Promo - ZJ1001 Cape Lambert Temporary Works Design
Project: Cape Lambert B
Client: Rio Tinto
Contractor: John Holland
Year: 2010-11
Contract period: 9 months
Project scope:
Seconded to John Holland for design of
temporary works for Cape Lambert Wharf
including dolphin piling frame and personnel
access.
Roam Marine personnel scope:
Work involved in several aspects of the
temporary works design and method statements
• Crane gantrys
• Crane runway beams
• Dolphin Piling frame
• Scaffold and access structures
Promo - ZJ1001 Cape Lambert Temporary Works Design
• Temporary bracing of the wharf
• Equipment trolleys
• Strengthening of existing service jetty for 280t
Crane.
• Pile Lifting
• Amenity structures