAL PROPOSAL” and
“COPY - PRICE PROPOSAL”, as appropriate. These
envelopes containing the original and the copies shall then be
enclosed in one single envelope.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 64
CESU, Odisha Page 64 Release Date: 27th February 2016
22.2 The inner and outer envelopes shall:
(a) bear the name and address of the Bidder;
(b) be addressed to the Purchaser in accordance with ITB
Sub-Clause 23.1; and
(c) bear the specific identification of this bidding process
indicated in the BDS.
22.3 The outer envelopes and the inner envelopes containing the
Technical Proposals shall bear a warning not to open before the
time and date for the opening of Technical Proposals, in
accordance with ITB Sub-Clause 26.1.
22.4 The inner envelopes containing the Price Proposals shall bear a
warning not to open until advised by the Purchaser in
accordance with ITB Sub-Clause 26.2.
22.5 If all envelopes are not sealed and marked as required, the
Purchaser will assume no responsibility for the misplacement or
premature opening and resultant disqualification of the bid.
23. Deadline for
Submission
of Bids
23.1 Bids must be received by the Purchaser no later than the date
and time, and at the address indicated in the BDS.
23.2 The Purchaser may, at its discretion, extend the deadline for the
submission of Bids by amending the Bidding Document in
accordance with ITB Clause 8, in which case all rights and
obligations of the Purchaser and Bidders previously subject to
the deadline shall thereafter be subject to the deadline as
extended.
24. Late Bids 24.1 The Purchaser shall not consider any Bid that arrives after the
deadline for submission of Bids, in accordance with ITB Clause
23. Any Bid received by the Purchaser after the deadline for
submission of Bids shall be declared late, rejected, and returned
unopened to the Bidder.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 65
CESU, Odisha Page 65 Release Date: 27th February 2016
25. Withdrawal,
Substitution,
and
Modification
of Bids
25.1 A Bidder may withdraw, substitute, or modify its Bid after it has
been submitted by sending a written Notice, duly signed by an
authorized representative, and shall include a copy of the
authorization in accordance with ITB Sub-Clause 21.2. The
corresponding substitution or modification of the bid must
accompany the respective written notice. All Notices must be:
(a) submitted in accordance with ITB Clauses 21 and 22
(except that Withdrawal Notices do not require copies),
and in addition, the respective inner and outer envelopes
shall be clearly marked “Withdrawal,” “Substitution,”
“Modification”; and
(b) received by the Purchaser prior to the deadline
prescribed for submission of bids, in accordance with ITB
Clause 23.
25.2 Bids requested to be withdrawn in accordance with ITB Sub-
Clause 25.1 shall be returned unopened to the Bidders.
25.3 No Bid shall be withdrawn, substituted, or modified in the interval
between the deadline for submission of bids and the expiration
of the period of bid validity specified in ITB Clause 19.1 or any
extension thereof.
26. Bid Opening 26.1 The Purchaser shall conduct the opening of Technical Proposals
in the presence of Bidders’ representatives who choose to
attend, at the address, date and time specified in the BDS.
26.2 The Price Proposals will remain unopened and will be held in
custody of the Purchaser until the time of opening of the Price
Proposals. The Purchaser shall advise the responsive bidders in
writing about the date, time, and location of the opening of Price
Proposals.
26.3 First, envelopes marked “WITHDRAWAL” shall be opened, read
out, and recorded, and the envelope containing the
corresponding Bid shall not be opened, but returned to the
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 66
CESU, Odisha Page 66 Release Date: 27th February 2016
Bidder. No Bid shall be withdrawn unless the corresponding
Withdrawal Notice contains a valid authorization to request the
withdrawal and is read out and recorded at bid opening.
26.4 Next, outer envelopes marked “SUBSTITUTION” shall be
opened. The inner envelopes containing the Substitution
Technical Proposal and/or Substitution Price Proposal shall be
exchanged for the corresponding envelopes being substituted,
which are to be returned to the Bidder unopened. Only the
Substitution Technical Proposal, if any, shall be opened, read
out, and recorded. Substitution Price Proposals will remain
unopened in accordance with ITB Sub-Clause 26.2. No
envelope shall be substituted unless the corresponding
Substitution Notice contains a valid authorization to request the
substitution and is read out and recorded at bid opening.
26.5 Next, outer envelopes marked “MODIFICATION” shall be
opened. No Technical Proposal and/or Price Proposal shall be
modified unless the corresponding Modification Notice contains
a valid authorization to request the modification and is read out
and recorded at the opening of Technical Proposals. Only the
Technical Proposals, both Original as well as Modification, are
to be opened, read out, and recorded at the opening. Price
Proposals, both Original as well as Modification, will remain
unopened in accordance with ITB Sub-Clause 26.2.
26.6 All other envelopes holding the Technical Proposals shall be
opened one at a time, and the following read out and recorded :
(a) the name of the Bidder;
(b) whether there is a modification or substitution;
(c) the presence of a Bid Security, if required; and
(d) any other details as the Purchaser may consider
appropriate.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 67
CESU, Odisha Page 67 Release Date: 27th February 2016
Only Technical Proposals read out and recorded at bid
opening shall be considered for evaluation. No Bid shall be
rejected at the opening of Technical Proposals except for late
bids in accordance with ITB Sub-Clause 24.1.
26.7 The Purchaser shall prepare a record of the opening of
Technical Proposals that shall include, as a minimum: the name
of the Bidder and whether there is a withdrawal, substitution,
modification; and the presence or absence of a Bid Security.
The Bidders’ representatives who are present shall be
requested to sign the record. The omission of a Bidder’s
signature on the record shall not invalidate the contents and
effect of the record. A copy of the record shall be distributed to
all Bidders.
26.8 On the basis of the evaluation of the Technical Proposals, the
Purchaser will invite bidders who have submitted responsive
Technical Proposals to attend the opening of the Price
Proposals. The date, time, and location of the opening of Price
Proposals will be advised in writing by the Purchaser. Bidders
shall be given reasonable notice of the opening of Price
Proposals.
26.9 The Purchaser will notify Bidders in writing who have been
rejected on the grounds of being non-responsive to the
requirements of the Bidding Document and return their Price
Proposals unopened, before the opening of the price proposal.
26.10 The Purchaser shall conduct the opening of Price Proposals
of all Bidders who submitted responsive Technical Proposals, in
the presence of Bidders` representatives who choose to attend
at the address, date and time specified by the Purchaser. The
Bidder’s representatives who are present shall be requested to
sign a register evidencing their attendance.
26.11 All envelopes containing Price Proposals shall be opened one
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 68
CESU, Odisha Page 68 Release Date: 27th February 2016
at a time and the following read out and recorded:
(a) the name of the Bidder
(b) whether there is a modification or substitution;
(c) the Bid Prices,; and
(d) any other details as the Purchaser may consider
appropriate.
Only Price Proposals, read out and recorded during the opening
of Price Proposals shall be considered for evaluation. No Bid
shall be rejected at the opening of Price Proposals.
26.12 The Purchaser shall prepare a record of the opening of Price
Proposals that shall include, as a minimum: the name of the
Bidder, the Bid Price. The Bidders’ representatives who are
present shall be requested to sign the record. The omission of a
Bidder’s signature on the record shall not invalidate the contents
and effect of the record. A copy of the record shall be distributed
to all Bidders.
E. Evaluation and Comparison of Bids
27. Confidentialit
y
27.1 Information relating to the examination, evaluation, comparison
and recommendation of contract award, shall not be disclosed
to Bidders or any other persons not officially concerned with
such process.
27.2 Any attempt by a Bidder to influence the Purchaser in the
examination, evaluation, comparison, and post qualification of
the Bids or Contract award decisions may result in the rejection
of its Bid.
27.3 Notwithstanding ITB Sub-Clause 27.2, from the time of opening
the Technical Proposals to the time of Contract award, if any
Bidder wishes to contact the Purchaser on any matter related to
the bidding process, it should do so in writing. If the bidder or
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 69
CESU, Odisha Page 69 Release Date: 27th February 2016
any of his subcontractors/consortium members meet the
Purchaser’s personnel, it will be considered as “coercive
practices”, and may result in rejection of the bid.
28. Clarification
of Bids
28.1 To assist in the examination, evaluation, comparison and post-
qualification of the Bids, the Purchaser may, at its discretion,
ask any Bidder for a clarification of its Bid. Any clarification
submitted by a Bidder that is not in response to a request by the
Purchaser shall not be considered. The Purchaser’s request for
clarification and the response shall be in writing. No change in
the prices or substance of the Bid shall be sought, offered, or
permitted, except to confirm the correction of arithmetic errors
discovered by the Purchaser in the evaluation of the Price
Proposals, in accordance with ITB Clause 30.
29. Responsivene
ss of
Technical
Proposal
29.1 The Purchaser’s determination of the responsiveness of a
Technical Proposal is to be based on the contents of the
Technical Proposal itself.
29.2 A responsive Technical Proposal is one that conforms to all the
mandatory requirements, terms, conditions, and specifications
of the Bidding Document without material deviation, reservation,
or omission. A material deviation, reservation, or omission is
one that:
(a) does not meet all the mandatory requirements (as
specified in Appendix-A)
(b) affects the scope, quality, or performance of the Goods
and Related Services specified in the Contract; or
(c) limits or is inconsistent with the Bidding Document, the
Purchaser’s rights or the Bidder’s obligations under the
Contract; or
(d) if rectified would unfairly affect the competitive position of
other Bidders presenting responsive Technical
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 70
CESU, Odisha Page 70 Release Date: 27th February 2016
Proposals.
29.3 If a Technical Proposal is not responsive to the Bidding
Document, it shall be rejected by the Purchaser and shall not
subsequently be made responsive by the Bidder by correction of
the material deviation, reservation, or omission.
30. Non
conformités,
Errors, and
Omissions
30.1 Provided that a Technical Proposal is responsive, the Purchaser
may waive any non-conformity or omission in the Bid that does
not constitute a material deviation.
30.2 Provided that a Technical Proposal is responsive, the Purchaser
may request that the Bidder submit the necessary information or
documentation, within a reasonable period of time, to rectify
nonmaterial, nonconformities or omissions in the Technical
Proposal related to documentation requirements. Such
omission shall not be related to any aspect of the Price Proposal
of the Bid. Failure of the Bidder to comply with the request may
result in the rejection of its Bid.
30.3 Provided that a Technical Proposal is responsive, the Purchaser
will rectify nonmaterial nonconformities or omissions. To this
effect, the Bid Price shall be adjusted during evaluation of Price
Proposals, for comparison purposes only, to reflect the price of
the missing or non-conforming item or component. The
adjustment shall be made using the method indicated in Section
13.2 of Section VII - GCC.
30.4 Provided that the Technical Proposal is responsive, the
Purchaser will correct arithmetical errors during evaluation of
Price Proposals on the following basis:
(a) if there is a discrepancy between the unit price and the
total price that is obtained by multiplying the unit price
and quantity, the unit price shall prevail and the total
price shall be corrected, unless in the opinion of the
Purchaser there is an obvious misplacement of the
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 71
CESU, Odisha Page 71 Release Date: 27th February 2016
decimal point in the unit price, in which case the total
price as quoted shall govern and the unit price shall be
corrected;
(b) if there is an error in a total corresponding to the addition
or subtraction of subtotals, the subtotals shall prevail and
the total shall be corrected; and
(c) if there is a discrepancy between words and figures, the
amount in words shall prevail. However, where the
amount expressed in words is related to an arithmetic
error, the amount in figures shall prevail subject to (a)
and (b) above.
(d) if there is a discrepancy between percentage and figures
related to various taxes or levies, the percentage shall
prevail over figure mentioned. However, where the
amount expressed in percentage is related to an
arithmetic error, the amount in figures shall prevail
subject to (a) and (b) above. It should also be noted that
at time of payment against, the prevailing tax/levy rates
will be used as on the date of approval of payment.
(e) Except as provided in sub-clauses (a) to (c) herein
above, the Purchaser shall reject the Price Proposal if
the same contains any other computational or arithmetic
discrepancy or error.
30.5 If the Bidder that submitted the lowest evaluated Bid does not
accept the correction of errors, its Bid shall be disqualified and
its Bid Security shall be forfeited.
31. Preliminary
Examination
of Bids
31.1 The Purchaser shall examine the Technical Proposal to confirm
that all documents and technical documentation requested in
ITB Sub-Clause 11.5 have been provided, and to determine the
completeness of each document submitted.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 72
CESU, Odisha Page 72 Release Date: 27th February 2016
31.2 The Purchaser shall confirm that the following documents and
information have been provided in the Technical Proposal. If
any of these documents or information is missing, the offer
shall be rejected.
(a) Technical Proposal Submission Sheet in accordance
with ITB Sub-Clause 12.1;
(b) written confirmation of authorization to commit the
Bidder;
(c) Bid Security; and
(d) Manufacturer’s Authorization, where applicable.
31.3 Likewise, following the opening of Price Proposals, the
Purchaser shall examine the Price Proposals to confirm that all
documents and financial documentation requested in ITB Sub-
Clause 11.6 have been provided, and to determine the
completeness of each document submitted.
31.4 The Purchaser shall confirm that the following documents and
information have been provided in the Price Proposal. If any of
these documents or information is missing, the offer shall be
rejected.
(a) Price Proposal Submission Sheet in accordance with ITB
Sub-Clause 12.1; and
(b) Price Schedules, in accordance with ITB Clauses 12, 14,
and 15.
32. Examination
of Terms and
Conditions;
Technical
Evaluation
32.1 The Purchaser shall examine the Bids to confirm that all terms
and conditions specified in the GCC and the SCC have been
accepted by the Bidder without any material deviation or
reservation.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 73
CESU, Odisha Page 73 Release Date: 27th February 2016
32.2 The Purchaser shall evaluate the technical aspects of the Bid
submitted in accordance with ITB Clause 18, to confirm that all
requirements specified in the Scope of Work at Section VI, of
the Bidding Document have been met without any material
deviation or reservation.
32.3 If, after the examination of the terms and conditions and the
technical evaluation, the Purchaser determines that the
Technical Proposal is not responsive in accordance with ITB
Clause 29, it shall reject the Bid.
33. Margin of
Preference
33.1 No margin of preference shall apply.
34. Evaluation of
Bids
34.1 The Purchaser shall evaluate Price Proposals of each Bid for
which the Technical Proposal has been determined to be
responsive.
34.2 To evaluate a Price Proposal, the Purchaser shall only use all
the criteria and methodologies defined in this Clause and in
Section IV, Eligibility Criteria and evaluation methodology in
Appendix-E. No other criteria or methodology shall be
permitted.
34.3 To evaluate a Price Proposal, the Purchaser shall consider the
following:
(a) the Bid Price quoted in Price Proposal Submission Sheet
i.e. inclusive of all duties, levies and taxes.
(b) Price adjustment in accordance with Clause 14.3 of ITB
for missing or non-conforming item(s) or component(s).
(c) price adjustment for correction of arithmetic errors in
accordance with ITB Sub-Clause 30.4;
34.4 For comparison of the combined Technical and Price Score of
all responsive bidders, following formula shall be used
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 74
CESU, Odisha Page 74 Release Date: 27th February 2016
(a) Total Score = (Technical Score x 0.50) + (LP/FPx100) x
0.50. Where LP is the lowest price offer and FP is the price
offer of the firm being evaluated
(b) Contracts shall be awarded only to the bidder with the
highest evaluated Total Score
35. Comparison
of Bids
35.1 The Purchaser shall compare all responsive bids to determine
the bid with the maximum score, in accordance with ITB Clause
34.
36. Post-
qualification
of the Bidder
36.1 The Purchaser shall determine to its satisfaction during the
evaluation of Technical Proposals whether Bidders are qualified
to perform the Contract satisfactorily.
36.2 The determination shall be based upon an examination of the
documentary evidence of the Bidder’s qualifications submitted
by the Bidder, pursuant to ITB Clause 18 and to clarifications in
accordance with ITB Clause 28. The eligible bidders shall only
be as empanelled by Nodal Agency meeting qualifying
requirements as mentioned in Eligibility Criteria (Section IV).
36.3 An affirmative determination in accordance with this clause shall
be a prerequisite for the opening and evaluation of a Bidder’s
Price Proposal. A negative determination shall result into the
disqualification of the Bid, in which event the Purchaser shall
return the unopened Price Proposal to the Bidder.
37. Purchaser’s
Right to
Accept Any
Bid, and to
Reject Any or
All Bids
37.1 The Purchaser reserves the right to accept or reject any Bid, and
to annul the bidding process and reject all Bids at any time prior
to Contract award, without thereby incurring any liability to the
Bidders.
F. Award of Contract
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 75
CESU, Odisha Page 75 Release Date: 27th February 2016
38. Award Criteria 38.1 The Purchaser shall award the Contract to the Bidder whose
offer has been awarded the maximum score and is responsive
to the Bidding Document, provided that such Bidder continues to
remain empanelled as per the list (along with any
updation/modifications from time to time) released by the Nodal
Agency.
39. Purchaser’s
Right to Vary
Quantities at
Time of
Award
39.1 At the time the Contract is awarded, the quantity of Goods and
Related Services for a town shall not be modified. However
Purchaser reserves the right to increase or decrease the
number of towns under the contract subject to the limit of 30% of
the existing number of towns covered under the contract,
without any change in the unit prices or other terms and
conditions of the Bid and the Bidding Document.
40. Notification of
Award
40.1 Prior to the expiration of the period of bid validity, the Purchaser
shall notify the successful Bidder, in writing, that its Bid has
been accepted.
40.2 Until a formal Contract is prepared and executed, the notification
of award shall constitute a binding Contract.
41. Signing of
Contract
41.1 Promptly after notification, the Purchaser shall send to the
successful Bidder the Agreement, a copy of SLA and the
General and Special Conditions of Contract.
41.2 Within fourteen (14) days of receipt of the Agreement, the
successful Bidder shall sign, date, and return it to the
Purchaser.
41.3 The successful Bidder shall provide an undertaking that the key
staff identified for the project (as submitted in its bid proposal)
shall be available for the respective proposed work requirement,
anytime during the duration of the project, till its successful
completion. The same is intended to be published by the Nodal
Agency on their website for the information of other utilities who
intend to appoint ITIA, for avoiding any duplicacy in resource
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 76
CESU, Odisha Page 76 Release Date: 27th February 2016
deployment
42. Performance
Security
42.1 Within fourteen (14) days of the receipt of notification of award
from the Purchaser, the successful Bidder shall furnish the
Performance Security in accordance with the GCC, using for
that purpose the Performance Security Form included in Section
IX, Contract Forms.
42.2 Failure of the successful Bidder to submit the above-mentioned
Performance Security or sign the Contract shall constitute
sufficient grounds for the annulment of the award and forfeiture
of the Bid Security. In that event the Purchaser may award the
Contract to the next successful Bidder whose offer is responsive
and is determined by the Purchaser to be qualified to perform
the Contract satisfactorily.
43. Local
Conditions
It will be imperative on each bidder to fully inform himself of all
local conditions and factors which may have any effect on the
execution of the works covered under these documents and
specifications. The purchaser shall not entertain any request for
clarifications from the bidders, regarding such local conditions. It
must be understood and agreed that such factors have properly
been investigated and considered while submitting the
proposals. No claim for financial adjustment to the contract
awarded under these specifications and documents will be
entertained by the purchaser. Neither any change in the time
schedule of the contract nor any financial adjustments arising
thereof shall be permitted by the purchaser, which are based on
the lack of such clear information or its effect on cost of the
works to the bidder.
G. Interpretation
44. Interpretation
of the SRS
44.1 This Bid Document, inclusive of the SRS document, Schedules,
annexure(s), the statements, exhibits and sections, if any,
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 77
CESU, Odisha Page 77 Release Date: 27th February 2016
and the RFP
document
comprises the whole and complete Document
44.2 This RFP document should be read in consonance with the SRS
document. In the RFP document references to the SRS have
been provided. In case there is no reference relating to a
particular clause(s) of the SRS, it should be deemed as the said
reference has been provided. The bidder is required to read
both the documents and would be deemed to be in knowledge
of the provisions of both the SRS and the RFP document. No
claim of any nature whatsoever shall be entertained in this
regard.
44.3 In case of any conflict with any provision relating to the SRS
document and the RFP document, the provisions of the RFP
document shall prevail for all intents and purposes
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 78
CESU, Odisha Page 78 Release Date: 27th February 2016
Section III. Bid Data Sheet
A. Introduction
ITB 1.1 The number of the Invitation for Bids is : CESU/ITCC/R-APDRP/07
ITB 1.1 The Purchaser is:
Senior General Manager (IT),
Central Electricity Supply Utility of Odisha,
8th Floor, IDCO Towers, Janpath, Bhubaneswar -751 022 Odisha
Phone No. - 0674-2545685 Fax No. - 0674-2543125
Email : [email protected]
ITB 1.1 The name of the ICB is: Supply, installation, integration, testing,
commissioning and facility management service of System Integration
Project covering software, hardware, field survey and networking
The identification number of the ICB is: CESU/ITCC/R-APDRP/07
B. Bidding Document
ITB 7.1 For clarification purposes only, the Purchaser’s address is:
Senior General Manager (IT),
Central Electricity Supply Utility of Odisha,
8th Floor, IDCO Towers, Janpath, Bhubaneswar -751 022 Odisha
Phone No. - 0674-2545685 Fax No. - 0674-2543125
Email : [email protected]
ITB 7.2 Details of Pre-Bid conference:
Date: 10th March 2016
Venue: Conference Hall, CESU, 3rd Floor, IDCO Towers, Janpath,
Bhubaneswar - 751 022
Time: from 12:00 Hrs to 14:00 Hrs
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 79
CESU, Odisha Page 79 Release Date: 27th February 2016
C. Preparation of Bids
ITB 10.1 The language of the Bid is: English
ITB 11.5 (g) The Bidder shall submit with its Technical Proposal the following additional
documents:
Refer to Appendix D.2
ITB 11.6 (b) The Bidder shall submit with its Price Proposal the following additional
documents:
Refer to Appendix D.3
ITB 13.1 Alternative Bids shall not be permitted.
ITB 14.4 The Incoterms edition is: Year 2000
ITB 14.5 The prices quoted by the Bidder shall be: Firm (subject to Section VII
GCC 13.2)
ITB 15.1 Bidders may express their bid price in INR. Wherever reference to
“Rupees” or “Rs” as currency has been made, the same should be taken
as “Indian Rupees”.
ITB 19.1 The bid validity period shall be 90 days after the bid submission deadline
date prescribed by the Purchaser.
ITB 20.1 The Bid Security shall be required and the amount required to be
furnished in Indian Rupee is indicated hereunder
Bid Identification No: CESU/ITCC/R-APDRP/07
Bid Security (INR): Rs. 1 Crore (One Crore only) in the form of Bank Guarantee in favour of “Central Electricity Supply Utility of Odisha”, Bhubaneswar, Odisha
D. Submission and Opening of Bids
ITB 21.1 In addition to the original of the bid, the number of copies is : ONE (Hard
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 80
CESU, Odisha Page 80 Release Date: 27th February 2016
Copy), FOUR (Soft Copies)
ITB 21.2 The written confirmation of Authorization to sign on behalf of the Bidder
shall consist of:
Notarized Power of Attorney: - If the bidder is from a country where this
practice is not used then a similar legal instrument of authorization as
applicable under the home country laws of bidder must be provided.
ITB 22.2 (c) The identification of this bidding process is:
The identification of this bidding process is: Single stage Two envelope
The name of ICB: Supply, installation, integration, testing,
commissioning and facility management service of System
Integration Project covering software, hardware, field survey
and networking
Bid Identification
No Particulars
The bid identification No. shall be mentioned by the Bidder prominently on
the top of envelope for the lots in the following manner :
(a) Bidding process for the bid is : “Single stage Two envelope”
(b) Bid identification No. CESU/ITCC/R-APDRP/07
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 81
CESU, Odisha Page 81 Release Date: 27th February 2016
ITB 23.1 For bid submission purposes only, the Purchaser’s address is :
IT Center,
Central Electricity Supply Utility of Odisha,
8th Floor, IDCO Towers, Janpath, Bhubaneswar -751 022 Odisha
Phone No. - 0674-2545685 Fax No. - 0674-2543125
Email : [email protected]
ITB 23.1 The deadline for bid submission is:
Date: 28th March 2016
Time: up to 13:00 Hrs
Wherever reference to “Time” has been made, the same shall be taken as
Indian Standard Time. If time is mentioned in “P.M.”, the same shall be
converted into Hours by adding 12 Hours e.g. 2 P.M. equal to 2 + 12 i.e.
“14.00 Hours IST”
ITB 26.1 The bid opening shall take place at:
Conference Hall
Central Electricity Supply Utility of Odisha,
3rd Floor, IDCO Towers, Janpath, Bhubaneswar -751 022 Odisha
Phone No. - 0674-2545685 Fax No. - 0674-2543125
Email : [email protected]
Date: 28th March 2016
Time: at 15:00 Hrs
E. Evaluation, and Comparison of Bids
ITB 33.1 A margin of preference shall not apply.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 82
CESU, Odisha Page 82 Release Date: 27th February 2016
ITB 34 The currency that shall be used for bid evaluation and comparison
purposes to convert all bid prices expressed in various currencies into a
single currency is: Indian Rupees.
F. Award of Contract
ITB 39.1 The percentage by which number of towns may be increased is: 30
percent of the total number of towns
The percentage by which number of towns may be decreased is: 30
percent of the total number of towns
ITB 42.1 If the successful bidder fails to furnish the required Performance Security
within 14 days of the receipt of notification of award, the Purchaser
reserves the right to terminate the award by forfeiting Bid Security without
any notice.
ITB 42.2 If the successful bidder fails to sign the Contract Agreement within 14
days from the date the successful bidder’s receipt of the Contract
Agreement, the Purchaser reserves the right to terminate the award by
forfeiting Bid Security without any notice.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 83
CESU, Odisha Page 83 Release Date: 27th February 2016
Section IV. Eligibility Criteria
Only those bidders which have been empanelled by the Nodal Agency shall be eligible for
bidding. The qualifying requirements for the various ITIA roles have been provided as
reference.
Qualifying Requirements
QR for System Integrator
The Lead member (referred as SI-Lead) and the 2nd consortium member (in case of a
consortium; referred as SI-2nd) should meet the QR as mentioned below:
For all bidders (except power sector utilities)
i. The SI must have implemented at least one system integration project covering IT
applications, Servers and PCs, WAN with connectivity between at least 10
locations, during the last three financial years. In case of a consortium, this
requirement needs to be met by the SI-Lead.
(Proof: Necessary Purchase order/LOI/Contract/Certification on client
letterhead/Performance certificate as proof of services provided for the last 3
financial years needs to be submitted)
ii. The SI should have cumulative turnover of at least Rs. 300 crore for the last three
audited financial years. In case of a consortium, the consortium as a whole (SI-
Lead and SI-2nd combined) should have cumulative turnover of at least Rs. 300
crore for the last three audited financial years. The SI-Lead should have a turnover
of at least Rs. 270 crore for the last three audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
iii. The SI should have a positive net worth not less than paid-up equity, in each of the
last three audited financial years. In case of a consortium, both the SI-Lead and SI-
2nd should have positive net worth not less than paid-up equity in each of the last
three audited financial years.
(Proof: Annual Accounts for last three financial years )
iv. The SI should have been in the IT / Software services for the last 3 years. In case
of a consortium, this requirement needs to be met by the SI-Lead.
(Proof for which to be submitted in the form of Incorporation Certificate along with
Memorandum & Articles of Association)
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 84
CESU, Odisha Page 84 Release Date: 27th February 2016
v. The SI should have implemented a turnkey Systems Integration project in the last
three financial years involving at least 5 of the following modules: GIS, MIS, Web
Self Service, Asset Management, Maintenance Management, Billing, Metering,
Energy Auditing/Accounting, Customer Care, Network, Hardware in any Utility
(Power/Gas/Water/Telecom sectors) or infrastructure sector (rail/road/port/airport).
The total consumer base covered by the SI for such project in the any Utility should
not be less than 50,000. This requirement is not applicable for infrastructure sector
(rail/road/port/airport) projects as these cater to mass consumers. In case of a
consortium, the requirement of at least 5 modules is distributed as follows: SI-Lead
needs to meet the above requirement for at least 4 modules, and the SI-2nd for at
least 1 module.
(Proof: Necessary Purchase order/LOI/Contract/Certification on client
letterhead/Performance certificate as proof of services provided for the last 3 financial
years needs to be submitted)
vi. The SI should have worked with at least one utility (Power/Gas/Water/Telecom
sectors) or infrastructure sector (rail/road/port/airport) in implementing turnkey
Systems Integration projects. The total worth of projects executed in this domain for
the last three financial years should be at least INR 50 crore (USD10 million). In
case of a consortium, this requirement needs to be met by the SI-Lead.
(Proof: Necessary Purchase order/LOI/Contract/Certification on client
letterhead/Performance certificate as proof of services provided for the last 3 financial
years needs to be submitted)
vii. The SI should be ISO 9001:2000 or have at least CMM/CMMI level 4 certification.
In case of a consortium, this requirement needs to be met by the SI-Lead.
(Proof: Copy of certification from authorized certification body)
viii. The SI should have at least 20 personnel on its rolls with a minimum experience of
5 years (either in his/her own or other organization). The roles & responsibilities of
the personnel should include system integration of IT applications or software or
hardware or network. In case of a consortium, the requirement of at least 20
personnel is distributed as follows: SI-Lead needs to meet the above requirement
for at least 15 CVs, and the SI-2nd for at least 5 CVs
(Proof: Signed resume of employees need to be submitted. Scanned signatures shall
be accepted.)
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 85
CESU, Odisha Page 85 Release Date: 27th February 2016
For power sector utility as bidder (no consortium allowed under this category)
i. The SI must have implemented, within its own organization, at least one system
integration project covering IT applications, Servers and PCs, WAN project with
connectivity between at least 10 locations during the last three financial years.
ii. The SI should have cumulative turnover of at least Rs.2,500 crore for the last three
audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
iii. The SI should have a positive net worth not less than paid-up equity in each of the
last three audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
iv. The SI should have implemented a turnkey Systems Integration project involving at
least any 5 of the following modules: GIS, MIS, Web Self Service, Asset
Management, Maintenance Management, Billing, Metering, Energy Auditing /
Accounting, Customer Care, Network, hardware. The total consumer base covered
by the SI for such project in the any Utility should not be less than 50,000. This
requirement is not applicable for infrastructure sector (rail/road/port/airport) projects
as these cater to mass consumers. The total worth of turnkey Systems Integration
projects implemented by the SI in above domain should be at least INR 50 crore
(USD10 million).
v. The SI should have at least 20 personnel on its rolls with a minimum experience of
5 years (either in his/her own or other organization). The roles & responsibilities of
the personnel should include system integration of IT applications or software or
hardware or network.
(Proof: Signed resume of employees need to be submitted. Scanned signatures shall
be accepted.)
Proof of credentials for experience (refer i and iv above) should be either of the following:
•The ARR/DPRs which have been approved by Regulatory Commission, with clear mention of
the project details and its value. The same should be supported by an undertaking from the
Company Secretary
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 86
CESU, Odisha Page 86 Release Date: 27th February 2016
•Auditor’s certification along with Undertaking by Company Secretary with clear mention of the
project details and its value (including module wise go-live dates and the current status of the
project)
QR for Network Solution Provider
For all bidders (except power sector utilities)
i. The Network Solution Provider should have implemented at least 5 multi location
WAN projects (installation, integration, maintenance & management) during the
last three financial years out of which at least two projects should have involved
Leased Lines or ISDN or VSAT or RF or DSL or VPN /MPLS or Fibre Optics or a
combination of these technologies for a customer having a minimum of 10 WAN
locations.
(Proof: Necessary Purchase order/LOI/Contract/Certification on client
letterhead/Performance certificate as proof of services provided for the last 3
financial years needs to be submitted)
ii. The Network Solution Provider should have been in the Network
installation/maintenance services for the last 3 years.
(Proof for which to be submitted in the form of Incorporation Certificate along with
Memorandum & Articles of Association)
iii. The Network Solution Provider should have cumulative turnover of at least Rs. 60
crore for the last three audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
iv. The Network Solution Provider should have a positive net worth in each of the last
three audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
v. Network Solution Provider should be an ISO 9001:2000 certified company.
(Proof: Copy of certification from authorized certification body)
vi. The Network Solution Provider should have at least 10 personnel on its rolls with
a minimum experience of 5 years (either in his/her own or other organization).
The roles & responsibilities of the personnel should include installation or
integration or maintenance or management of network systems.
(Proof: Signed resume of employees need to be submitted. Scanned signatures
shall be accepted.)
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 87
CESU, Odisha Page 87 Release Date: 27th February 2016
For power sector utility as bidder
i. The Network Solution Provider should have implemented, within its own
organization, at least one project involving Leased Lines or ISDN or VSAT or RF
or DSL or VPN /MPLS or Fibre Optics or a combination of these technologies
having a minimum of 10 WAN locations during last three financial years.
ii. The Network Solution Provider should have cumulative turnover of at least Rs.
2500 crore for the last three audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
iii. The Network Solution Provider should have a positive net worth in each of the last
three audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
iv. The Network Solution Provider should have at least 10 personnel on its rolls with
a minimum experience of 5 years (either in his/her own or other organization).
The roles & responsibilities of the personnel should include installation or
integration or maintenance or management of network systems.
(Proof: Signed resume of employees need to be submitted. Scanned signatures
shall be accepted.)
Proof of credentials for experience (refer i above) should be either of the following:
• The ARR/DPRs which have been approved by Regulatory Commission, with clear mention
of the project details and its value. The same should be supported by an undertaking from
the Company Secretary
• Auditor’s certification along with Undertaking by Company Secretary with clear mention of
the project details and its value (including module wise go-live dates and the current status
of the project)
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 88
CESU, Odisha Page 88 Release Date: 27th February 2016
QR for GIS Solution Provider
All bidders (except power sector utilities)
i. The GIS Solution Provider should have executed at least two GIS projects
(software development & customization & mapping and digitization) in utility
(Power/Gas/Water/Telecom sectors) or infrastructure sector (rail/road/port/airport)
during the last three financial years.
(Proof: Necessary Purchase order/LOI/Contract/Certification on client
letterhead/Performance certificate as proof of services provided for the last 3 financial
years needs to be submitted)
Additional Note: In case a company has implemented GIS systems in the last 5
years, and has been maintaining the same system since commissioning till date,
such maintenance contracts for the last three years, shall be acceptable as proof
ii. The GIS Solution Provider should have cumulative turnover of at least Rs. 10 crore
for the last three audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
iii. The GIS Solution Provider should have a positive net worth not less than paid-up
equity in each of the last three audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
iv. The GIS Solution Provider should have been in the GIS Software development &
customization or mapping or digitization services for the last 3 years.
(Proof for which to be submitted in the form of Incorporation Certificate along-with
Memorandum & Articles of Association)
v. GIS Solution Provider should be an ISO 9001:2000 certified company.
(Proof: Copy of certification from authorized certification body)
vi. The GIS Solution Provider should have at least 10 personnel on its rolls with a
minimum experience of 5 years (either in his/her own or other organization). The
roles & responsibilities of the personnel should include GIS software development
& customization or mapping or digitization.
(Proof: Signed resume of employees need to be submitted. Scanned signatures shall
be accepted)
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 89
CESU, Odisha Page 89 Release Date: 27th February 2016
For power sector utility as bidder
i. The GIS Solution Provider should have executed, within its own organization, at
least one GIS project (software development & customization & mapping and
digitization).
Additional Note: In case a company has implemented GIS systems in the last 5
years, and has been maintaining the same system since commissioning till date,
such maintenance contracts for the last three years, shall be acceptable as proof
ii. The GIS Solution Provider should have cumulative turnover of at least Rs. 2500
crore for the last three audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
iii. The GIS Solution Provider should have a positive net worth not less than paid-up
equity in each of the last three audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
iv. The GIS Solution Provider should have at least 10 personnel on its rolls with a
minimum experience of 5 years (either in his/her own or other organization). The
roles & responsibilities of the personnel should include GIS software development
& customization or mapping or digitization.
(Proof: Signed resume of employees need to be submitted. Scanned signatures shall
be accepted)
Proof of credentials for experience (refer i above) should be either of the following:
• The ARR/DPRs which have been approved by Regulatory Commission, with clear mention
of the project details and its value. The same should be supported by an undertaking from
the Company Secretary
• Auditor’s certification along with Undertaking by Company Secretary with clear mention of
the project details and its value (including module wise go-live dates and the current status
of the project)
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 90
CESU, Odisha Page 90 Release Date: 27th February 2016
QR for Meter Data Acquisition Solution Provider
All bidders (except power sector utilities)
i. The Meter Data Acquisition Solution Provider must have successfully implemented
at least one AMR project or data logging system or served a power distribution
utility providing services using meter reading instrument (MRI) in the last 3 financial
years.
(Proof: Necessary Purchase order/LOI/Contract/Certification on client
letterhead/Performance certificate as proof of services provided for the last 3
financial years needs to be submitted)
In case a company has implemented MDA systems in the last 5 years, and has been
maintaining the same system since commissioning till date, such maintenance
contracts for the last three years, shall be acceptable as proof.
ii. The Meter Data Acquisition Solution Provider should have been in the business of
Meter Data Acquisition (development and customization of software, and/or
commissioning AMR/Data logging system/MRI) for the last 3 financial years.
(Proof for which to be submitted in the form of Incorporation Certificate along-with
Memorandum & Articles of Association)
iii. The Meter Data Acquisition Solution provider should have cumulative turnover of at
least Rs. 10 crore for the last three audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
iv. The Meter Data Acquisition Solution Provider should have a positive net worth not
less than paid-up equity in each of the last three audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
v. Meter Data Acquisition Solution Provider should be an ISO 9001:2000 certified
company.
(Proof: Copy of certification from authorized certification body)
vi. The Meter Data Acquisition Solution provider should have at least 10 personnel on
its rolls with a minimum experience of 5 years (either in his/her own or other
organization). The roles & responsibilities of the personnel should include
development and/or customization of Meter Data Acquisition System.
(Proof: Signed resume of employees need to be submitted. Scanned signatures shall
be accepted.)
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 91
CESU, Odisha Page 91 Release Date: 27th February 2016
For power sector utility as bidder
i. The Meter Data Acquisition Solution Provider must have successfully implemented at least
one AMR project or data logging system or served a power distribution utility providing
services using meter reading instrument (MRI) in the last 3 financial years.
Additional note: In case a company has implemented MDA systems in the last 5 years, and
has been maintaining the same system since commissioning till date. Such maintenance
contracts for the last three years, shall be acceptable as proof
ii. The Meter Data Acquisition Solution provider should have cumulative turnover of at least
Rs. 2500 crore for the last three audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
iii. The Meter Data Acquisition Solution Provider should have a positive net worth not less
than paid-up equity in each of the last three audited financial years.
(Proof: Annual Audited Financial Statements for last three financial years )
iv. The Meter Data Acquisition Solution provider should have at least 10 personnel on its rolls
with a minimum experience of 5 years (either in his/her own or other organization). The
roles & responsibilities of the personnel should include development and/or customization
of Meter Data Acquisition System.
(Proof: Signed resume of employees need to be submitted. Scanned signatures shall be
accepted.)
Proof of credentials for experience (refer i above) should be either of the following:
• The ARR/DPRs which have been approved by Regulatory Commission, with clear mention
of the project details and its value. The same should be supported by an undertaking from
the Company Secretary
• Auditor’s certification along with Undertaking by Company Secretary with clear mention of
the project details and its value (including module wise go-live dates and the current status
of the project)
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 92
CESU, Odisha Page 92 Release Date: 27th February 2016
Section V. Bidding Forms
Table of Forms
1. TECHNICAL PROPOSAL SUBMISSION SHEET ............................................................... 93
2. PRICE PROPOSAL SUBMISSION SHEET ......................................................................... 95
3. BID SECURITY ........................................................................................................................ 96
4. MANUFACTURER’S AUTHORIZATION .............................................................................. 98
5. CERTIFICATE AS TO CORPORATE PRINCIPAL ............................................................. 99
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 93
CESU, Odisha Page 93 Release Date: 27th February 2016
1. Technical Proposal Submission Sheet
Date:
ICB No.:
Invitation for Bid No.:
Alternative No.:
To:
_______________________________________________________________________
We, the undersigned, declare that:
(a) We have examined and have no reservations to the Bidding Document, including
Addenda No. (if Any):
(b) We offer to supply in conformity with the Bidding Document and in accordance with
the delivery schedule, the following Goods and Related Services:
(c) Our Bid shall be valid for a minimum period of 90 days from the date fixed for the bid
submission deadline in accordance with the Bidding Document, and it shall remain
binding upon us and may be accepted at any time before the expiration of that period;
(d) If our Bid is accepted, we commit to obtain a Performance Security in the amount of
10 percent of the Contract Price for the due performance of the Contract;
(e) We are not participating, as Bidders, in more than one Bid in this bidding process in
accordance with the Bidding Document;
(f) Our firm, its affiliates or subsidiaries, including any subcontractors or suppliers for any
part of the Contract, has not been declared ineligible by the CESU.
(g) We understand that this Bid, together with your written acceptance thereof included in
your notification of award, shall constitute a binding contract between us, until a
formal Contract is prepared and executed.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 94
CESU, Odisha Page 94 Release Date: 27th February 2016
(h) We understand that you are not bound to accept the best evaluated bid or any other
bid that you may receive.
(i) We undertake to open office in Bhubaneswar after award of contract.
(j) The bidder shall give self declaration that the FMS Cost has been taken as minimum
20% of the total project cost (excluding FMS and bandwidth cost) and if it is less than
20%, its bid may be declared as non-responsive.
(k) We undertake to comply to the Quality Assurance plan conforming to the defined
standards in the SRS and RFP documents.
……………………………………………………………………………….
Name
In the capacity of
Signed
Duly authorized to sign the Bid for and on behalf of
Date
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 95
CESU, Odisha Page 95 Release Date: 27th February 2016
2. Price Proposal Submission Sheet
Date:
ICB No.:
Invitation for Bid No.:
Alternative No.:
To:
_______________________________________________________________________
We, the undersigned, declare that:
(a) We have examined and have no reservations to the Bidding Document, including
Addenda No. (if any):
(b) We offer to supply in conformity with the Bidding Document and in accordance with
the delivery schedule, the following Goods and Related Services:
(c) The total price of our Bid is:
(d) The following commissions, gratuities, or fees have been paid or are to be paid with
respect to the bidding process or execution of the Contract:
Name of Recipient Address Reason Amount
(If none has been paid or is to be paid, indicate “none.”)
Name
In the capacity of
Signed
Duly authorized to sign the Bid for and on behalf of
Date
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 96
CESU, Odisha Page 96 Release Date: 27th February 2016
3. Bid Security
(To be accompanied with the bank Guarantee)
Date: ________________________
ICB No.: _____________________
Invitation for Bid No.: __________
To: _____________________________________________________________________
Whereas
___________________________________________________________________
________________________________________________________________________
___ (hereinafter called “the Bidder”) has submitted its Bid dated
____________________________ for ICB No. ___________ for the supply of
______________________________________
____________________________________________________________ hereinafter
called “the Bid.”
KNOW ALL PEOPLE by these presents that WE _________________________________ of
___________________________________________________ having our registered
office at _________________________________________________ (hereinafter called
“the Guarantor”), are bound unto
___________________________________________________
_________________________________________________________________
(hereinafter called “the Purchaser”) in the sum of
________________________________________________ for which payment well and
truly to be made to the aforementioned Purchaser, the Guarantor binds itself, its
successors, or assignees by these presents. Sealed with the Common Seal of this
Guarantor this ____________________day of _________________________, _____.
THE CONDITIONS of this obligation are the following:
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 97
CESU, Odisha Page 97 Release Date: 27th February 2016
1. If the Bidder withdraws its Bid during the period of bid validity specified by the
Bidder in the Bid Submission Sheet, except as provided in ITB Sub-Clause 19.2; or
2. If the Bidder, having been notified of the acceptance of its Bid by the Purchaser,
during the period of bid validity, fails or refuses to:
(a) Execute the Contract; or
(b) Furnish the Performance Security, in accordance with the ITB Clause 42; or
(c) Accept the correction of its Bid by the Purchaser, pursuant to ITB Clause 30.
We undertake to pay the Purchaser without protest or demur up to the above amount upon
receipt of its first written demand, without the Purchaser having to substantiate its
demand, provided that in its demand the Purchaser states that the amount claimed by it is
due to it, owing to the occurrence of one or more of the above conditions, specifying the
occurred conditions.
This security shall remain in force up to and including sixty (60) days after the period of bid
validity, and any demand in respect thereof should be received by the Guarantor no later
than the above date.
Name
In the capacity of
Signed
Duly authorized to sign the Bid Security for and on behalf of
Date
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 98
CESU, Odisha Page 98 Release Date: 27th February 2016
4. Manufacturer’s Authorization
(To be obtained from all OEMs)
Date:
ICB No.:
Invitation for Bid No.:
Alternative No.:
To:
WHEREAS___________________________________________________ who are official
manufacturers of ____________________________________________________ having
factories at _______________________________________________________________
do hereby authorize ____________________________________________________ to
submit a Bid in relation to the Invitation for Bids indicated above, the purpose of which is
to provide the following Goods, manufactured by us ______________________________
and to subsequently negotiate and sign the Contract.
We hereby extend our full guarantee and warranty in accordance with Clause 26 of the
General Conditions of Contract, with respect to the Goods offered by the above firm in
reply to this Invitation for Bids.
Name
In the capacity of:
Signed
Duly authorized to sign the Authorization for and on behalf of
Date
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 99
CESU, Odisha Page 99 Release Date: 27th February 2016
5. Certificate as to Corporate Principal
CERTIFICATE AS TO CORPORATE PRINCIPAL
(To be signed by any of Board Directors or Co.Secry)
(To be accompanied along with requisite copy of the board resolution)
I _______________________ certify that I am _________________ of the
Company under the laws of _____________________ and that __________________ who
signed the above tender is authorized to bind the Company / Firm by authority of its
governing body.
Signature : _________________
Full Name : _________________
Address : _________________
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 100
CESU, Odisha Page 100 Release Date: 27th February 2016
Section VI. Scope of Work
1) Section G1
a. Clause 2: Intent of Specification
b. Clause 3: Scope of Work
c. Clause 4: Other Services and Items
d. Clause 5: Specific Exclusions
e. Clause 16: Spares
2) Section G2
a. ‘Objective’ mentioned in Clause 1.0: Meter data acquisition system
b. ‘Objective’ mentioned in Clause 2.0: Energy Audit
c. ‘Objective’ mentioned in Clause 3.0: New Connection
d. ‘Objective’ mentioned in Clause 4.0: Disconnection and Dismantling
e. ‘Objective’ mentioned in Clause 5.0: GIS based customer Indexing and asset mapping
f. ‘Objective’ mentioned in Clause 6.0: GIS based integrated network analysis module
g. ‘Objective’ mentioned in Clause 7.0: Customer care services
h. ‘Document Management Solution’ and ‘Data Warehousing and Business Intelligence’ mentioned in Clause 8.0: MIS
i. ‘Objective’ mentioned in Clause 9.0: Web self service
j. ‘Objective’ mentioned in Clause 10.0: Identity and Access Management System
k. ‘Objective’ mentioned in Clause 11.0: System Security Requirement
l. ‘Development of Commercial Database of Consumers’ mentioned in clause 12.0
m. ‘Objective’ mentioned in Clause 13.0: Metering
n. ‘Objective’ mentioned in Clause 14.0: Billing
o. ‘Objective’ mentioned in Clause 15.0: Collection
p. ‘Objective’ mentioned in Clause 16.0: Asset Management
q. ‘Objective’ mentioned in Clause 17.0: Maintenance Management
3) Section G3
a. Clause 1: Introduction
b. Clause 2: LAN
c. Clause 3: VPN/MPLS Wide Area Network
d. Clause 4: Implementation Plan
e. Clause 22: Disaster Recovery Centre
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 101
CESU, Odisha Page 101 Release Date: 27th February 2016
4) Section G4
a. Clause 2: Objectives
b. Clause 3: Scope of Work
c. Clause 4: Field survey and mapping
d. Clause 5: Indexing
e. Clause 6: Deliverables
f. Clause 7: Implementation Methodology
g. Clause 8: Satellite Imagery Specifications
5) Section G5
a. Clause 5: Scope of Work
6) Any other scope mentioned in the RFP Document
7) Scope of work mentioned for Non-R-APDRP Area in Bid Feature Section
The ITIA shall be responsible for integration of the IT system created under the R-APDRP scheme at all the selected Project Areas, Central Customer Care Centre, Disaster Recovery Centre and Data Centre, by using inter-operability profile/APIs, etc., for data exchange & seamless integration.
Since CESU is floating the RFP for IT Implementation Project across all selected Project Areas in CESU, the ITIA shall be interacting with utility for seamless operational integration of the whole project.
The bidders shall refer to the following appendices for details
Appendix-F: Geographic and administrative information
Appendix-G: List of offices for WAN connectivity
Appendix-H: Review of current IT Systems
Appendix-I: List of manuals/business processes to be converted to electronic form
Appendix-J: Review of current business processes
Appendix-K: Website
Appendix-L: List of goods and related services
Appendix-M: Estimated Man Power Requirement
Appendix-N: Expected Implementation Schedule
Appendix-O: Spot Billing Machine Specification
Appendix-P: Map of CESU of Odisha
Appendix-Q: Format of Price Bids
Appendix-R: Proposed Interface Scheme
Appendix-S: CESU Offices Locations for Network Connectivity
Appendix-T: Additional Clarifications
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 102
CESU, Odisha Page 102 Release Date: 27th February 2016
Appendix-U: No Deviation Certificate
Appendix-V: Abbreviations
Section VII. General Conditions of Contract
Table of Clauses
1. CONTRACT DOCUMENTS ....................................................................................................... 107
2. CORRUPT PRACTICES ............................................................................................................ 107
3. INTERPRETATION ................................................................................................................... 108
4. LANGUAGE .............................................................................................................................. 110
5. CONSORTIUM .......................................................................................................................... 111
6. NOTICES .................................................................................................................................. 112
7. GOVERNING LAW .................................................................................................................... 112
8. SETTLEMENT OF DISPUTES ................................................................................................... 112
9. SCOPE OF WORK .................................................................................................................... 113
10. DELIVERY ............................................................................................................................. 113
11. SUPPLIER’S RESPONSIBILITIES .......................................................................................... 113
12. PURCHASER’S RESPONSIBILITIES ..................................................................................... 114
13. CONTRACT PRICE ............................................................................................................... 114
14. TERMS OF PAYMENT .......................................................................................................... 115
15. TAXES AND DUTIES ............................................................................................................ 115
16. PERFORMANCE SECURITY ................................................................................................ 116
17. INTELLECTUAL PROPERTY ................................................................................................ 117
18. CONFIDENTIAL INFORMATION ........................................................................................... 118
19. SUBCONTRACTING............................................................................................................... 120
20. SPECIFICATIONS AND STANDARDS .................................................................................. 122
21. PACKING AND DOCUMENTS .............................................................................................. 122
22. INSURANCE ......................................................................................................................... 123
23. TRANSPORTATION ............................................................................................................... 123
24. INSPECTIONS AND TESTS .................................................................................................. 123
25. LIQUIDATED DAMAGES AND PENALTY ............................................................................ 125
26. WARRANTY .......................................................................................................................... 125
27. LIABILITY/ INDEMNITY ........................................................................................................ 126
28. LIMITATION OF LIABILITY ................................................................................................... 129
29. CHANGE IN LAWS AND REGULATIONS ............................................................................. 129
30. FORCE MAJEURE ................................................................................................................ 129
31. CHANGE ORDERS AND CONTRACT AMENDMENTS ........................................................ 131
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 103
CESU, Odisha Page 103 Release Date: 27th February 2016
32. EXTENSIONS OF TIME ......................................................................................................... 131
33. TERMINATION ...................................................................................................................... 132
34. ASSIGNMENT ....................................................................................................................... 135
35. DISCLAIMER ........................................................................................................................ 135
36. PUBLIC DISCLOSURE ......................................................................................................... 135
37. SLA AUDIT ............................................................................................................................ 135
38. ADHERENCE TO SAFETY PROCEDURES, RULES REGULATIONS AND RESTRICTION . 136
39. NON-SOLICITATION OF STAFF ........................................................................................... 137
40. SURVIVAL............................................................................................................................. 137
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 104
CESU, Odisha Page 104 Release Date: 27th February 2016
General Conditions of Supply
(1) Definitions The following words and expressions shall have the meanings
hereby assigned to them:
(a) “Contract” means the Agreement entered into
between the Purchaser and the Supplier, together with
the Contract Documents referred to therein, including all
attachments, appendices, and all documents
incorporated by reference therein.
(b) “Contract Documents” shall mean the following
documents listed, including any amendments thereto be
read and construed as part of this Agreement, viz.:
i. the Detailed award of contract;
ii. the Service level agreement;
iii. the Special Conditions of Contract;
iv. the General Conditions of Contract;
v. the Scope of Work;
vi. the System Requirement Specification Document (SRS)
vii. the Instructions to bidders;
viii. the Purchaser’s Notification to the Supplier for Award of
Contract;
ix. Supplier’s response (proposal) to the RFP, including the
Bid Submission Sheet and the Price Proposal submitted
by the Supplier;
x. Appendix A to B & E to S;
xi. Acceptance of purchaser’s notification
xii. RFQ document (Identification No: R-
APDRP/ITIA/2008/11) along with all corrigendum,
clarifications and related documents issued by the
Nodal Agency
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 105
CESU, Odisha Page 105 Release Date: 27th February 2016
(b) “Contract Price” means the price payable to the
Supplier as specified in the Agreement, subject to such
additions and adjustments thereto or deductions there
from, as may be made pursuant to the Contract.
(c) “Day” means calendar day.
(d) “Delivery” means the transfer of the Goods and
services from the Supplier to the Purchaser in
accordance with the terms and conditions set forth in
the Contract.
(e) “Completion” shall mean the completion of the
Related Services by the Supplier in accordance with the
terms and conditions set forth in the Contract.
(f) “GCC” means the General Conditions of Contract.
(g) “Goods” means all hardware, software, networking
equipment and/or other equipment accessories and
materials that the Supplier is required to supply to the
Purchaser under the Contract.
(h) “Intellectual Property Rights” means any patent,
copyright, trademark, trade name, service marks,
brands, propriety information, whether arising before or
after the execution of this Contract and the right to
ownership and registration of these rights.
(i) “Purchaser’s Country” shall mean India.
(j) “Purchaser” means the entities purchasing the
Goods and Related Services.
(k) “Related Services” means the services to be
provided as per the requirements / conditions specified
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 106
CESU, Odisha Page 106 Release Date: 27th February 2016
in the Contract. In addition to this, the definition would
also include other related/ancillary services that may be
required to execute this Contract.
(l) “SCC” means the Special Conditions of Contract.
(m) “Service Level Agreement” (SLA) shall mean the
Service Level Agreement entered into between the
Purchaser and the Supplier.
(n) “Subcontractor” means any natural person, private
or government entity, or a combination of the above,
including its legal successors or permitted assigns, to
whom any part of the Goods to be supplied or execution
of any part of the Related Services is subcontracted by
the Supplier, as per the provisions of Clauses 19 of the
GCC.
(o) “Supplier” means the empanelled System Integrator
(SI) whose bid to perform the Contract has been
accepted by the Purchaser and is named as such in the
Agreement, and includes the legal successors or
permitted assigns of the Supplier.
(p) “The MoP” is the Ministry of Power, Government of
India.
(q) “The Site,” shall mean all identified locations within
the CESU of Odisha, where the Supplier carries out any
installation of Goods or is required to provide any
Related Services.
(r) “OEM” means the Original Equipment Manufacturer
of any equipment / system / software / product that are
providing such goods to the Purchaser under the scope
of this Tender / Contract.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 107
CESU, Odisha Page 107 Release Date: 27th February 2016
(s) “Kick Off Meeting” means a meeting convened by
the Purchaser to discuss and finalize the work execution
plan and procedures with the Supplier.
(t) the term “in writing” means communicated in written
form with proof of receipt
1. Contract
Documents
1.1 Subject to the order of precedence set forth in the Agreement, all
documents forming the Contract (and all parts thereof) are intended
to be correlative, complementary, and mutually explanatory.
2. Corrupt
Practices
2.1 The Purchaser requires bidders, suppliers, and contractors to
observe the highest standard of ethics during the execution of
such contracts.
o The following definitions apply:
o “corrupt practice” means the offering, giving receiving, or
soliciting, directly or indirectly, of anything of value to
influence the action of any party in the procurement process
or the execution of a contract;
o “fraudulent practice” means a misrepresentation or omission
of facts in order to influence a procurement process or the
execution of a contract;
o “collusive practices” means a scheme or arrangement
between two or more bidders, with or without the knowledge
of the CESU, designed to influence the action of any party in
a procurement process or the execution of a contract;
o “coercive practices” means harming or threatening to harm,
directly or indirectly, persons, or their property to influence
their participation in a procurement process, or affect the
execution of a contract;
(a) The Purchaser will reject a proposal for award if it
determines that the bidder recommended for award has,
directly or through an agent, engaged in corrupt,
fraudulent, collusive, or coercive practices in competing
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 108
CESU, Odisha Page 108 Release Date: 27th February 2016
for the Contract.
(b) After the award of the contract if it is comes to the
knowledge of the Utility that the Supplier has engaged
in corrupt, fraudulent, collusive, or coercive practices at
any stage, the Purchaser shall forthwith terminate the
contract as per the provisions of GCC Clause 33.
3. Interpretation 3.1 In this Contract unless a contrary intention is evident:
A. In case of any conflict with any provision relating to the SRS
document and the RFP document, the provisions of the RFP
document shall prevail for all intents and purposes
B. the clause headings are for convenient reference only and do not
form part of this Contract;
C. unless otherwise specified a reference to a clause number is a
reference to all of its sub-clauses;
D. unless otherwise specified a reference to a clause, sub-clause or
section is a reference to a clause, sub-clause or section of this
Contract including any amendments or modifications to the same
from time to time;
E. a word in the singular includes the plural and a word in the plural
includes the singular;
F. a word importing a gender includes any other gender;
G. a reference to a person includes a partnership and a body
corporate;
H. a reference to legislation includes legislation repealing, replacing
or amending that legislation;
I. where a word or phrase is given a particular meaning it includes
the appropriate grammatical forms of that word or phrase which
have corresponding meanings
J. In the event of an inconsistency between the terms of this
Contract and the Bid document and the proposal, the terms of
this contract hereof shall prevail.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 109
CESU, Odisha Page 109 Release Date: 27th February 2016
K. Whenever a material or article is specified or described by the
name of a particular brand, manufacturer or trade mark, the
specific item shall be understood as establishing type, function
and quality desired. Products of other manufacturers may also
be considered, provided sufficient information is furnished so as
to enable the Purchaser to determine that the products are
equivalent to those named
3.2 Incoterms
The meaning of any trade term and the rights and obligations of
parties thereunder shall be as prescribed by Incoterms.
1. EXW, CIF, CIP, and other similar terms, shall be governed by
the rules prescribed in the current edition of Incoterms,
published by the International Chamber of Commerce at the
date of the Invitation for Bids or as specified in the SCC.
3.3 Entire Agreement
The Contract constitutes the entire agreement between the
Purchaser and the Supplier and supersedes all
communications, negotiations and agreements (whether
written or oral) of parties with respect thereto made prior to the
date of Contract.
3.4 Amendment
No amendment or other variation of the Contract shall be valid
unless it is in writing, is dated, expressly refers to the Contract,
and is signed by a duly authorized representative of each
party thereto.
3.5 Waiver
(a) Subject to GCC Sub-Clause 3.5.2 below, no relaxation,
forbearance, delay, or indulgence by either party in enforcing
any of the terms and conditions of the Contract or the
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 110
CESU, Odisha Page 110 Release Date: 27th February 2016
granting of time by either party to the other shall prejudice,
affect, or restrict the rights of that party under the Contract.
Neither shall any waiver by either party of any breach of
Contract operate as waiver of any subsequent or continuing
breach of Contract.
(b) The waiver by either party of a breach or default of any of
the provisions of this contract by the other party shall not be
interpreted as :
A) A waiver of any succeeding breach of the same or other
provision, nor shall any delay or omission on the part of
the other party to exercise; or
B) A way to avail itself of any right, power, or privilege that it
has or may have under this contract to operate as waiver
of any breach or default by the other party.
(c) Any waiver of a party’s rights, powers, or remedies under the
Contract must be in writing, dated, and signed by an
authorized representative of the party granting such waiver,
and must specify the right and the extent to which it is being
waived.
3.6 Severability
If any provision or condition of the Contract is prohibited or
rendered invalid or unenforceable, such prohibition, invalidity
or unenforceability shall not affect the validity or enforceability
of any other provisions and conditions of the Contract or the
contract as a whole and the remaining provisions of the
contract shall remain in full force and effect.
4. Language 4.1 The official language of the Contract is English. Contract as
well as all correspondence and documents relating to the
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 111
CESU, Odisha Page 111 Release Date: 27th February 2016
Contract exchanged by the Supplier and the Purchaser, shall
be written in English. Supporting documents and printed
literature that are part of the Contract may be in another
language provided they are accompanied by an accurate
translation of the relevant passages in English, in which case,
for purposes of interpretation of the Contract, the English
translation shall govern.
4.2 The Supplier shall bear all costs of translation to English and all
risks of the accuracy of such translation. The Supplier shall be
bound to the English translation and what has been stated
therein.
5. Consortium 5.1 If the Supplier is a consortium, the members of such
consortium shall be jointly and severally liable to the
Purchaser for the fulfillment of the provisions of the Contract.
Only the Lead Member (as mentioned at the Empanelment
stage) shall have the authority to conduct all businesses for
and on behalf of the Consortium during the bidding process
and, in the event the Consortium is awarded the Contract,
during contract execution, the composition of the consortium
cannot be altered.
(a) Without prejudice to Clause 5.1 of this GCC, for the
purposes of fulfillment of it’s obligations as laid down
under the Contract where the Purchaser deems fit and
unless the context requires otherwise, Supplier shall
refer to the Lead Member who shall be the sole point of
interface between the Purchaser and the Consortium
and would be absolutely accountable for the
performance of its own, the other members of
Consortium and/or its Team’s functions as also the
subcontractors.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 112
CESU, Odisha Page 112 Release Date: 27th February 2016
(b) All payments shall be made by the Purchaser in
favour of the Lead Member.
6. Notices 6.1 All notices and other communications under this contract must
be in writing, and must either be mailed by registered mail with
acknowledgement Due. Or hand delivered with proof of it
having been received.
6.2 If mailed, all notices will be considered as delivered after 5
days, of the notice having been mailed. If hand delivered, all
notices will be considered, when received by the party to
whom the notice is meant and sent for.
6.3 All notices under this contract shall be sent to or delivered at
the address as specified by the parties in the SCC.
6.4 A Notice shall be effective when delivered or on the Notice’s
effective date, whichever is later.
7. Governing Law 7.1 The Contract shall be governed by and interpreted in
accordance with the laws of the India. The High Court of
Judicature at Odisha High Court, Cuttack and Courts
subordinate to such High Courts shall have exclusive
jurisdiction in respect of any disputes relating to the tendering
process, award of Contract and execution of the Contract.
7.2 In all cases, this contract shall be governed by and interpreted
in accordance with the Law of the Union Of India. In this
context, the expression ‘Law’ takes within it’s fold Statutory
law, Judicial Decisional Law and Delegated Legislation as well
8. Settlement of
Disputes
8.1 The Purchaser and the Supplier shall make every effort to
resolve amicably by direct informal negotiation any
disagreement or dispute arising between them under or in
connection with the Contract.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 113
CESU, Odisha Page 113 Release Date: 27th February 2016
8.2 If the parties fail to resolve such a dispute (The date of
commencement of the dispute shall be taken from the date
when this clause reference is quoted by either party in a
formal communication clearly mentioning existence of dispute
or as mutually agreed) or difference by mutual consultation
within twenty-eight (28) days from the commencement of such
consultation, either party may require that the dispute be
referred for resolution to the formal mechanisms specified in
the SCC.
9. Scope of Work 9.1 The Goods and Related Services to be supplied are specified
in Appendix-L. At the time of awarding the contract, the
Purchaser shall specify any change in the Scope of Work.
Such changes may be due for instance, if the quantities of
goods and related services are increased or decreased at the
time of award.
9.2 Unless otherwise stipulated in the Contract, the Scope of Work
shall include all such items not specifically mentioned in the
Contract but that can be reasonably inferred from the Contract
as being required for attaining Delivery and Completion of the
Goods and Related Services as if such items were expressly
mentioned in the Contract.
10. Delivery 10.1 Subject to GCC Sub-Clause 32.1, the Delivery of the Goods
and Completion of the Related Services shall be in
accordance with the Implementation Schedule specified in the
Appendix-N. The details of shipping and other documents to
be furnished by the Supplier are specified in the SCC.
11. Supplier’s
Responsibilities
11.1 The Supplier shall supply all the Goods and Related Services
included in the Scope of Work and Appendix-L in accordance
with GCC Clause 9, and the Implementation Schedule, as per
GCC Clause 10.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 114
CESU, Odisha Page 114 Release Date: 27th February 2016
12. Purchaser’s
Responsibilities
12.1 Whenever the supply of Goods and Related Services requires
that the Supplier obtain permits, approvals, and import and
other licenses from local public authorities, the Purchaser
shall, if so required by the Supplier, make its best effort to
assist the Supplier in complying with such requirements in a
timely and expeditious manner.
12.2 The Purchaser shall bear all costs involved in the performance
of its responsibilities, in accordance with GCC Sub-Clause
13.1.
12.3 The IT Head / Chief Information Officer (CIO) of CESU or any
other person designated by the utility shall act as the nodal
point for implementation of the contract and for issuing
necessary instructions, approvals, commissioning, acceptance
certificates, payments etc. to the Supplier.
12.4 The IT Head / CIO of CESU or any other person designated by
the utility shall approve all such documents within 15 working
days.
12.5 Purchaser may provide on Supplier’s request, particulars/
information / or documentation that may be required by the
Supplier for proper planning and execution of Scope of Work
under this contract.
12.6 Purchaser shall provide to the Supplier sitting space and
infrastructure and utilities, in the Purchaser’s offices at such
location as may be mutually decided by the Parties.
13. Contract Price 13.1 The Contract Price shall be as specified in the Agreement
subject to any additions and adjustments thereto, or
deductions there from, as may be made pursuant to the
Contract as also subject to provisions of Clause 13.2.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 115
CESU, Odisha Page 115 Release Date: 27th February 2016
13.2 Prices charged by the Supplier for the Goods delivered and the
Related Services performed under the Contract shall not vary
from the prices quoted by the Supplier in its bid, with the
exception of any price adjustments authorized in the SCC.
14. Terms of
Payment
14.1 The Contract Price shall be paid in the manner specified in the
SCC. No invoice for extra work/change order on account of
change order will be submitted by the Supplier unless the said
extra work /change order has been authorized/approved by
the Purchaser in writing.
14.2 The Supplier’s request for payment shall be made to the
Purchaser in writing, accompanied by invoices describing, as
appropriate, the Goods delivered and Related Services
performed, accompanied by the documents submitted
pursuant to GCC Clause 10.
14.3 Payments shall be made promptly by the Purchaser, no later
than forty five (45) days after submission of an invoice or
request for payment by the Supplier, and the Purchaser has
accepted it.
14.4 If any excess payment has been made by the Purchaser due to
difference in quoted price in proposal and Supplier’s invoice,
the purchaser may without prejudice to its rights recover such
amounts by other means after notifying the Supplier or deduct
such excess payment from any payment subsequently falling
due to the Supplier.
14.5 The currency in which payment shall be made to the supplier
under this contract is Indian Rupees (INR).
15. Taxes and
Duties
15.1 The prices quoted by the supplier shall be inclusive of all
duties/taxes/levies. Responsibility for including all applicable
taxes/duties/levies in the proposal lie with the bidder and the
utility shall not be responsible for any error/omission on the
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 116
CESU, Odisha Page 116 Release Date: 27th February 2016
part of the bidder. Payment of taxes/duties/levies shall not be
made separately.
15.2 For goods supplied from outside the Purchaser’s country, the
Supplier shall be entirely responsible for all taxes, duties,
stamp duties, license fees, and other such levies imposed
outside the Purchaser’s country.
15.3 For goods supplied from within the Purchaser’s country, the
Supplier shall be entirely responsible for all taxes, duties, entry
tax, license fees, other levies etc, incurred until delivery of the
Goods and Related service to the Purchaser. The Purchaser
will provide Central sales tax Form C, whenever applicable.
15.4 The cost of Entry Tax as applicable will be the liability of the
Supplier i.e. the price quoted will be inclusive of Entry Tax.
The amount of Entry Tax will be deducted from the Supplier’s
invoice and remittance to tax dept. will be made by the
Purchaser under the TIN number of Purchaser. If any liability
is raised by the commercial tax department, Govt. of Odisha
on account of Entry Tax at a later date, the same shall be to
the Supplier's account and accordingly recovery shall be made
from the supplier's pending bills/security deposit as available
with the Purchaser.
16. Performance
Security
16.1 The Supplier shall, within fourteen (14) days of the notification
of Contract award, provide a Performance Security for the due
performance of the Contract in the amounts and currencies
specified in the SCC.
16.2 The Purchaser shall at its sole discretion invoke the Performance
Security and appropriate the amount secured thereunder, in the
event that the Supplier commits any delay or default in Delivery
of the Goods or Related Services or commits any other breach of
the terms and conditions of the Contract.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 117
CESU, Odisha Page 117 Release Date: 27th February 2016
16.3 The Performance Security shall be denominated in the
currencies of the Contract, and shall be in one of the forms
stipulated by the Purchaser in the SCC.
16.4 The Performance Security shall be discharged by the
Purchaser and returned to the Supplier not later than fourteen
(14) days following the date of completion of the Supplier’s
performance obligations including FMS under the Contract,
including any warranty obligations, unless specified otherwise
in the SCC.
17. Intellectual
Property
17.1 Purchaser shall own and have a right in perpetuity to use all
newly created Intellectual Property Rights which have been
developed solely during execution of this Contract, including
but not limited to all Source code, Object code, records,
reports, designs, application configurations, data and written
material, products, specifications, reports, drawings and other
documents which have been newly created and developed by
the Supplier solely during the performance of Related
Services and for the purposes of inter-alia use or sub-license
of such Services under this Contract. The Supplier undertakes
to disclose all such Intellectual Property Rights arising in
performance of the Related Services to the Purchaser and
execute all such agreements/documents and file all relevant
applications, effect transfers and obtain all permits and
approvals that may be necessary in this regard to effectively
transfer and conserve the Intellectual Property Rights of the
Purchaser. To the extent that Intellectual Property Rights are
unable by law to so vest, the Supplier assigns those
Intellectual Property Rights to Purchaser on creation.
17.2 The Supplier shall be obliged to ensure that all approvals,
registrations, licenses, permits and rights etc. which are inter-
alia necessary for use of the goods supplied / installed by the
Supplier, the same shall be acquired in the name of the
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 118
CESU, Odisha Page 118 Release Date: 27th February 2016
Purchaser, and the same may be assigned by the Purchaser
to the Supplier solely for the purpose of execution of any of its
obligations under the terms of this Contract. However,
subsequent to the term of this Contract, such approvals,
registrations, licenses, permits and rights etc. shall endure to
the exclusive benefit of the Purchaser.
17.3 The Supplier shall ensure that while it uses any software,
hardware, processes, document or material in the course of
performing the Services, it does not infringe the Intellectual
Property Rights of any person and the Supplier shall keep the
Purchaser indemnified against all costs, expenses and
liabilities howsoever, arising out any illegal or unauthorized
use (piracy) or in connection with any claim or proceedings
relating to any breach or violation of any permission/license
terms or infringement of any Intellectual Property Rights by the
Supplier or its personnel during the course of performance of
the Related Services. In case of any infringement by the
Supplier, the Supplier shall have sole control of the defense
and all related settlement negotiations
17.4 Subject to sub-clauses 17.1 to 17.3, the Supplier shall retain
exclusive ownership of all methods, concepts, algorithms,
trade secrets, software documentation, other intellectual
property or other information belonging to the Supplier that
existed before the effective date of the contract. .
18. Confidential
Information
18.1 Both parties undertake to each other to keep confidential all
information (written as well as oral) concerning the business
and affairs of the other, which has been obtained or received
as a result of the discussions leading upto or the entering of
the contract
18.2 After the entering of the contract the Purchaser and the
Supplier shall keep confidential and shall not, without the
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 119
CESU, Odisha Page 119 Release Date: 27th February 2016
written consent of the other party hereto, divulge to any third
party any documents, data, or other information furnished
directly or indirectly by the other party hereto in connection
with the Contract, whether such information has been
furnished prior to, during or following completion or termination
of the Contract. Notwithstanding the above, the Supplier may
furnish to its Subcontractor such documents, data, and other
information it receives from the Purchaser to the extent
required for the Subcontractor to perform its work under the
Contract, in which event the Supplier shall obtain from such
Subcontractor an undertaking of confidentiality similar to that
imposed on the Supplier under this Clause.
18.3 The Purchaser shall not use such documents, data, and other
information received from the Supplier for any purposes
unrelated to the Contract. Similarly, the Supplier shall not use
such documents, data, and other information received from
the Purchaser for any purpose other than the design,
procurement, or other work and services required for the
performance of the Contract.
18.4 The obligation of a party under GCC Sub-Clauses 18.1 and
18.2 above, however, shall not apply to information that:
(a) the Purchaser or Supplier need to share with the institutions
participating in the financing of the Contract;
(b) now or hereafter enters the public domain through no fault of
that party;
(c) can be proven to have been possessed by that party at the
time of disclosure and which was not previously obtained,
directly or indirectly, from the other party; or
(d) Otherwise lawfully becomes available to that party from a
third party that has no obligation of confidentiality.
18.5 The above provisions of GCC Clause 18 shall not in any way
modify any undertaking of confidentiality given by either of the
parties hereto prior to the date of the Contract in respect of the
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 120
CESU, Odisha Page 120 Release Date: 27th February 2016
Supply or any part thereof.
18.6 Each of the parties to this contract, undertakes to the other to
take all such steps as shall from time to time be necessary to
ensure compliance with the provisions of the above clauses by
it’s employees, agents and sub-contractors.
18.7 The provisions of GCC Clause 18 shall survive completion or
termination, for whatever reason, of the Contract.
19. Subcontracting 19.1 Except as provided hereunder under Clause 19.2 of the GCC,
the Supplier shall not be permitted to sub-contract any part of
its obligations under the Contract.
19.2 Supplier shall sub-contract the Network solution provider (NSP)
role and GIS solution provider (GSP) role only from the
empanelled members (as per the list issued/updated by the
Nodal Agency). Supplier shall have flexibility to subcontract
Meter Data Acquisition Solution Provider (MDASP) role, as
per his requirement. In case Supplier decides to subcontract
MDASP role, the MDASP subcontractor shall only be selected
from the empanelled list of MDASP (as per the list
issued/updated by the Nodal Agency).
19.3 The Supplier shall select the sub-contractors from the
empanelled list only. The names and roles of the same shall
be clearly mentioned in the proposal/bid.
19.4 The Supplier shall ensure that the sub-contractor appointed has
sufficient capacity to undertake the execution of the tasks they
will perform under this Contract.
19.5 The Supplier indemnifies and shall keep indemnified Purchaser
against any losses, damages, claims or such other
implications arising from or out of the acts and omissions of
such subcontractor. The Supplier shall be responsible for
making all payments to the subcontractor as may be
necessary, in respect of any Services performed or task
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 121
CESU, Odisha Page 121 Release Date: 27th February 2016
executed, and the Purchaser shall not be responsible for any
part or full payment which is to due to such subcontractor.
19.6 All rights of use of any process, product, service or facility
developed or any other task performed by the subcontractor
for the Supplier, under this contract would lie exclusively with
the Purchaser in perpetuity free from all liens, encumbrances
and other third party rights and the Supplier shall, wherever
required, take all steps that may be necessary to ensure the
transfer of such ownership in favor of the Purchaser.
19.7 Nothing in this clause 19 of the GCC shall relieve the Supplier
from its any of its liabilities or obligations under this Contract.
The Purchaser reserves the right to hold Supplier liable for
any act/omission of any subcontractor.
19.8 Where the Purchaser deems necessary, it shall have the right
to require replacement of any subcontractor with another
subcontractor and the Supplier shall in such case terminate
forthwith all agreements/contracts other arrangements with
such subcontractor and find suitable replacement for such
subcontractor to the satisfaction of the Purchaser at no
additional charge, from the empanelled list (as per the list
issued/updated by the Nodal Agency). Failure to terminate all
agreements/contracts with such sub-contractors, shall amount
to a breach of the terms hereof.
19.9 The Supplier shall be responsible for ensuring that the
Subcontractor shall comply with all relevant and applicable
provisions of the Contract. In default on the part of the sub-
contractor to comply with the terms and conditions of the
Contract wherever applicable, shall amount to breach on the
part of the Supplier, and the Purchaser in addition to all other
rights, have the right to claim damages add recover from the
Supplier all losses/ or other damages that may have resulted
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 122
CESU, Odisha Page 122 Release Date: 27th February 2016
from such failure
20. Specifications
and Standards
20.1 Technical Specifications and Drawings
(a) The Supplier shall ensure that the Goods and Related
Services comply with the technical specifications and other
provisions of the Contract.
(b) The Supplier shall be entitled to disclaim responsibility for
any design, data, drawing, specification or other document, or
any modification thereof provided or designed by or on behalf
of the Purchaser, by giving a notice of such disclaimer to the
Purchaser.
(c) The Goods and Related Services supplied under this
Contract shall conform to the standards mentioned in Section
VI, Scope of Work and, when no applicable standard is
mentioned, the standard shall be equivalent or superior to the
official standards whose application is appropriate to the
country of origin of the Goods.
20.2 Wherever references are made in the Contract to codes and
standards in accordance with which it shall be executed, the
edition or the revised version of such codes and standards
shall be those specified in the Section VI, Scope of Work.
During Contract execution, any changes in any such codes
and standards shall be applied only after approval by the
Purchaser and shall be treated in accordance with GCC
Clause 31.
21. Packing and
Documents
21.1 The Supplier shall provide such packing of the Goods as is
required to prevent their damage or deterioration during transit
to their final destination, as indicated in the Contract. During
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 123
CESU, Odisha Page 123 Release Date: 27th February 2016
transit, the packing shall be sufficient to withstand, without
limitation, rough handling and exposure to extreme
temperatures, salt and precipitation, and open storage.
Packing case size and weights shall take into consideration,
where appropriate, the remoteness of the final destination of
the Goods and the absence of heavy handling facilities at all
points in transit. The Purchaser shall not be responsible in any
manner for any loss or damage caused to the Goods during
Transit.
21.2 The packing, marking, and documentation within and outside
the packages shall comply strictly with such special
requirements as shall be expressly provided for in the
Contract and in any other instructions ordered by the
Purchaser.
22. Insurance 22.1 The Goods supplied under the Contract shall be fully insured by
the Supplier, in INR, against loss or damage incidental to
manufacture or acquisition, transportation, storage, and
delivery, in accordance with the applicable Incoterms or in the
manner specified in the SCC.
23. Transportation 23.1 Obligations for transportation of the Goods shall be borne by
the Supplier and shall be in accordance with the Incoterms
specified in Sections VI, Schedule of Supply.
24. Inspections and
Tests
24.1 The Supplier shall at its own expense and at no cost to the
Purchaser carry out all such tests and/or inspections of to
ensure that the Goods and Related Services are complying
with the functional parameters, codes and standards specified
in the Scope of Work at Section VI, to the satisfaction of the
Purchaser.
24.2 The inspections and tests may be conducted on the premises
of the Supplier, at point of delivery, and/or at the final
destination of the Goods, or in another place in the
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 124
CESU, Odisha Page 124 Release Date: 27th February 2016
Purchaser’s country as per the requirement of Section VI.
Subject to GCC Sub-Clause 24.3, if conducted on the
premises of the Supplier or its Subcontractor, all reasonable
facilities and assistance, including access to drawings and
production data, shall be furnished to the inspectors at no
charge to the Purchaser.
24.3 The Purchaser or its designated representative shall be entitled
to attend the tests and/or inspections referred to in GCC Sub-
Clause 24.2, provided that the Purchaser bear all of its own
costs and expenses incurred in connection with such
attendance including, but not limited to, all traveling and board
and lodging expenses.
24.4 Whenever the Supplier is ready to carry out any such test and
inspection, it shall give a reasonable advance notice, including
the place and time, to the Purchaser.
24.5 The Purchaser may require the Supplier to carry out any test
and/or inspection to verify that the characteristics and
performance of the Goods or Related Services comply with
the technical specifications, codes and standards under the
Contract.
24.6 The Supplier shall provide the Purchaser with a report of the
results of any such test and/or inspection.
24.7 The Purchaser may reject any Goods / Related Services or any
part thereof that fail to pass any test and/or inspection or do
not conform to the specifications. The Supplier shall either
rectify or replace such rejected Goods/ Related Services or
parts thereof or make alterations necessary to meet the
specifications at no cost to the Purchaser, and shall repeat the
test and/or inspection, at no cost to the Purchaser, upon giving
a notice pursuant to GCC Sub-Clause 24.4.
24.8 The Supplier agrees that neither the execution of a test and/or
inspection of the Goods / Related Services or any part thereof,
nor the attendance by the Purchaser or its representative, nor
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 125
CESU, Odisha Page 125 Release Date: 27th February 2016
the issue of any report pursuant to GCC Sub-Clause 24.6,
shall release the Supplier from any warranties or other
obligations under the Contract.
25. Liquidated
Damages and
Penalty
25.1 Except as provided under GCC Clause 30, if the Supplier fails
to deliver any or all of the Goods or perform the Related
Services within the period specified in the Contract, the
Purchaser may without prejudice to all its other remedies
under the Contract, deduct from the Contract Price, as
liquidated damages, a sum equivalent to 0.5% of the value of
the Goods or Related Services, supplied beyond stipulated
delivery schedule for each week or part thereof of delay until
actual delivery or performance, subject to a maximum of 10%
of value of such goods and services.
25.2 In addition, the Supplier is liable to the Purchaser for payment
penalty as specified in the SLA.
25.3 If the Goods and Related Services supplied do not meet the
minimum specifications as per the Contract, and the same is
not replaced/modified by the Supplier to meet the
requirements within 14 days of being informed by the Utility,
the Utility shall be free to impose any penalty as deemed fit. In
addition, the Utility shall reserve the right to terminate the
contract and recover liquidated damages by forfeiting the
performance guarantee submitted by the Purchaser.
26. Warranty 26.1 The Supplier warrants that all the Goods are new, unused, and
of the most recent or current models, and that they incorporate
all recent improvements in design and materials, unless
provided otherwise in the Contract.
26.2 Subject to GCC Sub-Clause 20.1, the Supplier further warrants
that the Goods shall be free from defects arising from any act
or omission of the Supplier or arising from design, materials,
and workmanship, under normal use in the conditions
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 126
CESU, Odisha Page 126 Release Date: 27th February 2016
prevailing in the country of final destination.
26.3 The warranty shall remain valid for the period Specified in the
SCC.
26.4 The Purchaser shall give Notice to the Supplier stating the
nature of any such defects together with all available evidence
thereof, promptly following the discovery thereof. The
Purchaser shall afford all reasonable opportunity for the
Supplier to inspect such defects.
26.5 Upon receipt of such Notice, the Supplier shall, within the
period specified in the SCC, expeditiously repair or replace the
defective Goods or parts thereof, at no cost to the Purchaser.
26.6 If having been notified, the Supplier fails to remedy the defect
within the period of warranty specified in the SCC; the
Purchaser may proceed to take within a reasonable period
such remedial action as may be necessary, at the Supplier’s
risk and expense and without prejudice to any other rights
which the Purchaser may have against the Supplier under the
Contract.
27. Liability/
Indemnity
27.1 The Supplier hereby agrees to indemnify the Purchaser, for all
conditions and situations mentioned in this clause, in a form
and manner acceptable to the Purchaser. The supplier agrees
to indemnify the Purchaser and its officers, servants, agents
(“Purchaser Indemnified Persons”) from and against any
costs, loss, damages, expense, claims including those from
third parties or liabilities of any kind howsoever suffered,
arising or incurred inter alia during and after the Contract
period out of:
(a) any negligence or wrongful act or omission by the
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 127
CESU, Odisha Page 127 Release Date: 27th February 2016
Supplier or its agents or employees or any third party
associated with Supplier in connection with or incidental
to this Contract; or
(b) any infringement of patent, trademark/copyright or
industrial design rights arising from the use of the
supplied Goods and Related Services or any part thereof.
27.2 The Supplier shall also indemnify the Purchaser against any
privilege, claim or assertion made by third party with respect
to right or interest in, ownership, mortgage or disposal of any
asset, property, movable or immovable as mentioned in any
Intellectual Property Rights, licenses and permits
27.3 Without limiting the generality of the provisions of this
clause 27.1 and 27.2, the Supplier shall fully indemnify, hold
harmless and defend the Purchaser Indemnified Persons from
and against any and all suits, proceedings, actions, claims,
demands, liabilities and damages which the Purchaser
Indemnified Persons may hereafter suffer, or pay by reason of
any demands, claims, suits or proceedings arising out of
claims of infringement of any domestic or foreign patent rights,
copyrights or other intellectual property, proprietary or
confidentiality rights with respect to any Goods, Related
Services, information, design or process supplied or used by
the Supplier in performing the Supplier’s obligations or in any
way incorporated in or related to the Project. If in any such
suit, action, claim or proceedings, a temporary restraint order
or preliminary injunction is granted, the Supplier shall make
every reasonable effort, by giving a satisfactory bond or
otherwise, to secure the suspension of the injunction or
restraint order. If, in any such suit, action, claim or
proceedings, the Goods or Related Services, or any part
thereof or comprised therein, is held to constitute an
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 128
CESU, Odisha Page 128 Release Date: 27th February 2016
infringement and its use is permanently enjoined, the Supplier
shall promptly make every reasonable effort to secure for the
Purchaser a license, at no cost to the Purchaser, authorizing
continued use of the infringing work. If the Supplier is unable
to secure such license within a reasonable time, the Supplier
shall, at its own expense, and without impairing the
specifications and standards, either replace the affected work,
or part, or process thereof with non-infringing work or part or
process, or modify the same so that it becomes non-infringing.
Survival on Termination
The provisions of this Clause 27 shall survive Termination.
27.4 Defense of Claims:
(a) If any proceedings are brought or any claim is made
against the Purchaser arising out of the matters referred
to in GCC Sub-Clause 27.1, 27.2, or 27.3 the Purchaser
shall promptly give the Supplier a notice thereof, and
the Supplier may at its own expense and in the
Purchaser’s name conduct such proceedings or claim
and any negotiations for the settlement of any such
proceedings or claim.
(b) If the Supplier fails to notify the Purchaser within
twenty-eight (28) days after receipt of such notice that it
intends to conduct any such proceedings or claim, then
the Purchaser shall be free to conduct the same on its
own behalf
(c) The Purchaser shall, at the Supplier’s request,
afford all available assistance to the Supplier in
conducting such proceedings or claim, and shall be
reimbursed by the Supplier for all reasonable expenses
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 129
CESU, Odisha Page 129 Release Date: 27th February 2016
incurred in so doing
28. Limitation of
Liability
28.1 Except in cases of gross negligence or willful misconduct :
(a) neither party shall be liable to the other party for any
indirect or consequential loss or damage, loss of use,
loss of production, or loss of profits or interest costs,
provided that this exclusion shall not apply to any
obligation of the Supplier to pay liquidated damages to
the Purchaser; and
(b) the aggregate liability of the Supplier to the
Purchaser, whether under the Contract, in tort, or
otherwise, shall not exceed the amount specified in the
Contract Price. Provided that this limitation shall not
apply to the cost of repairing or replacing defective
equipment, or to any obligation of the Supplier to
indemnify the Purchaser with respect to patent
infringement.
29. Change in Laws
and Regulations
29.1 Unless otherwise specified in the Contract, if after the date of
the Invitation for Bids, any law, regulation, ordinance, order or
bylaw having the force of law is enacted, promulgated,
abrogated, or changed in the place of the Purchaser’s country
where the Site is located (which shall be deemed to include
any change in interpretation or application by the competent
authorities) that subsequently affects the Delivery Date, then
such Delivery Date shall be correspondingly increased or
decreased, to the extent that the Supplier has thereby been
affected in the performance of any of its obligations under the
Contract.
30. Force Majeure 30.1 The Supplier shall not be liable for forfeiture of its Performance
Security, liquidated damages, or termination for default if and
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 130
CESU, Odisha Page 130 Release Date: 27th February 2016
to the extent that it’s delay in performance or other failure to
perform its obligations under the Contract is the result of an
event of Force Majeure.
30.2 For purposes of this Clause, “Force Majeure” means an event
or situation beyond the control of the Supplier that is not
foreseeable, is unavoidable, and its origin is not due to
negligence or lack of care on the part of the Supplier. Such
events may include, but not be limited to wars or revolutions,
earthquake, fires, floods, epidemics, quarantine restrictions,
and freight embargoes.
30.3 If a Force Majeure situation arises, the Supplier shall promptly
and no later than seven days from the first occurrence thereof,
notify the Purchaser in writing of such condition and the cause
thereof. Unless otherwise directed by the Purchaser in
writing, the Supplier shall continue to perform its obligations
under the Contract as far as is reasonably practical, and shall
seek all reasonable alternative means for performance not
prevented by the Force Majeure event
30.4 The decision of the Purchaser with regard to the occurrence,
continuation, period or extent of Force Majeure shall be final
and binding on the Supplier.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 131
CESU, Odisha Page 131 Release Date: 27th February 2016
31. Change Orders
and Contract
Amendments
31.1 The Purchaser may at any time order the Supplier through
Notice in accordance GCC Clause 6, (“Change Order”) to
make changes within the general scope of the Contract in any
one or more of the following:
(a) drawings, designs, or specifications, where Goods to be
furnished under the Contract are to be specifically
manufactured for the Purchaser;
(b) Specifications for hardware, software and Related Services
(c) the method of shipment or packing;
(d) the place of delivery; and
(e) the Related Services to be provided by the Supplier.
31.2 If any such Change Order causes an increase or decrease in
the cost of, or the time required for, the Supplier’s
performance of any provisions under the Contract, an
equitable adjustment shall be made in the Contract Price or in
the Delivery and Completion Schedule, or both, and the
Contract shall accordingly be amended. Any claims by the
Supplier for adjustment under this Clause must be asserted
within twenty-eight (28) days from the date of the Supplier’s
receipt of the Purchaser’s Change Order.
31.3 No variation or modification of the terms of the contract shall be
made except by written amendment signed by the parties.
32. Extensions of
Time
32.1 If at any time during performance of the Contract, the Supplier
or its Subcontractors should encounter conditions impeding
timely delivery of the Goods or completion of Related Services
pursuant to GCC Clause 10, the Supplier shall promptly notify
the Purchaser in writing of the delay, its likely duration, and its
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 132
CESU, Odisha Page 132 Release Date: 27th February 2016
cause. As soon as practicable after receipt of the Supplier’s
notice, the Purchaser shall evaluate the situation and may at
its discretion extend the Supplier’s time for performance, in
which case the extension shall be ratified by the parties by
amendment of the Contract.
32.2 Except in case of Force Majeure, as provided under GCC
Clause 30 or where the delay in delivery of the Goods or
completion of Related Services is caused due to any delay or
default of the Purchaser, any extension granted under clause
32.1 shall not absolve the Supplier from its liability to the pay
of liquidated damages pursuant to GCC Clause 25.
33. Termination 33.1 Termination for Default
(a) The Purchaser may, without prejudice to any other
remedy for breach of Contract, by Notice of default sent
to the Supplier, terminate the Contract in whole or in
part:
(i) if the Supplier fails to deliver any or all of the
Goods or Related Services within the period
specified in the Contract, or within any extension
thereof granted by the Purchaser pursuant to
GCC Clause 32; or
(ii) if the Supplier, in the judgment of the Purchaser
has engaged in corrupt, fraudulent, collusive, or
coercive practices, as defined in GCC Clause 2,
in competing for or in executing the Contract; or
(iii) Any representation made by the bidder in the
proposal is found to be false or misleading
(iv) if the Supplier commits any breach of the
Contract and fails to remedy or rectify the same
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 133
CESU, Odisha Page 133 Release Date: 27th February 2016
within the period of two weeks (or such longer
period as the Purchaser in its absolute discretion
decide) provided in a notice in this behalf from
the Purchaser.
(v) as specified in the SLA
(b) In the event the Purchaser terminates the Contract in
whole or in part, pursuant to GCC Clause 33.1.1, the
Purchaser may procure, upon such terms and in such
manner as it deems appropriate, Goods or Related
Services similar to those undelivered or not performed,
and the Supplier shall be liable to the Purchaser for any
additional costs for such similar Goods or Related
Services. However, the Supplier shall continue
performance of the Contract to the extent not
terminated.
33.2 Termination for Insolvency
The Purchaser may at any time terminate the Contract by
giving Notice to the Supplier if the Supplier becomes bankrupt
or otherwise insolvent. In such event, termination will be
without compensation to the Supplier, provided that such
termination will not prejudice or affect any right of action or
remedy that has accrued or will accrue thereafter to the
Purchaser.
33.3 Termination for Convenience
(a) The Purchaser, by Notice sent to the Supplier, may
terminate the Contract, in whole or in part, at any time
for its convenience. The Notice of termination shall
specify that termination is for the Purchaser’s
convenience, the extent to which performance of the
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 134
CESU, Odisha Page 134 Release Date: 27th February 2016
Supplier under the Contract is terminated, and the date
upon which such termination becomes effective.
(b) The Goods that are complete and ready for shipment
within twenty-eight (28) days after the Supplier’s receipt
of the Notice of termination shall be accepted by the
Purchaser at the Contract terms and prices. For the
remaining Goods, the Purchaser may elect:
(i) To have any portion completed and delivered at the Contract
terms and prices; and/or
(ii) to cancel the remainder and pay to the Supplier an agreed
amount for partially completed Goods and Related Services and for
materials and parts previously procured by the Supplier.
33.4 Consequences of Termination
Upon Termination of the Contract, the Supplier shall:
(i) Prepare and present a detailed exit plan within five
calendar days of termination notice receipt to the IT Head
/ CIO of CESU (“Exit Plan”).
(ii) The IT Head / CIO and along with designated team will
review the Exit plan. If approved, Supplier shall start
working on the same immediately. If the plan is rejected,
Supplier shall prepare alternate plan within two calendar
days. If the second plan is also rejected, the IT Head
/CIO or the authorized person will provide a plan for
Supplier and it should be adhered by in totality.
(iii) The Exit Plan should cover at least the following :-
a. Execute all documents that may be necessary to
effectively transfer the ownership and title, including
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 135
CESU, Odisha Page 135 Release Date: 27th February 2016
OEM warranties in respect of all equipment;
b. Handover all developed codes, related documentation
and other Configurable Items, if any in his
possession;
c. Handover the list of all IT Assets, passwords at all
locations to the Purchaser.
(iv) The supplier and the IT Head /CIO (or the authorized
person) will sign a completion certificate at the end of
successful completion (all points tracked to closure) of
the Exit Plan.
34. Assignment 34.1 The Supplier shall not assign, in whole or in part, their
obligations under this Contract.
35. Disclaimer 35.1 Purchaser reserves the right to share, with any consultant of its
choosing, any resultant Proposals in order to secure expert
opinion.
35.2 Purchaser reserves the right to accept any proposal deemed to
be in the best interest of the CESU
36. Public
Disclosure
36.1 All materials provided to the Purchaser by bidder are subject to
Country and Odisha public disclosure laws such as RTI etc.
36.2 The Supplier’s Team shall not make or permit to be made a
public announcement or media release about any aspect of
this Contract unless the Purchaser first gives the Supplier its
written consent.
37. SLA Audit 37.1 A designated team / person from CESU will review the
performance of Supplier against the SLA each month. The
review / audit report will form basis of any action relating to
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 136
CESU, Odisha Page 136 Release Date: 27th February 2016
imposing penalty on or breach of contract of the Supplier.
38. Adherence to
safety
procedures, rules
regulations and
restriction
38.1 Supplier shall comply with the provision of all laws including
labour laws, rules, regulations and notifications issued there
under from time to time. All safety and labour laws enforced by
statutory agencies and by Purchaser shall be applicable in the
performance of this Contract and Supplier’s Team shall abide
by these laws.
38.2 Access to the Datacenter Sites and Purchaser’s locations shall
be strictly restricted. No access to any person except the
essential personnel belonging to the Supplier who are
genuinely required for execution of work or for carrying out
management/maintenance who have been explicitly
authorized by the Purchaser shall be allowed entry to the
Datacenter Sites and some Purchaser’s locations. Even if
allowed, access shall be restricted to the pertaining equipment
of the Purchaser only. The Supplier shall maintain a log of all
activities carried out by each of its personnel.
38.3 The Supplier shall take all measures necessary or proper to
protect the personnel, work and facilities and shall observe all
reasonable safety rules and instructions. Supplier’s Team
shall adhere to all security requirement/regulations of the
Purchaser during the execution of the work. Purchaser’s
employee also shall comply with safety procedures/policy.
38.4 The Supplier shall report as soon as possible any evidence,
which may indicate or is likely to lead to an abnormal or
dangerous situation and shall take all necessary emergency
control steps to avoid such abnormal situations.
38.5 The Purchaser will be indemnified for all the situations
mentioned in this clause in the similar way as defined in GCC
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 137
CESU, Odisha Page 137 Release Date: 27th February 2016
clause 28.
39. Non-Solicitation
of Staff
39.1 For the purpose of this contract, both parties to this contract
agree, not to solicit either directly or indirectly with a view to
provide or offer employment to, offer to contract with or entice
a staff member of the other party to leave without the consent
of the other during the term of this agreement and for an
additional period of 180 days after termination
40. Survival 40.1 The clauses of this contract, which by nature are intended to
survive termination of this contract, shall remain in effect after
such termination
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 138
CESU, Odisha Page 138 Release Date: 27th February 2016
Section VIII. Special Conditions of Contract
The following Special Conditions of Contract (SCC) shall supplement the General Conditions of
Contract (GCC). Whenever there is a conflict, the provisions herein shall prevail over those in the
GCC.
GCC 1.1(j) The Purchaser’s country is: The Union Of India
GCC 1.1(k) The Purchaser is:
CESU of Odisha, India
GCC 1.1 (q) The web-sites are: www.cescoorissa.com/ www.cesuodisha.com
The details regarding the RFP process shall be available on the same. The eligible
bidders should visit the website from time to time and get the status updates. All
details uploaded on the website from time to time shall be deemed to have been
provided to all the bidders.
GCC 3.2 The version of Incoterms shall be: Incoterms 2000
GCC 4.1 The language shall be: English
GCC 6.1 For notices, the Purchaser’s contact details shall be:
Senior General Manager (IT),
Central Electricity Supply Utility of Odisha,
8th Floor, IDCO Towers, Janpath, Bhubaneswar -751 022 Odisha
Phone No. - 0674-2545685 Fax No. - 0674-2543125
Email : [email protected]
GCC 7.1 The governing law shall be: Laws applicable in exclusive jurisdiction of The High
Court Of Judicature at Odisha High Court, Cuttack, India and all courts
subordinate to it’s exclusive Jurisdiction.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 139
CESU, Odisha Page 139 Release Date: 27th February 2016
GCC 8.2 The formal mechanism for the resolution of disputes shall be:
If the parties fail to resolve such a dispute or difference by mutual consultation
within twenty-eight (28) days from the commencement of such dispute and
difference, either party may require that the dispute be referred for resolution to the
formal mechanisms, described below (The date of commencement of the dispute
shall be taken from the date when this clause reference is quoted by either party in
a formal communication clearly mentioning existence of dispute or as mutually
agreed) :
a. The mechanism for resolution of disputes for bidders shall be in accordance
with the Indian Arbitration and Conciliation Act of 1996. The Arbitral Tribunal
shall consist of 3 (Three) Arbitrators. Each Party shall nominate an
Arbitrator and the two nominated Arbitrators shall mutually agree and
nominate a third Presiding Arbitrator.
b. The Arbitrators shall necessarily be retired High Court Judges and the
umpire shall be a retired Chief Justice.
c. The place for arbitration shall be Bhubaneswar, Odisha
GCC 10.1
Details of shipping and documents to be furnished by the Supplier shall be:
FOR GOODS SUPPLIED FROM ABROAD AS PER INCOTERMS CIF :
Upon shipment, the Supplier shall notify the Purchaser and the Insurance Company
by telex or fax the full details of the shipment (Consignment through air is also
possible), including Contract number, description of Goods, quantity, the vessel,
the bill of lading number and date, port of loading, date of shipment, port of
discharge, etc. The Supplier shall send the following documents to the Purchaser,
with a copy to the Insurance Company.
(a) Copy of the Supplier’s invoice showing the description of the Goods, quantity,
unit CIF price and total amount;
(b) Copy of on-board bill of lading marked “freight prepaid”.
(c) Copy of the packing list identifying contents of each lot.
(d) Insurance certificate;
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 140
CESU, Odisha Page 140 Release Date: 27th February 2016
(e) Copy of test certificate approval and dispatch instructions issued by the
purchaser (combined or separately).
(f) Certificate of Origin.
(g) Manufacturer’s or supplier’s Warranty Certificate
The Purchaser shall receive the above documents at least two weeks before arrival
of the Goods at the port or place of arrival and, if not received, the Supplier will be
responsible for any consequent expenses.
For goods from within the Purchaser’s country as per INCOTERMS EXW
basis including freight and insurance charges:
Upon delivery of the Goods to the transporter, the Supplier shall notify the
Purchaser and send the following documents to the Purchaser;
a) Copy of the Supplier’s invoice showing the description of the Goods, quantity,
unit Ex-works price and total amount;
b) Copy of Motor Transport Receipt (MTR) of a transport contractor approved by
Indian Bankers Association or material receipt certificate from consignee.
c) Copy of test certificate approval and dispatch instructions issued by the
purchaser combined or separately.
d) Copy of packing list identifying contents of each lot.
e) Insurance certificate;
f) Certificate of Origin.
g) Manufacturer’s or supplier’s Warranty Certificate
The Purchaser shall receive the above documents before the arrival of the Goods
and, if not received, the Supplier will be responsible for any consequent expenses.
GCC 13.2 The price adjustment shall be:
The bidders may please note that the prices are upward/downward Adjustable.
Purchaser reserves the right to review and negotiate the charges payable at any
time to incorporate downward revisions as applicable and necessary, including due
to lowering of any applicable taxes, duties and any other statutory levies.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 141
CESU, Odisha Page 141 Release Date: 27th February 2016
Prices shall not be subject to any upward/downward revision on any account
whatsoever throughout the period of contract. Provided that any revision in taxes,
statutory levies, duties which is not occasioned due to any change in place, method
and time of supply or non-performance / non-fulfillment of any condition of any
exemption considered by the vendor at the time of proposal, shall be considered for
price adjustments.
The utility reserves the right to increase or decrease the number of towns under the
contract subject to the limit of 30% of the number of towns covered under the
contract. It is clarified that this increase or decrease of 30% shall not entitle either
party to claim revision of the unit price of the goods supplied.
In case of services where lump-sum prices are quoted, the increase or decrease of
30% of the number of towns shall be subject to mutual negotiations.
GCC 14.1 General terms and conditions of Payment Schedule
1) All payments shall be made by the Purchaser in favour of the Supplier
(System Integrator)
2) The release of payments will be Performance (output) based, where the
payments are made for measured deliverables and outputs. The SLAs will
govern the penalty and reductions from payments for inferior deliverables.
3) Payments made under the Contract shall be approved by the MoP in
accordance with the terms and conditions of the financing agreement
between the Purchaser and the MoP, and will be subject in all respects to
the terms and conditions of that financing/Loan Agreement
4) System Integrator should obtain completion certificate for each project area
from the utility and raise an invoice against the same.
5) Payments against invoice submitted (accompanied with all requisite
documents) shall be released within 45 days of submission of invoice.
6) System Integrator needs to ensure completion of all works for a project area
(town). This includes supply of required hardware, software, customization,
installation and commissioning. In addition others activities like field survey,
integration of identified legacy systems etc. shall also be completed.
Payments shall be made town wise based on activity/Milestone achieved. In
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 142
CESU, Odisha Page 142 Release Date: 27th February 2016
case part of the work is pending (applications or hardware or networking
etc.), for the town, payment for that activity/Milestone shall not be made.
7) Cost of setting up the data centre (including all hardware and
implementation cost) should be mentioned separately.
8) In case go-live of any project area/data centre is delayed, the entire cost
and/or time over-run shall be the responsibility of the Supplier and shall be
borne by him only.
9) Power to withhold: Notwithstanding anything contained in the payment
schedule mentioned below, if in the opinion of the Purchaser, any work
done or supply made or service rendered by Supplier is deficient in any
manner in comparison to the prescribed standards, Purchaser shall be at
liberty to withhold a reasonable portion of the payments due to the Supplier,
till such work/ supply/ service is made confirming to the prescribed
standards. These powers to withhold payments shall be without prejudice to
any other power/ right of the purchaser under this contract.
10) All payments for Facilities Management Services (FMS) shall only be made
after submission of the Audit reports (in original) which shall be submitted
by the Supplier along with the invoices and acceptance of the same by the
Purchaser.
Payment Schedule
Phase Activity Payment
Schedule Milestones
Advance
Payment
10 % of Project
Cost (excluding
FMS and
Bandwidth)
On Issuance of Letter
of Award by Utility &
team mobilization by
Vendor
Data Centre
(DC)
Data Centre
Design
5% of cost
quoted for Data
centre
On submission &
approval of High Level
Design, Low Level
Design
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 143
CESU, Odisha Page 143 Release Date: 27th February 2016
Installation,
Commissioning
& Configuration
of Hardware,
Networks &
Operating
System
25% of cost
quoted for Data
centre
On System testing by
Vendor &
management
confirmation that
material is received &
commissioned as per
the Work order
Installation,
Configuration &
Customization
Application
Software
20% of cost
quoted for Data
centre
On System testing by
Vendor &
management
confirmation that
software is installed &
running
User
Acceptance
testing
30% of cost
quoted for Data
centre
15% of Project
management cost
On Management
approval of User
Acceptance testing,
established through
operational
connectivity of project
areas of CESU (utility),
Disaster Recovery
centre, central
customer care centre,
etc. with the data
centre
Disaster
Recovery
Centre (DRC)
Disaster
Recovery
Centre Design
5% of cost
quoted for
Disaster
Recovery centre
On submission &
approval of High Level
Design, Low Level
Design
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 144
CESU, Odisha Page 144 Release Date: 27th February 2016
Installation,
Commissioning
& Configuration
of Hardware,
Networks &
Operating
System
25% of cost
quoted for
Disaster
Recovery centre
On System testing by
Vendor &
management
confirmation that
material is received &
commissioned as per
the Work order
Installation,
Configuration &
Customisation
of Application
Software
20% of cost
quoted for
Disaster
Recovery centre
On System testing by
Vendor &
management
confirmation that
software is installed &
running
User
Acceptance
testing
30% of cost
quoted for
Disaster
Recovery centre
5% of Project
management cost
On Management
approval of User
Acceptance testing,
established through
operational
connectivity of data
centre with the
Disaster Recovery
centre
Customer
Care Centre
(CC)
Customer Care
Centre Design
5% of cost
quoted for
Customer Care
Centre
On submission &
approval of High Level
Design, Low Level
Design
Installation,
Commissioning
& Configuration
of Hardware,
Networks &
Operating
System
25% of cost
quoted for
Customer Care
centre
On System testing by
Vendor &
management
confirmation that
material is received &
commissioned as per
the Work order
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 145
CESU, Odisha Page 145 Release Date: 27th February 2016
Installation,
Configuration,
Customisation &
Customisation
of Application
Software
20% of cost
quoted for
Customer Care
centre
On System testing by
Vendor &
management
confirmation that
software is installed &
running
User
Acceptance
testing
30% of cost
quoted for Data
centre
10% of Project
management cost
On Management
approval of User
Acceptance testing,
established through
operational
connectivity of project
areas with the central
customer care centre,
etc.
Sub-Division
Office
Infrastructure
Design
5% of cost
quoted for SDO
On submission &
approval of High Level
Design, Low Level
Design
DGPS Survey
Results
80% of DGPS
Cost (divided by
number of project
areas covered)
On Submission of
DGPS Survey results
& approval (project
area wise)
Installation,
Commissioning
& Configuration
of Hardware,
Networks &
Operating
System
25% of cost
quoted for SDO
On System testing by
Vendor &
management
confirmation that
material is received &
commissioned as per
the Work order
Installation,
Configuration &
Customisation
of Application
15% of cost
quoted for SDO
On System testing by
Vendor &
management
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 146
CESU, Odisha Page 146 Release Date: 27th February 2016
Software confirmation that
software is installed &
running
Integration with
legacy
applications &
Data Centre
network
5% of cost
quoted for SDO
5% of Project
management cost
On Management
approval that the
systems are integrated
with Data Centre &
legacy apps
User
Acceptance
testing
30 % of cost
quoted for SDO
5% of Project
management cost
On Management
approval of User
Acceptance testing
User Training
5% of Project
management cost
On User Training as
confirmed by
Management
Other offices
Infrastructure
Design
5% of cost
quoted for
individual offices
On submission &
approval of High Level
Design, Low Level
Design
DGPS Survey
Results
80% of DGPS
Cost (divided by
number of project
areas covered)
On Submission of
DGPS Survey results
& approval
Installation,
Commissioning
& Configuration
of Hardware,
Networks &
Operating
System
25% of cost
quoted for
individual offices
On System testing by
Vendor &
management
confirmation that
material is received &
commissioned as per
the Work order
Installation,
Configuration &
Customisation
of Application
15% of cost
quoted for
individual offices
On System testing by
Vendor &
management
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 147
CESU, Odisha Page 147 Release Date: 27th February 2016
Software confirmation that
software is installed &
running
Integration with
legacy
applications &
Data Centre
network
5% of cost
quoted for SDO
5% of Project
management cost
On Management
approval that the
systems are integrated
with Data Centre &
legacy apps
User
Acceptance
testing
30% of cost
quoted for
individual offices
20% of Project
management cost
(divided by
number of offices
covered)
On Management
approval of User
Acceptance testing
User Training
10 % of Project
management cost
(divided by
number of offices
covered)
On User Training as
confirmed by
Management
After
Completion
10 % of Project
Cost (excluding
FMS and
Bandwidth)
After 3 months of Go-
Live date, based on
management
confirmation that
system is meeting the
performance
requirements as
specified in Work order
End of Contract: Payment of the balance 10% of the contract value (except the
FMS cost) will be made after three months of successful running of the system. The
payment may be released earlier provided the supplier submits the Bank
Guarantee (BG) for an amount equivalent to 20% of contract value. This BG shall
remain in force up to and including 6 months after warranty period.
Facilities Management Services: Cost for support and maintenance will be payable
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 148
CESU, Odisha Page 148 Release Date: 27th February 2016
quarterly during the 5 years support and maintenance period from the date of
“Entire utility (CESU) wide rollout – go live date”. Quarterly installments will be
1/20th of the total IT support and maintenance cost. Payments will be subject to the
Audit reports for that quarter. The payment will be with reference to the cost
mentioned in Appendix D.3.
GCC 14.5 The currencies for payments shall be in Indian Rupees (INR).
GCC 16.1 The Supplier shall provide Performance Security of ten (10) percent of the total
Contract Price. The currency and amount of Performance Security shall be
specified at the time of awarding the contract to successful bidder.
However, an additional FMS Performance Bank Guarantee (FMS-PBG) equal to
20% of quoted FMS value shall be submitted by the selected bidder for a period of
5 years starting from beginning of the FMS period to take care of any non-
performance during FMS period. .
GCC 16.3 The Performance Security shall be in the form of Bank Guarantee issued by a
Scheduled Bank as notified by Reserve Bank of India
GCC 21.2 The packing, marking and documentation within and outside the packages if
applicable shall be: As specified (if any) in Technical Specification
GCC 22.1 The insurance coverage: Goods supplied under the contract shall be also fully
insured on all risk basis during inland transit up to destination store in the
purchaser’s country. The supplier must insure the Goods in an amount equal to
110% of CIF/EXW price of Goods.
GCC 26.3 The period of validity of the warranty shall be 36 (Thirty Six) months from the date
of commissioning or 42 (forty two) months from date of delivery at Purchaser’s
stores whichever is earlier.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 149
CESU, Odisha Page 149 Release Date: 27th February 2016
GCC 26.5 In case any damage or defect is found during verification after receipt of material at
Purchaser’s stores or material develops defects within warranty period, the supplier
shall attend/replace such defects free of all charges within 30 days of being notified
by the Purchaser, of the occurrence of such defects. In case the defect is not
attended or replacement of material is not received within specified period, then
apart from encashing the performance security deposit, the Purchaser may also
take suitable penal action including debarring from all future business.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 150
CESU, Odisha Page 150 Release Date: 27th February 2016
Section IX. Contract Forms
1 Agreement
THIS AGREEMENT is made on this ________ (eg. 3rd) day of
________________________(eg. November), _____(eg. 2015), between
______________________________________of __________________________
(hereinafter called “the Purchaser”) which expression shall unless repugnant to the context
thereof include his successors, heirs, assigns, of the one part, and
__________________________________ of ______________________________
(hereinafter called “the Supplier”) which expression shall unless repugnant to the context
thereof include his successors, heirs, assigns, of the other part.
WHEREAS the Purchaser had invited bids for certain Goods and Related Services, viz.,
____________________________________________________________________ (eg.
Name of bid) vide their bid document number
__________________________________________, dated _______________
AND WHEREAS various applications were received pursuant to the said bid
AND WHEREAS the Purchaser has accepted a Bid by the Supplier for the supply of those
Goods and Related Services in the sum of
________________________________________________________ (hereinafter “the
Contract Price”).
And in pursuance of having accepted the said bid the parties have agreed to enter into this
agreement.
NOW THIS AGREEMENT WITNESSETH AS FOLLOWS:
1. In this Agreement words and expressions shall have the same meanings as are
respectively assigned to them in the Contract referred to.
2. The following documents (collectively referred to as “Contract Documents”) shall be
deemed to form and be read and construed as part of this Agreement, viz.:
i. the Detailed award of contract;
ii. the Service level agreement;
iii. Instructions to Bidders
iv. the Special Conditions of Contract;
v. the General Conditions of Contract;
vi. the SRS document
vii. the Scope of Work;
viii. the Technical Specifications
ix. the Purchaser’s Notification to the Supplier for Award of Contract;
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 151
CESU, Odisha Page 151 Release Date: 27th February 2016
x. Vendor’s response (proposal) to the RFP, including the Bid Submission Sheet
and the Price Schedules submitted by the Supplier;
xi. Appendix A to B & E to U;
xii. Acceptance of purchaser’s notification
In the event of any discrepancy or inconsistency within the Contract documents, then the
documents shall prevail in the order listed above.
3. In consideration of the payments to be made by the Purchaser to the Supplier as
indicated in this Agreement, the Supplier hereby covenants with the Purchaser to provide
the Goods and Related Services and to remedy the defects therein and bring them in
conformity in all respects with the provisions of the Contract.
4. The Purchaser hereby covenants to pay the Supplier in consideration of the
provision of the Goods and Related Services and the remedying of defects therein, the
Contract Price or such other sum as may become payable under the provisions of the
Contract at the times and in the manner prescribed by the Contract.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed in
accordance with the laws of ________________________ on the day, month and year
indicated above.
Signed by __________________________________________ (Authorised Utility official)
Signed by __________________________________________________ (for the Supplier)
Witness-1
Witness-2
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 152
CESU, Odisha Page 152 Release Date: 27th February 2016
2 Performance Security (To be accompanied with the bank Guarantee)
Date:
Contract Name and No. :
To:
WHEREAS _______________________________________ (hereinafter called “the
Supplier”) which expression shall unless repugnant to the context thereof include his
successors, heirs, assigns has undertaken, pursuant to Contract No. ____________ dated
________________, _______ to supply
__________________________________________ (hereinafter called “the Contract”).
AND WHEREAS it has been stipulated by you in the aforementioned Contract that the
Supplier shall furnish you with a security ____________________ issued by a reputable
guarantor for the sum specified therein as security for compliance with the Supplier’s
performance obligations in accordance with the Contract.
AND WHEREAS the undersigned _____________________________________________
______________________, legally domiciled in ________________________________
____________________________________________, (hereinafter “the Guarantor”) which
expression shall unless repugnant to the context thereof include his successors, heirs,
assigns have agreed to give the Supplier a security:
THEREFORE WE hereby affirm that we are Guarantors and responsible to you, on behalf of
the Supplier, up to a total of
____________________________________________________ and we undertake to pay
you without protest and demur, upon your first written demand declaring the Supplier to be
in default under the Contract, without cavil or argument, any sum or sums within the limits
of __________ ____________ as aforesaid, without your needing to prove or to show
grounds or reasons for your demand or the sum specified therein.
This security is valid until _________ hours of the ___________________ day of
__________________, _____.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 153
CESU, Odisha Page 153 Release Date: 27th February 2016
Name
In the capacity of
Signed
Duly authorized to sign the security for and on behalf of
Date
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 154
CESU, Odisha Page 154 Release Date: 27th February 2016
Appendices
APPENDIX A – MANDATORY TECHNICAL SPECIFICATIONS ....................................................... 157
APPENDIX B – TECHNICAL SPECIFICATIONS ............................................................................... 162
APPENDIX C – SERVICE LEVEL AGREEMENT .............................................................................. 163
C.1 PURPOSE OF THIS AGREEMENT ..................................................................................................................... 163
C.2 DESCRIPTION OF SERVICES PROVIDED ......................................................................................................... 163
C.3 DURATION OF SLA.......................................................................................................................................... 163
C.4 SERVICE LEVEL AGREEMENTS & TARGETS ................................................................................................... 163
C.5 BREACH OF SLA ............................................................................................................................................. 172
C.6 EXCLUSIONS ................................................................................................................................................... 172
C.7 MONITORING AND AUDITING ........................................................................................................................... 172
C.8 REPORTING PROCEDURES ............................................................................................................................. 172
C.9 ISSUE MANAGEMENT PROCEDURES............................................................................................................... 172
C.9.1 General .................................................................................................................................................. 173
C.9.2 Issue Management Process ............................................................................................................... 173
C.10 SLA CHANGE CONTROL ............................................................................................................................... 173
C.10.1 General ................................................................................................................................................ 173
C.10.2 SLA Change Process ........................................................................................................................ 174
C.10.3 Version Control ................................................................................................................................... 174
C.11 MANAGEMENT ESCALATION PROCEDURES ................................................................................................. 174
C.12 SIGNATURE PAGE ......................................................................................................................................... 175
APPENDIX D - SUPPLIER RESPONSE FORMAT ............................................................................ 176
D.1 GENERAL GUIDELINES TO THE BIDDERS ........................................................................................................ 176
D.1.1 Guidelines for Technical proposal ...................................................................................................... 176
D.1.2 Guidelines for Price proposal .............................................................................................................. 176
D.1.3 Submission of proposal ....................................................................................................................... 177
D2 TECHNICAL PROPOSAL .................................................................................................................................... 178
D.2.1.1 Bid structure ...................................................................................................................................................... 178
D.2.1.2 Bidder - Company Statistics ........................................................................................................................... 178
D.2.2 Technical Specification requirement of Application packages ....................................................... 179
D.2.3 Hardware Technical Specifications (Including network equipment’s, LAN/WAN, Kiosk etc.) ... 179
Kindly attach the data sheets for the offered products. ............................................................................. 180
D.2.4 Approach and Methodology ................................................................................................................ 180
D.2.4.1 Understanding of Utility and its requirement ................................................................................................ 180
D.2.4.2 Details of proposed methodology .................................................................................................................. 181
D.2.4.3 Project Team Structure ................................................................................................................................... 181
D.2.4.4 Resource planning and estimation ................................................................................................................ 181
D.2.4.5 Risk planning .................................................................................................................................................... 182
D.2.4.6 Detailed work plan with timelines ................................................................................................................... 182
D.2.5 Project Experience ............................................................................................................................... 182
D.2.6 Team details (CVs)............................................................................................................................... 183
D.2.7 Firm Detail ............................................................................................................................................. 185
D.2.8 Facility Management Services Plan................................................................................................... 185
D.2.9 Project Management Practices .......................................................................................................... 185
D.2.10 Quality Assurance .............................................................................................................................. 185
D.2.11 Documentation .................................................................................................................................... 186
D.2.12 Deviations Sheet ................................................................................................................................ 186
D.3 PRICE PROPOSAL ............................................................................................................................................ 188
D.3.1 Project Area with Data Centre & Customer Care Centre ............................................................... 188
D.4 CHECKLISTS .................................................................................................................................................... 190
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 155
CESU, Odisha Page 155 Release Date: 27th February 2016
D.4.1 Mandatory forms that needs to be submitted ................................................................................... 190
D.4.2 Compliance checklist ........................................................................................................................... 190
APPENDIX E – EVALUATION METHODOLOGY .............................................................................. 192
E.1 SINGLE-STAGE: TWO-ENVELOPE BIDDING PROCEDURE ............................................................................... 192
E.2 EVALUATION AND COMPARISON OF BIDS ........................................................................................................ 193
APPENDIX F – GEOGRAPHICAL & ADMINISTRATIVE INFORMATION ......................................... 197
APPENDIX G – LIST OF OFFICES FOR WAN CONNECTIVITY ....................................................... 198
APPENDIX H – REVIEW OF CURRENT IT SYSTEMS ...................................................................... 199
EXISTING SOLUTIONS ............................................................................................................................................. 199
TECHNICAL EVALUATION – EXISTING IT SOLUTION ............................................................................................... 206
EXISTING HARDWARE ............................................................................................................................................ 209
APPENDIX I – LIST OF MANUALS/BUSINESS PROCESSES TO BE CONVERTED (DATA-ENTRY) INTO ELECTRONIC FORM ............................................................................................................... 214
APPENDIX J – REVIEW OF CURRENT BUSINESS PROCESSES ................................................... 215
NUMBER OF CONSUMER & ASSET INFORMATION IN CESU ................................................................................. 221
METERING, CONSUMER INDEXING AND ASSET MAPPING INFORMATION .............................................................. 222
PROJECT AREA NAME: CUTTACK ................................................................................................ 227
PROJECT AREA NAME: BHUBANESWAR ..................................................................................... 230
PROJECT AREA NAME: PURI ......................................................................................................... 233
PROJECT AREA NAME: KHORDHA................................................................................................ 236
PROJECT AREA NAME: JATNI ....................................................................................................... 239
PROJECT AREA NAME: DHENKANAL ........................................................................................... 243
PROJECT AREA NAME: ANGUL ..................................................................................................... 246
PROJECT AREA NAME: TALCHER ................................................................................................. 249
PROJECT AREA NAME: KENDRAPARA ......................................................................................... 252
PROJECT AREA NAME: PATTAMUNDAI ........................................................................................ 255
PROJECT AREA NAME: JAGATSINGHPUR ................................................................................... 258
PROJECT AREA NAME: PARADEEP .............................................................................................. 261
APPENDIX K – WEBSITE ................................................................................................................. 264
APPENDIX L: LIST OF GOODS AND RELATED SERVICES ........................................................... 266
APPENDIX M – ESTIMATED MANPOWER REQUIREMENT ............................................................ 267
APPENDIX N – EXPECTED IMPLEMENTATION SCHEDULE .......................................................... 268
APPENDIX O: SPOT BILLING MACHINE SPECIFICATION .......................................................... 270
APPENDIX P: MAP OF CESU OF ODISHA ................................................................................... 271
APPENDIX Q: FORMATS FOR PRICE BIDS .................................................................................. 272
APPENDIX R: PROPOSED INTERFACE SCHEME V2.4 ................................................................ 273
APPENDIX S: CESU OFFICES LOCATIONS FOR NETWORK CONNECTIVITY ............................ 274
APPENDIX T: ADDITIONAL CLARIFICATIONS ............................................................................. 274
APPENDIX U: NO DEVIATION CERTIFICATE ................................................................................ 276
APPENDIX V: ABBREVIATIONS ..................................................................................................... 277
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 156
CESU, Odisha Page 156 Release Date: 27th February 2016
List of Tables
Table 1: Mandatory Technical Specifications ............................................................................................ 157
Table 2: Service Level Chart ...................................................................................................................... 164
Table 3: Severity Definition Chart ............................................................................................................. 171
Table 4: Bid Structure ................................................................................................................................ 178
Table 5: Bidder – Company Statistics ........................................................................................................ 178
Table 6: Technical Specification for Application Packages ....................................................................... 179
Table 7: Details of Product Offered ........................................................................................................... 179
Table 8: Technical Specifications of Hardware ......................................................................................... 179
Table 9: Details of Hardware Offered ........................................................................................................ 180
Table 10: Proposed Project Team Structure ............................................................................................... 181
Table 11: Proposed Resource Planning and Estimation ............................................................................. 181
Table 12: Details of Project Experience ..................................................................................................... 182
Table 13: Format of Curriculum Vitae ....................................................................................................... 184
Table 14: Firm Detail ................................................................................................................................. 185
Table 15: Details of Certification ............................................................................................................... 186
Table 16: Format for Deviations ................................................................................................................ 187
Table 17: Check List for Mandatory Forms ............................................................................................... 190
Table 18: Check List for proper Documentation & Compliance ............................................................... 190
Table 19: Distribution of weights for bid evaluation ................................................................................. 193
Table 20: Score for Technical Evaluation .................................................................................................. 194
Table 21: Calculation of Technical Score .................................................................................................. 195
Table 22: Geographical & Administrative Information of all the Project Areas in CESU ........................ 197
Table 23: Geographical & Administrative Information of all the Project Areas in CESU ........................ 197
Table 24: List of Offices for WAN Connectivity in CESU ....................................................................... 198
Table 25: Details of existing Applications to be Upgraded or Integrated with new System ...................... 200
Table 26: Technical Evaluation of Existing IT Applications ..................................................................... 206
Table 27: Details of existing Hardware to be Upgraded or Integrated with new system ........................... 209
Table 28: List of Manuals/ Business Process to be converted into Electronic Form in CESU .................. 214
Table 29: Consumer Information for Utility and Project Areas ................................................................. 221
Table 30: Metering Information for Utility and Project Areas ................................................................... 222
Table 31: Consumer Indexing and Asset Mapping Information for Utility and Project Areas ................. 223
Table 32: Detail of existing Website in CESU ........................................................................................... 264
Table 33: Estimated Manpower Requirement ............................................................................................ 267
Table 34: Expected Implementation Schedule ........................................................................................... 268
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 157
CESU, Odisha Page 157 Release Date: 27th February 2016
Appendix A – Mandatory Technical Specifications
ITIA should provide documentary proof of compliance of following specification. Where it is not
possible to submit any certified proof for the same, ITIA shall self-certify that it would comply with
the specification during implementation.
Table 1: Mandatory Technical Specifications
A Solution Specifications Validation Through
(Certificate/
Document/ Self
Certify)
Available/
Not
available
A.1 The solution shall be designed with Service
Oriented Architecture.
The solution shall be designed based on
Component-based approach. It shall be highly
granular and loosely coupled to ensure that the
failure of one component does not cascade to
others.
Document
A.2 The solution shall be designed on web based
architecture.
Self Certify and
Document
A.3 The solution shall be horizontally and vertically
scalable and also have virtualization capability.
Self Certify and
Document
A.4 The solution shall be designed with Open Industry
Standards and not with Supplier’s proprietary
protocol.
Self Certify and
Document
A.5 The directory services shall be based on commonly
accepted application protocol like LDAP.
Self Certify and
Document
A.6 The proposed solution should be based on WS-*
specifications (Web services specifications) &
unified access framework compliant to W3C (World
Wide Web Consortium) specifications.
Self Certify and
Document
A.7 The application shall provide the functionality to
configure the parameters to define the business
rules with the application. These parameters shall
not be hard-coded in the application.
Self Certify
A.8 The solution shall provide the functionality to
configure the roles & responsibilities and grant role
based access to the users. Also, the system shall
Document and Self
Certify
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 158
CESU, Odisha Page 158 Release Date: 27th February 2016
have the capability to integrate with various
standard SSO (Single Sign-On) or IDM (Identity
Management) applications.
A.9 The solution shall use an integration middleware
layer so that all required external systems shall be
integrated on a continuous basis. The solution shall
conform to the requirements specified in Section
3.10 G1 of SRS document.
Self Certify and
Document
A.10 The solution shall provide the functionality to
encrypt the data stored or transmitted data.
Self Certify
A.11 The solution shall provide the functionality to
maintain the audit trail of all critical transactions.
Self Certify and
Document
A.12 The solution shall be able to interoperate with:
• standard RDBMS platforms like Oracle, MS
SQL, MY SQL, DB2, Informix, Sybase or any
other RDBMS confirming to ANSI/ISO SQL-
200n standards
• operating systems like Windows, Unix, Solaris
etc
• web browsers like Internet explorer, Mozilla
Firefox, Opera etc.
Self Certify and
Document
A.13 The solution shall be installed with the latest
security updates provided by software Supplier.
Self Certify
A.14 The software version shall be supported by the
software vendor for a minimum period of next five
years.
Self Certify and
Document
A1 Module: Meter Data Acquisition
A1.1 The Meter data acquisition Solution shall be
capable of collecting and analyzing data on a
common data structure/ format from system/
consumer meters of various makes and models.
The solution shall be compatible with present
modbus compliant meters installed in utilities as
well as future meters likely to be introduced in
Indian market complying with DLMS /COSEM/IEC-
62056/ANSI C-12.19/IEEE P-1377 Standards.
Certificate
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 159
CESU, Odisha Page 159 Release Date: 27th February 2016
A1.2 The regional hierarchy and network topology shall
be specific to the Indian context and flexible enough
to account for different voltage levels in Indian sub-
transmission and distribution networks e.g.
66/33/22/11/ 0.4 KV.
Self Certify
A2 Energy Audit
A2.1 The Energy Audit solution shall be able to
calculate allowable technical losses and estimated
technical & commercial losses in every part of the
network via integration with Network analysis
module, Meter data acquisition module, GIS
based indexing and asset mapping and
computerized billing & collection system.
Self Certify and
Document
A3 Module : GIS based customer Indexing and
asset mapping
A3.1 The Indexed customer database, when created and
operational, shall be capable of being ‘on line’
connected to other business process software
without any limitation.
The updation of GIS database is mandatory in case
of addition of customer/asset or dismantling of
existing customer/asset.
Self Certify and
Document
A3.2 The solution shall be based on open GIS
standards and shall be OGC (Open Geospatial
Consortium) Compliant.
The solution shall have a ready provision / facility
so that it can be easily integrated to the other
systems/applications, such as :
• SCADA
• Energy Audit and accounting system
• New connection, disconnection & dismantling
system
• Customer Care Centers
• Customer Information & Billing System
• Project Management etc.
Certificate and
Document
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 160
CESU, Odisha Page 160 Release Date: 27th February 2016
A4 Module: Customer care services
A4.1 The Customer care service solution shall have
single window interface through multiple touch
points.
Self Certify
A4.2 The Customer care service solution shall have call
escalation facility, in case the issues are not
resolved within the defined service levels.
Self Certify and
Document
A5 Module: Management information Systems
A5.1 The MIS solution shall provide Business
Intelligence Tools for data mining, analysis,
trending, simulation etc.
Document and Self
Certify
A6 Module: Identity and Access Management
Systems
A6.1 The Identity and access management solution shall
support two factor authentication (Biometrics,
tokens etc.)
Certificate
A6.2 The solution shall have feature to generate reports
in the lines of ISO 27001 standard.
Certificate
A6.3 The solution shall provide secure environment for
transmitting information across the Internet.
Self Certify
A6.4 The solution shall provide a mechanism to perform
the user authentication procedure. In case of
authentication failure, the feedback should not
include the reasons for such failure.
Document and Self
Certify
A7 Billing
A7.1 The Solution shall have a ready provision / facility
so that it can be easily integrated with
• Automatic online Meter Reading devices
and
• Handheld Computers / CMRI used for spot
metering and billing
Document and Self
Certify
A8 Asset Management, Maintenance
A8.1 The solution shall have a ready provision / facility
so that it can be easily integrated with
• GIS System
• Customer Care System
• SCADA
Document and Self
Certify
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 161
CESU, Odisha Page 161 Release Date: 27th February 2016
B Hardware Technical Specifications
B.1 The hardware solution shall meet the performance
criteria specified in the contract.
In case the offered hardware does not meet the
performance criteria, the supplier must provide
additional equipments or upgrade the equipments
without any additional cost to the utility.
Certificate
B.2 The hardware shall be scalable to manage
enterprise level solution for the entire utility.
Document and Self
Certify
B.3 The server hardware shall have 64 bit processing
capability.
Database servers shall be in cluster fail over mode
and Application servers shall be in scale out mode.
Document and Self
Certify
B.4 The supplier shall submit the data sheets for each
of the hardware model detailing the specifications of
the hardware.
Document
B.5 The hardware models shall be supported by the
hardware OEM for a minimum period of next five
years.
Self Certify from OEM
B.6 The hardware device operating system shall be
EAL 2 certified (Evaluation Assurance Level).
Certificate
C Mandatory Requirements of OEM for Hardware
C.1 The OEM vendor shall have ISO 9001:2000 and
ISO 14000 certifications. Certificate
C.2
The OEM vendor shall have an annual turnover
more than Rs. 250 crores from hardware business
in each of the last three financial years.
Document & Self
Certify
C.3
The OEM vendor shall have at least one service
center within the State of Odisha with sufficient
infrastructure.
Self Certify with
address details
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 162
CESU, Odisha Page 162 Release Date: 27th February 2016
Appendix B – Technical Specifications
• Please refer Excel Sheet – Appendix B
• The excel sheet has to be filled by the bidder as its response to technical
specifications requirements and to be submitted along with the bid, in a CD (in
duplicate)
• The hardcopy of the same should necessarily be submitted along with the
technical bid submission
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 163
CESU, Odisha Page 163 Release Date: 27th February 2016
Appendix C – Service Level Agreement
C.1 Purpose of this Agreement
The purpose of this SLA is to clearly define the levels of service to be provided by Supplier to
Purchaser for the duration of this contract or until this SLA has been amended. The benefits of
this SLA are to:
1 Trigger a process that applies Purchaser and Supplier management attention to some aspect
of performance only when that aspect drops below an agreed upon threshold, or target.
2 Makes explicit the performance related expectations on performance required by the
Purchaser
3 Assist the Purchaser to control levels and performance of services provided by Supplier
4 This SLA is between Supplier and Purchaser.
C.2 Description of Services Provided
Supplier shall provide service as defined in Section VI - Scope of Work, in accordance to the
definitions and conditions as defined in the Section VII - GCC and Section VIII - SCC.
C.3 Duration of SLA
This Service level agreement would be valid for entire period of contract. This SLA may be
reviewed and revised according to the procedures detailed in Section C.10 of SLA (SLA Change
Control).
C.4 Service Level Agreements & Targets
This section is agreed to by Purchaser and Supplier as the key supplier performance indicator for
this engagement. The following section reflects the measurements to be used to track and report
systems performance on a regular basis. The targets shown in the following tables are for the
period of contact or its revision whichever is later.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 164
CESU, Odisha Page 164 Release Date: 27th February 2016
Table 2: Service Level Chart
Mapping with Section G5 of SRS Document
Service Parameter Service Level
Validation Penalty
5.1 Project Management
Submission of Monthly Project Status reports & Conducting Status meetings
100% • Minutes of Meetings
• Approval of Status reports by Engineer-in-Charge
2% of monthly FMS charges for every default
5.2 Helpdesk Resolution of ticket logged as per the Severity definition chart
99% Reports generated from Ticket logging system
95%-99% calls resolved in specified time: 2% penalty on the monthly FMS charges
90% - 95% calls resolved in specified time: 5% penalty on the monthly FMS charges
5.3 Install, Moves, Add, Changes (IMAC) Services
Should be part of Monthly project status report
95% Report 0.2% of monthly FMS charges
5.4 Asset / Inventory Management
Provide monthly MIS Asset Inventory
95% Report 0.2% of monthly FMS charges
Provide monthly MIS on new requirements with procurement time
95% Report 0.2% of monthly FMS charges
Conduct Annual Physical Asset verification
100% Management approval of Physical Asset Verification report
0.5% of Yearly FMS charges
5.5 Supplier Management Services
Evaluation of Supplier Performance on quarterly basis
100% Management approval of Supplier Performance evaluation report
0.5% of Quarterly FMS charges
Tracking of Supplier SLA & tickets logged with suppliers
95% Status of tickets logged with Suppliers
0.5% of monthly FMS charges
MIS reporting on AMC tenure, License fees
95% Report 0.2% of monthly FMS charges
5.6 Desk Side Technical support Services
Resolution of ticket logged as per the Severity definition chart
95% Reports generated from Ticket logging system
1% of monthly FMS charges
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 165
CESU, Odisha Page 165 Release Date: 27th February 2016
Mapping with Section G5 of SRS Document
Service Parameter Service Level
Validation Penalty
5.7 Antivirus Management
Rollout of latest anti-virus definition file on workstations and Servers on being made available on Supplier's website within 24 Hours on Test Environment and within 48 hours on production environment
98% Reports generated from Anti Virus software console
1% of monthly FMS charges
5.8 LAN & local server administration
Resolution of ticket logged
99% Reports generated from Ticket logging system
Covered under 5.1
5.9
Network Monitoring & Management
SI to monitor the availability of the network link for 99% uptime. SI should measure link availability on a monthly basis.
99% Downtime reports
Reports on the Network performance
Penalty of 2% per month will be deducted from the monthly FMS charges of that utility, if the reports are not submitted by the SI.
Important: A separate SLA will be signed with bandwidth provider.
Resolution of ticket logged related to Networks
99% Reports generated from Ticket logging system
Covered under 5.1
Data Centre Network Availability
Minimum of 99.8% uptime measured on a monthly basis
99.8% Report • 2% of monthly FMS charges for less than 99.8%
• 3% of monthly FMS charges for less than 98.0%
• 5 % of monthly FMS charges for less than 95%
Regional Offices Network Availability
98% Report • 2% of monthly FMS charges for less than 98%
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 166
CESU, Odisha Page 166 Release Date: 27th February 2016
Mapping with Section G5 of SRS Document
Service Parameter Service Level
Validation Penalty
Minimum of 98% uptime measured on a monthly basis
• 3% of monthly FMS charges for less than 97%
• 5 % of monthly FMS charges for less than 95 %
Divisional & Other Offices Network Availability
Minimum of 97% uptime measured on a monthly basis
97% Report • 2% of monthly FMS charges for less than 97%
• 3% of monthly FMS charges for less than 95%
5.10 Data Centre Operations
MIS reporting on physical and environmental conditions controls
95% Report 0.2 % of monthly FMS charges
MIS reporting of health checkup of all systems & modules installed
95% Report 0.2 % of monthly FMS charges
5.11 Server Administration / Management
Rollout of patches (OS, infra level) on workstations and Servers after patch being approved on test environment
98% Patch update report
0.5% of monthly FMS charges
Uptime of app servers 99.8% Report • 2% of monthly FMS charges for less than 99.8%
• 3% of monthly FMS charges for less than 98%
• 5 % of monthly FMS charges for less than 95%
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 167
CESU, Odisha Page 167 Release Date: 27th February 2016
Mapping with Section G5 of SRS Document
Service Parameter Service Level
Validation Penalty
Uptime of utility servers except email
99.8% Report • 2% of monthly FMS charges for less than 99.8%
• 3% of monthly FMS charges for less than 98%
• 5 % of monthly FMS charges for less than 95%
5.12 Database Administration services
MIS report of database scheme, disk space, storage and user role
99% Report 0.5% of monthly FMS charges
5.13 Backup/ Restore Management
The Supplier should take backup as per the backup schedule defined by utility
99% Report If the negligence is found in monthly audit, the Bidder would be penalised a sum of Rs. 5,000/- per negligence.
Utility would periodically (once a quarter on a random day) request the Supplier to restore the backup data
100% Report Rs 5000/- for every restore test failure
5.14 Mail / Messaging System
Uptime of email server 99% Report • 2% of monthly FMS charges for less than 99%
• 3% of monthly FMS charges for less than 98%
• 5 % of monthly FMS charges for less than 95%
Provide monthly MIS of user account and mailboxes created/deleted.
95% Report 0.2% of monthly FMS charges
5.15 Management of utility’s EMS
Daily MIS of server and device health checkup (CPU, disk space, memory utilization, I/O
100% Reports generated from EMS system
0.5% of monthly FMS charges
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 168
CESU, Odisha Page 168 Release Date: 27th February 2016
Mapping with Section G5 of SRS Document
Service Parameter Service Level
Validation Penalty
utilization, Central Storage etc.)
6.1 Incident management
Resolution of ticket logged in Incident Management tool
99% Reports generated from Ticket logging system
0.5% of monthly FMS charges
6.2 Ticketing Management
Same as 6.1
6.3 Problem Management
Supplier shall analyze all the incidents and provide a root cause report every month if there are more than 10 incidents of the same type. Supplier shall take the needed corrective action to prevent further issues due to the same cause.
100% timely submission covering all incidents logged in that month
• Root cause report
• Incident report stating problems faced by the users
• Document detailing corrective action
• 5% penalty on the monthly FMS charges of that Project Area, if the Supplier does not submit a problem report for that month.
• 5% penalty on the monthly FMS charges of that Project Area, if the Supplier does not perform the corrective action for more than one calendar month.
6.4 Change Management
Resolution of Change Management ticket logged in Change Management tool
99% Reports generated from Change Management System
Covered under 5.1
6.5 Release Management
Same as 6.1
6.6 Email Listener Same as 5.14
6.7 Availability Management
Should be part of Monthly status report
95% Report 0.2% of monthly FMS charges
6.8 Performance Management
Should be part of Monthly status report
95% Report 0.2% of monthly FMS charges
6.9 Capacity management
Should be part of Monthly status report
95% Report 0.2% of monthly FMS charges
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 169
CESU, Odisha Page 169 Release Date: 27th February 2016
Mapping with Section G5 of SRS Document
Service Parameter Service Level
Validation Penalty
6.10 Security Management
Should be part of Monthly status report
95% Report 0.2% of monthly FMS charges
7
Resource Management
Number of shift days for which resource present at the designated location / Total number of shift days
98% averaged over all resources designated for SI services - calculated on a monthly basis
• Attendance track
• Call Log
• Audit calls/ visits
Measured on a monthly basis
If the resource availability is less than 95%, then payment shall be deducted based on the pro-rata basis.
(Total FMS cost per day divided by nos. of persons deployed)
Further deduction Rs.2,000/- per day per engineer/shall also be made on account of loss of utility/service
Resource provided is not as per specified certification / experiences
100% of the resource given
Experience Certificate of FMS personnel submitted by Supplier to Utility
Per day deduction =
0.5 * (Monthly value for that manpower as per SOR) / 30
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 170
CESU, Odisha Page 170 Release Date: 27th February 2016
Uptime Calculation for the month:
{[(Actual Uptime + Scheduled Downtime) / Total No. of Hours in a Month] x 100}
"Actual Uptime" means, of the Total Hours, the aggregate number of hours in any month during
which each equipment, is actually available for use.
"Scheduled Downtime" means the aggregate number of hours in any month during which each
equipment, is down during total Hours, due to preventive maintenance, scheduled maintenance,
infrastructure problems or any other situation which is not attributable to Supplier’s (or Service
provider's) failure to exercise due care in performing Supplier’s responsibilities.
The Purchaser would provide a maximum of 04 hours of planned downtime for the preventive
maintenance (as part of scheduled downtime) per month per equipment/service.
The downtime for scheduled maintenance (patch application, upgrades – OS, Database, etc.)
would need to be mutually agreed between Utility and the Bidder. To reduce this time, various
maintenance activities can be clubbed together with proper planning.
"Total Hours" means the total hours over the measurement period i.e. one month (24 * number of
days in the month).
Downtime Calculation:
The recording of downtime shall commence at the time of registering the call with Supplier or
Service Provider for any downtime situation for the equipment.
Downtime shall end when the problem is rectified and the application/ service is available to the
user.
Down time will not be considered for following:
1. Pre-scheduled preventive maintenance and health checks (Scheduled Downtime).
2. Failover time (30 minutes) in case of cluster environment. Beyond which the service
would be considered to be not available and appropriate penalty shall be imposed on the
Supplier.
3. Bug in any application which causes the non-availability of the service.
If the utility elects to continue the operation of the machine / equipment, when a part of the
machine is giving problem and leading to downtime, the commencement of downtime shall be
deferred until the utility releases the machine / equipment to the Bidder for remedial action.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 171
CESU, Odisha Page 171 Release Date: 27th February 2016
Severity definition chart is tabulated below for reference.
Table 3: Severity Definition Chart
Support
Category
Criteria Resolution Maximum
Response
Time
Critical
The system is unable to be used for
normal business activities. There is
certainty of financial loss to
PURCHASER.
90 Minutes
15 Minutes
Urgent
There is a problem with part of the
system, which impacts on Purchaser’s
decision making. No viable
workaround is available. There is a
likelihood of financial loss.
4 Hours
1 Hour
High
The efficiency of users is being
impacted, but has a viable
workaround.
6 hours
2 Hours
Medium
A low impact problem that affects the
efficiency of users but has a simple
workaround.
12 Hours
8 Hours
Low
A fault, which has no particular impact
on processing of normal business
activities.
One Week
8 Hours
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 172
CESU, Odisha Page 172 Release Date: 27th February 2016
C.5 Breach of SLA
In case the Supplier does not meet the service levels mentioned in Section C.4 of this Appendix
& Section G5 of SRS document, for three (3) continuous time-periods as specified in the relevant
clause, the Purchaser will treat it as a case of breach of Service Level Agreement. The following
steps will be taken in such a case:-
1. Purchaser issues a show cause notice to the Supplier.
2. Supplier should reply to the notice within three working days.
3. If the Purchaser authorities are not satisfied with the reply, the Purchaser will initiate
termination process as described in clause 33 of Section VII, GCC.
C.6 Exclusions
The Supplier will be exempted from any delays or slippages on SLA parameters arising out of
following reasons:-
1 Delay in execution due to delay (in approval, review etc) from Purchaser’s side. Any such
delays will be notified in written to the IT Team.
2 The network links will be provided by a third party and the Supplier will monitor and report
any problems on behalf of third party. If Supplier notifies and Purchaser approves that the
delay or fault was due to the third party link services then such loss will not be considered for
tracking Supplier’s SLA parameters (Also reduced from total service time).
C.7 Monitoring and Auditing
IT Team of Purchaser will review the performance of Supplier against the SLA parameters each
month, or at any periodicity defined in the contract document. The review / audit report will form
basis of any action relating to imposing penalty or breach of contract. Any such review / audit can
be scheduled or unscheduled. The results will be shared with the Supplier as soon as possible.
Purchaser reserves the right to appoint a third-party auditor to validate the SLA.
C.8 Reporting Procedures
The Supplier’s representative will prepare and distribute SLA performance reports in an agreed
upon format by the 10th working day of subsequent month of the reporting period. The reports
will include “actual versus target” SLA performance, a variance analysis and discussion of
appropriate issues or significant events. Performance reports will be distributed to the
Purchaser’s IT Team.
C.9 Issue Management Procedures
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 173
CESU, Odisha Page 173 Release Date: 27th February 2016
C.9.1 General
This process provides an appropriate management structure for the orderly consideration and
resolution of business and operational issues in the event that quick consensus is not reached
between Purchaser and Supplier. It is expected that this pre-defined process will only be used on
an exception basis if issues are not resolved at lower management levels.
C.9.2 Issue Management Process
• Either Purchaser or Supplier may raise an issue by documenting the business or technical
problem, which presents a reasonably objective summary of both points of view and identifies
specific points of disagreement with possible solutions.
• Purchaser and the Supplier’s representative will determine which committee or executive
level should logically be involved in resolution.
• A meeting or conference call will be conducted to resolve the issue in a timely manner. The
documented issues will be distributed to the participants at least 24 hours prior to the
discussion if the issue is not an emergency requiring immediate attention.
• Management of Purchaser and Supplier will develop a temporary, if needed, and the
permanent solution for the problem at hand. The Supplier will then communicate the
resolution to all interested parties.
• In the event a significant business issue is still unresolved, the arbitration procedures
described in the Contract will be used.
C.10 SLA Change Control
C.10.1 General
It is acknowledged that this SLA may change as Purchaser’s business needs evolve over the
course of the contract period. As such, this document also defines the following management
procedures:
1 A process for negotiating changes to the SLA.
2 An issue management process for documenting and resolving particularly difficult issues.
3 Purchaser and Supplier management escalation process to be used in the event that an
issue is not being resolved in a timely manner.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 174
CESU, Odisha Page 174 Release Date: 27th February 2016
Any changes to the levels of service provided during the term of this agreement will be
requested, documented and negotiated in good faith by both parties. Either party can request a
change. Changes will be documented as an addendum to this document and consequently the
contract.
C.10.2 SLA Change Process
Both the parties may amend this SLA by mutual agreement in accordance. Changes can be
proposed by either party. Normally the forum for negotiating SLA changes will be Purchaser’s
monthly review meetings.
C.10.3 Version Control
All negotiated SLA changes will require changing the version control number. As appropriate,
minor changes may be accumulated for periodic release (e.g. every quarter) or for release when
a critical threshold of change has occurred.
C.11 Management Escalation Procedures
The purpose of this escalation process is to provide a quick and orderly method of notifying both
parties that an issue is not being successfully resolved at the lowest possible management level.
Implementing this procedure ensures that purchaser and Supplier management are
communicating at the appropriate levels. Escalation should take place on an exception basis and
only if successful issue resolution cannot be achieved in a reasonable time frame.
1. All issues would be raised to the project management team, which is completely
responsible for the day to day aspects of the implementation. The project management
team shall classify the issues based on their severity level and resolve them within
appropriate timelines.
2. If project management team is unable to resolve an issue, the issue would be escalated
to the top management with options/ risks detailed for decision. Top management will
make decisions based on the options/ risks presented by the IT team.
3. In case one or both the parties are unsatisfied with the decision of the top management of
the Purchaser, the dispute will be resolved as specified in clause 8 of Section VIII – GCC.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 175
CESU, Odisha Page 175 Release Date: 27th February 2016
C.12 Signature Page
IN WITNESS WHEREOF, the parties hereto have caused this Service Level Agreement to be
executed by their respective authorized representatives as of the date first written above.
Supplier Purchaser
(On Behalf of all consortium members also)
Signature ------------------------ Signature ------------------------
Name ------------------------ Name ------------------------
Address ------------------------ Designation ------------------------
Company ------------------------
Date ------------------------ Date ------------------------
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 176
CESU, Odisha Page 176 Release Date: 27th February 2016
Appendix D - Supplier Response Format
D.1 General Guidelines to the bidders
The Purchaser will select a Supplier (also referred as the ‘bidder’) in accordance with the eligibility criteria indicated in Section IV.
The bidders are invited to submit a Technical Proposal and a Price Proposal for goods and related services required for the project as defined in Section VI, Scope of Work and Appendix L. This proposal will be the basis for contract negotiations and finalization of the contract with the successful bidder.
The bidders must familiarize themselves with local conditions and take these into account while preparing their proposals. To facilitate the bidders in making the Proposal, the Purchaser shall have a ‘Pre-Bid conference’ at the address and date as given in ITB, Section II.
Please note that:
• Costs involved in preparation of the proposal and of negotiating the contract, including a visit to the Purchaser, are not reimbursable.
• The final evaluation will be based on both technical and commercial factors as per the evaluation methodology mentioned in the Appendix E.
• Please check all attachments with the checklist provided at the end, prior to submission of bid.
D.1.1 Guidelines for Technical proposal
In preparing the Technical Proposal, bidders are expected to examine this Bid document in detail. The proposal should cover all the aspects of this bid document. Any bid not found responsive to this bid document shall be rejected. Material deficiencies in providing the information requested may also result in rejection of the proposal.
While preparing the technical proposal, bidders must give particular attention that the technical proposal does not include any financial information.
D.1.2 Guidelines for Price proposal
In preparing the price proposal, bidders are expected to take into account the requirements and conditions of the bid document. The price proposal should follow standard formats/forms as given in Appendix D.3.
Bidder should quote for each Project Area cost separately and also provide the consolidated cost of the project.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 177
CESU, Odisha Page 177 Release Date: 27th February 2016
Price Proposal should clearly indicate the price to be charged without any qualifications whatsoever and should include all taxes (sales, service, etc.), duties (excise & customs, etc), octroi, fees, levies, works contract tax, Entry tax and other charges as may be applicable, to be paid pre- or post-delivery or to be deducted by the purchaser at source, in relation to the Goods and Related Services. Such taxes, duties, cess, charges etc, if not explicitly mentioned in the Price bid tables in Appendix H.3, but applicable under law, should be included in the Quote under “Any other levies” column. The price proposal should be conformance to clause 12.3 of ITB, Section II.
D.1.3 Submission of proposal
• The original technical proposal and price proposal shall be prepared in indelible ink. It shall contain no inter-lineation or overwriting, except as necessary to correct errors made by the bidder itself. The authorised representative must initial any such corrections as mentioned in clause 21.2 ITB, Section II.
• An authorised representative of the bidder should initial all pages of the proposal.
• The bidders should submit two hard copies and five soft copies in separate compact discs (CD)/DVD as per clause 21.1 ITB, Section II. The soft copies should be necessarily in MS Word / MS Excel format (editable) besides other format(s).
• Bidders are requested to submit a proposal written in the English language. Bidders would need to submit both the technical and the price proposals.
• The proposal should be typed in “Times New Roman” font, size 11 with single line spacing.
• The document should be precise to requirements and concise in nature.
• Each technical proposal and price proposal should be marked "Original" or "Copy" as per clause 21.1 ITB. Section II. If there are any discrepancies between the original and the copy of the Proposal, the original governs. Proposals containing erasures or alterations are liable to be excluded from the evaluation process.
• The original and copy (also softcopies) of the technical proposal shall be placed in a sealed envelope clearly marked "Technical Proposal". The original and copy (also softcopies) of the price proposal should also be placed in a sealed envelope clearly marked "Price proposal" along with a warning: "Do not open with the Technical Proposal." Both envelopes shall be placed into an outer envelope and sealed. This outer envelope shall be super scribed with the following information:
1. Name of the bidder 2. Due date and time of submission 3. Submission address and contact detail
A clear marking stating: "DO NOT OPEN, EXCEPT IN PRESENCE OF THE EVALUATION COMMITTEE."
• Any omissions / deviations on the above, will cause rejection of the bid
The completed technical and price proposal must be delivered at the submission address on or before the time and date stated in the Bid Data Sheet, Section III. The Purchaser will not be responsible for any postal or transit delays. Any proposal received after the closing time for submission of proposals shall be returned unopened.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 178
CESU, Odisha Page 178 Release Date: 27th February 2016
D2 Technical Proposal
D.2.1 General Requirements D.2.1.1 Bid structure
THE RESPONSE SHOULD INCLUDE DETAILED STRUCTURE OF THE BID SPECIFYING THE NAMES OF
BIDDER, CONSORTIUM MEMBER (IF ANY) AND SUBCONTRACTORS, STATING THEIR RESPECTIVE
RESPONSIBILITIES. USE FOLLOWING FORMAT:-
Table 4: Bid Structure
Role Name of Company & Address
Bidder (SI/ Lead member in case of consortium for SI role) Consortium member (Second member in case of consortium for SI Role)
GIS Solution Provider
Network Solution Provider
Meter Data Acquisition Solution Provider, if required
D.2.1.2 Bidder - Company Statistics
PLEASE PROVIDE THE GENERAL AND FINANCIAL DETAILS OF EACH OF THE ENTITIES (BIDDER, CONSORTIUM MEMBER (IF ANY) AND SUBCONTRACTORS) IN THE FOLLOWING FORMATS:
Table 5: Bidder – Company Statistics
DETAILS SUPPLIER RESPONSE
BIDDER’S NAME
ADDRESS
CONTACT (S), TITLE (S), TELEPHONE (S), E-MAIL ID
(S)
NAME OF THE CHAIRMAN/ MD/ CEO/ PARTNERS
NATURE OF OWNERSHIP
DATE OF INCORPORATION OF COMPANY/ENTITY
HEADQUARTER LOCATION
OTHER OFFICE LOCATIONS, FUNCTIONS AND
PERSONNEL STRENGTH
NUMBER OF EMPLOYEES BY FUNCTION
Implementation Sales Support Quality Assurance Administrative Management
SIZE OF TEAM FOR THE PROPOSED SOLUTION
LOCATION OF SUPPORT CENTERS FOR PROPOSED
SOLUTION
OTHER BUSINESSES
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 179
CESU, Odisha Page 179 Release Date: 27th February 2016
D.2.2 Technical Specification requirement of Application packages
Refer to Technical Specifications, Appendix B.1 for details. Please respond to each specification in following format. Copy first three columns from Appendix B.1.
Table 6: Technical Specification for Application Packages
No Functional Requirements Criticality Supplier
Response Remarks
The code to be used for providing Supplier rating responses in the column "Supplier Response" for the functional requirements is provided below:
A - Functionality not available;
B - Available with modification/workaround
C - Functionality available
Please note that the rating as per the above scale is to be entered in the "Supplier Response" column, and column titled “Remarks” is to be used for commenting on aspects related to the functional specification. Bidders have to fill on two columns ("Supplier Response" & “Remarks”).
Please also note that the serial no. and format of response should be exactly similar to that given in Appendix B.1
PLEASE PROVIDE A SUMMARY OF VERSIONS OF VARIOUS MODULES, IF THE PROPOSED SOLUTION IS A
PRODUCT. USE FOLLOWING FORMAT:-
Table 7: Details of Product Offered
Name of product Module details Version and year of release
D.2.3 Hardware Technical Specifications (Including network equipment’s, LAN/WAN, Kiosk etc.)
Refer to Technical Specifications, Appendix B.2 for details.
Please respond to each specification in following format.
Table 8: Technical Specifications of Hardware
No Description/Requirements Priority Supplier Respons
e Remarks
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 180
CESU, Odisha Page 180 Release Date: 27th February 2016
The code to be used for providing Supplier rating responses in the column "Supplier Response" for the hardware requirements is provided below: The distribution of marks for Essential and Desirable specifications shall be as follows: A - Specifications not available B - Specifications available with modification* C - Specifications available The distribution of marks for vital specifications shall be as follows: A - Specification not available C - Specifications available
* This response is only acceptable for “Essential” & “Desirable” requirements.
Please note that the rating as per the above scale is to be entered in the "Supplier Response" column, and column titled “Remarks” is to be used for commenting on aspects related to the functional specification. Bidders have to fill on two columns ("Supplier Response" & “Remarks”).
Please also note that the serial no. and format of response should be exactly similar to that given in Appendix B.2.
PLEASE MENTION THE DETAILED SPECIFICATION OF HARDWARE EQUIPMENT AND SYSTEM SOFTWARE
(OPERATING SYSTEM, DATABASE ETC.) INCLUDING MANUFACTURER, TECHNICAL DETAILS ETC. THE
BIDDERS SHOULD PROVIDE DETAILS OF REQUIRED SYSTEM SOFTWARE LIKE OPERATING SYSTEM , DATABASE FOR SOLUTION AND UTILITIES IN FOLLOWING FORMAT :-
Table 9: Details of Hardware Offered
Product details No. of
installations Make and Model Version and year of release
Kindly attach the data sheets for the offered products.
D.2.4 Approach and Methodology
THE FOLLOWING TABLE ELABORATES VARIOUS REQUIREMENTS WITHIN A&M:
i. Understanding of Purchaser and its requirement with clear mention of the deliverables
ii. Details of proposed methodology iii. Project Team Structure iv. Resource planning and estimation v. Risk planning vi. Detailed work plan with timelines
D.2.4.1 Understanding of Utility and its requirement
BIDDER SHOULD DEPICT COMPLETE UNDERSTANDING OF THE AS-IS SYSTEM OF THE UTILITY BASED ON
THE INFORMATION PROVIDED IN THE BID DOCUMENT. IT SHOULD ALSO REQUIRE TO LIST DOWN ALL THE
DELIVERABLES THAT HAS BEEN PLANNED AS A PART OF THE OVERALL PROJECT WITH TIMELINES. ALSO
PROVIDE DETAILS OF PRIOR INTERACTION WITH UTILITY, IF ANY.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 181
CESU, Odisha Page 181 Release Date: 27th February 2016
D.2.4.2 Details of proposed methodology
PLEASE PROVIDE DETAILS OF METHODOLOGY FOLLOWED BY YOUR ORGANIZATION IN SUCCESSFULLY
IMPLEMENTING SIMILAR PROJECTS. ALSO HIGHLIGHT THE SPECIAL STEPS THAT YOUR ORGANIZATION/ CONSORTIUM INTENDS TO TAKE IN ORDER TO ENSURE THAT THE CHANGE FROM CURRENT SYSTEM TO
PROPOSED ONE WILL BE SMOOTH AND EFFECTIVE.
D.2.4.3 Project Team Structure
IN THIS SECTION PLEASE PROVIDE DETAIL OF THE TEAM THAT WOULD BE DEPLOYED BY YOUR
ORGANIZATION TO EXECUTE THE PROJECT. PLEASE PROVIDE DETAILS OF THE TEAM STRUCTURE IN THE
FOLLOWING FORMAT:
Table 10: Proposed Project Team Structure NAME OF
STAFF POSITION
ASSIGNED INTERNAT
IONAL OR
DOMESTI
C
FIRM EMPLOYME
NT STATUS
WITH THE
FIRM (FULL
TIME/ ASSOCIATE)
EDUCATION
(DEGREE, YEAR, INSTITUTION)
AREA OF
EXPERTISE AND
NUMBER OF
YEARS OF
RELEVANT
EXPERIENCE
TASK
ASSIGNED
A. PROFESSION
AL STAFF
B. SUPPORT
STAFF
D.2.4.4 Resource planning and estimation
BIDDER SHALL PROVIDE DETAILED STAFFING SCHEDULE OF THE PROFESSIONAL AND SUPPORT STAFF
IN THE FOLLOWING FORMAT:
For Professional Staff the input should be indicated individually; for Support Staff it should be indicated by category (e.g.: IT administrator, field survey staff etc.).
Months are counted from the start of the assignment. For each staff indicate separately staff input for off-site and on-site work.
Table 11: Proposed Resource Planning and Estimation NO
. NAME OF STAFF POSITIO
N STAFF INPUT
IN
WEEKS W1 W2 W3 W4 W5 ….. TOTAL
A. PROFESSIONAL
STAFF
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 182
CESU, Odisha Page 182 Release Date: 27th February 2016
B. SUPPORT STAFF
D.2.4.5 Risk planning
BIDDER SHALL ASSESS UNDERLYING RISKS IN IMPLEMENTATION OF THE PROJECT AND DETAIL OUT THE
METHODOLOGY TO MITIGATE THEM. IT MAY INCLUDE DEVELOPMENT OF A RISK ASSESSMENT MATRIX
INDICATING SEVERITY OF THE RISK, CHANCE OF ITS OCCURRENCE AND ITS MITIGATION APPROACH.
D.2.4.6 Detailed work plan with timelines
PLEASE REFER APPENDIX N FOR THE FORMAT.
D.2.5 Project Experience
BIDDER SHALL PROVIDE DETAILS OF PROJECTS WITH APPLICATION MODULES AND OTHER
REQUIREMENTS (AS MENTIONED IN ELIGIBILITY CRITERIA, SECTION IV) WHICH HAVE BEEN
SUCCESSFULLY COMPLETED DURING THE LAST 3 FINANCIAL YEARS.
PLEASE DO NOT SUPPLY THE NAMES OF CLIENTS WHO ARE NO LONGER USING YOUR
PRODUCT/SYSTEM.
Bidders need to submit the details as per the format in the table provided. Table: The details of the same should be included in the following format and necessary supporting documents should be attached with RFP:
Table 12: Details of Project Experience
SI. No
Name of project
Brief Scope necessarily including role played by Bidder, modules implemented, sector classification
Owner of Project assignment (Client name)
Cost of assignment
Date of Awarded commencement
Date of completion
Was assignment satisfactorily completed
Was it a Power Sector Project? (Y/N) Provide Detail
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 183
CESU, Odisha Page 183 Release Date: 27th February 2016
Please provide separate client details for bidder & each consortium member (Implementation partner, product Supplier, WAN/bandwidth/Internet service provider etc.)
D.2.6 Team details (CVs)
USE THE FOLLOWING FORMAT FOR KEY PERSONNEL WHO WOULD BE INVOLVED IN THE PROJECT. PLEASE INCLUDE DETAILS OF TEAM MEMBERS PROPOSED TO IMPLEMENT THE PROJECT, INSTALL OR
MANAGE HARDWARE, INSTALL AND MANAGE LAN/WAN AND RELATED EQUIPMENTS, PROVIDE GIS
SOLUTION ETC., PLEASE ENSURE THAT THE CV HAS A MAXIMUM LENGTH OF 3 PAGES.
IN CASE OF REPLACEMENT OF SUPPLIER PERSONAL FROM THE PROJECT TEAM, SUPPLIER IS REQUIRED
TO SUBMIT TO THE NOMINATED UTILITY PERSONAL THE CV OF THE NEW PERSON WITH EQUIVALENT OR
BETTER EDUCATION QUALIFICATION AND RELEVANT PROFESSIONAL EXPERIENCE WHO WILL BE JOINING
THE TEAM AND GET IN DULY APPROVED. THE NEW PERSON CAN START WORKING IN THE PROJECT ONLY
AFTER HIS/HER CV HAS BEEN APPROVED BY THE UTILITY.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 184
CESU, Odisha Page 184 Release Date: 27th February 2016
Table 13: Format of Curriculum Vitae
1. PROPOSED POSITION:
2. NAME OF FIRM AND ITIA ROLE
(SI/NSP/GSP/MDASP)
3. NAME OF STAFF:
4. DATE OF BIRTH: NATIONALITY:
5. EDUCATION:
YEAR DEGREE/EXAMINATION INSTITUTE/BOARD
6. MEMBERSHIP OF
PROFESSIONAL
ASSOCIATIONS:
7. OTHER TRAINING:
8. COUNTRIES OF WORK
EXPERIENCE:
9. LANGUAGES:
LANGUAGE SPEAKING READING WRITING
10. EMPLOYMENT RECORD:
FROM TO EMPLOYER POSITIONS HELD
11. DETAILED TASKS ASSIGNED: 12. WORK UNDERTAKEN THAT BEST ILLUSTRATES CAPABILITY TO
HANDLE THE TASKS ASSIGNED:
13. Certification:
I, the undersigned, certify that to the best of my knowledge and belief, this CV correctly describes myself, my qualifications, and my experience. I understand that any wilful misstatement described herein may lead to my disqualification or dismissal, if engaged.
Signature of authorised representative of the staff Date:
Full name of authorised representative:
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 185
CESU, Odisha Page 185 Release Date: 27th February 2016
D.2.7 Firm Detail
BIDDER SHALL PROVIDE DETAILS OF CMM/CMMI AND ISO CERTIFICATION ALONG WITH THE DETAILS
OF NET-WORTH AND TURNOVER FOR THE PAST THREE AUDITED FINANCIAL YEARS IN THE FOLLOWING
FORMAT:
Table 14: Firm Detail
DETAILS FY11-12 FY12-13 FY13-14
NET-WORTH
TURN-OVER
LEVEL OF CMM/CMMI CERTIFICATION (YES/NO)
ISO CERTIFICATION (YES/NO)
AUDITED FINANCIAL REPORTS AND COPY OF THE CERTIFICATES SUPPORTING THE ABOVE NEED TO BE
SUBMITTED AS PROOF.
D.2.8 Facility Management Services Plan
THE DETAIL PLAN FOR FMS SHALL BE GIVEN IN ACCORDANCE WITH THE SECTION G5 OF SRS
DOCUMENT.
D.2.9 Project Management Practices
PLEASE PROVIDE HIGH-LEVEL DETAILS OF THE PROJECT MANAGEMENT PRACTICES THAT WILL BE
FOLLOWED TO MANAGE THE PROJECT. THE PROJECT MANAGEMENT PRACTICES WOULD INCLUDE (BUT
NOT BE LIMITED TO) DETAILS OF:-
• BIDDER MUST PROVIDE DETAILS OF HOW THEY ENVISAGE THE CONTRACT BEING MANAGED
INCLUDING PRINCIPLES SUCH AS (BUT NOT LIMITED TO) JOINT PLANNING AND CONTROL
MECHANISMS; REGULAR AND ACTIVE REVIEW MEETINGS; PROJECT MANAGEMENT OF INDIVIDUAL
WORK STREAMS AND OVERALL PROGRAM MANAGEMENT OF THE ENTIRE SERVICE; PERFORMANCE
REPORTING
• BIDDER SHOULD OUTLINE THEIR PROPOSED GOVERNANCE STRUCTURE AND DESIGNATE A SERVICE
MANAGER TO CO-ORDINATE THEIR ACTIVITIES AND PROVIDE A FOCAL POINT OF CONTACT TO WHOM
UTILITY CAN REFER ON ANY MATTER CONCERNING THE SERVICE.
• REPORTING LINES AND DECISION-MAKING POWERS WITHIN THE BIDDER’S ORGANIZATION MUST BE
EXPLAINED
• REPORTING FORMATS AND TEMPLATES THAT WOULD BE FOLLOWED BY THE BIDDERS
• OUTLINE THE PROPOSED ESCALATION PROCEDURES IN THE EVENT THAT ISSUES ARISE.
D.2.10 Quality Assurance
• QUALITY OF SERVICE - SUPPLIERS MUST PROVIDE DETAILS OF THEIR PROPOSED APPROACH TO
QUALITY ASSURANCE TO ENSURE THE QUALITY OF SERVICES IN ACCORDANCE WITH CLAUSE 19 OF
SECTION G1 OF SRS DOCUMENT. THIS SHOULD INCLUDE:
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 186
CESU, Odisha Page 186 Release Date: 27th February 2016
• RESPONSIBILITY OF QUALITY OF SERVICE;
• HOW THE SUPPLIER WILL ENSURE QUALITY SERVICE IS PROVIDED;
• HOW QUALITY WILL BE MEASURED
Does your company (and consortium partner) have any quality certification / Assessment? If so, please provide your responses for the following:
Table 15: Details of Certification DESCRIPTION BIDDER’S
RESPONSE
CERTIFICATION / ASSESSMENT NAME
WHO ISSUED THE CERTIFICATION/ASSESSMENT?
WHEN WAS THE CERTIFICATION/ASSESSMENT OBTAINED?
DOES THIS CERTIFICATION/ASSESSMENT PROCESS INVOLVE PERIODIC
REVIEWS AND OBSERVATIONS/ REMARKS AFTER SUCH REVIEW? IF SO, PLEASE PROVIDE DETAILS AND SPECIFY WHEN YOUR COMPANY IS DUE FOR
ITS NEXT QUALITY REVIEW?
Please specify your company’s process for product development and enhancements
D.2.11 Documentation
PLEASE PROVIDE A LIST OF ALL USER DOCUMENTS THAT WILL BE PROVIDED ALONG WITH THE
SOFTWARE PACKAGE. THIS MUST INCLUDE THE FOLLOWING MINIMUM DOCUMENTS:
• SYSTEM AND ADMINISTRATION MANUALS
• TECHNICAL SUPPORT HANDBOOK
• USER MANUALS;
• ERROR MESSAGES AND THEIR MEANINGS;
• TRAINING MANUALS;
• ANALYSIS & DESIGN MANUALS WITH THE RELEVANT DATA FLOW DIAGRAMS, ENTITY RELATIONSHIP
DIAGRAMS, SCHEMAS ETC.;
• ADDITIONS/ CHANGES TO THE DOCUMENTS AFTER UPGRADES; AND
• OPERATIONS MANUALS.
D.2.12 Deviations Sheet Only “non-material deviations” (which means only those deviations that do not qualify as material deviations as defined in ITB clause 29.2 of bid document) will be considered by the purchaser. Please describe all the non-material deviations w.r.t Terms and conditions described in the General conditions of contract, Section VII & Special conditions of contract, Section VIII. If bidder desires to take any non-material deviation from the terms & conditions of the tender, it should be mentioned specifically in this deviation sheet. Unless such deviations are mentioned in this deviation sheet, the same will not be taken into consideration.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 187
CESU, Odisha Page 187 Release Date: 27th February 2016
Table 16: Format for Deviations
Tender Clarifications – Terms and Conditions Sl. No. Tender Reference (Section /
Clause number ) Details of Clauses / Section needing deviation
Deviation proposed
Except aforesaid deviations, the entire order, if placed, shall be executed in accordance with specifications and any other conditions, variations/deviations etc. if found, elsewhere in this proposal should not be given any consideration while finalizing the tender. It is not mandatory to consider and accept the deviation mentioned on deviation sheet proposed by the bidder. Note: - Continuation sheet of like size & format may be used as per bidder’s requirement wherever necessary.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 188
CESU, Odisha Page 188 Release Date: 27th February 2016
D.3 Price proposal Bidders are requested to provide cost for each of the Project Area in the subsequent formats. The Bidders should take a note of following points while filling the Price proposal.
1 Bidder will be responsible for payment of Taxes (including local entry taxes), duties, cess, charges etc, including taxes, duties, cess, charges etc, to be paid by the Supplier pre- or post-delivery. Such taxes, duties, cess, charges etc, if not explicitly mentioned in the following tables, but applicable under law, should be included in the Quote under “Any other levies” column.
2 The Bidder will provide Tax rates assumed for the calculation at the time of proposal for each item in notes to respective table.
3 Please refer to GCC Clause 13.2 and the SCC for Price adjustments due to change in Tax rates (including local entry taxes), duties, cess, charges etc.
4 Purchaser reserves the right to deduct and pay to the government authorities the taxes at applicable rates from the price payable to the supplier.
5 The unit prices mentioned for various components should be the same for all Project Areas. In case of any discrepancy among unit prices of various Project Areas, the lowest unit price of equipment mentioned for any Project Area shall prevail.
6 Utility proposes establishment of one centralized Data Centre and Customer Care Centre which are located in the Project Area(s) defined in the Appendix F (List of offices for WAN connectivity).
D.3.1 Project Area with Data Centre & Customer Care Centre
BIDDER SHOULD REFER APPENDIX F TO FILL IN FOLLOWING INFORMATION:
NAME OF PROJECT AREA (TOWN):-
LOCATION DATA CENTRE:-
LOCATION OF CUSTOMER CARE CENTRE:-
NUMBER SUBDIVISION OFFICES UNDER THE PROJECT
AREA:-
NUMBER OF OTHER OFFICES UNDER THE PROJECT AREA:-
• FORMS (FORM 1 TO FORM 6) MENTIONED IN THE APPENDIX C.3.1 SHOULD ONLY BE FILLED, BY THE
BIDDER, TO PROVIDE COST OF IT IMPLEMENTATION FOR PROJECT AREA WHERE DATA CENTRE AND
CUSTOMER CARE CENTRE ARE LOCATED. FOR OTHER PROJECT AREA(S) OF THE UTILITY, FORMS
(FORM 3 TO FORM 6) MENTIONED IN APPENDIX C.3.2 SHOULD BE FILLED.
• BIDDER SHOULD DEFINE QUANTITY AND UNIT PRICE WHICH INCLUDES FOB, FREIGHT & INSURANCE, EXCISE DUTY, CST/VAT AND ANY OTHER LEVIES FOR EACH ITEM LISTED BELOW IN THE
FOLLOWING FORMAT.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 189
CESU, Odisha Page 189 Release Date: 27th February 2016
• Sub-division offices are separated from other offices as Meter Data Acquisition Servers are planned to be setup only in sub-division offices. Other offices cover (but not limited to) head quarter, regional offices, circle offices, division offices, collection centre etc. These offices are not provided with any server and shall have connectivity with Data Centre to transfer/access information.
Form 1: Data Centre Cost • Bidder should provide lumpsum cost of installation, testing & commissioning, training of
employees, data migration cost etc. including all taxes in the format provided below. • WAN/LAN implementation charges shall include charges for setup, configuration, training,
installation, cables, liaisoning with service provider, etc.
Price Details are to be provided as per attached Price annexure. Bid Forms in Price Annexure are to be used as mentioned below (Details of Price Bid Formats are provided in Appendix Q):-
Bid Form No.
Bid Form Description
I This form is to be used for providing the price proposal of Bhubaneswar City including the Data Center Cost
II This form is to be used for providing the price proposal of Berhampur town or any other town to be selected by CESU for Disaster Recovery Center Cost
III This form is to be used for providing the price proposal of Bhubaneswar City including the Call Center Cost
IV This form is to be used for providing the price proposal of R-APDRP Towns other than Bhubaneswar and Cuttack.
V This form is to be used for FMS Charges
VI This form is to be used for providing the FMS Charges for R-APDRP
VII This form is to be used for providing the Total Cost of Ownership for R-APDRP area
VIII This form is to be used for Total Cost of Project covering both the Areas and including the FMS Charges. Project Proposals will be compared based on the Total project Cost mentioned in this sheet.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 190
CESU, Odisha Page 190 Release Date: 27th February 2016
D.4 Checklists
PLEASE SUBMIT A COPY OF THIS SECTION WITH COVER LETTER WHILE SUBMITTING THE PROPOSAL.
D.4.1 Mandatory forms that needs to be submitted
Table 17: Check List for Mandatory Forms S. No. Item Furnished
1 Documents against eligibility criteria Yes/ No
2 Bid Security Yes/ No
3 One original copy duly signed- Technical Proposal Yes/ No
4 One copy Technical Proposal - Hard copy Yes/ No
5 Five copies of Technical Proposal - Soft copies Yes/ No
6 One original copy duly signed- Price proposal Yes/ No
7 One copy of Financial Proposal - Hard copy Yes/ No
8 Five copies of Financial Proposal - Soft copies Yes/ No
9 Proof of turnover and net worth for the last three audited financial years of Bidder, consortium member (if any) and sub-contractors
Yes/ No
10 CV of key personnel in suggested format Yes/ No
11 Proposed SLA template Yes/ No
12 Filled-in copy of Bidding forms (Section V) Yes/ No
13 Receipt of purchase of tender Yes/ No
D.4.2 Compliance checklist
Table 18: Check List for proper Documentation & Compliance S. No. Item Furnished
1 Please confirm you agree to all clauses specified in the Section II, ITB Yes/ No
2 Please confirm you have submitted all the mandatory forms specified in Appendix D (Technical & Financial Proposal)
Yes/ No
3 Please confirm you have noted the bid submission deadline specified in Section III, BDS (ITB 23.1)
Yes/ No
4 Please confirm you have noted that the performance security will be furnished within time period as specified in Section II, ITB clause 42.1
Yes/ No
5 Please confirm you have provided all document proof to substantiate you qualifying the eligibility criteria as mentioned in Section IV
Yes/ No
6 PLEASE CONFIRM YOU HAVE COMPLIED WITH THE PROPOSED SOLUTION
ARCHITECTURE SPECIFIED IN SRS DOCUMENT Yes/ No
7 PLEASE CONFIRM YOU HAVE COMPLIED WITH ALL SERVICES SPECIFIED IN THE
SCOPE OF SERVICES MENTIONED IN SECTION VI Yes/ No
8 PLEASE CONFIRM THAT YOU COMPLY WITH ALL CLAUSES SPECIFIED IN THE
GENERAL CONDITIONS OF CONTRACT SPECIFIED IN SECTION VII Yes/ No
9 PLEASE CONFIRM THAT YOU COMPLY WITH ALL CLAUSES SPECIFIED IN THE
SPECIAL CONDITIONS OF CONTRACT SPECIFIED IN SECTION VIII Yes/ No
10 Please confirm that all goods (software and hardware) and services have been included in the price proposal and is complete in all respects without any deviation/ missing items
Yes/ No
11 Please confirm that you have not submitted any alternate proposal Yes/ No
12 PLEASE CONFIRM THAT YOU HAVE NOTED THE SLA GUIDELINES AND PENALTY
CLAUSES APPLICABLE AS SPECIFIED IN APPENDIX C. Yes/ No
13 PLEASE CONFIRM YOU HAVE PROVIDED SUFFICIENT BID SECURITY IN PROPER
FORM AS SPECIFIED IN CLAUSE 20, SECTION II ITB Yes/ No
14 PLEASE CONFIRM YOU HAVE RESPONDED TO ALL MANDATORY TECHNICAL
SPECIFICATION GIVEN IN APPENDIX A Yes/ No
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 191
CESU, Odisha Page 191 Release Date: 27th February 2016
15 PLEASE CONFIRM YOU HAVE RESPONDED TO ALL TECHNICAL SPECIFICATIONS (APPLICATIONS) GIVEN IN THE APPENDIX B.1
Yes/ No
16 PLEASE CONFIRM YOU HAVE RESPONDED TO ALL TECHNICAL SPECIFICATIONS
(HARDWARE) GIVEN IN THE APPENDIX B.2 Yes/ No
17 PLEASE CONFIRM THAT YOU HAVE CHECKED THE FINAL QUOTE PROVIDED IN
APPENDIX D (PRICE PROPOSAL) Yes/ No
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 192
CESU, Odisha Page 192 Release Date: 27th February 2016
Appendix E – Evaluation Methodology
• Alternate bids are not allowed
• Only bids from empanelled (by the nodal agency) bidders shall be evaluated
• The evaluation team will thoroughly review the proposals submitted by various bidders /
consortiums. The broad evaluation will be based as following:-
• Technical Proposal: 50% Weight
• Price Proposal: 50% Weight
• Pre-demo meetings will be conducted with all the bidders
• Each of the bidder will be requested to demonstrate the product and services.
• The technical evaluation will commence post the demonstrations
• Based on multiple parameters, the evaluation team will calculate the technical evaluation
score for each Supplier at the end of this phase
• Utility, in observance of best practices, shall:
• Maintain the bid evaluation process strictly confidential
• Reject any attempts or pressures to distort the outcome of the evaluation, including
fraud and corruption
• Strictly apply only and all of the evaluation and qualification criteria specified in the Bid
document
E.1 Single-Stage: Two-Envelope Bidding Procedure
In the Single-Stage: Two-Envelope bidding procedure, Bidders should submit two sealed
envelopes simultaneously, one containing the Technical Proposal and the other the Price
Proposal, enclosed together in an outer single envelope. Initially, only the Technical Proposals
are opened at the date and time advised in the Bidding Document. The Price Proposals remain
sealed and are held in custody by the Purchaser. The Technical Proposals are evaluated by the
Purchaser. No amendments or changes to the Technical Proposals are permitted. The objective
of the exercise is to allow the Purchaser to evaluate the Technical Proposals without reference to
price.
Bids of Bidders which do not conform to the mandatory requirements may be termed as non-
responsive and will not be evaluated further. Following the approval of the technical evaluation,
and at an address, date and time advised by the Purchaser, the Price Proposals are opened in
public. The Price Proposals are evaluated and, following approval of the price evaluation, the
Contract is awarded to the Bidder whose Bid has been determined to be have scored maximum
in the composite formula as defined below:
Total Score = 50% x Technical Proposal Score + 50% x Price Proposal Score
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 193
CESU, Odisha Page 193 Release Date: 27th February 2016
E.2 Evaluation and Comparison of bids
Initially the Supplier’s responses are reviewed for compliance with the Commercial terms and
conditions. The Suppliers who fail to comply with any of the commercial terms and conditions
mentioned may be termed as non-responsive and will not be evaluated further. For those
Suppliers who have qualified the commercial terms and conditions Technical evaluation will be
conducted followed by the Price-Bid evaluation. The Suppliers who qualify the minimum
technical requirement will be considered for the price-bid evaluation. The price bids will remain
sealed until the technical evaluation is complete.
Technical Evaluation
The technical bid has a weightage of 50%. Technical evaluation will happen in two stages.
Stage-1: Preliminary Evaluation
In stage-1, the following shall be confirmed: Deviations, Submission of Bank Guarantee,
Acceptance of terms and conditions, Acceptance to scope of work and compliance to mandatory
technical requirements (as mentioned in Appendix A). In case the bid doesn’t meet all the
mandatory requirements, the bid shall be termed as non-responsive and will not be evaluated
further
Stage-2
The distribution of weights shall be as follows:
Table 19: Distribution of weights for bid evaluation
No Description Weight
A Technical Proposal 50
1 Technical solution as per Appendix B.1 21
2 Approach & Methodology Nil
3 Project Experience 15
4 Team Details (CV) 6
5 Firm Details 8
B Price Proposal 50
Total Marks 100
Details for each of the above parameters is as mentioned subsequently.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 194
CESU, Odisha Page 194 Release Date: 27th February 2016
A. Technical Proposal: Following is the methodology which shall be used to evaluate the
various parameters under the technical proposal.
A.1 Technical solution Evaluation
Table 20: Score for Technical Evaluation
No Description Maximum
Score
Technical Solution Score 21
i) Appendix B.1 21
Each module has a relative importance based on the functionality/
requirements.
Module Weightage = Relative Importance of Module / Summation of
Relative Importance of Modules * 19 (max module score)
Each module has requirement which has been classified and given
score based on the following:
o Vital: 5
o Essential: 2
o Desirable: 1
Supplier shall submit their response (self evaluation as per the format
mentioned in Appendix D.2.2) against the requirement and score shall
be given as per the following:
o Functionality Not Avail: 0 marks
o Available with modifications / workaround: 2 marks
o Functionality available: 5 marks
ii) G3 Section of SRS (refer Appendix B.2) No Marks
The entire G3 section is the minimum requirement (and hence
mandatory) for the Utility and needs to be supplied as per the
specifications. In case the bidder decides to take any deviation, the
same has to be clearly mentioned under the deviations (D.2.12). Utility
shall decide if the same is acceptable or not. In case the same is not
acceptable, the bid shall be rejected and financial bid of the bidder
shall not be opened.
Bidder’s self-response to the solution (refer A.1 above) shall be as per the manner as indicated
in Appendix-B.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 195
CESU, Odisha Page 195 Release Date: 27th February 2016
The final score for Technical Specifications (G2 Section of SRS) will be calculated as follows:
Table 21: Calculation of Technical Score
Calculation of Score for Technical Solution
Step Description Calculation
1 Each requirement will have maximum
score
Criticality X Options Available for
Supplier
2 Supplier will get the score for each
requirement
Criticality X Options Chosen by
Supplier
3 Weightage Score Calculation per
module
Module Score / Maximum Module
Score * Module weightage
4 Weightage Score Calculation per TS TS Score / Maximum TS Score *
TS weightage
5 Final Score Summation of weightage score of
each module (refer step 3 & 4) of
G2
For qualifying, Supplier must score minimum of 10 marks in G2 Section and should comply with
all requirements of G2 Section . In case the bidder has taken any deviation in G2 Section Utility
shall decide whether the same shall be acceptable or not.
A.2 Approach & Methodology
This section shall be assigned 0 marks.
A.3 Project Experience: Shall be assigned 15 marks. The distribution of marks shall be as
follows:
• Indian Power Utilities Experience in Billing (3 marks)
• Indian Power Utilities Experience in Consumer Indexing (4 marks)
• Project Specific Experience (4 marks)
• IT Experience: Application Modules implemented (4 marks)
A 4 CV: Shall be assigned 6 marks. Following is the list of categorization of requirement of
personnel:
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 196
CESU, Odisha Page 196 Release Date: 27th February 2016
• GIS (Customer Indexing/ Asset Mapping/ Integrated Network Analysis
• Meter Data Acquisition/ Energy Audit
• Billing/Collection/New Connection/Disconnection
• Web Self Service/ Security/ MIS
• Customer Care
A.5 Firm details: Shall be assigned 8 marks. The distribution of marks shall be as follows:
i. Cumulative Turn-Over in the last 3 financial years (2.0 marks)
ii. Level of CMM/CMMI certification (2.0 marks)
Or ISO certification (2.0 marks)
iii. No. of locations in India (2 marks)
Bidders need to score a minimum score of “35” out of 50 in the technical evaluation; else
the bid shall be termed as non-responsive and will not be evaluated further.
B. Price-Bid Evaluation
The Price-Bid evaluation is done only for those bids which are responsive and which have a
Final Technical score which is more than or equal to the minimum score for technical proposal
mentioned in sub-section A above.
The net cost quoted will be calculated as simple addition of all the cost mentioned in the price
proposal (Clause D.3, Appendix D). The price proposal score shall be calculated with following
formula:
Price proposal score = (LP/FP)*50, where
LP: Lowest Price offer; FP: Firm’s Price
C. Total Score
Total score shall be calculated as below:
Total Score = Technical Proposal Score + Price Proposal Score
The bid with the highest overall score will be awarded the project.
CVC Guidelines will be followed regarding the issue of price negotiations with L1 bidder.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 197
CESU, Odisha Page 197 Release Date: 27th February 2016
Appendix F – Geographical & Administrative Information
Following is the list of towns which are included under the scope of work and Map of CESU of
Odisha is attached in the Appendix – P.
Table 22: Geographical & Administrative Information of all the Project Areas in CESU
General Description Detail
Name of town with HQ Bhubaneswar
Name of town with Data Centre Bhubaneswar
Name of Town with Disaster Recovery Centre
Berhampur or any other town to be
selected by CESU
Name of town with Customer Care Centre Bhubaneswar
Table 23: Geographical & Administrative Information of all the Project Areas in CESU
Name of
Project Area
(town)
Number of
Sub-
divisions
Offices
Number
of Other
Offices
Nearest
Railway
Station to HQ
Nearest
Functional
Airport to HQ
Total Area
of
Coverage
(Sq. Km.)
Total
Population
(as per 2001
census)
Cuttack 7 17 Cuttack Bhubaneswar 64 5,87,182
Bhubaneswar 8 38 Bhubaneswar Bhubaneswar 135 6,58,220
Puri 3 16 Puri Bhubaneswar 17 1,57,837
Khordha 2 3 Jatni Road Bhubaneswar 26 39,054
Jatni 1 3 Jatni Road Bhubaneswar 25 57,957
Dhenkanal 1 8 Dhenkanal Bhubaneswar 31 57,677
Angul 1 5 Angul Bhubaneswar 19 38,018
Talcher 1 2 Talcher Bhubaneswar 26 34,998
Kendrapara 2 3 Paradeep Bhubaneswar 11 30,824
Pattamundai 1 5 Dhanmandal Bhubaneswar 24 51,845
Jagatsinghpur 1 7 Gorekhnath Bhubaneswar 18 32,730
Paradeep 1 1 Paradeep Bhubaneswar 32 73,625
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 198
CESU, Odisha Page 198 Release Date: 27th February 2016
Appendix G – List of Offices for WAN Connectivity
List of Offices
Table 24: List of Offices for WAN Connectivity in CESU
Name of the
Town Name of Office at
Level 2*
Name of
Office at
Level 3*
Name of
Office at
Level 4*
Name of
Office at
Level 5*
Name of
Office at
Level 6*
Name of
any other
Office
Cuttack
1. CDD1–Div.Off-I Ranihat (BB) 2. CDD2-Div.Off. - II Badambadi Gridco Colony (BB)
- - - - -
Bhubaneswar Only HQ has Leased Lines from BSNL (Primary) and STPI (Secondary)
Bhubaneswar
1. BCDD1 Powerhouse Colony (BB) 2. BCDD2 IRC Village (BB) 3. BED Rasulgarh (BB)
- - - - -
Puri Puri Electrical Division, (BB)
- - - - -
Khordha Khordha Electric Divi. (BB)
- - - - -
Jatni - - - - - -
Dhenkanal Dhenkanal Electrical Div. Dhenkanal (BB)
- - - - -
Angul Angul Electrical Division, Angul (BB)
- - - - -
Talcher Talcher Electrical Division, Chainpal (BB)
- - - - -
Kendrapara Kendrapara Electrical Div – I (BB)
- - - - -
Pattamundai - - - - - -
Jagatsinghpur Jagatsinghpur Electrical Division (BB)
- - - - -
Paradeep Paradeep Electrical Division (BB)
- - - - -
Note: BB – Broadband Connection
• Levels refer to the position in the hierarchy of the office in the administrative setup assuming
Head Quarter as level 1.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 199
CESU, Odisha Page 199 Release Date: 27th February 2016
Appendix H – Review of Current IT Systems
Utility has reviewed its current IT infrastructure in order to provide complete picture of existing IT
system in the Utility to bidders. Following sections provide detail of applications, hardware &
network available in the Utility.
Existing solutions
The CESU has internally developed and implemented Information Technology (IT) systems for
computerization of various business processes. These are:
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 200
CESU, Odisha Page 200 Release Date: 27th February 2016
Table 25: Details of existing Applications to be Upgraded or Integrated with new System
Ap
plicati
on
Na
me &
fu
ncti
on
al d
es
cri
pti
on
Sta
nd
-alo
ne /In
teg
rate
d A
pp
licati
on
Oth
er
ap
plic
ati
on
s in
teg
rate
d w
ith
?
Fu
ture
Pla
ns (
Ph
ase o
ut
or
co
nti
nu
e)
Ap
plicati
on
Typ
e -
Batc
h (
BC
H),
On
lin
e (
ON
), P
C,
Clien
t S
erv
er
(CS
), W
eb
(W
EB
)
Ho
urs
of
Ap
plic
ati
on
Av
ail
ab
ilit
y t
o B
us
iness
(D
ay
s
X H
ou
rs)
Su
pp
lier
nam
e,
rele
ase
Make
/ V
ers
ion
Nu
mb
er
of
Lic
en
se
s
Pla
tfo
rm
OS
Data
bas
e
A B C D E F G H I J K L
NRBS- SBM Billing System S N Y BCH 250 NA NA NA FoxPro Win FoxPro
EBSYS- Non-SBM Billing System I Y Y BCH 250 NA NA NA FoxPro Win FoxPro
Fixed Asset Information System
(Both Online & Offline) S N Y BCH
Once
in
Year
NA NA NA VB,ASP Win Oracle
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 201
CESU, Odisha Page 201 Release Date: 27th February 2016
Consumer Billing and Payment Information I Y Y ON 250 NA NA NA ASP Win Oracle
Cash Collection Management System
(Both Online & Offline) I Y Y ON 150 NA NA NA VB,ASP Win Oracle
Billing and Payment information to the high value consumers through e-Mail and SMS
I Y Y BCH,
ON 250 NA NA NA Java
Win,
Linux Oracle
New Service Connection Management System I Y Y ON 150 Phoeni
x NA 1 Java
Win,
Linux Oracle
Advanced Complaint Handling Procedure I Y Y ON 250 Phoeni
x NA 1 Java Win Oracle
KYC (Know Your Consumer) Data Entry S N Y ON 150 NA NA NA ASP Win Oracle
Management Information System (MIS) I Y Y ON 250 NA NA NA ASP,
Java
Win,
Linux Oracle
Meter Testing & MRT Squad Operation Management I Y Y BCH,
ON NA NA NA Java
Win,
Linux Oracle
Load Monitoring System (schedule vs. Drawal) I Y Y BCH,
ON NA NA NA NA Java
Win,
Linux Oracle
CWTT (Consumer wise Transformer Tagging) S N Y BCH 250 NA NA NA FoxPro Dos,
Win FoxPro
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 202
CESU, Odisha Page 202 Release Date: 27th February 2016
Mi-Power software for Consumer-Indexing based energy audit.
S N Y BCH 250 PRDC NA NA C, C++ Win Access
ASD Software - Additional Security Deposit
Calculation and Notifications S N Y BCH
Once
in a
year
PRDC NA NA FoxPro Win FoxPro
Software workflow for requisition of meters for 3-
phase consumers from requisition to installation
process handling
I Y Y BCH,
ON 250 PRDC NA NA ASP Win Oracle
Human Resource Information System. S N Y BCH,
ON 250 NA NA NA Java
Win,
Linux Oracle
Tally Software S N Y BCH 250 Tally ERP
Tally
Softwar
e
Win Prop.
DB
Capacity Building Management System S N Y BCH 250 NA NA NA JAVA Win/
Linux Oracle
Collaboration with SREI Sahaj e-Village Limited for
Bill Collection in remote areas operated by OCAC.
(IT Integration provided at division level)
I Y Y ON 250
Govt
Of
Odisha
NA NA
Service provided by Govt of
Odisha Online Bill Payment through web via
<www.orissaonline.gov.in> (OCAC/ OeSL)
(IT Integration provided at division level)
I Y Y ON 250
Govt
Of
Odisha
NA NA
Bill Payment through via ECS (Direct Debit)
(IT Integration provided at division level) I Y Y BCH 250 RBI NA NA FoxPro Win
MS
Access,
FoxPro
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 203
CESU, Odisha Page 203 Release Date: 27th February 2016
Single Sign On (SSO) I Y Y ON 250 NA NA NA Java Win,
Linux Oracle
Interfacing Tools S N Y ON 24Hrs NA NA NA Java/
FTP Linux Oracle
Reports, Statistics and Data Analysis I Y Y ON 24Hrs NA NA NA ASP WIN Oracle
Email Service I N Y WEB 24Hrs Service provided by Gmail
File Transfer Protocol – Secured Platform for data
file movement between Divisions, Circles and HQ I Y Y WEB 24Hrs MS NA NA
Microsof
t Win Nil
Official Website I Y Y WEB 24Hrs Cyber
Soft NA NA
ASP,
HTML Win Oracle
Electricity Theft Eradication Database S N Y WEB 250 NA NA NA Java Win,
Linux Oracle
Billing Engine (Revenue Assurance Module) I Y Y WEB 250 NA NA NA Java Win,
Linux Oracle
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 204
CESU, Odisha Page 204 Release Date: 27th February 2016
Ap
plicati
on
Na
me &
fun
cti
on
al d
esc
rip
tio
n
Th
ird
Pa
rty T
oo
ls
An
y r
un
tim
e lic
en
ses
ex,
Testi
ng
to
ols
To
tal F
TE
s
Lo
cati
on
of
Reso
urc
es
Do
cu
men
tati
on
Av
ailab
le
(Y/N
)
Nu
mb
er
of
Co
ncu
rren
t
Users
(H
igh
:10
0+
, M
ed
:10
-
100, L
ow
:<10)
Co
mm
en
ts
A M N O P Q R S
NRBS- SBM Billing System Nil N NA IT N Med Nil
EBSYS- Non-SBM Billing System Nil N NA IT N Med Nil
Fixed Asset Information System (Both Online & Offline)
Nil N NA IT N Low Nil
Consumer Billing and Payment Information Nil N NA IT N Med Nil
Cash Collection Management System (Both Online & Offline)
Nil N NA IT N Med Nil
Billing and Payment information to the high value consumers through e-Mail and SMS
Nil N NA IT N Med Nil
New Service Connection Management System Nil N NA IT N Med Nil
Advanced Complaint Handling Procedure Nil N NA IT N Med Nil
KYC (Know Your Consumer) Data Entry Nil N NA IT N Med Nil
Management Information System (MIS) Nil N NA IT N Med Nil
Meter Testing & MRT Squad Operation Management Nil N NA IT N Med Nil
Load Monitoring System (schedule vs. Drawal) Nil N NA IT N Med Nil
CWTT (Consumer wise Transformer Tagging) Nil N NA IT N Med Nil
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 205
CESU, Odisha Page 205 Release Date: 27th February 2016
Mi-Power software for Consumer-Indexing based energy audit.
Nil N NA IT N High Nil
ASD Software - Additional Security Deposit Calculation and Notifications
Nil N NA IT N Med Nil
Software workflow for requisition of meters for 3-phase consumers from requisition to installation process handling
Nil N NA IT N Med Nil
Human Resource Information System. Nil N NA IT N Med Nil
Tally Software Nil N NA IT N High Nil
Capacity Building Management System Nil N NA IT N Med Nil
Collaboration with SREI Sahaj e-Village Limited for Bill Collection in remote areas operated by OCAC. (IT Integration provided at division level)
Nil N NA IT N Med Nil
Online Bill Payment through web via <www.orissaonline.gov.in> (OCAC/ OeSL) (IT Integration provided at division level)
Nil N NA IT N Med Nil
Bill Payment through via ECS (Direct Debit) (IT Integration provided at division level)
Nil N NA IT N Med Nil
Single Sign On (SSO) Nil N NA IT N High Nil
Interfacing Tools. Nil N NA IT N Med Nil
Reports, Statistics and Data Analysis Nil N NA IT N Med Nil
Email Service Nil N NA IT N High Nil
File Transfer Protocol – Secured Platform for data file
movement between Divisions, Circles and HQ Nil N NA IT N
Med Nil
Official Website Nil N NA IT N High Nil
Electricity Theft Eradication Database Nil
N NA IT N Low Nil
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 206
CESU, Odisha Page 206 Release Date: 27th February 2016
Technical evaluation – Existing IT Solution
The summary of evaluation performed during IT system review is presented below in a pictorial form. The application and platform details
should be mentioned and suitably rated (as per the details mentioned below the table). All the below mentioned applications and platforms
need to be integrated with the new proposed system by the Supplier:
Table 26: Technical Evaluation of Existing IT Applications A
pp
licati
on
Pla
tfo
rm
Fu
ncti
on
ality
Tech
no
log
y
Usab
ilit
y
Main
tain
-ab
ilit
y
Inte
gra
tio
n
wit
h
oth
er
syste
ms
Rem
ark
NRBS- SBM Billing System FoxPrp √ √ √ √ √ √
EBSYS- Non-SBM Billing System FoxPrp √ √ √ √ √ √
Fixed Asset Information System
(Both Online & Offline)
Oracle,ASP, Access
√ √ √ √ √ √
Consumer Billing and Payment Information Oracle,ASP,JSP
√ √ √ √ √ √
Cash Collection Management System
(Both Online & Offline)
Oracle, VB, Access
√ √ √ √ √ √
Billing and Payment information to the high value consumers through e-Mail and SMS
Oracle, Java, FoxPro
√ √ √ √ √ √
Advanced Complaint Handling Procedure Oracle, JSP, Java
√ √ √ √ √ √
KYC (Know Your Consumer) Data Entry FoxPro √ √ √ √ √ √
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 207
CESU, Odisha Page 207 Release Date: 27th February 2016
Management Information System (MIS) Oracle, ASP, Java
√ √ √ √ √ √
Meter Testing & MRT Squad Operation Management Oracle, ASP, Java
√ √ √ √ √ √
Load Monitoring System (schedule vs. Drawal) Oracle, ASP, Java
√ √ √ √ √ √
CWTT (Consumer wise Transformer Tagging) FoxPro √ √ √ √ √ √
Mi-Power software for Consumer-Indexing based energy audit.
Oracle, VB, Java
√ √ √ √ √ √
ASD Software - Additional Security Deposit Calculation and
Notifications
Oracle, ASP √ √ √ √ √ √
Software workflow for requisition of meters for 3-phase
consumers from requisition to installation process handling
Oracle,Java √ √ √ √ √ √
Human Resource Information System. Oracle, Java √ √ √ √ √ √
Tally Software Tally DB √ √ √ √ √ √
Capacity Building Management System Oracle,Java √ √ √ √ √ √
Collaboration with SREI Sahaj e-Village Limited for Bill
Collection in remote areas operated by OCAC.
(IT Integration provided at division level)
Dot Net, Oracle √ √ √ √ √ √
Online Bill Payment through web via
<www.orissaonline.gov.in> (OCAC/ OeSL)
(IT Integration provided at division level)
Dot Net, Oracle √ √ √ √ √ √
Bill Payment through via ECS (Direct Debit)
(IT Integration provided at division level)
FoxPro, Access √ √ √ √ √ √
Single Sign On (SSO) Oracle, Java √ √ √ √ √ √
Interfacing Tools. Oracle, Java √ √ √ √ √ √
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 208
CESU, Odisha Page 208 Release Date: 27th February 2016
Reports, Statistics and Data Analysis Oracle, Java √ √ √ √ √ √
Email Service Google √ √ √ √ √ √
File Transfer Protocol – Secured Platform for data file
movement between Divisions, Circles and HQ
Linux √ √ √ √ √ √
Official Website HTML √ √ √ √ √ √
Electricity Theft Eradication Database Oracle, Java √ √ √ √ √ √
√ Meets Expectation √√ Meets Current and Future Expectations √√√ Exceeds Expectations
x Below expectation x x Poor x x x Very poor / Functionality not available
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 209
CESU, Odisha Page 209 Release Date: 27th February 2016
Existing Hardware
Table 27: Details of existing Hardware to be Upgraded or Integrated with new system H
ard
ware
(S
erv
er/
P
C/
Sto
rag
e D
evic
es/
UP
S/
Netw
ork
ing
eq
uip
men
ts (S
wit
ch
es,
Ro
ute
rs)/
Pri
nte
rs e
tc.)
Nu
mb
er/
Un
it
Make
Mo
del
Mem
ory
(R
AM
) (C
ap
acit
y a
nd
Typ
e)
Sto
rag
e (
HD
D)
(Cap
acit
y a
nd
Typ
e)
Pro
cesso
r (N
os &
typ
e)
Typ
e/ IO
S R
ele
as
e
Nu
mb
er
of
Po
rts
Typ
e o
f P
ort
s
Yea
r o
f P
urc
ha
se
Sh
ari
ng
w
ith
o
ther
ap
plicati
on
s
or
for
exclu
siv
e u
se
Servers
IBM X3400 2 IBM X3400 4 GB 130 GB 1, Intel
XEON NA
6 2 NIC,
4 USB
2008
IBM X3550 M2 1 IBM X3550 4 GB 278 GB 1, Intel
XEON NA
6 2 NIC,
4 USB 2009
DELL PowerEdge 2 DELL R-910 32 GB 1.6 TB 1, Intel
XEON NA
10 4 NIC
6 USB 2014
WorkStation PC
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 210
CESU, Odisha Page 210 Release Date: 27th February 2016
Hard
ware
(S
erv
er/
P
C/
Sto
rag
e D
evic
es/
UP
S/
Netw
ork
ing
eq
uip
men
ts (S
wit
ch
es,
Ro
ute
rs)/
Pri
nte
rs e
tc.)
Nu
mb
er/
Un
it
Make
Mo
del
Mem
ory
(R
AM
) (C
ap
acit
y a
nd
Typ
e)
Sto
rag
e (
HD
D)
(Cap
acit
y a
nd
Typ
e)
Pro
cesso
r (N
os &
typ
e)
Typ
e/ IO
S R
ele
as
e
Nu
mb
er
of
Po
rts
Typ
e o
f P
ort
s
Yea
r o
f P
urc
ha
se
Sh
ari
ng
w
ith
o
ther
ap
plicati
on
s
or
for
exclu
siv
e u
se
IBM IBM 512 MB 40 GB P3 NA 3 1 NIC
2 USB 2000
DELL DELL OptiPlex 1 GB 160 GB Core i3 NA 11 1 NIC
10 USB 2011-12
ACER ACER 512 MB 40 GB P3 NA 3 1 NIC
2 USB 2000
Lenovo Lenovo 1 GB 166 GB Intel Core
2 Duo NA
5 1 NIC
4 USB 2008-9
Compaq Compaq 512 MB 40 GB P4 NA 3 1 NIC
2 USB 2000
Storage & Backup
Devices
EMC(2)AX4 Clarion 1 AX4 Clarion NA 1.3 TB NA NA NA NA 2009
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 211
CESU, Odisha Page 211 Release Date: 27th February 2016
Hard
ware
(S
erv
er/
P
C/
Sto
rag
e D
evic
es/
UP
S/
Netw
ork
ing
eq
uip
men
ts (S
wit
ch
es,
Ro
ute
rs)/
Pri
nte
rs e
tc.)
Nu
mb
er/
Un
it
Make
Mo
del
Mem
ory
(R
AM
) (C
ap
acit
y a
nd
Typ
e)
Sto
rag
e (
HD
D)
(Cap
acit
y a
nd
Typ
e)
Pro
cesso
r (N
os &
typ
e)
Typ
e/ IO
S R
ele
as
e
Nu
mb
er
of
Po
rts
Typ
e o
f P
ort
s
Yea
r o
f P
urc
ha
se
Sh
ari
ng
w
ith
o
ther
ap
plicati
on
s
or
for
exclu
siv
e u
se
UPS & Battery
System
Liebert Emerson 6 Kva 1 Liebert Emerso
n NA NA NA NA
NA NA NA
Emerson 2 Kva 20 Emerson NA NA NA NA NA NA NA
Printers
Lipi 6306 & T6050 14 Lipi 6306
T6050
2007-08
Wep P-1000 5 Wep P-1000 2007-08
Machines
KIOSK NIL
IDMS along with NIL
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 212
CESU, Odisha Page 212 Release Date: 27th February 2016
Hard
ware
(S
erv
er/
P
C/
Sto
rag
e D
evic
es/
UP
S/
Netw
ork
ing
eq
uip
men
ts (S
wit
ch
es,
Ro
ute
rs)/
Pri
nte
rs e
tc.)
Nu
mb
er/
Un
it
Make
Mo
del
Mem
ory
(R
AM
) (C
ap
acit
y a
nd
Typ
e)
Sto
rag
e (
HD
D)
(Cap
acit
y a
nd
Typ
e)
Pro
cesso
r (N
os &
typ
e)
Typ
e/ IO
S R
ele
as
e
Nu
mb
er
of
Po
rts
Typ
e o
f P
ort
s
Yea
r o
f P
urc
ha
se
Sh
ari
ng
w
ith
o
ther
ap
plicati
on
s
or
for
exclu
siv
e u
se
Automatic Token
Dispenser Machine
Cash/ Cheque
Collection KIOSK
NIL
Spot Billing Machine
with Printer
Analogic 200 Analogic Micro
PSD 16 MB Nil
1 RJ 45 2011
Billing System
VisionTek
(LinkWell) 500
VisionTe
k 93 POS
256
RAM,
2 GB
(data
Card)
ARM 9
2
3
RJ 45
USB 2012-13 Billing System
Server Racks (42 U) 1 APW
Rack 1 NA NA NA NA
NA
NA 2009
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 213
CESU, Odisha Page 213 Release Date: 27th February 2016
Hard
ware
(S
erv
er/
P
C/
Sto
rag
e D
evic
es/
UP
S/
Netw
ork
ing
eq
uip
men
ts (S
wit
ch
es,
Ro
ute
rs)/
Pri
nte
rs e
tc.)
Nu
mb
er/
Un
it
Make
Mo
del
Mem
ory
(R
AM
) (C
ap
acit
y a
nd
Typ
e)
Sto
rag
e (
HD
D)
(Cap
acit
y a
nd
Typ
e)
Pro
cesso
r (N
os &
typ
e)
Typ
e/ IO
S R
ele
as
e
Nu
mb
er
of
Po
rts
Typ
e o
f P
ort
s
Yea
r o
f P
urc
ha
se
Sh
ari
ng
w
ith
o
ther
ap
plicati
on
s
or
for
exclu
siv
e u
se
Switches
DLink (Layer 3) 1 DLink DGS
3610
V10.3
(5p1)
24 2012
DLink (Layer 2) 2 DLink DGS
3100 3.60.28
24 2012
Routers 1 CISCO 1841
Modular 12.4
2 2009
Firewall 1 SonicWa
ll
NSA
2400 5.8.1.13-10
6 2009
Cable/Optical Fiber Nil
KVM Switch 1 DLink NA NA 8 2009
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 214
CESU, Odisha Page 214 Release Date: 27th February 2016
Appendix I – List of Manuals/Business Processes to be converted (data-entry) into electronic form
The following manuals/business processes need to be converted into electronic form
Details will be provided during the preparation of ‘To Be document’ with the Selected ITIA.
Table 28: List of Manuals/ Business Process to be converted into Electronic Form in CESU
Name of the application/ business process that requires data migration into the proposed applications
Type (Standalone application/ Integrated application/ Manual Business Process)
If Integrated, what are the other applications integrated with this?
Database (Access, SQL etc.)
Data Format (Access Table, Paper forms, Excel Sheets etc.)
Quantity per period (e.g. number of bills generated per month etc.)
Volume of Data (1000 records, 5000 pages etc)
Data mirroring/ replication needed?
Comments
MIS
Energy Audit
Billing
Metering
Collection
New Connection / Disconnection
Enforcement And Respective Assessment
Meter Data Acquisition
Asset Management / Maintenance Management
Web Self Service
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 215
CESU, Odisha Page 215 Release Date: 27th February 2016
Appendix J – Review of Current Business Processes
1. AMR & Meter Data Acquisition and Energy Audit System:
While Input / output (exchange) meters are being installed at all locations and it is nearing
completion, meters for energy audit purpose are available only at selected locations.
Readings from these are downloaded manually and processed using primitive tools like
Excel or manually for the purpose of energy audit and identifying high loss area. Current
process is too cumbersome and granularity is not up to desired level.
2. New Connection: With respect to process being followed, this can be divided into two
broad categories:
a. Single phase connection in Bhubaneswar: Prospective consumer (applicant)
approaches Customer Care Center & call center located at Power House Square,
Bhubaneswar. The Application Form are registered by Customer Care Center
executive in new connection service module provided by M/s Phoenix IT Solutions
Ltd. Applicant will be asked to submit required documents and an
acknowledgement No. is given to the applicant for subsequent follow up.
Required documents include an agreement between utility and applicant.
Applicant is also required to provide neighboring consumer numbers. These
documents would be scrutinized by CESU officers for completeness. If the
documents are in order (if document are incomplete then either consumer has to
complete it or the request gets rejected) then based on address at which
connection is required, respective JE is sent the New Application file. Such
dispatches are done once a day by M/s Phoenix IT Solutions Ltd.
Concern JE does the field survey and sends his recommendations. These
recommendations would contain details like -
1. Availability of LT network and/or augmentation, if required
2. Any details gathered from field for existence of earlier connections for same
premises.
In case LT network is available then commercial officer in concerned sub-division
will ascertain pending of any earlier dues on same premises. Applicant is required
to clear earlier dues, if any. After file is cleared by both JE (for technical feasibility)
and commercial officer then it is sent back to Customer Care Center. Customer
Care Center generated demand note and inform to the consumer to pay it at the
collection window situated within Customer Care Center. The breakup details of
demand note charges are available in new connection service module. Customer
Care Center also manages inventory of single phase meters and services lines for
cases cleared for energization. Meter, service line and requisite material is issued
for installation and energization of connection. After energization, physical file is
sent to divisional office for entering details in billing system. Consumer No. is
generated by billing system and same is recorded on file. The completed file is
again sent back to Customer Care Center to capture the energization details and
consumer No. in new connection service module.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 216
CESU, Odisha Page 216 Release Date: 27th February 2016
In case existing network is to be augmented then cost is borne by utility. However,
if network is to be laid only for one new applicant then cost of network is to be
borne by applicant.
During all intermediate stages of requests, M/s Phoenix IT Solutions Ltd.,
manually tracks the status of the request and updates the system so that it can be
informed to consumer.
b. Three phase connection and single phase connection in Cuttack: The process is
similar to single phase connection at Bhubaneswar, except that complete
processing is done in respective divisional office and demand note charges are
collected manually (not in system) and manual receipt is given to consumer.
Applicable network augmentation charges are collected from applicant before
augmenting the network, if such charges are payable by consumer.
3. Disconnection & Dismantling:
Disconnection is a process of discontinuing the electric supply to the premise. This is
done by disconnecting the supply from pole and removing the meter and service line.
This also amounts to termination of agreement between consumer and utility.
The consumer applies for the disconnection with an application for the request at the
Customer care center (for single phase cases in Bhubaneswar). The disconnection case
is registered checking that there should not be any dues on the consumer. If any, would
be settled before disconnection. The meter is removed and details entered in billing
system to stop subsequent billing. Final bill is generated manually after getting reading on
the date of removal.
After settlement of dues of final bill, consumer has to give separate request for refund of
security deposit.
4. Customer Indexing, Asset Management, Maintenance Management and Network
Analysis
Currently customer indexing is more on the basis of geography and route for reaching to
consumer for reading, billing and collection. Assets management and network analysis is
manual and mostly triggers from consumer requests for new connection and load
enhancement.
5. Centralized Customer Care Services and customer call center applications:
In addition to new connection requests, Customer Care Center/ call center registers all
kinds of consumer requests (supply as well as commercial complaints & requests from
single phase consumers of Bhubaneswar. Currently, it has four seats and service is
provided on 24x7 basis. The cash collection timing is 8 AM to 8 PM.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 217
CESU, Odisha Page 217 Release Date: 27th February 2016
Complaint is followed up with respective offices for resolution. Below mentioned types of
complaints are managed by the Customer care Center:
a. Reading/ billing/ collection complaints
b. Meter related complaints (slow/ fast/faulty/burnt meter)
c. Attribute change (Load reduction/ category change/ name change)
d. Reconnection (After disconnection due to non-payment)
e. Supply Interruption
f. Voltage Problem
g. Power Theft in neighborhood etc.
While the request registration, follow up and status update is done by call center
executive, actual processing of such requests/ complaint is outside the system. Only
status is maintained in call center.
6. Management Information System (MIS):
The billing and collection data are collected from divisions and migrated to Centralised
Database at CESU HQ IT Center and various in-house built tools are used to generate
MIS reports.
7. Identity and Access Management System:
Presently no centralized User Access control is implemented. Active Directory and role
based policies are required to be strengthened. The domain and e-mail services are
provided by Google whereas website is hosted by Cybersoft and regular updation are
done at HQ IT Center.
8. System Security Requirement, Antivirus and Firewall System:
Currently Sonic UTM firewall is implemented and QuickHeal antivirus license for 200+
clients are in place. It is required to be strengthened and re-implemented for proposed
data centers, servers and end user devices.
Processes like security policy and its implementation are in building up stage.
9. Development of Commercial Database of Consumers:
The activity will require migration of consumer database, call center open requests,
security deposit data, transaction data in files i.e. payment and requests being processed,
meters issued but not installed, etc. Since there is distinct possibility of Franchisee Towns
directly coming under CESU control, need for migration of data for remaining town may
arise any time during the project life cycle, which is five years from go live.
10. Metering:
Electricity supply to any consumer is to be given through correct metering.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 218
CESU, Odisha Page 218 Release Date: 27th February 2016
Since Single phase consumers are billed through SBM, metering data for single phase
consumers is first downloaded in SBM. Consumers are grouped based on geographical
area and routes. On average, in one SBM around 1000 consumer records are uploaded.
Reading gets downloaded at the time of billing data download from SBM.
For non-SBM cases, which are around 15K for two towns, previous month reading data is
printed in hard copy for specific cases. Otherwise reading is taken through CMRI and
same is uploaded in system for billing
11. Billing:
Bills are generated by the CESU on monthly basis. Spot Billing Machine (SBM) is used
for single phase consumers whereas for three phase consumers, billing is done at
Division offices.
SBM (Spot Billing Machine) Consumers
In the consumer premises Meter Reader punches the current month’s reading into the
SBM machine and spot bill is generated. At the end of the billing cycle data is uploaded
into Divisional billing system for month-end processing along with collection and other
data. MIS gets generated and the data also gets reflected under consumer account in the
website. However, especially at Bhubaneswar, Cuttack and Paradeep, SBM billing data is
uploaded on daily basis into Divisional billing system and Centralised web server for Web
display and SMS / eMail to consumers regarding their current Billing.
Non-SBM Consumers
Currently Meter reading is brought in through CMRI device or manually and Reading is
then punched in the divisional billing system for bill generation. Bills are generated in
Division offices using common billing software. After verification of the bills, printing is
done and distributed to consumers. Subsequently, billing data is uploaded in the
Centralised web server for Web display and SMS / eMail to consumers regarding their
current Billing.
12. Collection: Payment is made by the consumers through any of the methods mentioned
below and Collection information is sent to the consumers through SMS and eMail.
a. Collection Centers (Computerised Online)
b. Collection Centers (Computerised Offline)
c. Collection Centers (Manual)
d. Collection through Web
e. ECS Collection
f. Manual Collection by meter readers
g. Collection through ATP Machines
h. Collection Drop Boxes
Collection through Website:
In this method, consumers pay the bills online in CESU’s website through Odisha
government Payment Gateway (OdishaOnline). In this regard, OdishaOnline Server and
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 219
CESU, Odisha Page 219 Release Date: 27th February 2016
CESU Centralised Servers are integrated for required consumer information, Billing
information and payment information exchange. Collection details can be viewed and
downloaded from the website by the concerned officers at division level using their login
credentials.
Cash Collection Centers (Offline):
In this method, consumers pay the bills at the cash collection center and system
generated offline receipts are issued to the consumers from the stand-alone systems due
to unavailability of network.
Cash Collection Centers (Online):
In this method, the payment transactions are made in the Centralised Server and System
generated online receipts are issued to the consumers at the cash collection centers.
Once the payment is received then the divisional billing system is updated and it also
instantly reflects in the consumer data online.
ECS Collection:
ECS functionality is currently available only for domestic consumers. To opt for this
option, first consumer has to register for ECS option and provide his / her bank details
and specify limit for due amount. These details are validated (one time) and ECS option
is activated. In this method, CESU presents the bill to the bank via RBI; the amount is
debited from the consumer’s bank account and credited directly to CESU’s bank account.
All successful ECS transaction cases are intimated by RBI to CESU and the same are
updated in the Divisional billing system.
For Manual collections, DC sheets and the used Money Receipt Books are returned to
the Division office where the DC sheets are digitised after due verification and updated in
the Divisional billing system.
The Processed data is finally submitted to the corporate head office after the month-end
processing. MIS gets generated and the data also gets reflected under consumer account
in the website.
13. Document Management System:
Presently all consumer related documents are stored in physical hardcopy file. Only on
need basis documents are scanned selectively. In the proposed process documents are
required to be scanned as part of in-line process at the stage where it is received/
generated to completely eliminate physical movement of file for processing purpose.
14. Web Self Service & Mail / Messaging System:
Website: CESU Website is maintained by CESU HQ IT staff. Initially it was developed
by Cyber Wizard Technologies.
Mail / Messaging System: For the E-mail the Google services are subscribed and
domain name is hosted on cloud under agreement with Google.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 220
CESU, Odisha Page 220 Release Date: 27th February 2016
15. Enterprise Management System and Network Management System:
Automated proactive monitoring of IT systems and communication network is not
implemented. It is presently performed manually by the IT Staff.
16. Data Warehouse System with MIS application:
There is no data Warehouse System. However, locally build Oracle 10g R2 based system
is operational to meet the requirements of MIS and analysis of consumer related data.
The data in soft form is available since 2005.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 221
CESU, Odisha Page 221 Release Date: 27th February 2016
Number of Consumer & Asset Information in CESU
Following is the consumer related information of the Utility and the Project Areas proposed in the scope of work for the previous financial year.
Table 29: Consumer Information for Utility and Project Areas
Consumer
Information (Last
Financial Year)
UTILITY
Number of
Metered
Consumers
Estimated Number
of Unmetered
Consumers
Metered
Sales
Assessed
Energy
Sales
Total Sales Connected
Load Billing Collection
No. No. MUs MUs MUs kW Rs. Cr. Rs. Cr.
LT Domestic 1,206,359 315,553 1064.69 654.6 1719.29 1,845,260 652.3497 541.7083
LT Commercial 90,684 25,379 398.32 100 498.32 352,563 327.4706 301.1357
LT Industry 8,646 640 104.68 7.81 112.49 146,105 81.1064 84.258
LT Agriculture 4,689 6,016 3.6 23.6 27.2 52,703 4.0483 3.2013
LT Others 7,340 4,018 77.02 47.81 124.83 67,834 79.1312 61.5796
HT Railways 5 0 244.36 0.00 244.36 53,000 155.60 121.62
HT Industrial 404 8 1486.59 6.81 1493.4 579,513 830.7552 837.5554
HT Commercial 458 16 273.17 12.66 285.83 146,097 174.6809 172.5077
HT Others 481 63 146.04 11.28 157.32 76,923 87.6831 77.6036
Total 1,319,066 351,693 3798.47 864.57 4663.04 3,319,998 2392.83 2201.1681
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 222
CESU, Odisha Page 222 Release Date: 27th February 2016
Metering, Consumer Indexing and Asset Mapping Information
Following is the metering status of Utility and the Project Areas proposed in the work as on Last Financial Year
Table 30: Metering Information for Utility and Project Areas
Project Area
Consumers
UTILITY
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with
Static
Meters
Metered Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
LT Domestic No. 0 0 0 0 138,264 202,775 13,775 354,814
LT Commercial No. 0 0 0 0 28,712 29,911 2,689 61,312
LT Industry No. 0 0 0 0 2,536 132 32 2,700
LT Agriculture No. 0 0 0 0 104 37 259 400
LT Others No. 0 0 0 0 2,111 1,216 481 3,808
HT Railways No. 0 0 0 0 3 0 0 3
HT Industrial No. 0 0 0 0 222 0 5 227
HT Commercial No. 0 0 0 0 994 0 7 1,001
HT Others No. 0 0 0 0 824 0 45 869
Total 138,264 202,775 13,775 354,814
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 223
CESU, Odisha Page 223 Release Date: 27th February 2016
Following is the status of consumer indexing & asset mapping in the Utility & Project Areas proposed in the work as on Last financial Year
Table 31: Consumer Indexing and Asset Mapping Information for Utility and Project Areas
Project Area Name:
UTILITY, Cuttack, Bhubaneswar, Puri, Khordha,
Jatni, Dhenkanal, Angul, Talcher, Kendrapara,
Pattamundai, Jagatsinghpur, Paradeep.
% of
Indexing
completed
Number of
Consumers
Covered
Date of
survey
completed
Specify File,
Formats of the
Output (e.g.
XML, CSV etc.)
Specify consumers/
assets covered (e.g.
HT, LT, poles, lines,
switches etc.)
Consumer Indexing
HT
GIS Based % Nil Nil Nil Nil
Non-GIS Based % Nil Nil Nil Nil
LT
GIS Based % Nil Nil Nil Nil
Non-GIS Based % Nil Nil Nil Nil
Asset Mapping
66 kV System
GIS Based % Nil Nil Nil Nil
Non-GIS Based % Nil Nil Nil Nil
33 kV System
GIS Based % Nil Nil Nil Nil
Non-GIS Based % Nil Nil Nil Nil
11 kV System
GIS Based % Nil Nil Nil Nil
Non-GIS Based % Nil Nil Nil Nil
LT System
GIS Based % Nil Nil Nil Nil
Non-GIS Based % Nil Nil Nil Nil
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 224
CESU, Odisha Page 224 Release Date: 27th February 2016
Assets (Last Financial Year) Utility
Total Number of EHV Sub-stations feeding the Project Area
Numbers 29
Total Number of Power Transformers Numbers 82
Total Capacity of Power Transformers MVA 3480.5
Total Number 66/33 kV Feeders Numbers 121
Total Length of 66/33 kV Feeders (Overhead) kM 2900.08
Total Length of 66/33 kV Feeders (Under-ground) kM
Total Number of 66/11 kV and 33/11 kV Sub-stations feeding the Project Area
Numbers 191
Total Number of Power Transformers Numbers 445
Total Capacity of Power Transformers MVA 1894.43
Total Number 11 kV Feeders Numbers 652
Number of Metered 11 kV Feeders Numbers 540
Total Length of 11 kV Feeders (Overhead) kM 25158.94
Total Length of 11 kV Feeders (Under-ground) kM 3.75
Total Length of LT Lines (Overhead) kM 39891.07
Total Length of LT Lines (Under-ground) kM
Total Number of Distribution Transformers Numbers 48184
Number of Metered Distribution Transformers Numbers 13334
Total Capacity of Distribution Transformers MVA 2688.96
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 225
CESU, Odisha Page 225 Release Date: 27th February 2016
Assets (Last Financial Year) Unit Cuttack Bhubaneswar
Puri Khordha Jatni Dhenkanal
Total Number of EHV Sub-stations feeding the Project Area
Numbers 3 4 1 1 1 1
Total Number of Power Transformers Numbers 9 11 3 3 3 3
Total Capacity of Power Transformers MVA 386 627.00 103 120 120 120
Total Number 66/33 kV Feeders Numbers 48 67 10 4 6 4
Total Length of 66/33 kV Feeders (Overhead)
kM 122.75 221.595 10 7 35 28
Total Length of 66/33 kV Feeders (Under-ground)
kM 3.25 0.4 1 0 0 0
Total Number of 66/11 kV and 33/11 kV Sub-stations feeding the Project Area
Numbers 22 30 4 2 2 1
Total Number of Power Transformers Numbers 48 67 10 4 6 4
Total Capacity of Power Transformers MVA 395.15 579.3 80 41 24.75 24.15
Total Number 11 kV Feeders Numbers 91 127 16 7 6 7
Number of Metered 11 kV Feeders Numbers 45 79 16 2 5 7
Total Length of 11 kV Feeders (Overhead) kM 479.75 1367.05 115.08 133.6 32.5 73.3
Total Length of 11 kV Feeders (Under-ground)
kM 3.75 6.55 0.3 0 0 0.2
Total Length of LT Lines (Overhead) kM 1053.09 2501.476 324 83 57 114
Total Length of LT Lines (Under-ground) kM 0 0 0 0 0 0
Total Number of Distribution Transformers Numbers 2238 5,074 582 139 69 165
Number of Metered Distribution Transformers
Numbers 246 1235 208 31 5 0
Total Capacity of Distribution Transformers MVA 489 755.291 80.506 14.81 10.09 24.073
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 226
CESU, Odisha Page 226 Release Date: 27th February 2016
Assets (Last Financial Year) Unit Angul Talcher Kendrapara Pattamundai Jagatsinghpur Paradeep
Total Number of EHV Sub-stations feeding the Project Area
Numbers 1 1 1 1 1 1
Total Number of Power Transformers Numbers 2 3 1 3 3 3
Total Capacity of Power Transformers MVA 80 80 40 52.5 60 52.50
Total Number 66/33 kV Feeders Numbers 7 4 5 2 4 3
Total Length of 66/33 kV Feeders (Overhead)
kM 10 11 2 2.1 5 15.6
Total Length of 66/33 kV Feeders (Under-ground)
kM 0.4 0.3 4
Total Number of 66/11 kV and 33/11 kV Sub-stations feeding the Project Area
Numbers 3 1 1 1 1 1
Total Number of Power Transformers Numbers 7 4 5 2 4 3
Total Capacity of Power Transformers MVA 32.25 24.15 29.15 8.15 20.65 17.6
Total Number 11 kV Feeders Numbers 7 3 5 2 4 1
Number of Metered 11 kV Feeders Numbers 6 3 5 2 4 1
Total Length of 11 kV Feeders (Overhead) kM 72.00 40 28 48.9 68.75 45.1
Total Length of 11 kV Feeders (Under-ground)
kM 0.65 0.5 0.3 0.25 1
Total Length of LT Lines (Overhead) kM 253 90.75 199.01 136.3 134 51.2
Total Length of LT Lines (Under-ground) kM 0.3
Total Number of Distribution Transformers Numbers 201 163 132 71 145 88
Number of Metered Distribution Transformers
Numbers 0 23 0 0 48 0
Total Capacity of Distribution Transformers MVA 23.5 12.8 13.424 6.774 10.909 7.225
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 227
CESU, Odisha Page 227 Release Date: 27th February 2016
Project Area Name: Cuttack
Project Area Consumer
Information
(Last Financial Year)
Number of Metered
Consumers
Estimated Number
of Unmetered
Consumers
Metered
Sales
Assessed
Energy
Sales
Total
Sales
Connected
Load Billing Collection
No. No. MUs MUs MUs kW Rs. Cr. Rs. Cr.
LT Domestic 67,893 5,747 150.425433 41.03432 191.46 1686385.18 88.53518 79.46178
LT Commercial 13,068 1,011 43.56131 12.08456 55.646 482841.53 37.16933 33.00472
LT Industry 997 21 15.274723 0.664329 15.939 226042.46 10.79263 9.949651
LT Agriculture 9 21 0.190809 0.190122 0.3809 2164 0.043489 0.034207
LT Others 375 118 1.069904 0.571037 1.6409 10277.56 1.364871 0.803908
HT Railways 0 0 0 0 0 0 0 0
HT Industrial 106 1 48.6689609 2.378745 51.048 233123.158 35.85014 32.44375
HT Commercial 482 6 40.1627605 2.577246 42.74 263900.789 29.66414 28.67055
HT Others 364 33 31.4913923 10.33307 41.824 248351.24 26.1363 22.38253
Total 83,294 6,958 330.85 69.83 400.7 3,153,086 229.56 206.75
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 228
CESU, Odisha Page 228 Release Date: 27th February 2016
Consumer Metering Information
Project Area
Consumers
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
LT Domestic No. 0 0 0 0 34,079 33,814 5,747 73,640
LT Commercial No. 0 0 0 0 6,983 6,085 1,011 14,079
LT Industry No. 0 0 0 0 997 0 21 1,018
LT Agriculture No. 0 0 0 0 8 1 21 30
LT Others No. 0 0 0 0 149 226 118 493
HT Railways No. 0 0 0 0 0 0 0 0
HT Industrial No. 0 0 0 0 106 0 1 107
HT Commercial No. 0 0 0 0 482 0 6 488
HT Others No. 0 0 0 0 364 0 33 397
43,168 40,126 6,958 90,252
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 229
CESU, Odisha Page 229 Release Date: 27th February 2016
Asset Metering Information
Project Area Assets
Metered with AMR Meters
Metered
with AMR
Compatible
Meters
Metered
with Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
Import Points above 33kV level No. 0 0 0 0 0 0 0 0
Export Points above 33kV level No. 0 0 0 0 0 0 0 0
33 kV Feeder at 33/11 kV SS No. 0 0 0 0 10 0 38 48
Import Points at 33kV feeders
other than 33/11 kV SS No. 0 0 0 0 10 0 0 10
Export Points at 33kV feeders No. 0 0 0 0 0 0 1 1
11 kV feeders at 33/11 kV SS No. 0 0 0 0 48 0 43 91
Import Points at 11kV feeders No. 0 0 0 0 0 0 0 0
Export Points at 11kV feeders No. 0 0 0 0 0 0 4 4
Distribution Transformers No. 0 0 0 0 246 0 1,992 2,238
Import Points at LT feeders No. 0 0 0 0 0 0 0 0
Export Points at LT feeders No. 0 0 0 0 0 0 0 0
314 0 2,078 2,392
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 230
CESU, Odisha Page 230 Release Date: 27th February 2016
Project Area Name: Bhubaneswar
Project Area Consumer
Information
(Last Financial Year)
Number of Metered
Consumers
Estimated
Number of
Unmetered
Consumers
Metered
Sales
Assessed
Energy
Sales
Total
Sales
Connected
Load Billing Collection
No. No. MUs MUs MUs kW Rs. Cr. Rs. Cr.
LT Domestic 188,694 1,159 417.740 38.305 456.04 1,419,082.0 192.383 189.722
LT Commercial 28,006 294 151.930 12.096 164.03 567,567.2 108.680 108.154
LT Industry 890 0 19.035 0.465 19.5 30,921.2 13.970 13.635
LT Agriculture 59 10 0.540 0.100 0.64 749.0 0.090 0.040
LT Others 1,443 87 19.699 7.506 27.206 24,789.5 14.636 13.289
HT Railways 0 0 0.000 0.000 0 0.0 0.000 0.000
HT Industrial 62 0 46.615 0.210 46.825 20,373.4 26.772 26.206
HT Commercial 466 1 208.272 6.401 214.67 578,444.4 135.382 137.227
HT Others 414 10 111.325 11.577 122.9 203,330.7 68.313 66.530
Total 220,034 1,561 975.156 76.661 1,052 2,845,257 560.226 554.803
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 231
CESU, Odisha Page 231 Release Date: 27th February 2016
Consumer Metering Information
Project Area Consumers Metered with
AMR Meters
Metered
with AMR
Compatib
le Meters
Metered
with
Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetere
d Total
GSM/ GPRS/
EDGE CDMA
LPR/Othe
rs
LT Domestic No. 69,162 119,532 1,159 189,853
LT Commercial No. 13,470 14,536 294 28,300
LT Industry No. 887 3 0 890
LT Agriculture No. 59 0 10 69
LT Others No. 874 569 87 1,530
HT Railways No. 0 0 0 0
HT Industrial No. 62 0 0 62
HT Commercial No. 466 0 1 467
HT Others No. 414 0 10 424
85,394 134,640 1,561 221,595
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 232
CESU, Odisha Page 232 Release Date: 27th February 2016
Asset Metering Information
Project Area Assets
Metered with AMR Meters
Metered with
AMR
Compatible
Meters
Metered
with
Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Ot
hers
Import Points above 33kV level No. 0 0 0 0
Export Points above 33kV level No. 0 0 0 0
33 kV Feeder at 33/11 kV SS No. 36 0 31 67
Import Points at 33kV feeders
other than 33/11 kV SS No.
0 0 0 0
Export Points at 33kV feeders No. 2 0 0 2
11 kV feeders at 33/11 kV SS No. 79 0 48 127
Import Points at 11kV feeders No. 11 0 3 14
Export Points at 11kV feeders No. 1 0 8 9
Distribution Transformers No. 1,235 0 3,839 5,074
Import Points at LT feeders No. 0 0 0 0
Export Points at LT feeders No. 0 0 0 0
1,364 3,929 5,293
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 233
CESU, Odisha Page 233 Release Date: 27th February 2016
Project Area Name: Puri
Project Area Consumer
Information
(Last Financial Year)
Number of Metered
Consumers
Estimated
Number of
Unmetered
Consumers
Metered
Sales
Assessed
Energy
Sales
Total
Sales
Connected
Load Billing Collection
No. No. MUs MUs MUs kW Rs. Cr. Rs. Cr.
LT Domestic 30,810 90 26.228 20.389 46.617 40998.6 20.05 13.76
LT Commercial 5,999 8 20.538 6.311 26.849 19791.4 18.68 16.09
LT Industry 75 0.61 0.01 0.62 899.0 0.43 0.38
LT Agriculture 4 5 0.07 0.07 38.5 0.01 0.01
LT Others 443 29 5.148 3.17 8.318 3825.9 5.59 3.79
HT Railways 0 0 0 0 0 0 0 0
HT Industrial 1 0 0.6 0.6 111 0.38 0.50
HT Commercial 23 0 8.79 0.23 9.02 4321 5.76 5.56
HT Others 9 0 1.31 0.04 1.35 1750 0.92 0.71
Total 37,364 132 63.294 30.150 93.444 71,735 51.82 40.81
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 234
CESU, Odisha Page 234 Release Date: 27th February 2016
Consumer Metering Information
Project Area Consumers
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with
Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
LT Domestic No. 0 0 0 0 7,486 23,324 90 30,900
LT Commercial No. 0 0 0 0 1,505 4,494 8 6,007
LT Industry No. 0 0 0 0 75 0 0 75
LT Agriculture No. 0 0 0 0 4 0 5 9
LT Others No. 0 0 0 0 242 201 29 472
HT Railways No. 0 0 0 0 0 0 0 0
HT Industrial No. 0 0 0 0 1 0 0 1
HT Commercial No. 0 0 0 0 23 0 0 23
HT Others No. 0 0 0 0 9 0 0 9
9,345 28,019 132 37,496
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 235
CESU, Odisha Page 235 Release Date: 27th February 2016
Asset Metering Information
Project Area Assets
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with
Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
Import Points above 33kV level No. 0 0 0 0 0 0 0 0
Export Points above 33kV level No. 0 0 0 0 0 0 0 0
33 kV Feeder at 33/11 kV SS No. 0 0 0 0 3 0 0 3
Import Points at 33kV feeders other
than 33/11 kV SS No. 0 0 0 0 0 0 0 0
Export Points at 33kV feeders No. 0 0 0 0 1 0 0 1
11 kV feeders at 33/11 kV SS No. 0 0 0 0 16 0 0 16
Import Points at 11kV feeders No. 0 0 0 0 0 0 1 1
Export Points at 11kV feeders No. 0 0 0 0 0 0 3 3
Distribution Transformers No. 0 0 0 0 208 0 374 582
Import Points at LT feeders No. 0 0 0 0 0 0 0 0
Export Points at LT feeders No. 0 0 0 0 0 0 0 0
228 0 378 606
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 236
CESU, Odisha Page 236 Release Date: 27th February 2016
Project Area Name: Khordha
Project Area Consumer
Information
(Last Financial Year)
Number of Metered
Consumers
Estimated
Number of
Unmetered
Consumers
Metered
Sales
Assessed
Energy
Sales
Total
Sales
Connected
Load Billing Collection
No. No. MUs MUs MUs kW Rs. Cr. Rs. Cr.
LT Domestic 5488 1665 8.507 3.746 12.253 11250 5.51 4.40
LT Commercial 1126 103 1.679 0.516 2.195 1723 1.40 1.14
LT Industry 0 0 0 0 0 0 0 0
LT Agriculture 0 0 0 0 0 0 0 0
LT Others 150 11 3.004 0.835 3.839 1908 2.26 1.69
HT Railways 0 0 0 0 0 0 0 0
HT Industrial 0 0 0 0 0 0 0 0
HT Commercial 0 0 0 0 0 0 0 0
HT Others 4 0 0.892 0.892 962 1.36 1.02
Total 6,768 1,779 14.08 5.10 19.18 15,843 10.54 8.25
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 237
CESU, Odisha Page 237 Release Date: 27th February 2016
Consumer Metering Information
Project Area
Consumers
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
LT Domestic No. 0 0 0 0 2,607 2,881 1,665 7,153
LT Commercial No. 0 0 0 0 468 658 103 1,229
LT Industry No. 0 0 0 0 0 0 0 0
LT Agriculture No. 0 0 0 0 0 0 0 0
LT Others No. 0 0 0 0 150 0 11 161
HT Railways No. 0 0 0 0 0 0 0 0
HT Industrial No. 0 0 0 0 0 0 0 0
HT Commercial No. 0 0 0 0 0 0 0 0
HT Others No. 0 0 0 0 4 0 0 4
3,229 3,539 1,779 8,547
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 238
CESU, Odisha Page 238 Release Date: 27th February 2016
Asset Metering Information
Project Area Assets
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with
Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
Import Points above 33kV level
No. 0 0 0 0 0 0 0 0
Export Points above 33kV level
No. 0 0 0 0 0 0 0 0
33 kV Feeder at 33/11 kV SS No. 0 0 0 0 1 0 3 4
Import Points at 33kV feeders other than 33/11 kV SS
No. 0 0 0 0 2
0 0 2
Export Points at 33kV feeders No. 0 0 0 0 1 0 0 1
11 kV feeders at 33/11 kV SS No. 0 0 0 0 2 0 5 7
Import Points at 11kV feeders No. 0 0 0 0 0 0 0 0
Export Points at 11kV feeders No. 0 0 0 0 1 0 2 3
Distribution Transformers No. 0 0 0 0 31 0 108 139
Import Points at LT feeders No. 0 0 0 0 0 0 0 0
Export Points at LT feeders No. 0 0 0 0 0 0 0 0
38 0 118 156
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 239
CESU, Odisha Page 239 Release Date: 27th February 2016
Project Area Name: Jatni
Project Area Consumer
Information
(Last Financial Year)
Number of Metered
Consumers
Estimated
Number of
Unmetered
Consumers
Metered
Sales
Assessed
Energy
Sales
Total
Sales
Connected
Load Billing Collection
No. No. MUs MUs MUs kW Rs. Cr. Rs. Cr.
LT Domestic 5,294 907 9.025 1.941 10.966 9089 4.68 3.64
LT Commercial 699 38 0.844 0.103 0.947 761 0.95 0.51
LT Industry 0 0 0 0 0 0 0 0
LT Agriculture 0 0 0 0 0 0 0 0
LT Others 187 2 3.519 0.006 3.525 3371 2.61 2.38
HT Railways 0 0 0 0 0 0 0 0
HT Industrial 0 0 0 0 0 0 0 0
HT Commercial 0 0 0 0 0 0 0 0
HT Others 9 2 13.032 0.504 13.536 4386 8.37 8.14
Total 6,189 949 26.42 2.55 28.97 17,607 16.61 14.67
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 240
CESU, Odisha Page 240 Release Date: 27th February 2016
Consumer Metering Information
Project Area
Consumers
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
LT Domestic No. 0 0 0 0 2,113 3,181 907 6,201
LT Commercial No. 0 0 0 0 219 480 38 737
LT Industry No. 0 0 0 0 0 0 0 0
LT Agriculture No. 0 0 0 0 0 0 0 0
LT Others No. 0 0 0 0 187 0 2 189
HT Railways No. 0 0 0 0 0 0 0 0
HT Industrial No. 0 0 0 0 0 0 0 0
HT Commercial No. 0 0 0 0 0 0 0 0
HT Others No. 0 0 0 0 9 0 2 11
2,528 3,661 949 7,138
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 241
CESU, Odisha Page 241 Release Date: 27th February 2016
Asset Metering Information
Project Area Assets
Metered
with
AMR
Meters
Metered
with AMR
Compatible
Meters
Metered
with
Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
Import Points above 33kV level
No. 0 0 0 0 0 0 0 0
Export Points above 33kV level
No. 0 0 0 0 0 0 0 0
33 kV Feeder at 33/11 kV SS
No. 0 0 0 0 1
0 5 6
Import Points at 33kV feeders other than 33/11 kV SS
No. 0 0 0 0 1
0 1 2
Export Points at 33kV feeders
No. 0 0 0 0 0 0 0 0
11 kV feeders at 33/11 kV SS
No. 0 0 0 0 5 0 1 6
Import Points at 11kV feeders
No. 0 0 0 0 0 0 1 1
Export Points at 11kV feeders
No. 0 0 0 0 0 0 4 4
Distribution Transformers No. 0 0 0 0 5 0 64 69
Import Points at LT feeders No. 0 0 0 0 0 0 0 0
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 242
CESU, Odisha Page 242 Release Date: 27th February 2016
Export Points at LT feeders No. 0 0 0 0 0 0 0 0
12 0 76 88
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 243
CESU, Odisha Page 243 Release Date: 27th February 2016
Project Area Name: Dhenkanal
Project Area Consumer
Information
(Last Financial Year)
Number of Metered Consumers
Estimated Number of Unmetered Consumers
Metered Sales
Assessed Energy Sales
Total Sales
Connected Load
Billing Collection
No. No. MUs MUs MUs kW Rs. Cr. Rs. Cr.
LT Domestic 11,985 427 11.492 12.764 24.256 20143.5 11.102 8.571
LT Commercial 1,771 37 1.696 1.850 3.546 2274.0 1.609 1.242
LT Industry 500 0.48 0.514 0.994 6917.5 0.445 0.344
LT Agriculture 36 0.035 0.037 0.072 60.0 0.031 0.023
LT Others 53 44 0.052 0.087 0.139 0.7 0.078 0.063
HT Railways 1 14.637 15.676 30.313 8100 20.406 13.7594
HT Industrial 11 6.22 6.663 12.883 5393 7.547 7.1415
HT Commercial 6 3.455 3.700 7.155 2997 4.195 3.9692
HT Others 7 4.144 4.439 8.583 4453 5.031 4.7584
Total 14,370 508 42.211 45.730 87.941 50,339 50.445 39.872
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 244
CESU, Odisha Page 244 Release Date: 27th February 2016
Project Area Consumers Metered
with AMR Meters
Metered with AMR
Compatible Meters
Metered with Static Meters
Metered with Electro-
magnetic Meters & Others
Unmetered Total
GSM/ GPRS/ EDGE
CDMA LPR/Others
LT Domestic No. 0 0 0 0 3,716 8,269 427 12,412
LT Commercial No. 0 0 0 0 539 1,232 37 1,808
LT Industry No. 0 0 0 0 410 90 0 500
LT Agriculture No. 0 0 0 0 6 30 0 36
LT Others No. 0 0 0 0 42 11 44 97
HT Railways No. 0 0 0 0 1 0 0 1
HT Industrial No. 0 0 0 0 11 0 0 11
HT Commercial No. 0 0 0 0 6 0 0 6
HT Others No. 0 0 0 0 7 0 0 7
4,738 9,632 508 14,878
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 245
CESU, Odisha Page 245 Release Date: 27th February 2016
Asset Metering Information
Project Area Assets
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with
Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
Import Points above 33kV level No. 0 0 0 0 0 0 0 0
Export Points above 33kV level No. 0 0 0 0 0
33 kV Feeder at 33/11 kV SS No. 0 0 0 0 3 3
Import Points at 33kV feeders
other than 33/11 kV SS No. 0 0 0 0
1 0 1
Export Points at 33kV feeders No. 0 0 0 0 0 0 0
11 kV feeders at 33/11 kV SS No. 0 0 0 0 6 1 7
Import Points at 11kV feeders No. 0 0 0 0 3 0 3
Export Points at 11kV feeders No. 0 0 0 0 0 4 4
Distribution Transformers No. 0 0 0 0 165 165
Import Points at LT feeders No. 0 0 0 0 0 0 0 0
Export Points at LT feeders No. 0 0 0 0 0 0 0 0
10 0 173 183
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 246
CESU, Odisha Page 246 Release Date: 27th February 2016
Project Area Name: Angul
Project Area Consumer
Information
(Last Financial Year)
Number of
Metered
Consumers
Estimated Number of
Unmetered
Consumers
Metered
Sales
Assessed
Energy
Sales
Total
Sales
Connected
Load Billing Collection
No. No. MUs MUs MUs kW Rs. Cr. Rs. Cr.
LT Domestic 8,767 1,492 17.878 3.576 21.454 17298.0 9.024 7.318
LT Commercial 2,634 433 10.139 0.965 11.104 11702.0 7.122 6.179
LT Industry 72 2 0.92 0.92 6424.0 0.614 0.592
LT Agriculture 7 10 0.01 0.05 0.06 2513.0 0.010 0.005
LT Others 40 170 1.22 0.0921 1.3121 2016.0 0.899 0.714
HT Railways 0 0 0 0 0 0 0 0
HT Industrial 21 2.366 2.366 2000 1.4912 1.4352
HT Commercial 13 1.045 1.045 1068 0.8175 0.7521
HT Others 8 0.406 0.48 0.886 0.8901 0.3717
Total 11,562 2,107 33.98 5.16 39.15 43,021 20.868 17.367
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 247
CESU, Odisha Page 247 Release Date: 27th February 2016
Consumer Metering Information
Project Area
Consumers
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
LT Domestic No. 0 0 0 0 7,231 1,536 1,492 10,259
LT Commercial No. 0 0 0 0 2,375 259 433 3,067
LT Industry No. 0 0 0 0 72 0 2 74
LT Agriculture No. 0 0 0 0 7 0 10 17
LT Others No. 0 0 0 0 40 0 170 210
HT Railways No. 0 0 0 0 0 0 0 0
HT Industrial No. 0 0 0 0 21 0 0 21
HT Commercial No. 0 0 0 0 13 0 0 13
HT Others No. 0 0 0 0 8 0 0 8
9,767 1,795 2,107 13,669
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 248
CESU, Odisha Page 248 Release Date: 27th February 2016
Asset Metering Information
Project Area Assets
Metered with AMR Meters
Metered with
AMR
Compatible
Meters
Metered
with Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/ GPRS/
EDGE CDMA LPR/Others
Import Points above 33kV level
No. 0 0 0 0 0 0 0 0
Export Points above 33kV level
No. 0 0 0 0 0 0 0 0
33 kV Feeder at 33/11 kV SS No. 0 0 0 0 0 0 7 7
Import Points at 33kV feeders other than 33/11 kV SS
No. 0 0 0 0 2 0 0 2
Export Points at 33kV feeders No. 0 0 0 0 0 0 1 1
11 kV feeders at 33/11 kV SS No. 0 0 0 0 6 0 1 7
Import Points at 11kV feeders No. 0 0 0 0 0 0 2 2
Export Points at 11kV feeders No. 0 0 0 0 2 0 10 12
Distribution Transformers No. 0 0 0 0 0 0 201 201
Import Points at LT feeders No. 0 0 0 0 0 0 0 0
Export Points at LT feeders No. 0 0 0 0 0 0 0 0
10 0 222 232
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 249
CESU, Odisha Page 249 Release Date: 27th February 2016
Project Area Name: Talcher
Project Area Consumer
Information
(Last Financial Year)
Number of
Metered
Consumers
Estimated
Number of
Unmetered
Consumers
Metered Sales
Assessed
Energy
Sales
Total
Sales
Connected
Load Billing Collection
No. No. MUs MUs MUs kW Rs. Cr. Rs. Cr.
LT Domestic 4,260 292 4.723 4.482 9.2046 6,403.0 4.2355 2.3287
LT Commercial 1,582 30 4.680 0.812 5.492 3,966.0 3.6635 2.917
LT Industry 15 1 0.092 0.013 0.1049 137.0 0.0597 0.0586
LT Agriculture 1 8 0.011 0.011 0.023 13.5 0.0015 0.0014
LT Others 177 3 1.449 0.804 2.2534 719.5 1.0084 0.4323
HT Railways 1 0.964 0.9639 110.0 0.5479 0.5416
HT Industrial 2 2.234 2.234 2,389.0 1.4578 2.5039
HT Commercial 0 0 0 0 0 0 0 0
HT Others 3 0.449 0.4487 352.2 0.4082 0.2222
Total 6,041 334 14.60 6.12 20.72 14,090 11.383 9.006
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 250
CESU, Odisha Page 250 Release Date: 27th February 2016
Consumer Metering Information
Project Area Consumers
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
LT Domestic No. 0 0 0 0 1,278 2,982 292 4,552
LT Commercial No. 0 0 0 0 475 1,107 30 1,612
LT Industry No. 0 0 0 0 3 12 1 16
LT Agriculture No. 0 0 0 0 1 0 8 9
LT Others No. 0 0 0 0 54 123 3 180
HT Railways No. 0 0 0 0 1 0 0 1
HT Industrial No. 0 0 0 0 2 0 0 2
HT Commercial No. 0 0 0 0 0 0 0 0
HT Others No. 0 0 0 0 3 0 0 3
1,817 4,224 334 6,375
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 251
CESU, Odisha Page 251 Release Date: 27th February 2016
Asset Metering Information
Project Area Assets
Metered
with AMR
Meters
Metered
with AMR
Compatible
Meters
Metered
with Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
Import Points above 33kV level
No. 0 0 0 0 0 0 0 0
Export Points above 33kV level
No. 0 0 0 0 0 0 0 0
33 kV Feeder at 33/11 kV SS No. 0 0 0 0 2 0 2 4
Import Points at 33kV feeders other than 33/11 kV SS
No. 0 0 0 0 2
0 0 2
Export Points at 33kV feeders No. 0 0 0 0 0 0 1 1
11 kV feeders at 33/11 kV SS No. 0 0 0 0 3 0 0 3
Import Points at 11kV feeders No. 0 0 0 0 0 0 0 0
Export Points at 11kV feeders No. 0 0 0 0 3 0 2 5
Distribution Transformers No. 0 0 0 0 23 0 140 163
Import Points at LT feeders No. 0 0 0 0 0 0 0 0
Export Points at LT feeders No. 0 0 0 0 0 0 0 0
33 0 145 178
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 252
CESU, Odisha Page 252 Release Date: 27th February 2016
Project Area Name: Kendrapara
Project Area Consumer
Information
(Last Financial Year)
Number of
Metered
Consumers
Estimated
Number of
Unmetered
Consumers
Metered Sales
Assessed
Energy
Sales
Total
Sales
Connected
Load Billing Collection
No. No. MUs MUs MUs kW Rs. Cr. Rs. Cr.
LT Domestic 5,393 1,084 7.152 2.099 9.251 9,681.5 4.3200 2.8100
LT Commercial 1,825 583 3.818 1.453 5.271 3,988.4 3.5800 2.9500
LT Industry 70 7 1.128 0.173 1.301 1,190.5 0.8200 1.1400
LT Agriculture 8 7 0.001 0.008 0.009 62.0
LT Others 11 4 0.196 0.200 0.396 151.0 0.4500 0.3800
HT Railways 0 0 0 0 0 0 0 0
HT Industrial 12 4 2.001 0.041 2.042 748.0 1.4000 1.6600
HT Commercial 0 0 0 0 0 0 0 0
HT Others 0 0 0 0 0 0 0 0
Total 7,319 1,689 14.30 3.97 18.27 15,821 10.570 8.940
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 253
CESU, Odisha Page 253 Release Date: 27th February 2016
Consumer Metering Information
Project Area Consumers
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unme
tered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
LT Domestic No. 0 0 0 0 3,593 1,800 1,084 6,477
LT Commercial No. 0 0 0 0 1,621 204 583 2,408
LT Industry No. 0 0 0 0 63 7 7 77
LT Agriculture No. 0 0 0 0 8 0 7 15
LT Others No. 0 0 0 0 7 4 4 15
HT Railways No. 0 0 0 0 0 0 0 0
HT Industrial No. 0 0 0 0 12 0 4 16
HT Commercial No. 0 0 0 0 0 0 0 0
HT Others No. 0 0 0 0 0 0 0 0
5,304 2,015 1,689 9,008
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 254
CESU, Odisha Page 254 Release Date: 27th February 2016
Asset Metering Information
Project Area Assets
Metered
with AMR
Meters
Metered
with AMR
Compatible
Meters
Metered
with Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
Import Points above 33kV level
No. 0 0 0 0 0
0 0 0
Export Points above 33kV level
No. 0 0 0 0 0
0 0 0
33 kV Feeder at 33/11 kV SS No. 0 0 0 0 1 0 4 5
Import Points at 33kV feeders other than 33/11 kV SS
No. 0 0 0 0 0
0 0 0
Export Points at 33kV feeders No. 0 0 0 0 0 0 0 0
11 kV feeders at 33/11 kV SS No. 0 0 0 0 5 0 0 5
Import Points at 11kV feeders No. 0 0 0 0 0 0 0 0
Export Points at 11kV feeders No. 0 0 0 0 0 0 3 3
Distribution Transformers No. 0 0 0 0 0 0 132 132
Import Points at LT feeders No. 0 0 0 0 0 0 0 0
Export Points at LT feeders No. 0 0 0 0 0 0 0 0
6 0 139 145
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 255
CESU, Odisha Page 255 Release Date: 27th February 2016
Project Area Name: Pattamundai
Project Area Consumer
Information
(Last Financial Year)
Number of Metered
Consumers
Estimated
Number of
Unmetered
Consumers
Metered
Sales
Assessed
Energy
Sales
Total
Sales
Connected
Load Billing Collection
No. No. MUs MUs MUs kW Rs. Cr. Rs. Cr.
LT Domestic 4,770 493 4.053 1.205 5.26 6636.5 1.5 1.010
LT Commercial 524 102 1.705 0.239 1.94 1210 1.5 1.060
LT Industry 21 1 0.148 0.90 0.16 198.5 0.1 0.090
LT Agriculture 6 189 0.045 0.05 623 0.0 0.004
LT Others 22 9 0.289 0.224 0.51 233 0.4 0.290
HT Railways 0 0 0 0 0 0 0 0
HT Industrial 0 0 0 0 0 0 0 0
HT Commercial 0 0 0 0 0 0 0 0
HT Others 0 0 0 0 0 0 0 0
Total 5,343 794 6.20 2.61 7.92 8,901 3.503 2.454
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 256
CESU, Odisha Page 256 Release Date: 27th February 2016
Consumer Metering Information
Project Area Consumers
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with
Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
LT Domestic No. 0 0 0 0 1,777 2,993 493 5,263
LT Commercial No. 0 0 0 0 162 362 102 626
LT Industry No. 0 0 0 0 1 20 1 22
LT Agriculture No. 0 0 0 0 0 6 189 195
LT Others No. 0 0 0 0 4 18 9 31
HT Railways No. 0 0 0 0 0 0 0 0
HT Industrial No. 0 0 0 0 0 0 0 0
HT Commercial No. 0 0 0 0 0 0 0 0
HT Others No. 0 0 0 0 0 0 0 0
1,944 3,399 794 6,137
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 257
CESU, Odisha Page 257 Release Date: 27th February 2016
Asset Metering Information
Project Area Assets
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with
Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
Import Points above 33kV level No. 0 0 0 0 0 0 0 0
Export Points above 33kV level No. 0 0 0 0 0 0 0 0
33 kV Feeder at 33/11 kV SS No. 0 0 0 0 1 0 2 3
Import Points at 33kV feeders other than 33/11 kV SS
No. 0 0 0 0 1 0 0 1
Export Points at 33kV feeders No. 0 0 0 0 0 0 0 0
11 kV feeders at 33/11 kV SS No. 0 0 0 0 2 0 0 2
Import Points at 11kV feeders No. 0 0 0 0 0 0 0 0
Export Points at 11kV feeders No. 0 0 0 0 0 0 6 6
Distribution Transformers No. 0 0 0 0 0 0 69 69
Import Points at LT feeders No. 0 0 0 0 0 0 0 0
Export Points at LT feeders No. 0 0 0 0 0 0 0 0
4 0 77 81
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 258
CESU, Odisha Page 258 Release Date: 27th February 2016
Project Area Name: Jagatsinghpur
Project Area Consumer
Information
(Last Financial Year)
Number of Metered Consumers
Estimated Number of Unmetered Consumers
Metered Sales
Assessed Energy Sales
Total Sales
Connected Load
Billing Collection
No. No. MUs MUs MUs kW Rs. Cr. Rs. Cr.
LT Domestic 4,717 214 10.780 0.380 11.160 6488.0 4.620 2.155
LT Commercial 979 14 3.890 0.010 3.900 2713.0 2.453 2.253
LT Industry 21 0 0.300 0 0.300 145.0 0.232 0.215
LT Agriculture 10 9 0.540 0 0.540 20.0 0.004 0.007
LT Others 420 1 0.660 0.110 0.770 586.0 0.471 0.410
HT Railways 0 0 0 0 0 0 0 0
HT Industrial 0 0 0 0 0 0 0 0
HT Commercial 0 0 0 0 0 0 0 0
HT Others 0 0 0 0 0 0 0 0
Total 6,147 238 16.170 0.500 16.670 9,952 7.780 5.040
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 259
CESU, Odisha Page 259 Release Date: 27th February 2016
Consumer Metering Information
Project Area Consumers
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with
Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
LT Domestic No. 0 0 0 0 2,974 1,743 214 4,931
LT Commercial No. 0 0 0 0 627 352 14 993
LT Industry No. 0 0 0 0 21 0 0 21
LT Agriculture No. 0 0 0 0 10 0 9 19
LT Others No. 0 0 0 0 356 64 1 421
HT Railways No. 0 0 0 0 0 0 0 0
HT Industrial No. 0 0 0 0 0 0 0 0
HT Commercial No. 0 0 0 0 0 0 0 0
HT Others No. 0 0 0 0 0 0 0 0
3,988 2,159 238 6,385
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 260
CESU, Odisha Page 260 Release Date: 27th February 2016
Asset Metering Information
Project Area Assets
Metered with AMR Meters
Metered with
AMR
Compatible
Meters
Metered
with Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
Import Points above 33kV level No. 0 0 0 0 0 0 0 0
Export Points above 33kV level No. 0 0 0 0 0 0 0 0
33 kV Feeder at 33/11 kV SS No. 0 0 0 0 1 0 0 1
Import Points at 33kV feeders
other than 33/11 kV SS No. 0 0 0 0 0 0 0 0
Export Points at 33kV feeders No. 0 0 0 0 0 0 0 0
11 kV feeders at 33/11 kV SS No. 0 0 0 0 4 0 0 4
Import Points at 11kV feeders No. 0 0 0 0 0 0 0 0
Export Points at 11kV feeders No. 0 0 0 0 0 0 7 7
Distribution Transformers No. 0 0 0 0 48 0 97 145
Import Points at LT feeders No. 0 0 0 0 0 0 0 0
Export Points at LT feeders No. 0 0 0 0 0 0 0 0
53 0 104 157
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 261
CESU, Odisha Page 261 Release Date: 27th February 2016
Project Area Name: Paradeep
Project Area Consumer
Information
(Last Financial Year)
Number of Metered
Consumers
Estimated Number
of Unmetered
Consumers
Metered Sales Assessed
Energy Sales
Total
Sales
Connected
Load Billing Collection
No. No. MUs MUs MUs kW Rs. Cr. Rs. Cr.
LT Domestic 2,968 205 5.05 0.598 5.648 4893 2.38 2.19
LT Commercial 410 36 1.308 0.3 1.608 1310 0.99 0.98
LT Industry 7 0.13 0.125 148
LT Agriculture 1 2
LT Others 6 3 0.164 0.09 0.254 164 0.23 0.23
HT Railways 1 0.892 0.892 300 0.47 0.47
HT Industrial 7 9.72 9.72 175 2.38 2.27
HT Commercial 4 7.65 7.65 360 1.94 1.85
HT Others 6 4.648 4.648 60 9.76 9.76
Total 3,410 244 29.56 0.99 30.55 7,412 18.15 17.75
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 262
CESU, Odisha Page 262 Release Date: 27th February 2016
Consumer Metering Information
Project Area Consumers
Metered
with AMR
Meters
Metered with
AMR
Compatible
Meters
Metered
with
Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmetered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
LT Domestic No. 0 0 0 0 2248 720 205 3,173
LT Commercial No. 0 0 0 0 268 142 36 446
LT Industry No. 0 0 0 0 7 0 0 7
LT Agriculture No. 0 0 0 0 1 0 0 1
LT Others No. 0 0 0 0 6 0 3 9
HT Railways No. 0 0 0 0 1 0 0 1
HT Industrial No. 0 0 0 0 7 0 0 7
HT Commercial No. 0 0 0 0 4 0 0 4
HT Others No. 0 0 0 0 6 0 0 6
2,548 862 244 3,654
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 263
CESU, Odisha Page 263 Release Date: 27th February 2016
Asset Metering Information
Project Area Assets
Metere
d with
AMR
Meters
Metered
with AMR
Compatible
Meters
Metered
with
Static
Meters
Metered
with
Electro-
magnetic
Meters &
Others
Unmet
ered Total
GSM/
GPRS/
EDGE
CDMA LPR/Others
Import Points above 33kV level No. 0 0 0 0 0 0 0 0
Export Points above 33kV level No. 0 0 0 0 0 0 0 0
33 kV Feeder at 33/11 kV SS No. 0 0 0 0 1 0 2 3
Import Points at 33kV feeders other than 33/11 kV SS
No. 0 0 0 0 1 0 1 2
Export Points at 33kV feeders No. 0 0 0 0 1 0 0 1
11 kV feeders at 33/11 kV SS No. 0 0 0 0 0 0 1 1
Import Points at 11kV feeders No. 0 0 0 0 0 0 3 3
Export Points at 11kV feeders No. 0 0 0 0 0 0 2 2
Distribution Transformers No. 0 0 0 0 0 0 88 88
Import Points at LT feeders No. 0 0 0 0 0 0 0 0
Export Points at LT feeders No. 0 0 0 0 0 0 0 0
3 0 97 100
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 264
CESU, Odisha Page 264 Release Date: 27th February 2016
Appendix K – Website Table 32: Detail of existing Website in CESU
Particulars Facility Available/Not Available
URL of the Website www.cescoorissa.com /
www.cesuodisha.com
Major facilities being provided to the
consumers/suppliers/employees/other stakeholders
through website
Log in Yes, only for employees.
Registration User Registration Form Is Available
Forgot password/ change password Change Password Only
Complain registration & status Yes
Contact us Yes
Privacy policy
Business associate
Consumer Related (Illustrative)
Application form submission for new connection Yes
Application form submission for disconnection No
Registration of complaint against outages Yes
Registration of complaint against corruption Yes
Online bill payment Yes
View bill summary Yes
Other 1
….
Supplier Related (Illustrative)
Tender information Yes
Tendering or Bid submission Yes
Online payment
Other 1
Other 2
….
Employees Related (Illustrative)
Payroll System
Leave balance
Expense Claim
Other 1
Other 2
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 265
CESU, Odisha Page 265 Release Date: 27th February 2016
Particulars Facility Available/Not Available
…..
Other Stakeholder (Illustrative)
Projects Yes
AT&C Loss Status Yes
Other commercial & financial information Yes
Other 1
Other 2
…..
….
Security Features
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 266
CESU, Odisha Page 266 Release Date: 27th February 2016
Appendix L: List of Goods and related services
List of Goods and related services: This section contains indicative list of goods and services to be delivered as per approved DPR. The delivered system should comply with performance level mentioned in the clause 9 of section G1 of SRS and meet the SLA
Attached as per BOM appendix L
Note: Bidder must provide 3 years Annual Technical Support Pack after go-live for all the Server Operating Systems. Bidder must include any extra software/OS/Database licenses required for DR Site as per the licensing policy of the offered solution.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 267
CESU, Odisha Page 267 Release Date: 27th February 2016
Appendix M – Estimated Manpower Requirement SI to deploy manpower, as per requirement as per Clause 7.0 of Section G.5 of SRS document keeping in view of project completion time. In addition to this following is the list of minimum number of resources required to be deployed by the bidder under various roles: Table 33: Estimated Manpower Requirement
Roles Dedicated Resources Shared Resources
Number Man months Number Man months
System Integrator 15 270 60 1080
GIS Service Provider 8
(Other than Field
Survey)
144 65 1170
Meter Data
Acquisition Service
Provider
10 180 60 1080
Network Service
Provider
10 180 40
720
Necessary resources for FMS shall be provided by the System Integrator in accordance with the clause 7.0 of Section G5 of SRS Document.
Handholding Support
Handholding support for application related operations at Division and Sub Division level shall be provided by the selected vendor for which at least one person per Division and Sub Division shall be deputed till the completion of the project.
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 268
CESU, Odisha Page 268 Release Date: 27th February 2016
Appendix N – Expected Implementation Schedule
The bidder is expected to complete the implementation of Data Center at Bhubaneswar, Customer Care Center at Bhubaneswar and pilot projects at Bhubaneswar for CESU within 12 months from the date of issue of LOI to successful bidder by the CESU. Pilot is the first project area (consisting of the data centre) that goes live in a utility. The bidder is expected to complete the Utility-wide (CESU) implementation for all the other identified project areas with-in 18 (eighteen) calendar months, from the date of issue of LOI to successful bidder by the CESU.
Facilities Management Services post successful completion of acceptance tests shall be provided for a period of five years from the date of completion of go-line in all project areas.
Bidder shall submit a detail Gantt chart as per along with the following implementation schedule. Bidders shall drill down these activities into sub/sub-sub activity in the chart. The chart shall also detail out time and resource effort required to execute each activity. The detailed bar charts for all the work activity shall however, be discussed and agreed to by the successful Bidder with the owner before start of the execution of work.
Table 34: Expected Implementation Schedule
Activity/ Sub Activity Start
Date Weekly Plan
End
Date
W1 W2 W3 W4 W5 …
1
Mobilization at site with establishment of
site office, requisite resource
deployment etc.
2
System Design (Pre-Implementation
Plan, Testing and Development) and
Approval from the owner
3
Field Survey for Consumer Indexing &
Asset mapping & GIS System
Implementation
4 Establishment of Data Center
5 Implementation of AMR System
6
Establishment of First Customer care
center (First Customer care center after
completion of work at all sub divisions
under the requisite town, for town wise
establishment of CC Center) -
7
Creation of IT Infrastructure at Other
Utility offices viz. Division, Circle etc. (In
a phased manner for associated
completed sub division wise) -
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 269
CESU, Odisha Page 269 Release Date: 27th February 2016
8
Integration of entire IT infrastructures
created at data center, Sub division
offices, Customer care centers,
Electrical sub stations and other utility
offices on a GIS platform with
Acceptance / Performance test
9 Facility Management Services (FMS)
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 270
CESU, Odisha Page 270 Release Date: 27th February 2016
Appendix O: Spot Billing Machine Specification
Attached separately as an document file
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 271
CESU, Odisha Page 271 Release Date: 27th February 2016
Appendix P: Map of CESU of Odisha
Attached separately as a pdf file
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 272
CESU, Odisha Page 272 Release Date: 27th February 2016
Appendix Q: Formats for Price Bids
Attached separately as an Excel file
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 273
CESU, Odisha Page 273 Release Date: 27th February 2016
Appendix R: Proposed Interface Scheme v2.4
Attached separately as a pdf file
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 274
CESU, Odisha Page 274 Release Date: 27th February 2016
Appendix S: CESU Offices Locations for Network Connectivity
Attached separately as an excel file
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 275
CESU, Odisha Page 275 Release Date: 27th February 2016
Appendix T: Additional Clarifications
Attached separately as an excel file
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 276
CESU, Odisha Page 276 Release Date: 27th February 2016
Appendix U –No Deviation Certificate
No Deviation Certificate
To: Senior General Manager (IT), Central Electricity Supply Utility of Odisha, 8th Floor, IDCO Towers, Janpath, Bhubaneswar -751 022 Odisha Dear Sir, We, the undersigned, hereby declare that while responding to your RFP Notice No. ………………
dated ……………., our bid response DOES NOT DEVIATE from the RFP, SRS and their
amendment/corrigendum issued till the date of bid submission.
Name: In the capacity of:
Signed:
Duly authorized to sign the Bid for and on behalf of:
Date:
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 277
CESU, Odisha Page 277 Release Date: 27th February 2016
Appendix V - Abbreviations
The abbreviations mentioned in the document has been expanded hereunder: Appendix T
Abbreviation Meaning
AMR Automated Meter Reading
B/W Black & White
BDS Bid Data Sheet
BG Bank Guarantee
CEO Chief Executive Officer
CIO Chief Information Officer
CST Central Sales Tax
CTI Computer Telephony Integration
CV Curriculum Vitae
DNS Domain Name Server
EMS Enterprise Management System
ExW Ex-Works
FMS Facility Management Services
FoB Freight on Board
GCC General Conditions of Contract
GIS Geographical Information System
GIS Geographical Information System
GoI Government of India
GPS Geographic Positioning System
GSP GIS Solution Provider
HQ Head Quarter
HT High Tension
ICB International Competitive Bidding
INR Indian Rupee
IP Internet Protocol
IPR Intellectual Property Rights
IST Indian Standard Time
IT Information Technology
ITB Instructions to Bidders
ITC IT Consultant
ITIA IT Implementation Agency
LAN Local Area Network
RFP (Identification No. CESU/ITCC/R-APDRP/07) for Appointment of IT
Implementation Agency under R-APDRP SCHEME for CESU, Odisha P a g e | 278
CESU, Odisha Page 278 Release Date: 27th February 2016
Abbreviation Meaning
LDAP Lightweight Directory Access Protocol
LoI Letter of Intend
LP Lowest Prize
LT Low Tension
MBC Metering Billing Collection
MD Managing Director
MDASP Meter Data Acquisition Solution Provider
MoP Ministry of Power
MTR Motor Transport Receipt
NIT Notice Inviting Tender
NSP Network Solution Provider
OEM Original Equipment Manufacturer
OS Operating System
PC Personal Computer
PFC Power Finance Corporation
R-APDRP Restructured Accelerated Power Development Reforms Programme
RFP Request for Proposal
RFQ Request for Qualification
SAN Storage Area Network
SCC Special Conditions of Contract
SI System Integrator
SLA Service Level Agreement
SRS System Requirement Specifications
T/O Turnover
TS Technical Section
UPS Uninterrupted Power Supply
VAT Value Added Tax
VPN Virtual Private Network
WAN Wide Area Network