PRY Base - Contents
PRY Support/Base/Platform in the MICE Hall Requirements Environment Design Structural Integrity Preparation Installation Absorber Change Schedule Conclusion
Jason Tarrant – Integration Engineering
![Page 2: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/2.jpg)
PRY Base - Requirements Requirements – Load (before cross-bars added)
Fix to floor
~25 tonnes (self weight)
Overturning
Compression
Tension
NO CAPACITY FOR SIGNIFICANT OVERTURNING
FROM MAGNETIC LOAD – This will be taken by the
cross-bars, leg ties & link plate connections
![Page 3: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/3.jpg)
PRY Base - Environment Requirements
– North side
Plate roof on north
side
Edge of floor / trench
Services in trench on wall and
ceiling
Services trench directly under leg
Trench ends
False floor
![Page 4: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/4.jpg)
PRY Base - Environment Requirements
– South side
South mezzanine
uprights
Services trench
Ramp
Walkway
![Page 5: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/5.jpg)
PRY Base - Environment Requirements
- Services
Tracker Cryo
South mezzanine
Vacuum system
![Page 6: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/6.jpg)
PRY Base - Design TD-1189-2090 - North East Quadrant
Existing Base
PRY Legs
PRY Connector
Tie down bars and bases
Support Bridge
Trench & trench services
Trench edge
![Page 7: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/7.jpg)
PRY Base - Design TD-1189-2090 – North West Quadrant
Existing Base (shown cutaway)
PRY Legs
PRY Connector
Tie down bars and bases
Support Bridge
Trench & trench services
Trench edge
Short columns
where raised
floor endsVacuum system (installed later)
![Page 8: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/8.jpg)
PRY Base - Design TD-1189-2090 – South West Quadrant
New base / platform
PRY Legs
PRY Connector
Vacuum system
Support Bridge
Short columns where raised floor ends
Tie down bars and bases
Brackets and floor anchors
![Page 9: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/9.jpg)
PRY Base - Design TD-1189-2090 – South East Quadrant
New base / platform
PRY Legs
PRY Connector
Support Bridge
Services trench
Brackets and floor anchors
Vacuum system
South mezzanine
supports
![Page 10: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/10.jpg)
PRY Base – Structural Integrity Testing
Floor anchor pull out (TD-1189-1922)
Component load tests
Analysis & calculation
![Page 11: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/11.jpg)
PRY Base - Preparation South Mezzanine
Full length of hinged platforms
Raised platformsReduced
leading edge & cut beams
Removable section for easy absorber change
Fit around PRY
![Page 12: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/12.jpg)
PRY Base - Preparation Trench
Water circuit move
Ladder move and change
North-east tie bars pass between trench services (water and
ISIS cables
![Page 13: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/13.jpg)
PRY Base - Installation Bases
Floor anchors (TD-1189-2152) Pillars, tie plates & sub-floor (TD-1189-2153)
Top plate installation (blue)
& hole drilling (TD-1189-2136)
![Page 14: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/14.jpg)
PRY Base - Installation Installation
Survey inside bridges into place Add legs & connectors(+ bespoke shims to set position)
Add outer bridges
Add tie downs / bolt to floor
![Page 15: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/15.jpg)
PRY Base – Absorber Change Absorber change
![Page 16: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/16.jpg)
PRY Base – Schedule Schedule
Prep for frame by July 2014, PRY install by end Aug 2014
![Page 17: PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation](https://reader036.vdocuments.us/reader036/viewer/2022062805/5697c0041a28abf838cc410c/html5/thumbnails/17.jpg)
Conclusion Design done (top level = TD-1189-2152,2153,2136 & 2090) Calculation and analysis shows OK for self weight only (not
magnetic load) in terms of stress and strain Piece parts out for manufacturing quotation South mezzanine structural engineering drawings near
completion (OPUS) RFS placed for floor quality tests Load testing on critical parts will be undertaken Possibility of strain gauges on critical parts as per main PRY (H
Witte investigating) Schedule currently predicting manufacture, prep and install to
coincide with PRY delivery (final install dependant on PRY frame delivery)