public utility district no. 1 of chelan county …
TRANSCRIPT
Bid No. 20-SW05 Page 1 of 4 Addendum No. 2 May 20, 2021
PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY
ADDENDUM NO. 2 BID NO. 20-SW05
ROCKY REACH DAM CENTRAL MAINTENANCE SUPPORT FACILITIES -CM4 REMODEL
TO ALL BIDDERS: The following modifications to the proposal documents for the above named project as originally issued on May 3, 2021, are hereby incorporated into said documents and shall be fully considered in preparation of proposals.
SR-3 COMPLETION SCHEDULE/CONTRACT TIME Delete: The Contractor shall complete such Work in a diligent and workmanlike manner. Work is required to be completed by August 27th, 2021. Insert: The Contractor shall complete such Work in a diligent and workmanlike manner. Work is required to be completed by October 15th, 2021. EXHIBIT S - SPECIFICATIONS is modified as follows: Delete: Exhibit S – Specifications, Table of Contents Insert: Revised Exhibit S – Specifications, Table of Contents as attached to this Addendum. Delete:
Bid No. 20-SW05 Page 2 of 4 Addendum No. 2 May 20, 2021
SECTION 230900 INSTRUMENTATION AND CONTROL PERFORMANCE SPECIFICATION Add: SECTION 230933 ELECTRIC AND ELECTRONIC CONTROL SYSTEM FOR HVAC SECTION 262726 WIRING DEVICES SECTION 262800 OVERCURRENT PROTECTIVE DEVICES SECTION 262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS SECTION 264300 SURGE PROTECTIVE DEVICES SECTION 265100 LIGHTING EXHIBIT T – CONTRACT DRAWINGS is modified as follows: Delete: Exhibit T – Contract Drawings, Table of Contents Insert: Revised Exhibit T – Contract Drawings, Table of Contents as attached to this Addendum. Delete: Contract Drawings:
7 of 27 Acm4-5.01 EXTERIOR ELEVATIONS, BUILDING SECTION & RCP 22 of 27 Mcm4-2.01 FLOOR PLAN - MECHANICAL 26 of 27 Ecm4-3.01 FLOOR PLAN - POWER/SIGNAL 27 of 27 Ecm4-5.01 SINGLE LINE DIAGRAMS - ELECTRICAL
Insert: Revised Contract Drawings:
7 of 27 Acm4-5.01 Rev 1 EXTERIOR ELEVATIONS, BUILDING SECTION & RCP 22 of 27 Mcm4-2.01 Rev 1 FLOOR PLAN - MECHANICAL 26 of 27 Ecm4-3.01 Rev 1 FLOOR PLAN - POWER/SIGNAL 27 of 27 Ecm4-5.01 Rev 1 SINGLE LINE DIAGRAMS - ELECTRICAL
Bid No. 20-SW05 Page 3 of 4 Addendum No. 2 May 20, 2021
QUESTIONS & ANSWERS Q#1: Sheet Ecm4-3.01 has a note that reads “Extend Conduits to Existing Conduits see Ecm4-1.01” I do not see a sheet Ecm4-1.01. A#1: This Contract Drawing has been revised to remove reference to sheet Ecm4-1.01 (Addendum No. 2). Q#2: Sheet Ecm4-5.01 calls for a new Surge protective device to be installed for existing panel ‘A’. No spec information provided for SPD device. Please provide spec information on desired new Surge Protective Device. A#2: See new Section 264300, Surge Protective Devices (Addendum No. 2). Q#3: The published Substantial Completion date for the project is August 27th. After speaking to Subcontractors and Suppliers about material availability for the products specified, we don’t believe this date can be achieved. We formally request the Substantial Completion date be revised to October 15, 2021. It’s mostly overhead doors and metal wall panels where we are seeing potential procurement issues. But things are changing almost daily right now. A#3: See revised SR-3, Completion Schedule/Contract Time (Addendum No. 2). Q#4: We are hearing from a few of our subs that they cannot perform take-off on the current set of plans because the file is locked when they pull up the PDF. Do you have an unlocked version so they are able to complete their take-off? A#4: Only registered plan holders that have been approved by the District as Small Works Contractors with the appropriate codes (3, 11, 13) have access to Contract Document pdfs that are not locked. Planholders that have received printable pdfs may share the document with subcontractors. Q#5: Please confirm the DDC system is to tie into the existing DDC system that is currently being installed at the PUD Rocky Reach Facility. This tie-in will occur at the IT cabinet via a copper connection to a spare Ethernet port. This port will be provided by the Electrical Contractor. Please confirm graphics/trends/schedules/alarms will be added to the Automated Logic WebCTRL software. A#5: The DDC system has been removed and replaced by localized control without remote reporting capabilities. See new Section 230933, Electric and Electronic Control System for HVAC (Addendum No. 2).
Bid No. 20-SW05 Page 4 of 4 Addendum No. 2 May 20, 2021
Q#6: What elevations do the HVAC louvers get installed at? (Exhaust fan & Ducting)? A#6: See revised Contract Drawing Acm4-5.01 Exterior Elevations, Building Section & RCP (Addendum No. 2). Q#7: Our painting subs are having a hard time understanding what items are to be painted for the paint scope. Can your confirm if the following will require paint? Exposed duct, exposed existing steel joists, existing concrete walls, new plywood wainscot and overhead doors. The specs seem to mention everything and I am not seeing a finish schedule. A#7: See Contract Drawing Acm4-74.10 Signage, Color & Material Schedules.
END OF ADDENDUM NO. 2
Exhibit S - Specifications Bid 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel Table of Contents Page 1 of 3
EXHIBIT S – SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
011000 Summary of Work 012000 Measurement and Payment 013000 Administrative Requirements 013119 Coordination and Meetings 013524 Safety Requirements 014100 Air Barrier System 014516 Contractor Quality Control 014523 Testing and Inspection Services 014554 Air Barrier and Leak Mitigation 015000 Temporary Facilities and Controls 016000 Product Requirements 017700 Closeout Procedures
DIVISION 02 – EXISTING CONDITIONS 024119 Selective Site Demolition
DIVISION 3 - CONCRETE 032000 Concrete Reinforcing 033000 Cast-in-Place Concrete
DIVISION 5 – METALS 051200 Structural Steel Framing 054000 Cold Formed Metal Framing
DIVISION 6 – WOOD, PLASTICS AND COMPOSITES
061000 Rough Carpentry
061600 Sheathing 061800 Glued-Laminated Construction
DIVISION 7 – THERMAL AND MOISTURE PROTECTION 072100 Thermal Insulation 072119 Foamed-in-Place Insulation 072500 Weather Barriers 072600 Vapor Retarders 074213.13 Formed Metal Wall Panels 076200 Sheet Metal Flashing and Trim
Exhibit S - Specifications Bid 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel Table of Contents Page 2 of 3
079200 Joint Sealants
DIVISION 8 - OPENINGS
081113 Hollow Metal Doors and frames 083613 Sectional Doors 087100 Finish Hardware 088000 Glazing 089119 Fixed Louvers
DIVISION 9 - FINISHES 099000 Paint, Stain and Coatings
DIVISION 10 - SPECIALTIES 101419 Dimensional Letter Signage 104416 Fire Extinguishers 109900 Miscellaneous Specialties and Equipment
DIVISION 23 – HEATING, VENTILATING AND AIR CONDITIONING (HVAC)
230000 Heating, Ventilating and Air Conditioning (HVAC) Basic Requirements
230529 Hangers and Supports for HVAC Piping, Ductwork and Equipment 230548 Vibration and Seismic Controls for HVAC Equipment 230553 Identification for HVAC Piping, Ductwork and Equipment 230593 Testing, Adjusting and Balancing for HVAC 230900 Instrumentation and Control Performance Specification 230933 Electric and Electronic Control System for HVAC 233100 HVAC Ducts and Casing 233300 Air Duct Accessories 233400 HVAC Fans 233700 Air Outlets and Inlets 238200 Terminal Heat Transfer Equipment
DIVISION 26 - ELECTRICAL 260000 Electrical Basic Requirements 260509 Equipment Wiring 260519 Low-Voltage Electrical Power Conductors and Cables 260526 Grounding and Bonding for Electrical Systems 260529 Hangers and Supports for Electrical Systems and Equipment 260533 Raceways 260534 Boxes 260553 Identification for Electrical Systems
Exhibit S - Specifications Bid 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel Table of Contents Page 3 of 3
END OF TABLE OF CONTENTS
260810 Building Lighting Acceptance Testing and Documentation 260923 Occupancy and Vacancy Sensors 262726 Wiring Devices 262800 Overcurrent Protective Devices 262816 Enclosed Switches and Circuit Breakers 264300 Surge Protective Devices 265100 Lighting
DIVISION 31 - EARTHWORK 312300 Excavation and Fill
DIVISION 32 – EXTERIOR IMPROVEMENTS 321116.16 Gravel Base Course 321123.23 Gravel Top Course 321216 Asphalt Paving
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 230933 - Electric and Electronic Control System for HVAC
Page 1 of 4
SECTION 230933 - ELECTRIC AND ELECTRONIC CONTROL SYSTEM FOR HVAC
PART 1 - GENERAL
1.01 SUMMARY
A. Work Included:
1. Room Thermostats
2. Relays and Contactors
3. Transformers
4. Wiring
5. Damper Operators
1.02 RELATED SECTIONS
A. Contents of Division 23, HVAC and Division 01, General Requirements apply to this Section.
B. In addition, reference the following:
1. Power wiring per Division 26, Electrical.
1.03 REFERENCES AND STANDARDS
A. References and Standards as required by Section 23 00 00, HVAC Basic Requirements and Division 01, General Requirements.
1.04 SUBMITTALS
A. Submittals as required by Section 23 00 00, HVAC Basic Requirements and Division 01, General Requirements.
B. In addition, provide:
1. Drawings: complete control diagram, including written description of control sequences.
2. Operation and Maintenance Manual: Include record wiring drawings showing installed condition and operating changes made during start-up.
1.05 QUALITY ASSURANCE
A. Quality assurance as required by Section 23 00 00, HVAC Basic Requirements and Division 01, General Requirements.
1.06 WARRANTY
A. Warranty of materials and workmanship as outlined in Section 23 00 00, HVAC Basic Requirements and Division 01, General Requirements.
B. In addition, provide:
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 230933 - Electric and Electronic Control System for HVAC
Page 2 of 4
1. Within 30 days prior to warranty expiration date, control supplier to visit job site and check calibration, operation, and adjustment of temperature, pressure and humidity sensors, valves, dampers, thermostats and other devices installed by control supplier. Make repair or replacement of defective control equipment as required at no charge to Owner.
2. Submit letter to Owner certifying that this work has been completed.
3. Attach copy of service report signed by Owner's Authorized Representative.
PART 2 - PRODUCTS
2.01 MANUFACTURERS
A. Room Thermostats:
1. Honeywell
2. Siemens
3. Johnson Controls
4. Reliable Controls
5. Alerton
B. Damper Operators:
1. Belimo
2. Honeywell
3. Siemens
2.02 ROOM THERMOSTATS
A. Line Voltage, Electric Heater Thermostat: Wall mounted thermostat, non-programmable, dial adjustment between 50 degrees F and 80 degrees F, white color. Basis of Design: Honeywell CT62.
2.03 RELAYS AND CONTACTORS
A. Provide relays and contactors where required or as shown on Contract Drawings to meet operating sequence where not internal to manufacturer's equipment.
B. Furnish relays or contactors with required coil voltage and contact amperage rating for use specified on Contract Drawings and in manufacturer's equipment.
C. Mount relays in single control cabinet with hinge door and latch.
D. Control cabinet contains relays and numbered terminal strips for connection of relays and field wiring. Mount cabinet on painted plywood panel securely attached to wall framing. Mount time clock, transformer and motor contactors (if required) on plywood adjacent to control panel.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 230933 - Electric and Electronic Control System for HVAC
Page 3 of 4
2.04 TRANSFORMERS
A. Transformers selected and sized for appropriate VAC capacity and installed and fused according to applicable codes. Provide wiring to nearest suitable power source as required.
2.05 WIRING
A. In accordance with Division 26, Electrical and applicable codes.
B. Provide line and low voltage wiring relating to control system. Includes wiring of contactors, relays, circuits, and incidental power wiring: operation power for time clock, power when run through stat/timeclock/relay, transformers.
2.06 DAMPER OPERATORS
A. Size operators to operate dampers properly against system pressures, pressure differentials and velocities. Damper operators sized for 150 percent of damper forces normally encountered. Spring return closed for outside air applications.
PART 3 - EXECUTION
3.01 SEQUENCE OF OPERATION
A. Unit Heaters (UH-CM4-1 & UH-CM4-2): Provide thermostat for heating with setpoint at 60 degrees F.
B. Exhaust Fans:
1. EF-CM4-1: Controlled from wall switch. Provide delay-off relay and set to turn fan off 5-minutes after switch is turned off. Provide line voltage from fan circuit to exhaust and make-up air damper so that dampers open when fan is switched on. Dampers closed when fan is off.
3.02 INSTALLATION OF AUXILIARY CONTROL DEVICES
A. General:
1. Install thermostats in accordance with manufacturer's recommendations.
2. Room thermostats installed at 48-inches AFF to midline of sensor on concealed junction boxes properly supported by wall framing at the locations shown on the Drawings.
B. Actuators:
1. General:
a. Mount and link control damper actuators according to manufacturer's instructions.
b. Check operation of damper/actuator combination to confirm that actuator modulates damper smoothly throughout stroke to both open and closed positions.
2. Actuator Mounting for Damper arrangements to comply to the following:
a. Damper Actuators: Do not install in the air stream.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 230933 - Electric and Electronic Control System for HVAC
Page 4 of 4
b. Damper actuator ambient temperature not-to-exceed 122 degrees F through any combination of medium temperature or surrounding air. Provide appropriate air gaps, thermal isolation washers or spacers, standoff legs, or insulation as necessary. Mount per manufacturer's recommendations.
c. Actuator cords or conduit to incorporate a drip leg if condensation is possible. Do not allow water to contact actuator or internal parts. Location of conduits in temperatures dropping below dew point to be avoided to prevent water from condensing in conduit and running into actuator.
END OF SECTION
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities - CM4 Remodel
Section 262726 - Wiring Devices Page 1 of 5
SECTION 262726 - WIRING DEVICES
PART 1 - GENERAL
1.01 SUMMARY
A. Work Included: Provision of materials, installation and testing of:
1. Wall Switches
2. Receptacles
3. Finish Plates
4. Surface Covers
1.02 RELATED SECTIONS
A. Contents of Division 26, Electrical and Division 01, General Requirements apply to this Section.
1.03 REFERENCES AND STANDARDS
A. References and Standards as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
B. In addition, meet the following:
1. UL 498, Attachment Plugs and Receptacles.
2. UL 943, Ground Fault Circuit Interrupters (Class A GFCI).
3. UL 1472, Standard for Solid State Dimming Controls.
1.04 SUBMITTALS
A. Submittals as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
B. In addition, provide:
1. Wall switches and Dimmers
2. Receptacles
3. Wall Plates
4. In-Use Cover
1.05 QUALITY ASSURANCE
A. Quality assurance as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
1.06 WARRANTY
A. Warranty of materials and workmanship as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities - CM4 Remodel
Section 262726 - Wiring Devices Page 2 of 5
PART 2 - PRODUCTS
2.01 MANUFACTURERS
A. Wall Switches:
1. Toggle Type Characteristics:
a. Cooper AH1201
b. Hubbell HBL1221
c. Leviton 1221
d. Legrand P&S PS20AC1
2. Lighted Handle Switches:
a. Cooper
b. Hubbell
c. Leviton
d. Legrand P&S
B. Receptacles:
1. Industrial Grade:
a. Cooper 5362
b. Hubbell HBL5362
c. Bryant BRY5362
d. Leviton 5362
e. Legrand P&S 5362A
2. Ground Fault Circuit Interrupter (GFCI) Receptacle - 20 Amp:
a. Cooper WRSGF20W
b. Hubbell GFR5362SGW
c. Legrand P&S 2097TRWR
C. Finish Plates:
1. Bryant
2. Cooper
3. Hubbell
4. Leviton
5. Legrand P&S
D. Surface Covers:
1. Aluminum with Gasket, Blanks, Single Gang:
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities - CM4 Remodel
Section 262726 - Wiring Devices Page 3 of 5
a. Bell 240-ALF
b. Carlon
2. 2-Gang:
a. Bell 236-ALF
b. Carlon
3. While-in-Use Weatherproof Cover:
a. Die Cast Cover:
1) Intermatic
2) Hubbell
3) Cooper
E. Provide lighting switches and receptacles of common manufacturer and appearance.
2.02 WALL SWITCHES
A. Characteristics: Toggle type, quiet acting, 20 amp, 120/277 volt, UL listed for motor loads up to 80 percent of rated amperage, extra heavy duty.
B. Lighted Handle Switches: Lighted handle, quiet acting, 20 amp, 120/277 volt, toggle type, red unless noted otherwise neon lamp. Lamp energized when load is not energized.
C. Finish: Gray.
2.03 RECEPTACLES
A. Duplex Receptacles Characteristics: Straight parallel blade, 125 volt, 2 pole, 3 wire grounding.
1. Industrial Grade: Back and side wired. Single piece, rivetless. Brass grounding strap and back-wired ground screw. 20 amp.
B. Ground Fault Circuit Interrupter (GFCI) Receptacle: Feed through type, back-and-side wired, tamper-resistant, weather resistant self-testing, 20 amp, 125VAC.
C. Special Purpose Receptacles: Reference Drawings for NEMA Standard Specification.
D. Finish:
1. Same exposed finish as switches.
2.04 FINISH PLATES
A. Finish Plates: Type 302 stainless steel with smooth satin finish.
B. Provide telephone/signal device plates; activated outlets to have coverplates to match modular jack.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities - CM4 Remodel
Section 262726 - Wiring Devices Page 4 of 5
2.05 SURFACE COVERS
A. Material: Galvanized steel, 1/2-inch raised industrial type with openings appropriate for devices installed on surface receptacles.
B. Cast Box and Extension Adaptors: Aluminum with gasket, blanks single gang.
C. While-in-Use Weatherproof Cover: NEMA 3R when closed over energized plug. Vertical mount for duplex receptacle. Provide continuous use cover with cover capable of closing over energized cord cap with bottom aperture for cord exit.
1. Die cast cover with closed cell neoprene foam gasket: Capable of being locked closed to prevent tampering or unauthorized use.
PART 3 - EXECUTION
3.01 GENERAL INSTALLATION REQUIREMENTS
A. See Contract Drawings for location and mounting height of wiring devices. Review Contract Drawings prior to rough-in and contact Owner immediately if conflicts are found. Do not rough-in devices until conflicts are resolved.
B. Install wiring devices and finish plates plumb with building lines, equipment cabinets and adjacent devices. Devices not plumb will be fixed at no additional cost to Owner.
C. Orientation:
1. Install wiring devices with long dimension oriented vertically at centerline height shown on Contract Drawings or as specified.
2. Vertical Alignment: When more than one device is shown on drawings in close proximity to each other, but at different elevations, align devices on a common vertical center line for best appearance. Verify with Architect.
3. Horizontal Alignment: When more than one device is shown on drawings in close proximity to each other with same elevation, align devices on a common horizontal center line for best appearance. Verify with Architect.
D. Provide labeling per Section 26 05 53, Identification for Electrical Systems.
E. Test wiring devices to ensure electrical continuity of grounding connections, and after energizing circuitry, to demonstrate compliance with requirements. Test receptacles for line to neutral, line to ground and neutral to ground faults. Correct any defective wiring.
3.02 WALL SWITCHES INSTALLATION
A. At time of substantial completion, replace those items which have been damaged.
3.03 RECEPTACLES INSTALLATION
A. Upon installation, adhere to proper and cautious use of convenience receptacles. At time of substantial completion, replace those items which have been damaged, including those burned and scored by faulty receptacles or cord caps.
B. GFCI Receptacles: One GFCI receptacle may not be used to provide GFCI protection to downstream duplex receptacles on the same branch circuit.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities - CM4 Remodel
Section 262726 - Wiring Devices Page 5 of 5
3.04 FINISH PLATES INSTALLATION
A. Do not install items until finish painting is complete. Replace scratched and paint splattered finish plates and wiring devices.
3.05 SURFACE COVERS INSTALLATION
A. Do not install items until finish painting is complete. Replace scratched and paint splattered finish plates and wiring devices.
END OF SECTION
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 262800 - Overcurrent Protective Devices Page 1 of 3
SECTION 262800 - OVERCURRENT PROTECTIVE DEVICES
PART 1 - GENERAL
1.01 SUMMARY
A. Work Included:
1. Fuses
2. Molded Case Circuit Breakers
1.02 RELATED SECTIONS
A. Contents of Division 26, Electrical and Division 01, General Requirements apply to this Section.
1.03 REFERENCES AND STANDARDS
A. References and Standards as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
1.04 SUBMITTALS
A. Submittals as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
B. In addition, provide:
1. Product data and instantaneous let-through current curves and average melting time current curves for fuses supplied to project.
2. Product data and time/current trip curves for circuit breakers supplied to project.
1.05 QUALITY ASSURANCE
A. Quality assurance as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements apply to this Section.
1.06 WARRANTY
A. Warranty of materials and workmanship as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
PART 2 - PRODUCTS
2.01 MANUFACTURERS
A. Fuses:
1. Bussmann
2. Ferraz-Shawmut
3. Littelfuse
4. McGraw-Edison
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 262800 - Overcurrent Protective Devices Page 2 of 3
B. Molded Case Circuit Breakers:
1. Eaton Electrical
2. General Electric
3. Schneider Electric/Square D
2.02 FUSES
A. Characteristics:
1. Dual element, time delay, current limiting, nonrenewable type, rejection feature. Blown-fuse indicator window.
2. Combination Loads: UL Class RK1, 1/10 to 600 amp. UL Class L, above 600 amps.
3. Motor Loads: UL Class RK5, 1/10 to 600 amp.
4. Fuse pullers for complete range of fuses.
2.03 MOLDED CASE CIRCUIT BREAKERS
A. 1-, 2- or 3-pole bolt-on, single handle common trip, 600VAC or 250VAC as indicated on Drawings.
B. Overcenter toggle-type mechanism, quick-make, quick-break action. Trip indication is by handle position.
C. Calibrate for operation in 40 degrees C ambient temperature.
D. 15 to 150 Amp Breakers: Permanent trip unit containing individual thermal and magnetic trip elements in each pole.
PART 3 - EXECUTION
3.01 GENERAL INSTALLATION REQUIREMENTS
A. Coordination:
1. Obtain and review the submitted product data for equipment furnished by the Owner, and furnished under other Divisions of these Contract Documents, particularly under Division 23.
2. Confirm the equipment nameplate maximum overcurrent protection (MOCP) and make accommodations and adjustments to overcurrent protective devices as necessary to coordinate with the nameplate rating.
B. Install all items in accordance with manufacturers written instructions.
3.02 FUSES
A. Fuses: For each class and ampere rating of fuse installed, provide the following quantities of spares for quantity of fuses installed:
1. 0 to 24: Provide 6 spare.
2. 25 to 48: Provide 9 spare.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 262800 - Overcurrent Protective Devices Page 3 of 3
3. 49 and Above: Provide 12 spare.
3.03 MOLDED CASE CIRCUIT BREAKERS
A. Provide testing of ground fault interrupting breakers.
B. Provide circuit breakers, as specified and shown on Contract Drawings, for installation in panelboards, individual enclosures or combination motor starters.
C. Provide ground fault interrupter circuit breakers for equipment in damp or wet locations.
D. Provide device on handle to lock breaker in "ON" position for breakers feeding time switches, night lights and similar circuits required to be continuously energized.
E. Shunt Trip Circuit Breakers: Provide wiring to remote trip switch/contacts as indicated on Drawings.
F. Provide multi-pole branch circuit breakers for multiwire branch circuits for simultaneous disconnection of circuits.
END OF SECTION
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 262816 - Enclosed Switches and Circuit Breakers Page 1 of 5
SECTION 262816 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS
PART 1 - GENERAL
1.01 SUMMARY
A. Work Included:
1. Toggle Type Disconnect Switches
2. Manual Motor Starters
3. Safety Switches
4. Enclosed Circuit Breakers
5. Molded Case Switches
1.02 RELATED SECTIONS
A. Contents of Division 26, Electrical and Division 01, General Requirements apply to this Section.
B. In addition, reference the following:
1. Section 26 28 00, Overcurrent Protective Devices.
1.03 REFERENCES AND STANDARDS
A. References and Standards as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
1.04 SUBMITTALS
A. Submittals as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
1.05 QUALITY ASSURANCE
A. Quality assurance as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
1.06 WARRANTY
A. Warranty of materials and workmanship as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
PART 2 - PRODUCTS
2.01 MANUFACTURERS
A. Toggle Type Disconnect Switches:
1. Cooper
2. Hubbell
3. Leviton
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 262816 - Enclosed Switches and Circuit Breakers Page 2 of 5
4. Legrand (Pass & Seymour)
5. Slater
B. Manual Motor Starters:
1. Eaton Electrical
2. General Electric
3. Schneider Electric/Square D
C. Safety Switches:
1. Eaton Electrical
2. GE Industrial
3. Schneider Electric/Square D
D. Enclosed Circuit Breakers:
1. Eaton Electrical
2. GE Industrial
3. Schneider Electric/Square D
E. Molded Case Switches:
1. Eaton Electrical
2. General Electric
3. Schneider Electric/Square D
2.02 TOGGLE TYPE DISCONNECT SWITCHES
A. Rating: 120 or 277 volt, 1 or 2 pole, 20 amp, 1 hp maximum.
B. Enclosure:
1. NEMA 1: Dry locations/Indoors.
2. NEMA 3R: Damp or wet locations/Outdoors.
C. Handle lockable in 'off' position.
2.03 MANUAL MOTOR STARTERS
A. Quick-Make, Quick-Break. Thermal overload protection. Device labeled with maximum voltage, current, and horsepower.
B. Enclosure:
1. NEMA 1: Dry locations/Indoors.
2. NEMA 3R: Damp or wet locations/Outdoors.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 262816 - Enclosed Switches and Circuit Breakers Page 3 of 5
2.04 SAFETY SWITCHES
A. Heavy duty fusible type and non-fusible type (as indicated on drawings), dual rated, quick-make, quick-break with fuse rejection feature for use with Class R fuses only, unless other fuse type is specifically noted.
B. Clearly marked for maximum voltage, current, and horsepower.
C. Operable handle interlocked to prevent opening front cover with switch in 'on' position.
D. Switches rated for maximum available fault current.
E. Handle lockable in 'off' position.
F. Enclosure:
1. NEMA 1: Dry locations/Indoors.
2. NEMA 3R: Damp or wet locations/Outdoors.
2.05 ENCLOSED CIRCUIT BREAKERS
A. Molded case circuit breakers:
1. 1-, 2-, or 3-pole bolt on, single-handle common trip, 600VAC or 250VAC as indicated on Contract Drawings.
2. Overcenter toggle-type mechanism, quick-make, quick-break action. Trip indication is by handle position.
3. Calibrate for operation in 40C ambient temperature.
4. 15 to 150 Amp Breakers: Permanent trip unit containing individual thermal and magnetic trip elements in each pole.
5. Provide handle mechanisms that are lockable in the open (off) position.
6. Circuit breakers to have minimum symmetrical interrupting capacity as indicated on Contract Drawings.
B. Enclosure:
1. NEMA 1: Dry locations/Indoors.
2. NEMA 3R: Damp or wet locations/outdoors.
2.06 MOLDED CASE SWITCHES
A. Removable cover, galvanized steel enclosure, powder coat painted.
B. Provide cover padlock provision.
C. Provide trip unit with no overcurrent, overload, or low level fault protection. Trip unit to be high instantaneous magnetic fixed trip type with magnetic trip reset at factory to interrupt high fault currents at or above preset level.
D. Enclosure:
1. NEMA 1: Dry locations/Indoors.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 262816 - Enclosed Switches and Circuit Breakers Page 4 of 5
2. NEMA 3R: Damp or wet locations/Outdoors.
PART 3 - EXECUTION
3.01 GENERAL INSTALLATION REQUIREMENTS
A. Obtain and review the submitted product data for equipment furnished by the Owner, and furnished under other Divisions of these Contract Documents, particularly under Division 23.
B. Confirm the equipment nameplate maximum overcurrent protection (MOCP) and make accommodations and adjustments to switches, fuses and circuit breakers as necessary to coordinate with the nameplate rating
C. Install in accordance with manufacturer's instructions.
D. Provide engraved nameplates per Section 26 05 53, Identification for Electrical Systems.
E. Apply neatly typed adhesive tag on inside door of each fusible switch indicating NEMA fuse class and size installed.
3.02 TOGGLE TYPE DISCONNECT SWITCHES
A. Install fuses in fusible disconnect switches. Coordinate fuse ampere rating with installed equipment. Do not provide fuses of lower ampere rating than motor starter thermal units.
B. Install products, systems and equipment in accordance with manufacturers written instructions and requirements.
C. See General Installation Requirements above.
3.03 MANUAL MOTOR STARTERS
A. Provide disconnecting means within sight of each motor controller and of each motor. Motor controller disconnecting means equipped with lock-out/tag-out padlock provisions do not require a disconnect switch at the controlled motor location. Locate disconnect means in view of and not inside of equipment, such that tools are not needed to remove covers to access the disconnecting means.
B. Install products, systems and equipment in accordance with manufacturers written instructions and requirements.
C. See General Installation Requirements above.
3.04 SAFETY SWITCHES
A. Install products, systems and equipment in accordance with manufacturers written instructions and requirements.
B. See General Installation Requirements above.
3.05 ENCLOSED CIRCUIT BREAKERS
A. Install products, systems and equipment in accordance with manufacturers written instructions and requirements.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 262816 - Enclosed Switches and Circuit Breakers Page 5 of 5
B. See General Installation Requirements above.
3.06 MOLDED CASE SWITCHES
A. Install products, systems and equipment in accordance with manufacturers written instructions and requirements.
B. See General Installation Requirements above.
END OF SECTION
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 264300 - Surge Protective Devices Page 1 of 4
SECTION 264300 - SURGE PROTECTIVE DEVICES
PART 1 - GENERAL
1.01 SUMMARY
A. Work Included:
1. Surge Protective Devices (“SPD”) for Distribution Panels - Nonmodular Type
1.02 RELATED SECTIONS
A. Contents of Division 26, Electrical and Division 01, General Requirements apply to this Section.
1.03 REFERENCES AND STANDARDS
A. References and Standards as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
B. In addition, meet the following:
1. Listed per UL 1449, third edition, and complimentary listed per UL 1283 as FRI/EMI filter.
2. Comply with ANSI/IEEE C62.45 test procedures for Category-C3 established in C62.41.2 and CSA certified (C22.2).
1.04 SUBMITTALS
A. Submittals as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
B. In addition, provide:
1. Related SPD specifications, drawings, maintenance manuals, installation instructions, and UL 1449, third edition, listed surge suppression ratings of specified protection modes.
2. Project Record Documents: Record actual locations of SPDs.
3. Maintenance Data:
a. Include module replacement instructions.
b. Include maintenance and troubleshooting instructions for electronic components.
1.05 QUALITY ASSURANCE
A. Quality assurance as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
B. In addition, meet the following:
1. Manufacturer's Qualifications: ISO 9001 certification SPD manufacturer's complete quality control and documentation procedures of firms regularly engaged in manufacturers of SPD product for Category-C3
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 264300 - Surge Protective Devices Page 2 of 4
(ANSI/IEEEC62.41.2) and whose product has been of satisfactory service for not less than 5 years.
a. Provide local support for SPD.
b. Provide both service entrance and distribution panel SPD of same manufacturer.
2. Manufacturer Qualifications: Company specializing in manufacturing products specified in this Section with minimum three years documented experience.
1.06 WARRANTY
A. Warranty of materials and workmanship as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
PART 2 - PRODUCTS
2.01 MANUFACTURERS
A. Advanced Protection Technologies, Inc. (APT)
B. Current Technology
C. Eaton Electrical
D. Lea International
E. Liebert
F. Schneider Electric/Square D
G. Surge Suppression Inc. (SSI)
2.02 SPD FOR DISTRIBUTION PANELS - NONMODULAR TYPE
A. List SPD in accordance with UL 1449 (third edition), Standard for Safety, Surge Protective Devices, and UL 1283, Electromagnetic Interference Filters.
B. Independently test SPD with Category-C3 high exposure waveform (20KV - 1.2/50 µs, 10 kA - 8/20 µs) per ANSI/IEEE C62.41.2 (2002)
C. Provide SPD with copper bus bars for surge current path. Small gauge round wiring, plug-in type connections, or printed circuit boards not be used in path for surge current diversion. Equally distribute surge current to MOV components to ensure equal stressing and maximum performance. Surge suppression platform must provide equal impedance paths to each matched MOV.
D. Use no plug in component modules or printed circuit boards as surge current conductors. Hardwire internal components with connections utilizing low impedance conductors and compression fittings.
E. In order to isolate SPD under any fault condition, manufacturer to provide:
1. Individually fuse the MOV via copper fuse. Copper fuse provides protection during high (ka) surge events.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 264300 - Surge Protective Devices Page 3 of 4
2. Equip MOVs with thermal fuse which allows disconnection of suppression component at overheating stage common during TOV.
3. Test overcurrent protection components in compliance with UL 1449 (3rd Edition) Limited Current Test and AIC rating test.
F. Equip SPD with an audible alarm that activates when one of surge current modules have failed. Provide an alarm on/off switch to silence alarm. Provide an alarm push-to-test switch to test the alarm. Locate switches and alarm on the front cover of the SPD's enclosure.
G. Provide SPD that Meet or Exceed the Following Criteria:
1. Provide maximum single impulse current rating at no less than 100 kA per phase. Manufacturers must provide documented proof of independent third party verification of single impulse current withstand capabilities.
2. Pulse Life Test: Capable of protecting against and surviving 2000 ANSI/IEEE C62.41.2 Category-C3 transients without failure or degradation of UL 1449 (third edition) clamp voltage by more than 10 percent.
3. UL 1449 (third edition) clamping voltage not to exceed the following:
VOLTAGE L-G L-N N-G 208Y/120V 800V 800V 800V 480Y/277V 1200V 1200V 1200V
4. Nominal discharge current of 20KA I (n).
H. Make SPD of solid-state components which operate bidirectionally.
I. Provide SPD with response time no greater than five nanoseconds for individual protection modes.
1. SPD designed to withstand maximum continuous operating voltage (MCOV) of not less than 115 percent of nominal RMS voltage.
2. Provide visible indication of proper SPD connection and operation. Provide 10 year warranty, incorporating unlimited replacements of SPD if they are destroyed by transients within warranty period.
J. Provide SPD designed to withstand maximum continuous operating voltage (MCOV) of not less than 115 percent of nominal RMS voltage.
1. Provide terminals for necessary power and ground connections.
2. Provide SPD with minimum EFI/RFI filtering of 30dB at 100KHZ with an insertion loss ratio of 316:1 using Military Standard 220A methodology.
3. Provide SPD with 10 year warranty, incorporating unlimited replacement parts if they are destroyed by transients during warranty period.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 264300 - Surge Protective Devices Page 4 of 4
PART 3 - EXECUTION
3.01 SPD FOR DISTRIBUTION PANELS - NONMODULAR TYPE INSTALLATION
A. Install one secondary SPD at each distribution panel location as indicated on Contract Drawings. SPD unit to be integral to panelboard.
END OF SECTION
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 265100 - Lighting Page 1 of 10
SECTION 265100 - LIGHTING
PART 1 - GENERAL
1.01 SUMMARY
A. Work Included:
1. Luminaires
2. LED Drivers
3. Lamps
B. Provide wiring for complete and operating lighting system.
1.02 RELATED SECTIONS
A. Contents of Division 26, Electrical and Division 01, General Requirements apply to this Section.
1.03 REFERENCES AND STANDARDS
A. References and Standards as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
B. In addition, meet the following:
1. NECA 500 - Commercial Lighting.
2. UL 8750 – Light Emitting Diode (LED) equipment for use in lighting products.
1.04 SUBMITTALS
A. Submittals as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
B. In addition, provide:
1. Submit product data for:
a. LED Luminaires: Electrical ratings, dimensions, mounting, material, clearances, terminations, wiring, connection diagram, LM-79 photometric data, LM-80 lumen depreciation data.
b. LED Drivers
c. Lamps
2. Submittal Cutsheets: Highlight, circle or otherwise graphically indicate which option(s) are being selected for the products submitted. Cutsheets that are not edited to indicate which products and options are submitted for this project or that list only catalog numbers to identify submitted options are not acceptable.
3. Provide the following operating and maintenance instructions as required by Section 26 00 00, Electrical Basic Requirements:
a. Luminaires
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 265100 - Lighting Page 2 of 10
b. LED Drivers
c. Lamps
1.05 QUALITY ASSURANCE
A. Quality assurance as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
B. In addition, meet the following:
1. Provide luminaires acceptable to code authority for application and location installed.
2. Comply with applicable ANSI standards.
3. Comply with applicable NEMA standards.
4. Provide luminaires and lampholders that comply with UL standards and have been listed and labeled for location and use indicated by a testing agency acceptable by the AHJ (e.g., UL, ETL, and the like).
5. Comply with NEC as applicable to installation and construction of luminaires.
6. Comply with fallout and retention requirements of IBC for diffusers, baffles, and louvers.
7. Provide LED luminaires from the same manufacturer and manufacturing LED source batch for similar applications (e.g., all LED downlights from a single manufacturer and batch, all linear LED products from single manufacturer and batch).
1.06 WARRANTY
A. Warranty as required by Section 26 00 00, Electrical Basic Requirements and Division 01, General Requirements.
B. In addition, provide:
1. LED Luminaire Manufacturer's Warranty: Not less than 5 years for luminaire based on date of substantial completion. Includes normal cost of labor to replace luminaire. Replacement luminaire will match physical dimensions, physical appearance, chromaticity, lumen output and photometric characteristics of original installed equipment.
PART 2 - PRODUCTS
2.01 MANUFACTURERS
A. Luminaires:
1. Reference description and manufacturers in Luminaire Schedule on Contract Drawings.
B. LED Drivers:
1. Indoor Drivers:
a. eldoLED Series
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 265100 - Lighting Page 3 of 10
b. Advance/Philips
c. Osram Sylvania
2. Outdoor Drivers:
a. Advance/Philips
b. Osram Sylvania
c. LG
C. Lamps:
1. LED (Light Emitting Diode) Lamps:
a. Nichia
b. Cree
c. Osram Sylvania
d. GE Lumination
2. Unless specific manufacturer not shown on this list is indicated in the Luminaire Schedule.
3. Special types as indicated in Luminaire Schedule in Contract Drawings.
2.02 LUMINAIRES
A. Luminaires: Reference description and manufacturers in Luminaire Schedule on Contract Drawings.
B. Where recessed luminaires are installed in cavities intended to be insulated, provide IC rated luminaires or other code approved installation.
C. UL label luminaires installed under canopies, roof or open porches, and similar damp or wet locations, as suitable for damp or wet location.
D. Suspended luminaires: Provide minimum 24-inch adjustability in aircraft cable length where used.
E. Recessed Luminaires: Frame compatible with ceiling material installed at particular luminaire location. Provide proper factory trim and frame for luminaire to fit location and ceiling material. Verify with Architectural Reflected Ceiling Plan prior to submittals.
F. Finishes:
1. Manufacturer's standard finish (unless otherwise indicated) over corrosion resistant primer.
2. Interior Light Reflecting Finishes: White or specular finish with not less than 85 percent reflectance.
3. Exterior Finishes: As detailed in Luminaire Schedule or on Contract Drawings. Refer cases of uncertain applicability to Architect for resolution prior to release for fabrication.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 265100 - Lighting Page 4 of 10
G. Light Transmitting Components:
1. Plastic diffusers, molded or extruded of 100 percent virgin acrylic.
2. Prismatic acrylic, extruded, flat diffusers, 0.125-inch overall thickness, unless otherwise noted.
H. LED Luminaires:
1. UL listing of luminaire includes drivers, transformers, enclosures, rated wire, communications devices and accessories needed for a complete and functional system.
2. LM-79: Testing and measurement of absolute photometry, chromaticity (CCT) and luminaire power. Report provided by DOE certified independent testing laboratory. CCT as specified in Luminaire Schedule.
3. Standards: ANSI C78.377, LM-79 and LM-82 compliant for performance characteristics, photometry, colorimetry, efficacy and thermal characteristics.
4. LM-80 + TM-21: Testing and measurement, and statistical prediction of LED lamp life. Report provided by DOE certified independent testing laboratory.
5. LEDs in one module/luminaire: Supplied from same batch/bin and fall within 3-step MacAdam Ellipse, or as described in Luminaire Schedule, whichever is the more stringent requirement.
6. Provide luminaires with integral LED thermal management system (heat sinking).
7. Luminaires to be equipped with an LED driver that accepts 120V through 277V, 50Hz to 60Hz (universal). Component-to-component wiring within the luminaire will carry no more than 80 percent of rated current and be listed by UL for use at 600VAC at 302 degrees F/150 degrees C or higher. Plug disconnects to be listed by UL for use at 600VAC, 15A or higher.
8. Provide luminaires with individual LED arrays/modules and drivers that are accessible and replaceable from exposed side of the luminaire.
2.03 LED DRIVERS
A. General:
1. Performance: Meet dimming range called out in Luminaire Schedule, free from perceived flicker or visible stroboscopic flicker, smooth and continuous change in level (no visible steps in transitions), natural square law response to control input, and stable when input voltage conditions fluctuate over what is typically experienced in a commercial environment. Demonstration of this compliance to dimming performance will be necessary for substitutions or prior approval.
2. Ten-year expected life while operating at maximum case temperature and 90 percent non-condensing relative humidity.
3. Minimum efficiency of 85 percent, power factor greater than or equal to 0.90, compliance with reduction of hazardous substances (RoHS). Rated for operating temperature range of area in which driver is installed.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 265100 - Lighting Page 5 of 10
4. Limit inrush current to minimize breaker tripping.
a. Base specification: NEMA 410 standard for inrush current for electronic drivers.
b. Preferred Specification: Meet or exceed 30 milliamp-squared-seconds at 277VAC for up to 50 watts of load and 75 amps at 240 microseconds at 277VAC for 100 watts of load.
5. Withstand up to a 1,000 volt surge without impairment of performance as defined by ANSI C62.41 Category A.
6. No visible change in light output with a variation of plus/minus 10 percent line voltage input.
7. Total Harmonic Distortion less than 10 percent and meet ANSI C82.11 maximum allowable THD requirements at full output. THD at no point in the dimming curve allows imbalance current to exceed full output THD.
8. Support automatic adaptation, allowing for future luminaire upgrades and enhancements and deliver improved performance:
a. Adjustment of forward LED voltage, supporting 3V through 55V.
b. Adjustment of LED current from 150mA to 1.4A at the 100 percent control input point in increments of 1mA.
c. Adjustment for operating hours to maintain constant lumens (within 5 percent) over the 50,000 hour design life of the system, and deliver up to 20 percent energy savings early in the life cycle.
9. Operate for a (+/- 10 percent) supply voltage of 120V through 277VAC at 60Hz.
10. UL Recognized under the component program and modular for simple field replacement. Drivers that are not UL Recognized or not suited for field replacement will not be considered.
11. Ability to provide no light output when the analog control signal drops below 0.3 V, or the DALI/DMX digital signal calls for light to be extinguished and consume 0.5 watts or less in this standby. Control dead band between 0.3V and 0.65V included to allow for voltage variation of incoming signal without causing noticeable variation in luminaire to luminaire output.
B. Light Quality:
1. Over the entire range of available drive currents, driver to provide step-free, continuous dimming to black from 100 percent to 0.1 percent and 0 percent relative light output, or 100 percent to 1 percent light output and step to 0 percent where indicated. Driver to respond similarly when raising from 0 percent to 100 percent.
a. Driver must be capable of 20 bit dimming resolution for white light LED drivers or 15 bit resolution for RGBW LED drivers.
2. Driver must be capable of configuring a linear or logarithmic dimming curve, allowing fine grained resolution at low light levels.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 265100 - Lighting Page 6 of 10
3. Drivers to track evenly across multiple luminaires at all light levels, and must have an input signal to output light level that allows smooth adjustment over the entire dimming range.
4. Driver and luminaire electronics to deliver illumination that is free from objectionable flicker as measured by flicker index (ANSI/IES RP-16-10). At all points within the dimming range from 100 percent to 0.1 percent luminaire will have:
a. LED dimming driver to provide continuous step-free, flicker free dimming similar to incandescent source.
b. Base specification: Based on IEEE PAR1789, minimum output frequency should be greater than 1250 Hz.
c. Preferred specification: Flicker index to be equal to incandescent, less than 1 percent at all frequencies below 1000 Hz.
C. Control Input:
1. Provide control protocol to match lighting control system specified for use with luminaire.
2. 4-Wire (0-10V DC Voltage Controlled) Dimming Drivers:
a. Meet IEC 60929 Annex E for General White Lighting LED drivers.
b. Connect to devices compatible with 0 to 10V Analog Control Protocol, Class 2, capable of sinking 0.6 ma per driver at a low end of 0.3V. Limit the number of drivers on each 0-10V control output based on voltage drop and control capacity.
c. Meet ESTA E1.3 for RGBW LED drivers.
2.04 LAMPS
A. Provide lamps for luminaires.
B. Provide lamp catalogued for specified luminaire type.
C. Incandescent Lamps: Not allowed unless noted in Luminaire Schedule.
D. LED (Light Emitting Diode):
1. LED manufacturer will include, but not be limited to, light source, luminaire, power supply and control interface with added components as needed for complete and functioning system.
a. Comply with ANSI chromaticity standard for classifications of color temperature. See Luminaire Schedule for specified LED lamp color and color temperature. UL or ETL listed and labeled.
b. Luminaire testing per IESNA LM-79 and LM-80 procedures.
c. Lamp life for white LEDs: 50,000 plus hours with lamp failure occurring when LED produces 70 percent of initial rated lumens.
d. Lamp life for color LEDs: 30,000 plus hours with lamp failure occurring when LED produces 50 percent of its initial rated lumens.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 265100 - Lighting Page 7 of 10
e. LED Drivers: Reverse polarity protection, open circuit protection, require no minimum load. Minimum 80 percent efficiency. Class A noise rating.
f. Dimming: LED system capable of full and continuous dimming.
g. Correlated Color Temperature (CCT): See Luminaire Schedule for selection of color temperature for each luminaire. Ranges given below reflect maximum allowable tolerances for color temperature range for each nominal CCT.
1) Nominal CCT:
(a) 2700 K (2725 ± 145)
(b) 3000 K (3045 ± 175)
(c) 3500 K (3465 ± 245)
(d) 4000 K (3985 ± 275)
h. Color Rendering Index (CRI) to be greater than or equal to 80.
2. Special types as indicated in Luminaire Schedule.
PART 3 - EXECUTION
3.01 GENERAL INSTALLATION REQUIREMENTS
A. Install per manufacturer's written installation instructions and requirements.
B. Install luminaires securely, in neat and workmanlike manner.
C. Install luminaires of types indicated where shown and at indicated heights in accordance with manufacturer's written instructions and with recognized industry practices to ensure that luminaires comply with requirements and serve intended purposes.
D. Wiring:
1. Recessed luminaires to be installed using flexible metallic conduit with luminaire conductors spliced to branch circuit conductors in nearby accessible junction box over ceiling. Junction box fastened to building structural member within 6-feet of luminaire.
2. Luminaires for lift out and removal from ceiling pattern without disconnecting conductors or defacing ceiling materials.
3. Flexible connections where permitted to exposed luminaires; neat and straight, without excess slack, attached to support device.
4. Install junction box, flexible conduit and high temperature insulated conductors for through wiring of recessed luminaires.
E. Relamp luminaires which have failed lamps at substantial completion.
F. Replace LED drivers deemed as excessively noisy by Architect, Engineer, or Owner.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 265100 - Lighting Page 8 of 10
G. Install suspended luminaires and exit signs using pendants supported from swivel hangers. Provide pendant length required to suspend luminaire at indicated height.
H. Support luminaires larger than 2- by 4-foot size independent of ceiling framing.
I. Locate recessed ceiling luminaires as indicated on architectural reflected ceiling plan.
J. Install surface mounted luminaires and exit signs plumb and adjust to align with building lines and with each other. Secure to prevent movement.
K. Exposed Grid Ceilings:
1. Support surface mounted luminaires in grid ceiling directly from building structure.
2. Provide auxiliary members spanning ceiling grid members to support surface mounted luminaires.
3. Fasten surface mounted luminaires to ceiling grid members using bolts, screws, rivets, or suitable clips.
L. Install recessed luminaires to permit removal from below.
M. Install recessed luminaires using accessories and firestopping materials to meet regulatory requirements for fire rating.
N. Install clips to secure recessed grid-supported luminaires in place.
O. Install wall mounted luminaires, emergency lighting units, and exit signs at height as indicated on Contract Drawings.
P. Install accessories furnished with each luminaire.
Q. Make wiring connections to branch circuit using building wire with insulation suitable for temperature conditions within luminaire.
R. Bond products and metal accessories to branch circuit equipment grounding conductor.
S. Install specified lamps in each emergency lighting unit, exit sign, and luminaire.
T. Where manufactured wiring assemblies are used, ensure that wiring assembly manufacturer sends components to appropriate luminaire manufacturer for respective installation of proper components.
U. Coordination:
1. Coordination of Conditions: Coordinate ceiling construction, recessing depth and other construction details prior to ordering luminaires for shipment. Refer cases of uncertain applicability to Architect for resolution prior to release of luminaires for shipment. Where luminaires supplied do not match ceiling construction, replace luminaires at no cost to Owner.
2. Electrical drawings are schematic, identifying quantity and type of luminaires used and their approximate location, but are not to be used for dimensional purposes. Reference architectural drawings for exact locations, including mounting heights.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 265100 - Lighting Page 9 of 10
3. Provide lighting indicated on drawings with luminaire of the type designated and appropriate for location.
4. Provide LED luminaires with driver compatible to lighting control system as shown in Contract Drawings and as specified.
5. Where remote drivers are required, ensure adequate accessibility to driver. Upsize conductors between luminaire and driver to accommodate voltage drop.
V. Field Quality Control:
1. Perform field inspection in accordance with Division 01, General Requirements.
2. Operate each luminaire after installation and connection. Inspect for proper connection and operation.
W. Cleaning:
1. Clean electrical parts to remove conductive and deleterious materials.
2. Remove dirt and debris from enclosures.
3. Clean paint splatters, dirt, dust, fingerprints, and debris from luminaires.
4. Clean photometric control surfaces as recommended by manufacturer.
5. Clean finishes and touch up damaged finishes per by manufacturer's instructions.
X. Demonstrate luminaire operation for minimum of two hours.
3.02 LUMINAIRES
A. Install per manufacturer's written installation instructions and requirements.
B. Align, mount and level luminaires uniformly. Use ball hangers for suspended stem mounted luminaires.
C. Avoid interference with and provide clearance from equipment. Where indicated locations for luminaires conflict with locations for equipment, change locations for luminaire by minimum distance necessary as directed by Architect.
D. Suspended Luminaires: Mounting heights indicate clearances between bottom of luminaire and finished floors.
E. Emergency Egress Luminaires: Provide unswitched emergency circuit to exit signs and emergency luminaires. Where test switch cannot be integral to luminaire, mount remote test switch flush-to-ceiling and adjacent to egress luminaire.
F. Interior Luminaire Supports:
1. Support Luminaires: Anchor supports to structural slab or to structural members within a partition, or above a suspended ceiling.
2. Maintain luminaire positions after cleaning and relamping.
3. Support luminaires without causing ceiling or partition to deflect.
Exhibit S – Specifications BID 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel
Section 265100 - Lighting Page 10 of 10
4. Provide mounting supports for recessed and pendant mounted luminaires as required by IBC.
G. Adjusting:
1. Aim and adjust luminaires as indicated.
2. Focus and adjust floodlights, spotlights and other adjustable luminaires, with Architect, at such time of day or night as required.
3. Align luminaires that are not straight and parallel/perpendicular to structure.
4. Position exit sign directional arrows as indicated.
3.03 LED DRIVERS
A. Install lamps per manufacturer's installation instructions and requirements.
B. Where driver is remote mounted, size wiring based on type of driver, driver distance from luminaire, and voltage/power level, and manufacturer's installation instructions.
C. Protect 0-10V input from line voltage mis-connection, and so it will be immune and the output unresponsive to induced AC voltage on the control leads.
END OF SECTION
Exhibit T – Contract Drawings Bid 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel Table of Contents Page 1 of 2
EXHIBIT T – CONTRACT DRAWINGS
TABLE OF CONTENTS
GENERAL
1 of 27 G1.00 COVER SHEET & SHEET INDEX 2 of 27 G2.01 GENERAL ABBREVIATIONS & NOTES, SYMBOLS 3 of 27 G3.01c CODE REVIEW SUMMARY & TYP MOUNTING HEIGHTS 4 of 27 G3.02 CODE PLANS DEMOLITION 5 of 27 Acm4-2.01 DEMOLITION PLAN & ELEVATIONS, NOTES & LEGEND ARCHITECTURAL 6 of 27 Acm4-2.01 FLOOR & ROOF PLANS, SYMBOLS & NOTES 7 of 27 Acm4-5.01 REV 1 EXTERIOR ELEVATIONS, BUILDING SECTION & RCP 8 of 27 Acm4-6.01 WALL SECTION, WALL & ROOF DETAILS 9 of 27 Acm4-30.01 BUILDING & WALL TYPES/SECTIONS GENERAL NOTES 10 of 27 Acm4-30.10 EXTERIOR WALL TYPES & ASSEMBLY TYPES 11 of 27 Acm4-60.01 OPENING DIAGRAMS & INTERIOR ELEVATIONS 12 of 27 Acm4-61.01 LOUVER TYPE & SCHED., DETAILS, NOTES & ABBR 13 of 27 Acm4-62.01 DOOR TYPES & SCHEDULE, DETAILS, ABBREVIATIONS 14 of 27 Acm4-74.10 SIGNAGE, COLOR & MATERIAL SCHEDULES STRUCTURAL 15 of 27 S1.0 STRUCTURAL NOTES 16 of 27 S1.1 OVERALL PLANS & NOTES 17 of 27 S2.0 TYPICAL DETAILS 18 of 27 S3.0 PARTIAL FOUNDATION & ROOF FRAMING PLAN 19 of 27 S4.0 SECTIONS & ELEVATIONS 20 of 27 S5.0 DETAILS MECHANICAL
21 of 27 Mcm4-0.01 SYMBOLS LISTS & GEN. NOTES- MECHANICAL 22 of 27 Mcm4-2.01 REV 1 FLOOR PLAN - MECHANICAL
Exhibit T – Contract Drawings Bid 20-SW05
Rocky Reach Dam Central Maintenance Support Facilities – CM4 Remodel Table of Contents Page 2 of 2
ELECTRICAL 23 of 27 Ecm4-0.01 SYMBOLS LISTS & GEN. NOTES - ELECTRICAL 24 of 27 Ecm4-0.02 LUMINAIRE SCHEDULE 25 of 27 Ecm4-2.01 FLOOR PLAN - LIGHTING 26 of 27 Ecm4-3.01 REV 1 FLOOR PLAN - POWER/SIGNAL 27 of 27 Ecm4-5.01 REV 1 SINGLE LINE DIAGRAMS - ELECTRICAL
END OF TABLE OF CONTENTS
F
F
F
OS
OS
OS
OS
OS
OS
OS
OS
F F F F
0"
T.O. SLAB
2 41 3
7' - 3 3/4"
T.O. (E) CONCRETE WALL
A1
Acm4-6.01
2
Acm4-6.01
1
Acm4-6.01
6
0"
T.O. SLAB
A EAcm4-5.01
6B C D
0"
T.O. SLAB
24 13
KNOX BOX
A2
2' - 2"
Acm4-6.01
6
Acm4-6.01
1
Acm4-6.01
2
12' - 7
3/4"
ADD 2
0"
T.O. SLAB
AEAcm4-5.01
6 BCDSI2
ALIGN EDGE OF SIGN W/ FINISH OPENING
EQ
EQ
Acm4-74.10
2
Acm4-6.01
1
Acm4-6.01
6
Acm4-6.01
4
LEGEND
(E) EXPOSED CAST-IN-PLACE CONCRETE WALL
METAL WALL PANEL - COLOR BLACK
MS-1
(E) METAL WALL PANEL
0"
T.O. SLAB
24 1
7' - 3 3/4"
14' - 6" 16' - 0"
(E) PURLINS BTWN GRIDS A-B (E) B.O. FLANGE
(E) T.O. CONCRETE
ROOF OVERHANG(E) 4' - 0 3/4"
(E) SOG
CIPC SOG, SSD
ASPHALT PATCH W/ TOP & BASE COURSE ROCK, SEE SPECS
(E) ASPHALT
ROLLINGSTOCK
STORAGE100
19' - 4"
(E) T.O. STEELSTRUCTURE
CLR
REQ'D (GRIDS A
-D)
14' - 0
"
CLR
REQUIRED (GRIDS D
-E)
16' - 0
"
A
A
2 2
E
E
4 4
1 1
Acm4-5.016
Acm4-5.016
B
B
C
C
D
D
3 3
ROLLINGSTOCK
STORAGE100
TYPC6
TYPC5
TYPC5
C5
TYPC6
GENERAL NOTESA. SEE COLOR AND MATERIAL FINISH SCHEDULE ON SHEETS A74.10
FOR COLOR TREATMENT AND COLOR DEFINITIONSB. SEE GENERAL NOTES ON SHEET G2.01 FOR ADDITIONAL
INFORMATIONC. ARCHITECTURAL DRAWINGS DO NOT ILLUSTRATE ALL MECHANICAL
AND ELECTRICL ITEMS AND DEVICES, NEW OR EXISTING. ITEMS AND DEVICES WHICH ARE SHOWN ARE FOR COORDINATION AND LOCATING PURPOSES
A. CONTRACTOR SHALL COORDINATE THE WORK OF THE APPLICABLE TRADES TO PROVIDE PROPER LOCATIONS AND INSTALLATION OF CEILING ELEMENTS AND SYSTEMS.
B. MECHANICAL AND ELECTRICAL INFORMATION SHOWN ON ARCHITECTURAL REFLECTED CEILING PLANS IS FOR USE IN LOCATING CEILING MOUNTED FIXTURES, DIFFUSERS, GRILLES, ETC. REFER TO MECHANICAL AND ELECTRICAL DRAWINGS AND SPECIFICATIONS FOR QUANTITIES OF DEVICES AND ALL OTHER RELATED INFORMATION.
C. STRUCTURAL ELEMENTS ARE SHOWN FOR CONTRACTORS CONVENIENCE, SEE STRUCTURAL DRAWINGS FOR ACTUAL SIZES AND SPACING OF SUCH ELEMENTS.
D. IF LIGHT FIXTURE IS NOT DIMENSIONALLY LOCATED, CENTER IN ROOM. COORDINATE WITH ARCHITECT.
E. AIR BARRIER: THE FINISH CEILING ABOVE THE THIRD FLOOR IS CONSIDERED AN AIR BARRIER. ALL FIXTURES, EQUIPMENT, AND PENETRATIONS INSTALLED IN THE BUILDING'S THERMAL ENVELOPE SHALL BE AIR-TIGHT AND SEALED TO THE ADJACENT BUILDING MATERIALS. ALL LIGHTING FIXTURES SHALL BE IC RATED.
RCP GENERAL NOTES
May 19, 2021
BID NO. 20-SW05RC KE
.
www.tcfarchitecture.com
Tacoma, Washington 98403902 North SecondStreet
F.253.572.1445P.253.572.3993
TCF Architecture, PLLC
RANDY COOK
MARK WINSOR
PRIM. ENG.
2ND ENG.
DESIGNER
APPROVAL
PRIM. ENG.
2ND ENG.
PROJ. MGR. CASEY HALL
CO
NSU
LTA
NT
CHELAN PUD NO.1 SCALE
REV DATE
VERIFY SCALEBAR IS ONE INCH ON ORIGINAL DRAWING
IF NOT ONE INCH ON THIS SHEET, ADJUST
SCALES ACCORDINGLY.0 1"
REQ. BY
DRFT
DOCUMENT CLASS: ID:
ROCKY REACH, CHELAN COUNTY, WASHINGTON
ORIGINAL DWG. #:
DATE
DWG. ORIG. DATE
ORIG. DRAWN
PUBLIC UTILITY DISTRICT NO. 1
OF CHELAN COUNTYWENATCHEE, WASHINGTON
ADDENDUM NO.205/19/21
STORAGE BUILDINGCM-4
ORIG. DRAWN
1/11/2021
REVISION 1
1
REVISION 1As indicated
Acm4-5.01
EXTERIOR ELEVATIONS, BUILDING SECTION & RCPGO/KJ
RC
GO/KJ
SHEET 7 OF 26
1/8" = 1'-0"1NORTH ELEVATION
1/8" = 1'-0"4WEST ELEVATION
1/8" = 1'-0"3SOUTH ELEVATION
1/8" = 1'-0"2EAST ELEVATION
1/8" = 1'-0" 1 / Acm4-2.016BUILDING SECTION
1/8" = 1'-0"5REFLECTED CEILING PLAN
SI2 SIGN TYPE 'O', SEE SIGNAGE SCHEDULE
KEYNOTES
C5 LIGHT FIXTURE, SEE ELEC
C6 MECHANICAL EQUIPMENT, SEE MECH
PLANNORTH
ROLLING STOCKSTORAGE
100
UH-CM4-1 UH-CM4-2
32x32 LOUVER WITH MINIMUM 50% FREE AREA
A
2
E
4
1
B C D
3
EF-CM4-1
54018x10 EG-1
TYP. 5
32x12 20x10
2
McM2.01
3
McM2.01
3
McM2.01
1 1
LOCKOUT UNIT HEATER IF ANY ROLL UP DOOR IS OPEN. PROVIDE WIRING FROM EACH ROLL-UP DOOR CONTROLLER TO CONTROL SYSTEM
3'x2'-4" INTAKE LOUVER, MIN. 50 PCT. FREE AREA, WITH MOTORIZED DAMPER. COORDINATE LOCATION WITH ARCHITECTURAL ELEVATIONS AND STRUCTURE.
MDMD
Addendum2
T
Addendum2
T
CONNECT TO STRUCTURE.CABLES IN EACH OF 4 DIRECTIONS.PROVIDE SEISMIC RESTRAINT
45° MAX.
FAN.IN-LINE
3/8"Ø STEEL THREADED ROD.
ENTIRE CONTACT AREA (TYP.).NEOPRENE PAD OVER
SPRING VIBRATIONISOLATORS (4 REQ'D.).
HANGER ROD (4 REQ'D.)
DUCT TRANSITION ASREQUIRED.
SUPPORT FROMSTRUCTURE ASREQUIRED.
FLEXIBLE CONN.(TYP.).
MOUNTINGBRACKETS (TYP.).
.
UNIT HEATER INSTALLED AS HIGH AS POSSIBLE.
SEISMIC RESTRAINT: PROVIDE ANGLE IRON BRACING (SHEET METAL NOT ALLOWED) (TYP.).
DOWNWARD ANGLE.VANES AT 30°SET AIR DEFLECTION
ROOF TRUSS.
3" PIPE.
THREADEDROD. 45°MAX.
45°
MAX. WELD STEEL BAR TO
PIPE SUPPORT AT EACH END OF PIPE.
NOTE: UNIT HEATER MAY BE INSTALLED FROM WALL IF WALL IS PREPARED FOR INSTALLATION.
LN
SA
31,577
NSS IO
ORP
EF
RE
IG
GNLA E
IRTS E
DE
REE
N
W.
RDN
E F
TA
T
E
O
W
TG
ISAWI
HN
FR
CTH
O
05/19/2021
BID NO. 20-SW05JR
.
PRIM. ENG.
2ND ENG.
DESIGNER
APPROVAL
PRIM. ENG.
2ND ENG.
PROJ, MGR. CASEY HALL
CO
NSU
LTA
NT
CHELAN PUD NO.1 SCALE
REV DATE
VERIFY SCALEBAR IS ONE INCH ON ORIGINAL DRAWING
IF NOT ONE INCH ON THIS SHEET, ADJUST
SCALES ACCORDINGLY.0 1"
REQ. BY
DRFT
DOCUMENT CLASS: ID:
ROCKY REACH, CHELAN COUNTY, WASHINGTON
ORIGINAL DWG. #:
DATE
DWG. ORIG. DATE
ORIG. DRAWN
PUBLIC UTILITY DISTRICT NO. 1
OF CHELAN COUNTYWENATCHEE, WASHINGTON
5/19/21
STORAGE BUILDINGCM-4
SD ADDENDUM NO.2
5/19
/2021 8:46:39 AM
As indicated
Mcm4-2.01
FLOOR PLAN - MECHANICAL
SHEET 23 OF 27
1
REVISION 1
SD
ANDY FRICHTL
STEVE DACUS
ANDY FRICHTL REVISION 1
PLANNORTH
1/8" = 1'-0"1FLOOR PLAN - MECHANICAL
FAN SCHEDULE
SYMBOL LOCATION
BASIS OF DESIGN
TYPE DRIVEAIR FLOW(CFM)
ESP(IN H20)
FANRPM
MAXRPM
SOUNDS(SONES)
ELECTRICAL MAXWT
(LBS) COMMENTSMFR MODEL VOLTS PH BHP MHPEF-CM4-1 ROLLING STORAGE GREENHECK SQ-160-VG INLINE DIRECT 2700 0.5 1124 1140 11.5 208 1 0.52 0 140 1,2
COMMENTS:1 PROVIDE WITH ECM MOTOR.2 PROVIDE WITH VARIABLE SPEED CONTROLLER.
UNIT HEATER SCHEDULE
EQUIPMENTTAG LOCATION
BASIS OF DESIGN AIRFLOW(CFM)
HEAT(KW) STAGES
ELECTRICAL MAXWT
(LBS) COMMENTSMFR MODEL VOLTS PHUH-CM4-1 ROLLING STORAGE MARLEY IUH 270 7.5 2 208 3 55 1
UH-CM4-2 ROLLING STORAGE MARLEY IUH 270 7.5 2 208 3 55 1
COMMENTS:1 PROVIDE WITH MANUFACTURER'S WALL MOUNTING KIT.
DIFFUSER, REGISTER AND GRILLE SCHEDULE
SYMBOL TYPE FACE FRAME DAMPER FINISH
BASIS OF DESIGN
COMMENTSMFR. MODELEG-1 EXHAUST GRILLE FIXED BAR 1/4" BORDER NONE WHITE TITUS 350RL
NO SCALE2IN-LINE FAN
NO SCALE3UNIT HEATER INSTALLATION
SHEET KEYNOTES1 INSTALL THERMOSTAT ON WALL WITH INSULATED BACKPLATE.
PROJECT
CONTACT
www.interfaceengineering.com
Steve Dacus
2019-0147 100 SW Main Street, Suite 1600Portland, OR 97204
TEL 503.382.2266
Addendum2
FF
F
M
F F F F
ROLLING STOCKROLLING STOCKROLLING STOCKROLLING STOCKSTORAGESTORAGESTORAGESTORAGE
100100100100
A-1.
UHUHUHUH----CM4CM4CM4CM4----2222
EFEFEFEF----CM4CM4CM4CM4----1111
UHUHUHUH----CM4CM4CM4CM4----1111
AAAA
2222
EEEE
4444
1111
BBBB CCCC DDDD
3333(E) (E) (E) (E) PANEL 'A'PANEL 'A'PANEL 'A'PANEL 'A'
1111111111111111
A-5,7,9. A-5,7,9. A-11,13,15. A-11,13,15.
+24"+24"+24"+24"
+24"+24"+24"+24"
A-1.
AddendumAddendumAddendumAddendum2222
AddendumAddendumAddendumAddendum2222
AddendumAddendumAddendumAddendum2222
AddendumAddendumAddendumAddendum2222
AddendumAddendumAddendumAddendum2222
AddendumAddendumAddendumAddendum2222
EXHAUST FANEXHAUST FANEXHAUST FANEXHAUST FANWALL SWITCHWALL SWITCHWALL SWITCHWALL SWITCH
MDMDMDMD MDMDMDMD2222 2222
00005555////11119999////2222000022221111
BID NO. 20BID NO. 20BID NO. 20BID NO. 20----SW05SW05SW05SW05JR JR JR JR
....
PRIM. ENG.PRIM. ENG.PRIM. ENG.PRIM. ENG.
2ND ENG.2ND ENG.2ND ENG.2ND ENG.
DESIGNERDESIGNERDESIGNERDESIGNER
APPROVALAPPROVALAPPROVALAPPROVAL
PRIM. ENG.PRIM. ENG.PRIM. ENG.PRIM. ENG.
2ND ENG.2ND ENG.2ND ENG.2ND ENG.
PROJ, MGR.PROJ, MGR.PROJ, MGR.PROJ, MGR. CASEY HALL CASEY HALL CASEY HALL CASEY HALL
CONSULTANT
CHELAN PUD NO.1 SCALESCALESCALESCALE
REVREVREVREV DATEDATEDATEDATE
VERIFY SCALEVERIFY SCALEVERIFY SCALEVERIFY SCALEBAR IS ONE INCH ON BAR IS ONE INCH ON BAR IS ONE INCH ON BAR IS ONE INCH ON ORIGINAL DRAWINGORIGINAL DRAWINGORIGINAL DRAWINGORIGINAL DRAWING
IF NOT ONE INCH ON IF NOT ONE INCH ON IF NOT ONE INCH ON IF NOT ONE INCH ON THIS SHEET, ADJUST THIS SHEET, ADJUST THIS SHEET, ADJUST THIS SHEET, ADJUST
SCALES ACCORDINGLY.SCALES ACCORDINGLY.SCALES ACCORDINGLY.SCALES ACCORDINGLY.0000 1"1"1"1"
REQ. REQ. REQ. REQ. BYBYBYBY
DRFTDRFTDRFTDRFT
DOCUMENT CLASS:DOCUMENT CLASS:DOCUMENT CLASS:DOCUMENT CLASS: ID:ID:ID:ID:
ROCKY REACH, CHELAN COUNTY, WASHINGTONROCKY REACH, CHELAN COUNTY, WASHINGTONROCKY REACH, CHELAN COUNTY, WASHINGTONROCKY REACH, CHELAN COUNTY, WASHINGTON
ORIGINAL DWG. #:ORIGINAL DWG. #:ORIGINAL DWG. #:ORIGINAL DWG. #:
DATE DATE DATE DATE
DWG.DWG.DWG.DWG. OO OORR RRII II GG GG.. .. DD DDAA AATT TT EE EE
OO OORR RRII II GG GG.. .. DD DDRR RRAA AAWW WWNN NN
PUBLIC UTILITY DISTRICT NO. 1
OF CHELAN COUNTYWENATCHEE, WASHINGTON
5/19/215/19/215/19/215/19/21
SSSSTTTTOOOORRRRAAAAGGGGEEEE BBBBUUUUIIIILLLLDDDDIIIINNNNGGGGCCCCMMMM----4444
SD SD SD SD ADDENDUM NO.2ADDENDUM NO.2ADDENDUM NO.2ADDENDUM NO.2
55 55// //11 1199 99// //22 2200 0022 2211 11 99 99:: :: 11 1133 33:: :: 55 5522 22 AA AAMM MM
1/8" = 1'1/8" = 1'1/8" = 1'1/8" = 1'----0"0"0"0"
Ecm4Ecm4Ecm4Ecm4----3333....00001111
FLOOR PLAN FLOOR PLAN FLOOR PLAN FLOOR PLAN ---- POWER/SIGNALPOWER/SIGNALPOWER/SIGNALPOWER/SIGNAL
SHEET 26 OF 27SHEET 26 OF 27SHEET 26 OF 27SHEET 26 OF 27
1111
REVISION 1REVISION 1REVISION 1REVISION 1
JEMJEMJEMJEM
DAVID CHESLEYDAVID CHESLEYDAVID CHESLEYDAVID CHESLEY
JASON MATHEISJASON MATHEISJASON MATHEISJASON MATHEIS
DAVID CHESLEYDAVID CHESLEYDAVID CHESLEYDAVID CHESLEY REVISION 1REVISION 1REVISION 1REVISION 1
1/8" = 1'1/8" = 1'1/8" = 1'1/8" = 1'----0"0"0"0"1111FLOOR PLAN FLOOR PLAN FLOOR PLAN FLOOR PLAN ---- POWER/SIGNALPOWER/SIGNALPOWER/SIGNALPOWER/SIGNAL
PLANPLANPLANPLANNORTHNORTHNORTHNORTH
SHEET KEYNOTESSHEET KEYNOTESSHEET KEYNOTESSHEET KEYNOTES1. 1. 1. 1. ROLLROLLROLLROLL----UP DOOR: 208UP DOOR: 208UP DOOR: 208UP DOOR: 208----VOLT, 3VOLT, 3VOLT, 3VOLT, 3----PHASE, 3/4PHASE, 3/4PHASE, 3/4PHASE, 3/4----HORSE POWER.HORSE POWER.HORSE POWER.HORSE POWER.
2. 2. 2. 2. INTERLOCK MOTORIZED DAMPER WITH EFINTERLOCK MOTORIZED DAMPER WITH EFINTERLOCK MOTORIZED DAMPER WITH EFINTERLOCK MOTORIZED DAMPER WITH EF----CM4CM4CM4CM4----1 SO THAT 1 SO THAT 1 SO THAT 1 SO THAT DAMPER OPENS WITH FAN OPERATION.DAMPER OPENS WITH FAN OPERATION.DAMPER OPENS WITH FAN OPERATION.DAMPER OPENS WITH FAN OPERATION.
GENERAL NOTES
A. A. A. A. DEVICES THIS SHEET CIRCUITED TO PANEL DEVICES THIS SHEET CIRCUITED TO PANEL DEVICES THIS SHEET CIRCUITED TO PANEL DEVICES THIS SHEET CIRCUITED TO PANEL ‘‘‘‘AAAA’’’’UNLESS OTHERWISE NOTED ON SHEET. NUMBER UNLESS OTHERWISE NOTED ON SHEET. NUMBER UNLESS OTHERWISE NOTED ON SHEET. NUMBER UNLESS OTHERWISE NOTED ON SHEET. NUMBER ADJACENT TO DEVICE INDICATES CIRCUIT NUMBER.ADJACENT TO DEVICE INDICATES CIRCUIT NUMBER.ADJACENT TO DEVICE INDICATES CIRCUIT NUMBER.ADJACENT TO DEVICE INDICATES CIRCUIT NUMBER.
PROJECTPROJECTPROJECTPROJECT
CONTACTCONTACTCONTACTCONTACT
www.interfaceengineering.comwww.interfaceengineering.comwww.interfaceengineering.comwww.interfaceengineering.com
Jason Matheis
2019-0147 100 SW Main Street, Suite 1600Portland, OR 97204
TEL 503.382.2266
AddendumAddendumAddendumAddendum2222
SEE SITESEE SITESEE SITESEE SITEPLANPLANPLANPLAN
(E) METER BASE(E) METER BASE(E) METER BASE(E) METER BASE
M
UTILITY TRANSFORMER
T
(E)
(E)PANEL'A'
(E) 4 #3/0 CU IN 2"C.(E) 4 #3/0 CU IN 2"C.(E) 4 #3/0 CU IN 2"C.(E) 4 #3/0 CU IN 2"C.
(E) 4 #3/0 CU IN 2"C.(E) 4 #3/0 CU IN 2"C.(E) 4 #3/0 CU IN 2"C.(E) 4 #3/0 CU IN 2"C.
POINT OF SERVICEPOINT OF SERVICEPOINT OF SERVICEPOINT OF SERVICE
SPD
NEW SURGE PROTECTIVE DEVICENEW SURGE PROTECTIVE DEVICENEW SURGE PROTECTIVE DEVICENEW SURGE PROTECTIVE DEVICE
00005555////11119999////2222000022221111
BID NO. 20BID NO. 20BID NO. 20BID NO. 20----SW05SW05SW05SW05JR JR JR JR
....
PRIM. ENG.PRIM. ENG.PRIM. ENG.PRIM. ENG.
2ND ENG.2ND ENG.2ND ENG.2ND ENG.
DESIGNERDESIGNERDESIGNERDESIGNER
APPROVALAPPROVALAPPROVALAPPROVAL
PRIM. ENG.PRIM. ENG.PRIM. ENG.PRIM. ENG.
2ND ENG.2ND ENG.2ND ENG.2ND ENG.
PROJ, MGR.PROJ, MGR.PROJ, MGR.PROJ, MGR. CASEY HALL CASEY HALL CASEY HALL CASEY HALL
CONSULTANT
CHELAN PUD NO.1 SCALESCALESCALESCALE
REVREVREVREV DATEDATEDATEDATE
VERIFY SCALEVERIFY SCALEVERIFY SCALEVERIFY SCALEBAR IS ONE INCH ON BAR IS ONE INCH ON BAR IS ONE INCH ON BAR IS ONE INCH ON ORIGINAL DRAWINGORIGINAL DRAWINGORIGINAL DRAWINGORIGINAL DRAWING
IF NOT ONE INCH ON IF NOT ONE INCH ON IF NOT ONE INCH ON IF NOT ONE INCH ON THIS SHEET, ADJUST THIS SHEET, ADJUST THIS SHEET, ADJUST THIS SHEET, ADJUST
SCALES ACCORDINGLY.SCALES ACCORDINGLY.SCALES ACCORDINGLY.SCALES ACCORDINGLY.0000 1"1"1"1"
REQ. REQ. REQ. REQ. BYBYBYBY
DRFTDRFTDRFTDRFT
DOCUMENT CLASS:DOCUMENT CLASS:DOCUMENT CLASS:DOCUMENT CLASS: ID:ID:ID:ID:
ROCKY REACH, CHELAN COUNTY, WASHINGTONROCKY REACH, CHELAN COUNTY, WASHINGTONROCKY REACH, CHELAN COUNTY, WASHINGTONROCKY REACH, CHELAN COUNTY, WASHINGTON
ORIGINAL DWG. #:ORIGINAL DWG. #:ORIGINAL DWG. #:ORIGINAL DWG. #:
DATE DATE DATE DATE
DWG.DWG.DWG.DWG. OO OORR RRII II GG GG.. .. DD DDAA AATT TT EE EE
OO OORR RRII II GG GG.. .. DD DDRR RRAA AAWW WWNN NN
PUBLIC UTILITY DISTRICT NO. 1
OF CHELAN COUNTYWENATCHEE, WASHINGTON
5/19/215/19/215/19/215/19/21
SSSSTTTTOOOORRRRAAAAGGGGEEEE BBBBUUUUIIIILLLLDDDDIIIINNNNGGGGCCCCMMMM----4444
SD SD SD SD ADDENDUM NO.2ADDENDUM NO.2ADDENDUM NO.2ADDENDUM NO.2
55 55// //11 1199 99// //22 2200 0022 2211 11 99 99:: :: 11 1133 33:: :: 55 5533 33 AA AAMM MM
NO SCALENO SCALENO SCALENO SCALE
Ecm4Ecm4Ecm4Ecm4----5555....00001111
SINGLE LINE DIAGRAMS SINGLE LINE DIAGRAMS SINGLE LINE DIAGRAMS SINGLE LINE DIAGRAMS ---- ELECTRICALELECTRICALELECTRICALELECTRICAL
SHEET 27 OF 27SHEET 27 OF 27SHEET 27 OF 27SHEET 27 OF 27
1111
REVISION 1REVISION 1REVISION 1REVISION 1
JEMJEMJEMJEM
DAVID CHESLEYDAVID CHESLEYDAVID CHESLEYDAVID CHESLEY
JASON MATHEISJASON MATHEISJASON MATHEISJASON MATHEIS
DAVID CHESLEYDAVID CHESLEYDAVID CHESLEYDAVID CHESLEY REVISION 1REVISION 1REVISION 1REVISION 1
NO SCALENO SCALENO SCALENO SCALE1111ONEONEONEONE----LINE POWER DISTRIBUTION DIAGRAMLINE POWER DISTRIBUTION DIAGRAMLINE POWER DISTRIBUTION DIAGRAMLINE POWER DISTRIBUTION DIAGRAM
WH = Water Heater
factor=100%. If 6 or more units to a panel Demand...
K=Kitchen Equipment. If <6 units to a panel, then demand
H = Heating 7500.0 100.00% 7500.0
L = Lighting 276.0 125.00% 345.0 Total Est. Demand Current: 67.6 A
C = Continuous General Load Total Conn. Current: 62.2 A
G = General (Non-Continuous) 1000.0 100.00% 1000.0 Total Est. Demand: 24364.0 VA
Motor = Largest Motor at 125%, all others at 100% 13284.0 114.11% 15159.0 Total Conn. Load: 22420.0 VA
R = Receptacles - to 10 kVA 100%, over 10 kVA 50% 360.0 100.00% 360.0
Load Classification Connected Load Demand Factor Estimated Demand Panel Totals
Notes:
Total Connected load Ph. C 7036 VA 59 A
Total Connected load Ph. B 7400 VA 62 A Total Demand Load: 24.4 kVA 67.6 A
Total Connected load Ph. A 7984 VA 67 A Panel Connected Load: 22.4 kVA 62.2 A
41 -- -- -- -- -- 0 0 -- -- -- -- -- 42
39 -- -- -- -- -- 0 0 -- -- -- -- -- 40
37 SPARE BREAKER -- 100 3 0 0 3 100 -- SPARE BREAKER 38
35 -- -- -- -- -- 0 0 -- -- -- -- -- 36
33 -- -- -- -- -- 0 0 -- -- -- -- -- 34
31 SPARE BREAKER -- 60 3 0 0 3 60 -- SPARE BREAKER 32
29 -- -- -- -- -- 0 0 -- -- -- -- -- 30
27 -- -- -- -- -- 0 0 -- -- -- -- -- 28
25 SPARE BREAKER -- 30 3 0 0 3 30 -- SPARE BREAKER 26
23 SPARE BREAKER -- 20 1 0 0 1 20 -- SPARE BREAKER 24
21 SPARE BREAKER -- 20 1 0 0 1 20 -- SPARE BREAKER 22
19 SPARE BREAKER -- 20 1 0 500 1 20 G MOTORIZED DAMPER 20
17 SPARE BREAKER -- 20 1 0 500 1 20 G MOTORIZED DAMPER 18
15 -- -- -- -- -- 768 2,500 -- -- -- -- -- 16
13 -- -- -- -- -- 768 2,500 -- -- -- -- -- 14
11 MOTORIZED SHOP DOORS Motor 20 3 1 768 2,500 1 3 30 H UH-CM4-2 12
9 -- -- -- -- -- 768 2,500 -- -- -- -- -- 10
7 -- -- -- -- -- 768 2,500 -- -- -- -- -- 8
5 MOTORIZED SHOP DOORS Motor 20 3 768 2,500 1 3 30 H UH-CM4-1 6
3 SHOP LIGHTS L 20 1 276 588 -- -- -- -- -- 4
1 R - BELOW PANEL R 20 1 360 588 1 2 20 Motor EF-CM4-1 2
CKT Description/Location Type C.B. Poles Note
A B C A B C
Note Poles C.B. Type Description/Location CKT
Load (VA)
AIC RATING: 10,000 A SUPPLIED FROM:
EQUIPMENT RATING: 3 PHASE, 4 WIRE LOCATION: ROLLING STOCK...
BUS AMPACITY: 225 ENCLOSURE: Type 1
MAIN CIRCUIT BREAKER: 200 MOUNTING: Surface Access.:
PANELBOARD: A
MECHANICAL EQUIPMENT CONNECTION SCHEDULEMECHANICAL EQUIPMENT CONNECTION SCHEDULEMECHANICAL EQUIPMENT CONNECTION SCHEDULEMECHANICAL EQUIPMENT CONNECTION SCHEDULE
WTWTWTWT DESCRIPTIONDESCRIPTIONDESCRIPTIONDESCRIPTION LOCATIONLOCATIONLOCATIONLOCATION VOLTSVOLTSVOLTSVOLTS PHPHPHPHLOAD(VLOAD(VLOAD(VLOAD(V
A)A)A)A) HPHPHPHP MCAMCAMCAMCA MOCPMOCPMOCPMOCPCIRCUITCIRCUITCIRCUITCIRCUITNUMBERNUMBERNUMBERNUMBER
WIRE /WIRE /WIRE /WIRE /CONDUITCONDUITCONDUITCONDUIT NOTESNOTESNOTESNOTES
120120120120 1111 0.00.00.00.0 0000 (none)(none)(none)(none)
EF-CM4-1EF-CM4-1EF-CM4-1EF-CM4-1 EXHAUST FANEXHAUST FANEXHAUST FANEXHAUST FAN ROLLING STORAGE 100ROLLING STORAGE 100ROLLING STORAGE 100ROLLING STORAGE 100 208208208208 1111 1176.01176.01176.01176.0 1/21/21/21/2 20202020 A-2,4A-2,4A-2,4A-2,4 202202202202
UH-CM4-1UH-CM4-1UH-CM4-1UH-CM4-1 UNIT HEATERUNIT HEATERUNIT HEATERUNIT HEATER ROLLING STORAGE 100ROLLING STORAGE 100ROLLING STORAGE 100ROLLING STORAGE 100 208208208208 3333 7500.07500.07500.07500.0 30303030 A-6,8,10A-6,8,10A-6,8,10A-6,8,10 303303303303
UH-CM4-2UH-CM4-2UH-CM4-2UH-CM4-2 UNIT HEATERUNIT HEATERUNIT HEATERUNIT HEATER ROLLING STORAGE 100ROLLING STORAGE 100ROLLING STORAGE 100ROLLING STORAGE 100 208208208208 3333 7500.07500.07500.07500.0 30303030 A-12,14,16A-12,14,16A-12,14,16A-12,14,16 303303303303
WIRE/CONDUIT SCHEDULEWIRE/CONDUIT SCHEDULEWIRE/CONDUIT SCHEDULEWIRE/CONDUIT SCHEDULE
202202202202 2 #12 CU, 1 #12 CU GND., IN 3/4" C.2 #12 CU, 1 #12 CU GND., IN 3/4" C.2 #12 CU, 1 #12 CU GND., IN 3/4" C.2 #12 CU, 1 #12 CU GND., IN 3/4" C.
303303303303 3 #10 CU, 1 #10 CU GND., IN 3/4" C.3 #10 CU, 1 #10 CU GND., IN 3/4" C.3 #10 CU, 1 #10 CU GND., IN 3/4" C.3 #10 CU, 1 #10 CU GND., IN 3/4" C.
C.C.C.C. PROVIDE DISCONNECTING MEANS FOR EACH ITEM OF EQUIPMENT LISTED IN THE SCHEDULE ABOVE, EXCEPT AS SPECIFICALLY NOTED OTHERWISE IN SCHEDULE NOTES, BELOW.PROVIDE DISCONNECTING MEANS FOR EACH ITEM OF EQUIPMENT LISTED IN THE SCHEDULE ABOVE, EXCEPT AS SPECIFICALLY NOTED OTHERWISE IN SCHEDULE NOTES, BELOW.PROVIDE DISCONNECTING MEANS FOR EACH ITEM OF EQUIPMENT LISTED IN THE SCHEDULE ABOVE, EXCEPT AS SPECIFICALLY NOTED OTHERWISE IN SCHEDULE NOTES, BELOW.PROVIDE DISCONNECTING MEANS FOR EACH ITEM OF EQUIPMENT LISTED IN THE SCHEDULE ABOVE, EXCEPT AS SPECIFICALLY NOTED OTHERWISE IN SCHEDULE NOTES, BELOW.
B.B.B.B.MOCP = MAXIMUM OVER CURRENT PROTECTION.MOCP = MAXIMUM OVER CURRENT PROTECTION.MOCP = MAXIMUM OVER CURRENT PROTECTION.MOCP = MAXIMUM OVER CURRENT PROTECTION.MCA = MINIMUM CIRCUIT AMPACITYMCA = MINIMUM CIRCUIT AMPACITYMCA = MINIMUM CIRCUIT AMPACITYMCA = MINIMUM CIRCUIT AMPACITY
A.A.A.A.THE ABOVE INFORMATION IS FOR A SPECIFIC MANUFACTURER. ACTUAL MANUFACTURER FOR EQUIPMENT MAY BE DIFFERENT. COORDINATE WITH MECHANICAL EQUIPMENT SUBMITTALS FORTHE ABOVE INFORMATION IS FOR A SPECIFIC MANUFACTURER. ACTUAL MANUFACTURER FOR EQUIPMENT MAY BE DIFFERENT. COORDINATE WITH MECHANICAL EQUIPMENT SUBMITTALS FORTHE ABOVE INFORMATION IS FOR A SPECIFIC MANUFACTURER. ACTUAL MANUFACTURER FOR EQUIPMENT MAY BE DIFFERENT. COORDINATE WITH MECHANICAL EQUIPMENT SUBMITTALS FORTHE ABOVE INFORMATION IS FOR A SPECIFIC MANUFACTURER. ACTUAL MANUFACTURER FOR EQUIPMENT MAY BE DIFFERENT. COORDINATE WITH MECHANICAL EQUIPMENT SUBMITTALS FORLOADS AND OVER CURRENT PROTECTION REQUIREMENTS PRIOR TO INSTALLATION OF WIRING.LOADS AND OVER CURRENT PROTECTION REQUIREMENTS PRIOR TO INSTALLATION OF WIRING.LOADS AND OVER CURRENT PROTECTION REQUIREMENTS PRIOR TO INSTALLATION OF WIRING.LOADS AND OVER CURRENT PROTECTION REQUIREMENTS PRIOR TO INSTALLATION OF WIRING.
GENERAL MECHANICAL EQUIPMENT CONNECTION NOTE:GENERAL MECHANICAL EQUIPMENT CONNECTION NOTE:GENERAL MECHANICAL EQUIPMENT CONNECTION NOTE:GENERAL MECHANICAL EQUIPMENT CONNECTION NOTE:
PROJECTPROJECTPROJECTPROJECT
CONTACTCONTACTCONTACTCONTACT
www.interfaceengineering.comwww.interfaceengineering.comwww.interfaceengineering.comwww.interfaceengineering.com
Jason Matheis
2019-0147 100 SW Main Street, Suite 1600Portland, OR 97204
TEL 503.382.2266
AddendumAddendumAddendumAddendum2222