proposed 400 kv kokerboom substation to auas...
TRANSCRIPT
PROPOSED 400 kV KOKERBOOM SUBSTATION TO AUAS SUBSTATION TRANSMISSION POWER LINE
ENVIRONMENTAL IMPACT ASSESSMENT PROCESS
Final Scoping Report Environmental Assessment Practitioner: Mrs Jaana-Maria Ball
March 2018
i Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
March 2018
DECLARATION OF INDEPENDENCE
I, Jaana-Maria Ball, confirm my independence as an Environmental Scientist and declare that I
have no interest, be it business, financial, personal or other, in any proposed activity, application
or appeal in respect of which Lithon Project Consultants (Pty) Ltd was appointed to manage the
Environmental Impact Assessment (EIA) process or I was appointed as the Environmental
Assessment Practitioner (EAP), in terms of the Environmental Management Act, 2007 (Act No.
7 of 2007) and the Environmental Impact Assessment (EIA) Regulations, 2012, other than fair
remuneration for worked performed, specifically in connection with the EIA process for the
construction and operation of the 400 kV transmission power line from the Kokerboom
Substation to the Auas Substation. I further declare my objectivity in these assessments and
that I am confident in the results of the studies undertaken and conclusions drawn as a result –
within the limitations as are described in the associated reports.
___________________________
Full Name: Jaana-Maria Ball
Title / Position: Environmental Consultant
Qualification(s): BSc (Botany and Zoology), BSc (Hons), MSc (Botany), MBA, Dip.
Proj. Man, Dip. Bus. Man.
Experience: years: >20 years
Professional
registrations and date of
first registration:
Pr. Sci. Nat. (400049/98), 1998 SAIE&ES, 1998
SAAB, 2000 EAPAN, 2014
Contact details: Email: [email protected]; Cell: +27 83 650 5489
ii Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
Related expertise and experience in undertaking EIAs for power infrastructure developments is:
NUCLEAR-1 EIA AND EMP - Project Director and Manager (2007 – 2013)
Mega-EIA for the proposed construction, operation and decommissioning of a conventional nuclear power
station and associated infrastructure (including transmission lines from the power stations to the
substations) in the Western, Northern and Southern Cape Provinces, South Africa. The EIA included the
screening and selection of a suitable site for the nuclear plant as well as the transportation of fuel and
spent fuel, as well as a scoping process and detailed environmental impact assessment. The study
involved 29 detailed, independent specialist studies that required integration, the assessment process, a
complex consultation process, review studies and compilation of Environmental Management
Programmes (EMPs) for the construction and operational phases.
PEBBLE BED MODULAR REACTOR EIA AND EMP - Project Director and Reviewer (2007 – 2010)
Mega-EIA for the proposed construction, operation and decommissioning of the Pebble Bed Modular
Reactor and associated infrastructure (including power lines from the station to the substation) in the
Western Cape, South Africa. The EIA included a detailed environmental impact assessment, specialist
studies, public consultation and compilation of EMPs.
PERSEUS - GAMMA, HYDRA - GAMMA AND HYDRA - PERSEUS TRANSMISSION LINE EIAS AND
EMPS – Project Director (1999 – 2007)
Multiple EIAs and Public Consultation Processes for the proposed 765 kV transmission power lines from
various substations in the Northern Cape and Free State, South Africa. The EIAs included the assessment
of turn-ins to the substations and their expansion, as well as associated infrastructure and included the
integration of numerous independent specialist studies. EMPs were compiled for the construction and
operational phases. A post-authorisation ‘walkdown’ of the line was undertaken with specialists to
determine final pylon placement.
BANTAMSKLIP TRANSMISSION LINE EIA AND EMP - Project Director (2008 – 2012)
The EIA was undertaken for the proposed construction, operation and decommissioning of the over 9 000
km of 765 kV transmission lines from the Bantamsklip Nuclear Power Station to the Kappa and Bacchus
Substation, the Bacchus to Kappa Substations and the 400 kV transmission line from the Bacchus to
Muldersvlei Substations, as well as all associated infrastructure at the Bantamsklip Power Station site
(Western Cape, SA) and expansions required at the substations. The EIA included the screening and
selection of suitable corridors, as well as a scoping process and detailed impact assessment. The EIA
included a complex consultation process and legal review.
BRAAMHOEK PUMPED STORAGE SCHEME EIA AND EMP - Team Leader (2004 – 2005)
Mega-EIA, Public Consultation Process, EMP, Water Use Licensing Applications, General Authorisation
for Water Use and the South African Department of Mineral and Energy Affairs Applications for the
proposed Eskom Braamhoek Pumped Storage Scheme in the Drakensberg. The proposed scheme
comprises two reservoirs, interconnected by enclosed tunnel systems, with pump turbine units with a
potential generation capacity of approximately 1 333 MW.
A full Curriculum Vitae detailing my knowledge and experience in undertaking assessments,
including knowledge of the Environmental Management Act, 2007, the Environmental Impact
Assessment Regulations, 2012, and the related guidelines, that have relevance to the proposed
activity, is appended in Appendix A: Curriculum Vitae of Mrs. Jaana-Maria Ball.
iii Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
ENVIRONMENTAL IMPACT ASSESSMENT FOR THE PROPOSED 400 kV TRANSMISSION POWER LINE FROM THE KOKERBOOM
SUBSTATION TO THE AUAS SUBSTATION, NAMIBIA
SCOPING REPORT
EXECUTIVE SUMMARY
NamPower, the electricity utility of the Republic of Namibia, intends to construct a single-
circuit 400 kV transmission power line from the Kokerboom Substation (near Windhoek)
to the Auas Substation (near Keetmanshoop), a distance of approximately 500 km. The
conductor would be strung onto 45 m high steel pylons placed approximately 500 m
apart. Pylons will be of the cross-rope suspension tower, strain tower or the self-
supporting suspension (open-V) tower design.
The Kokerboom and Auas Substations have been operated by NamPower for the past
37 (with the new section for the 400 kV power line entry being commissioned 17 years
ago) and 17 years, respectively. A 400 kV and a 220 kV transmission power line have
been operational between the two substations for the past 17 and 37 years, respectively.
The existing line infrastructure cannot meet future power requirements and needs to be
supplemented with another transmission power line to ensure system reliability.
Additional benefits include improved network stability and redundancy, improved
network capacity to supply the system demands, improved dynamic stability and lower
network power losses. The proposed new 400 kV power line is being constructed in
order to strengthen Namibia’s overall transmission network. The proposed project needs
to be completed by 2023, or as soon thereafter as possible, to avoid constraints to power
supply.
An application for an Environmental Clearance Certificate was submitted to the
Environmental Commissioner on 20 April 2016. This independent Scoping Assessment
was undertaken and submitted, in terms of the Environmental Management Act, 2007,
(Act No 7 of 2007) and the Environmental Impact Assessment Regulations, 2012.
Given the technical nature of the work, NamPower will invite companies that have
experience and expertise in transmission line construction to tender for the construction
work. The construction period will be approximately twenty four (24) months and it is
likely to proceed on multiple construction fronts. The existing transmission power lines
will remain operational during this period and into the future.
The Environmental Impact Assessment (EIA) for the Kokerboom to Auas transmission
power line assessed the environmental acceptability of constructing and operating the
power line within an identified power line corridor alignment (of approximately 500 km
length and 500 m width [250 m from the proposed centreline], as well as an access road
that is proposed to run parallel to the power line and within the same corridor. The
transmission power line will have a final servitude of 80 m width, with 12 m of that being
cleared for an access track. The access track will be used to bring in construction
materials, as well as to access the power line and its associated pylons for maintenance
purposes, throughout the infrastructure’s life span.
Emphasis within the EIA process (and especially the scoping phase) was placed on the
optimisation of proposed power line corridor route (and its centreline i.e. the position of
power line pylons) as well as cumulative impacts of three power lines within the study
iv Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
area. The initial proposed power line corridor presented to the EIA Team ran parallel to
the existing 220 kV power line, in the northern part, for some of its length. A number of
alternative power line corridors alignments were assessed during scoping. Based on
feedback from the technical specialists, the power line corridor was screened/ scoped
and adapted to avoid biophysical and social receptors. Each successive alternative
alignment put forward for assessment further avoided potential negative biophysical
(e.g. traversing mountains and sensitive avifaunal habitats) as well as socio-economic
impacts (e.g. bisecting land parcels and traversing over areas with incompatible land
uses). Input on the proposed power line corridor and centreline alignment was also
obtained during an extensive public consultation process, which included public
meetings in towns (Keetmanshoop, Tses, Gibeon, Mariental, Kalkrand, Rehoboth,
Dordabis and Windhoek) within the proposed power line corridor. A further amendment
to the proposed power line corridor route was suggested by the avifaunal specialist at
the end of scoping and investigated further in subsequent phases of the EIA.
Alternatives (e.g. ‘no-go’, transmission corridor alignments, technology, methods for
construction and operation, equipment, and mitigation measures) to the proposed
project were considered, and either scoped out or assessed in detail.
This Scoping Report, which documents the scoping assessment, aims to provide a:
Description of the proposed project and its alternatives
Record of the scoping assessment, including the public consultation process
Summary of and feedback on comments received from the authorities, public,
and directly affected and neighbouring landowners; stating how each of the
issues has been addressed
Preliminary assessment of potential environmental impacts and a
Terms of Reference for how these impacts will be assessed in detail, as well as
suggestions for mitigation measures and management actions made to either
avoid or reduce potential negative impacts and enhance positive impacts.
Five independent technical studies informed the scoping assessment, namely an:
Avifaunal Assessment
Vegetation Assessment
Floodline Evaluation
Archaeology Assessment and
Social Assessment.
The results and recommendations from these specialist studies are:
Landuse
The proposed power line corridor comprises Bushveld Savannah vegetation and is
dominated by commercial stock farming, mostly on private land. Further to the north,
large stock farming is dominant while small stock is more prevalent in the south.
Commercial game farms are also encountered.
Avifauna
Over 200 bird species were recorded from 207 survey visits to the nineteen quarter
degree (15’ x 15’) squares traversed by the proposed 400 kV transmission line from
Kokerboom near Keetmanshoop to Auas near Windhoek, drawn from information
contained in Namibia’s Avifaunal Database. The avifaunal assemblages were assessed
v Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
for each of the four vegetation types through which the line is expected to pass. The
number of Threatened and Near Threatened Red Data species range from 8 to 12 for
the four vegetation types while species endemic and near-endemic to Namibia are
confined mainly to the northern section of the transmission line in the Highland Shrubland
vegetation, between Rehoboth and Auas. The number of birds endemic to the south-
west arid zoo-geographic zone of southern Africa range from 33 to 63 with 14 species
having 40% or more of their global populations within Namibia.
Given that the study area is rich in bird species, and that similar infrastructure contributes
to bird injuries and deaths, the potential impacts on birds will be assessed in more detail
during the assessment phase of the EIA. In particular the following potential impacts are
to be assessed during the construction and operational phases, namely the impact of
the infrastructure on bird collision and electrocution; and during the operational phase
only, risks to the proposed infrastructure as a result of bird perching and roosting.
The specialist specifically recommended that two high risk avifauna areas (the Karas
Dwarf Shrubland and the Ecotone between the Dwarf Shrub and Kalahari Savanna near
Kalkrand) be avoided by means of a shifting of the centreline of the proposed power line.
He further recommended that in areas where the existing and the proposed 400 kV
power lines run adjacent and parallel to each other that the pylons be “staggered” to
further reduce unnecessary bird mortalities. This recommendation was supported by an
independent avifaunal specialist, Dr. Rob Simmons, after a site visit. The
recommendations were taken forward into the remainder of the EIA process.
Terrestrial Ecology
The proposed Kokerboom to Auas power line corridor traverses three distinct vegetation
zones, of which the Highland Savanna is the most sensitive, supporting numerous
endemic and/or protected species. However, in that zone most of the species of high
concern occur on the slopes of koppies and mountains, which are largely avoided.
Damage to flora and fauna is predicted to be limited, and of a low significance, if careful
planning and mitigation of collateral damage to the surrounding natural environment is
implemented, both during construction and operation. Potential impact throughout the
proposed power line area will be highest on protected trees, which must be conserved
as far as possible. Given careful placement of pylon sites and strict control of tree
removal and unnecessary collateral damage, as well as uncontrolled wood/ pod
harvesting, the impact on plants could be relatively low. The species of highest concern
is camel thorn (Acacia erioloba).
As a precautionary measure the potential impacts on plants will, however, be assessed
in more detailed during the assessment phase of the EIA. In particular the following
predicted impacts are to be confirmed by means of a desk-top assessment for both the
construction and operational phases, namely the impact of unnecessary collateral
damage due to track proliferation, resulting in high loss of vegetation and increased
visual damage; impact of illegal wood collection; as well as the impact of illegal plant
collection.
Floodline
The proposed power line corridor was sub-divided into three sections related to drainage characteristics, namely:
Section 1 commences at the Kokerboom sub-station and extends north for
approximately 75 km. This section of the powerline traverses the eastern edge
vi Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
of the Fish River catchment. Five catchments of interest drain towards, and cross
the power line route.
Section 2 extends north for a further 210 km up to the town of Kalkrand. This
section of the line runs mainly along the top of the plateau which forms the
eastern border of the Fish River catchment. For most of its length the power line
runs along the watershed that forms the catchment boundary between the Fish
River to the west and the Auob River to the east. Except for two relatively small
catchments there are no drainage areas of interest. The two catchments are the
Dabib and Auob Rivers that flow into the Fish River north of Mariental.
Section 3 extends from Kalkrand northwards to the Auas sub-station over a
distance of approximately 170 km. This section traverses the area with the
biggest challenge related to drainage. The area principally drains from the Auas
Mountains just south of Windhoek. This is also the area with the highest rainfall
within the proposed corridor alignment. The largest catchment is the one that
drains the Oanob River. This is a large catchment with a significant 1 in 100 year
flow magnitude.
The elements of the environment around which the floodline study was centred are
essentially the catchment areas and the streams which they feed. Run-off with return
periods of 50 and 100 years were calculated and the flood levels for the larger
catchments were estimated. There are some significant drainage catchments in the
northern part of the proposed transmission line corridor that may affect the construction
of the proposed power line. Approximately 300 km of the proposed transmission line
corridor alignment will not be affected by flooding. The affected environment has a high
tolerance to disturbance from the envisaged infrastructure.
No negative impacts of a high significance are foreseen, however, during both the
construction and operational phases, erosion could potentially be a problem. As a
precautionary measure, the potential impacts of run-off flows on erosion and of flood
water on the proposed infrastructure will be assessed in more detailed during the
assessment phase of the EIA.
Heritage and Cultural Resources
The proposed power line corridor will traverse a potentially sensitive archaeological
landscape. Pleistocene stone artefact finds are associated with the generally deflated
surface of the Nama Karoo Basin and the retreating scarp line of the Weissrand Plateau.
In confirmation of observations from earlier archaeological surveys the Kalahari
Sandveld and Khomas Hochland are generally associated with younger archaeological
sites related to Holocene occupation of the central arts of Namibia. Previous
archaeological surveys in this area have revealed traces of intermittent human
occupation over the last approximately 400 000 years. Early colonial settlement remains
including graves are a significant feature of this area. The baseline archaeological survey
will locate and document any sites that may be affected by the proposed development
and this will form the basis of a detailed archaeological impact assessment. Most of the
area to be affected by the proposed transmission line project are considered to be of
relatively low archaeological sensitivity.
Negative impacts on archaeological sites may occur during the construction phase.
Potential negative impacts may be mitigated by adjustment of the power line centreline
alignment. Where this is not possible, mitigation to reduce the significance of the impact
could include the use of minimum buffer zones for the positioning of pylons, buffer zones
for deviations in the servitude track, the use of high visibility barrier mesh around the
vii Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
sites during construction, the rehabilitation of the construction phase track used during
the stringing of the transmission line, and detailed documentation as well as possible
excavation of affected archaeological sites.
An Archaeological Chance Finds Procedure will be included in the Environmental
Management Plans (EMPs). This includes guidelines for mitigation of new
archaeological finds that may be made in the course of construction and operation.
Social
The transmission line corridor centreline has been revised to avoid impacts on existing
infrastructure. This realignment has served to avoid and reduce potential negative
impacts of the proposed Project on socio-economic receptors (notably infrastructure).
The potential negative social impacts of the construction phase are expected to be
relatively minor and manageable through effective mitigation.
The positive impact associated with the construction and operation of the proposed
transmission line is the improved transmission network nationally. This impact may serve
to enhance the economy as commercial and private electricity provision becomes more
reliable and consistent potentially enabling business enhancements and a generally
better quality of life. Some direct, indirect and induced employment opportunities will be
created by the Project itself and through procurement spend. Benefits will be limited in
the local area as the successful contractor (to be determined through an open tender
process) is likely to use skilled workers that are already known and trusted by them.
Some short-term contract employment should be available to local people.
The negative impacts linked to the proposed Project are likely to be localised and affect
land owners, land users and tourists differently. Existing agricultural activities will largely
be able to continue unhindered during the construction and operation phases. Planning
and control will be required to minimise disruptions during construction. Tourism
activities may be more sensitive to the construction phase nuisance factors and the
visual intrusion of the line during the operational phase; these could impact on the sense
of place for some receptors. Where the line is visible, specifically from private
residences, some of the land owners and users may also experience a negative effect
on sense of place. The power line may negatively affect farm management in some
cases. The cumulative visual impact and hence the impact on sense of place, and the
cumulative impact on disruption to farm management will be assessed in more detail in
the assessment phase.
The “No-go” alternative (i.e. leave the status quo and do not construct the power line), is
not recommended given the need to strengthen the overall power supply system in
Namibia, as well as the need for NamPower to fulfil its mandate as a national utility.
viii Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
A summary of the predicted impacts, made by the Environmental Assessment
Practitioner, after the scoping assessment for the construction and operation of the
transmission power line between the Kokerboom and Auas Substations within the
identified corridor alignment are:
Environmental Aspect
Project Phase Significance of Potential Impact
without Mitigation
Significance of Potential Impact with Mitigation
Avifauna Construction Low (-) Low (-)
Operation High (-) Low (-)
Flora Construction Low (-) Low (-)
Operation Low (-) Low (-)
Fauna Construction Low (-) Low (-)
Operation Moderate (-) Low (-)
Archaeology and Heritage Resources
Construction Moderate (-) Low (-)
Operation Low (-) Low (-)
Floodlines Construction Low (-) Low (-)
Operation Low (-) Low (-)
Social Construction (Disruption to livelihoods, activities and lifestyles, Destruction or disruption of homesteads and farm infrastructure)
Low-Medium (-) Very Low (-)
Operation (Change of sense of place, Disruption to farm management)
Moderate (-) Low-Moderate (-)
Economic Construction (Employment and procurement)
Low (+) Low-Moderate (+)
Operation (Benefits to the economy)
Low-Moderate (+) Low-Moderate (+)
Note: 1. These findings are from a preliminary assessment and will be confirmed in the
Impact Assessment phase of the EIA through detailed studies. 2. Impacts can be Negative (-), Neutral (*) or Positive (+). 3. The significance of a potential impact is based on the combination of consequence
of the impact and probability of the impact occurring, and defines the level to which the impact will influence the proposed project and/or the environment. It determines whether mitigation measures need to be identified and implemented or whether the resource is irreplaceable and/or the activity has an irreversible impact. Significance is rated as either Low, Moderate (Medium) or High.
The majority of potential environmental impacts of constructing and operating the
proposed transmission power line between the Kokerboom and Auas Substations, that
have been identified in the scoping assessment, do not raise major ‘red flags’ except for
the avifaunal issues. The negative impacts are manageable through effective mitigation
ix Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
and/ or management and the positive impacts will generate long-term socio-economic
benefits. This, however, will be confirmed through detailed studies
As part of the EIA process a public consultation process was undertaken. It aimed to
inform Interested and Affected Parties (I&APs) about the proposed project, the EIA
process and the potential environmental impacts, as well as obtain their views on the
proposed Project. The affected landowners, neighbouring landowners, organs of state
and public, who involved themselves in the environmental process, recognise the need
to strengthen the transmission power line network. There was general support of the
conclusions and recommendations of the scoping assessment as presented at the public
meetings.
Concerns about potential impacts on individual farms and inhabitants were, however, voiced by affected landowners and include:
Concerns over the impacts on avifauna, change of sense of place, long-term
disruption to livelihoods (e.g. high-end tourism) and life (including homesteads
and farm infrastructure) as well as short-term disruption to farm management
(including safety concerns regarding use of gyrocopters near power lines).
Suggestions were made to realign the power line away from established
infrastructure (e.g. landing strips, graves) to minimise/ avoid impacts to
livelihoods, as well as away from habitats that support sensitive avifauna (e.g.
rare and endangered bird breeding sites and from their flight paths) and flora (e.g.
forests). There was also support for the avifaunal specialist’s recommendation to
place the pylons close to the existing pylons, but in a staggered arrangement.
Some landowners were concerned about the cumulative impacts of multiple
power lines within a particular area (e.g. around the Substations).
A number of specific mitigation measures/ management actions were proposed for investigation in the assessment phase.
There was support for the proposed EMPs for the construction and operational phases in order to mitigate potential detrimental impacts.
Public consultation process: request to be registered and informed as the process proceeds.
In conclusion, it is recommended that the following detailed studies be undertaken in the
assessment phase of the EIA:
Assessment of potential impacts on the avifauna, and suggestions for mitigation
of any negative impacts and enhancement of any positive impacts
Assessment of potential impacts on the vegetation, and suggestions for
mitigation of any negative impacts and enhancement of any positive impacts
Assessment of potential impacts of erosion due to water runoff, and potential
impacts of water runoff on the proposed infrastructure, and suggestions for
mitigation of any negative impacts and enhancement of any positive impacts
Assessment of potential impacts on the archaeology and heritage resources, and
suggestions for mitigation of any negative impacts and enhancement of any
positive impacts
Assessment of potential social impacts, and suggestions for mitigation of any
negative impacts and enhancement of any positive impacts
Project specific EMPs for the construction and operational phases will be prepared,
which included all of the proposed management actions/ mitigation measures
recommended in the EIA and its associated public consultation process. These Plans
x Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
shall include an Avifaunal Monitoring Plan for the pre- and post-construction phases as
well as detailed specifications for vegetation and flood management, as well as
archaeological chance finds.
After the Assessment Report has been put out for public review and finalised it will be
submitted to the Environmental Commissioner for review and consideration as to
whether an Environmental Clearance Certificate should be granted. Once a decision is
made, any person aggrieved by a decision made; may on points of law only, appeal
against that decision to the High Court within the prescribed time and in the prescribed
manner.
1 Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
EIA FOR THE PROPOSED 400 kV TRANSMISSION POWER LINE BETWEEN THE KOKERBOOM AND AUAS SUBSTATIONS, NAMIBIA
FINAL SCOPING REPORT
CONTENTS
Chapter Description Page
GLOSSARY OF TERMS, DEFINITIONS AND ABBREVIATIONS 5
1 INTRODUCTION 10
1.1 Background 10
1.2 Environmental Study Objectives 12
1.3 Report Content 14
1.4 Details of the Principal Parties 14
1.5 Environmental Study Approach 15 1.5.1 Methodology 18 1.5.2 Assumptions and Limitations 21
1.6 Policy, Legal and Administrative Framework 22
2 NEED FOR THE PROPOSED PROJECT 24
3 DESCRIPTION OF AFFECTED ENVIRONMENT 25 3.1.1 Climate 26 3.1.2 Terrestrial Ecology 27
(a) Section A (Dwarf Shrub Savanna) 28 (b) Section B (Mixed Tree and Shrub Savanna) 28 (c) Section C (Highland Savanna) 29
3.1.3 Critical Biodiversity Areas 34 3.1.4 Avifauna 35 3.1.5 Floodline 38 3.1.6 Heritage and Cultural Resources 42 3.1.7 Social 46 3.1.8 Administration and Organisation 46 3.1.9 Population Demographics 48
(a) Size and Distribution 48 (b) Sex and Age 49 (c) Language 50
3.1.10 Literacy and Education 50 3.1.11 Economy, Employment and Income 51
(a) Economic Overview 51 (b) Agriculture 52 (c) Tourism 53 (d) Economically Active and Inactive Population 54
2 Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
(e) Income 56 3.1.12 Health and Welfare 57 3.1.13 Infrastructure and Services 59
(a) Water and Sanitation 59 (b) Energy Sources 60 (c) Housing 60
3.1.14 Land Tenure and Management 60 3.1.15 Project Area 61
(a) Farm Status 61 (b) Land Use 64 (c) Infrastructure and Services 64
4 DESCRIPTION OF THE PROPOSED DEVELOPMENT 65
4.1 Alternatives 68
5 POTENTIAL IMPACTS 70
5.1 Identification of Potential Impacts 71 5.1.1 Construction Phase 71 5.1.2 Operational Phase 74 5.1.3 Cumulative Impacts 76
5.2 Mitigation of Impacts 77
5.3 Summary of Identified Potential Impacts 80
6 PUBLIC CONSULTATION PROCESS 84
7 CONCLUSIONS AND RECOMMENDATIONS 86
8 REFERENCES 92
3 Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
FIGURES Figure 1: Project Area showing existing power line network
Figure 2: EIA process flow diagram
Figure 3: Mean annual rainfall for Namibia
Figure 4: Overview of vegetation sections within the proposed power line corridor route
alignment
Figure 5: Section A traverses Dwarf Shrub Savanna vegetation
Figure 6: Section B traverses a mixed tree and shrub savanna on an area of red sandy
dunes interspersed by gravelly valleys
Figure 7: Section C traverses the Highland Savanna, an area of high diversity and
endemism.
Figure 8: Drainage map of the Study Area
Figure 9: Drainage – Section 1
Figure 10: Drainage – Section 2
Figure 11: Drainage – Section 3
Figure 12: The archaeological setting of the proposed Kokerboom to Auas power line
Figure 13: Government system in Namibia
Figure 14: Land tenure map showing freehold and communal areas
Figure 15: Proposed routing of ‘bird-friendly’ deviation of the proposed Auas – Kokerboom
400 kV transmission line
TABLES
Table 1: Species assessed that require mitigation within the proposed power line
corridor.
Table 2: Number of bird species recorded, Red Data species, Namibian endemic and
near-endemic species, and southern African endemics, for the quarter degree
(15’ x 15’) squares in the four vegetation types (of two biomes) traversed by the
proposed Kokerboom to Auas 400 kV transmission line corridor.
Table 3: The local status of Red Data bird species in different sections of the proposed
Kokerboom to Auas 400 kV transmission line corridor
Table 4: The local status of endemic and near endemic birds to Namibia in different
sections of the proposed Kokerboom to Auas 400 kV transmission line corridor.
Table 5: Population size and distribution
Table 6: Vulnerable households
Table 7: Sex and age composition
Table 8: Distribution of first languages spoken at household level
Table 9: Levels of literacy and education
Table 10: Economic activity
Table 11: Primary income sources
Table 12: Health indicators
Table 13: Public infrastructure
4 Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
APPENDICES APPENDIX A: CURRICULUM VITAE OF MRS. JAANA-MARIA BALL APPENDIX B: LOCALITY PLANS APPENDIX C: PHOTOGRAPHS APPENDIX D: FACILITY ILLUSTRATIONS APPENDIX E: PUBLIC PARTICIPATION INFORMATION APPENDIX E1: PROOF OF SITE NOTICE APPENDIX E2: WRITTEN NOTICES ISSUED AS REQUIRED IN TERMS OF THE
REGULATIONS APPENDIX E3: PROOF OF NEWSPAPER ADVERTISEMENTS APPENDIX E4: COMMUNICATIONS TO AND FROM INTERESTED AND AFFECTED
PARTIES APPENDIX E5: MINUTES OF ANY PUBLIC AND/OR STAKEHOLDER MEETINGS APPENDIX E6: COMMENTS AND RESPONSES REPORT APPENDIX E7: COPIES OF COMMENT RECEIVED APPENDIX E8: REGISTER OF INTERESTED AND AFFECTED PARTIES APPENDIX F: COPY OF APPLICATION FOR AN ENVIRONMENTAL CLEARANCE
CERTIFICATE APPENDIX G: TERMS OF REFERENCE FOR THE DETAILED ASSESSMENT APPENDIX H: TECHNICAL SPECIALIST’S REPORTS
- AVIFAUNAL ASSESSMENT SCOPING REPORT – OCTOBER 2015
- VEGETATION ASSESSMENT SCOPING REPORT – SEPTEMBER 2015
- FLOODLINE EVALUATION SCOPING REPORT – SEPTEMBER 2015
- ARCHAEOLOGY ASSESSMENT SCOPING REPORT – SEPTEMBER 2015
- SOCIAL ASSESSMENT SCOPING REPORT – MAY 2016
5 Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
GLOSSARY OF TERMS, DEFINITIONS AND ABBREVIATIONS
Affected
Environment
Those parts of the socio-economic and biophysical
environment impacted on by development
Alternatives A possible course of action, in place of another, that would
meet the same purpose, need and requirements of the
proposal. Alternatives can refer to any of the following but are
not limited hereto: alternatives sites (location) for development,
type of activity, alternative site layouts, alternative designs,
alternative technology (including processes and materials),
operational aspects. In Integrated Environmental Management
the so-called “no action” (‘no go”) alternative may also require
investigation in certain circumstances.
Application An Application for an Environmental Clearance Certificate in
terms of the EIA Regulations (2012).
Assessment The process of collecting, organising, analysing, interpreting
and communicating data that are relevant to the decision.
Assessment
Register
Assessment Register referred to in regulation 27 of the EIA
Regulations (2012).
Catchment area An area of land where surface water from rain, converges to a
single point at a lower elevation, usually the exit of the basin.
Construction
Activity
A construction activity is any action taken by the Contractor,
his subcontractors, suppliers or personnel during the
construction process.
Construction
Phase
The period during which activities pertaining to the preparation
for and the physical construction of the proposed development
take place.
Contractor That main organisation appointed by the Developer, through
the Project Manager (PM), to undertake construction activities
on the site.
Cumulative effect The effect of an activity that in itself may not be significant but
may become significant when added to the existing and
potential effects eventuating from similar or diverse activities or
undertakings in an area.
DEA Directorate of Environmental Affairs
Decommissioning To take out of active service permanently or dismantle partly
or wholly, or closure of a facility to the extent that it cannot be
readily re-commissioned.
6 Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
Developer (or
Project Proponent/
Applicant)
NamPower, the electricity utility of the Republic of Namibia
EAP Environmental Assessment Practitioner who has been
designated by the proponent to manage the assessment
process.
EIA Environmental Impact Assessment
ECD Early Childhood Development
EIR Environmental Impact Report; A report describing the process
of examining the environmental effects of a development
proposal, the expected impacts and the proposed mitigation
measures.
EMP Environmental Management Plan: The EMP for the project
sets out general instructions that will be included in a contract
document for the construction phase of the project. It describes
how activities that may have significant environmental effects
on the receiving environment are to be mitigated, controlled
and monitored. The EMP will ensure the construction activities
are undertaken and managed in an environmentally sound and
responsible manner.
Environment Means the surroundings within which humans exist and that
are made up of:
The land, water and atmosphere of the earth.
Micro-organisms, plant and animal life.
Any part or combination of a) and b) and the interrelationships
among and between them.
The physical, chemical, aesthetic and cultural properties and
conditions of the foregoing that influence human health and
well-being.
Environmental
Specifications (ES)
Instructions and guidelines for specific construction activities
designed to help prevent, reduce and/or control the potential
environmental implications of these construction activities.
EPC Engineering, Procurement, and Construction
Floodline A line on a topographic map which defines the level to which
flood waters will rise for a specified return period.
Flood return period 1 in 50 year flood has a return period of 50 years. Also referred
to as a flood that has an annual probability of exceedance of
2% which is statistically more correct.
7 Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
GDP Gross Domestic Product
GIS Geographical Information System
Gini Coefficient The Gini coefficient indicates the level of concentration of
wealth (0 being an equal distribution and 1 a totally unequal
distribution).
Holocene From 10 000 years ago, continuing
Hydrology The science of collecting and analysing data needed to predict
runoff from a catchment and using the data to determine flows
(normally in m3/s) at a defined point in a stream for different
return periods
I&APs Interested and Affected Parties: In relation to the assessment
of the listed activity includes any person, group of persons or
organisation interested in or affected by an activity, and any
organ of state that may have jurisdiction over any aspect of the
activity.
kV Kilo volts
MET Ministry of Environment and Tourism
Method Statement A written submission by the Contractor to the Project Manager
in response to the Specification setting out the plant, materials,
labour, timing and method the Contractor proposes using to
carry out an activity. The Method Statement shall cover
applicable details with regard to:
Construction procedures.
Materials and equipment to be used.
Getting the equipment to and from site.
How the equipment/material will be moved while on site.
How and where material will be stored.
The containment (or action to be taken if containment is not
possible) of leaks or spills of any liquid or solid material that
may occur.
Timing and location of activities.
Compliance/ non-compliance with the Specifications.
Any other information deemed necessary by the Project
Manager.
m3/s cubic metres per second
My Million years
8 Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
NAD Namibia’s Avifaunal Database
NHC National Heritage Council
OIS Oxygen Isotope Stage
Pleistocene From 2 million years ago to approximately 40 000 years ago
Operational Phase The period following the Construction Phase, during which the
proposed development will be operational. Also known as the
Post-Construction Phase.
PM Project Manager: Appointed firm responsible for overall
management of the construction phase of the project including
the management of all contractors.
PMI Project Management Implementation (a NamPower business
unit)
PPP Public Participation (Consultation) Process: A process referred
to in Regulation 21 of the EIA Regulations (2012), in which
potential interested and affected parties are given an
opportunity to comment on, or raise issues relevant to, specific
matters.
Project This refers to all construction activities associated with the
proposed activities.
PSD Project System Development (a NamPower business unit)
Rehabilitation Rehabilitation is defined as the return of a disturbed area,
feature or structure to a state that approximates to the state
(where possible) that it was before disruption, or to an
improved state.
Scoping Report A document prepared by the proponent (or someone appointed
by them) to present the case for the assessment of an activity
as part of the initial assessment process.
SIA Social Impact Assessment
SHEW Safety, Health, Environment and Wellness
Solid Waste Means all solid waste, including construction debris, chemical
waste, excess cement/concrete, wrapping materials, timber,
tins and cans, drums, wire, nails, food and domestic waste
(e.g. plastic packets and wrappers).
the Act or EMA Environmental Management Act, 2007 (Act No. 7 of 2007).
ToR Terms of Reference: A document which forms part of a
Scoping Report (Appendix G: Terms of Reference for the
9 Kokerboom to Auas Transmission Line EIA Version 1 / March 2018 Scoping Report
Detailed Assessment) and sets out how an impact
assessment must be carried out.
TX Transmission
TXMP NamPower Transmission Management Plan
Kokerboom to Auas Transmission Line EIA 10 Version 1 / March 2018 Scoping Report
1 INTRODUCTION
1.1 Background
NamPower proposes to construct a single-circuit 400 kV transmission power line
(hereafter referred to as the power line) from the Kokerboom Substation (near
Keetmanshoop) to the Auas Substation (near Windhoek), a distance of approximately
500 km. The pylon (tower) height will be approximately 45 m and the distance between
pylons approximately 500 m. The steel pylons proposed are the cross-rope suspension
tower, strain tower or the self-supporting suspension (open-V) tower design. The
transmission line corridor studied between the two substations is 500 m wide and is
referred to as the Study/ Project Area.
There are two existing transmission lines connecting the Kokerboom and Auas
Substations, a 400 kV and a 220 kV line, but this infrastructure alone is considered
inadequate to meet the future demand needs of the country (also refer to Section 4.1).
The existing power line network within the Project Area is shown in Figure 1 below.
Figure 1: Project Area showing existing power line network
Kokerboom to Auas Transmission Line EIA 11 Version 1 / March 2018 Scoping Report
The purpose of the proposed Project is to strengthen the overall transmission network
in Namibia. It is proposed that the line be constructed in approximately 5 - 10 years’
time (i.e. by 2023 or as soon thereafter as possible), and possibly earlier if the Kudu
Gas Project comes on line earlier than is currently expected. NamPower’s
Transmission Master Plan (TXMP) assumes that the proposed Kudu Project will be
constructed and come into operation in 2018/ 2019. The proposed Kokerboom to Auas
400 kV line is part of the Kudu integration solution. The TXMP also indicates that
without the proposed Kudu Project, this transmission line is required based on the last
signed-off power supply scenarios. Without upgrades to the transmission line network
future electricity supply in Namibia will become constrained, and as a result, restrict
development (mining, industrial and residential) and negatively impact quality of life in
the country as a whole.
The proposed transmission power line is for the benefit of the Namibian electricity
transmission backbone and Namibian economy as a whole. It does not serve only the
specific area where the transmission power line is to be constructed. The expected
Namibian electricity load growth together with possible transfer of power northwards,
via the Zambezi Link Interconnector High Voltage DC (HVDC) scheme, requires this
transmission line to be operational. Also, the number of cases where an outage of the
existing 400 kV line can be accommodated (hence relying only on the 220 kV
interconnector from South Africa) is becoming less and less each year as the Namibian
electricity load grows.
The transmission line route (within the proposed power line corridor) has been revised
to avoid impacts on existing infrastructure, as far as possible. NamPower identified a
suitable routing option for the transmission line with input from the environmental
consultants and relevant specialists. The line was realigned several times to avoid and
reduce potential negative impacts of the proposed Project on the environment, and in
particular socio-economic receptors (notably infrastructure) and areas sensitive from
an ecological perspective (Appendices B: Locality Plans and C: Photographs).
The proposed transmission line route runs north from the Kokerboom Substation, which
is 23 km north east of Keetmanshoop, to the Auas Substation near the Hosea Kutako
international airport 30 km east of Windhoek.
The Project Area can be described as Bushveld Savannah and is dominated by
commercial stock farming, mostly on private land. Further to the north, large stock
farming is dominant while small stock is more prevalent in the south. Commercial game
farms are also common.
The proposed power line corridor traverses three (3) regions, namely Khomas, Hardap
and //Karas. Khomas is comprised of 10 constituencies with the capital being
Windhoek. Hardap’s capital is Mariental and comprises six (6) constituencies, and
//Karas has six (6) constituencies with Keetmanshoop as the capital. Khomas region is
one of the most densely populated regions of Namibia; it is home to the national capital,
Windhoek. It is landlocked and centrally located in Namibia. South of Khomas is the
Hardap region and south of Hardap is the //Karas region; both extend across Namibia
(west to east) and together comprise southern Namibia. The potentially affected
Kokerboom to Auas Transmission Line EIA 12 Version 1 / March 2018 Scoping Report
constituencies are: Windhoek Rural, Mariental Rural, Mariental Urban, Rehoboth Rural,
Gibeon, Berseba and Keetmanshoop Rural.
Hardap and //Karas regions are geographically extensive regions with low levels of
population density; large parts of these regions comprise the Namib and Kalahari
deserts. The Project Area is also defined by high levels of poverty, relatively low levels
of access to infrastructure, and poor quality rangelands. Livestock agriculture and game
farming is the most dominant economic sector in the Project Area. The majority of the
employed population derive income as employees. There are no formal settlements
located underneath the proposed power line. The area is used for grazing
(domesticated livestock and game) and some eco-tourism and hunting activities. There
are some private residences and tourist facilities located in close proximity to the
proposed transmission line.
1.2 Environmental Study Objectives
This independent Scoping Study (or scoping assessment) forms part of the
Environmental Impact Assessment (EIA) process undertaken, and which the
documentation emanating there from, will be submitted to the competent authority, The
Directorate of Environmental Affairs: Ministry of Environment and Tourism (MET-DEA),
for consideration and decision-making by the Environmental Commissioner.
According to Section 3(2)(e) of the Environmental Management Act (Act No 7 of 2007)
“assessments must be undertaken for activities which may have a significant effects on
the environment or the use of natural resources." As per the Annexure to the
Government Notice No. 29 of 2012, List of Activities that May Not Be Undertaken
Without Environmental Clearance Certificate, “the erection or construction of facilities
for the commercial transmission and supply of electricity with the exception of power
supply lines of less than 2 km in length” may not be undertaken without an
Environmental Clearance Certificate. As such an Application for Environmental
Clearance was submitted to the Environmental Commissioner on 20 April 2016
(Appendix F: Copy of Application for an Environmental Clearance Certificate).
The study identified a preferred power line corridor alignment, within which an access
track is proposed to run parallel to the power line. The transmission power line will have
a final servitude of 80 m width, with 12 m of that being cleared for the access track. The
track will be used to bring in construction materials, as well as to access the power line
and its associated poles for maintenance purposes, throughout the infrastructure’s life
span. The two substations are not proposed to be expanded or upgraded by NamPower
as part of this proposed project.
The EIA assessed the environmental acceptability of constructing, operating and
maintaining a power line in corridor alignment with a length of approximately 500 km
and width of 500 m (250 m each side of the original proposed centre line). Emphasis
Kokerboom to Auas Transmission Line EIA 13 Version 1 / March 2018 Scoping Report
was placed on the optimisation of the corridor route, as well as cumulative impacts of
three power lines within the Study Area.
This Scoping Study, and its independent technical specialist studies, considered the
potential impacts of constructing and operating (including maintaining) the transmission
power line and its associated infrastructure (i.e. access road) within the identified
transmission line corridor alignment between the Kokerboom and Auas Substations
(Appendix D: Facility Illustrations).
The environmental scoping assessment’s objectives are to assess potential
alternatives, scope the potential issues surrounding the proposed development and
provide an assessment of the potential impacts (negative, neutral or positive) of the
proposed activities, as well as suggest mitigation measures/ management actions to
be implemented to avoid or reduce potential negative impacts. It also makes
suggestions for further studies in the detailed assessment phase.
The decision as to whether to grant Environmental Clearance on the findings,
conclusion and recommendations of the EIA process, or even refuse Environmental
Clearance, will rest with the Environmental Commissioner.
Given the above, the aim of this Scoping Report which documents the Scoping Study
for the proposed construction and operation of a transmission power line between the
Kokerboom and Aussenkehr Substations, is to provide a:
Description of the proposed expansion project
Record of the Scoping process (or Study), including the public consultation
process
Summary of and feedback on comments received from the authorities, public
and directly affected and neighbouring landowners, stating how each of the
issues has been addressed
Preliminary assessment of potential environmental impacts and
Terms of Reference for the assessment phase of the EIA, which includes a
detailed impact assessment and suggestions for mitigation measures and
management actions to either avoid or reduce potential negative impacts and
enhance positive impacts.
In order to achieve this, five independent, technical specialist studies were undertaken
to inform the overall assessment, conclusions and recommendations. The specialists
undertaking each of these assessments is presented in Section 1.4 and their
declarations of independence, as well as experience and qualifications in the front of
their respective Scoping Assessment Reports which are found in Appendix G:
Technical Specialist’s Reports. The findings, conclusions and recommendations of
the studies are summarised within this Scoping Report in Sections 5 and 7.
Kokerboom to Auas Transmission Line EIA 14 Version 1 / March 2018 Scoping Report
1.3 Report Content
The content of this Scoping Report is consistent with the requirements as set out in the
EIA Regulations, 2012, and in summary the Scoping Report contains:
Details and experience of the person who undertook the assessment and
prepared the Report (Declaration of Independence signed by Mrs. Ball and
located above, Section 1.4 below and Appendix A: Curriculum Vitae of Mrs.
Jaana-Maria van der Merwe [nee’ Ball])
Description of the policy, legal and administrative/ institutional framework within
which the proposed project is proposed and is being assessed in relation to
(Section 1.6)
Description of the need and desirability of the proposed project and alternatives
considered (Section 2)
Description of the proposed activity and its alternatives (Section 3)
Description of the proposed site and the proposed activities’ location, as well as
the study area (Section 3)
Detailed description of the environment that may be affected by the proposed
activity and the manner in which the geographical, physical, biological, social,
economic and cultural aspects of the environment may be affected by the
proposed listed activity (Section 3)
Methodology used (Appendix G: Assessment Methodology), as well as the
assumptions and limitations of the environmental study (Section 1.5.2)
Details of the public consultation process conducted in terms of regulation 7(1)
(Section 6, Appendices E1 – E8: Public Participation Information)
Description of the anticipated potential environmental impacts (including
cumulative impacts) (Section 5), which require further assessment in the
detailed assessment phase; and for which a description of recommended
methods and procedures for mitigating these identified negative impacts and
enhancing the identified positive impacts will be made
Terms of Reference for any further studies in the assessment phase or
monitoring (Section 7) and
References (Section 8).
1.4 Details of the Principal Parties
The Project Proponent/ Applicant is NamPower, the Namibian state power utility.
The EIA process is being managed by Lithon Project Consultants (Pty) Ltd and the
appointed independent Environmental Assessment Practitioner (EAP) is Mrs. Jaana-
Maria van der Merwe (nee’ Ball) who is a registered Reviewer and Lead Practitioner
with the Environmental Assessment Practitioners Association of Namibia (EAPAN).
She prepared all the documentation emanating from this process.
Kokerboom to Auas Transmission Line EIA 15 Version 1 / March 2018 Scoping Report
The independent technical specialist studies that were undertaken to inform the
scoping assessment of any potential impacts arising from the proposed development
were undertaken by:
Avifuanal Assessment – Dr. CJ Brown of Sustainable Solutions Trust
Vegetation (botanical) Assessment – Dr. Colleen Mannheimer
Drainage Assessment – Mr. Chris Muir
Social Impact Assessment – Mrs. Kerryn McKune-Desai
Archaeology Assessment – Prof. John Kinahan of Quaternary Research
Services
Their contact details, expertise and experience as well as Declarations of
Independence are found in in the front of their respective Scoping Reports which are
found in Appendix H: Technical Specialist’s Reports.
Mr. Johan van Rensburg was the spatial mapping expert who undertook all
Geographical Information System (GIS) the mapping for the EIA.
1.5 Environmental Study Approach
The EIA will assess the environmental acceptability of constructing, operating and
maintaining a power line from the Kokerboom to the Auas Substation, with a length of
approximately 500 km and width of 500 m (250 m from the centreline) and a final
servitude of 80 m width, with 12 m of that being cleared for an access track. Emphasis
was placed on the optimisation of the power line corridor alignment as well as
cumulative impacts of three power lines within the study area.
A number of alternative power line corridors alignments were assessed during this
scoping assessment. An original power line corridor with a proposed centreline
alignment was presented to the EIA Team and reviewed by the technical specialists.
Based on feedback, the power line corridor was adapted to avoid biophysical and social
receptors. Each successive alternative alignment was screened/ scoped and a new
‘improved’ alternative alignment put forward for assessment that further avoided
potential negative biophysical (e.g. traversing over mountains) as well as socio-
economic impacts (e.g. bisecting land parcels and traversing over incompatible land
uses). The technical specialists assessed a corridor of 500 m wide and approximately
500 km in length.
The ‘no-go’ alternative of not constructing the transmission power line is not a
reasonable and feasible option as the demand for power is continually increasing within
Namibia (Sections 2 and 4.1).
This scoping assessment was undertaken after an initial screening of corridor alternatives, as per Figure 2: EIA Process Flow Diagram overleaf.
Kokerboom to Auas Transmission Line EIA 16 Version 1 / March 2018 Scoping Report
Figure 2: EIA process flow diagram
Kokerboom to Auas Transmission Line EIA 17 Version 1 / March 2018 Scoping Report
The scoping assessment was undertaken in three parts as follows: a) Desktop Study
All available secondary documents were gathered for the Project Area and the
proposed project itself. This information was reviewed and relevant information
extracted. Gaps were identified and every effort was made to fill these gaps during this
phase; where this was not possible, the gaps will be addressed during the Impact
Assessment Phase. The types of secondary documents gathered and reviewed
include:
Previous Scoping and Assessment Reports and associated annexures for
infrastructure in the Study Area
A description of the project activities
Maps and figures
National and local census reports
Biophysical data
Health reports
Economic reports
Studies for similar projects and
NamPower policies, procedures as well as the generic Environmental
Management Programme (EMP) for the construction phase.
b) Field Visits
The EAP and technical specialists visited the project site to undertake their field work
for their scoping assessment between July and October 2015 and in May 2016. They
undertook key informant interviews with NamPower and representatives of the
potentially affected farms; and other Interested and Affected Parties (I&APs). Follow-
up telephonic interviews were undertaken. The objectives of the site visits and
interviews were to:
Meet the project team and the Applicant
Observe the Project Area (notably the proposed project corridor site, the
Kokerboom and Auas Substations and nearby towns and settlements)
Meet selected I&APs and key project stakeholders, including representatives of
the affected farms
Refine the area of influence in consultation with the project team and
NamPower
Verify secondary information gathered and address gaps identified and
Gather additional secondary data and maps.
c) Scoping Report
The results of the field assessment were then written up and incorporated into the
desktop assessment, and documented in this Scoping Report. The technical specialists
were provided with a Scoping Report template. These Scoping Reports were in turn
Kokerboom to Auas Transmission Line EIA 18 Version 1 / March 2018 Scoping Report
used by the EAP to compile this Scoping Report. The Scoping Reports (including this
one) used information gathered from primary and secondary sources to develop an
appropriately detailed baseline description, and to identify the potential impacts to be
further described and assessed in the Scoping Assessment. The Scoping Report was
further informed by additional independent technical input by an avifaunal specialist,
Dr. Rob Simmons of Birds and Bats Limited, who confirmed the assessment findings
and recommendations undertaken by avifaunal specialist Dr. Chris Brown.
Key sections of the Scoping Report include:
A baseline project description (fit for a Scoping)
Scoping of issues
Preliminary identification of potential impacts and
Refinement of the scope of work for the Impact Assessment, including
information gaps.
As part of the environmental study an extensive public consultation process was undertaken in accordance with the EIA Regulations, 2012. This process is documented in Section 6 and Appendix E: Public Participation Information.
1.5.1 Methodology The terms of reference for the independent technical scoping studies is presented below: Avifaunal Assessment
Compile a list of birds known to occur within the four quarter degree squares
(2817Ad, 2817Bc, 2817Cb and 2817Da) from Namibia’s avifaunal database.
Assess this list in terms of Endemic and Red Data species, and species
potentially at risk from electrocution, collision or any other impacts
Assess the list in terms of bird species likely to impact on the proposed
substation.
A field visit to assess the proposed transmission power line corridor site, paying
particular attention to micro-habitat, high-risk species, sensitive and high risk
areas to birds, potential flight path conflict areas, nesting areas and any
potential issues of birds having a negative impact the operation of the
substation.
Submission of an avifaunal scoping assessment report, including a preliminary
assessment of potential impacts and issues.
The Avifaunal Scoping Assessment was based on national long-term bird data
collection projects which are contained within Namibia’s Avifaunal Database
(NAD). The NAD provides data on the occurrence, distribution and relative
abundance of all bird species in Namibia, per 15 min by 15 min (quarter degree)
grid square. A list of bird species recorded in the project area was derived from
the NAD. Each species was then assessed in terms of its Red Data status and
whether it is endemic to Namibia and to southern Africa. This forms the basis
of an assessment of the risk that each species might face as a result of the
Kokerboom to Auas Transmission Line EIA 19 Version 1 / March 2018 Scoping Report
proposed project, based on experiences from surveys of other power
infrastructure in Namibia.
Vegetation Assessment:
By means of a review of relevant information (e.g. published papers and known plant species distribution according to the National Herbarium Database (BRAHMS), identify the plant species and habitats that occur or are thought to occur along the route, with emphasis on those that are valuable from a biodiversity and/or ecological point of view.
Identify areas with sensitive vegetation (species that are endemic, protected, or otherwise of high conservation value) along the proposed route and, where pertinent, explain the value of each site.
Identify relevant national and international guidelines, protocols, legal and permit requirements (if any) to ensure compliance with such.
Undertake a preliminary assessment of potential impacts.
Suggest mitigation and management actions to avoid/ reduce detrimental impacts.
Assess the need for further studies.
Nomenclature in the Vegetation Assessment Report follows Klaassen and
Kwembeya (eds) 2013.
Floodline Evaluation:
Collect available rainfall and run-off data.
Define the floodlines for the larger rivers and their catchments.
Evaluate the proposed project with respect to the risk of possible flooding.
Carry out the hydrological and floodline analysis, and estimate the 1 in 50 and
1 in 100 year flows. This will be done in accordance with the Namibian Drainage
Manual (Roads Authority Manual, 2012).
Provide suggestions for the optimisation of the power line corridor alignment taking environmental constraints into consideration
Undertake a preliminary assessment of the environmental acceptability of constructing, operating and maintaining a power line within the study area.
Indicate mitigation measures to be considered in order to ensure that the power line is constructed and operated in the most sustainable manner.
The information sources for the study were the: Namibia Meteorological
Services, Ministry of Agriculture, Water and Forestry, Namibia Water
Corporation (Pty) Ltd, NamPower and South African Weather Services.
Social Assessment:
Prepare a socio-economic baseline description.
Identify potential socio-economic impacts.
Undertake a preliminary assessment of potential impacts.
Suggest mitigation and management actions to avoid/ reduce detrimental impacts
List information gaps to be filled during the Assessment phase and monitoring
to be undertaken.
The Social Assessment Report was aligned with the principles and
commitments as outlined in The Constitution of the Republic of Namibia, of
Kokerboom to Auas Transmission Line EIA 20 Version 1 / March 2018 Scoping Report
1990, and drew on international best practice (International Finance
Corporation Performance Standards of 2012) to inform social performance and
practice.
The proposed project does not affect any communal land, as such the recently
adopted revised Compensation Policy and Guidelines for Communal Land
Areas in Namibia do not apply.
Archaeology Assessment:
Review of all known archaeological occurrences within the power-line corridors.
Compile GIS files for the archaeology of the corridors, including predicted occurrence of unrecorded occurrences.
Field survey of the power-line corridors with emphasis on areas of predicted archaeological sensitivity.
Submit an assessment report and proposals for mitigation measures including procedures for the handling of chance finds such as human remains discovered in the course of site development work.
The Archaeological Scoping Assessment was based on available field survey
observations from the area surrounding the proposed Kokerboom to Auas
transmission line corridor. No previous archaeological survey or assessment
had been carried out in the area to be directly affected by the power
infrastructure.
The Archaeological Assessment was based on protocols developed for
archaeological assessment in Namibia, intended to take into account the terms
of the National Heritage Act (2004). The study aimed to identify potential
sources of risk posed by the proposed project. These sources of risk are specific
to the archaeology of the area as it is known from existing data and the results
of the additional field survey reported here.
Archaeological Assessment in Namibia follows a basic three-phase process of
evaluation; followed by assessment based on field survey with limited sampling
and including proposals for mitigation of impacts and mitigation, which involves
detailed field investigation, laboratory analysis and the preparation of site
management plans.
The Scoping Assessment was based on existing archaeological survey data,
including archaeological GIS and project design data and the Impact
Assessment phase entailed direct field survey of ground not covered by
previous surveys. Archaeological sites were assessed according to standard
criteria, including the physical setting of the site – mainly with reference to
geological or topographic features; the type of archaeological site; the affinity of
the site – based on a field estimation of the site age and cultural affinity, and
observations, and where pertinent, on the size, density and characteristic
features of the site. Project development activities were evaluated according to
parallel 0 - 5 scales, which allows for independent assessments of significance
and vulnerability.
Kokerboom to Auas Transmission Line EIA 21 Version 1 / March 2018 Scoping Report
1.5.2 Assumptions and Limitations
The assumptions and limitations of this Scoping Assessment are:
The assessment is based on the project information provided at the time of the study. It was assumed that information provided by NamPower is accurate and up to date, and that the technical specifications of the proposed project and site selection are in accordance with the relevant legislative and regulatory requirements.
This Scoping Report and scoping assessment depends on the accuracy of the secondary data. The data was considered sufficient for the purposes of this study.
The contact details of all the key stakeholders were not available at the time of drafting this Scoping Report. As such, some current activities, opinions and concerns have not been incorporated. These will be incorporated into the Assessment Report.
The site visits and technical assessments were carried out between July and October 2015 and May 2016 and are a ‘snap shot’ of the environmental conditions. Birds, for example, are highly mobile and respond rapidly to changing environmental conditions. Most arid-zone animals are nomadic in nature. They may be absent from areas seasonally or for many years when rainfall is low, but very common when conditions are favourable.
The opinions expressed by I&APs during PPP were provided by members of the public who attended the meetings and made verbal or written comment. These opinions are thus peoples’ individual opinions and should not necessarily to be taken to represent the views of all the community members who are based in the Project Area.
The Scoping Report was compiled by the EAP, based on the Scoping Assessments Reports compiled by the technical specialists, as well as Dr. Rob Simmon’s (independent avifaunal specialist of Birds and Bats Limited) recommendations of early 2018.
The technical specialist Scoping Assessments were finalised on: - Avifauna – October 2015 - Vegetation – September 2015 - Floodline – September 2015 - Archaeology – September 2015 - Social – May 2016
All assessments of vegetation sensitivity were made in the context of the nature of this proposed project, which is narrow and linear. These sensitivities would not necessarily apply to the greater area if the impact was broader or more extensive, or if the project was re-routed. The Vegetation Scoping Assessment was a desktop study and no field assessment was undertaken because it was deemed unnecessary by the technical specialist.
The Archaeological Assessment relied on the indicative value of surface finds, augmented by the results of excavations carried out in the Study Area. Based on these data, it is possible to predict the likely occurrence of further archaeological sites with some accuracy, and to present a general statement of the local archaeological site distribution. Since the Archaeology Scoping Assessment is limited to surface observations, it is necessary to caution the proponent that hidden, or buried archaeological remains might be exposed as the project proceeds. A further limitation, regarding the Archaeological Assessment, is that continuing development in the project area will over time
Kokerboom to Auas Transmission Line EIA 22 Version 1 / March 2018 Scoping Report
raise the significance of finds reported here as the extent of undisturbed ground diminishes.
For the Floodline Evaluation Study it was assumed that sufficient rainfall data with the required accuracy will be available for the study area and that the available digital elevation model is sufficiently accurate. The lack of run-off data for the Study Area with which to calibrate the hydrological analysis is a limitation to the Floodline Evaluation Study.
This Social Impact Report and assessment depended on the legitimacy and accuracy of the secondary data, such as Census Data. The data was considered sufficient for the purpose of conducting the assessment.
The Social assessment is based on project information available and provided at the time of the study. Limited information was available about employment, skills development and procurement. This will only be determined once the Engineering, Procurement, and Construction (EPC) Contractor is appointed.
Selected land owners and land users were contacted and interviewed, not all details provided by the Deeds Office were correct and some land owners were unreachable.
Impacts for the construction and operational phases of the project have been predicted and assessed. No assessment has been undertaken for possible decommissioning phase impacts as this is not anticipated.
The environment is dynamic and constantly adapts to changes. Often this makes it challenging to predict project specific impacts as if they happen in a vacuum, uninfluenced by pre-existing conditions.
1.6 Policy, Legal and Administrative Framework
This environmental study is focused on sound environmental management practices
and is based on national and international best practices, and relevant legislation,
policies and guidelines. The following Acts, Ordinances, policies, and conventions were
considered in the preparation of this Scoping Assessment Report and the technical
specialist Scoping Reports:
The Constitution of the Republic of Namibia, 1990
Electricity Act, Act No. 4 of 2007
Nature Conservation Ordinance, 4 of 1975
Nature Conservation Amendment Act, Act No. 5 of 1996
Forestry Act, Act No.12 of 2001
National Development Plan: Vision for 2030
Environmental Management Act, Act No. 7 of 2007
Environmental Assessment Policy for Sustainable Development and
Environmental Conservation, 1995
Convention on Biological Diversity, 1992
Convention to Combat Desertification, 1994
EIA Regulations, 2012 (GN No 28-30, GG No 4878)
Labour Act, Act No. 11 of 2007
Health and Safety Regulations (GN 156/1997)
Public Health Act, Act No. 36 of 1919
Kokerboom to Auas Transmission Line EIA 23 Version 1 / March 2018 Scoping Report
Water Act, Act No. 54 of 1956
Town Planning Ordinance 18 of 1954
Burial Places Ordinance, 27 of 1966
As the Forest Act (Act no. 12 of 2001) has no regulations, the proposed new list of
protected species (S. Loots, Red Data and in situ conservation officer, Namibia
National Botanical Research Institute, pers. comm. by Dr. C. Mannheimer) was applied
in the Vegetation Assessment.
The principal instrument of legal protection for heritage resources in Namibia is the
National Heritage Act (Act No. 27 of 2004). Part V Section 46 of the Act prohibits
removal, damage, alteration or excavation of heritage sites or remains (defined in Part
1, Definitions 1), while Section 48 ff sets out the procedure for application and granting
of permits such as might be required in the event of damage to a protected site
occurring as an inevitable result of development. Section 51 (3) sets out the
requirements for impact assessment. Part VI Section 55 Paragraphs 3 and 4 require
that any person who discovers an archaeological site should notify the National
Heritage Council (NHC).
No regulations have been formulated for the implementation of the National Heritage
Act, and there is no official procedure concerning impact assessment. However,
archaeological impact assessment of large projects has become accepted practice in
Namibia, especially where project proponents need also to consider international
guidelines. The appropriate international guidelines are those of the World Bank OP
and BP 4.11 guidelines in respect of “Physical Cultural Resources” (R2006-0049,
approved April 17, 2006). Of these guidelines, those relating to project screening,
baseline survey and mitigation are the most relevant.
Recent or historical grave sites, their conservation and possible removal where impact
is unavoidable is governed by the Burial Places Ordinance, 27 of 1966. Permits for the
excavation, collection and appropriate deposition of archaeological materials are
issued by the NHC, while permits for the possible removal of recent or historical graves
are issued by the Office of the President.
The list of applicable legislation provided above is intended to serve as a guideline only
and is not exhaustive nor inclusive.
Kokerboom to Auas Transmission Line EIA 24 Version 1 / March 2018 Scoping Report
2 NEED FOR THE PROPOSED PROJECT
The purpose of the proposed Project is to strengthen the overall transmission network
in Namibia. It is proposed that the line be constructed in approximately 5 - 10 years’
time (i.e. before 2026), and possibly earlier if the Kudu Gas Project comes on line earlier
than is currently expected. NamPower’s Transmission Master Plan (TXMP) assumes
that the proposed Kudu Project will be constructed and come into operation in
2018/2019. The proposed Kokerboom to Auas 400 kV line is part of the Kudu
integration solution. The TXMP also shows that without the proposed Kudu Project, this
transmission line is required based on the last signed-off power supply scenarios.
Without upgrades to the transmission line network future electricity supply in Namibia
will become constrained, and as a result, restrict development (mining, industrial and
residential) and negatively impact quality of life in the country as a whole.
The proposed transmission power line is for the benefit of the Namibian electricity
transmission backbone and Namibian economy as a whole. It does not serve only the
specific area where the transmission power line is to be constructed. The expected
Namibian electricity load growth together with possible transfer of power northwards,
via the Zambezi Link Interconnector High Voltage DC (HVDC) scheme, requires this
transmission line to be operational. Also, the number of cases where an outage of the
existing 400 kV line can be accommodated (hence relying only on the 220 kV
interconnector from South Africa) is becoming less and less each year as the Namibian
electricity load grows.
Kokerboom to Auas Transmission Line EIA 25 Version 1 / March 2018 Scoping Report
3 DESCRIPTION OF AFFECTED ENVIRONMENT
The Kokerboom Substation is located approximately 23 km North of Keetmanshoop
and the Auas Substation is located approximately 30 km East of Windhoek near the
Hosea Kutako international airport and farming settlement of Dordabis (refer to
Appendices B: Locality Plan and C: Photographs). The surrounding land use is
mainly game farming.
The Kokerboom Substation is currently connected to the Auas Substation by a 500 km
long 400 kV and 220 kV transmission power lines. The proposed new 400 kV power
line is proposed to run North East from the Kokerboom Substation and enter the Auas
Substation from the South West.
The majority of the proposed project corridor (Project Area) is defined by low population
densities, high levels of poverty, relatively low levels of access to infrastructure, and
poor quality rangelands.
The proposed power line corridor traverses two biomes and four vegetation types, and
crosses a rainfall gradient of about 200 mm, from just under 200 mm in the south to
about 400 mm in the north. The average annual rainfall in the Fish River catchment,
which is typical of the southern and central areas of the proposed corridor, is between
150 and 250 mm. The variations from these values can be considerable. As an
illustration the area experienced rainfall of 675 mm for the big rain year of 1933/34 and
only 45 mm for the drought year 1944.
In the south the transmission line passes through Karas Dwarf Shrubland (Kokerboom
to near Mariental) and across the eastern edge of the Dwarf Shrub Savanna (near
Mariental to Duineveld), both in the Nama Karoo biome. The topography comprises
mainly gravel and rocky undulating plains with low shrubs and grassland. The
transmission line then runs along the western edge of the Southern Kalahari (Duineveld
to near Rehoboth) and into the Highland Shrubland (Rehoboth to Auas), both in the
Acacia Tree-and-shrub Savanna biome. The topography of the Southern Kalahari
comprises wind-blown red kalahari sand forming linear partly vegetated dunes with
grassy inter-dune “valleys”. The land rises in the Highland Savanna to about 1,800 m
and consists of an undulating highland plateau with mountain ranges rising to over
2,500 m. In the Mariental area the line corridor passes near to the Hardap Dam, the
only large water body (a man-made impoundment) near the proposed alignment.
The proposed transmission line corridor traverses three regions (namely Khomas,
Hardap and //Karas). Khomas is comprised of 10 constituencies with the capital being
Windhoek. The potentially affected constituencies are: Windhoek Rural, Mariental
Rural, Mariental Urban, Rehoboth Rural, Gibeon, Berseba and Keetmanshoop Rural.
Hardap’s capital is Mariental and comprises six (6) constituencies, and //Karas has six
(6) constituencies with Keetmanshoop as the capital. Khomas region is one of the most
densely populated regions of Namibia; it is home to the national capital, Windhoek. It
is landlocked and centrally located in Namibia. South of Khomas is the Hardap region
Kokerboom to Auas Transmission Line EIA 26 Version 1 / March 2018 Scoping Report
and south of Hardap is the //Karas region. Both regions are extensive, geographically,
extending across Namibia from west to east. The regions contain the Namib and
Kalahari deserts, and together comprise southern Namibia.
Livestock agriculture is the dominant economic sector in the proposed Project area.
The majority of the employed population derive income as employees (i.e. private,
commercial agriculture and government). There are 89 potentially affected farms within
the Study Area. These are predominantly owned privately (freehold tenure) or by the
state and used as communal land. No formal settlements are traversed by the proposed
centreline. The Study Area is predominantly used for grazing (domesticated livestock
and game) and some eco-tourism and hunting activities. There are some private
residences and tourist facilities located in close proximity to the proposed transmission
line.
3.1.1 Climate The Study Area is characterised by extreme droughts and years of high rainfall. The
average annual rainfall in the Fish River catchment, which is typical of the southern and
central areas of the project area, is between 150 and 250 mm. The variations from
these values can be considerable. Keetmanshoop, with a mean annual rainfall of
150 mm is considerably drier than Windhoek which has a mean annual rainfall of
360 mm. A map of the mean annual rainfall of Namibia is shown in Figure 3 for
Namibia.
The average maximum temperature at Keetmanshoop during the hottest month is 34 -
36°C while in Windhoek it is 32 - 34°C. Temperature averages about 20°C. In summer
temperatures above 40°C are common.
Kokerboom to Auas Transmission Line EIA 27 Version 1 / March 2018 Scoping Report
Figure 3: Mean annual rainfall for Namibia
As a consequence of the climatic conditions described above, wind-blown dust is an
issue throughout Namibia as well as runaway fires, especially during the dry months.
3.1.2 Terrestrial Ecology
The Vegetation Assessment Scoping Report (Appendix H: Technical Specialist’s
Reports) reported that the proposed transmission line corridor traverses four different
vegetation types of two biomes, with varying sensitivity. For distinct vegetation types
exist within the power line corridor, namely:
1. Kokerboom to near Mariental, a distance of about 205 km through Karas Dwarf
Shrubland of the Nama Karoo biome, with the line passing through nine quarter
degree (15’ x 15’) squares;
2. Mariental to Duineveld, a distance of about 100 km through the eastern edge of
Dwarf Shrub Savanna of the Nama Karoo biome, passing through three quarter
degree squares;
3. Duineveld to near Rehoboth, a distance of about 70 km through the western edge
of the Southern Kalahari of the Acacia Tree-and-shrub Savanna biome, passing
through three squares; and
N
Kokerboom to Auas Transmission Line EIA 28 Version 1 / March 2018 Scoping Report
4. Rehoboth to Auas, a distance of about 85 km through Highland Shrubland of the
Acacia Tree-and-shrub Savanna biome, and passing through four squares.
The section of the route from the Kokerboom substation to just north of Mariental
(Section A) traverses the Dwarf Shrub Savanna (Giess 1998), which forms part of the
Nama-Karoo Biome, for approximately 300 km, to approximately 15 km north of
Kalkrand. From there it continues through the Mixed Tree and Shrub Savanna of the
Southern Kalahari for about 55 km (Section B), until it reaches the foothills of the
Highland Savanna, which it traverses for about 100 km before reaching the Auas
substation (Section C). Figures 4 - 7 depict these three sections.
(a) Section A (Dwarf Shrub Savanna)
This zone is characterised by shallow, stony soils that carry a predominance of grasses
and Karoo shrubs (Giess 1998). Sizeable woody species known from that zone are
largely confined to drainage lines and the verges of seasonally wet depressions and
pans, including protected species such as Acacia erioloba, Ziziphus mucronata,
Searsia lancea and Euclea pseudebenus. Protected woody species of a more scattered
distribution in the zone include Aloe dichotoma, Albizia anthelmintica, Boscia albitrunca
and Maerua schinzii. Although 18 endemic and 11 protected species are recorded for
the general area, no species of high conservation concern (range or habitat restricted
endemic or protected species) are presently known or expected to occur in any
meaningful numbers along the route in this vegetation zone. Those recorded there are
all reasonably widespread and very unlikely to be threatened by this proposed project.
However, Aloe dichotoma (Kokerboom, Quiver tree) does occasionally form dense
stands which would make them of concern in that instance. The sensitivity of this
section is Low.
(b) Section B (Mixed Tree and Shrub Savanna)
This is largely an area of red sandy dunes generally slanting from north-west to south-
east interspersed with harder inter-dune valleys with stonier, harder substrates. Harder,
more compact soils are also characteristic of the river banks, and many small pans
(often with clay/calcrete substrates) are scattered throughout the zone. Although only
one wide-ranging endemic herb is recorded from the vicinity of the route, several
protected trees species are common in this vegetation type, including Acacia erioloba,
Albizia anthelmintica, Boscia albitrunca and Maerua schinzii. Ziziphus mucronata is
also typical along rivers and drainage lines. The route east of Tsumis between
approximately 23° 42’ 14” s and 23° 51’ 34” S is of concern regarding the dense stands
of Acacia erioloba and dune areas along this section also support large specimens of
Acacia erioloba and Albizia anthelmintica that are valued by farmers for the shade and
the forage they offer to stock animals. This is valuable woodland that raises the relative
sensitivity of this zone. The sensitivity of this section is Medium to High.
Kokerboom to Auas Transmission Line EIA 29 Version 1 / March 2018 Scoping Report
(c) Section C (Highland Savanna)
This is one of the zones of highest plant diversity and endemism in Namibia. It is a
mixed tree and shrub savanna that includes many protected tree species, such as
Acacia erioloba, Aloe littoralis, Boscia albitrunca, Albizia anthelmintica, Maerua schinzii
and Erythrina decora as well as those typical of drainage lines, ie: Ziziphus mucronata
and Searsia lancea. Thirty six (36) endemic and 9 protected species have been
recorded in the area around the route. Species of potential concern include the
protected trees and a number of other protected and/or restricted range endemics (e.g.
Anacampseros filamentosa subsp. tomentosa, Aloe viridiflora). With the exception of
Acacia erioloba, which occurs in dense stands over much of this section, and other
protected trees that occur as scattered individuals (e.g. Boscia albitrunca, Albizia
anthelmintica), the species of highest concern occur entirely or mostly on high-lying
slopes or at the edges of pans, which are not affected to any large extent by this project.
The sensitivity of this section is High.
An annotated list of species of potential concern is provided within Appendix 1 of the
Vegetation Scoping Assessment Report (refer to Appendix H: Technical
Specialist’s Reports) to give an overview of their extent of occurrence, conservation
status, known occurrence in the vicinity of the proposed route and notes on action
needed regarding this proposed project. Those requiring mitigation are summarised in
Table 1: Species assessed that require mitigation within the proposed power line
corridor. No Red Data species belonging to any threatened category were listed.
Kokerboom to Auas Transmission Line EIA 30 Version 1 / March 2018 Scoping Report
Figure 4: Overview of vegetation sections within the proposed power line corridor route alignment.
(Note the proposed centreline of the power line corridor is indicated by a white line)
Kokerboom to Auas Transmission Line EIA 31 Version 1 / March 2018 Scoping Report
Figure 5: Section A traverses Dwarf Shrub Savanna vegetation.
(Note the proposed centre line of the power line corridor is indicated by a white line)
Kokerboom to Auas Transmission Line EIA 32 Version 1 / March 2018 Scoping Report
Figure 6: Section B traverses a mixed tree and shrub savanna on an area of red sandy dunes interspersed by gravelly valleys.
(Note the proposed centreline of the power line corridor is indicated by a white line)
Kokerboom to Auas Transmission Line EIA 33 Version 1 / March 2018 Scoping Report
Figure 7: Section C traverses the Highland Savanna, an area of high diversity and endemism.
(Note the proposed centreline of the power line corridor is indicated by a white line)
Kokerboom to Auas Transmission Line EIA 34 Version 1 / March 2018 Scoping Report
Table 1: Species assessed that require mitigation within the proposed power line corridor.
Species Conservation
status
Range in
Namibia
Habitat if
restricted
Occurrence in
vicinity of
proposed
route if of
possible
concern
Notes
Acacia
erioloba
Protected Widespread Dense
populations
near Tsumis as
well as
scattered from
just south of
bend point 4 to
the Hohewarte
area, as well as
in riparian
areas alongside
drainage lines
and on dune
areas.
Albizia
anthelmintica
Protected Widespread
Aloe
dichotoma
Protected Widespread,
sometimes in
dense stands
Aloe littoralis Protected Widespread,
sometimes in
dense stands
Boscia
albitrunca
Protected Widespread
Cyperus
rehmii
Endemic Known
distribution
highly
restricted but
almost
certainly
undercollected
Pans,
seasonally
wet areas
Farm
Binsenheim/
Rietfontein
Unlikely to
be affected,
but can
mitigate
Euclea
pseudebenus
Protected Widespread
Maerua
schinzii
Protected Widespread
Ziziphus
mucronata
Protected Widespread
3.1.3 Critical Biodiversity Areas
Areas along the route east of Tsumis, as well as the southern parts of Section C and
the portion south and north of Bend Point 4 carry dense populations of Acacia erioloba.
Kokerboom to Auas Transmission Line EIA 35 Version 1 / March 2018 Scoping Report
However, there are scattered densities of this species over much of the route in
Sections B and C. This species, and other protected species, such as Albizia
anthelmintica, often favour dune areas. It is thus virtually impossible to define a “critical”
area regarding these species without including most of Sections B and C.
Slopes of koppies and mountains in the Highland Savanna (Section C) carry numerous
species of concern and should be avoided as far as possible. At present this habitat is
almost untouched by the proposed route.
Pan verges and banks of rivers and drainage lines are known to harbour higher than
average numbers and sizes of protected woody species, as well as sedges such as
Cyperus rehmii. Although it is very likely that this species is severely undercollected
(most sedges are in Namibia), and may be more widespread and common than is
presently known, the precautionary principle should be followed by avoiding this habitat
for pylon sites. This will also favour the protected trees.
Dense stands of Aloe dichotoma, although rare, may be encountered in the
southernmost extent of the route. They are very easy to identify and, if encountered,
should be avoided for pylon placement. Service tracks should easily be able to
circumvent the majority of individuals, which are usually sufficiently widely scattered.
3.1.4 Avifauna
The Avifaunal Assessment Scoping Report (Appendix H: Technical Specialist’s
Reports and Appendix 1 of the Avifaunal Assessment Scoping Report) reported
that birds often perch on the 400 kV and 220 kV power lines between the Kokerboom
and Auas Substations within the Study Area, making them potentially vulnerable to
electrocution, but also causing flash-overs which impact on power supply.
The proposed 400 kV power line corridor traverses two biomes and four vegetation
types. The Tree-and-shrub Savanna supports a number of near endemic birds to
Namibia, for which Namibia has primary global responsibility. The Nama Karoo and
Acacia Tree-and-shrub Savanna biomes provides the core range of a number of large
cursorial birds such as bustards (e.g. Ludwig’s Bustard and Kori Bustard), korhaans
and Secretarybird which are at high risk from power line collision. These three species
have recently been listed at threatened in Namibia because of high incidents of
mortality on power lines. Other species could also potentially be impacted, including
vultures, eagles and flamingos (e.g. Great Flamingo). Both biomes provide important
habitat for many species endemic to the south-west arid zoo-geographic zone of
southern Africa, with 14 of these species having 40% or more of their global populations
within Namibia. The Highland Shrubland is particularly important for species near-
endemic to Namibia. The proposed transmission line passes near to the Hardap Dam,
the only large artificial impoundment with a significant fish-eating bird population along
the proposed route. Wetland birds often perch on nearby power line support structures,
making them potentially vulnerable to electrocution, but also causing flash-overs which
impact of power supply.
Kokerboom to Auas Transmission Line EIA 36 Version 1 / March 2018 Scoping Report
Specifically within each of the four vegetation types traversed by the proposed
transmission line, the following emerged during the avifaunal scoping assessment:
1. Karas Dwarf Shrubland of the Nama Karoo biome, Kokerboom to near Mariental
(about 205 km, nine quarter degree squares) – 113 bird species from 41 survey
visits (refer to Appendix 1 of the Avifaunal Scoping Assessment Report). Of
these, eight species are listed as “Threatened” or “Near Threatened” in Namibia’s
Red Data book (Simmons et al. 2015). There were no species endemic to Namibia
reported from this section of the proposed line but 41 species are endemic to the
south-west arid zoo-geographic zone of southern Africa (Table 2: Number of bird
species recorded, Red Data species, Namibian endemic and near-endemic
species, and southern African endemics, for the quarter degree (15’ x 15’)
squares in the four vegetation types (of two biomes) traversed by the
proposed Kokerboom to Auas 400 kV transmission line corridor) of which eight
species have 40% or more of their global range within Namibia.
Table 2: Number of bird species recorded, Red Data species, Namibian endemic and near-endemic species, and southern African endemics, for the quarter degree (15’ x 15’) squares in the four vegetation types (of two biomes) traversed by the proposed Kokerboom to Auas 400 kV transmission line corridor.
Section of transmission line
Approx. distance
(km) Biome Vegetation type
No. survey visits No. bird
species
No. Red Data
species
No. Namibia endemic
s
No. southern African
endemics
Kokerboom to Mariental
205 Nama Karoo Karas Dwarf Shrubland
41 113 8 0 41
Mariental to Duineveld
100 Nama Karoo Dwarf Shrub Savanna (eastern edge)
193 200 12 1 63
Duineveld to Rehoboth
70 Acacia Tree-and-shrub Savanna
Southern Kalahari (western edge)
16 117 8 0 33
Rehoboth to Auas
85 Acacia Tree-and-shrub Savanna
Highland Shrubland
57 177 11 7 41
2. Dwarf Shrub Savanna of the Nama Karoo biome, Mariental to Duineveld (about 100
km, three quarter degree squares) – 200 bird species from 193 survey visits (refer
to Appendix 2 of the Avifaunal Assessment Scoping Report). This large species
diversity is influenced by the presence of Hardap Dam and its wetland habitat within
an otherwise arid and semi-arid landscape. Twelve species along this section of
the proposed line corridor are listed as Threatened or Near Threatened, one
species is near-endemic to Namibia and 63 species are endemic to southern Africa
of which 14 have 40% or more of the global range within Namibia.
3. Southern Kalahari of the Tree-and-shrub Savanna biome, Duineveld to near
Rehoboth (about 70 km, three quarter degree squares) – 117 bird species from 16
survey visits (refer to Appendix 3 of the Avifaunal Scoping Assessment
Report). This stretch of line has received the least bird survey work, reflected in the
recorded species diversity. Eight species along this section of the proposed line are
Kokerboom to Auas Transmission Line EIA 37 Version 1 / March 2018 Scoping Report
listed as Threatened. There are no Namibian endemic or near-endemic species
here but 33 southern African endemics of which 10 species have 40% or more of
their global range in Namibia.
4. Highland Savanna of the Tree-and-shrub Savanna biome, near Rehoboth to Auas
(about 85 km, four quarter degree squares) – 177 bird species from 57 survey visits
(refer to Appendix 4 of the Avifaunal Scoping Assessment Report). This section
of the proposed line has 11 Threatened and Near Threatened bird species, six
species near-endemic to Namibia and 41 southern African endemics of which 12
species have 40% or more of their global range in Namibia.
In total 16 species of Threatened and Near Threatened birds have been recorded in
the vicinity of the proposed transmission line (Table 3: The local status of Red Data
bird species in different sections of the proposed Kokerboom to Auas 400 kV
transmission line corridor), one Critically Endangered species, six Endangered, four
Vulnerable and five Near Threatened species.
Table 3: The local status of Red Data bird species in different sections of the proposed Kokerboom to Auas 400 kV transmission line corridor.
Red Data Category
Species Red Data bird status in the Kokerboom to Aus corridor
Kokerboom to Mariental
Mariental to Duneveld
Duineveld to Rehoboth
Rehoboth to Auas
Critically Endangered
Cape Vulture - Rare - -
Endangered
White-backed Vulture Uncommon Uncommon Common Uncommon
Tawny Eagle - Rare Rare Uncommon
Booted Eagle Rare Uncommon - -
Martial Eagle Uncommon Uncommon Uncommon Rare
Black Harrier - Rare - Rare
Violet Wood-Hoopoe - - - Rare
Vulnerable
Greater Flamingo - Rare -
Ludwig’s Bustard Rare Uncommon - -
Secretarybird Uncommon Rare Uncommon Uncommon
Lappet-faced Vulture Rare Rare Common Uncommon
Near Threatened
Marabou Stork - - Rare Rare
Verreaux’s Eagle Common Uncommon - Uncommon
Kori Bustard Common Uncommon - Rare
Rüppell’s Parrot - - Common Uncommon
Sclater’s Lark - Rare - -
Seven near endemic bird species have been recorded in the vicinity of the proposed
line (Table 4: The local status of endemic and near endemic birds to Namibia in
different sections of the proposed Kokerboom to Auas 400 kV transmission line
corridor), all occurring in the section of through the Highland Savanna vegetation type
and only one being recorded from Dwarf Shrub Savanna.
Kokerboom to Auas Transmission Line EIA 38 Version 1 / March 2018 Scoping Report
Table 4: The local status of endemic and near endemic birds to Namibia in different sections of the proposed Kokerboom to Auas 400 kV transmission line corridor.
Species Kokerboom to Mariental
Mariental to Duneveld
Duineveld to Rehoboth
Rehoboth to Auas
Rüppell’s Parrot - - - Uncommon
Violet Wood-Hoopoe - - - Rare
Damara Hornbill - Rare - Rare
Monteiro’s Hornbill - - - Rare
Carp’s Tit - - - Rare
Rockrunner - - - Uncommon
White-tailed Shrike - - - Uncommon
Dr. Simmons (an independent avifaunal specialist who was consulted independently to
the appointed EIA specialist) confirmed that the main habitats where the red data
species were concentrated were as follows:
Two (Red Data) Verreaux’s Eagle Aquila verreauxii nest sites in the first major
Schaap River valley on the farm Volmoed, 13 km west of Dordabis;
Up to 100 (Red Data) White-backed Vultures Gyps africanus reported and
Black-chested Snake Eagles Circaetus pectoralis recorded in the KlipVlei and
Wilderness farms 70 km and 135 km south of Auas Substation; and
Threatened Ludwig’s Bustard Neotis ludwigii mortalities on the existing 400 and
220 kV lines occurred throughout, but were highest in the open (Karas Dwarf)
shrubland in the south – particularly in open gravel/grassy plains areas and
particularly under 400 kV lines.
3.1.5 Floodline
The Floodline Evaluation Scoping Report (Appendix H: Technical Specialist’s
Reports) reports that the elements of the environment around which the floodline study
was centred are essentially the catchment areas and the streams which they feed.
There are some significant drainage catchments in the northern part of the proposed
transmission line corridor that may affect the construction of the proposed power line.
Approximately 300 km of the proposed transmission line corridor alignment will not be
affected by flooding. The affected environment could thus be categorised as having a
high tolerance to disturbance from the envisaged infrastructure.
Apart from the five border rivers, namely the Kunene, Okavango, Linyanti and Zambezi
Rivers in the north and Orange River in the south, there is no river in Namibia that
conveys water throughout the year. The largest river in the interior is the Fish River,
which is impounded by the Hardap Dam near Mariental. Even this river flows only a few
weeks to some months in the year. Nevertheless, considerations related to floods are
decisive in estimating extreme flows in the ephemeral rivers which prevail in the study
area.
A drainage Map of the Study Area is shown in Figure 8.
Kokerboom to Auas Transmission Line EIA 39 Version 1 / March 2018 Scoping Report
The study area is characterised by extreme droughts and years of high rainfall. The
average annual rainfall in the Fish River catchment, which is typical of the southern and
central areas of the project area, is between 150 and 250 mm. The variations from
these values can be considerable. As an illustration the area experienced rainfall of 675
mm for the big rain year of 1933/34 and only 45 mm for the drought year 1944.
Runoff values show an even stronger variation than the rainfall values. Variations in the
annual water flows measured in the Fish River vary between 1 x 106 and 1 000 x 106.
Namibia may be a very dry country, but it is in general not a country with low flood
runoff. High intensity rainfall often falls in a very short time and catchments also run off
in a short time. This results in steep flood waves with high peak values. A reasonably
reliable estimate of floods requires the availability of rainfall and runoff values. While
there is a reasonable record of rainfall measurements, runoff measurements are
scarce.
Figure 8: Drainage map of the Study Area
Kokerboom to Auas Transmission Line EIA 40 Version 1 / March 2018 Scoping Report
It should be noted that the proposed centreline of the proposed 400 kV line does not
traverse the Fish River catchment. However, the existing 400 kV line does.
For purposes of describing the affected environment, the route was sub-divided into
three sections, with differing drainage characteristics (Figures 9 – 11):
Section 1 commences at the Kokerboom sub-station and extends north for
approximately 75 km. This section of the powerline traverses the eastern edge of the
Fish River catchment. Five catchments of interest drain towards, and cross the power
line route.
Section 2 extends north for a further 210 km up to the town of Kalkrand. This section
of the line runs mainly along the top of the plateau which forms the eastern border of
the Fish River catchment. For most of its length the power line runs along the watershed
that forms the catchment boundary between the Fish River to the west and the Auob
River to the east. Except for two relatively small catchments there are no drainage
areas of interest. Within this section the two catchments are the Dabib and Auob Rivers
that flow into the Fish River north of Mariental.
Section 3 extends from Kalkrand northwards to the Auas sub-station over a distance
of approximately 170 km. This section traverses the area with the biggest challenge
related to drainage. The area principally drains from the Auas Mountains just south of
Windhoek. This is also the area with the highest rainfall within the proposed corridor
alignment. The largest catchment within this section is the one that drains the Oanob
River. This is a large catchment with a significant 1 in 100 year flow magnitude.
Figure 9: Drainage – Section 1
Kokerboom SS
25 km
N
Kokerboom to Auas Transmission Line EIA 41 Version 1 / March 2018 Scoping Report
Figure 10: Drainage –Section 2
Figure 11: Drainage – Section 3
100 km
Auas SS
Kalkrand
25 km
N
N
Kalkrand
Kokerboom to Auas Transmission Line EIA 42 Version 1 / March 2018 Scoping Report
3.1.6 Heritage and Cultural Resources
The Archaeological Assessment Scoping Report (Appendix H: Technical
Specialist’s Reports) reports that due to its aridity, southern Namibia presents a
marginal environment for human occupation, and in the past, particularly during periods
of climatic cooling and hyper-aridity, the region may have been quite inimical to
settlement. These conditions are reflected in the available archaeological evidence,
which spans the last 0.8 million years with a sequence that is characterized by short
periods of relatively intensive occupation, and long periods in which there appears to
have been little or no human presence.
The regional sequence may be simplified as follows:
Early to mid-Pleistocene (ca. 2my to 0.128my; OIS 6, 7, 19 &c): represented by
surface scatters of stone tools and artefact debris, usually transported from
original context by fluvial action, and seldom occurring in sealed stratigraphic
context.
Mid- to upper Pleistocene (ca. 0.128my to 0.040my; OIS 3, 4 & 5a-e):
represented by dense surface scatters and rare occupation evidence in sealed
stratigraphic context, with occasional associated evidence of food remains.
Late Pleistocene to late Holocene (ca. 0.040my to recent; OIS 1 & 2):
represented by increasingly dense and highly diverse evidence of settlement,
subsistence practices and ritual art, as well as grave sites and other remains.
Historical (the last ca. 250 years): represented by remains of crude buildings,
livestock enclosures, wagon routes and watering points. Some evidence of
trade with indigenous communities, including metals, ceramics and glass
beads.
For the most part, early to mid-Pleistocene sites are associated with pans, outwash
gravels, drainage lines and river gravels. These sites are difficult to detect and are
usually overlooked in the course of construction work. Mid- to upper Pleistocene sites
occur in similar contexts to the earlier material, but hill foot-slopes and outcrops of rock
suitable for artefact production (e.g. chert, fine-grained quartzites) are also focal points.
Late Pleistocene to late Holocene sites occur in almost every terrain setting, with the
exception of very steep slopes and mountain tops. These sites often exhibit locally
integrated distribution patterns which allow some reconstruction of land-use and
subsistence. Major sites include rock shelters with well stratified occupation deposits,
containing an array of organic and inorganic residues. Early historical sites tend to be
concentrated along routes suitable for wagon transport, and a more recent, broader
landscape distribution associated with the establishment of farming settlement.
Southern and central Namibia is the area to be affected by the planned Kokerboom to
Auas power line project and is not well studied archaeologically, but the small number
Kokerboom to Auas Transmission Line EIA 43 Version 1 / March 2018 Scoping Report
of field surveys that have been carried out indicate that the archaeological sequence
as set out in the previous section is represented over the whole of southern and central
Namibia. The physical setting of the known archaeological sites while focussed on the
main river valleys, also emphasizes the higher and mid- slopes of the hill, as well as a
number of localized resources such as small springs and outcrops.
The most detailed available data for the area to be affected by the proposed Kokerboom
to Auas power line project comes from an archaeological survey of the route for the
existing 200 kV line carried out in 1999 (QRS Report 14) (Figure 11: The
archaeological setting of the proposed Kokerboom to Auas power line).
Figure 12: The archaeological setting of the proposed Kokerboom to Auas power line.
Note: Yellow squares are precise locations of archaeological sites recorded during the survey of the existing
power-line); green squares are low precision data gleaned from the archaeological accessions register of the
National Museum of Namibia. The latter sites have a relative precision of 5 km.
Kokerboom to Auas Transmission Line EIA 44 Version 1 / March 2018 Scoping Report
At the time of that survey very little was known of the archaeology of central and
southern Namibia in the affected area and for that reason a detailed foot survey was
carried out over the entire 714 km distance from Aries on the Orange River, to Auas.
The survey located and described a total of 189 archaeological sites covering the last
two million years of human occupation. More importantly, however, the survey helped
to define the most sensitive landscape contexts that would require detailed assessment
for new projects.
Pre-Quaternary (<2my):
The previous survey examined a number of exposures of Palaeozoic shale beds in the
area near the existing Kokerboom Substation. These included fossiliferous Ecca
Whitehill and Prince Albert formations. Other sites of palaeontological potential located
in the course of the survey were associated with the Zamnareb member of the Nababis
formation at the crossing of the Packriem River. Overall, the survey route was
considered to have very low palaeontological potential.
Mid- to late Pleistocene (1 million to 40 000 years):
Archaeological sites dating to the second half of the Pleistocene formed a major
component of the survey results, although most were dispersed scatters with very low
artefact densities, or isolated finds. The 68 mid- to late Pleistocene sites comprised
36% of all archaeological sites. In some area, particularly those least affected by active
drainage and wind-blown sand cover, these sites accounted for up to 53% of all finds.
Mid- to late Pleistocene sites were very strongly associated with outcrops of rock types
such as fine-grained quartzites which are suitable for the manufacture of stone artefacts
and the presence of these sites is therefore to some extent predictable.
Of particular interest is the fact that no mid- to late Pleistocene sites were found north
of 23° South latitude. This was considered to be a reflection of the relatively youthful
drainage systems in the central highland area, associated with steep stream gradients,
sharply defined bank profiles and heavy boulder and pebble loads. Although the overall
distribution pattern of these sites was informative it is relevant to the present scoping
exercise that only two of the sites were found to be in a stratigraphically sealed context
where further investigation might be justified. The survey concluded that the power-
line project would have very little impact on the archaeological record of this period.
Late Pleistocene to early Holocene (40 000 years to 5 000 years):
Reliable identification of late Pleistocene material requires the presence of specific
diagnostic artefact evidence which is frequently lacking from dispersed scatters such
as are characteristic of this area. Identification in the field is therefore based on intuitive
assessment or core size, flaking patterns and indications of retouch. As a provisional
estimate, sites of this period comprised 19% of finds over the entire survey, with some
significant local concentrations such as in the areas of Tses and Kokerboom where
Late Pleistocene to early Holocene sites comprised about 40% of all finds. As with the
Mid- to late Pleistocene component of the sequence, very few sites were found north
of 23° South latitude. Of particular relevance to the present scoping exercise is a
consistent association of late Pleistocene to early Holocene sites with small pans and
related endoreic drainage features. Only two sites of this period were considered to be
important to the archaeological record of this period, both associated with pan features.
Kokerboom to Auas Transmission Line EIA 45 Version 1 / March 2018 Scoping Report
Late Holocene to recent pre-colonial (5 000 years to 250 years):
The previous survey yielded a total of 75 Late Holocene to recent pre-colonial sites,
comprising approximately 40% of all sites. The prominence of this group is underlined
by the fact that this period represents approximately 0.5% of the time-span of the
archaeological sequence. The group included a total of 21 suspected burial sites,
including a number of large, elaborately constructed examples that probably represent
elite burials. However, most of the suspected burials were relatively informal stone
cairns, usually located on stream terraces or other substrate that would be suitable for
the excavation of a grave shaft. The burial sites are considered to be highly sensitive.
In addition to the suspected burial sites, the survey located a number of large stone
cairns along natural routes of access between drainage basins or across watersheds.
These marker cairns are well known throughout Namibia and although they usually do
not contain burials, they do provide important evidence of human movement.
Associated with these suspected routes were the remains of several nomadic pastoral
encampment sites. These consist of several rings of anchor stones, usually with a
diameter of about 5m marking the perimeter of a portable mat hut. These structures
were widely used in southern Namibia until the early colonial era when nomadic
movement ceased.
The previous survey located a number of rock painting and rock engraving sites in the
area to the north of 23° South latitude. These are considered especially important under
Namibian heritage regulations. Rock art sites were in some instances associated with
small rock shelters with sealed deposits of occupation debris. These are also
considered important although their value is usually not apparent prior to test
excavation. Rock shelter deposits with rock art are uncommon, however, and only two
examples were located during the survey.
Colonial (250 years to present):
In southern Namibia the colonial period effectively begins at the end of the eighteenth
century when missionary settlement and regular contact with the Cape Colony and the
outside work were established. By the end of the nineteenth century colonial settlement
and communications networks covered the whole of the central and southern parts of
the country and anti-colonial uprisings had begun in several areas. The proposed
Kokerboom to Auas power line route traverses a region which saw several outbreaks
of fighting, culminating with the South African invasion in 1915. The area contains
numerous relics of this period and the previous survey located several fortifications,
early settler farm sites, wells and military bivouac sites. The survey also located a
number of early colonial quarry and small-scale mining sites.
On the basis of the available evidence, the transmission power line corridor area is
fairly certain to contain some archaeological sites. These will in all likelihood include
mid- to late Holocene pre-colonial and early colonial sites. There is a high likelihood
that the project area will contain graves and that these may require some mitigation
work prior to the construction phase of the project. On the whole, however, the survey
of the project area is not expected to yield high densities of archaeological sites.
Kokerboom to Auas Transmission Line EIA 46 Version 1 / March 2018 Scoping Report
Nevertheless the precautionary principle should be applied as the greater area is rich
in archaeological sites.
The generally open and unobstructed character of the terrain over most of the proposed
Kokerboom to Auas power line route means that archaeological sites are highly visible
and easy to locate. Archaeological survey in such conditions usually provides excellent
results with high levels of confidence. On the other hand, this sort of terrain is highly
sensitive to physical disturbance, thus affecting the preservation of archaeological
remains, and highly sensitive to visual impact on the landscape setting of the
archaeology. Under Namibian law National Heritage Act 27 of 2004) archaeological
remains and their physical setting are both protected. In view of these two
considerations, the study area has potentially a “low tolerance” to disturbance.
In the light of the evidence found during the previous survey, a field survey of the
proposed Kokerboom to Auas power line route is expected to yield the following results:
1. Pre-Quaternary palaeontological evidence in insignificant quantity and mainly in the
vicinity of Palaeozoic shale outcrops near Kokerboom
2. Generalized occurrence of mid- to late Pleistocene artefact scatters primarily to the
south of 23° South latitude
3. Generalized occurrence of late Pleistocene to early Holocene artefact scatters
primarily to the south of 23° South latitude
4. Moderately high density of late Holocene to recent pre-colonial archaeological sites
throughout the extent of the power-line route, including burial cairns and remains of
nomadic pastoral encampments, as well as possibly some rock art sites and rock
shelter sites containing sealed occupation debris
5. Generalized occurrence of colonial era sites, including farm settlements, battlefield
sites and related remains.
3.1.7 Social
The Social Assessment Scoping Report (Appendix H: Technical Specialist’s
Reports) reports that the proposed transmission line corridor traverses three (3)
regions (namely Khomas, Hardap and //Karas). Khomas Region is centrally located
and landlocked; it has a population density of 9.3 people per km². Hardap has a low
population density of 0.7 people per km2. The //Karas Region is the most southern and
largest region in Namibia, with an area of 161,215 km²; it is the least densely populated
of Namibia’s 14 regions with only 0.5 people per km². The line passes through 6
constituencies, the majority of which are rural.
3.1.8 Administration and Organisation
Namibia has a three-tier system of governance comprising of central government,
regional councils and local authorities; the Decentralisation Policy of Namibia was
launched in 1998. The aim of decentralisation is to enable:
Economic, cultural and socio-economic development;
Broad public participation in decision-making; and
Kokerboom to Auas Transmission Line EIA 47 Version 1 / March 2018 Scoping Report
Democracy - based on National ideals and values1.
Local authorities are established in urban areas and are responsible for service
delivery. Municipal councils (2 types), town councils and village councils are
responsible for governing the affairs of the local authorities. Regional councils are
responsible for specified service delivery in rural areas. The 14 Regional Councils run
the regions; Municipal, Town and Village Councils are not sub-ordinate to them2.
Figure13: Government System in Namibia presents the government system in
Namibia.
Figure 13: Government system in Namibia
CENTRAL GOVERMENT
President, prime minister, other ministers Parliament:
National Assembly National Council
REGIONAL GOVERMENT
14 Regions Regional council
Governor
PART 1 MUNICIPALITY
Municipal council
PART 2 MUNICIPALITY
Municipal council
TOWN
Town council
VILLAGE
Village council
Source: Adapted from Peltola 2008, in Local Government System in Namibia, 2009.
To make provision for the direct involvement of the community, Statutory Development
Committees were established. These committees are responsible for identifying
problems and needs of their specific constituencies; their specific functions include the
coordination of planning and development within the constituencies. Statutory
Development Committees operate at regional and local levels and are focused on the
region, the regional constituencies, the local authority, village and settlement. Although
each is composed differently, they are constituted to involve elected members,
traditional authorities and representatives from non-governmental and community-
based organisations3.
1 Local Government System in Namibia, 2009. 2 Local Government System in Namibia, 2009. 3 Local Government System in Namibia, 2009.
Kokerboom to Auas Transmission Line EIA 48 Version 1 / March 2018 Scoping Report
3.1.9 Population Demographics
(a) Size and Distribution
Table 5: Population size and distribution, 2011
Indicator Namibia Khomas Hardap //Karas
2011 2001 2011 2001 2011 2001 2011 2001
Total population 2,113,077 1,830,330 342,141 250,262 79,507 68,249 77,421 69,329
Annual growth rate 1.4 2.6 3.1 1.9 1.5 0.3 1.1 1.1
Population density
(persons/km2)
2.6 2.1 9.2 6.8 0.7 0.6 0.5 0.4
% Urban 43 33 95 93 60 28 54 54
%Rural 57 67 5 7 40 72 46 46
# of Households 464,839 346,455 89,438 58,580 19,307 15,039 21,283 16,839
Household size 4.4 5.1 3.7 4.2 4.0 4.4 4.2 4.7
Source: Population and Housing Census Main Report (2013), Population and Housing Census: Khomas Regional
Profile (2014), Population and Housing Census: Hardap Regional Profile (2014), and Population and Housing Census:
//Karas Regional Profile (2014).
Table 5: Population size and distribution provides an overview of the population size
and distribution in Namibia, and the affected regions in 2001 and 2011. The national
population grew steadily to ~2.1 million in 2011, an average 1.5% per annum increase
since 2001. The majority of the population reside in rural areas (57%), and the
remaining 43% live in urban centres. There are high rates of rural-urban migration in
Namibia; since 2001, the urban population grew by ~50% and the rural population
decreased by ~1.5%.
With a population of 342,141, Khomas accounts for 16% of Namibia’s total population.
Khomas is significantly more populated than Hardap and //Karas which comprise 3.8%
and 3.7% of the national population, respectively. The total population in all regions has
increased consistently overtime; Khomas had a significantly higher population growth
rate than Namibia, Hardap and //Karas between 2001 and 2011. Differing from the
national distribution, the majority of the population in all 3 regions reside in urban
centres; 95% in Khomas, 60% in Hardap and 54% in //Karas.
The average population density in Namibia is 2.6 people/ km2, this is low but it is
significantly higher than Hardap and //Karas regions which have densities of 0.7% and
0.5%, respectively. Khomas is more densely populated with 9.2 people/ km2. In the
project-affected constituencies, the population density is even lower; ranging from
0.2 people/km2 in Gibeon to 0.6 people/km2 in Windhoek Rural.
Between 2001 and 2011, household size has reduced across the project affected area.
National level household size is the largest (4.4 people), followed by //Karas
(4.2 people), Hardap (4 people) and then Khomas (3.7 people).
Kokerboom to Auas Transmission Line EIA 49 Version 1 / March 2018 Scoping Report
Households headed by females, children and orphans are considered to be vulnerable;
in the project area there are a small percentage of these, as outlined in Table 6:
Vulnerable Households.
Table 6: Vulnerable households, 2011
Namibia Khomas Hardap //Karas
Female headed households 43.8 38.8 36.4 37.1
Child headed households 1.7 1.1 1.2 1.1
Orphan headed households 0.6 0.4 0.6 0.4
Source: Population and Housing Census Main Report (2013), Population and Housing Census: Khomas Regional
Profile (2014), Population and Housing Census: Hardap Regional Profile (2014), and Population and Housing Census:
//Karas Regional Profile (2014).
(b) Sex and Age
Table 7: Sex and Age Composition shows the sex and age composition of the
population in the potentially affected project area. The distribution of men and women
varies across the affected area and over time. There are more females than males in
Namibia and in Khomas at 52% and 50.4%, respectively. In Hardap and //Karas there
were more males (51% each) than females (49% each) in 2011. The dominance of
mining in these regions may account for the elevated number of males.
The Namibian population is relatively young with 37% of people below the age of
15 years. Khomas, Hardap and //Karas have a smaller portion of people below the age
of 15 years (27%, 32% and 30%, respectively); at the constituency level, there are
slightly more people in this age category, however still fewer than a the national level.
The majority of the population in Namibia, Khomas, Hardap and //Karas are of working
age (between the ages of 15 and 59 years); Khomas and //Karas have a particularly
high percentage of people of working age at 69% and 63%, respectively. The high
percentage of working age people in the region may indicate that people migrate to the
area for work opportunities or that younger and older people migrate out of the area
(particularly //Karas) for schooling and care facilities. However, in the project affected
constituencies, the percentage of working age people are far lower (62% in Windhoek
Rural to 53% in Berseba.
Kokerboom to Auas Transmission Line EIA 50 Version 1 / March 2018 Scoping Report
Table 7: Sex and age composition, 2011
Indicator Namibia Khomas Hardap //Karas
2011 2001 2011 2001 2011 2001 2011 2011
Total Population 2,113,077 1,830,330 342,141 250,262 79,507 68,249 77,421 69,329
% Male 48 49 49.6 50.6 51 50.6 51 58
% Female 52 51 50.4 49.4 49 49.4 49 42
Sex ratio: Males/ 100
females
94 94 98 103 104 103 104 114
Age composition (%)
Under 5 years 14 13 11 11 11 13 11 11
5-14 years 23 26 16 18 21 23 19 20
15-59 years 57 52 69 67 59 55 63 63
60+ years 7 7 4 4 7 8 6 6
Source: Population and Housing Census Main Report (2013), Population and Housing Census: Khomas Regional
Profile (2014), Population and Housing Census: Hardap Regional Profile (2014), and Population and Housing Census:
//Karas Regional Profile (2014).
(c) Language
The main languages spoken in households differed significantly nationally and across
the 3 regions (see Table 8). In Namibia and Khomas, Oshiwambo languages were by
far the most commonly spoken first language (~49% and ~41%, respectively). In
Hardap, Nama/Damara and Afrikaans were almost equally as dominant at ~43% and
41%, respectively. While in //Karas there were 3 fairly dominant first languages, namely
Afrikaans (~36%), Oshiwambo languages (27%), and Nama/Damara (24%).
Table 8: Distribution of first languages spoken at household level, 2011
Namibia Khomas Hardap //Karas
Oshiwambo languages
(~49%)
Oshiwambo languages
(~41%) Nama/Damara (~43%) Afrikaans (~36%)
Nama/Damara (11%) Afrikaans (~18%) Afrikaans (41%) Oshiwambo languages
(27%)
Afrikaans (10%) Nama/Damara (~12%) Oshiwambo languages
(~10%) Nama/Damara (24%)
Otjiherero languages (9%) Herero languages (~10%)
Kavango languages (9%) English (~9%)
Source: Population and Housing Census Main Report (2013), Population and Housing Census: Khomas Regional
Profile (2014), Population and Housing Census: Hardap Regional Profile (2014), and Population and Housing Census:
//Karas Regional Profile (2014).
3.1.10 Literacy and Education
Table 9: Levels of literacy and education presents selected statistics reflecting levels
of literacy and education in the affected project area. In 2011, literacy rates in people
aged 15 years and older were 97% in Khomas and //Karas, and 91% in Hardap. Hardap
and //Karas saw a significant increase in literacy from 2001. These rates are higher
Kokerboom to Auas Transmission Line EIA 51 Version 1 / March 2018 Scoping Report
than the national rate of 89%. Literacy levels at the constituency level are lower than
the regional levels (specifically in Hardap), they are closely aligned with the national
literacy level. At a national and regional level, adult literacy was higher in urban areas
than in rural areas and there was little difference between males and females. Youth
literacy (15-24 years) was highest in //Karas (99%), followed by Khomas (98%), then
Hardap (96%); the national average was 94%, similar to the constituencies.
Approximately 13% of children aged 0-4 years attended early childhood development
programmes (ECD) (ie. pre-primary school/ kindergarten) in Namibia. This number was
significantly higher in urban areas (~19%) than in rural areas (~10%). Slightly more girls
than boys were enrolled in ECD programmes in both rural and urban areas. In Khomas,
nearly 23% of children attend pre-primary school; with a significantly higher rate of
attendance in the urban areas. Approximately 18% of children in //Karas attend pre-
primary, with a slightly higher percentage in the urban areas. A low percentage of
children are enrolled into ECD programmes in Hardap region (~7%).
At the national level, a high percentage of the population have no or incomplete Primary
school education (25%). At the regional level, Hardap has the highest proportion of
people with incomplete Primary education (~34%), followed by //Karas (~19%) and
Khomas (~17%). The majority of the population have completed Primary school
education as their highest qualification (~49% in Namibia, 39% in Khomas, 43% in
Hardap, and ~54% in //Karas). The population of Khomas have attained the highest
levels of education; ~31% have completed secondary schooling and 13% completed
tertiary level education.
Table 9: Levels of literacy and education, 2011
Indicator Namibia Khomas Hardap //Karas
2011 2001 2011 2001 2011 2001 2011 2011
Literacy rate, 15+ years (%) 89 81 97 96 91 83 97 87
ECD attendance, 0-4 years (%) 13.3 - 22.9 - 7.3 - 16.9 -
Urban 19.4 - 23.7 - 8.1 - 18.2 -
Rural 9.8 - 8.7 - 6.2 - 15.2 -
Highest education level, 15+ years (%)
No formal education 1.5 - 0.8 - 1 - 0.7 -
Incomplete Primary 23.7 - 16 - 33.4 - 18.7 -
Complete Primary 48.5 - 39 - 43 - 53.9 -
Complete Secondary 20.5 - 31.2 - 19.9 - 22.9 -
Complete Tertiary 5.8 - 13 - 2.7 - 3.8 -
Source: Population and Housing Census Main Report (2013), Population and Housing Census: Khomas Regional
Profile (2014), Population and Housing Census: Hardap Regional Profile (2014), and Population and Housing Census:
//Karas Regional Profile (2014).
3.1.11 Economy, Employment and Income
(a) Economic Overview
The Gross Domestic Product (GDP) of Namibia has grown in excess of 5% per annum
since 2010, with the latest GDP growth accelerating to 5.3% for 2014. Strong
Kokerboom to Auas Transmission Line EIA 52 Version 1 / March 2018 Scoping Report
construction and mining sector activities have been the primary drivers of the consistent
domestic economic recovery. However, this has substantially slowed for 2014, due to
a general slowdown in demand for commodities in global markets. It is expected that
over the next few years, the economy will continue to grow as a result of external
demand for goods and services produced in the economy4. Namibia’s GDP growth
exceeded global GDP growth (2.5%) over the medium-term, thus confirming Namibia’s
relatively healthy economic status.
Namibia’s tight monetary policy aimed to keep inflation at 3-6% per annum; this was
successfully achieved with the latest inflation rate being 3.3% as at end July 20155.
There is thus no concern over an overheated economy, which allows for more stability
on the repo rate of the country.
Growth in the primary sector (which represents 20% of the GDP) remained unchanged
in 2014. The key reasons for this near zero growth were: a decline in agricultural
growth, a fall in the global price of uranium, and weak offshore mining slowed mining
growth. Mining dominates the primary sector (63%) with diamonds contributing the
largest share. Due to the arid climate, livestock production forms the largest share of
the agricultural sector. In order to address Namibia’s socio-economic disparities across
the regions/ constituencies, deeper structural reforms are required to broaden non-
mineral diversification and intensify added value in agriculture6.
Khomas houses the capital city of Windhoek; making it the administrative, legislative
and judicial centre of Namibia. It is also the commercial/ business, educational and
transport (ie. rail, road, air) centre of the country; most farming goods produced in the
surrounding areas are marketed through Windhoek. Khomas borders Hardap along its
southern boundary. This area forms the northern part of the former Rehoboth Gebiet7,
comprising an area which is predominantly cattle-producing (characteristic of central
Namibia). Hardap, however, is predominantly characterised by small livestock farming
as is the rest of southern Namibia.
The //Karas region is rich in natural resources, such as alluvial gold, diamonds, iron
and zinc, and hosts the country’s largest mining activities (predominantly in the region’s
western constituencies). The perennial Orange River is also a valuable resource to the
region, offering high potential for green scheme (irrigation) projects and tourism (eg.
river rafting). These projects could have a poverty reducing impact, especially in
Berseba, Keetmanshoop Rural and Karasburg constituencies8.
(b) Agriculture
At the national level, crop farming was the most common type of agriculture as it is
practiced by nearly 33% of households, followed by livestock farming (25%) and poultry
4 African Economic Outlook: Namibia, 2015. 5 African Economic Outlook: Namibia, 2015. 6 African Economic Outlook: Namibia, 2015. 7 The Rehoboth Basters, amongst other ‘Baster’ groups, migrated north of the Orange River, as they were not permitted to own land in the Cape. They searched for new homes and secure pastures. With Independence, their Gebiet ceased to exist; what remained were farms in the personal possession of individual Basters, making it difficult to maintain the cultural cohesion of the group. 8 Namibia Poverty Mapping, 2015.
Kokerboom to Auas Transmission Line EIA 53 Version 1 / March 2018 Scoping Report
farming (13.5%). In rural areas, more than half (57%) of households are involved in
crop farming followed by livestock farming (42%). Namibia is the most arid country in
sub-Saharan Africa; as such land is fragile and productivity is low. In addition, there is
substantial land degradation due to large numbers of livestock exceeding the carrying
capacity of the rangeland, as well as inappropriate agricultural practices9.
Due to the arid climate, pastoral livestock farming was the most common agricultural
practice in all regions of the project area (~8% in Khomas, ~19% in Hardap, and 12%
in //Karas). Crop and poultry farming were considerably less significant, specifically in
Hardap and //Karas. The project-affected constituencies throughout the 3 regions are
largely rural in nature and heavily reliant on small livestock farming. Overall, livestock
farming was even more significant at the constituency-level throughout the Project area
(Berseba (~45%), Gibeon (~37%), Rehoboth Rural (~26%), Keetmanshoop Rural
(~24%), Mariental Rural (~21%), and Windhoek Rural (~17%))10.
In the west, south and central areas of Namibia, the majority of households live in small
villages and their livestock forage in the surrounding commonage pastures (communal
land). On average, households have no more than 10 cattle, goats or sheep11.
All the potentially Project-affected farms interviewed indicated that they are involved in
agriculture. The majority of the farms are used for commercial livestock farming (cattle,
sheep and goats), the animals are sold on auction or to the local abattoirs. Many of the
farms also farm game; the game is sold for meat, for relocation to other farms or for
hunting.
(c) Tourism
In 2014, there were nearly 1.5 million foreign visitors to Namibia. The majority (~89%)
of the visitors were tourists; tourism grew by 34% between 2010 and 2014 and by 12%
between 2013 and 201412. During this time, Africans accounted for the largest
proportion of tourists to Namibia (notably Angolans, South Africans and Zambians at
40%, 26% and 11%, respectively), European tourists totalled 17% (predominantly
Germans at 7%), and 2% were North Americans. The reason for tourist travel to
Namibia differed by the origin of the tourists; most Africans (~56%) entered the country
to visit family and friends, while 75% of European and 73% of American tourists were
holidaymakers13.
The total economic contribution of travel and tourism equated to nearly 15% of
Namibia’s GDP in 2014, and is forecast to rise by 5.6% in 2015, and to rise by 7.2%
per annum until 2025 (21.6% of GDP)14. The total economic contribution includes all
9 Property Rights and Resource Governance Profile: Namibia, 2010. 10 Population and Housing Census Main Report (2013), Population and Housing Census: Khomas Regional Profile (2014), Population and Housing Census: Hardap Regional Profile (2014), and Population and Housing Census: //Karas Regional Profile (2014). 11 An Overview of Communal Land Tenure in Namibia, 2012. 12 Tourist Statistical Report, 2014. 13 Tourist Statistical Report, 2014. 14 Travel and Tourism Economic Impact Namibia, 2015.
Kokerboom to Auas Transmission Line EIA 54 Version 1 / March 2018 Scoping Report
direct, indirect and induced expenditure across the economy. Domestic tourists
accounted for more than 56% of all direct expenditure in this sector15.
The project affected regions are sparsely populated and generally valued for their vast
open spaces. Tourist attractions are focussed along the coast, with a number of specific
attractions located throughout the regions; namely the Hardap Dam, Fish River Canyon
and the hot water springs at Ai-Ais. The Project area is primarily used for stock farming;
increasingly some of the farmers are offering hunting and eco-tourism (hiking, horse
riding, mountain biking) experiences (see Section 3.1.15).
(d) Economically Active and Inactive Population
Khomas is the main employment centre in Namibia; providing jobs to 21% of the
employed population. As a result, Khomas (specifically Windhoek) sees high levels of
in-migration of rural dwellers in search of employment opportunities. //Karas region
provides about 5% of Namibia’s employment. Hardap region provides the least
employment of these regions.
Table 10: provides a summary of the labour force participation rates in the project area.
Of the country’s economically active population (employed and unemployed), 64% of
the national population aged 15 years and above were economically active and ~29%
were economically inactive16. The economically active population at the regional level
was significantly higher at 70% in Khomas, 71% in Hardap and 75% in //Karas.
Consequently, the percentage of economically inactive people is lower. In all regions,
more males are economically active than females; this is most notable in Hardap and
//Karas. There are slightly higher levels of economically active people in urban areas
across the project area, with the exception of //Karas where it was equal.
Across the project area, the levels of employment decreased between 2001 and 2011
and the levels of unemployment have increased; with the exception of Khomas where
employment levels remained the same. The highest unemployment rate is experienced
at the national level (37%), followed by Hardap (35%), then //Karas (32%), and Khomas
(30%).
Table 10: Economic Activity, 2011
Indicator Namibia Khomas Hardap //Karas
2011 2001 2011 2011 2011 2001 2011 2011
Economically active, 15+ years (%) 64 54 74 76 71 64 75 67
Employed 63 69 70 70 65 66 68 71
Unemployed 37 31 30 30 35 34 32 29
Economically inactive, 15+ years (%) 29 39 21 21 23 29 19 24
Student 52 35 69 55 31 29 39 28
Homemaker 15 43 8 24 20 37 15 40
Retired, too old, etc. 27 22 15 21 39 33 35 32
15 Travel and Tourism Economic Impact Namibia, 2015. 16 Economically inactive people (ie. students, homemakers and income recipients) accounted for 28.5% of the population and information on 7.5% of the population was not available.
Kokerboom to Auas Transmission Line EIA 55 Version 1 / March 2018 Scoping Report
Source: Population and Housing Census Main Report (2013), Population and Housing Census: Khomas Regional
Profile (2014), Population and Housing Census: Hardap Regional Profile (2014), and Population and Housing Census:
//Karas Regional Profile (2014).
According to the Labour Force Survey (2014), the dependency ratio in Namibia is high,
at nearly 70%. As such, approximately 7 people must be sustained by every 10 people
of economically active age.
The primary employer at the national and regional level is the agricultural sector, with
the exception of Khomas where agriculture only accounts for 3% of employment. Retail
and construction are also relatively large employers. Administrative work is the most
dominant activity in the Khomas region and the second most dominant nationally.
Mining is the second largest employer in //Karas region but it is not significant
elsewhere. There are some tourist facilities located throughout the area, however these
are not significant contributors as regional employers. The main employers are listed
below.
Main employers in Namibia17:
Main employers in Khomas Region18:
agriculture, forestry and fishing (30%) administration and support (13%)
administration and support (9%) construction (11%)
wholesale and retail trade (7%) wholesale and retail trade (10%)
construction (7%) transportation and storage (7%)
Main employers in Hardap Region19:
Main employers in //Karas Region20:
agriculture, forestry and fishing (29%) agriculture, forestry and fishing (32%)
construction (12%) mining and quarrying (9%)
activities of private households (10%) wholesale and retail trade (6%)
wholesale and retail trade (8%) construction (6%)
17 Population and Housing Census Main Report (2013). 18 Population and Housing Census: Khomas Regional Profile (2014). 19 Population and Housing Census: Hardap Regional Profile (2014). 20 Population and Housing Census: //Karas Regional Profile (2014)
Kokerboom to Auas Transmission Line EIA 56 Version 1 / March 2018 Scoping Report
The main occupations of the employed population at the national and regional levels
are listed below.
Main occupations in Namibia21:
Main occupations in Khomas Region22:
skilled agricultural/ fishery workers
(26%)
service workers (17%)
elementary occupations (16%) elementary occupations (16%)
service workers (14%) craft and related trade workers (16%)
craft and related trade workers (12%) professionals (12%)
technician/associate professionals
(10%)
Main occupations in Hardap Region23:
Main occupations in //Karas Region24:
elementary occupations (24%) elementary occupations (26%)
skilled agricultural/fishery workers
(21%)
skilled agricultural/fishery workers
(20%)
craft and related trade workers (17%) service workers (13%)
service workers (13%) craft and related trades workers (12%)
(e) Income
Table 11: Primary income source shows the primary income sources across the
project area. At the national level, wages and salaries accounted for nearly half (48%)
of all household income. The second main source of income was farming (16%),
followed by pensions (14%), and non-farming business activities (12%). In urban areas,
68% of households reported wages and salaries as the main source of income, followed
by non-farming business activities (15%). The rural areas were very different, reporting
farming to be the primary income source (~30%), followed by wages and salaries (28%)
and pensions (22.5%).
At the regional level, wages and salaries also dominated as the primary source of
income, followed by business in Khomas and pensions in Hardap and //Karas. Despite
the prominence of agriculture as the primary employer and occupations, farming
accounted for only 7% and 5% in Hardap and //Karas, respectively and just 1% in
Khomas. Agriculture is a subsistence/ lifestyle activity for the majority of the population,
only those with the means to irrigate, apply fertilisers and employ labour can produce
adequate surpluses to be sold25. A similar pattern of income distribution is evident at
the constituency-level.
21 Population and Housing Census Main Report (2013) 22 Population and Housing Census: Khomas Regional Profile (2014). 23 Population and Housing Census: Hardap Regional Profile (2014). 24 Population and Housing Census: //Karas Regional Profile (2014) 25 An Overview of Communal Land Tenure in Namibia, 2012.
Kokerboom to Auas Transmission Line EIA 57 Version 1 / March 2018 Scoping Report
Table 11: Primary income sources, 2011 (%)
Indicator Namibia Khomas Hardap //Karas
2011 2001 2011 2011 2011 2001 2011 2011
Farming 16 28 1 1 7 9 5 7
Wages/ Salaries 48 41 73 74 64 61 72 69
Cash remittance 5 6 5 7 7 7 5 6
Business (non-farming) 12 9 14 11 4 5 5 5
Pension 15 11 4 3 15 15 11 10
Source: Population and Housing Census Main Report (2013), Population and Housing Census: Khomas Regional
Profile (2014), Population and Housing Census: Hardap Regional Profile (2014), and Population and Housing Census:
//Karas Regional Profile (2014).
Wealth in Namibia is unevenly distributed, with a national Gini coefficient of 0.42.
Wealth inequalities are higher in rural areas (0.45) than in urban areas (0.24). Relative
to other regions, //Karas has one of the lowest wealth disparities at (0.28)26. However,
the incidence of poverty in //Karas is estimated at 14%, having decreased by 3.4% over
the past ten years. About 7% of the regional population is estimated to be severely
poor, having declined by 2.6% since 200127.
The incidence of poverty is estimated to be 17% in Hardap (highest in Gibeon,
Rehoboth Rural and Mariental Rural constituencies), 14% in //Karas (with Berseba
registering the highest incidence of poverty) and nearly 5% in Khomas region.
At the national level, the average monthly wage is N$6,626. The highest average wage
is N$21,749 per month (Mining and Quarrying), while the lowest is N$1,168 per month
(private household work). The average monthly wages recorded in the sectors
dominant in the project area are listed below28; for the majority of sectors males earn
more than females with the exception of agriculture and construction.
Sector Average Monthly Wage
mining and quarrying - N$21,749
service workers - N$4,665
administration and support - N$4,611
wholesale and retail trade - N$4,474
construction - N$4,140
agriculture, forestry and fishing - N$2,114
elementary occupations - None recorded
3.1.12 Health and Welfare
Nationally, there are 14 Regional Health Directorates that oversee service delivery in
34 health districts. The role of each district is to implement regionally directed
programmes and projects. Throughout Namibia, there are 30 public district hospitals,
26 The Namibia Demographic and Health Survey, 2014. 27 Namibia Poverty Mapping, 2015. 28 Labour Force Survey, 2014.
Kokerboom to Auas Transmission Line EIA 58 Version 1 / March 2018 Scoping Report
44 health centres, and 269 clinics. Given the vastness of the country, the sparse
distribution of the population, and the lack of access to permanent health facilities in
some communities, outreach (mobile clinic) services are provided at about 1,150
outreach points across the country. The national referral hospital (Windhoek Central
Hospital) provides support to the district hospitals29.
In Namibia, the average number of children born per woman dropped by almost 50%
to 3.6 children compared to 4.1 children in 2001 and 6.1 children in 1991. There has
been no change in fertility over the last 6 years30. In 2011, this rate was lower in urban
areas (3%) and higher in rural areas (4.3%). The regional and constituency level rates
are lower than the national rate at ~3% each (see Table 12:).
Nationally, the maternal median age of first births is 21.6 years; however there was an
increase in the percentage of young mothers (aged 15-19 years) from 15% in 2006/7
to 19%31. Teenage pregnancy is more than three times higher among young women in
the lowest wealth quintile than among those in the highest wealth quintile. Only half of
women make use of contraception; use is highest amongst those aged 25-29 years
and those living in urban areas. Contraceptive use is positively associated with
women’s level of education and wealth32
The crude death rate (number of deaths / 1,000 people) was the same for Namibia and
//Karas (10.7), lower in Khomas (6.7) and higher in Hardap (13). There were a higher
number of deaths in rural areas than in the urban centres, across Namibia, Khomas
and //Karas; in Hardap, deaths in urban areas exceeded those in rural areas (see Table
12: Health indicators).
Table 12: Health indicators, 2011
Indicator Namibia Khomas Hardap //Karas
2011 2001 2011 2011 2011 2001 2011 2011
Average number children/
women (%)
3.6 4.1 2.8 4.9 3.5 3.6 3.1 3.1
Number of deaths/ 1,000 people 10.7 - 6.9 - 13 - 10.7 -
Urban 8.6 - 6.7 - 13 - 10.2 -
Rural 12.2 - 11.5 - 12 - 11.2 -
Disability (%) 5 5 3 4 4 6 4 3
Source: Population and Housing Census Main Report (2013), Population and Housing Census: Khomas Regional
Profile (2014), Population and Housing Census: Hardap Regional Profile (2014), and Population and Housing Census:
//Karas Regional Profile (2014).
Across the country, the HIV prevalence rate has been on the decline since 200233.
Between 2006 and 2014, the HIV prevalence rate amongst pregnant women receiving
antenatal care has gradually declined nationally from ~20% to 17%34.
29 The Namibia Demographic and Health Survey, 2014. 30 The Namibia Demographic and Health Survey, 2014. 31 The Namibia Demographic and Health Survey, 2014. 32 The Namibia Demographic and Health Survey, 2014. 33 National HIV Sentinel Survey, 2008. 34 Surveillance Report of the 2014 National HIV Sentinel Survey, 2014.
Kokerboom to Auas Transmission Line EIA 59 Version 1 / March 2018 Scoping Report
3.1.13 Infrastructure and Services
Table 13: Public infrastructure presents an overview of selected public infrastructure
in the project area. This is discussed further below.
Table 13: Public infrastructure, 2011 (%)
Indicator Namibia Khomas Hardap //Karas
2011 2001 2011 2011 2011 2001 2011 2011
Safe water 80 87 99 98 93 95 92 94
Flush toilet (various) 40 - 76.2 - 54.5 - 64 -
No toilet facilities 49 69 20 20 35 34 23 26
Electricity for lighting 42 32 68 69 66 51 67 50
Wood/charcoal for cooking 54 62 8 9 45 20 28 35
Source: Population and Housing Census Main Report (2013), Population and Housing Census: Khomas Regional
Profile (2014), Population and Housing Census: Hardap Regional Profile (2014), and Population and Housing Census:
//Karas Regional Profile (2014).
(a) Water and Sanitation
In 2013, 87% of Namibian households had access to safe water sources (ie. 37% from
piped water into the dwelling, 14% from water piped to the yard, and 26% from a public
tap)35. Almost all urban households (98%) have access to safe water as compared to
76% of rural households36. Over half of households can access water immediately on
their premises, while 31% take less than 30 minutes to obtain drinking water, and 15%
take more than 30 minutes.
At the regional level, a far higher percentage of households have access to safe water
(99% in Khomas, 93% in Hardap, and 92% in //Karas). At the regional level, households
in urban areas largely had access to safe water; these levels were lower in rural areas.
The constituencies of Rehoboth Rural and Berseba have notably lower levels of access
to safe water at 84% and 85%, respectively.
A range of flush toilets are used across the project area. Flush toilets are dominant at
the regional level. At the national level, 49% of households have no toilet facilities.
Households with no toilet facilities are considerably higher in the rural areas. The
majority of the project area is located in rural constituencies with no access to toilet
facilities for over 45% of households in the project-affected constituencies in Hardap
and //Karas.
Poor sanitation and inadequate access to safe water are public health concerns as they
can create conditions conducive to the spread of diseases.
35 Namibia Demographic and Health Survey (2014). 36 Namibia Demographic and Health Survey, 2014.
Kokerboom to Auas Transmission Line EIA 60 Version 1 / March 2018 Scoping Report
(b) Energy Sources
The most dominant energy sources differ for lighting, cooking and heating. In Namibia,
the most common source of energy for lighting is electricity from the main grid (~42%);
with over two-thirds (70%) of urban households relying on electricity, and half of rural
households using candles for lighting. On the contrary, 54% of households use wood
for cooking (with over 86% relying on wood in the rural areas) and 33% use electricity.
At the regional level, the most common source of energy for lighting was electricity
(between 66% and 68%). The majority of households in urban and rural areas relied
on electricity (most dominant in urban areas), followed by candles.
Electricity is the main energy source used for cooking in Khomas, Hardap and //Karas
(64%, 49% and 42%). In Khomas, the second most common fuel sources were paraffin
and gas (14% each) and in //Karas, it was gas (29%). In Hardap, wood was almost as
commonly used for cooking as electricity at 45%. The majority of urban households use
electricity while wood is the most common fuel for cooking in rural areas.
(c) Housing
The most common house type varies across the project area. Nationally, traditional
dwellings are the most common (~38%), regionally, detached houses are the most
common; most notably in Hardap. The next most common house types nationally were
detached houses (~30%) and shacks (16%); shacks were the second most common
regionally. Traditional houses comprised 11% in //Karas and less than 0.6% in Khomas
and Hardap.
3.1.14 Land Tenure and Management
When Namibia gained independence in 1990, approximately 5,000 commercial farms
(averaging 7,200 ha in size) were owned by white farmers. These were primarily
commercial livestock farms. Communal land was largely used for subsistence/ livestock
farming and hunter-gatherer activities by approximately 1.5 million people
(predominantly Black)37. The Ministry of Lands and Resettlement38 was established and
was mandated to “manage, administer and ensure equitable access to Namibia’s land
resource”, as such, their mission was to ensure that Namibia’s land resources were
equitably allocated, efficiently managed and sustainably used for the benefit of all
Namibians39.
Private individuals, entities and the state are all able to own land40. There are 5 tenure
types specified in Namibia; namely ownership/freehold (private), communal,
conservancies, leasehold, and occupancy in informal settlements41. Of relevance to
this Project are private farms (ownership/ freehold tenure), and state-owned land
(communal and leasehold tenure); these are described further below.
37 Property Rights and Resource Governance Profile: Namibia, 2010. 38 Now the Ministry of Land Reform. 39 Ministry of Lands and Resettlement: Strategic Plan 2013-2017, 2013. 40 Legal Assistance Centre (2005) in Property Rights and Resource Governance Profile: Namibia, 2010. 41 Property Rights and Resource Governance Profile: Namibia, 2010.
Kokerboom to Auas Transmission Line EIA 61 Version 1 / March 2018 Scoping Report
Private ownership/ freehold tenure: Owners of freehold land in Namibia have
rights to hold the land in perpetuity, to use, transfer, and dispose of the land, and to
exclude others from the land. Forty-four percent of Namibia’s land comprises
freehold tenure.
Communal tenure: About 38% of Namibia is designated communal land. All
communal land is held in trust by the state, as stipulated in Article 17 (1) of the
Communal Land Reform Act of 2002: “Subject to the provisions of this Act, all
communal land areas vest in the State in trust for the benefit of the traditional
communities residing in those areas and for the purpose of promoting the economic
and social development of the people of Namibia, in particular the landless and
those with insufficient access to land who are not in formal employment or engaged
in non-agriculture business activities.”
Communal land cannot be sold; transfers of use rights are permissible and must be
administered by Traditional Authorities and Land Boards. Traditional Authorities
and Land Boards are responsible for allocating land for residences, agriculture, or
other uses recognised by the Minister. All communal land is registered with the
Land Board.
Leasehold tenure: Common law and the Communal Land Reform Act allow for
land leases. Leases of communal and commercial land can be granted by
Communal Land Boards and government officials for a period of 99 years and may
be transferred, inherited, renewed, and mortgaged. Namibians, who were
historically unable to access land, can apply for the use of commercial agricultural
land. The relevant authority will assign land to these farmers on a contract basis,
they are referred to as ‘resettlement farmers’; it is expected that the land must be
farmed commercially42.
3.1.15 Project Area
(a) Farm Status
The proposed transmission line passes through 89 farms43, the distribution and
ownership status44 of these farms is presented in Table 13: Distribution and tenure
status of affected farms. Figure 14: Land tenure map showing freehold and
communal areas illustrates the freehold and communal areas in the 3 project-affected
regions. Appendix 2 in the Social Assessment (refer to Appendix H: Technical
Specialist Reports) lists the details as provided by the Surveyor General, and the
affected farms have been mapped and highlighted for reference.
42 Pers comms, various respondents, October 2016. 43 This information was collected from the Deeds Office. The accuracy of the information is variable. 44 The ownership status is as captured at the Deeds Office in 2009.
Kokerboom to Auas Transmission Line EIA 62 Version 1 / March 2018 Scoping Report
Table 13: Distribution and tenure status of affected farms
Region Constituency Total Farms Private State-
Owned
Unknown
Individuals Companies
Khomas Windhoek Rural 28 22 6 - -
Hardap Mariental Rural 19 10 5 3 1
Mariental Urban 1 1 - - -
Rehoboth Rural 18 13 2 3 -
Gibeon 10 - - 10 -
//Karas Berseba 6 - 1 5 -
Keetmanshoop Rural 7 2 - 5 -
TOTAL 89 50 14 24 1
Source: Surveyor General, May 2016 and personal interviews, October 2016.
Figure 14: Land tenure map showing freehold and communal areas
Source: Adapted from An Overview of Communal Land Tenure in Namibia, 2012.
The farms located in Windhoek Rural are 100% privately owned by individuals or
companies. In Mariental Rural, Mariental Urban and Rehoboth Constituencies, ~82%
of the farms are privately owned and 16% are state-owned.
The Rehoboth ‘Baster Gebiet’ is largely located in Rehoboth Constituency and crosses
the boundary into the southern parts of Windhoek Rural Constituency. ‘Baster Gebiet’
Khomas
Hardap
//Karas
Kokerboom to Auas Transmission Line EIA 63 Version 1 / March 2018 Scoping Report
refers to land located in the vicinity of Rehoboth, Duineveld and Kalkrand towns. The
Rehoboth Basters, amongst other ‘Baster’ groups, migrated north of the Orange River,
as they were not permitted to own land in the Cape. They searched for new homes and
secure pastures. With Namibian independence, their communal ‘Gebiet’ ceased to
exist; the land was divided up into privately owned freehold farms (registered to
individual Basters); together with other factors, this made it difficult for the Baster
community to retain historical cultural cohesion45. These farms are often divided
between family members following the death of the registered owners; this occurs
informally and is not reflected at the Deeds Office. As such, in practice, these farms
may be smaller than those recorded at the Deeds Office.
South of Kries, almost 100% of the farms are state-owned in Gibeon and Berseba
constituencies. Five of the 7 affected farms in Keetmanshoop Rural (71%) are state-
owned and the remaining 2 are private. In Gibeon and Berseba, some of the state-
owned land is leased on a contract basis as ‘resettlement farms’; however, the majority
of state land is communal and under the jurisdiction of the Traditional Authorities. The
Ministry of Land Reform has over-arching responsibility for all state-owned land.
Straddling the boundary of the Hardap and //Karas regions is the communal land (this
includes the ‘pre-independence private farms); see Figure 14: and Appendix 2. The
proposed transmission line will run through this area, ending approximately 23km north-
east of Keetmanshoop. The communal area is referred to as Namaland and is occupied
and used by the Nama people. Kries, Gibeon, Amper-Bo, and Tses are some of the
established settlements that accommodate many of the Nama households, education
and healthcare facilities. There are structures (including kraals, water points, small
houses) scattered throughout the communal area, however these are sparsely
distributed.
Based on the information available from the Deeds Office, the farms vary from large
commercial farms to subsistence based farms. The farms range in size as follows:
Windhoek Rural – 55,7143 ha to 12486,3955 ha (average 4234 ha46);
Mariental Rural – 2132,5081 ha to 21125,4031 ha (average 6634 ha47);
Mariental Urban – 400,3935 ha48;
Rehoboth Rural– 0,1050 ha to 2950,5441 ha (average 1482 ha49);
Gibeon – 2184,8179 ha to10384,1156ha (average 6268 ha50);
Berseba – incomplete information51; and
Keetmanshoop Rural – 2158,2846 ha to 12483,0890ha (average 6724 ha52).
45 Rehoboth, Namibia – Past & Present, 2012. 46 Average based on 20 farms. 47 Average based on 16 farms. 48 Only 1 affected farm in Mariental Urban. 49 Average based on 10 farms. 50 Average based on 10 farms. 51 Farm area only provided for 1 out of 6 farms. 52 Average based on 6 affected farms.
Kokerboom to Auas Transmission Line EIA 64 Version 1 / March 2018 Scoping Report
(b) Land Use
Most Project affected farms are used for commercial livestock farming. Cattle, sheep
and goats are farmed across the Project area; the animals are sold to local abattoirs
and on auction. The private commercial farmers often own/ farm more than one farm;
this is most notable for the smaller land parcels that are not commercially viable when
farmed in isolation. Typically, each land parcel is divided into several camps (each one
fenced) to enable rotational grazing and effective farm management.
There are several other farms that practice commercial livestock agriculture and have
relatively significant tourism offerings (hunting and eco-tourism including (hiking/
walking, horse riding, mountain biking, and photography); they include but are not
limited to Hohenau, Hohewarte, Voigtland, Koichas, Rem. Of Ptn. 5 of Orab,
Wilderness Rem Ptn53.
There are 3 known farms that are used solely for tourism activities; namely Rem of
Gravenstein, Ptn 2 of Duineveld and Ptn 3 of Duineveld. Over the past 5 years, all
infrastructure and domesticated livestock have been removed and game introduced to
restore these farms to their natural and pristine state. The farms offer exclusive hunting
and eco-tourism options to guests.
Tourist numbers are reported to have been increasing into the area54, specifically to the
farms in Khomas and Rehoboth Rural constituencies due to their relative proximity to
Windhoek. The tourists that visit these farms include Namibians, South Africans,
Americans and Europeans.
Most of the commercial farmers reside on the farms together with their workers. Some
landowners live and work in town and use their farms as weekend retreats, the workers
manage the livestock in the absence of the landowner.
The ‘resettlement farms’ are required, by contract, to be farmed commercially. The
communal land is expansive and largely unfenced, livestock roam freely over the area
and due to the general lack of effective land management and lack of water, the area
is currently extremely over-grazed and degraded. There are no reports of tourism or
other economic activities on the ‘resettlement farms’ or communal land.
(c) Infrastructure and Services
It seems that almost all the potentially affected farms have some form of infrastructure
on them; notably residential dwellings, out-buildings, water sources, large fenced
camps, small kraals, gravel roads, fire breaks.
Access to reliable electricity supply, telephone lines and internet varies across the area.
53 This information is based on key informant interviews; not all land owners/users were contacted/ available for interviews. 54 Several of the land owners reported that the tourism market is increasing.
Kokerboom to Auas Transmission Line EIA 65 Version 1 / March 2018 Scoping Report
4 DESCRIPTION OF THE PROPOSED DEVELOPMENT
The proposed project comprises the construction and operation of a new 400 kV
transmission power line between the Kokerboom and Auas Substations. The proposed
transmission line corridor between the two substations is approximately 457 km long
and 500 m wide.
The proposed centreline of the power line was changed a number of times during the
scoping process to avoid sensitive environmental features, most notably mountain
slopes which are susceptible to erosion and support sensitive biota, current and future
land use, infrastructure (e.g. landingstrips and homesteads) and high-value cultivated
land. It also avoided socio-economic receptors and areas of high avifaunal sensitivity.
The transmission line centre line between the Kokerboom and Auas Substations
assessed during the Scoping Phase is presented in Appendix B: Site Locality Plan.
The centreline pass a number of towns; including (from north to south):
Dordabis (~13.5 km[1]),
Groot Aub (~33 km),
Rehoboth (~37 km),
Duineveld (~1 km),
Hoachanas (~52 km),
Kalkrand (~0.5 km),
Stampriet (~44 km),
Mariental (~7 km),
Kries (~1 km),
Amper-Bo (~3 km) and
Tses (16.5 km).
The proposed 400 kV transmission line will enter the Auas Substation from the South
West and the Kokerboom Substation from the North East.
The infrastructure proposed is illustrated in Appendix D: Facility Illustrations. It
includes a 400 kV transmission line conductor strung onto 45 m-high steel pylons, of
the Open-V or the Self-Supporting design, placed approximately 500 m apart. These
pylons are to be placed on a 10 m by 10 m concrete base. The line needs to be at least
100 m away from the 220 kV power line.
The proposed construction work to be carried out on the power line includes:
Site establishment, including site demarcation and fencing (temporary and only
where required), layout and establishment of the contractor’s camps including
ablution and cooking facilities (this will only be established if required by the
appointed Contractor);
[1] Distances were measured from the point in town closest to the proposed transmission line to the centre line.
Kokerboom to Auas Transmission Line EIA 66 Version 1 / March 2018 Scoping Report
Bush clearing at pylon base sites and to facilitate access (where necessary), for
construction and safe operation of the power line;
Excavation of holes for the concrete pylon base and foundations;
Casting of concrete platforms for the pylons (10 m x 10 m);
Transportation of plant, machinery and equipment to site;
Transport of the conductor into position by means of a pulley system or by rolling
large coils of conductor into position;
Hoisting and lifting of the pylons into position;
Stringing and regulation of the conductor;
Construction of the access road;
Rehabilitation of disturbed areas and erosion prevention;
Final inspection and handover for operation; and
Rehabilitation of the site.
The transmission power line will take approximately 24 months to construct, depending
on whether one or more Contractors are appointed to undertake the work and/ or the
working front is on both ends of the transmission line. Most experienced contractors
can string the lines at a rate of approximately 6 km/ day so the work will proceed along
the line relatively quickly. Each farmer will be ‘disturbed’ intermittently for a period of 6
to 8 weeks during the construction period. This period would depend on the length of
power line on each farm.
Prior to construction, a final ‘walkdown’ of the proposed centreline of the transmission
power line corridor alignment will be undertaken and the sites of each of the poles
finalised and demarcated. During final positioning of the poles sensitive features (e.g.
plant habitats and archaeological sites) will be avoided.
An Environmental Management Plan (EMP) for the construction phase will be
compiled. It will be included in the tender documentation and the Contract with the
appointed Contractor. It will contain all the mitigation measures/ management actions
proposed in this EIA process and will be included in draft format in the Assessment
Report, which will be compiled in the next phase of this EIA.
NamPower is required to negotiate with each individual affected property owner
regarding compensation and mitigation. If Environmental Clearance is granted and
prior to construction, NamPower will approach each one of the potentially affected
farmers with the view of negotiating use of a ‘right of way’ servitude (80 m i.e.
approximately 40 m either side of the centre line of the power line) over the affected
properties for the purpose of constructing and operating the proposed transmission line.
Negotiations will include access requirements (including gates), which will be locked at
all times; keys will be provided to both parties. Infrequent access will be required
(approximately every 3 years).
All areas marked as no-go areas, identified by means of the EIA process, located inside
the servitude shall be treated with the utmost care and responsibility. The final servitude
will need to be registered and the land handed over to NamPower. Access to the
Kokerboom to Auas Transmission Line EIA 67 Version 1 / March 2018 Scoping Report
servitude will need to be negotiated and the necessary infrastructure erected e.g.
access roads and gates.
After construction the power line will immediately put into operation and if appropriately
maintained will have a lifespan of at least 30 years plus.
All parties operating the power lines or performing ongoing maintenance must comply
with NamPower’s safety standards.
NamPower has operated the existing 400 kV and 220 kV powerlines between the
Kokerboom and Auas Substations for the past 17 and 37 years, respectively. The
Kokerboom and Auas Substations have been operated by NamPower for the past 37
(with the new section for the 400 kV power line entry being commissioned 17 years
ago) and 17 years, respectively. These substations will not be expanded in this
proposed Project.
NamPower Wires Business Section will be the owner and operator of the proposed
transmission power line. The operation and maintenance of the new power line will be
a continuation of the current NamPower operational and maintenance activities for
transmission lines, namely:
Transportation of plant, machinery and equipment to site in the event of
maintenance work or restringing being required;
Transport of the conductor into position by means of a pulley system or by rolling
large coils of conductor into position (if a conductor needs replacing);
Hoisting and lifting of any pylons parts into position (if needing repair/
replacement);
Stringing and regulation of the conductor in the event of maintenance work or
restringing being required;
Repair and maintenance of the access road;
Vegetation management, including herbicide application and manual vegetation
clearing;
Erosion prevention;
Final inspection and handover of any construction sites;
Site inspections, including Technical and Safety, Health, Environment and
Wellness (SHEW); and
Rehabilitation of any disturbed areas.
High voltage power lines require a clearance area for safety precautions. Shrubs which
interfere with the operation and/or reliability of the power line must be trimmed or
completely cleared. The clearing of vegetation must take place, with the aid of a
surveyor, along approved profiles and in accordance with this EMP and NamPower’s
standards for vegetation clearing. A vegetation specialist may need to be consulted
during initial and ongoing vegetation clearance.
After the power lines has reached the end of its lifespan it will be decommissioned.
Kokerboom to Auas Transmission Line EIA 68 Version 1 / March 2018 Scoping Report
The above construction and operational activities formed the development ‘proposal’
(hereafter referred to as the proposed project) as assessed in the environmental
assessment process.
An Environmental Management Plan (EMP) for the operational phase will also be
compiled. It will contain all the mitigation measures/ management actions proposed in
this EIA process and will be included in draft format in the Assessment Report, which
will be compiled in the next phase of this EIA.
4.1 Alternatives
A number of alternatives (‘no-go’, technology, methods of construction and operation,
equipment, and mitigation measures) to the construction and operation of the
transmission power line were considered by NamPower and assessed during the EIA
process.
The ‘no-go’ alternative is not recommended given the importance of the Kokerboom to
Auas Substation transmission line in the supply of power to Namibia and fulfilment of
the NamPower’s mandate. Without upgrades to the transmission line network future
electricity supply in Namibia will become constrained, and as a result, restrict
development (mining, industrial and residential) and negatively impact quality of life in
the country as a whole.
The purpose of the Kokerboom to Auas Substation 400 kV transmission line project is
to support system reliability. Additional benefits include improved network stability and
redundancy, improved network capacity to supply the system demands, improved
dynamic stability and lower network power losses. The proposed line will also enable
NamPower to accommodate increased electricity transfer and wheeling from south to
north and vice versa, thus increasing utilisation of the network to the benefit of all.
The proposed transmission power line does not only serve the specific area where the
transmission power line is to be constructed, but is for the benefit of the Namibian
electricity transmission backbone and Namibian economy as a whole. The expected
Namibian electricity load growth together with possible transfer of power northwards,
via the Zambezi Link Interconnector High Voltage DC (HVDC) scheme, requires this
transmission line to be operational. Also, the number of cases where an outage of the
existing 400 kV line between Auas and Kokerboom Substations can be accommodated
(hence relying only on the 220 kV interconnector from South Africa) is becoming less
and less each year as the Namibian electricity load grows.
It is proposed that the line construction be completed by 2023, or as soon thereafter as
possible.
Kokerboom to Auas Transmission Line EIA 69 Version 1 / March 2018 Scoping Report
During this environmental process the transmission line route (centreline) was revised
to avoid impacts on existing infrastructure, as far as possible. NamPower identified a
suitable routing option for the transmission line with input from the environmental
consultants and relevant specialists. The line was realigned several times to avoid and
reduce potential negative impacts of the proposed Project on the environment, and in
particular socio-economic receptors (notably infrastructure) and areas sensitive from
an avifauna perspective. Each alternative was scoped and a new alternative put
forward for assessment that avoided potential negative biophysical as well as socio-
economic impacts. The favoured alternative is presented in Appendix B: Site Locality
Plan.
Mitigation and management alternatives were considered by the technical specialists
when making suggestions to avoid/ reduce negative impacts.
In sourcing the specific equipment for the proposed transmission line project,
NamPower will assess alternatives in terms of availability, efficiency, compatibility with
the existing equipment, cost and environmental sustainability, before making a final
decision.
Operational alternatives are limited as NamPower already has an operational protocol
for the existing 400 kV power lines, and specifically for the two lines between the
Kokerboom and Auas Substations, which is working well. Operational procedures will
be a continuation of the status quo, as new operational procedures are considered
unnecessary by NamPower given that the current ones are tried and tested and
considered effective, efficient and sustainable.
Kokerboom to Auas Transmission Line EIA 70 Version 1 / March 2018 Scoping Report
5 POTENTIAL IMPACTS
The objective of the impact assessment, in the context of this scoping assessment, was
to undertake a preliminary assessment of the significant environmental (biophysical
and socio-economic) impacts that may arise as a result of the proposed activities, in
terms of the following criteria:
a. Nature of the impact
b. Extent of the impact
c. Duration of the impact
d. Intensity
e. Reversibility
f. Irreplaceability
g. Consequence
h. Probability of occurrence
i. Significance
j. Degree of confidence in predictions
k. Cumulative impacts
A description of these criteria and how the results of the assessment methodology links
to recommendations for decision-making are presented in Appendix G: Assessment
Methodology.
The significance of a potential impact is based on the combination of consequence of
the impact and probability of the impact occurring, and defines the level to which the
impact will influence the proposed project and/or the environment. It determines
whether mitigation measures need to be identified and implemented or whether the
resource is irreplaceable and/or the activity has an irreversible impact. Significance is
rated as either Low, Medium (Moderate) or High.
Impacts of a Low significance should not have an influence on the decision to proceed
with the proposed project, if recommended mitigation measures to mitigate impacts are
implemented. Impacts of a Medium (Moderate) significance should influence the
decision to proceed with the proposed project, provided that recommended measures
to mitigate impacts are implemented. Impacts of a High significance strongly influence
the decision to proceed with the proposed project regardless of mitigation measures.
A summary table was completed for each identified impact in each phase of the project
lifetime, without and with effective mitigation measures in place. A detailed assessment
of all identified impacts, for both the construction and operational phases, will be
undertaken in the Assessment phase of the EIA and documented in the Assessment
Report. The Assessment phase technical specialist studies will identify the most
practical and economically viable management, mitigation and monitoring measures.
Kokerboom to Auas Transmission Line EIA 71 Version 1 / March 2018 Scoping Report
5.1 Identification of Potential Impacts
NamPower identified the transmission line corridor alignment (and its proposed
centreline position and subsequent amendments thereof) in consultation with the
directly affected land owners, key stakeholders, and with input from the environmental
consultants, relevant technical specialists and registered I&APs. The screening of
corridor alignments and the development of a “preferred” alignment has already served
to avoid and reduce potential negative impacts of the proposed project on biophysical
and socio-economic receptors, notably avifaunal sensitive areas, infrastructure and
cultivated land.
The key impacts that may arise as a result of the construction of the proposed 500 km
400 kV transmission power line from the Kokerboom Substation to the Auas Substation
for the construction and operational phase, as well as the cumulative impacts, are
briefly discussed below per technical discipline for the construction and operational
phases. Many of the potential impacts are
5.1.1 Construction Phase
Landuse:
The negative impacts linked to the proposed Project will be localised (and limited to a
demarcated construction site and is largely far away from development and
homesteads) and will affect land owners, land users and tourists in different ways.
Existing agricultural activities will largely be able to continue unhindered during the
construction and operation processes. As far as possible landing strips and farms used
for high-end tourism activities has been avoided.
Some planning will be required to minimise disruptions during construction. Tourism
activities may be more sensitive to the construction phase nuisance factors.
Visual and Sense of Place:
The area is characterised by wide open untouched spaces, agricultural lands (cattle
and game farming) and tourism ranches. The general sense of place could be affected
by visual, noise and dust impacts linked to the proposed Project if allowed to take place
without planning and management. Noise and dust impacts are likely to be generated
by construction vehicles and equipment, as well as an increased number of people on
the working site(s). These factors may change the ‘feel’ of the area and create
increased levels of annoyance during the 24 month construction phase.
Kokerboom to Auas Transmission Line EIA 72 Version 1 / March 2018 Scoping Report
Terrestrial Ecology:
The transmission line corridor has been realigned to avoid traversing areas of high
botanical diversity and endemism, as well as sensitivity. No fatal flaws were identified.
The northern section of the route traverses the Highland Savanna, a zone of high
diversity and endemism, but most of the species of high concern are concentrated on
slopes of mountains and koppies, which are largely avoided by the route. Should this
proposed corridor change then damage or destruction to endemic plant species would
be of concern.
However, the proposed powerline corridor traverses areas where there are dense
stands of the endemic Acacia erioloba, including many of appreciable size and age.
Because this is a slow-growing, protected species facing increasing cumulative impacts
country-wide, negative impacts on this species will have to be strictly constrained and
regulated. Illegal collection of plant material such as wood or pods should be prevented
within the construction site, once declared.
A “walkdown” of the proposed pylon sites by a professional botanist, prior to
construction, is recommended.
Given careful planning and placement of pylon sites and mitigation of unnecessary
collateral damage to vegetation specifically, damage to the flora could be very limited
due to the linear nature of the proposed facility and relatively narrow, greatly limiting
the probable extent of impact on any habitat or species.
Small animals that may be resident on the site are likely to move away.
Avifauna:
The proposed construction activities will be restricted to the site and thus potential
impacts on the avifauna are predicted to be low.
A potential impact of construction is that habitat degradation could occur due to
negligence on the part of the Contractor and this may be detrimental to bird breeding
or feeding conditions.
The potential impacts of the proposed development are estimated on the basis of
available data from long-term bird monitoring projects and from experience of impacts
from other power lines.
The field survey will investigate these aspects in relation to the bird species expected
to occur in the project area.
Floodline:
The proposed transmission power line is expected to have little impact on the
environment as it relates to floodlines. The impacts of the environment on the project
will be more significant. In this context the habitat is able to withstand significant
Kokerboom to Auas Transmission Line EIA 73 Version 1 / March 2018 Scoping Report
disturbance without a marked impact on its biodiversity. The affected environment
could thus be categorised as having a high tolerance to disturbance from the envisaged
infrastructure.
No negative impacts are foreseen on the floodline that cannot be effectively mitigated
to an acceptable significance.
The impacts in the construction phase will relate mainly to excavations required for the
pylon foundations. This may require blasting and the disposal of surplus excavation
material.
The floodline assessment will assist in ensuring that the power line route is selected
and optimised taking into consideration the preliminary route identified.
Archaeology and Heritage Resources:
The potential impacts of the proposed development are estimated on the basis of
available data from previous surveys. The proposed development may result in direct
disturbance to or destruction of archaeological remains, early colonial sites and grave
sites, as well as visual impact on the physical setting of the sites. The baseline
archaeological survey undertaken during the assessment phase will confirm the
presence or absence of archaeological sites in the area of the proposed development.
Social:
The positive impact associated with the construction of the proposed transmission line
is the improved transmission network nationally. This impact may serve to enhance the
economy as commercial and private electricity provision becomes more reliable and
consistent potentially enabling business enhancements and a generally better quality
of life. Some direct, indirect and induced employment opportunities will be created by
the Project itself and through procurement spend. Benefits will be limited in the local
area as the successful Contractor (origin still to be determined through an open tender
process) is likely to use skilled workers that are already known and trusted by them.
Some short-term contract employment should be available to local people.
The footprint of the proposed project will not result in the loss of agricultural land; the
transmission line has been aligned to avoid impacts to cultivated land. However,
agricultural activities could be disrupted during the course of the construction activities.
These disruptions could occur as a result of scheduling conflicts, interference with, or
damage to, farm infrastructure, (e.g. fences, gates and water resources).
Typically, an influx of workers and job-seekers can be anticipated into an area where
there are potential job opportunities. Influx can be associated with increased levels of
crime, increased spread of sexually transmitted diseases (including HIV/AIDS),
unwanted pregnancies, domestic violence, alcohol and drug abuse, and increased
levels of tension within the communities.
Kokerboom to Auas Transmission Line EIA 74 Version 1 / March 2018 Scoping Report
5.1.2 Operational Phase Land use:
Few operational impacts are predicted as a result of the proposed development as
NamPower and the surrounding farms have operated successfully in the past and very
few operational changes are expected as a result of the proposed Project. If operational
problems do arise these can be mitigated through altered management actions.
Visual and Sense of Place:
Tourism activities may be more sensitive to the visual intrusion of the power line (and
other infrastructure such as access roads) during the operational phase. These could
impact on the sense of place for some receptors. Where the power line is visible,
specifically from private residences, some of the land owners and users may also
experience a negative effect on sense of place. Not all tourists and land owners will
respond in the same way to the existence of the line. Local experience of existing power
lines, however, indicates that existing lines have not affected tourism or sense of place
for most receptors.
Terrestrial Ecology:
Minimal negative impacts are anticipated on the terrestrial ecology due to the fact that
access to the transmission line is only required infrequently.
Direct destruction of, or damage to, protected and/or endemic plant species, Acacia erioloba in particular. Illegal collection of plant material such as wood or pods. Avifauna:
The potential impacts of the proposed development on the avifauna were assessed on
the basis of available data from long-term bird monitoring projects and from experience
of operational impacts from other power lines.
The main impacts of power line operation on birds are:
Birds colliding with the lines. There are a number of species that are particularly
vulnerable to power line collision, to the extent that they are now considered
threatened specifically because of high mortality rates from power line
collisions resulting in declining populations. e.g. large cursorial birds such as
bustards, Secretarybird, wetland birds (e.g. flamingos), and birds of prey
(mainly vultures and large eagles). All these species have low reproductive
rates. This is the most important environmental issues from the perspective of
avifaunal conservation and power lines.
Birds being electrocuted on the lines, mainly large-bodied species and usually
on the towers, and mainly impacting large slow-breeding species. This threat
has largely been eliminated in the design of modern support structures and the
careful selection of infrastructure.
Kokerboom to Auas Transmission Line EIA 75 Version 1 / March 2018 Scoping Report
Degradation of breeding and/or feeding habitat. Disturbance and destruction of
nests during inspection and maintenance, mainly relevant to threatened
species breeding on the support structures.
The main impacts of birds on power lines are:
Birds causing short-circuits (flash-overs) and potential power outages and
damage to equipment. This can happen when birds are electrocuted, when
fish-eating birds perch above insulators and defecate over insulators;
Birds building nests in support towers which may cause short circuits,
particularly after rain, and catch fire causing damage to infrastructure; and
Defecation on insulators mainly by large, sometimes colonial, fish-eating birds
where power lines pass close to large water bodies.
The field survey will investigate these aspects in relation to the bird species expected
to occur in the Project Area.
Floodline:
The anticipated impacts are related to erosion damage to the access road, the
unsurfaced access track and to the pylons from stormwater runoff.
Archaeology and Heritage Resources:
The predicted impacts on archaeological and heritage resources are the inadvertent
damage to archaeological sites within the project servitude during normal operational
activities, i.e. line maintenance; unregulated public use of servitude tracks resulting in
damage to archaeological sites.
Social:
The positive impact associated with the operation of the proposed transmission line is
the improved transmission network nationally. This impact may serve to enhance the
economy as commercial and private electricity provision becomes more reliable and
consistent potentially enabling business enhancements and a generally better quality
of life.
Some direct, indirect and induced employment opportunities will be created by the
Project itself although this is limited in the operational phase as work is mainly for highly
skilled and technical workers. Bush clearing opportunities do exist. This work should
be available to local Contractors and workers.
Tourism activities may be more sensitive to nuisance factors during the operational
phase.
The presence of transmission lines affects the ease with which helicopters/ gyrocopters
(and similar aircraft) can fly over the farms. These aircraft are used by a small number
of farmers as a means of managing farming activities. Flying becomes increasingly
risky as a result of the lines due to low visibility and an inability to fly close to the ground
Kokerboom to Auas Transmission Line EIA 76 Version 1 / March 2018 Scoping Report
in areas where lines are present. The addition of this proposed line will negatively affect
farm management for some farmers.
5.1.3 Cumulative Impacts
Land use: Limited cumulative impacts on land use are anticipated. Visual:
Visual damage due to uncontrolled creation of unsightly tracks.
Terrestrial Ecology: Acacia erioloba is being over-harvested for wood and for pods at present. Cumulative impacts are likely to be of concern in future.
Avifauna:
Every additional power line constructed poses an additional threat, particularly to
species vulnerable to collision. The more spread-out across the landscape are the
power lines, the greater the threat. Bundling transmission lines as closely as possible
reduces the geographic footprint and thus the exposure of a larger part of the
populations of vulnerable bird species to risk.
Floodline:
It is not expected that there will be long term cumulative impacts of the transmission
power lines running within the same Study Area and at times parallel to each other, on
the stormwater runoff and drainage of the catchments.
The access track will need to be planned carefully to avoid cumulative impacts of
channelling stormwater flows, which could eventually lead to erosion gullies.
The potential impact of floods on the proposed infrastructure is negligible if the
proposed mitigation measures and management actions are implemented. Without
mitigation the impact on the cost of repairs to pylons can be significant. Resulting power
outages can have major downstream impacts on the Namibian economy.
Social: The cumulative visual impact and hence the impact on sense of place, and the
cumulative impact on disruption to farm management - resulting from the addition of
the proposed transmission line - will exacerbate the already negative impacts
experienced as a result of existing lines for some receptors.
Kokerboom to Auas Transmission Line EIA 77 Version 1 / March 2018 Scoping Report
Archaeology and Heritage Resources:
Encroachment of servitude tracks on archaeological sites and possible accelerated soil
erosion as a result of water run-off from compacted track surfaces is a concern. These
potential cumulative impacts can, however, be mitigated.
5.2 Mitigation of Impacts
The basic principle of mitigation is to guide development to either avoid potential
negative impacts or achieve the least possible negative impact on resources. Mitigation
measures and/ or management actions are designed to reduce the consequence or
probability of an impact, or to reduce both consequence and probability. Mitigation
measures will be refined and expanded upon in the detailed assessment phase, with
input from the technical specialists and NamPower. Mitigation measures aim to be
practicable with measurable targets, as far as possible.
The transmission line route has already been altered to avoid impacts on existing
infrastructure and cultivated land. NamPower identified suitable routing options for the
transmission line in consultation with the directly affected land owners, key
stakeholders, and with input from the environmental consultants and relevant
specialists. The realignment has already served to avoid and reduce potential negative
impacts of the proposed Project on socio-economic receptors (notably infrastructure
and cultivated land).
Further mitigation will strive to achieve the following:
Rectification: impact is mitigated after it has occurred e.g. rehabilitation of areas
disturbed by construction;
Compensation: providing a substitute resource for a resource that has been lost
because of the project (e.g. “conservation offsets”);
No action (least preferred); and
Enhancement: establish optimisation measures that will enhance the benefits
of the positive impacts.
Landuse: Mitigation of potential impacts will take the form of restriction of working areas and access routes and the rehabilitation of the construction phase track used during the stringing of the transmission line. Visual and Sense of Place: Visual disturbance and loss of sense of place can be largely mitigated by the sensitive alignment of the power line to avoid sensitive receptors and the use of the least visually intrusive infrastructure, as well as the careful placement thereof when the final alignment and pylon positioning is determined.
Kokerboom to Auas Transmission Line EIA 78 Version 1 / March 2018 Scoping Report
Terrestrial ecology: Whenever possible trees, in particular camel thorn trees (Acacia erioloba), should be trimmed rather than destroyed. This applies particularly to the construction and operational phases. Wherever possible pylon sites should be carefully selected and placed so as to avoid pan edges, banks of rivers and other drainage lines, and large camel thorn trees. Creation of additional tracks, including those made by bulldozers and other large construction vehicles, outside of the service track should be not be permitted unless absolutely necessary. Staff camps should be pre-determined and marked. Penalties should be in place for all Contractors and Sub-contractors that cause unnecessary collateral damage. Random collection of wood for fuel and/or heating should be forbidden. No harvesting of wood by operational/maintenance staff should be permitted. Any wood used by staff for any purpose whatsoever must be permitted wood supplied by the farmers along the route themselves, or be invader species wood sourced from elsewhere. Plant collection of any plants or parts thereof, including seeds and pods, should be forbidden. Penalties, including dismissal for repeat offenders, should be in place for all transgressors. Avifauna:
Avifaunal mitigation measures for power lines typically focus on (a) alignment to avoid
potential risk areas, (b) means to limit habitat degradation, (c) ways to reduce birds
colliding with lines, (d) avoid electrocution and (e) reduce the likelihood of flash-overs
that may cause power disruptions and damage to equipment. In addition, the
Environmental Management Plan usually requires a level of monitoring that would
reveal any unanticipated impacts.
The issue of birds colliding with power lines is usually significantly more important than
the other potential impacts. Reducing the extent of collision is usually best approached
by:
Aligning the power line to avoid the proximity of wetlands and bird flight paths,
as well as habitat that supports high populations of vulnerable species. In the
case of perhaps the most vulnerable cursorial species in the area of the
proposed Kokerboom to Auas 400kV transmission line, Ludwig’s Bustard, Kori
Bustard and Secretarybird, the gentry undulating sparsely vegetated shrub
karoo and semi-arid gravel and sandy plains of the savanna biomes, with
somewhat more vegetated ephemeral drainage lines to the east of the
Windhoek to Keetmanshoop road would be expected to support larger
populations of these high-risk species than the more broken, rocky and hilly
terrain to the west of the road;
Kokerboom to Auas Transmission Line EIA 79 Version 1 / March 2018 Scoping Report
Bundling power lines as closely together as possible, to reduce the geographic
impact across the population distribution of high-risk species;
Where an existing line of the same type (e.g. an existing 400 kV line of the same
configuration) exists, aligning the proposed new line as closely as possible to
this, so that the line and tower heights are approximately the same;
Adjusting the distribution of the support structures of the proposed new
transmission line to fall approximately mid-way between the support structures
of the existing line. This could increase the visibility of both lines, each mitigating
potential mid-line collision of the other, and may have a significant impact on
reducing the incidents of collision on both lines. It may also reduce the need for
the use of line markers; and
If, after field assessment, collision is considered to be a significant risk in
sections of the line, then line markers (e.g. flappers) may be considered for high
risk areas.
The design of the towers, insulators and line configuration is important to avoid
electrocution. Fitting perch dissuaders (e.g. wire brushes) above insulators or providing
alternative perch sites have been used where birds foul insulators, causing short
circuits. These possible mitigation approaches will be considered if due justification is
found from the field assessment.
Floodline: The footprint of construction activities must be clearly defined, especially during the initial clearing and levelling operations. Pylon footings must avoid all streams where possible. Where footings must, of necessity be placed in stormwater run-off channels they must be protected against erosion. Movement of vehicles needs to be strictly monitored. The access route must be identified and pegged before any construction work commences. Existing roads must be utilised where possible. Monitoring of erosion following any stormwater runoff is required so that damage can be assessed and repairs effected. It is recommended that more detailed studies be carried out during the assessment phase to make specific recommendations regarding the mitigation measures and management actions. Archaeology and Heritage Resources:
The basic principle of archaeological mitigation is to guide development to achieve the
least possible impact on protected archaeological resources. Thus, field survey,
documentation and evaluation of archaeological sensitivity are indispensable
precursors of mitigation. The field survey results not only inform the process towards
mitigation but also serve as a basic record of the archaeology in the event of inadvertent
impact. Where impact is an unavoidable consequence of development full
Kokerboom to Auas Transmission Line EIA 80 Version 1 / March 2018 Scoping Report
archaeological mitigation is required to comply with national laws, international
guidelines and professional best practice standards. This may involve higher level
documentation, collection and removal of archaeological remains and excavation of
sites such as graves. The decision as to the most appropriate mitigation course is taken
by the NHC in light of recommendations set out in a project mitigation proposal.
Archaeological mitigation may also include the fine adjustment of the power line
alignment during the “walkdown”, demarcation of archaeological “no-go” areas and
buffer zones for the positioning of pylons, buffer zones for deviations in the servitude
track; the proclamation of archaeological Conservation Areas under the National
Heritage Act, and negotiation of substantial changes in the project footprint. It is an
important principle that damage to archaeological sites is irreparable and must
therefore be avoided if at all possible. It is a further principle, also held in the National
Heritage Act, that both the archaeological site and its physical/ visual setting are
protected under the law. At all times the precautionary principal should be applied.
No specific sites are recommended for such actions at this stage. An Archaeological
Chance Finds procedure contains guidelines for mitigation of new archaeological finds
that may be made in the course of construction and operation and will be incorporated
into the EMPs for the Construction and Operational phases.
It is therefore likely that archaeological remains, if present, have been disturbed or
damaged. Disturbance or destruction of archaeological remains during construction is
a risk, as is the potential negative impact on the physical landscape setting of
archaeological sites.
Should artefacts be found these must be appropriately managed to avoid negative
impacts and preserve the remains and applicable legislation followed. If found, the
immediate advice of a professional archaeology specialist or the NHC must be sought
in this regard before any further damage is done. The area should be immediately
marked and cordoned off until expert instruction is obtained. Detailed documentation
should be kept and possible excavation of affected archaeological sites be actioned,
following advice.
Social:
Mitigation measures include the restriction of working hours, location of Contractor’s
Camps, a protocol for the communication of complaints, which will all be contained
within the EMP for the construction phase.
5.3 Summary of Identified Potential Impacts
Potential environmental and social impacts of the proposed construction and operation
of the 400 kV power line between the Kokerboom and the Auas Substations were
assessed as part of the EIA process. These potential positive and negative impacts
were spread through the four project phases. Some of the major impacts and the
proposed mitigation measures within each of the project phases.
Kokerboom to Auas Transmission Line EIA 81 Version 1 / March 2018 Scoping Report
Pre-Construction Phase
The first site activities before mobilization of equipment will be a survey, required for
final design of power line structures. It is advisable that walk downs by the vegetation,
avifaunal and heritage specialists be undertaken, and be used to inform the final pylon
prior to their finalisation. These are only required in areas that have been identified as
being sensitive. The avifaunal walk down should identify the spans that will require
mitigation devices to be installed, if required. There could be negative impacts on land
associated with storage of construction materials especially if on agriculturally
productive land or land utilised for wildlife tourism. Expectations of improvement in
livelihood among locals must be addressed. Construction contracts will include
environmental monitoring and management procedures and requirements. These must
be in place prior to the commencement of any construction activities.
Construction Phase
This phase of the activity will have both positive and negative impacts. The positive
impacts are some employment opportunities offered to the construction workers and
any other labourer who will be hired to provide their services during the construction
phase. The negative impacts would include wastes generated, accidents, health and
safety, air, dust and noise pollution, vegetation clearance, soil erosion, socio-
environmental issues, loss of trees, and compaction of soil. Most of the negative
impacts are minor and temporary. To mitigate negative impacts, the contractor shall
ensure that all staff have adequate protective clothing and are adequately trained. The
whole range of mitigation measures are however, outlined in the EMP for the
construction phase in this regard.
Operational Phase
The proposed project will have minimal negative effects which mainly relate to loss of
aesthetic value as well as nuisance to affected landowners. Operationally-related
nuisances (noise, dust, litter, disruption to livelihoods and activities) can be fully
mitigated to acceptable levels, provided mitigation measures stipulated in the EMP are
followed. An environmentalist from within NamPower’s SHEW Section should be
employed throughout the operation and during all maintenance activities on the line to
ensure mitigation is effectively implemented.
Decommissioning Phase
As with any project, the facilities used in this project will have a lifespan after which they
may no longer be cost effective to continue with operation or may degrade and become
inoperable. At that time (> 30 years after construction of the power line), the project
would be decommissioned, and the existing equipment removed and most likely
replaced. The mitigation measures highlighted in the construction phase will once again
become applicable as the construction of new infrastructure would essentially be
associated with similar activities and would likely result in similar impacts. The disposal
of materials from the decommissioned structures is not viewed as high risk. Much of
the material would be recyclable (steel structures) or inert (insulators, concrete
foundations, etc.). Very little contaminated soil, if any, is expected. These materials
would, however, need to be disposed of at a formal waste disposal or recycling centre.
Mitigation measures implemented during construction phase with regards to site
establishment and equipment will remain the same for the decommissioning phase.
Kokerboom to Auas Transmission Line EIA 82 Version 1 / March 2018 Scoping Report
Only existing access roads shall be used. Ongoing stakeholder involvement (via
community leaders and key affected stakeholders) is also recommended during this
phase, including notification of start and process to be followed, activities expected and
their scheduling, community health and safety, as well as a reporting channel should
problems arise. All exposed soil surfaces shall be revegetated to limit erosion. All exotic
vegetation must be removed from the site.
Based on the above information, it is unlikely that the project will have many adverse
social and environmental impacts. Most adverse impacts will be of a temporary nature
during the construction phase and can be managed to acceptable levels with
implementation of the recommended mitigation measures for the project such that the
overall benefits from the project will greatly outweigh the few adverse impacts. All the
negative impacts will either be moderate or lesser in rating and could be easily
mitigated. Generally, the proposed power line will result in appreciable benefits to the
people of Namibia and accompany opportunities for development in the country.
The potential impacts identified during the construction and operational phases are
summarised as follows:
Environmental Aspect
Project Phase Significance of Potential
Impact without Mitigation
Significance of Potential Impact with Mitigation
Avifauna Construction Low (-) Low (-)
Operation High (-) Low (-)
Flora Construction Low (-) Low (-)
Operation Low (-) Low (-)
Fauna Construction Low (-) Low (-)
Operation Moderate (-) Low (-)
Archaeology and Heritage Resources
Construction Moderate (-) Low (-)
Operation Low (-) Low (-)
Floodlines Construction Low (-) Low (-)
Operation Low (-) Low (-)
Social Construction (Disruption to livelihoods, activities and lifestyles, Destruction or disruption of homesteads and farm infrastructure)
Low-Medium (-) Very Low (-)
Operation (Change of sense of place, Disruption to farm management)
Moderate (-) Low-Moderate (-)
Economic Construction (Employment and procurement)
Low (+) Low-Moderate (+)
Operation (benefits to the economy)
Low-Moderate (+)
Low-Moderate (+)
Kokerboom to Auas Transmission Line EIA 83 Version 1 / March 2018 Scoping Report
Note: 1. These findings are from a preliminary assessment and will be confirmed in the
Impact Assessment phase of the EIA through detailed studies. 2. Impacts can be Negative (-), Neutral (*) or Positive (+). 3. The significance of a potential impact is based on the combination of
consequence of the impact and probability of the impact occurring, and defines the level to which the impact will influence the proposed project and/or the environment. It determines whether mitigation measures need to be identified and implemented or whether the resource is irreplaceable and/or the activity has an irreversible impact. Significance is rated as either Low, Moderate (Medium) or High.
This assessment, by the EAP, was based on the technical specialist’s scoping reports
on the sensitivity of the receiving environment, as well as the advice of Dr. Simmons
(avifaunal specialist).
Given the low significance of negative potential impacts, and the potential for positive
impacts of a high significance on social and economic development, as well as the fact
that the proposed project will have a positive impact on the ability of NamPower to
continue providing the services of power, the scoping phase of the EIA recommended
that the proposed project be subject to a detailed assessment. During this phase it is
proposed that EMPs for the construction and operational phases be prepared. These
EMPs would contain all the mitigation measures/ management actions, proposed by
the technical specialists and EAP, to avoid or reduce the potential negative impacts
and be implemented by the responsible parties, should the proposed project receive
Environmental Clearance.
It was not recommended that the ‘no-go’ alternative be considered given the
importance of the proposed additional power line between the Kokerboom and the
Auas Substations in the overall power supply system in Namibia.
Kokerboom to Auas Transmission Line EIA 84 Version 1 / March 2018 Scoping Report
6 PUBLIC CONSULTATION PROCESS
As required by the Environmental Management Act (Act No. 7 of 2007) and in terms of by the EIA Regulations, 2012, and the Competent Authority, a public consultation process (or Public Participation Process - PPP) was undertaken as part of the EIA process (refer to Appendix E: Public Participation Information for documents relating to this process and referred to below). The pubic consultation process aimed to inform all I&APs and Organs of State of the proposed transmission line project and the potential environmental impacts thereof. The process was considered adequate and special attention was given to the involvement of local communities within the proposed power line corridor. The process was facilitated in such a manner that all potential I&APs were provided with a reasonable opportunity to comment on the Application. All the comments received were recorded and responded to and this was captured in the Comments and Responses Report, as prescribed in the EIA Regulations, and is appended as Appendix E6: Comment and Response Report. As of 25 May 2016, seventy seven (77) I&APs were pre-registered to be included in the public consultation process. Most were Organs of State, neighbouring landowners and non-governmental Organisations, as required by the EIA Regulations. Each pre-identified individual/ organisation was included on the Register of I&APs (Appendix E8: Register of Interested and Affected Parties) and sent an individual letter requesting their involvement in the EIA process (Appendix E2: Written Notices Issued). The I&AP Register has grown significantly as the EIA process has progressed. This has been via word-of-mouth and active approach by the EIA Team. Information about the proposed project was disseminated to I&APs and the Organs of State via:
One–on-one meetings (and follow-up communication) have been held throughout the Scoping phase with pre-identified potentially affected landowners neighbouring landowners (Appendix E4: Communication to and from Interested and Affected Parties)
Regional Councillors from the three affected regions are registered I&APs.
Notice Boards placed on site at the Auas and Kokerboom Substations, as well as where the existing transmission powerlines traverse the national road, informing the public about the proposed project and the EIA process, process for registering on the register of I&APs, as well as the details for the public meetings (Appendix E1: Proof of Site Notice). These notices have been in place since May 2016.
Notices placed at public places, for example at shopping centres, bus stations, clinics etc. informing the public about the proposed project and the EIA process, process for registering on the register of I&APs, as well as the details for the public meetings (Appendix E2: Written Notices Issued). These notices were placed in May 2016.
Advertisement of the proposed project and the EIA process in the Republikein and The Namibian Newspapers for two consecutive weeks, namely on 03 and 10 May 2016 (Appendix E3: Proof of Newspaper Advertisements).
Introductory Letter sent to all neighbours and pre-identified I&APs within the proposed power line corridor inviting them to register as well as inform others
Kokerboom to Auas Transmission Line EIA 85 Version 1 / March 2018 Scoping Report
about the proposed project and EIA process Appendix E2: Written Notices Issued). The letter was sent in 25 April 2016.
Invitation to the public meetings sent to all neighbours and pre-identified I&APs within the proposed power line corridor (Appendix E2: Written Notices Issued) on 29 April 2016.
Documentation placed on a website (www.Lithon.com)
Public Consultation Office with which I&APs could communicate with verbally, via email, fax and post. This office has been operational since June 2015.
Public meetings held between 30 May and 01 June 2016 at the following venues:
- Keetmanshoop Show Hall, Keetmanhoop - Tses Community Hall, Tses - Gibeon Community Hall, Gibeon - Mariental Hotel, Mariental - Kalkrand Community Hall, Kalkrand - Hermann van Wyk Memorial Hall, Rehoboth - Dordabis Farmer’s Association Hall, Dordabis and - NamPOwer Convention Centre, Windhoek.
The Minutes of these meetings which were distributed to all attendees of the meetings on 16 June 2016 (Appendix E5: Minutes of any public or Stakeholder Meeting).
Forty six (46) I&APs have commented on the EIA process to date (for a copy of the I&AP details refer to Appendix E6: Comment and Response Report). Comment received during the Scoping phase fell broadly into the following categories:
Support of the conclusions and recommendations of the scoping assessment (as presented at the public meetings)
Confirmation of the need for the proposed project due to the unreliable electricity supply in the area and the need to strengthen the counties’ overall transmission line network, and the encouragement of NamPower to construct the proposed project
Support for the proposed EMPs for the construction and operational phases in order to mitigate potential detrimental impacts
Concerns over the impacts on avifauna, change of sense of place, long-term
disruption to livelihoods and life (including homesteads and farm infrastructure)
as well as short-term disruption to farm management. Suggestions were made
to realign the powerline away from established infrastructure to minimise/ avoid
impacts to livelihoods.
A number of specific mitigation measures/ management actions were proposed
for investigation in the Assessment Phase.
Public consultation process: request to be registered and informed as the process proceeds
Copies of comment received are appended in Appendix E7: Copies of Comment Received and transcribed and responded to in Appendix E6: Comment and Response Report. The public consultation process is ongoing and will continue into the assessment phase, with a review of the draft Assessment Report and a further round of public meetings to obtain comment on the Assessment Report before it is finalised.
Kokerboom to Auas Transmission Line EIA 86 Version 1 / March 2018 Scoping Report
7 CONCLUSIONS AND RECOMMENDATIONS
Given that the realignment of the proposed Kokerboom to Auas Substation
transmission power line corridor (i.e. screening of alternatives) has already served to
avoid and reduce potential negative impacts of the proposed project on the
environment, the low significance of any predicted negative potential impacts (after
mitigation/ management action is implemented) and the potential for positive impacts
of a high significance on the social and economic development, as well as the fact that
the proposed transmission line project will have a positive impact on the ability of
NamPower to continue providing the services of power, this Scoping Report
recommends that the proposed EIA process proceed into the next phase.
Specific conclusions and recommendations of the appointed technical specialists are
as follows:
Vegetation
The proposed power line corridor traverses three distinct vegetation zones, of which
the Highland Savanna is the most sensitive, supporting numerous endemic and/or
protected species. However, in that zone most of the species of high concern occur on
the slopes of koppies and mountains, which are largely avoided at present.
Impact throughout the route will be highest on protected trees, which must be
conserved as far as possible. Given careful placement of pylon sites and strict control
of tree removal and unnecessary collateral damage, as well as uncontrolled wood/pod
harvesting, the impact on plants could be relatively low. The species of highest concern
is camel thorn (Acacia erioloba).
The vegetation specialist further recommended that a field study for vegetation was
unnecessary for this proposed project and EIA process, unless the transmission line
corridor route reviewed here is altered such that it impinges to an appreciably greater
extent on the higher slopes and koppies of the Highland Savanna, in which case a field
study should be undertaken.
Avifauna
Power lines across the Karoo and semi-arid Tree-and-shrub Savanna biomes, in both
Namibia and South Africa, have been shown to have a significant impact on some bird
species, mainly as a result of birds flying into the lines. Ludwig’s Bustard, Kori Bustard
and Secretarybird are all listed as Threatened Red Data species. In the case of the
bustards, the main cause of mortality appears to be power line collisions, resulting in
significant population declines. For a number of other large Red Data bird species such
as flamingos, vultures and eagles, power line collision is an important contributing
factor to the level of threat that they face. Effective and cost-efficient mitigating
measures to power line collision are proving to be elusive, and the current best practice
approach is to bundle lines as closely as possible, avoid high risk areas and deploy line
markers.
Kokerboom to Auas Transmission Line EIA 87 Version 1 / March 2018 Scoping Report
This proposed transmission line offers the opportunity to test placing the two 400 kV
lines closely parallel to one another, with support towers of the new line mid-way
between those of the existing line. This might prove to be the most effective mitigation
measure to birds colliding with the lines, driving birds to fly higher and over the lines.
Because of the high risk posed to birds mainly by collision with power lines, all proposed
lines should be carefully evaluated in the field as part of the overall environmental
assessment, with particular attention on how bird collision could be mitigated.
Following the avifaunal specialist’s (Dr. Chris Brown) highlighting of the sensitivities
within the proposed power line corridor and his recommendations to slightly reroute the
power line corridor centreline and stagger the pylons with that of the existing 400 kV
power line for part of its route another independent specialist (Dr. Rob Simmons) was
asked to investigate and verify the validity of these recommendations. He visited the
power line corridor and undertook further detailed avifaunal surveys. He concurred with
Dr. Brown’s recommendations and specifically recommended that two most important
high risk areas from an avifaunal perspective should be avoided, namely the:
1. Karas Dwarf shrubland where collision-prone bustards are at high density and
risk from a new 400 kV line, and the
2. Ecotone between the Dwarf Shrub and Kalahari Savanna near Kalkrand where
breeding and Endangered White-backed Vultures and Lappet-faced Vultures
occur on the farms Wilderness Rem, Battle and Friesenland.
He suggested the avoidance of the above sensitive areas by rerouting the power line.
The proposed centreline (refer to Figure 15: Proposed rerouting of bird-friendly
proposed Auas – Kokerboom 400 kV transmission line overleaf) would head south
from the Auas Substation and then south of Rehoboth it would join the existing 400 kV
line to the south-west in the most direct and engineeringly-feasible way south of the
C25. The proposed centreline of power line would then run parallel with the existing
400 kV line all the way to Kokerboom substation with staggered pylons i.e. the tower of
one line lies in the mid-span of the adjacent line.
Kokerboom to Auas Transmission Line EIA 88 Version 1 / March 2018 Scoping Report
Figure 15: Proposed Routing of Bird-friendly proposed Auas – Kokerboom 400 kV transmission line.
The two avifauna specialists concurred on their recommendations for the final proposed
realignment of the centreline of the power line from the Kokerboom to the Auas
Substation (a distance of approximately 448 km) – this will subsequently be known as
the “bird” friendly” deviation of the proposed centreline in the EIA process. This included
the pylons of the new 400 kV power line being staggered with that of the existing
400 kV power line (the tower of one line lies in the mid-span of the adjacent line).
Floodline
Although at least 300 km of the 500 km proposed transmission line corridor will not be
impacted by flooding there are some significant drainage catchments in the northern
part of the proposed transmission line corridor.
No negative impacts are foreseen during the construction and operational phases that
cannot be effectively mitigated to an acceptable significance. The potential impact of
floods on the proposed infrastructure is expected to be negligible if the proposed
mitigation measures and management actions are implemented. Without mitigation the
impact on the cost of repairs to pylons can be significant. Resulting power outages can
have major downstream impacts on the Namibian economy.
Kokerboom to Auas Transmission Line EIA 89 Version 1 / March 2018 Scoping Report
Recommended mitigation measures during the construction phase include:
Halting construction activities in the rivers when there is flow
Not storing equipment or materials in the 1 in 100 year flood zone of the river Recommended mitigation measures during the operational phase include:
Proper design and construction of the access track to ensure that it does not create an obstacle to the flow
Not constructing pylons in the flood zone of the rivers, alternatively if pylons have to be constructed within the flood zone and the
Provision of proper erosion protection to pylon bases.
Archaeology
The proposed power line corridor will traverse of potentially sensitive archaeological
landscape. Previous archaeological surveys in this area have revealed traces of
intermittent human occupation over the last approximately 400 000 years. Early colonial
settlement remains including graves are a significant feature of this area. The baseline
archaeological survey will locate and document any sites that may be affected by the
proposed development and this will form the basis of a detailed archaeological impact
assessment.
Social
The potential negative social impacts of the construction phase are expected to be
relatively minor and manageable through effective mitigation.
The positive impact associated with the construction and operation of the proposed
transmission line is the improved transmission network nationally. This impact may
serve to enhance the economy as commercial and private electricity provision becomes
more reliable and consistent potentially enabling business enhancements and a
generally better quality of life. Some direct, indirect and induced employment
opportunities will be created by the Project itself and through procurement spend.
Benefits will be limited in the local area as some short-term contract employment should
be available to local people.
The negative impacts linked to the proposed Project are likely to be localised and affect
land owners, land users and tourists differently. Existing agricultural activities will
largely be able to continue unhindered during the construction and operation phases.
Planning and control will be required to minimise disruptions during construction.
Tourism activities may be more sensitive to the construction phase nuisance factors
and the visual intrusion of the line during the operational phase; these could impact on
the sense of place for some receptors. Where the transmission line is visible,
specifically from private residences, some of the land owners and users may also
experience a negative effect on sense of place. The power line may negatively affect
farm management in some cases. The cumulative visual impact and impact on sense
of place, and the cumulative impact on disruption to farm management will be assessed
in more detail in the assessment phase.
Kokerboom to Auas Transmission Line EIA 90 Version 1 / March 2018 Scoping Report
It is not recommended that the ‘no-go’ alternative be considered further given the
importance of the transmission lines between the Kokerboom and Auas Substations in
the overall power supply system in Namibia. As the existing transmission lines cannot
cope with Namibia’s future power requirements, it is recommended that an additional
power line be installed between the two Substations provided:
A bird-friendly centreline be investigated further;
The technical specialists assess the proposed power line corridor with the view
of identifying potential impacts; and that the
Proposed mitigation measures/ management actions recommended by the
specialists and I&APs be implemented and monitored.
It is anticipated that construction- and operational-related nuisances can be fully
mitigated to acceptable levels, provided mitigation measures are stipulated in the EMPs
for the construction and the operational phases are followed. It is recommended that
all the suggestions for mitigation measures/ management actions/ monitoring
suggested by the technical specialists and EAP be implemented in order to avoid and/
or minimise any potential negative impacts and enhance any positive impacts.
It is therefore concluded that the recommendation from this Scoping Assessment is that
the EIA should proceed into the assessment phase and that this assessment be
undertaken as proposed in Appendix G: Terms of Reference for the Detailed
Assessment. The assessment phase will culminate with the preparation and
submission of an Assessment Report to the Environmental Commissioner for his
decision on the ECC Application. EMPs for the construction and operational phases
will be included in the Assessment Report. The objectives of an EMP are to:
Ensure compliance with all relevant legislation and Regulations with bearing on the
proposed project.
Verify environmental performance through information on impacts as they occur.
Provide required management actions in order to respond to unforeseen events.
Provide feedback for continual improvement in environmental performance.
Refine identified mitigation measures to further reduce potential impacts to minimal
or insignificant levels.
Stipulate specific actions to assist in mitigating the environmental impact of the
project.
Identify measures that could optimize beneficial impacts.
Create management structures that address the concerns and complaints of
Interested and Affected Parties (I&APs) with regards to the proposed project
(development).
Establish a method of monitoring and auditing environmental management
practices during all phases of the activity.
Ensure that environmental safety recommendations are complied with.
Specify time periods within which mitigation measures must be implemented, where
appropriate.
The completion and operation of the project (should it receive the necessary
Environmental Clearance) is not delayed due to problems with landowners.
Kokerboom to Auas Transmission Line EIA 91 Version 1 / March 2018 Scoping Report
Included in the EMPs are details of the roles and responsibilities of all parties involved,
specifications for vegetation and soil management, an Archaeological Chance Finds
Procedure, as well as an avifaunal monitoring plan for both pre- and post- construction.
The latter monitoring plan is particular important given the avifaunal sensitivities within
the Study Area as well as the mitigation proposed by the avifaunal specialists, which is
new and as yet ‘untested’.
Based on the outcome of this detailed assessment and the contents of the Assessment
Report the Environmental Commissioner will decide whether Environmental Clearance
Certificate be granted for the proposed construction of the transmission power line
between the Kokerboom and Auas Substations, in terms of in terms of the
Environmental Management Act, 2007, (Act No 7 of 2007) and the Environmental
Impact Assessment Regulations, 2012.
Should the proposed project receive a Clearance Certificate by the environmental
authorities and after negotiations for a final alignment with landowners, the centre line
of the power line and co-ordinates of each bend point must be determined. Optimal
pylon types and positions must be identified and verified. The draft EMPs for the
construction and operational phases may require updating after this “walkdown”.
Kokerboom to Auas Transmission Line EIA 92 Version 1 / March 2018 Scoping Report
8 REFERENCES
Giess, W. 1998. A preliminary vegetation map of Namibia. Dinteria 4: 1 – 112. Klaassen, E.S. and Kwembeya, E.G. (eds). 2013. A Checklist of Namibian Indigenous and Naturalised Plants. Occasional Contributions No. 5, Windhoek: National Botanical Research Institute. Loots, S. 2005. Red Data Book of Namibian Plants. Southern African Botanical Diversity Network Report 38. Pretoria: SABONET. National Herbarium of Namibia (WIND). 2015. BRAHMS Database. National Herbarium of Namibia (WIND). Windhoek: National Botanical Research Institute. Roads Authority of Namibia. 2012. Namibian Drainage Manual.
Deacon, J. 1984. The Later Stone Age of southernmost Africa. Oxford, BAR. Namibia Statistics Agency. 2015. Namibia Labour Force Survey 2014 Report. Namibia Statistics Agency, Windhoek.