Public Private Partnerships in India

March 11, 2013

Page 2: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

India front-runner in PPP RACE

World Bank

• 1st semester of 2011, PPP activity was concentrated in

one country: India

• Since 2006, India top recipient of PPP activity

• In 2011, implemented 43 new projects of USD 20.7

billion

• ADB

• 2nd in Asia only behind Korea; China & Japan follow; 4th

in Asia- Pacific; UK & Australia ahead

• PPP development in India has been driven by strong

political will & advances in public capacity & processes 2

Page 3: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

BACKGROUND

3

Page 4: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

BACKGROUND Spending on infrastructure about 5% of GDP as compared to 10-12% of East Asian countries, now increased to about 8%

Infrastructure constraint; investment envisaged – Rs. 20 lakh crore during 2007-2012; private sector contributed 38%

Limited budgetary resources

4

Page 5: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Infrastructure Deficit Power 11.1% peaking deficit and 8.5% energy shortage; 27% T&D losses;

absence of competition; and inadequate private investment

Highways 71,772 Km of NH (2% of network, 40% of traffic): only 25% Four-

lane; 54% Two-lane; and 21% Single-lane; State highways also suffer from prolonged neglect

Ports Inadequate berths, rail / road connectivity and draft are

constraints

Airports Inadequate capacity: Runways, aircraft handling capacity, parking

space & terminal buildings

Railways Old technology; saturated routes: slow average speeds (freight:

22 kmph; passengers: 50 kmph); low payload to Tare ratio (2.5) 5

Page 6: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

-

200,000

400,000

600,000

800,000

1,000,000

1,200,000

1,400,000

1,600,000

1,800,000

XI Plan Anticipated

XII Plan Projected

XII Plan: Projected: (Rs. 55,76,822 cr.)

XI Plan:

Anticipated : (Rs. 24,24,277 cr.)

Projected Investment in Infrastructure (12th Five Year Plan)

6

Rs.

cro

re

(Rs. crore at nominal prices)

Page 7: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Financing Infrastructure: the challenge

• Investment in infrastructure is lumpy

• Projects have a long gestation period, i.e. the returns come in many

years so the private sector is not willing to invest

• Traditionally, all over the world, infrastructure investment has

been through the budget

• Generates externalities, i.e. even those who do not use the service

benefit, e.g. with the advent of metro, there is less congestion on

roads, less accidents, saving in time, less pollution, etc. therefore,

those who do not use but benefit should also pay some charge

7

Page 8: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Policy Challenges

Challenges for large capacity addition

Time-bound delivery under budgetary constraints

World class yet cost effective

Commercially sustainable yet affordable

Policy responses for attracting private investment

Policy and regulatory framework for PPPs is in place

Institutional restructuring and reorientation underway

Financial support to bridge viability gap of PPP projects

IIFCL, Infrastructure Debt Funds etc. for long term debt 8

Page 9: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Share of Private Investment in different Sectors

(11th Five Year Plan)

9

Per

cen

t Sh

are

82 78

64

43

20

5

-

10.00

20.00

30.00

40.00

50.00

60.00

70.00

80.00

90.00

Ports Telecom Airports Electricity Roads & Bridges Railways

Page 10: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Relative Share of Private Investment (12th Five Year Plan)

10

Per

cen

t Sh

are

0.00

10.00

20.00

30.00

40.00

50.00

60.00

70.00

2012-13 2013-14 2014-15 2015-16 2016-17

Public Private

Page 11: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Some illustrative PPP projects

Delhi, Mumbai, Hyderabad & Bangalore Airports

Two metro-rail projects in Mumbai and one in Hyderabad

Four Ultra mega Power Projects: Sasan(MP), Mundra

(Gujarat), Krishnapatnam (AP) and Tilaiya (Jharkhand)

Container terminals at JNPT, Chennai & Tuticorin

Operation of container trains

Jhajjar Power Transmission Project, Haryana

161 National Highway projects (12,005 km) for Rs.1,07,596

cr

137 State Highway projects (8,862 km) for Rs. 64,787 cr

22 central sector port terminals for Rs. 18,489 cr and 57 state

sector port terminals for Rs. 71,253 cr

11

Page 12: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

The Transactions

Page 13: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Options for the Government

• Implement the project

•Through conventional procurement

•Funded through the budget, or

•Loans against government guarantees

•As a Public Private Partnership (PPP)

Page 14: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

What is a PPP?

• Contract by Public Authority for provision of asset and/or

services

• With private entity

• Private finance used to fund asset/service

• Long-term in nature

• Allocates risk between the Authority and the private sector

• Annuity or User Charge based

• Performance-linked payments

• Output based 14

Page 15: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Standard Modes of Private Sector

Participation

DBFOT Design Build Finance Operate Transfer

BOT Build Operate Transfer

BOLT Build Own Lease Transfer

OMT Operate Manage Transfer

BOO Build Own Operate

Page 16: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

When to use PPPs

• User Charge Based

• Project is revenue bearing

• Annuity Based

• Shortage of funds

• No sustainable revenue

• Other factors

• Possibility for long-term contracts involving asset-based procurement

• Opportunity to design & implement a performance-based contract

• Possibility of utilising additional capacity of the assets through generation of third party revenues

16

Page 17: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

When to use PPPs (contd.)

• Transport

• Metros, roads, ports, railways, airports

• Social sector services – education, health, etc

• Water supply and solid waste management

• Power sector – generation, transmission, distribution

• Irrigation projects

• Modern storage/warehousing

17

Page 18: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Features of PPP Projects

• PPP infrastructure projects involve

• Transfer of public assets

• Delegation of Governmental authority for recovery of user

charges,

• Private control of monopolistic services

• Sharing of risks and contingent liabilities by the Government

• Protection of user interests and securing value for public

money over lifecycle of the project

• Complex deals with high transaction costs

18

Page 19: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

PPP Transaction

• Preparation of concept paper

• Feasibility study

• Preparation of documents

• In-Principle approval by Public Private Partnership Appraisal

Committee (PPPAC) /Empowered Institution (EI)

• Request For Qualification

• Final Approval by PPPAC/EI

• Request For Proposal

• Award

19

Page 20: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Typical documents for PPP projects

Substantive Documents

- Concession Agreements

- Manual of Specifications & Standards

- Rules for user charges

Process Documents

- RFP for selection of consultants

- RFQ for pre-qualification of bidders

- RFP for financial bids 20

Page 21: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Request for Qualification (RFQ)

• Following ‘in-principle’ clearance expressions of interest

to be invited in the form of RFQ

• Objective to identify credible bidders possessing requisite

technical and financial capacity to undertake the project

• Prepare a short list for stage two of the bidding process

referred to as the Request for Proposal (RFP) or invitation

of financial bids

• Balanced & transparent evaluation criteria

• Approved model document at www.infrastructure.gov.in

21

Page 22: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

22

Request for Qualification (RFQ)

Number of bidders to be pre-qualified and short-listed

Adequate to ensure competition but not large enough to

dampen competition

Evaluation criteria

Technical capacity

Project/construction experience

O&M experience

Financial capacity

Net worth

No technical proposals except where in case of

exceptionally complex projects the project authority so

determines

Page 23: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Request for Proposal (RFP)

• Invitation to submit financial bids

• Includes a copy of all agreements proposed to be

entered into with successful bidder

• Administrative Ministry to seek clearance of PPPAC

after formulating the draft RFP along with copies of the

draft concession agreements

Page 24: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Concession Agreements

Sectors National Highways

State Highways

Ports

Operation & Maintenance of Highways

Urban Rail Systems (Metro rail)

Container Train Operation

Redevelopment of Railway Stations

Non-metro Airports

Greenfield Airports

Procurement-cum-Maintenance of Locomotives

Transmission of electricity

24

Page 25: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Financial Support: Viability Gap Funding

• Upto 20% of total project cost

• Process of selection should be open competitive bidding;

bidding parameter

• Private company should be responsible for financing,

construction, maintenance and operation of the project

during the concession period

• Project should provide a service against payment of a pre-

determined tariff or user-charge

• Project should be from infrastructure sectors included in the

guidelines of the scheme

Page 26: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Stages of PPPs

I. Public sector provision of Infrastructure: Command & Control

- PPP by exception

II. Introduction of PPPs: The Transition - still on in some sectors/states

- Largely negotiated, often opaque

- Often driven by private beneficiaries

III. PPPs gain acceptability: Enhancing welfare & efficiency

- Transparent, competitive and fair

- Driven by the government; good governance becomes the key

- Objective is to attract private capital in public projects

Indian PPP projects are mostly in Stage III 26

Page 27: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Governance Structure for PPPs

Constitution of a Cabinet Committee on Investment (CCI)

• Prime Minister is the Chairperson

• Ministers of Infrastructure Ministries, Finance Minister and Deputy Chairman, Planning Commission are members

• Fast track approvals & monitor progress

PPP Appraisal Committee

• Appraises & recommends all PPP projects of the Central Government

• Chaired by Finance; appraisal by Planning Commission

Empowered Committee

• Approves proposals for Viability Gap Funding (upto 20% of capital costs)

• Chaired by Finance; appraisal by Planning Commission

Pla

nnin

g C

om

mis

sion/I

SB

/120711

27

Page 28: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Management & Monitoring

Management by contract

Guidelines for monitoring of PPP projects

28

Page 29: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Model Concession Agreements

29

Page 30: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Concession Agreement

• Enable the private sector to secure a reasonable return at manageable levels of risk

• Assure user of adequate service quality at affordable cost

• Facilitate the government in procuring value for public money

• Risk mitigation arrangements require detailed legal and contractual arrangements which specify: o Obligations of different participants

o Clear penalties for non-performance

o Protection to investors for events beyond their control

o Risk allocation

Page 31: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Grant of Concession

• Scope of Project

• Construction, Operation & Maintenance

• Site; License

• Term of Concession

• Right to collect and appropriate User Fee

• Financing

• Charge over assets, land

31

Page 32: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Grant of Concession

• Concessionaire’s Obligation

• Finance, design, engineer, construct, operate and

maintain Project

• Sub Contracts should be consistent with Concession

Agreement

• Change in Ownership - restricted

32

Page 33: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Grant of Concession

• Conditions Precedent (CP)

• Authority’s CP

• Land , Applicable Permits

• Damages for Delay

• Concessionaire’ s CPs

• Financial Closure

• Failure to fulfill CPs

• Waiver

• Appointed Date – Financial Close

33

Page 34: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Independent Engineer

• IE’s Role

• Appointed in a transparent manner through open

competitive bidding

• Government’s Representative

• No approvals – review and comments

34

Page 35: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Grant of Concession

• Government’s Obligations

• Support and Assistance in procuring permits

• Maintenance prior to Appointed Date

• Competing Projects

35

Page 36: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Bidding Parameter - Grant

• Grant or Negative Grant (Premium)

• Grant to be disbursed as follows:

• Equity Support

• O & M Support

• Negative Grant to be paid in addition to Concession

fee

36

Page 37: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Financial Convenants

• Financial Close

• Concessionaire to secure Financial Close within pre-

determined time frame

• Termination in event of failure to achieve Financial

Close

• Encashment of Bid Security in case of such termination

37

Page 38: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

User Fee

• Fee Notification

• Principles for revision of Fee

38

Page 39: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Concession Fee

• Typically nominal fee

• Revenue sharing may start10th year onwards

• Link Concession Fee to Concessionaire’s Realisable

Fee

• Monitoring of User Fee

39

Page 40: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Force Majeure and Termination

• Force Majeure

• Non-political Event – Act of God, etc.

• Indirect Political Event – War, Civil Commotion, etc.

• Political Event – Change in law, etc.

• Consequences - extension of Concession Period or

termination

• Termination Payment

• Non-political Event – 90% of Debt Due less Insurance

• Indirect Political Event – Debt Due less insurance, plus

110% of Adjusted Equity

• Political Event – Equivalent to Government default

40

Page 41: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Termination for Breach

• Termination Payment

• Construction Period

• Operations Period

• Concessionaire Default – 90% of Debt Due less Insurance

• Government Default – Debt Due less insurance, Plus

150% of Adjusted Equity

41

Page 42: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Residual Clauses

• Financing – Substitution Agreement

• Change in Law – Increase in Costs

• Dispute Resolution

42

Page 43: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Conflict of Interest

• ‘Conflict of Interest’ related problems are not fully

appreciated

• Private investment in infrastructure projects requires

level playing field

• Government cannot act as both regulator and

implementer

• Badly structured PPP project can cause more potential

harm than normal projects

Page 44: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Consultant Conflict of Interest

• Conflict between consulting activities and procurement

of goods, work or services

• Consulting firm should not be involved in

investing/development activity

44

Page 45: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Conflict Amongst Bidders

• Applicant/Associate have common shareholding

• Constituent of one applicant, also constituent of

another

• Applicant receives subsidy from another applicant

• Same legal representative

• Applicant has relationship with other applicant

through third party

• Applicant participated as Consultant for the project

45

Page 46: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Delhi Noida Toll Bridge

• Concession agreement provides guaranteed return of 20%

on total project cost; no commercial risk on concessionaire

• Project cost specified ex-post; no cap on project cost;

authority unaware of financial commitment when signing

Concession Agreement

• Shortfalls in returns of previous years to be added to

project cost in following year

• Provides for extension of concession period until

concessionaire recovers 20% + TPC

• Development rights may be granted in lieu of extension of

concession period

Page 47: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Solid Waste Management

• Concession awarded by a society which does not

own underlying assets

• In case of termination, for authority default,

concessionaire entitled to receive all revenues that

would have accrued over the concession period.

• In case of termination on concessionaire default,

authority to be paid 80% of debt due; debt due not

defined, hence, open ended liability

Page 48: Public Private Partnerships in Indiaaitd.net.in/pdf/14/1. Public Private Partnerships in... · 2019-11-30 · Delhi Noida Toll Bridge •Concession agreement provides guaranteed return

Common Problems

• Open ended costs

• Output parameters not defined

• Performance standards no specified

• Tariffs not in user interests