public information meeting rehabilitation of bridge no. 00245 flat rock hill road over i-95 old...

26
Public Information Meeting Rehabilitation of Bridge No. 00245 Flat Rock Hill Road over I-95 Old Lyme, Connecticut

Upload: edgar-black

Post on 24-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Public Information MeetingPublic Information Meeting

Rehabilitation of

Bridge No. 00245

Flat Rock Hill Road over I-95

Old Lyme, Connecticut

Rehabilitation of

Bridge No. 00245

Flat Rock Hill Road over I-95

Old Lyme, Connecticut

Bridge No. 00245

CTDOT Role and MissionCTDOT Role and Mission

Bureau of Engineering and Construction

• Responsible for engineering design, construction, and inspection of transportation projects

Project Manager: Mr. Louis D. Bacho

Contact: Ms. Mary E. Baker

Bureau of Engineering and Construction

• Responsible for engineering design, construction, and inspection of transportation projects

Project Manager: Mr. Louis D. Bacho

Contact: Ms. Mary E. Baker

Close, Jensen and Miller, P.C.Consultant Liaison EngineersClose, Jensen and Miller, P.C.Consultant Liaison Engineers

CTDOT has retained the firm of Close, Jensen and Miller to supervise the activities relative to the design of this bridge project.

Contact: Mr. Jeffrey J. Fontaine

CTDOT has retained the firm of Close, Jensen and Miller to supervise the activities relative to the design of this bridge project.

Contact: Mr. Jeffrey J. Fontaine

Project GoalsProject Goals

• Rehabilitate Bridge No. 00245

• Minimize disturbance to traveling public

• Complete construction in a timely manner

• Effectively use funds

Address above with consideration for context sensitive design

• Rehabilitate Bridge No. 00245

• Minimize disturbance to traveling public

• Complete construction in a timely manner

• Effectively use funds

Address above with consideration for context sensitive design

Bridge No. 00245 Elevation looking East

on Interstate 95

Bridge No. 00245 Elevation looking East

on Interstate 95

Bridge No. 00245 Elevation looking West

on Interstate 95

Bridge No. 00245 Elevation looking West

on Interstate 95

Existing Bridge Description Bridge No. 00245

Existing Bridge Description Bridge No. 00245

• Four-Span, Continuous Steel Multi-Girder Structure built in 1958

• Carries one lane of traffic in each direction– Estimated Average Daily Traffic (ADT) on Flat Rock Hill Road ~116 vehicles (2007)

– ADT on Interstate 95 under Bridge No. 00245 ~67,900 (2009)

• Structure Dimensions– Total Length = 173’

– Overall Width = 45’ 7”

– Roadway Width = Originally 40’ 0”

Reduced to 26’ 5” due to concrete

barrier curb along Eastern side for

girder protection

• Four-Span, Continuous Steel Multi-Girder Structure built in 1958

• Carries one lane of traffic in each direction– Estimated Average Daily Traffic (ADT) on Flat Rock Hill Road ~116 vehicles (2007)

– ADT on Interstate 95 under Bridge No. 00245 ~67,900 (2009)

• Structure Dimensions– Total Length = 173’

– Overall Width = 45’ 7”

– Roadway Width = Originally 40’ 0”

Reduced to 26’ 5” due to concrete

barrier curb along Eastern side for

girder protection

Bridge No. 00245looking South

Bridge No. 00245looking South

Bridge No. 00245looking North

Bridge No. 00245looking North

Existing Bridge Description (cont’d) Bridge No. 00245

Existing Bridge Description (cont’d) Bridge No. 00245

• Minimum Vertical Clearance over I-95 = 14’-2”

• Reinforced concrete deck with concrete wearing surface

• Substructure (Foundation)– Concrete abutments on steel piles

– Two intermediate concrete piers and one center concrete pier on spread footings founded on bedrock

• Minimum Vertical Clearance over I-95 = 14’-2”

• Reinforced concrete deck with concrete wearing surface

• Substructure (Foundation)– Concrete abutments on steel piles

– Two intermediate concrete piers and one center concrete pier on spread footings founded on bedrock

Reasons for Project Reasons for Project

Structure recommended for rehabilitation under the State Bridge Program.

• Structurally Deficient:– Overall Superstructure Condition Rating “4”

– Jersey Barriers used to keep live loads off fascia girders

– Fascia girders exhibit extensive vehicular impact damage

– Girders exhibit moderate to heavy rust

• Functionally Obsolete:– Minimum Vertical Clearance is Substandard

Structure recommended for rehabilitation under the State Bridge Program.

• Structurally Deficient:– Overall Superstructure Condition Rating “4”

– Jersey Barriers used to keep live loads off fascia girders

– Fascia girders exhibit extensive vehicular impact damage

– Girders exhibit moderate to heavy rust

• Functionally Obsolete:– Minimum Vertical Clearance is Substandard

Reasons for ProjectReasons for Project

Fascia Girder over SB Traffic Impact damage

Fascia Girder over SB Traffic Impact damage

Bearing PadsSheared bolt due to impact damage

Bearing PadsSheared bolt due to impact damage

Reasons for ProjectReasons for Project

Steel GirdersRust along underside of structure

Steel GirdersRust along underside of structure

PiersLight to moderate scaling, rust along underside of structure

PiersLight to moderate scaling, rust along underside of structure

Proposed ConstructionProposed Construction

• New two-span continuous multi-girder, high strength weathering steel superstructure

• Increased Minimum Vertical Clearance over I-95– Existing: 14’-2”– Proposed: 16’-3”

• Deck will consist of cast-in-place reinforced concrete with membrane waterproofing and an asphaltic overlay.

• Structure Dimensions– Total Length slightly increased due to abutment

modifications– Match Existing Out to Out Width

• New two-span continuous multi-girder, high strength weathering steel superstructure

• Increased Minimum Vertical Clearance over I-95– Existing: 14’-2”– Proposed: 16’-3”

• Deck will consist of cast-in-place reinforced concrete with membrane waterproofing and an asphaltic overlay.

• Structure Dimensions– Total Length slightly increased due to abutment

modifications– Match Existing Out to Out Width

Proposed Construction (cont’d)Proposed Construction (cont’d)

• Pier Repair and Modification– Removal of Intermediate Piers– Reconstruction of Center Pier to form Pier Wall– Concrete Repairs to spalls and hollow areas

• Abutments will be modified to accommodate increased loads and raised profile– Addition of heel length– Third row of steel H-piles– Minor concrete repairs to existing abutment stems

• Pier Repair and Modification– Removal of Intermediate Piers– Reconstruction of Center Pier to form Pier Wall– Concrete Repairs to spalls and hollow areas

• Abutments will be modified to accommodate increased loads and raised profile– Addition of heel length– Third row of steel H-piles– Minor concrete repairs to existing abutment stems

Proposed ConstructionProposed Construction

Bridge Elevation

Stage 1 ConstructionStage 1 Construction

Stage 2 ConstructionStage 2 Construction

Proposed ConstructionProposed Construction

Bridge Cross Section

Public UtilitiesPublic Utilities Utilities at the bridge site consist of aerial facilities (electric,

telecommunication and cable) and a VMS cabinet located Northeast of the bridge.

CTDOT has notified the appropriate utility companies of the scheduled project.

Utilities will be temporarily relocated as part of the proposed construction activities.

Utilities at the bridge site consist of aerial facilities (electric, telecommunication and cable) and a VMS cabinet located Northeast of the bridge.

CTDOT has notified the appropriate utility companies of the scheduled project.

Utilities will be temporarily relocated as part of the proposed construction activities.

Rights-of-WayRights-of-WayBased upon the State boundary map, the width of ROW for Interstate Route 95 at the bridge site is approximately 500 feet. No impacts to private property are anticipated. All work will be within the DOT-ROW.

Based upon the State boundary map, the width of ROW for Interstate Route 95 at the bridge site is approximately 500 feet. No impacts to private property are anticipated. All work will be within the DOT-ROW.

Project CostProject Cost

The estimated construction cost for the project is approximately $5,800,000.

This bridge replacement is anticipated to be undertaken using Federal and State funds.

The estimated construction cost for the project is approximately $5,800,000.

This bridge replacement is anticipated to be undertaken using Federal and State funds.

Project Schedule Project Schedule

Construction of Bridge No. 00245 is anticipated to begin in the spring of 2013 and be completed in the fall of 2014.

The schedule is preliminary and is predicated upon the availability of funding.

Construction of Bridge No. 00245 is anticipated to begin in the spring of 2013 and be completed in the fall of 2014.

The schedule is preliminary and is predicated upon the availability of funding.

Contact InformationContact Information CTDOT

Ms. Mary E. Baker

2800 Berlin Turnpike, P.O. Box 317546

Newington, Connecticut 06131-7546

(860) 594-3402 or [email protected]

Close, Jensen and Miller, P.C.

Mr. Jeffrey J. Fontaine

1137 Silas Deane Highway

Wethersfield, Connecticut 06109

(860) 563-9375 or [email protected]

CTDOTMs. Mary E. Baker

2800 Berlin Turnpike, P.O. Box 317546

Newington, Connecticut 06131-7546

(860) 594-3402 or [email protected]

Close, Jensen and Miller, P.C.

Mr. Jeffrey J. Fontaine

1137 Silas Deane Highway

Wethersfield, Connecticut 06109

(860) 563-9375 or [email protected]

THANK YOU…THANK YOU…

FOR YOUR TIME AND

ATTENTION

FOR YOUR TIME AND

ATTENTION