  • 7/25/2019 Punch List 01

    1/1

    Observation Report i

    November 05, 2015

    GeriS. Main StreetTexas

    Re: Punch List

    The following is a punch list of outstanding work to be completed as observed on the renovation of Ms.Escobars residence on November 04, 2015:

    Exterior

    All of the exterior siding requires a close inspection to fully drive in all nail heads All of the exterior siding requires a close inspection to touch up with paint all areas

    that have been repaired. All of the exterior siding requires a close inspection to fully seal the siding to trimboards.

    All of the exterior siding requires a close inspection to seal around all penetrationswith backer rod and sealant.

    Trim boards and front and rear decks require repainting and to include the top andbottom edges.

    The posts on the front deck are to be sealed and the base and 4x4 wood anglebrackets added to the tops.

    Add cedar trim to the corner of the front deck near the entry stairs. Add wood colored sealant to all front and rear deck railing that does not meet flush. The roof flashing on the north side of the building requires a seam to be added and

    drip edge. The electric service head pipe is insufficiently anchored to the building, requires

    properly sized screws. The flashing around the roof penetration is incorrectly installed. All termite shields need to verified that the sheet metal is correctly placed and neatly

    folded downward to piers. Hose bib piping on the northwest corner of the building requires foam insulation. Verify that rigid insulation for underside of floor deck is in-place and firmly secured to

    framing.

    Interior

    All surfaces need to be wiped of construction dust. Pipe penetration in floor of mechanical closet requires backrod and sealant. Wall paint requires touch-up through out the building. All case work and millwork requires paint touch-up. Sealant at joint with wall. Two areas of the floor in the dining area require additional bracing to the structure.

    Regrout tile work in the master bathroom on the backside of the shower curb and theleft side of the shower wall. Add sealant to the head of the wall. Add exterior exhaust for range hood.

    .

    MG