public hearings january 13, 2015. case: psp-14-05-132 project: avalon park pd / avalon town center...

8
Public Hearings January 13, 2015 Board of County Commissioners

Upload: brianna-atkinson

Post on 16-Dec-2015

218 views

Category:

Documents


2 download

TRANSCRIPT

Public Hearings

January 13, 2015

Board of County Commissioners

Case: PSP-14-05-132

Project: Avalon Park PD / Avalon Town Center PSP / A Portion of Tract 3 Uptown Avalon PSP

Applicant: Dave Schmitt, Dave Schmitt Engineering, Inc.

District: 4

Acreage: 1.15

Request: Preliminary Subdivision Plan to construct 16 single-family residential dwelling units, of which 10 will contain office / retail units (11,760 SF of C-1 uses) on the ground floor.

Avalon Park PD / Avalon Town Center PSP / A Portion of Tract 3 Uptown Avalon PSP Avalon Park PD / Avalon Town Center PSP / A Portion of Tract 3 Uptown Avalon PSP

Avalon Park PD / Avalon Town Center PSP / A Portion of Tract 3 Uptown Avalon PSPZoning Map

Avalon Park PD / Avalon Town Center PSP / A Portion of Tract 3 Uptown Avalon PSPZoning Map

Avalon Park PD / Avalon Town Center PSP / A Portion of Tract 3 Uptown Avalon PSPFuture Land Use Map

Avalon Park PD / Avalon Town Center PSP / A Portion of Tract 3 Uptown Avalon PSPFuture Land Use Map

Avalon Park PD / Avalon Town Center PSP / A Portion of Tract 3 Uptown Avalon PSPAerial Map

Avalon Park PD / Avalon Town Center PSP / A Portion of Tract 3 Uptown Avalon PSPAerial Map

Avalon Park PD / Avalon Town Center PSP / A Portion of Tract 3 Uptown Avalon PSP Avalon Park PD / Avalon Town Center PSP / A Portion of Tract 3 Uptown Avalon PSP

Avalon Park PD / Avalon Town Center PSP / A Portion of Tract 3 Uptown Avalon PSP Avalon Park PD / Avalon Town Center PSP / A Portion of Tract 3 Uptown Avalon PSP

Proposed New COA #16

16. The construction plan submittal shall include a Traffic Control Signage and Stripping Plan for installation of stop signs at the project

entrance on Tanja King Boulevard for review and approval by the County.

District 4

Action RequestedMake a finding of consistency with the Comprehensive Plan and approve the Avalon Park PD / Avalon Town Center – A Portion of Tract 3 Uptown Avalon PSP dated “Received October 23, 2014,” subject to the conditions listed under the DRC Recommendation in the staff report, with the addition of new COA #16.

District 4