Purbrook Way Hulbert Road Junction – Phasing Drawings
Revision 3
Current at 21-04-2016
![Page 2: Purbrook Way Hulbert Road Junction –Phasing · PDF filePurbrook Way Hulbert Road Junction –Phasing Drawings Revision 3 Current at 21-04-2016. ... • SWGE01-0001-TMA01. From: Thursday](https://reader031.vdocuments.us/reader031/viewer/2022030423/5aaac5057f8b9a81188e6eb6/html5/thumbnails/2.jpg)
From: Monday 18th April
To: Thursday 21st April
4 Nights
Surface Course
• HRN and Roundabout
Asda exit lane reduced in width
� Single file, one direction traffic control in place
Over night closures with 4-Way Traffic Light System in place
Roundabout returned to normal operation during the day
Extent of TM
Extent of Surfacing
LEGEND
TM Plan:
• W2549TMA26 Rev B
Diversion Plan:
• W2936TMA05
![Page 3: Purbrook Way Hulbert Road Junction –Phasing · PDF filePurbrook Way Hulbert Road Junction –Phasing Drawings Revision 3 Current at 21-04-2016. ... • SWGE01-0001-TMA01. From: Thursday](https://reader031.vdocuments.us/reader031/viewer/2022030423/5aaac5057f8b9a81188e6eb6/html5/thumbnails/3.jpg)
Plane Out, Install Reinforcement Grid,
lay Binder & Surface Course
• Purbrook Way (East)
Asda exit lane reduced in width
� Two lines of traffic cannot safely join a roundabout with only 1 lane.
From: Monday 25th April
To: Wednesday 27th April
3 Nights
Extent of TM
Extent of Surfacing
LEGEND
TM Plan:
• W2549TMA27 Rev B
Diversion Plan:
• SWGE01-0001-TMA01
![Page 4: Purbrook Way Hulbert Road Junction –Phasing · PDF filePurbrook Way Hulbert Road Junction –Phasing Drawings Revision 3 Current at 21-04-2016. ... • SWGE01-0001-TMA01. From: Thursday](https://reader031.vdocuments.us/reader031/viewer/2022030423/5aaac5057f8b9a81188e6eb6/html5/thumbnails/4.jpg)
From: Thursday 28th April
To: Thursday 5th May
5 Nights
Note: Bank Holiday Monday 2nd May
Plane Out, Install Reinforcement Grid,
lay Binder & Surface Course
• Purbrook Way (West)
Over night closures with 4-Way Traffic Light System in place
Roundabout returned to normal operation during the day
Asda exit lane reduced in width
� Single file, one direction traffic control in place
� During this phase there will be the need to stop all traffic for 15-20mins
to allow surfacing vehicles to lay entrance area. This will be controlled
and co-ordinated with Asda and the public.
Extent of TM
Extent of Surfacing
LEGEND
TM Plan:
• W2549TMA25 Rev B
Diversion Plan:
• EC/CJ007741/TRO/04
![Page 5: Purbrook Way Hulbert Road Junction –Phasing · PDF filePurbrook Way Hulbert Road Junction –Phasing Drawings Revision 3 Current at 21-04-2016. ... • SWGE01-0001-TMA01. From: Thursday](https://reader031.vdocuments.us/reader031/viewer/2022030423/5aaac5057f8b9a81188e6eb6/html5/thumbnails/5.jpg)
From: Friday 6th May
To: Wednesday 11th May
4 Nights
Surface Course
• Hulbert Road (South)
Over night closures with 4-Way Traffic Light System in place
Roundabout returned to normal operation during the day
Asda exit lane reduced in width
� Single file, one direction traffic control in place
� During this phase there will be the need to stop all traffic for 15-20mins
to allow surfacing vehicles to lay entrance area. This will be controlled
and co-ordinated with Asda and the public.
Extent of TM
Extent of Surfacing
LEGEND
TM Plan:
• W2549tma24 Rev B
Diversion Plan:
• 0100-CI-DRG-005
![Page 6: Purbrook Way Hulbert Road Junction –Phasing · PDF filePurbrook Way Hulbert Road Junction –Phasing Drawings Revision 3 Current at 21-04-2016. ... • SWGE01-0001-TMA01. From: Thursday](https://reader031.vdocuments.us/reader031/viewer/2022030423/5aaac5057f8b9a81188e6eb6/html5/thumbnails/6.jpg)
Asda exit lane reduced in width
� Works adjacent to Asda entrance/exit required, resulting in reduced width.
From: Monday 16th May
To: Wednesday 18th May• 2 days Break out and kerbing
• 1 day (Wednesday 18th May) surfacing
Break out and build Asda Splitter island
(including footway crossing and original
kerbing)
• Asda entrance/exit
Surface Course
• Around Asda splitter island
Signage, Guardrail, Traffic Signals, Street
Lighting, CCTV, Landscaping works
• Multiple areas
![Page 7: Purbrook Way Hulbert Road Junction –Phasing · PDF filePurbrook Way Hulbert Road Junction –Phasing Drawings Revision 3 Current at 21-04-2016. ... • SWGE01-0001-TMA01. From: Thursday](https://reader031.vdocuments.us/reader031/viewer/2022030423/5aaac5057f8b9a81188e6eb6/html5/thumbnails/7.jpg)
Notes
• The dates and durations detailed are the current best forecast based on
current design and programme. They are subject to change should
unforeseen circumstances arise, design changes, weather etc.
• This phasing is different to that originally planned and has been produced
to minimise the disruption to local stakeholders and travelling public.
• Traffic Management layouts will be assessed when installed and may
require alteration on site to reflect Health, Safety and operational
requirements.