PS LIU EN/EL 2012 J. Devine (EL/BT) EN/EL Transformer EMT104*45 relocation: Activity Outline

Upload: verdad

Post on 12-Feb-2016

24 views

Category:

Documents


0 download

DESCRIPTION

EN/EL Transformer EMT104*45 relocation: Activity Outline. PS LIU EN/EL 2012. J. Devine (EL/BT). EN/EL Transformer EMT104*45 relocation. Summary of activity: Remove spare transformer Cast new transformer slab Drill new access holes into Building 365 Pull HV and LV cables in preparation - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: PS LIU  EN/EL 2012

PS LIU EN/EL 2012 J. Devine (EL/BT)

EN/EL Transformer EMT104*45 relocation:

Activity Outline

Page 2: PS LIU  EN/EL 2012

PS LIU EN/EL 2012 J. Devine (EL/BT)

EN/EL Transformer EMT104*45 relocation

Summary of activity:

• Remove spare transformer• Cast new transformer slab• Drill new access holes into Building 365• Pull HV and LV cables in preparation• Disconnection and re-location of transformer• Connection of new cables & commissioning• Removal of old cables

Page 3: PS LIU  EN/EL 2012

PS LIU EN/EL 2012 J. Devine (EL/BT)

EN/EL Transformer EMT104*45 relocation

Page 4: PS LIU  EN/EL 2012

PS LIU EN/EL 2012 J. Devine (EL/BT)

EN/EL Transformer EMT104*45 relocation

Page 5: PS LIU  EN/EL 2012

PS LIU EN/EL 2012 J. Devine (EL/BT)

EN/EL Transformer EMT104*45 relocation

Actors:

• GS – Civil Engineering elements• Transport – Relocation of transformers• C209/C210 contractors for LV & HV cables• EN/EL-OP Permits to work• EN/EL-HV Electrical protection modifications

Page 6: PS LIU  EN/EL 2012

PS LIU EN/EL 2012 J. Devine (EL/BT)

EN/EL Transformer EMT104*45 relocationBudget PS LIU - Transformer Relocation

20/06/2011

ML/quant Prix Unitaire Prix Total

Transformer EMT104*45Civil works for transfo EMT104*45 CHF 15,000Re-location transformer CHF 10,000HV cables (30m*3ph*95mm^2) 300 CHF 40 CHF 12,000HV cable termination [(transfo+cubicle)*3ph] 6 CHF 600 CHF 3,600

CHF 40,600

Total CHF 40,600

ML/quant Prix Unitaire Prix TotalDepose Estimatif CHF 3,000.00

Total CHF 3,000.00Cheminement

Echelle a cable 400 100 23.659 CHF 2,365.90Total CHF 2,365.90

Cablage et fournitureCables Cuivre 240 Cu 600 30 CHF 18,000.00Racordement 240 Cu 32 47 CHF 1,504.00Total CHF 19,504.00

DocumentationsSchemas Base-de-donnes CHF 400.00Schemas Cablotheque CHF 400.00Schemas Cheminment 1 440 CHF 440.00Total CHF 1,240.00

Total CHF 26,109.90

HV CHF 40,600LV CHF 26,110

Total CHF 66,710+10% Contingency CHF 73,381

HV

LV

Summary

Page 7: PS LIU  EN/EL 2012

PS LIU EN/EL 2012 J. Devine (EL/BT)

EN/EL Transformer EMT104*45 relocation

Questions?