proton driven plasma wakefield acceleration – awake – project
TRANSCRIPT
2
Outline
• Introduction• Plasma Wakefield Acceleration• Mandate of the AWAKE project• AWAKE Project Structure and Organization• AWAKE Project Studies
E. Gschwendtner, 4/9/2012
3
Why
In recent years several Laser or Electron-driven Plasma Wakefield experiments:
– E.g. SLAC (2007) 50GV/m over 0.8m with electron-driven PWA some electrons doubled energy from 42GeV to 80GeV
Advantage of proton driven plasma wakefield acceleration:– high stored energy available in the driver.
• Existing proton bunches carry many kJ of stored energy (high power lasers carry 1-5 J)
• Reduces drastically the number of required driver stages.
Proof-of principle demonstration experiment proposed at SPS:– first beam-driven wakefield acceleration experiment in Europe, and the
first Proton-Driven PWA experiment worldwide.
E. Gschwendtner, 4/9/2012
4
IntroductionLetter of Intent: positive review in SPSC October 2011Research Board December 2011:
submit Conceptual Design Report during following yearJune 2012: Official CERN AWAKE project (including project-budget) with mandate sent by S.
Myers to DHs.CERN project leader (E.G.) organize CERN efforts to produce parts of CDR under CERN responsibility
CDR includes detailed budget, CERN manpower and schedule plans for design, construction, installation and commissioning.
Deliverables:End 2012: preliminary report summarizing the ongoing study to the A&T sector Management Q1 2013: Conceptual Design Report to the A&T sector Management.
AWAKE collaboration: 25 institutes
E. Gschwendtner, 4/9/2012
5
Principle of Plasma Wakefield Acceleration I
++++++++++++++ ++++++++++++++++
----- --- -------------------
-----------
--------- ------- -
------------------- - --
---- - -- ---
------ -- -- ---- - - - - - --
---- - -- - - - --- -
-
- -- - - - - -
---- - ----
-----
+ + + + + + + + + + ++ + + + + + + + + + + + + + ++ + + + + + + + + + + + + + ++ + + + + + + + + + + + + + +-
- --
--- --
Ez
Drive beam
Plasma electrons oscillate with:
Plasma wavelength:
e.g. for typical plasma density of np = 1015cm-3 lp =1mm
Maximal axial electric field: Ez,max = Nprotons/bunch
sz (rms bunch length)
With plasma wavelength of 1mmalso drive beam rms length of 1mm
Produce an accelerator with mm (or less) scale ‘cavities’
np
Space charge of drive beam displaces plasma electrons. Plasma ions exert restoring force.
E. Gschwendtner, 4/9/2012
6
Principle of Plasma Wakefield Acceleration IISPS beam: rms length of ~12cm But strong self-modulation effect of proton beam due to transverse wakefield in plasma
Starts from any perturbation and grows exponentially until fully modulated. Ultra-short bunch slices are naturally produced with a spacing of plasma wavelength lp.
p-beam density profile after 4.8m propagation in plasma.
Seeding of bunch modulation with laser: Ionization of Plasma
Produce start of bunch-modulation in a controlled way
laser pulse proton bunch
gasPlasmaIntense short laser pulse co-propagates with proton bunch. plasma get ionized at fixed position. generates large perturbation and seeds modulation.
E. Gschwendtner, 4/9/2012
7
Principle of Plasma Wakefield Acceleration III
Inject electron beam to accelerateElectron bunch injected off-axis at an angle and some metres downstream along the plasma-cell: merges with the proton bunch once the modulation is developed.
Longitudinal electric field generated in plasma as function of propagation distance. 100-1000MV/m.
Particle-in-cell simulations predict acceleration of injected electrons to beyond 1 GeV.
E. Gschwendtner, 4/9/2012
8
Experimental Layout
E. Gschwendtner, 4/9/2012
Plasma-cellProton beam dump
RF gun
Laser
Laser dump
OTRStreak camera
CTREO diagnostic
e- spectrometer
e-
SPSprotons
~3m
10m 15m?20m 10m?
10m
9
Beam Specifications
E. Gschwendtner, 4/9/2012
Parameter Nominal
Beam Energy 450 GeV
Bunch intensity 3×1011 p
Number of bunches 1
Repetition rate 0.03 Hz
Transverse norm. emittance 3.3-3.5 mm
Transverse beam size (at b*=5m)
0.2 mm
Bunch length 12 cm
Energy in bunch 21 kJ
Number of run-periods/year 4
Length of run-period 2 weeks
Total number of beam shots/year (100% efficiency)
162000
Total number of protons/year 4.86×1016 p
Proton beam specifications
Parameter Value
Beam Energy 5 or 10 or 20 MeV
Bunch intensity 108 electrons
Bunch length 0.165mm<l<1mm
Repetition rate 0.03 Hz
Transverse norm. emittance
< 25 mm mrad
Transverse beam size (at beta*=?m)
??
Angle(mrad) ~5-20 mrad
Electron beam specifications
Laser:30fs, 800nm, ~TW.
R & D facility: frequent access to plasma cell, laser, etc… needed.
10
Mandate of CERN AWAKE Project• Identify the best site for installation of the facility on the SPS by carrying out a study covering:
– The design of the proton beam-line from the SPS to the entry point of the plasma cell, to meet the required parameters.
– The design of the downstream beam-line from the plasma cell to the beam dump. – The design the common beam-line for the proton, electron and laser light beam at the entry into the plasma
cell. Specification of the parameters for these incoming beams. – The design of the experimental area (envelope) considering layout optimization of all components in the area. – The study of access possibilities and assess radiation and safety aspects. – The study of the general infrastructures (Civil Engineering, Access, CV, EL, transport, handling, control).– The physics program that could be carried out on each site. – The comparison of the cost and of the schedule of the alternative sites.
• Based on the study, recommend a site for the facility and deliver the chapters, covering the beam line, the experimental area and all interfaces and services at CERN, in the conceptual design report (CDR) of the AWAKE CERN facility. The CDR should include the points mentioned in the section above plus the following information:– Specification of the baseline beam parameters to be used for the design.– Predictions of measurable quantities in the diagnostic instrumentation.– Specification of diagnostic instrumentation in the experimental area.– Design and interface with the electron beam up to the plasma cell. – Study all interfaces between the different systems (plasma cell, electron beam, proton beam, laser…) – Evaluation of time scale and costs of all items at a level needed for the CDR.– Evaluate dismantling feasibility and cost.
E. Gschwendtner, 4/9/2012
Beam-LinesChiara Bracco
Accelerator & Infrastructure CoordinatorEdda Gschwendtner (CERN Project leader)
Experimental AreaEdda Gschwendtner
Radiation ProtectionHelmut Vincke
AWAKE Project Structure
Experiment CoordinatorPatric Muggli
Simulation/Theory CoordinatorKonstantin Lotov
AWAKE CollaborationSpokesperson: Allen Caldwell
Deputy: Matthew Wing
Metal Vapor Plasma CellErdem Öz, MPP
Helicon Plasma Cell Olaf Grülke, IPP
Pulsed Discharge Plasma CellNelson Lopes, IST Lisbon
Electron SpectrometerSimon Jolly, UCL
Optical DiagnosticsPeter Norreys, CLF, RAL (tbc)
Electron SourceTim Noakes, ASTeC
SimulationsKonstantin Lotov
TASKS
E. Gschwendtner, 4/9/2012 11
12
CERN AWAKE Project Structure
Radiation Protection: Helmut VinckeCivil Engineering: John OsborneGeneral Safety and Environment: Andre Jorge HenriquesGeneral Services: CV, EL, access, storage, handling
WP3: Primary beam-linesChiara Bracco
CERN AWAKE ProjectProject leader: Edda Gschwendtner
Deputy: Chiara Bracco
WP4: Experimental AreaEdda Gschwendtner
WP2: SPS beamElena Chapochnikova
WP1: Project ManagementEdda Gschwendtner
E. Gschwendtner, 4/9/2012
A& T sector management:Engineering, Beams, Technology Departments
Injectors and Experimental Facilities Committee (IEFC)
13
WP1: Project Management
E. Gschwendtner, 4/9/2012
• Specification and engineering documents (EDMS)• Project cost and schedule• Resource planning and scheduling with groups and departments• Quality control, documentation and final acceptance• Safety file and safety officer
• Specifications for RF bunch compression studies• Specifications for bunch compression requirements • Interface to SPS beam
WP2: SPS beam
E.G.
Elena Chapochnikova
14
WP3 Primary beam-lines
E. Gschwendtner, 4/9/2012
• Collection of geometrical, beam parameters, optical requirements and constraints
• Design of beam-line geometry and optics• Specification of main, correction and switch magnet parameters, associated
powering parameters, beam instrumentation• Design of interface of different beam-lines (merging magnets, fast shutter,
laser, etc…)• Definition of vacuum chamber aperture, pumping and sectorisation required.• Specification of magnet and pickup support and alignment structures• Specification of requirements for cabling, cooling&ventilation, interlock
system, control& alarm, doors, access.• Integration studies• Technical coordination of studies, construction, installation and
commissioning of all systems• Transport and handling needs, installation logistics, storage studies• Definition of naming convention, commissioning strategy• ECRs as required (for changes in TT60)• Planning for design, construction, assembly, test and commissioning• Dose rate and activation studies• RP monitoring system• Radioactive waste study and preferred material checks• Decommissioning impact/cost studies• Safety, including safety folders
Chiara BraccoEDMS:
15
WP4 Experimental Area
E. Gschwendtner, 4/9/2012
• Conceptual design of secondary beam-lines• Specification of secondary beam instrumentation• Specifications of shielding, dumps (with RP) • Specification of interaction region p/e/laser/cell• Layout and Integration studies • Specification of infrastructure needs• Layout of shielding• Layout of beam dump(s)• Interface with laser• Specification of requirements for cabling, cooling & ventilation• Specification for interlock system, control& alarm, doors, access.• Storage studies• Integration studies• Transport and handling needs, installation logistics• Coordination of installation• Definition of naming convention, commissioning strategy• ECRs as required • Technical coordination of studies, construction, installation and commissioning
of all systems• Planning for design, construction, assembly, test and commissioning• Dose rate and activation studies• RP monitoring system• Radioactive waste study and preferred material checks• Decommissioning impact/cost studies• Safety, including safety folders
E.G.EDMS:
16
CERN AWAKE Project Organization INDICO: https://indico.cern.ch/categoryDisplay.py?categId=4278
E. Gschwendtner, 4/9/2012
Weekly (Project mgt team) monthly bi-weekly (Collaboration board)
Each work-packages organizes their corresponding meeting.Depending on issues, people are invited to CERN project team meeting
Work-package meetings To be setup by WP leader, starts now!
EDMS: https://edms.cern.ch/nav/P:CERN-0000094988:V0/P:CERN-0000094988:V0
17
Milestones
• 18-19 October 2012 (Collaboration Mtg @ CERN):West Area:– Proton beam-line design– Layout of experimental areaFirst studies on CNGS
• End 2012: – Submission of a preliminary report summarizing the ongoing study to the A&T sector
Management by December 2012 comparison of different sites
• Q1 2013:– Submission of the Conceptual Design Report to the A&T sector Management.
including detailed budget, CERN manpower and schedule plans for design, construction, installation and commissioning.
E. Gschwendtner, 4/9/2012
18
Facility Site I: West Area1.) In LoI proposal to use West Area TT61/TT4/TT5 as experimental area.
E. Gschwendtner, 4/9/2012
19
Facility Site II: CNGS
E. Gschwendtner, 4/9/2012
hadron absorber
2.) Alternative experimental area (underground): CNGS decision on continuation of CNGS not yet taken start with West Area studies.
26
West Area Integration Studies
a
c
b
Plasma cellf
gRF
gun k
ie
h
a
c
b
d e
fg
h
ij
k
ii
i
~70m
TT61
TT4TT5
Beam from TCC6 - SPS
AWAKE
183Integration of AWAKE equipment in experimental area in TT4.The beam dump is at the end of TT5.
dump
Ans Pardons, Sylvain Girod EN/MEF
E. Gschwendtner, 4/9/2012
TT5
Beam Impact on Dump Muon Dose Estimates I
E. Gschwendtner, 4/9/2012 27
Make sure that radiation levels from muons are below RP criteria: Optimization criteria: dose rate at end of West hall must be below 100 mSv/year
and at CERN fence below 10 mSv/year
Distance between beam impact point and end of West hall: ~300 mDistance between beam impact point to CERN fence: ~600 m
CERN fence
West hall
Helmut Vincke DGS/RP
28
Beam Impact on Dump Muon Dose Estimates II
E. Gschwendtner, 4/9/2012
Several simulations were performed to check the muon dose estimates (for 1/30Hz and 3E13 p/shot).
West hallCERN fence
dump
600m 300m
Plasma cell
Helmut Vincke DGS/RP
BUT: dose from beam-losses must be further studied!
Plasma cell
dump
Proton beam
In case the beam is bent by 2 degrees towards the soil and the beam impacts the dump 2m below the surface both dose rates outside the West hall and outside the CERN territory fulfill the optimization criteria. Muon Dose from beam dump is manageable.
As a consequence of these first studies: Build a trench in TT4/TT5!
Preliminary design!!
Plasma cell
p+ beamLase
r
Dump
QDMBAMBAMBA
MBB
QD
QF
QF
Top view
Side view
Floor
Beam bent by 2°
Studies on Proton Beam Line Design
Chiara Bracco TE/ABT
E. Gschwendtner, 4/9/2012
30
West Area
E. Gschwendtner, 4/9/2012
Civil-engineering studies: John Osborne, Antoine Kosmicki, GS-SE
31
Facility Site II: CNGS
E. Gschwendtner, 4/9/2012
hadron absorber
2.) Alternative experimental area (underground): CNGS decision on continuation of CNGS not yet taken start with West Area studies.
100m extraction together with LHC, 620m long arc to bend towards Gran Sasso, 120m long focusing section
32
CNGS Layout
TargetJunction chamber / TCC4Proton beam line TT41 Horn
TSG41
TCV4
Storage gallery TSG40
TSG4 tap can be removedTSG41 tap can be moved inside TCV4 – TSG41
TSG4 - racks
(120 m)
Proton beam line TT41
Access Gallery TSG41
Junction chamber TCC4 Target chamber TSG4
E. Gschwendtner, 4/9/2012
35
West Area vs CNGS
E. Gschwendtner, 4/9/2012
West Area CNGS
Proton beam line To be done Most of it exists
Prompt dose issues(muon dose, beam dump)
To be improved/built civil engineering!
OK, under control
Size of experimental area Seems OK Small, needs to be enlarged?!
Access flexibility Experimental area nearby
Long access to experimental area
… … …
… … …
… … …
To be studied!
36
Collaboration time-scale
Plasma-Cell: • Dec 2013
– Demonstrate at least one technology for a plasma length 5m with 1015 cm-3 , uniformity better than 2%, define baseline choice(s)
– Demonstrate seeding in experimental tests, define baseline• Dec 2014
– Demonstrate 1% uniformity and complete operational plasma cell(s)• Aug 2015
– Beam to plasma-cell in experimental facility
E. Gschwendtner, 4/9/2012
37
Summary
CERN AWAKE project started in June 2012 official project, with mandate and project budget
Many studies needed to deliver a CDR in Q1 2013 Expertise in many different domainsStart now
E. Gschwendtner, 4/9/2012
Awaken the AWAKE project!!
39
IngredientsPlasma Cell
Metal vapor, a la SLAC experiment:Max Planck Institute for Physics
Laser: Plasma ionization Seeding the proton-bunch modulation
30fs, 800nm, ~TW
E. Gschwendtner, 4/9/2012
40
Electron bunch
Proton bunch
Electron beam:~10 MeV
Electron bunch injected off-axis at an angle and some metres downstream: merges with the proton bunch once the modulation is developed.
Diagnostics: Proton beam diagnostics: study modulation process as bunch passes through plasma. Proton bunch longitudinal profile
Electron beam diagnostics: study acceleration from 10MeV/c to up to 2000MeV/c Electron spectrometer
Ingredients
E. Gschwendtner, 4/9/2012
41
CERN AWAKE Project Structure
Radiation Protection: Helmut VinckeGeneral Safety and Environment: Andre Jorge Henriques
WP3: Primary beam-linesChiara Bracco• Warm magnets (proton and electron beam)• Power converters• Vacuum• Beam instrumentation• Radioprotection• Civil Engineering• Electrical distribution and cabling• Cooling and ventilation• Transport• Integration• Design office• Control• Planning• Beam transfer
CERN AWAKE ProjectProject leader: Edda Gschwendtner
WP4: Experimental AreaEdda Gschwendtner• Secondary beam line• Secondary beam diagnostics• Spectrometer• Interface p/e/laser plasma cell• Beam dump• Radioprotection• Civil engineering• Electrical distribution and cabling• Cooling and ventilation• Transport• Layout & Integration• Control• Planning• Design office
WP2: SPS beamElena Chapochnikova• RF Issues
WP1: Project ManagementEdda Gschwendtner
E. Gschwendtner, 4/9/2012
42
WP3 Primary beam-lines
E. Gschwendtner, 4/9/2012
• Beam transfer• Warm magnets (proton and electron beam)• Power converters• Vacuum• Beam instrumentation• Radioprotection• Civil Engineering• Electrical distribution and cabling• Cooling and ventilation• Transport• Integration• Design office• Control• Storage• Planning
Composition of WG3: EDMS Structure:
43
WP4 Experimental Area
E. Gschwendtner, 4/9/2012
• Interface p/e/laser with plasma cell• Secondary beam line• Secondary beam diagnostics• Electron spectrometer• Beam dump• Shielding• Laser• Radioprotection• Civil engineering• Electrical distribution and cabling• Cooling and ventilation• Transport and handling needs• Layout & Integration• Control• Planning• Storage• Design office
Composition of WG4: EDMS Structure:
44
First Studies on Proton Beam Line DesignChiara Bracco TE/ABT
As a consequence of these first studies: Build a trench in TT4/TT5!
E. Gschwendtner, 4/9/2012
Beam bent by 2°
45
CNGS Primary Beam Line100m extraction together with LHC, 620m long arc to bend towards Gran Sasso, 120m long focusing section
Magnet System:• 73 MBG Dipoles
– 1.7 T nominal field at 400 GeV/c• 20 Quadrupole Magnets
– Nominal gradient 40 T/m• 12 Corrector Magnets
Beam Instrumentation:• 23 Beam Position Monitors (Button Electrode BPMs)
– recuperated from LEP– Last one is strip-line coupler pick-up operated in air– mechanically coupled to target
• 8 Beam profile monitors– Optical transition radiation monitors: 75 mm carbon or 12 mm titanium screens
• 2 Beam current transformers• 18 Beam Loss monitors
– SPS type N2 filled ionization chambers
E. Gschwendtner, 4/9/2012