Public Involvement Meeting March 3, 2004 Former Raytheon Facility Wayland, Massachusetts Presented by: Edwin P. Madera

Upload: others

Post on 09-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Public Involvement Meeting

March 3, 2004

Former Raytheon FacilityWayland, Massachusetts

Presented by:Edwin P. Madera

Page 2: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Purpose of Meeting•Groundwater

• Phase IV Addendum - Southern Area

• Update on Northern Area Groundwater Investigations

•Wetland Excavation and Remediation Status

•Public Involvement Plan Revision

•Upcoming Reports

•Question and Answer Period

Page 3: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Locus Map

Site

Page 4: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

CVOCsPCBsPAHsMetals

CVOCs

Page 5: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

GroundwaterPhase IV Addendum

Page 6: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Groundwater Phase IV Addenduml Pilot studies completed as part of Release Abatement Measure

Plan (RAM) activities

l Pilot demonstrated permanganate is effective at destroying chlorinated volatile organic compounds (VOCs) in groundwater

l Sodium permanganate as preferred oxidant

l Pressure injection techniques provide increased radius of influence

l Groundwater Monitoring Program

– Baseline

– Post-injection– Quarterly – Field Parameters– Semi-Annual Monitoring

Page 7: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Groundwater Phase IV Addenduml ISCO Injections Planned for four areas at Site:

– MW-102 Area– Low and high pressure injections– Multiple injection points

– MW-40 Area– Low Pressure Injection– One injection point

– MW-43 Area– Low pressure injection– One injection point

– MW-33 Area– Low and high pressure injection– Multiple injection points

– Building Area– Being Evaluated

Page 8: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Proposed Oxidant Injection Locations

Page 9: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

GroundwaterNorthern Area Investigation

Page 10: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Groundwater – Northern Area l Northern Area (RTN 3-22408)

– Tier IB Permit Presumptively approved

l Vertical Profiling– Currently conducting vertical

profiling in accordance with Scope of Work

– Ten locations initiated

– Approximately 50 groundwater samples collected for analysis of volatile organic compounds

– Approximately 900 feet advanced

l Wetlands Well Installation– Will commence either Spring or

Fall pending Natural Heritage & Endangered Species Program approval

Vertical profiling not initiated at location

Vertical profiling initiated at location

Proposed well location

Page 11: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Wetland Remediation and Restoration

Page 12: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Construction Layout

Page 13: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Aerial Photo - October 2003

Outfall OF-1Outfall OF-1

Page 14: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Aerial Photo - November 2003

Outfall OF-1Outfall OF-1

Page 15: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Verification Sampling

Page 16: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Verification Samplingl 20’ x 20’ grid across

excavation areas

l Over 225 composite samples (proposed 200 composite samples)

l Over 55 perimeter locations (proposed 47 perimeter samples)

l Target analytes

– PCBs

– PAHs

– Metals

Page 17: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Verification Sampling

57.5372Copper

14.7210Lead

1.613Silver

55.7332Chromium

8.111Arsenic

1.69.0PAHs

0.312.0PCBs

Average Residual Concentration

Remedial Goal(mg/kg)

Compounds of Concern

Page 18: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Removal Actions To Date

l Excavation of 2.0 acres of wetland soil/sediment

l Treated approximately 7,335,000 gallons of water as part of de-watering activities

l Stabilized and transported off-site approximately 5,000 cubic yards of impacted soil

l Achieved remedial goals

l Re-soiled excavation area and planted approximately 71,000 wetland species plants

l Transitioning into wetland monitoring phase

Page 19: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Wetland Restoration Project

Adding New Soil

Spreading of New Soil

Page 20: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Wetland Restoration Project

Wetland Bulb

Wetland Plants in Trays

Page 21: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Wetland Restoration Project

Wetland Species Seeds

Planting

Page 22: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Wetland Restoration Project

Redesigned Outfall

Meandering Channel

Page 23: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Public Involvement Plan Revision

Page 24: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Revision to PIP

l Public Involvement Plan (PIP) updated due to the addition of Northern Area RTN 3-22408

l Primary Changes to PIP:

– Update to Site history

– Summary of past PIP activities

– Extend public comment period from 21 days to 30 days

l One Public Involvement Plan for entire Site

Page 25: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Upcoming Reports

Page 26: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Upcoming Reports/Documents

• Northern Area Investigation (RTN#3-22408)

– Phase II Scope of Work, Summer/Fall 2004

l Wetlands Remedial Action Closure Reports

– Spring/Summer 2004

l Public comments

– Phase IV Addendum due April 5, 2004

– PIP Revisions due (TBD)

– Comments addressed to:

Edwin P. MaderaRaytheon CompanyMail Stop 1880528 Boston Post RoadSudbury, MA 01776

Page 27: Public Involvement Meeting - Raytheon Involvement... · 2004-03-04 · lExcavation of 2.0 acres of wetland soil/sediment lTreated approximately 7,335,000 gallons of water as part

Q & A