prolongation cost in eot claims

Upload: albert-lucky

Post on 08-Jul-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/19/2019 Prolongation Cost in Eot Claims

    1/3

     

    PROLONGATION COST IN EOT CLAIMS

    Once a Contractor has secured an extension of time and relief from liquidated

    damages, thoughts will quickly turn to recovery of the costs incurred due to

    the delayed completion date – i.e. “Prolongation Costs.

    !f you ask an "mployer#s $% how such costs should &e determined the answer

    is often an unequivocal statement that the rates and prices from the

    Preliminaries 'O$ shall &e divided &y the original contract duration and the

    derived daily rate for preliminaries shall then &e applied to the extended

    duration. (he sharp witted "mployer#s $% may even refine this logic with the

    caveat that the 'O$ rates and prices should first &e ad)usted to remove fixed

    costs, mo&ili*ation and demo&ili*ation costs, overheads and profit.

     +hilst &oth answers are quite wrong, these approaches are often used in order

    to achieve result, despite the inaccurate answer. (he pro&lem is that neither

    approach attempts to address the underlying question of what costs losses

     were actually incurred &y the Contractor as a consequence of the delaying

    events for which the "mployer was responsi&le. (he answer to this question

    cannot &e found in the 'O$, &ut can -and should &e found in a detailed

    analysis of the Contractor#s cost records (he express wording of the contract

     will dictate which heads of claim are admissi&le, &ut in general terms an

  • 8/19/2019 Prolongation Cost in Eot Claims

    2/3

    accurate understanding of Prolongation Cost entitlement can &e derived &y

    application of the following &asic principles/

    0Identify the events that gave rise to the extension of time – as it is the cost loss

    arising from these events that the Contractor is entitled to recover1

    0Identify the point in time that the delay occurred – a common mistake is to

    identify the costs that were incurred over the extended duration at the end of

    the contract period. (his is incorrect. (he delay may have occurred prior to

    full mo&ili*ation and thus the actual costs incurred at that time may &e lower1

    -Identify the direct costs that follow from the compensable delay events – the

    Contractor is not entitled to costs arising from delay events for which it is

    responsi&le. %eparation of the two can defeat arguments that the claim is

    glo&al and includes elements of the Contractor#s own culpa&ility1

    0Assess only time related costs and not one off capital costs – time related costs

    are those which necessarily arise as a consequence of additional time spent on

    the pro)ect and would typically include staff salaries1 insurance, rents, utilities,

     &onds, accommodation, office services, car leases 2 running costs, etc. &ut

     would not include purchase costs of offices, photocopiers, vehicles etc.

    0Exclude task related costs – a common mistake is to include task related costs

    -e.g. la&our, plant hire or scaffolding costs that would have &een incurred in

    any event. (hese costs may only have &een incurred at a later point in time

    and are therefore not additional. %uch costs would need to &e separately

    recovered through a properly formulated disruption cost claim1

    0Exclude profit – the purpose of the claim is to put the Contractor &ack into

    the position it would have &een, &ut for the delay. 3Profit# is not 3cost# and thus

    any claim for profit can only &e &y way of a 3loss of opportunity# claim – which

    may &e expressly precluded &y the wording of the contract and would in any

  • 8/19/2019 Prolongation Cost in Eot Claims

    3/3

    case have to &e proved, i.e. that opportunities did in fact present themselves

    and were refused &ecause key resources could not &e released from the

    delayed pro)ect1

    0Allow for off-site costs – costs incurred in the Contractor#s head office -and

    elsewhere may &e as a direct result of the pro)ect delay. (he fact that these

    costs were incurred off site does not mean that the Contractor is not entitled to

    receive them1

    0If possible, avoid formulae for determining overheads -e.g. 4udson#s, "mden#s

    etc. – unless you are a Contractor and you fully understand the &asis of your

    3loss of opportunity# claim and how to present it5 'y indentifying actual

    incurred overhead costs rather than rely on theory &ased formulae that

    commonly produce high assessments1

    0Interest / Finance Charges – remem&er that charging interest on a de&t may

     &e prohi&ited in your )urisdiction or &y your contract. 6ost interest or finance

    claims suffer from a lack of facts and are commonly/ unsupported, theoretical

    assessments of loss. 4owever, a skilled claimant can often find ways to lend

    credi&ility to this type of claim.