PSD Permitting Process. Nancy Mayer EPA OAQPS. Topics. Find technical resources for permit review Describe how permits are constructed Describe what to look for when reviewing a permit. Useful Areas of Expertise. Air pollution modeling Air pollution control Equipment Practices - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/1.jpg)
PSD Permitting Process
Nancy Mayer
EPA OAQPS
![Page 2: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/2.jpg)
2
Topics
Find technical resources for permit review Describe how permits are constructed Describe what to look for when reviewing a
permit
![Page 3: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/3.jpg)
3
Useful Areas of Expertise
Air pollution modeling Air pollution control
– Equipment – Practices
Law
![Page 4: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/4.jpg)
4
Typical Permit Format
General source identification Source location Emissions information Control technology analysis - BACT
– Top-down approach
Air Quality Impact Analysis
![Page 5: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/5.jpg)
5
General Source Information
Name Source classification –
– On list to count fugitive emissions?
Generally what construction/modification is being proposed – Reason for construction
![Page 6: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/6.jpg)
6
Source ID–what to look for
Is source classification correct? Does reason for modification make sense?
![Page 7: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/7.jpg)
7
Source Location
Location – Attainment/nonattainment area– Nearby class I areas
Source site diagram
![Page 8: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/8.jpg)
8
Source location–what to look for
Is location accurate? Does permit ID all Class I areas and tribal
lands within 100 KM? Does it ID all nearby nonattainment areas? Does site diagram clearly explain what is
being proposed? Unexplained buildings in diagram?
![Page 9: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/9.jpg)
9
Emissions Data
Existing emissions baseline Change in emissions
– Netting calculation, if any
Stack height
![Page 10: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/10.jpg)
10
Emissions Data–what to look for
What method is used to measure emissions? – Stack tests – when, how often?– Correct emission factors?– Do assumptions make sense? – Is baseline year the correct year? – Is averaging done correctly?
Is calculation for the emissions change clearly shown and explained?
Is stack height measured correctly?
![Page 11: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/11.jpg)
11
Air Quality Impact Analysis
Terrain Model name Features selected Results
– Increment– NAAQS– Class I areas
![Page 12: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/12.jpg)
12
Modeling–what to look for
All important terrain features identified? Correct model being used?
– Pollutants – sources Assumptions reasonable? Correct meteorological data set being used? All results presented, or only summaries?
![Page 13: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/13.jpg)
13
More modeling things to look for
Increment analyses done correctly?– Baseline area?– All relevant pollutants – Any increment violations?
Do emission increases cause new NAAQS violations?
Do emissions impact existing nonattainment areas?– Impacts mitigated?
![Page 14: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/14.jpg)
14
Control technology
Proposed Best Available Control Technology (BACT) – Top-down approach
Describe other alternatives For each relevant pollutant
![Page 15: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/15.jpg)
15
Control Technology–what to look for
Reasons for not choosing best technology? Technology from BACT/LAER
Clearinghouse? Technology for all relevant pollutants?
![Page 16: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/16.jpg)
16
Public Participation/Notice
Date, time documentation Notice in readily available local newspaper Contacted Relevant Federal Land Managers Contacted nearby tribes
![Page 17: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/17.jpg)
17
Public comment–what to look for
All FLM concerns addressed? Public notice clear and well publicized? Any public comments? Public comments adequately addressed?
![Page 18: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/18.jpg)
18
Were formalities met?
Did source submit permit application before commencing construction?
Has the state been working with source? Permit easy to follow?
![Page 20: PSD Permitting Process](https://reader036.vdocuments.us/reader036/viewer/2022081506/568150f8550346895dbf1725/html5/thumbnails/20.jpg)
20
How to submit comments
States must send copy of permit to tribal governing body
Public-comment period Can request public hearing and provide
verbal comments Special Class I protection
– Lower increment allowed– Visibility