PUNJAB STATE ELECTRICITY BOARD
PR Circular No. 01/2010 Dated 4.1.2010
From The Chief Engineer/SO&C, Power Regulation & Control Dte., PSEB, 220KV S/Stn., Ablowal, Patiala.
To 1. All EIC/CEs/Distribution in PSEB. 2. Chief Engineer/P&M, PSEB, Ludhiana. 3. Chief Engineer/Enforcement, PSEB, Patiala. 4 All Dy.CEs/SEs/Distribution in PSEB. They are requested to send copy of this
circular to their Sr. Xens and SDOs 5. All Dy. CEs/SEs/P&M in PSEB. They are requested to send copy of this circular
to their Sr. Xens and SDOs 6. All Dy.CEs/Directors/Enforcement & EA & MMTS. They are requested to send
copy of this circular to their Sr. Xens and SDOs
Memo No. 19408/19548/SO/PRC/LD-38
Dated: 4.1.2010
Subject: Relaxation/Rescheduling of Power Regulatory Measures on Industries. Due to improvement in Power supply Position and decrease in load on the
system, following relaxations were given through various telephone messages as under:
1 Industrial consumers feeding from Cat-II feeders (except Induction and Rolling mill consumers) were allowed to observe weekly off day from 0800 hours to 2100 hours instead of 0800 hours to 0800 hours of next day w.e.f 15.12.09 to 31.1.2010
2 Arc/Induction furnace and Rolling mill consumers were allowed to use power from 2100 hours to 0600 hours during weekly off days. Thus these consumers were to observe weekly off day from 0600 hours to 2100 hours instead of 2100 hour to 2100 hours w.e.f 15.12.09 to 31.1.2010. Days of weekly off day remained unchanged.
3 On account of Curfew in Ludhiana on 7.12.09, all industrial consumers of Ludhiana being fed from Cat - 2 & 3 feeders (Including Arc/Induction and Rolling Mills) whose weekly off day was falling on 8.12.09 to 13.12.09 were relaxed from observing weekly off days on these dates.
Director/PR&C for Chief Engineer/SO&C, PSEB, Patiala CC: 1 Chairman, PSEB & All Members/PSEB. 2. Secretary/Punjab State Electricity Regulatory Commission,
220-221, Sector-34-A, Chandigarh. 3. OSD to Chairman, PSEB, Patiala. 4. Chief Engineer/Commercial, PSEB, Patiala. 5. Chief Engineer/QI & TA, PSEB, Patiala. 6. Director/I.R., PSEB, Patiala. 7. Director/Technical, PSEB, Patiala. He is requested to endorse the same to
Dy.Secy./Services-III & Dy.Secy./Tech.I, II & III, PSEB, Patiala. 8. Director/I.T., PSEB Patiala for putting the above circular on PSEB web-site. 9. Dy.Director/Sr.XEN/CBC, PSEB, Patiala, Ludhiana & Jalandhar.
PUNJAB STATE ELECTRICITY BOARD
P.R. Circular No 02/2010 Dated: 05.02.2010 From
The Chief Engineer/S.O.&C,
Power Regulation & Control Dte.,
PSEB, 220KV S/Stn., Ablowal, Patiala.
To
1. All EIC/CEs/Distribution in PSEB.
2. Chief Engineer/P&M, PSEB, Ludhiana.
3. Chief Engineer/Enforcement, PSEB, Patiala.
4. All Dy.CEs/SEs/Distribution in PSEB.
5. All Dy.CEs/SEs/P&M in PSEB.
6. All Dy.CEs/Directors/Enforcement & EA&MMTS.
7. All Addl.SEs/Sr.XENs/Distribution along with 5 spare copies for further
distribution amongst XENs/AEEs/AEs.
8. All Addl.SEs/Sr.XENs/P&M, Grid Mtc. & Distribution.
9. All Addl. SEs/Sr.XENs/Enforcement & EA&MMTS.
Memo No. 20492/20632 /SO/PRC/LD-38 Dated: 05.02.2010
Subject: COMPULSORY WEEKLY OFF-DAY ON INDUSTRIES.
Due to increase in additional demand from agriculture sector, it has been decided
to impose Compulsory Staggered Weekly Off day for one day on all General Industries (Large
Supply, Medium Supply, Small Power) including Arc & Induction Furnace Consumers being fed
through category- II & Category-III feeders w.e.f 08.02.2010 till further instructions. The
compulsory weekly Off-day shall not be applicable on General Industrial Consumers including
Arc & Induction Furnace Consumers being fed from Category-I feeders, Urban Pattern Supply
3 Phase 3 wire, 3 phase 4 Wire Feeders & Rural (AP) feeders.
These instructions will be applicable w.e.f 8.2.2010 and industrial consumers
being fed from Cat-II feeders will continue to observe weekly off days from 0800 hours to
2130/2200 hours and Arc Induction and Rolling Mill consumers being fed from Cat-II & Cat-III
feeders will continue to observe weekly off days from 0600 to 2130/2200 hours depending upon
end of Peak Load Hour Restrictions upto 7.2.2010 as already intimated
The following schedule for Compulsory Weekly Off-day shall be observed:
S.No. Name of Distribution Weekly Off-day
Circle
1. Amritsar (City & Suburban) and Monday
Ferozepur Circle
2. Gurdaspur, Nawanshahar Circle Tuesday
3. Faridkot, Hoshiarpur Wednesday
4. Ludhiana (Suburban), Muktsar and Thursday
Tarn Taran Circle
5 Ropar & Bathinda Circle Friday
6. Mohali & Kapurthala Circle Saturday
7. Sangrur, Khanna Circle (except Sunday
Mandi Gobindgarh), Patiala Circle
and Jalandhar Circle
Regarding Ludhiana (City East & City West Circles) & Mandi Gobindgarh, the
staggered Weekly Off-day for General Industries including Arc & Induction Furnaces shall be
observed as per details given below:-
Ludhiana (City East & West) Mandi Gobindgarh
(Area to remain off) (Area to remain off)
MONDAY 66KV Dhandari Kalan-II 66KV S/Stn. Talwara
66KV Focal Point, Phase-VIII (T/F T-1,T-2, T-3 & T-4)
66KV Focal Point-I 66KV Oasis Enterprises feeder
66KV Ludhiana Steel (E/F 66KV S/S Talwara)
66KV Mahavir Spg.
66KV Haibowal
66KV Billet Factory
66KV Sambhav Spg. Mills
TUESDAY 66KV Indra Park 66KV S/Stn.Amloh Road,
66KV D.C.Complex Mandi Gobindgarh
66KV Model Town
66KV Vardhman Spg.Mills
66KV Punjab Concast
220KV Dhandari Kalan-B
66KV Upper India
WEDNESDAY 66KV Giaspura i) 220KV S/S G-II M.Gobindgarh
(Transformer T-2, T-4 & T-6)
220KV Jamalpur ii) 66KV Punjab Forging Feeder
66KV Nurewal (E/F 220KV S/Stn.G-II)
66KV Vishav Karma
66KV Jail Road
66KV Urban Estate Dugri
THURSDAY 66KV Sahnewal i) 66KV S/Stn. Grain Market
66KV Transport Nagar (T/F T-1, T-2 & T-3)
66KV Avery ii) 66KV Nabha Feeder
66KV Aarti Steel (E/F 220KV S/Stn.G-I)
220KV Sahnewal
66KV Balloke
66KV Oswal Woolen Mills
FRIDAY 66KV Kanganwal i) 220KV S/S G-I M.Gobindgarh
66KV Hero (T/F T-1 & T-4)
66KV Ralson ii) 66KV Central S/Stn.
66KV Vardhman Spl.Steel (T/F T-1, T-2 & T-3)
66KV Railway Traction iii) 66KV S/Stn. Focal Point
66KV GT Road
66KV Gill Road
SATURDAY 220KV Dhandari Kalan-A i) 66KV Dutt Feeder
66KV Ferozepur Road (E/F 220 KV S/S G-I)
66KV Amaltas ii) 66KV Bassi Feeder
66KV South City (E/F 220 KV S/S G-I)
66KV Sharu Steel iii) a) 66KV Bhatia Feeder
66KV Chandigarh Road b) 66KV Punjab Steels feeder
66KV Sharu Industries (w.e.f. 5.2.08)
c) 66KV K.C.Soni feeder
(w.e.f. 2.11.07)
(E/F 66KV S/S Amloh Road)
iv) 66KV Bhiwani Indl. Feeder
(E/F 220 KV S/S G-I)
SUNDAY 66KV Dholewal i) 66KV Modern Feeder
66KV Aarti International (E/F 220 KV S/S G-I)
66KV Gaunsgarh ii) 66KV Jyoti Bansal Feeder
66KV Millerganj (E/F 220 KV S/S G-I)
66KV Rockman
66KV Basant Park
66KV Happy Forging
If any S/Stn. has not been covered in the above list, the concerned Dy.CE/SE/DS
may intimate to this office, so that weekly off of that S/Stn. is fixed accordingly.
The timings of Off-day for General Industry will be from 08.00 hrs. to 08.00 hrs. of
next day (i.e. for example, the Weekly Off-day for Monday will start at 08.00 hrs. on Monday and
end at 08.00 hrs. on Tuesday).
The timings of Weekly Off-day in respect of Arc & Induction Furnace & Rolling
Mill Consumers (irrespective of category of feeders) will be from the expiry of Peak Load Hours
of previous day to the expiry of Peak Load Hours of Off-day. For example if the timings of Peak
Load Hours Restrictions are from 19.00 hrs. to 22.00 hrs. then the Weekly Off-day for Monday
will start at 22.00 hrs. on Sunday and end at 22.00 hrs. on Monday.
All Continuous Process/Essential Industries (declared by this office) fed through
Independent Feeders shall be exempted from observing Compulsory Weekly Off-days. The
Essential Services viz. Government Hospitals, Railway Stations, Railway Installations, Defence
& Military Installations, P&T Installations, All India Radio/T.V., Water Supply & Sewerage
Installations and News Paper Printing Presses/News Service Installations will be exempted from
observing Compulsory Weekly Off-day. Milk Plants, Milk Processing Plants, Milk Chilling Units,
Ice Factories, Cold Storages, Oil Depots/L.P.G Depots, Poultry Farms, Ice Candy Units and
Exclusively Bread Mfg. Units will also be exempted from observing Compulsory Weekly Off-day.
The Evening Peak Load Hours Restrictions on Large Supply consumers shall
remain applicable as here to fore.
It is clarified that those Large supply industrial consumers who have taken
permission for running some load during Peak Load Hours on payment of Peak Load Exemption
Charges (PLEC) as per P.R.Circular No. 02/98 & 9/2007 (except Continuous Process/Essential
Industries, mentioned above) shall not be allowed to use the same during Weekly Off-days
including Peak Load Hours. The Peak Load Exemption Charges (PLEC) for the Off-days shall
not be levied. However, all general Industrial Consumers including Arc & Induction Furnace
Consumers shall be allowed to avail eligible exemption as admissible to them as per P.R.
Circular No. 02/98 dated 28.04.98 i.e. the exemption which is eligible to them without payment
of PLEC during Peak Load Hours Restrictions.
The penalty on defaulting consumers who do not observe Weekly Off-days as
per schedule will be levied as per P.R. Circular No. 07/2004 dated 05.07.04 & 08/2004 dated
19.07.04.
It is requested to get these instructions noted from all concerned consumers well
in advance and ensure meticulous compliance of these instructions. These instructions may
also be got displayed on the Grid Sub-Station and Complaint
Centers besides informing various offices of Industrial Associations.
These instructions can also be down loaded from PSEB’s Website
www.psebindia.org.
Director/PR&C,
Encl: As above for Engineer-in-Chief/S.O & C,
PSEB, Patiala.
CC: 1) Chairman, PSEB & All Members/PSEB.
2) Secretary/Punjab State Electricity Regulatory Commission, 220-21,
Sector-34 A, Chandigarh.
3) O.S.D. to Chairman, PSEB, Patiala.
4) Chief Engineer/Commercial, PSEB, Patiala.
5) Chief Engineer/QI & TA, PSEB, Patiala.
6) Director/I.R., PSEB, Patiala.
7) Director/Technical, PSEB, Patiala. He is requested
to endorse the same to Dy.Secy./Services- III &
Dy.Secy./Tech. I, II & III, PSEB, Patiala.
8) Director/I.T., PSEB, Patiala for putting the
above Circular on PSEB Web-site.
9) Dy.Director/Sr.Xen/CBC, PSEB, Patiala, Ludhiana & Jalandhar.
PUNJAB STATE ELECTRICITY BOARD
P.R. Circular No 03/2010
Dated: 18.3.2010
From
The Chief Engineer/S.O.&C,
Power Regulation & Control Dte.,
PSEB, 220KV S/Stn., Ablowal, Patiala.
To
1. All EIC/CEs/Distribution in PSEB.
2. Chief Engineer/P&M, PSEB, Ludhiana.
3. Chief Engineer/Enforcement, PSEB, Patiala.
4. All Dy.CEs/SEs/Distribution in PSEB.
5. All Dy.CEs/SEs/P&M in PSEB.
6. All Dy.CEs/Directors/Enforcement & EA&MMTS.
7. All Addl.SEs/Sr.XENs/Distribution along with 5 spare copies for further
distribution amongst XENs/AEEs/AEs.
8. All Addl.SEs/Sr.XENs/P&M, Grid Mtc. & Distribution.
9. All Addl. SEs/Sr.XENs/Enforcement & EA&MMTS.
Memo No.21596/21736 /SO/PRC/LD-38 Dated: 18.3.2010
Subject: Additional Power Regulatory Measures.
Due to increase in demand in power supply it is decided to impose additional
power regulatory measures with immediate effect for One week w.e.f. 19.3.2010 to 25.3.2010
on Industrial consumer feeding from Category-II, III & IV feeder as under:
1 Category-II feeders: Industrial consumer feeding from Cat-II feeders will
observe weekly off day for 58/58.5 hours instead of 24 hours (1 day). Thus the
consumers whose weekly off day falls on 19.3.2010 (Friday) will observe weekly off day
w.e.f end of Peak Load Hour Restriction of 18.3.10 (Thursday) up to 0800 hours of
21.3.2010 (Sunday) and so on.
2 Arc Induction Furnace and rolling mill consumers: Arc Induction Furnace and
rolling mill consumers, irrespective of the feeder, will observe weekly off day for two days
instead of One day being observed presently. Thus the consumers whose weekly of day
falls on 19.3.2010, will observe weekly off day for 19.32010 to 20.3.2010 and so on.
3 Continuous process industrial consumers: The industrial consumer having
continuous process status, feeding from Cat-IV feeders will observe Peak Load Hours
Restrictions for 12 hours instead of 3 hours being observed presently. Thus these
consumers will observe Peak Load Hours Restrictions from 1830/1900 hours to
0630/0700 hours w.e.f 18.3.10 to 24.3.10 (One week) depending upon the time of start
of Peak Load Hour Restrictions. However, industries other than continuous process
industries like essential/IT industries will observe peak load restriction for 3 hours.
The consumers are requested to download the information regarding Peak Load
Restrictions/weekly off days from the PSEB website. They are asked to visit the website
of the PSEB on regular basis in future.
The field officers are requested to display the relevant Circulars on the Notice Boards
of Complaint Centres as well as Sub Divn Offices/Grid Sub Stations.
The consumers are also requested to watch newspapers for information.
The Relevant information is also being conveyed to PSEB field officers and selected
representatives of Industrial associations. The consumers can also get this information
on Telephone from field officers.
Director/PR&C,
for Chief Engineer/S.O & C,
PSEB, Patiala.
CC: 1) Chairman, PSEB & All Members/PSEB.
2) Secretary/Punjab State Electricity Regulatory Commission, 220-21,
Sector-34 A, Chandigarh.
3) O.S.D. to Chairman, PSEB, Patiala.
4) Chief Engineer/Commercial, PSEB, Patiala.
5) Chief Engineer/QI & TA, PSEB, Patiala.
6) Director/I.R., PSEB, Patiala.
7) Director/Technical, PSEB, Patiala. He is requested
to endorse the same to Dy.Secy./Services- III &
Dy.Secy./Tech. I, II & III, PSEB, Patiala.
8) Director/I.T., PSEB, Patiala for putting the
above Circular on PSEB Web-site.
9) Dy.Director/Sr.Xen/CBC, PSEB, Patiala, Ludhiana & Jalandhar.
PUNJAB STATE POWER CORPORATION LIMITED
P.R. Circular No 04/2010
Dated: 12.05.2010
From
The Chief Engineer/S.O.&C,
Power Regulation & Control Dte.,
Powercom, 220KV S/Stn., Ablowal, Patiala.
To
1. All EIC/CEs/Distribution in PSPCL.
2. Chief Engineer/P&M, PSPCL, Ludhiana.
3. Chief Engineer/Enforcement, PSPCL, Patiala.
4. All Dy.CEs/SEs/Distribution in PSPCL.
5. All Dy.CEs/SEs/P&M in PSPCL.
6. All Dy.CEs/Directors/Enforcement & EA&MMTS.
7. All Addl.SEs/Sr.XENs/Distribution along with 5 spare copies for further
distribution amongst XENs/AEEs/AEs.
8. All Addl.SEs/Sr.XENs/P&M, Grid Mtc. & Distribution.
9. All Addl. SEs/Sr.XENs/Enforcement & EA&MMTS.
Memo No. 853/993 /SO/PRC/LD-38 Dated: 12.05.2010
Subject: COMPULSORY WEEKLY OFF-DAY ON INDUSTRIES.
In super session to PR Circular 3/2010, it was decided to impose following additional
power regulatory measures on all General Industries (Large Supply, Medium Supply, Small
Power) including Arc & Induction Furnace Consumers being fed through category- II, III & IV
feeders w.e.f 20.3.10 to 29.3.10 onwards as under:
S No. Category of
consumer on
which
additional
power
regulatory
measures
imposed
Timings of
weekly off
day/Descriptio
n of PR
measures
Date of
applicability
Remarks
(A)1 General
Consumers
fed from Cat-
II feeder
except Arc
Induction
and Rolling
Mill
consumers
58/58.5 hours
instead of 24
hours (1 day)
20.3.10 to
29.3.10
These consumers whose 1st weekly off day
was falling on 20.3.2010 (Saturday) were to
observe weekly off day w.e.f end of Peak
Load Hour Restriction of 19.3.10 (Friday)
up to 0800 hours of 22.3.2010 (Monday)
and so on.
2 -do- One weekly 30.3.10 to If 1st Weekly off day of the consumer was
off day
6.4.10 falling on 30.3.10, it was applicable from
0800 hours of 30.3.10 up to 0800 hours of
31.3.1.0 & so on.
3
-do- Two days
weekly off day
instead of
One weekly
off day
7.4.10 to
15.4.10
If 1st Weekly off day of the consumer was
falling on 7.4.10 it was applicable from 0800
hours of 7.4.10 up to 0800 hours of 9.4.1.0
& so on
4 -do- 58/57.5 Hours
Instead of 2
days
16.4.10 to
3.5.10
If 1st Weekly off day of the consumer was
falling on 17.4.10 it was applicable from end
of peak load hours restrictions of 16.4.10 up
to 0800 hours of 19.4.1.0 & so on
5
-do-
34/33.5 Hours
Weekly off
day
applicable
4.5.10 to
11.5.10
If 1st weekly off day of the consumer was
falling on 3.5.2010, the consumer was to
observe weekly off days from end of Peak
load hours restrictions hours of 2.5.10 up to
0800 hours of 4.5.2010 and so on.
6 -do- 2 weekly off
days instead
of 34/33.5
hours
12.5.10 to
onwards
If 1st weekly off day of the consumer was
falling on 11.5.10, it was applicable from
0800 hours of 11.5.10 to 0800 hours of
13.5.10 and so on.
(B) 1. Arc,
Induction
and Rolling
Mill
consumers
feeding from
Cat-II & III
feeders
3 weekly off
days instead
of one weekly
off day
20.3.10 to
29.3.10
The consumer, whose 1st weekly of day
was falling on 20.3.2010, was to observe
weekly off day for 20.3.2010 to 22.3.2010
and so on. (From end of Peak load hour
restriction of 19/3/10 to end of PLHRs of
22.3.10)
2
-do- One Weekly
off day
applicable
30.3.10 to
6.4.10
If 1st Weekly off days of the consumer was
falling on 30.3.10, it was applicable from
end of peak load hours of 29.3.10 up to
end of peak load hours of 30.3.1.0 & so on.
3
-do- Two Weekly
off days
applicable
7.4.10 to
15.4.10
Consumer, whose 1st weekly off day was
falling on 7.4.10 was also to observe 2nd
weekly off day on 8.4.10 and so on.
4
-do-
58/57.5 Hours
instead of two
weekly off
days
16.4.10 to
3.5.10
Those consumers whose 2nd weekly off day was falling on 16.4.2010 were to observe weekly off day up to 0800 hours of 17.4.10 (instead of up to end of peak load hours restrictions of 16.4.10) and so on.
5
-do-
34/33.5 Hours 4.5.10 to
7.5.10
If first weekly off day of the consumer was
falling on 3.5.2010 , it was applicable from
end of peak load hours restrictions hours of
2.5.10 up to 0800 hours of 4.5.2010 and so
on.
6
-do- 2 days weekly
off days
8.5.10 to
Onwards
The consumer whose 2nd weekly off day
was to end at 08:00 hrs of 08-05-10 will
now be applicable up to end of peak load
restriction hours of 08-05-10 and so on.
PEAK LOAD
HOURS
RESTRICTIO
NS
(C) 1 Continuous
Process
industrial
(Cat-IV)
Consumers
12 Hours
peak load
hours
restrictions
Instead of 3
hours
20.3.10 to
29.3.10
(with 100%
PLE)
16.4.10 to
3.5.10
(with 75%
PLE refer
para D)
1) These consumers were to observe Peak
Load Hours Restrictions from 1830/1900
hours to 0630/0700 hours (or 1900/1930 to
0700/0730) depending upon the time of
start of Peak Load Restrictions timings.
These consumers who had been allowed to
use some load during Peak load hours,
could use that load for 12 hours but will be
charged only for 3 hours.
2) Normal 3 hours PLHRs remained
applicable on other industries like essential/
IT industry.
2 UPS 3 phase
3 wire
feeders
3 hours peak
load
restrictions
23.3.10 to
29.3.10
Peak load hours restrictions on these
consumers were withdrawn w.e.f 30.3.10 till
further orders. It was also decided that no
peak load violation charges are to be levied
on these consumers, if they could not have
observed peak load hours restrictions.
PEAK LOAD
EXEMPTION
(D) Industrial
Consumers
feeding from
Cat-II, III & IV
(continuous
process
industry)
feeders
Peak Load
Exemptions
were curtailed
to the extent
of 75% of
PLE allowed
7.4.10 to
3.5.10
Applicable
only for
continuous
process
industries
(Cat-IV
feeder) the
100% Peak load exemption remained
applicable with 3 hours peak load hours
restrictions for industrial consumer being
fed from Cat-I feeders, IT Industry and
essential industries covered under PR
Circular 12/98 dated 3.8.98 and other
exempted categories of industries like cold
storages/Slaughter houses with partly cold
storage load Ice factories, poultry farms, Ice
candy plants, milk plants/milk chilling units
consumers
were
allowed to
use PLE up
to the extent
of 75%
allowed.
and exclusively bread manufacturing units.
All other terms and conditions of PR Circular No. 2/2010 dated 5.2.10 including penalty for
violation remained unchanged. The instructions to switch off mixed category-II feeders
for 4 hours during weekly off days were also withdrawn w.e.f 6.5.10 to onwards.
Note: Peak Load Exemption charges are to be levied on the consumer to the
extent of 75% for the period the peak load exemption usage was curtailed to 75%.
The consumers were requested to download the information regarding Peak Load
Restrictions/weekly off days from the PSEB website. They were asked to visit the website of
the PSEB on regular basis in future.
The field officers were requested to display the relevant Circulars on the Notice Boards
of Complaint Centres as well as Sub Divn Offices/Grid Sub Stations.
The Relevant information is also being conveyed to PSEB field officers and selected
representatives of Industrial associations. The consumers could also get this information on
Telephone from field officers.
Dy. Chief Engineer / PR&C
For Chief Engineer / SO&C
PSPCL, Patiala.
CC: 1) Chairman, PSEB & All Members/PSPCL.
2) Secretary/Punjab State Electricity Regulatory Commission, 220-21, Sector-34 A, Chandigarh. 3) O.S.D. to Chairman, PSEB, Patiala. 4) Chief Engineer/Commercial, PSPCL, Patiala. 5) Chief Engineer/QI & TA, PSPCL, Patiala. 6) SE/I.R., PSPCL, Patiala. 7) SE/Technical, PSPCL, Patiala. He is requested to endorse the same to Dy.Secy./Services- III & Dy.Secy./Tech. I, II & III, PSPCL, Patiala. 8) SE/I.T., PSPCL, Patiala for putting the
above Circular on PSEB Web-site. 9) Addl SE/Sr.Xen/CBC, PSPCL, Patiala, Ludhiana & Jalandhar.
PUNJAB STATE POWER CORPORATION LIMITED
P.R. Circular No. 5/2010
Dated: 31.5.10
From
Engineer-in-Chief /Commercial
Punjab State Power Corporation Limited
Patiala.
To
1. All EIC/CEs/Distribution in PSPCL.
2. Chief Engineer/P&M, PSPCL, Ludhiana.
3. Chief Engineer/Enforcement, PSPCL, Patiala.
4. All Dy.CEs/SEs/Distribution in PSPCL.
5. All Dy.CEs/SEs/P&M in PSPCL.
6. All Dy.CEs/SEs/Enforcement & EA&MMTS.
7. All Addl.SEs/Sr.XENs/Distribution along with 5 spare copies for further
distribution amongst XENs/AEEs/AEs.
8. All Addl.SEs/Sr.XENs/P&M, Grid Mtc. & Distribution along with 5 spare copies.
9. All Addl. SEs/Sr.XENs/Enforcement & EA&MMTS along with 5 spare copies.
Memo No. 1413/1553 /SO/PRC/LD-38 Dated 31.5.10
Subject: COMPULSORY WEEKLY OFF-DAYS ON INDUSTRIES. - RELAXATIONS
PSPCL has filed a Petition before PSERC regarding imposing power cuts and
other regulatory measures which has been approved by PSERC and accordingly it is decided
that following categories of consumers will be exempted from observing compulsory weekly off
days.
1. All Continuous Process Industries (declared) being fed from through Independent feeders.
2. Essential services covered under PR Circular No. 12/98. 3. Essential Industries covered under PR Circular No. 12/98. 4. Other exempted categories such as cold storage, ice factories, ice candy plants,
slaughter houses, poultry farms and exclusively bread manufacturing units. The evening peak load hours restrictions on large supply consumers shall remain
applicable as here to fore.
It is clarified that those Large supply industrial consumers who have taken permission for
running some load during peak load hours on payment of peak Load Exemption Charges
(PLEC) as per PR Circular No. 2/98 and 9/2007 (except Continuous Process/Essential
Industries and exempted categories mentioned above) shall not be allowed to use the same
during weekly off days including Peak Load Hours nor the Peak Load Exemption Charges
(PLEC) for the off-days shall be levied.
The penalty on defaulting consumers who do not observe Weekly Off-days as per
schedule will be levied as per P.R. Circular No. 07/2004 dated 05.07.04 & 08/2004 dated
19.07.04.
The consumers are requested to down load the above instructions from PSPCL website.
www.psebindia.org.
It is requested to get these instructions noted from all concerned consumers well in
advance and ensure meticulous compliance of these instructions. These instructions may also
be got displayed on the Grid Sub-Station and Complaint Centers besides informing various
offices of Industrial Associations.
SE / ISB,
for Er-in-Chief/Commercial,
PSPCL, Patiala.
CC:
1) Chairman, PSPCL & All Members/PSPCL.
2) Secretary/Punjab State Electricity Regulatory Commission, 220-21,
Sector-34 A, Chandigarh.
3) O.S.D. to Chairman, PSPCL, Patiala.
4) Er-in-Chief /Commercial, PSPCL, Patiala.
5) Chief Engineer/QI & TA, PSPCL, Patiala.
6) Director/I.R., PSPCL, Patiala.
7) SE/Technical, PSPCL Patiala. He is requested
to endorse the same to Dy.Secy./Services- III &
Dy.Secy./Tech. I, II & III, PSPCL, Patiala.
8) SE/I.T., PSPCL, Patiala for putting the
above Circular on PSPCL Web-site.
9) Addl SE/Sr.Xen/CBC, PSPCL, Patiala, Ludhiana & Jalandhar.
PUNJAB STATE POWER CORPORATION LIMITED
P.R. Circular No. 6/2010
Dated: 31.5.10
From
Engineer-in-Chief /Commercial
Punjab State Power Corporation Limited
Patiala.
To
1. All EIC/CEs/Distribution in PSPCL.
2. Chief Engineer/P&M, PSPCL, Ludhiana.
3. Chief Engineer/Enforcement, PSPCL, Patiala.
4. All Dy.CEs/SEs/Distribution in PSPCL.
5. All Dy.CEs/SEs/P&M in PSPCL.
6. All Dy.CEs/SEs/Enforcement & EA&MMTS.
7. All Addl.SEs/Sr.XENs/Distribution along with 5 spare copies for further
distribution amongst XENs/AEEs/AEs.
8. All Addl.SEs/Sr.XENs/P&M, Grid Mtc. & Distribution along with 5 spare copies.
9. All Addl. SEs/Sr.XENs/Enforcement & EA&MMTS along with 5 spare copies.
Memo No. 1778/1918 /SO/PRC/LD-38 Dated 31.5.10
Subject: PR Circular 9/2007 - Levy of Peak Load Exemption Charges and imposition of
weekly off day restrictions – Amendment Thereof
All Large Supply Consumers except Essential Services (such as Hospitals, Railway
Stations, Railway Installations, Defence & Military Installations, All India Radio/T.V.,
Water Supply & Sewerage Installations, P&T Installations and News Service
Installations etc.) are required to observe Evening Peak Load Hours restrictions. As
per P.R. Circular No. 9/2007, exemptions from observing Peak Load Restrictions
are being allowed as per their request, to Large Supply consumers against payment
of Peak Load Exemption Charges as fixed by the Board in addition to normal tariff.
A peak load policy was prepared and submitted to Hon ‘able Punjab State
Electricity Regulatory Commission for approval. As per approval of PSERC, it is
decided to amend PR Circular 9/2007 as under:
1 Dy CEs/SE/DS will allow PLE up to 100 KW (instead of 100 KW).
2 Peak Load Exemption charges will remain unchanged and will be applicable.
3 Peak Load Exemption above 100 KW will be issued by the office of Engineer-in-
Chief /Commercial.
4 The condition to avail PLE for minimum 6 months in first instance and for minimum 3
months in subsequent instance has been substituted with one month. Now the
industrial consumers will be allowed to increase/decrease/withdraw peak load
exemption after one month of its grant whether in first or in subsequent instance.
5 Peak load exemption issued to consumers up to 31.5.10 will not be extended further
in paddy season except for following categories of consumers:
Categories of consumers entitled to PLH exemptions:
(a) Information Technology based industries. (b) Essential industries i.e Fertilizer Plants (except N.F.L. Bathinda and N.F.L. Nangal
(New), Gas Plants, Sugar Mills, Vanspati Mills, Milk Plants, Milk processing Plants,
Malt processing plants, Breweries & Distilleries, Roller Floor mills, Railway
workshops, oil Depots/L.P.G. Depots, Drugs & Pharmaceuticals Units, Environment
Treatment Plants (E.T.P Plants )/ Pollution Control Equipment. and other exempted
categories such as cold storages, ice factories, ice candy plants, slaughter houses,
poultry farms and exclusively bread manufacturing units.
(c) Central sectors PSUs i.e NFLs, Railway workshops, Punjab Govt. Sponsored projects such as PACL & SIEL and cement manufacturers obtaining fly ash from the thermal plants of Powercom.
(d) Continuous process industries declared as such by the competent authority designated by Powercom.
(e) There will be no curtailment in Peak load exemption or extension in peak load hour restrictions in case of consumers at sr no.5(a) to 5(d) above.
6 Applications of consumers not falling in the essential industries and exempted categories enumerated above but seeking exemptions from PLH restrictions will be dealt with as below:
i) First preference will be given to the consumers who had regularly obtained PL exemptions in the previous years. In case adequate power to accommodate all such exemptees is not likely to be available, then the permissible load in the case of all exemptees will be reduced on pro- rata basis.
ii) If power availability makes it possible to accommodate more consumers, then Powercom will, one month before it proposes to grant PLEs, seek applications from intending consumers and further PLH exemption, will be granted on first come first served basis.
7 The consumers who are running their TG/DG sets with synchronization of PSPCL system will continue to get PLE on day to day basis in case of breakdown of their TG/DG sets subject to availability of power on real time basis. The consumer who have been allowed to use some load during peak
load hour restrictions against the payment of Peak Load Exemption Charges,
will not use this load (except continuous process/essential industry and other
exempted industry to which exemption from observing weekly off days is
allowed) during weekly off days and nor the payment of Peak Load Exemption
Charges will be charged to them.
8 It is once again reiterated that the peak load exemption allowed to any consumer will not entitle him to claim it as a matter of right since peak load exemption can be withdrawn by the PSPCL completely/partially keeping in view the system constraints/power availability during peak load exemption period.
9 The other terms and conditions on the subject including penalty for violation remains unchanged.
SE / ISB,
for Er-in-Chief/Commercial,
PSPCL, Patiala.
CC:
1) Chairman, PSPCL & All Members/PSPCL.
2) Secretary/Punjab State Electricity Regulatory Commission, 220-21,
Sector-34 A, Chandigarh.
3) O.S.D. to Chairman, PSPCL, Patiala.
4) Er-in-Chief /Commercial, PSPCL, Patiala.
5) Chief Engineer/QI & TA, PSPCL, Patiala.
6) Director/I.R., PSPCL, Patiala.
7) SE/Technical, PSPCL Patiala. He is requested
to endorse the same to Dy.Secy./Services- III &
Dy.Secy./Tech. I, II & III, PSPCL, Patiala.
8) SE/I.T., PSPCL, Patiala for putting the
above Circular on PSPCL Web-site.
9) Addl SE/Sr.Xen/CBC, PSPCL, Patiala, Ludhiana & Jalandhar.
PUNJAB STATE POWER CORPORATION LIMITED
P.R. Circular No 07/2010
Dated: 29.07.2010
From
The Chief Engineer/Commercial,
Power Regulation & Control Dte.,
Powercom, 220KV S/Stn., Ablowal, Patiala.
To
1. All EIC/CEs/Distribution in PSPCL.
2. Chief Engineer/P&M, PSPCL, Ludhiana.
3. Chief Engineer/Enforcement, PSPCL, Patiala.
4. All Dy.CEs/SEs/Distribution in PSPCL.
5. All Dy.CEs/SEs/P&M in PSPCL.
6. All Dy.CEs/Directors/Enforcement & EA&MMTS.
7. All Addl.SEs/Sr.XENs/Distribution along with 5 spare copies for further
distribution amongst XENs/AEEs/AEs.
8. All Addl.SEs/Sr.XENs/P&M, Grid Mtc. & Distribution.
9. All Addl. SEs/Sr.XENs/Enforcement & EA&MMTS.
Memo No. 2574/2714/SO/PRC/LD-38 Dated: 29.7.10
Subject: COMPULSORY WEEKLY OFF-DAY ON INDUSTRIES.
As per the availability of power regulatory measures were taken in the month of
May & June of 2010 through various telephone messages by this office. Details of
weekly off days applicable to Industrial consumer during these months are listed below:
1
2 3 4 5
S No. Category of
consumer on
which
additional
power
regulatory
measures
imposed
Timings of
weekly off
day/Descriptio
n of PR
measures
Date of
applicability
Remarks
(A)1 General
Consumers
fed from Cat-
II feeder
except Arc
Induction
and Rolling
Mill
2 weekly off
days.
12.5.10 to
onwards
If 1st weekly off day of the
consumer was falling on 11.5.10,
it was applicable from 0800 hours
of 11.5.10 to 0800 hours of
13.5.10 and so on.
As per PR circular 4/2010 dated
consumers 12.5.10
2 -do- 1 weekly off
day.
w.e.f.
28.5.10 to
6.6.10
The consumer whose 1st weekly
off day was falling on 27.5.10, was
not to observe 2nd weekly off day
on 28.5.10 and so on.
3
-do- Relaxation
from
observing
weekly off
day.
7.6.10 to
19.6.10
No weekly off day was applicable
during this period
4 -do- One weekly
off day
20.6.10 to
onwards
The consumers were required to
observe one weekly off day from
0800 hrs of weekly off day to 0800
hours of next day
5
-do-
Relaxation
from
observing
weekly off
day.
25.6.10 to
28.6.10 and
1.7.10 to
5.7.10
The consumers were not required
to observe any weekly off day
during this period
6 -do-
(B) 1. Arc,
Induction
and Rolling
Mill
consumers
feeding from
Cat-II & III
feeders
2 days weekly
off days
8.5.10 to
Onwards
The consumer whose 2nd weekly
off day was to end at 08:00 hrs of
08-05-10 will now be applicable up
to end of peak load restriction
hours of 08-05-10 and so on.
As per PR circular 4/2010 dated
12.5.10
2
-do- 1 weekly off
day.
w.e.f.
28.5.10 to
31.5.10
The consumer whose 1st weekly
off day was falling on 27.5.10, was
not to observe 2nd weekly off day
on 28.5.10 and so on.
3
-do- Two Weekly
off days
applicable
1.6.10 to
6.6.10
Consumer, whose 1st weekly off
day was falling on 1.6.10 was also
to observe 2nd weekly off day on
2.6.10 and so on.
4
-do-
One weekly
off day
7.6.10 to
7.6.10
The consumers were to observe
only first weekly off day
5 Relaxation 8.6.10 to The consumers were not required
-do- from
observing
weekly off
days
19.6.10 to observe any weekly off day during this period
6
-do- One weekly
off day
20.6.10 to
21.6.10
The consumers were allowed to
observe only one weekly off day
from end of peak load hour of
19.6.10 to end of PLHR of 20.6.10
and so on.
7 -do- Two weekly
off days
22.6.10 to
onwards
except
relaxation at
Sr. No. 8
The consumer whose weekly off
day was falling on 21.6.10 were
also to observe 2nd weekly off day
on 22.6.10
8 -do- Relaxation
from
observing
weekly off
days
25.6.10 to
28.6.10 and
1.7.10 to
5.7.10
The consumers were not required
to observe any weekly off day
during this period
Note: 1) Mixed Cat-II feeders (Mixed feeders only) are to be switched off from Grid S/Stn
during their weekly off days (applicable to General industry being fed from Cat-II
feeders) from 1000 to 1200 hours and 1500 to 1700 hours.
2) Weekly off day for all industrial consumers under the jurisdiction of Patiala Circle
falling on 27.6.10 was relaxed, on account of Disturbance in supply on 23.6.10. This
was a one time relaxation and thereafter from 28.6.10 the consumers are required to
observe weekly off day as applicable/intimated from time to time.
The consumers were requested to download the information regarding Peak Load
Restrictions/weekly off days from the PSPCL website. They were asked to visit the website of
the PSPCL on regular basis in future.
The field officers were requested to display the relevant Circulars on the Notice Boards
of Complaint Centres as well as Sub Divn Offices/Grid Sub Stations.
The Relevant information is also being conveyed to PSPCL field officers and
selected representatives of Industrial associations. The consumers could also get this
information on Telephone from field officers.
This issues with the approval of competent authority.
Dy Chief Engineer / ISB,
for Chief Engineer/Commercial,
PSPCL, Patiala.
CC: 1) Chairman, PSEB & All Members/PSPCL.
2) Secretary/Punjab State Electricity Regulatory Commission, 220-21,
Sector-34 A, Chandigarh.
3) O.S.D. to Chairman, PSEB, Patiala.
4) Chief Engineer/Commercial, PSPCL, Patiala.
5) Chief Engineer/QI & TA, PSPCL, Patiala.
6) SE/I.R., PSPCL, Patiala.
7) SE/Technical, PSPCL, Patiala. He is requested
to endorse the same to Dy.Secy./Services- III &
Dy.Secy./Tech. I, II & III, PSPCL, Patiala.
8) SE/I.T., PSPCL, Patiala for putting the
above Circular on PSEB Web-site.
10) Addl SE/Sr.Xen/CBC, PSPCL, Patiala, Ludhiana & Jalandhar.
PUNJAB STATE POWER CORPORATION LIMITED
P.R. Circular No 08/2010
Dated: 13.08.2010 From The Chief Engineer/Commercial, Power Regulation & Control Dte., Powercom, 220KV S/Stn., Ablowal, Patiala. To
1. All EIC/CEs/Distribution in PSPCL. 2. Chief Engineer/P&M, PSPCL, Ludhiana. 3. Chief Engineer/Enforcement, PSPCL, Patiala. 4. All Dy.CEs/SEs/Distribution in PSPCL. 5. All Dy.CEs/SEs/P&M in PSPCL. 6. All Dy.CEs/Directors/Enforcement & EA&MMTS. 7. All Addl.SEs/Sr.XENs/Distribution along with 5 spare copies for further
distribution amongst XENs/AEEs/AEs. 8. All Addl.SEs/Sr.XENs/P&M, Grid Mtc. & Distribution. 9. All Addl. SEs/Sr.XENs/Enforcement & EA&MMTS.
Memo No. 2925/3065/SO/PRC/LD-38 Dated: 13.8.10
Subject: COMPULSORY WEEKLY OFF-DAY ON INDUSTRIES.
As per the availability of power regulatory measures/relaxations were imposed in
the month of July of 2010 through various telephone messages by this office. Details of
weekly off days applicable to Industrial consumer during these months are listed below:
1 2 3 4 5
S No. Category of
consumer on
which
additional
power
regulatory
measures
imposed
Timings of
weekly off
day/Descriptio
n of PR
measures
Date of
applicability
Remarks
(A)1 General
Consumers
fed from Cat-
II feeder
except Arc
Induction
and Rolling
Mill
consumers
Relaxation
from
observing
weekly off
day.
1.7.10 to
5.7.10
As per PR circular 7/2010
2 -do- Relaxation
from
observing
weekly off
6.7.10 to
15.7.10
The consumers were not
required to observe any
weekly off day during this
day. period
3
-do- One weekly
off day
16.7.10 to
19.7.10
Only one weekly off day
was applicable
4 -do- Relaxation from
observing
weekly off day.
20.7.10 to
28.7.10
The consumers were not
required to observe any
weekly off day during this
period
5
-do-
One weekly
off day of
13.5/14 hours
29.7.10 to
onwards
The consumers were to
observe weekly off day
from 0800 hrs to end of
peak load hour restrictions
(B) 1. Arc,
Induction
and Rolling
Mill
consumers
feeding from
Cat-II & III
feeders
Relaxation
from
observing
weekly off
day.
1.7.10 to
5.7.10
As per PR circular 7/2010
2
-do- Relaxation
from
observing
weekly off day
6.7.10 to
14.7.10
The consumers were not
required to observe any
weekly off day during this
period
3
-do- One weekly
off day
15.7.10 to
18.7.10
Only one weekly off day
was applicable
4
-do-
Two weekly
off days
19.7.10 to
19.7.10
If 1st weekly off day of
consumer was on 18.7.10,
he was to observe 2nd
weekly off day on 19.7.10
and so on
5
-do-
Relaxation
from
observing
weekly off
days
20.7.10 to
28.7.10
The consumers were not required to observe any weekly off day during this period
6
-do- Two weekly
off days of
16.5/17 hours
each
29.7.10 to
onwards
The consumers were to
observe weekly off day
from 0600 hrs to end of
peak load hour restrictions
Note: 1) Mixed Cat-II feeders (Mixed feeders only) are to be switched off from Grid S/Stn
during their weekly off days (applicable to General industry being fed from Cat-II
feeders) from 1000 to 1200 hours and 1500 to 1700 hours as per PR Circular 7/2010
dated 29.7.10.
The consumers were requested to download the information regarding Peak Load
Restrictions/weekly off days from the PSPCL website. They were asked to visit the website of
the PSPCL on regular basis in future.
The field officers were requested to display the relevant Circulars on the Notice Boards
of Complaint Centres as well as Sub Divn Offices/Grid Sub Stations.
The Relevant information is also being conveyed to PSPCL field officers and
selected representatives of Industrial associations. The consumers could also get this
information on Telephone from field officers.
This issues with the approval of competent authority.
Dy Chief Engineer / ISB,
for Chief Engineer/Commercial,
PSPCL, Patiala.
CC: 1) Chairman, PSEB & All Members/PSPCL.
2) Secretary/Punjab State Electricity Regulatory Commission, 220-21,
Sector-34 A, Chandigarh.
3) O.S.D. to Chairman, PSEB, Patiala.
4) Chief Engineer/Commercial, PSPCL, Patiala.
5) Chief Engineer/QI & TA, PSPCL, Patiala.
6) SE/I.R., PSPCL, Patiala.
7) SE/Technical, PSPCL, Patiala. He is requested
to endorse the same to Dy.Secy./Services- III &
Dy.Secy./Tech. I, II & III, PSPCL, Patiala.
8) SE/I.T., PSPCL, Patiala for putting the
above Circular on PSEB Web-site.
11) Addl SE/Sr.Xen/CBC, PSPCL, Patiala, Ludhiana & Jalandhar.
PUNJAB STATE POWER CORPORATION LIMITED
P.R. Circular No 09/2010
Dated: 27.09.2010
From
The Chief Engineer/Metering,
PSPCL, Patiala.
To
1. All EIC/CEs/Distribution in PSPCL.
2. Chief Engineer/P&M, PSPCL, Ludhiana.
3. Chief Engineer/Enforcement, PSPCL, Patiala.
4. All Dy.CEs/SEs/Distribution in PSPCL.
5. All Dy.CEs/SEs/P&M in PSPCL.
6. All Dy.CEs/Directors/Enforcement & EA&MMTS.
7. All Addl.SEs/Sr.XENs/Distribution along with 5 spare copies for further
distribution amongst XENs/AEEs/AEs.
8. All Addl.SEs/Sr.XENs/P&M, Grid Mtc. & Distribution.
9. All Addl. SEs/Sr.XENs/Enforcement & EA&MMTS.
Memo No. 3971/4111 /SO/PRC/LD-38 Dated: 27.09.2010
Subject: Policy Regarding grant of Continuous Process Status to
Industry and providing Independent feeder – Reconstitution of
Committee
In continuation to PR Circular 8/2003 dated 23.7.03, it is
decided to reconstitute the committee consisting of following officers
and representative of industry nominated by PSERC for grant of
Continuous Process Status/ Independent feeder to Industrial
consumers.
1 Director/Distribution, PSPCL Chairman
2 Er-in-Chief/CE/DS concerned Member
3 Er-in-Chief/CE Incharge
Power Regulation Member
4 Mr Akshay Bector, Managing Director,
M/s Bector Food Specialities Ltd,
Theing Road, Phillaur, District Jalandhar Member
5 Dy Chief Engineer/SE, Incharge Power Regulation Conveyor
Other terms and conditions of PR Circular 8/2003 will remain
unchanged
Dy Chief Engineer / PR&C,
for Chief Engineer/Metering,
PSPCL, Patiala.
CC: 1) Chairman, PSPCL & All Members/PSPCL.
2) Secretary/Punjab State Electricity Regulatory Commission, 220-21,
Sector-34 A, Chandigarh.
3) Mr Akshay Bector, Managing Director, M/s Bector Food Specialities Ltd,
Theing Road, Phillaur, District Jalandhar
4) O.S.D. to Chairman, PSPCL, Patiala.
5) Chief Engineer/Commercial, PSPCL, Patiala.
6) Chief Engineer/QI & TA, PSPCL, Patiala.
7) SE/I.R., PSPCL, Patiala.
8) SE/Technical, PSPCL, Patiala. He is requested
to endorse the same to Dy.Secy./Services- III & Dy.Secy./Tech. I, II &
III, PSPCL, Patiala.
9) SE/I.T., PSPCL, Patiala for putting the above Circular on PSEB Web-site.
10) Addl SE/Sr.Xen/CBC, PSPCL, Patiala, Ludhiana & Jalandhar.
PUNJAB STATE POWER CORPORATION LIMITED
P.R. Circular No 10/2010
Dated: 30.09.2010
From
The Chief Engineer/Metering,
PSPCL, Patiala.
To
1. All EIC/CEs/Distribution in PSPCL.
2. Chief Engineer/P&M, PSPCL, Ludhiana.
3. Chief Engineer/Enforcement, PSPCL, Patiala.
4. All Dy.CEs/SEs/Distribution in PSPCL.
5. All Dy.CEs/SEs/P&M in PSPCL.
6. All Dy.CEs/Directors/Enforcement & EA&MMTS.
7. All Addl.SEs/Sr.XENs/Distribution along with 5 spare copies for further
distribution amongst XENs/AEEs/AEs.
8. All Addl.SEs/Sr.XENs/P&M, Grid Mtc. & Distribution.
9. All Addl. SEs/Sr.XENs/Enforcement & EA&MMTS.
Memo No. 4914/5054 /SO/PRC/LD-38 Dated: 30.09.2010
Subject: Grant of Peak Load Exemption to General Industrial
Consumers.
To avoid delay in grant of Peak Load Exemption to General LS
consumers, it is intimated that general industrial consumers, who had
applied for Peak Load Exemption above 100 KW in this office or in the
office of respective Chief Engineer/DS, are allowed to use Peak Load
Exemption w.e.f. 1.10.10 onwards up to 31.5.11 as per their
requirement (maximum up to 90% sanctioned contract demand).
sanction letters are being issued separately.
The consumers seeking Peak Load Exemption above 100 KW,
who have not already applied to this office should apply immediately
through e-mail, fax or post directly to this office.
Dy Chief Engineer / PR&C,
for Chief Engineer/Metering,
PSPCL, Patiala.
CC: 1) Chairman, PSPCL & All Members/PSPCL.
2) Secretary/Punjab State Electricity Regulatory Commission, 220-21,
Sector-34 A, Chandigarh.
3) Mr Akshay Bector, Managing Director, M/s Bector Food Specialities Ltd,
Theing Road, Phillaur, District Jalandhar
4) O.S.D. to Chairman, PSPCL, Patiala.
5) Chief Engineer/Commercial, PSPCL, Patiala.
6) Chief Engineer/QI & TA, PSPCL, Patiala.
7) SE/I.R., PSPCL, Patiala.
8) SE/Technical, PSPCL, Patiala. He is requested
to endorse the same to Dy.Secy./Services- III & Dy.Secy./Tech. I, II &
III, PSPCL, Patiala.
9) SE/I.T., PSPCL, Patiala for putting the above Circular on PSEB Web-site.
11) Addl SE/Sr.Xen/CBC, PSPCL, Patiala, Ludhiana & Jalandhar.
PUNJAB STATE POWER CORPORATION LIMITED
P.R. Circular No.11/2010
Dated: 12.10.2010
From
Chief Engineer/Metering
Punjab State Power Corporation Limited
Patiala.
To
1. All EIC/CEs/Distribution in PSPCL.
2. Chief Engineer/P&M, PSPCL, Ludhiana.
3. Chief Engineer/Enforcement, PSPCL, Patiala.
4. All Dy.CEs/SEs/Distribution in PSPCL.
5. All Dy.CEs/SEs/P&M in PSPCL.
6. All Dy.CEs/SEs/Enforcement & EA&MMTS.
7. All Addl.SEs/Sr.XENs/Distribution
8. All Addl.SEs/Sr.XENs/P&M, Grid Mtc. & Distribution.
9. All Addl. SEs/Sr.XENs/Enforcement & EA&MMTS.
Memo No. 6967/7087/SO/PRC/LD-38 Dated 12.10.2010
Subject: COMPULSORY WEEKLY OFF-DAYS ON IT BASED INDUSTRIES -
RELAXATIONS
As per clarification given by Hon' able Punjab State Electricity
Regulatory Commission following categories of consumers will be exempted from
observing compulsory weekly off days.
1. All Continuous Process Industries (declared) being fed from through
Independent feeders. 2. Essential services covered under PR Circular No. 12/98.
3. Essential Industries covered under PR Circular No. 12/98. 4. Other exempted categories such as cold storage, ice factories, ice candy
plants, slaughter houses, poultry farms and exclusively bread
manufacturing units. 5. Information Technology based industries.
The PR Circular 5/2010 dated 31.5.10 may be treated as amended up to
this extent.
Dy Chief Engineer/PR&C
for Chief Engineer/Metering,
PSPCL, Patiala.
CC:
1) Chairman, PSPCL & All Members/PSPCL.
2) Secretary/Punjab State Electricity Regulatory Commission, 220-21,
Sector-34 A, Chandigarh.
3) O.S.D. to Chairman, PSPCL, Patiala.
4) Er-in-Chief /Commercial, PSPCL, Patiala.
5) Chief Engineer/QI & TA, PSPCL, Patiala.
6) Director/I.R., PSPCL, Patiala.
7) SE/Technical, PSPCL Patiala. He is requested to endorse the same to
Dy.Secy./Services- III & Dy.Secy./Tech. I, II & III, PSPCL, Patiala.
8) SE/I.T., PSPCL, Patiala for putting the above Circular on PSPCL Web-
site.
9) Addl SE/Sr.Xen/CBC, PSPCL, Patiala, Ludhiana & Jalandhar.
PUNJAB STATE POWER CORPORATION LIMITED
P.R. Circular No 12/2010 Dated: 03.11.2010
From
Chief Engineer/Power Purchase & Regulation,
PSPCL, Patiala.
To
1. All EIC/CEs/Distribution in PSPCL.
2. Chief Engineer/P&M, PSPCL, Ludhiana.
3. Chief Engineer/Enforcement, PSPCL, Patiala.
4. All Dy.CEs/SEs/Distribution in PSPCL.
5. All Dy.CEs/SEs/P&M in PSPCL.
6. All Dy.CEs/Directors/Enforcement & EA&MMTS.
7. All Addl.SEs/Sr.XENs/Distribution along with 5 spare copies for further
distribution amongst XENs/AEEs/AEs.
8. All Addl.SEs/Sr.XENs/P&M, Grid Mtc. & Distribution.
9. All Addl. SEs/Sr.XENs/Enforcement & EA&MMTS.
Memo No. 81618301 /SO/PRC/LD-38 Dated: 03.11.2010
Subject: COMPULSORY WEEKLY OFF-DAY ON INDUSTRIES.
As per the availability of power regulatory measures/relaxations were imposed in
the month of August of 2010 through various telephone messages by this office. Details
of weekly off days applicable to Industrial consumer during these months are listed
below:
1 2 3 4 5
S No. Category of
consumer on
which
additional
power
regulatory
measures
imposed
Timings of
weekly off day
/ Description
of PR
measures
Date of
applicability
Remarks
(A)1 General
Consumers
fed from Cat-
II feeder
except Arc
Induction
and Rolling
Mill
consumers
One weekly
off day of
14.5/15 hours
29.7.10 to
31.7.10
The consumers were to
observe weekly off day
from 0800 hrs to end of
PLHRs of weekly off day
2 -do- Relaxation
from
1.8.10 to
3.8.10
The consumers were not
required to observe any
observing
weekly off
day.
11.8.10 to
15.8.10
18.8.10 to
31.8.10,
4.9.10 to
30.9.10 and
10.10.10 to
onwards
weekly off day during this
period
3 -do- One weekly
off day
4.8.10 to
10.8.10
16.8.10 to
17.8.10,
1.9.10 to
3.9.10 and
1.10.10 to
9.10.10
Only one weekly off day
was applicable from 0800
hours of weekly off day to
0800 hrs of next day
(B) 1. Arc,
Induction
and Rolling
Mill
consumers
feeding from
Cat-II & III
feeders
Two weekly of
days of
16.5/17 hours
each
29.7.10 to
31.7.10
The consumers were to
observe weekly off day
from 0600 hrs to end of
PLHRs of weekly off days
2 -do- Relaxation
from
observing
weekly off
day.
1.8.10 to
3.8.10
11.8.10 to
15.8.10
18.8.10 to
31.8.10,
4.9.10 to
30.9.10 and
10.10.10 to
onwards
The consumers were not
required to observe any
weekly off day during this
period
3
-do- Two weekly
off days
4.8.10 to
10.8.10
If 1st weekly off day of
consumer was on 3.8.10,
he was to observe 2nd
weekly off day on 4.8.10
and so on. If 1st weekly off
day was on 4.8.10 the
consumer was to observe
weekly of days from end of
16.8.10 to
17.8.10,
1.9.10 to
3.9.10 and
1.10.10 to
9.10.2010
PLHRs of 3.8.10 to end of
PLHRs of 5.8.10 and so
on.
The consumers were requested to download the information regarding Peak Load
Restrictions/weekly off days from the PSPCL website. They were asked to visit the
website of the PSPCL on regular basis in future.
The field officers were requested to display the relevant Circulars on the Notice Boards
of Complaint Centres as well as Sub Divn Offices/Grid Sub Stations.
The Relevant information is also being conveyed to PSPCL field officers and
selected representatives of Industrial associations. The consumers could also get this
information on Telephone from field officers.
This issues with the approval of competent authority.
Dy Chief Engineer / P R,
for Chief Engineer/PP&R,
PSPCL, Patiala.
CC: 1) Chairman, PSPCL & All Members/PSPCL.
2) Secretary/Punjab State Electricity Regulatory Commission, 220-21,
Sector-34 A, Chandigarh.
3) O.S.D. to Chairman, PSPCL, Patiala.
4) Chief Engineer/Commercial, PSPCL, Patiala.
5) Chief Engineer/QI & TA, PSPCL, Patiala.
6) SE/I.R., PSPCL, Patiala.
7) SE/Technical, PSPCL, Patiala. He is requested
to endorse the same to Dy.Secy./Services- III &
Dy.Secy./Tech. I, II & III, PSPCL, Patiala.
8) SE/I.T., PSPCL, Patiala for putting the
above Circular on PSEB Web-site.
12) Addl SE/Sr.Xen/CBC, PSPCL, Patiala, Ludhiana & Jalandhar.
PUNJAB STATE POWER CORPORATION LIMITED
P.R. Circular No.13/2010
Dated: 28-12-2010
From
Engineer-in-Chief /PP&R,
Punjab State Power Corporation Limited
Patiala.
To
1. All EIC/CEs/Distribution in PSPCL.
2. Chief Engineer/P&M, PSPCL, Ludhiana.
3. Chief Engineer/Enforcement, PSPCL, Patiala.
4. All Dy.CEs/SEs/Distribution in PSPCL.
5. All Dy.CEs/SEs/P&M in PSPCL.
6. All Dy.CEs/SEs/Enforcement & EA&MMTS.
7. All Addl.SEs/Sr.XENs/Distribution
8. All Addl.SEs/Sr.XENs/P&M, Grid Mtc. & Distribution.
9. All Addl. SEs/Sr.XENs/Enforcement & EA&MMTS.
Memo No.9613/9753/SO/PRC/LD-38 Dated 28-12-10
Subject: Power Regulatory Measures on Industrial Consumers
Due to increase in demand, it was decided to impose power regulatory
measure on industrial consumers w.e.f. 4-12-2010 to 14-12-2010. These
regulatory measures were relaxed w.e.f. 15.12.2010 onwards.
1. Two weekly off days on Arc/induction and rolling mill consumers
feeding from category-II and III feeders. Timings of weekly off days
were from 0700 hrs to end of peak load restriction hours i.e. 2100 hrs.
These consumers were allowed to use load from end of peak load
restriction hours i.e. 2100 hours to 0700 hours of next day. If first
weekly off day of these consumers was falling on 3-12-2010, they
were to observe second weekly off day on 4.12.2010 and so on.
2. One weekly off day on general industrial consumers feeding from
category-II feeders. Timings of weekly off days were from 0800 hrs to
end of peak load restriction hours i.e. 2100 hrs. These consumers were
allowed to use load from end of peak load restriction hours i.e. 2100
hrs to 0800 hrs of next day.
Note:- Days of weekly off days remained unchanged as already
intimated.
Dy. Chief Engineer/PR
for Er-in-Chief/PP& R PSPCL
Patiala
CC:
1) Chairman, PSPCL & All Members/PSPCL.
2) Secretary/Punjab State Electricity Regulatory Commission,
220-21,
Sector-34 A, Chandigarh.
3) O.S.D. to Chairman, PSPCL, Patiala.
4) Er-in-Chief /Commercial, PSPCL, Patiala.
5) Chief Engineer/QI & TA, PSPCL, Patiala.
6) Director/I.R., PSPCL, Patiala.
7) SE/Technical, PSPCL Patiala. He is requested to endorse the same to
Dy.Secy./Services- III & Dy.Secy./Tech. I, II & III, PSPCL, Patiala.
8) SE/I.T., PSPCL, Patiala for putting the above Circular on PSPCL Web-
site.
9) Addl SE/Sr.Xen/CBC, PSPCL, Patiala, Ludhiana & Jalandhar.