public information meeting rehabilitation of bridge no. 00245 flat rock hill road over i-95 old...
TRANSCRIPT
Public Information MeetingPublic Information Meeting
Rehabilitation of
Bridge No. 00245
Flat Rock Hill Road over I-95
Old Lyme, Connecticut
Rehabilitation of
Bridge No. 00245
Flat Rock Hill Road over I-95
Old Lyme, Connecticut
CTDOT Role and MissionCTDOT Role and Mission
Bureau of Engineering and Construction
• Responsible for engineering design, construction, and inspection of transportation projects
Project Manager: Mr. Louis D. Bacho
Contact: Ms. Mary E. Baker
Bureau of Engineering and Construction
• Responsible for engineering design, construction, and inspection of transportation projects
Project Manager: Mr. Louis D. Bacho
Contact: Ms. Mary E. Baker
Close, Jensen and Miller, P.C.Consultant Liaison EngineersClose, Jensen and Miller, P.C.Consultant Liaison Engineers
CTDOT has retained the firm of Close, Jensen and Miller to supervise the activities relative to the design of this bridge project.
Contact: Mr. Jeffrey J. Fontaine
CTDOT has retained the firm of Close, Jensen and Miller to supervise the activities relative to the design of this bridge project.
Contact: Mr. Jeffrey J. Fontaine
Project GoalsProject Goals
• Rehabilitate Bridge No. 00245
• Minimize disturbance to traveling public
• Complete construction in a timely manner
• Effectively use funds
Address above with consideration for context sensitive design
• Rehabilitate Bridge No. 00245
• Minimize disturbance to traveling public
• Complete construction in a timely manner
• Effectively use funds
Address above with consideration for context sensitive design
Bridge No. 00245 Elevation looking East
on Interstate 95
Bridge No. 00245 Elevation looking East
on Interstate 95
Bridge No. 00245 Elevation looking West
on Interstate 95
Bridge No. 00245 Elevation looking West
on Interstate 95
Existing Bridge Description Bridge No. 00245
Existing Bridge Description Bridge No. 00245
• Four-Span, Continuous Steel Multi-Girder Structure built in 1958
• Carries one lane of traffic in each direction– Estimated Average Daily Traffic (ADT) on Flat Rock Hill Road ~116 vehicles (2007)
– ADT on Interstate 95 under Bridge No. 00245 ~67,900 (2009)
• Structure Dimensions– Total Length = 173’
– Overall Width = 45’ 7”
– Roadway Width = Originally 40’ 0”
Reduced to 26’ 5” due to concrete
barrier curb along Eastern side for
girder protection
• Four-Span, Continuous Steel Multi-Girder Structure built in 1958
• Carries one lane of traffic in each direction– Estimated Average Daily Traffic (ADT) on Flat Rock Hill Road ~116 vehicles (2007)
– ADT on Interstate 95 under Bridge No. 00245 ~67,900 (2009)
• Structure Dimensions– Total Length = 173’
– Overall Width = 45’ 7”
– Roadway Width = Originally 40’ 0”
Reduced to 26’ 5” due to concrete
barrier curb along Eastern side for
girder protection
Existing Bridge Description (cont’d) Bridge No. 00245
Existing Bridge Description (cont’d) Bridge No. 00245
• Minimum Vertical Clearance over I-95 = 14’-2”
• Reinforced concrete deck with concrete wearing surface
• Substructure (Foundation)– Concrete abutments on steel piles
– Two intermediate concrete piers and one center concrete pier on spread footings founded on bedrock
• Minimum Vertical Clearance over I-95 = 14’-2”
• Reinforced concrete deck with concrete wearing surface
• Substructure (Foundation)– Concrete abutments on steel piles
– Two intermediate concrete piers and one center concrete pier on spread footings founded on bedrock
Reasons for Project Reasons for Project
Structure recommended for rehabilitation under the State Bridge Program.
• Structurally Deficient:– Overall Superstructure Condition Rating “4”
– Jersey Barriers used to keep live loads off fascia girders
– Fascia girders exhibit extensive vehicular impact damage
– Girders exhibit moderate to heavy rust
• Functionally Obsolete:– Minimum Vertical Clearance is Substandard
Structure recommended for rehabilitation under the State Bridge Program.
• Structurally Deficient:– Overall Superstructure Condition Rating “4”
– Jersey Barriers used to keep live loads off fascia girders
– Fascia girders exhibit extensive vehicular impact damage
– Girders exhibit moderate to heavy rust
• Functionally Obsolete:– Minimum Vertical Clearance is Substandard
Reasons for ProjectReasons for Project
Fascia Girder over SB Traffic Impact damage
Fascia Girder over SB Traffic Impact damage
Bearing PadsSheared bolt due to impact damage
Bearing PadsSheared bolt due to impact damage
Reasons for ProjectReasons for Project
Steel GirdersRust along underside of structure
Steel GirdersRust along underside of structure
PiersLight to moderate scaling, rust along underside of structure
PiersLight to moderate scaling, rust along underside of structure
Proposed ConstructionProposed Construction
• New two-span continuous multi-girder, high strength weathering steel superstructure
• Increased Minimum Vertical Clearance over I-95– Existing: 14’-2”– Proposed: 16’-3”
• Deck will consist of cast-in-place reinforced concrete with membrane waterproofing and an asphaltic overlay.
• Structure Dimensions– Total Length slightly increased due to abutment
modifications– Match Existing Out to Out Width
• New two-span continuous multi-girder, high strength weathering steel superstructure
• Increased Minimum Vertical Clearance over I-95– Existing: 14’-2”– Proposed: 16’-3”
• Deck will consist of cast-in-place reinforced concrete with membrane waterproofing and an asphaltic overlay.
• Structure Dimensions– Total Length slightly increased due to abutment
modifications– Match Existing Out to Out Width
Proposed Construction (cont’d)Proposed Construction (cont’d)
• Pier Repair and Modification– Removal of Intermediate Piers– Reconstruction of Center Pier to form Pier Wall– Concrete Repairs to spalls and hollow areas
• Abutments will be modified to accommodate increased loads and raised profile– Addition of heel length– Third row of steel H-piles– Minor concrete repairs to existing abutment stems
• Pier Repair and Modification– Removal of Intermediate Piers– Reconstruction of Center Pier to form Pier Wall– Concrete Repairs to spalls and hollow areas
• Abutments will be modified to accommodate increased loads and raised profile– Addition of heel length– Third row of steel H-piles– Minor concrete repairs to existing abutment stems
Public UtilitiesPublic Utilities Utilities at the bridge site consist of aerial facilities (electric,
telecommunication and cable) and a VMS cabinet located Northeast of the bridge.
CTDOT has notified the appropriate utility companies of the scheduled project.
Utilities will be temporarily relocated as part of the proposed construction activities.
Utilities at the bridge site consist of aerial facilities (electric, telecommunication and cable) and a VMS cabinet located Northeast of the bridge.
CTDOT has notified the appropriate utility companies of the scheduled project.
Utilities will be temporarily relocated as part of the proposed construction activities.
Rights-of-WayRights-of-WayBased upon the State boundary map, the width of ROW for Interstate Route 95 at the bridge site is approximately 500 feet. No impacts to private property are anticipated. All work will be within the DOT-ROW.
Based upon the State boundary map, the width of ROW for Interstate Route 95 at the bridge site is approximately 500 feet. No impacts to private property are anticipated. All work will be within the DOT-ROW.
Project CostProject Cost
The estimated construction cost for the project is approximately $5,800,000.
This bridge replacement is anticipated to be undertaken using Federal and State funds.
The estimated construction cost for the project is approximately $5,800,000.
This bridge replacement is anticipated to be undertaken using Federal and State funds.
Project Schedule Project Schedule
Construction of Bridge No. 00245 is anticipated to begin in the spring of 2013 and be completed in the fall of 2014.
The schedule is preliminary and is predicated upon the availability of funding.
Construction of Bridge No. 00245 is anticipated to begin in the spring of 2013 and be completed in the fall of 2014.
The schedule is preliminary and is predicated upon the availability of funding.
Contact InformationContact Information CTDOT
Ms. Mary E. Baker
2800 Berlin Turnpike, P.O. Box 317546
Newington, Connecticut 06131-7546
(860) 594-3402 or [email protected]
Close, Jensen and Miller, P.C.
Mr. Jeffrey J. Fontaine
1137 Silas Deane Highway
Wethersfield, Connecticut 06109
(860) 563-9375 or [email protected]
CTDOTMs. Mary E. Baker
2800 Berlin Turnpike, P.O. Box 317546
Newington, Connecticut 06131-7546
(860) 594-3402 or [email protected]
Close, Jensen and Miller, P.C.
Mr. Jeffrey J. Fontaine
1137 Silas Deane Highway
Wethersfield, Connecticut 06109
(860) 563-9375 or [email protected]