eAM Projects Process Overview Page 2 as at Sunday, 12 February 2012
GL PostingOption
Account Option Interface Accountingto GL
Project Transactions
Manufacturing N/A All accountingfrom Inventory
Accounted byInventory
Projects Use Auto Accounting
Not from Inventory.PA Send to GL
PA generates
Projects Send Accounts toPA
Not from Inventory.PA Send to GL
Accounted byInventory
Very briefly, the implication of this table is that you may choose to generate the accounting for projectrelated eAM transactions from either eAM or from Projects. The gotcha with the latter approach isthat all eAM transactions must then flow into GL through PA and that requires a common project(sort of a dummy project used by non-project related transactions 3).
Our site chose to generate the accounting from eAM, using project specific work orders. Thisrequires an additional project definition step for each new project, during which the appropriate WIPclass is linked to the new project (Project Parameters form in Project Manufacturing application).
The Process FlowSo having completed the set-up, what happens when project related WO transactions are processed?The following diagram provides an overview and assumes that both Inventory issues to projects (MTL/ material transactions) and eAM / WIP transactions:
WIPTransactions
Expenditure InquiryWindows
Transaction Interface
Projects
Transaction ImportProcess
Maintenance (eAM)
General Ledger
SubLedger Accounting
Create Accounting Process(Cost Management SLA)
Cost CollectorProcess
Transactionscreated in eAM
MTLTransactions
Inventory
Transactionscreated in INV
Note the implicit sequence in which the processes run:Cost Manager (Inventory process: creates costing and accounting)
Create Accounting & Transfer to GL (Cost Mgmt SLA)Cost Collector (Project Manufacturing)Transaction Import (Projects)
These processes deal transparently with both sources i.e. WIP and MTL; it is only necessary tounderstand them separately when troubleshooting transactions that get stuck.
The Cost Manager is called to calculate the cost of the transaction and to assign the accounting to it.In our configuration, this was unchanged by the implementation of Project Manufacturing. If you are,however, new to the Inventory / Manufacturing applications, the Cost Manager can be a dauntingnew dis covery. If it fails, you will see pending transactions reported during month -end processingand be unable to close the Inventory period 4. Typically your Inventory / Finance team will follow theseup prior to running Create Accounting at month-end.
The Cost Collector process is then run from the Project Manufacturing application to assign projectattributes to transactions and to transfer them to the Projects Transaction Interface. One of ourbiggest challenges was in understanding where the Cost Collector was looking for those values.
-
8/10/2019 Projects eAM JD.pdf
3/24
eAM Projects Process Overview Page 3 as at Sunday, 12 February 2012
Briefly, we needed to add project attributes to resources and departments as well as making all ourHR Organisations also Expenditure Organisations. (For further detail see also Phil Millers OAUG2010 presentation Understa nding the Transactional Flow .5
A second challenge was in understanding that once the Cost Collector has attempted to process atransaction, there is no way to reset the error flag at application level this must be done using SQL.(Refer to MOS # 422044.1 for support instruction for this SQL.)
Briefly it is necessary to:
Identify the problem that caused the Cost Collector to fail and fix that first.
In the underlying table WIP_TRANSACTIONS or MTL_MATERIAL_TRANSACTIONS reset theflag on the specific transaction i.e. update field PM_COST_COLLECTED changing it fromE to N
Rerun the Cost Collector 6
Once the Cost Collector has completed successfully, you can run Transaction Import from withinProjects. Note that when submitting this process, you must specify a transaction source. Thefollowing diagram 7 indicates how to understand these:
Of course, we know all of this now but our first inkling that we had a problem was when we ran thereport EXC: Transaction Exception Details by GL Period in Projects and it gave us 1,200 pages oferrors! Each line listed a Transaction ID, however we werent sure where to look for the transaction:the report simply listed Originating Table = 2.
Eventually it emerged that this report identifies stuck transactions as being fromTable 1 = MTL_MATERIAL_TRANSACTIONS orTable 2 = WIP_TRANSACTIONS. 8
It then became clear that we needed to understand the entire process flow now described brieflyabove.
Key Learnings
eAM is a relatively new application, apparently built on the back of existing eBS architecture. As
a result, if you log an SR, it is likely to spawn other SRs related to individual system componentsfor what to the end-user is simply one integrated process. In our case what we thought of assimply a probl em closing the Projects period, required the involvement of the Cost Management,
-
8/10/2019 Projects eAM JD.pdf
4/24
eAM Projects Process Overview Page 4 as at Sunday, 12 February 2012
Bill of Materials and Work in Process Support teams who apparently only talked to one anotherthrough us! Getting an end-to-end process view was almost impossible. So our recommendationis that if you strike an integration problem, consider finding someone genuinely skilled in the endto end flow even if they are on another continent or cost a mint and involve them early on.The right knowledge can solve the problem quickly.
Do not underestimate the complexity of implementing Project Manufacturing, the impact of all thepossible combinations of available options makes it almost impossible for Oracle to providecomprehensive documentation hence you are very likely to find the voluminous documentationinsufficient! (i.e. Which bit did I read in the BOM manual? Which bit was in the Inventory usersguide? Oh, and the bit about set- up was in the Cost Management Guide) Metalink is helpfulhowever you will need to ensure your consultants provide you documentation about how your system derives its accounting outcomes, as well as maintenance instructions for all thecomponents that support those outcomes (e.g. what has to be set up for a new project, a newproject organisation etc) and trouble-shooting tips 9.
Ensure your User Acceptance Testing (UAT) focuses on end-to-end transaction flows and thatsomeone verifies that the accounting outcomes are correct. Include a month-end in your UAT our problems didnt start until we tried to close Projects, even though we had successfully closedInventory. It then took nearly a year and several SRs to resolve those problems!
AcknowledgementsThe author would like to thank Wesfarmers Resources for their willingness to share their experienceswith the wider user community via the publication of this article. We are grateful for the assistance ofOracle Consultings Brian Devlin who was key to solving the eAM/ PA mystery. Doug Volz 10 alsoprovided remote assistance; his help and the OAU Gs conference paper repository providing accessto papers such as those from Dina Rotem cited above, once again demonstrated the value of the usercommunity to its members.
Author BackgroundJeannie Dobney is an independent consultant with over a decade s experience with the OracleeBusiness suite, specialising in Oracle Projects; she has held leadership positions for both AUSOUGand the OAUG. She can be contacted via email at [email protected] ; her earlier papers(including an overview of eAM) may be found at her web site: jdobney.com
mailto:[email protected]:[email protected]:[email protected]:[email protected] -
8/10/2019 Projects eAM JD.pdf
5/24
eAM Projects Process Overview Page 5 as at Sunday, 12 February 2012
Appendix: Detail of eAM to Projects Transaction Process FlowThe following over view diagram was shown in the body of this paper.
WIPTransactions
Expenditure InquiryWindows
Transaction Interface
Projects
Transaction ImportProcess
Maintenance (eAM)
General Ledger
SubLedger Accounting
Create Accounting Process(Cost Management SLA)
Cost CollectorProcess
Transactionscreated in eAM
MTLTransactions
Inventory
Transactionscreated in INV
This Appendix provides further detail on these process flows.
Process Flow DetailThe following diagram shows the 2 separate process flows in more detail:- WIP transactions and- Material transactionseach of these is described in more detail in the following pages.
The diagram is also helpful because it shows that the Cost Manager process is in fact a cluster ofprocesses as well as other details which have been omitted in this overview 11 .
-
8/10/2019 Projects eAM JD.pdf
6/24
eAM Projects Process Overview Page 6 as at Sunday, 12 February 2012
-
8/10/2019 Projects eAM JD.pdf
7/24
COLLABORATE 12 Jeannie Dobney Page 7
WIP Transaction Process Flow
What about?WMTI WIP_MOVE_TXN_INTERFACEWMT WIP_MOVE_TRANSACTIONS
Receiving Transaction orTimesheet entered by worker,creates a resource t ransaction
WCTIWIP_Cost_TXN_Interface
WTIEWIP_TXN_INTERFACE_ERRORS
Resource transaction error messagesgenerated by Cost Manager)
are placed in WTIE, join on Transaction_ID
WTWIP_TRANSACTIONS
WTAWIP_TRANSACTION_ACCOUNT
Cost Manager Process
SLA to GL andCost Collector to Projects
Error messages from the CostCollector are also placed in
WTIE, join on Transaction_ID
Narrative Version
TableAcronym
Application Window Table or Process or Action Comments
Resource transactionentered by user
Source may be atimesheet entry or areceiving transaction
WCTI Pending ResourceTransaction
WIP_Cost_TXN_Interface aka ResourceTransaction interface
Cost Manager
WT andWTA
View ResourceTransactions(& Res Trans Distributions)
WIP_TransactionsWIP_Transaction_Accounts
Create Accounting (to GL)
And Cost Collector to
Projects
Transactions will initially hit WIP_COST_TXN_INTERFACE (Pending Resource form) where they willremain until the inventory cost manager runs, validates and costs the transactions. If successfullyvalidated and costed the transactions are moved to WIP_TRANSACTIONS andWIP_TRANSACTION_ ACCOUNTS (Resources Form). Where validation errors exist the recordremains in WIP_COST_TXN_INTERFACE until the error is rectified. Once an error occurs allsubsequent transactions will back up behind the errored record and will not be processed until theerrored record is rectified and re-processed.
Once costed if the transactions are project related the cost collection manager (project cost transfer)process will transfer the records to PA_TRANSACTIONS_INTERFACE where they will be available toimport using the PRC: Transaction Import process from the relevant source. Note the Project cost
transfer will pick up both eAM and Inventory transactions which are projects related.So the Cost Manager does 2 things cost calculations and accounting for transactions:
-
8/10/2019 Projects eAM JD.pdf
8/24
COLLABORATE 12 Jeannie Dobney Page 8
1) Takes the rows from WIP_COST_TXN_INTERFACE and:
a) Creates the resource transaction and INSERTS into WIP_TRANSACTIONS, while also,
b) Creates the resource accounting transaction and INSERTS intoWIP_TRANSACTION_ACCOUNTS
Notes
The WIP Interface table includes:a flag to show the status of Cost Manager processing for each transaction
The WIP Transactions table includes:- PM_COST_COLLECTED flag to show if Cost Collection has run successfully- WIP_ENTITY_ID which is the primary key for the work order- SOURCE column may be used to distinguish e.g. PO and RCV transactions
Refer debugging document for SQL relating to these.
The Cost Collector which copies relevant Inventory transactions into the PA transactionInterface, is not the same as the Cost Manager, which is an Inventory (Cost management)process which calculates the cost of a transaction such as 8 hours of labour from Joestimesheet.there is a Metalink Note with more detail on this:MOS # 412562.1 - How Cost Collector Transfers Cost To ProjectsThe Cost Collector log may show no transactions to process so the view'cst_pm_pending_txn_v' may be very helpful
To check the Cost Manager: N > SetUp ~ Transactions ~ Interface Managersthe Cost Manager process should be active and on 5 minute resubmission.
It is sometimes necessary to stop the Cost Manager,There is a specific MOS Note on this:MOS 435487.1 - How To Stop the Flow of Incoming Events
-
8/10/2019 Projects eAM JD.pdf
9/24
COLLABORATE 12 Jeannie Dobney Page 9
Material Transaction Process Flow
What about?Completion transactions?
Inventory transactione.g. Material issue
createsPending Inventory Transaction
MMTTMTL_material_transactions_temp
MTAMTL_TRANSACTION_ACCOUNT
SLA to GL andCost Collector to Projects
MMTMTL_material_transactions
Transaction Interface Manager background process
Cost Manager ProcessCost Manager updates
transaction with cost and adds
accounting
WTIE
WIP_TXN_INTERFACE_ERRORS
Error messages from the CostCollector are placed in WTIE,
join on Transaction_ID
Acronym Window Table or Process or Action Comments
Material transaction(e.g. stock issue to WO)
MMTT Pending InventoryTransaction
MTL_material_transactions_temp
Inv Transaction Interface Mgr
MMT Material Transactions MTL_material_transactions
Cost Manager
Cost Manager doesnt movethe transaction but populatesthe related Distribution detail
MTA Material Distributions MTL_transaction_accounts
Create Accounting (to GL)
AndCost Collector to Projects
Notes
The MTL Material Transactions table includes:- PM_COST_COLLECTED flag to show if Cost Collection has run successfully
-
8/10/2019 Projects eAM JD.pdf
10/24
COLLABORATE 12 Jeannie Dobney Page 10
Appendix: Troubleshooting Inventory to Projects Flow(Projects Perspective)Run the Projects Exception Report:
From Projects standard Request Submission, select: EXC: Transaction Exception Details by GL Period
Note that report refers to an originating table as a number, this number is a key to understandingwhich process flow to review :1 = Material Transactions2 = WIP Transactions
The SQL on which this report is based (for Inventory and eAM errors) is found in the viewCST_PM_PENDING_TXN_V
Trouble-shoot backwards from Projects
First check the Transaction Interface
Either submit the Transaction Import and check the output / log
N > Expenditures ~ Transaction Import ~ Import Transactions
For transaction Sources: Inventory, Inventory Misc and Work In Process
Or query back stuck transactions in the interface:
N > Expenditures ~ Transaction Import~ Review Transactions
For transaction Sources: Inventory, Inventory Misc and Work In Process
And Transaction Status: Import Rejected
See also SQL later in this paper
Launch the Cost Collector a nd review outcomes
From Project Manufacturing
N > Control ~ Transfer Costs to Projects ~ Manufacturing CostsReview the log
Note that once a transaction is marked as an error by the Cost Collector, it will not bereprocessed until the processing flag is reset using SQL hence it is possible to notsee error messages if the Cost Collector process is rerun.
You will need to use SQL to1. Delete WTIE records2. Reset Cost collector flags
Refer to SQL at the end of this paper And then rerun the cost collector (see path above)
At the Application level, to view transactions that have errored as a result of the CostCollection Process:
For Material Transactions:From Project Manufacturing Responsibility:
N > Inquiry ~ Transaction Information ~ Material transactions
Ensure Transaction Date fields are cleared and select Error in theTransferred to Project field, then click Find
For Resource TransactionsFrom Project Manufacturing Responsibility:
-
8/10/2019 Projects eAM JD.pdf
11/24
COLLABORATE 12 Jeannie Dobney Page 11
N > Inquiry ~ Transaction Information ~ Resource transactions
Ensure Transaction Date fields are cleared and select Error in theTransferred to Project field, then click Find
At the Application level, to view transactions that have errored as a result of the CostManager Process:
For Material Transactions:From Project Manufacturing Responsibility:
N > Inquiry ~ Transaction Information ~ Material transactions
Ensure Transaction Date fields are cleared and select Error in the Costed field, then click Find
For Resource TransactionsFrom eAM Responsibility:
N > Work Order Transactions ~ Pending Resource Transactions
Ensure Transaction Date fields are cleared and select Error in the ProcessStatus field, then click Find
The Errors button in the Inquiry window provides detail about specific errors
MOS # 462657.1 makes the following 2 key points relevant for trouble-shooting PendingTransactions:
If there are uncosted / pending transactions, check that the Cost Manager is activeCost Manager (see screen shots below)
In an Implementation that uses Average Costing, a single error in eitherwip_cost_txn_interface or mtl_material_transactions tables will cause the processing
of all transactions in that table to stop. Find the transaction preventing the CostManager progressing, fix it and continue; there are screen shots in the next sectionexplaining how to do this.
Detail on Trouble-Shooting TechniquesTo view Resource Transactions
In eAMN > Work Order Transactions ~ View Resource Transactions
From Project ManufacturingN > Inquiry Transaction Information ~ Resource Transactions
The Project Manufacturing form has a field that allows users to query for transactions that haveCost Collector errors (see following screen shot)
-
8/10/2019 Projects eAM JD.pdf
12/24
COLLABORATE 12 Jeannie Dobney Page 12
To find Material Transaction s that have Cost Collection errors, use the Material Transactions Inquiryform
Remove the Transaction Dates and select Error (or No) in the Transferred to Project field
(Note that the Costed field relates to the Cost Manager process not the Cost Collector process).
SQL for Trouble-ShootingViews upon which the Exception report is based are:
Supplier Invoice related exceptions: from the view 'pa_ap_inv_exceptions_sum_v'PO Receipts shown in the exception from the view 'pa_rcv_exceptions_det_v'Uncosted transactions during the period it takes from 'pa_gl_uncost_except_sum_v'
-
8/10/2019 Projects eAM JD.pdf
13/24
COLLABORATE 12 Jeannie Dobney Page 13
Any Costing exceptions: 'pa_cost_exceptions_det_v'Inventory/Project Manufacturing Exception 'cst_pm_pending_txn_v'
View transactions stuck in Projects Transaction interface select *from PA_transaction_interface_all
where Transaction_source in ('Inventory', 'Inventory Misc', 'Work In Process');-- or
select transaction_source , transaction_status_code , count(*)from pa_transaction_interface_allgroup by transaction_source, transaction_status_code;
To view error messages related to Cost Collector for WIP Transactions:Select WTIE.Transaction_ID, WTIE.ERROR_MESSAGE, WTIE.LAST_UPDATE_DATEfrom WIP_TXN_INTERFACE_ERRORS WTIE, -- error message tableWIP_TRANSACTIONS WT -- WIP transactionsWHERE WTIE.TRANSACTION_ID = WT.TRANSACTION_ID -- join tablesand Error_Column = 'PM_COST_COLLECTED' -- Only Cost Collector errorsand WT.PM_COST_COLLECTED = 'E';
Given that this table stores error messages after the errors are cleared,it may be worth using the date column to view only recent errorsOR clearing it regularly
To view error messages related to Cost Collector for MTL Transactions: Select WTIE.Transaction_ID, WTIE.ERROR_MESSAGE, WTIE.LAST_UPDATE_DATEfrom WIP_TXN_INTERFACE_ERRORS WTIE, -- error message tableMTL_Material_TRANSACTIONS MTL -- MTL transactionsWHERE WTIE.TRANSACTION_ID = MTL.TRANSACTION_ID -- join tablesand Error_Column = 'PM_COST_COLLECTED' -- Only Cost Collector errorand MTL.PM_COST_COLLECTED = 'E';
To find transaction detail related to Cost Collector errors, simply run a script such as the following:
select * from mtl_material_transactions -- or WIP_TRANSACTIONSwhere PM_COST_COLLECTED = 'E';
To find the Work Order related to an errored transaction, use the following SQL:
Select WO.wip_entity_name WO_Number, WO.description, WT.TRANSACTION_IDfrom WIP_entities WO,
WIP_TRANSACTIONS WTwhere WT.WIP_ENTITY_ID = WO.WIP_ENTITY_IDand WT.TRANSACTION_ID = X; -- or whatever criteria
To reset the Cost Collector Flags so that the process can be called again on the same transactions(e.g. after fixing a set up error). Refer to MOS # 422044.1 for Support instruction for this SQL.
-- Delete error messages for WIP Transactions
delete from WIP_TXN_INTERFACE_ERRORS WTIEWHERE Error_Column = 'PM_COST_COLLECTED' andWTIE.TRANSACTION_ID IN(SELECT WT.TRANSACTION_IDFROM WIP_TRANSACTIONS WTWHERE PM_COST_COLLECTED = 'E');
-- Reset Flags
UPDATE WIP_TRANSACTIONSSET LAST_UPDATE_DATE = SYSDATE,LAST_UPDATED_BY = 26941, -- optionally set user ID for audit purposes
-
8/10/2019 Projects eAM JD.pdf
14/24
COLLABORATE 12 Jeannie Dobney Page 14
LAST_UPDATE_LOGIN = 26941, -- optionally set user ID for audit purposesPROGRAM_UPDATE_DATE = SYSDATE,PM_COST_COLLECTED ='N', -- Change flag from E to N PM_COST_COLLECTOR_GROUP_ID =NULL -- Clear Group IDWHERE PM_COST_COLLECTED = 'E'and wt.organization_id = :Your organization; -- only your Inventory org / OU
The equivalent MTL scripts are-- Delete error messages
delete from WIP_TXN_INTERFACE_ERRORS WTIEWHERE Error_Column = 'PM_COST_COLLECTED' andWTIE.TRANSACTION_ID IN(SELECT MTL.TRANSACTION_IDFROM MTL_MATERIAL_TRANSACTIONS MTLWHERE PM_COST_COLLECTED = 'E');
-- Reset Flags
update MTL_MATERIAL_TRANSACTIONSset pm_cost_collected = 'N',pm_cost_collector_group_id = NULLwhere pm_cost_collected = 'E'and organization_id = :Your organization;
Dont forget to Commit!
If the Cost Collector is not the problem then it may be the Cost Manager process ; this script showsrelevant MTL errors
-- MTL transactions
SELECT transaction_id txn_id, organization_id org,substr(error_code,1,30) errc,substr(error_explanation,1,100) erre
FROM mtl_material_transactionsWHERE costed_flag = 'E';
-- WIP Transactions
select wcti.transaction_id, WCTI.TRANSACTION_DATE, WCTI.WIP_ENTITY_NAME WO,WTIE.ERROR_MESSAGE, WTIE.ERROR_COLUMNFROM WIP_COST_TXN_Interface WCTI,
WIP_TXN_INTERFACE_ERRORS WTIEWHERE WTIE.TRANSACTION_ID = WCTI.TRANSACTION_IDand WCTI.process_status = 3and WCTI.Organization_ID = :Your organization;
-- An alternative script including completion transactions is:
select wtie.TRANSACTION_ID txn_id,wtie.ERROR_MESSAGE msg,wtie.ERROR_COLUMN col,wcti.organization_id
from wip_txn_interface_errors wtie,wip_cost_txn_interface wcti
where wcti.transaction_id = wtie.transaction_idand (wcti.process_status = 3
OR
wcti.completion_transaction_id IN(SELECT completion_transaction_id
FROM mtl_material_transactions
-
8/10/2019 Projects eAM JD.pdf
15/24
COLLABORATE 12 Jeannie Dobney Page 15
WHERE costed_flag = 'E'))
The flags in these tables may be understood as follows:
WIP_COST_TXN_INTERFACEprocess status (i.e. of the Cost Manager)1, 'Pending',2, 'Running',3, 'Error',4, 'Completed',5, 'Warning'
WIP_TRANSACTIONScost_collected column may be either N or E (I.e. Cost Collector status) 'N', 'Pending','E', 'Error',
MTL_MATERIAL_TRANSACTIONS- costed column may be null or costed_flag = E (i.e. Cost Manager status)
and cost_collected IN (N, E) (I.e. Cost Collector) 'N', 'Pending','E', 'Error',
Note that WTIE (WIP_TXN_INTERFACE_ERRORS) includes a column for the program that createdthe error, by using the following it is possible to retrieve the program name:
select user_concurrent_program_name from FND_CONCURRENT_PROGRAMS_TLwhere CONCURRENT_PROGRAM_ID = NNNN;
The Projects Exception Report gets its error text from function calls toPA_EXCEPTION_REASONS_PUB.GET_EXCEPTION_TEXTFrom looking at the underlying view (CST_PM_MATL_TXN_V) it would seem that if the value incolumn PM_COST_COLLECTED = E, then the text says to look in the Cost Collector log. If howeverthe value in column PM_COST_COLLECTED = N, then the system reports an undefined error.
Additional Material that May be Useful
MOS # 865438.1 Extremely detailed document on resolving Costing errors
MOS # 422044.1 - for Support instruction on SQL to reset Cost Collector flags
MOS # 462657.1 Possible causes for pending transactions
MOS # 435487.1 - How to stop the Cost manager
MOS # 378348.1 - Data Collection Scripts for Cost Management CstCheck.sql and Err_txn.sqlincludes useful SQL on which much of the above was based
-
8/10/2019 Projects eAM JD.pdf
16/24
COLLABORATE 12 Jeannie Dobney Page 16
Appendix: Inventory Period End Process and Trouble-ShootingSample Inventory Close Process may need to be co-ordinated with Projects
1. Review All Pending/Stuck Transactions2. Resubmit Pending Transactions
3. Run Create Accounting (Draft)4. Open Next Inventory Period5. Resubmit Pending Transactions6. Run Create Accounting and Transfer to GL7. Close Current Inventory Period8. Troubleshooting Inventory Close Process9. ReRun Create Accounting and Transfer to GL until successful10. Reconcile Inventory Control Account11. Check for Unposted Journals
Compare this with Chapter 11 of the Cost Mgmnt users Guide and Oracle Metalink Whitepaper MOS# 961285.1
Note that the Cost Management - SLA responsibility enables users to Create Accounting transactionsfor:
Inventory ( Internal Orders/Issues/Miscellaneous/Deliver into Inventory)Receiving (Deliver to Expense Destination & Receipt into Inspection/Clearing)Work in Process (EAM Work Orders)
Create Accounting may be run the program in Draft or Final Mode.
When run in Draft the user can view potential accounting entries.
When run in Final the user can create and transfer accounting entries to the General Ledger.
Key points from Oracle Cost Management Users Guide (specifically in reference to eAM):
If Subledger Accounting (SLA) is enabled and SLA rules are customized, then the defaultaccounts may not be used.
The period close process permanently closes an open period. You can no longer chargetransactions to a closed period. Once you close a period, you cannot reopen it. As aprecaution, you can do a GL transfer without closing the period.(i.e. run Create Accounting in Draft mode).
Notes to Month End Process Steps1. Complete All Transactions for the Period Being Closed
Ensure that all issues, shipping, receipts, and adjustments have been entered and verify that nohard copy records exist, or are awaiting data entry(e.g. packing slips in receiving).
2. Check Inventory and Work in Process Transaction InterfacesCheck the Interface Managers window to ensure that there are no unprocessed background orconcurrent programs.
The interface managers that need to be run are as follows:* Cost Manager (mandatory)* Material Transaction Ma nager (Optional, depending on INV profile option TPINV: Transaction
Processing Mode)* Move Transaction Manager (for IWIP)
-
8/10/2019 Projects eAM JD.pdf
17/24
COLLABORATE 12 Jeannie Dobney Page 17
3. Check and fix pending TransactionsCheck and fix any rejected transactions from the Inventory Accounting Period Window: click onthe pending button to display pending transactions. This will display transactions under thefollowing statuses:
* Resolution Required: Displays the number of unprocessed material transactions, uncosted
material transactions, and pending IWIP costing transactions existing in this period. These mustbe resolved before the period is closed.
* Resolution Recommended: Displays the number of pending receiving transactions, pendingmaterial transactions, and pending shop floor move transactions existing in this period. Thoughthe accounting period can be closed, once it is closed these transactions cannot be processed inthat period.
Note: This process needs to be completed for each defined Inventory Organization.
In case of error, correct the error at the source, and then relaunch transactions using:* INV / Transactions / Pending transactions* INV/ Transactions / Transaction Open interface* OM / Shipping / Interfaces
This check should be done during the month to avoid cumulative problems at month end beforeclosing.
All Pending Inventory transactions must be processed for the period. You will not be able to closethe Inventory Period without processing all Inventory and WIP transactions. When the Supplyteam attempt to Close an Inventory Period they can view all Pending transactions at that point.
Commonly, some Inventory transactions will get stuck due to invalid Accounting Combinations.When these invalid combinations are changed or where there is a need to temporarily relax theCross Validation Rule. The Cost Manager, which is scheduled to run every 5 minutes, needs tobe run manually to process these transactions.
Once there are no longer any Pending Transactions the Create Accounting Program for CostManagement should be run to account/transfer and post to the General Ledger.
4. Transfer Summary or Detail TransactionsIf Order Management is used, for the order-shipments which have been invoiced in AR, revenuerecognition has been processed in AR, and the accounting entries between Deferred COGSaccount and COGS account must be generated in INVCST.
For this purpose you need to run these 2 concurrent programs:
* Collect Revenue Recognition information
* Generate COGS Recognition event
Run the Create Accounting -Cost Management program up to the period end date before closingthe period. Since a period, once closed, cannot be re-opened, running this process prior toclosing the period facilitates validating the interface transactions.
Any adjustments to the period can be made via new inventory transactions as required.If the Create Accounting Program is run in Final Mode without transferring to GL then run theTransfer Journal Entries to GL Cost Management which transfers the accounting to GL.
Attention: The Transfer Journal Entries to GL Cost Management Program transfers theaccounting details for all the inventory organizations within a Ledger.
Attention: If this step was by-passed, and the period was closed, a GL Transfer wouldautomatically be initiated. But no adjustments to that period can then be entered, sincetransactions cannot be posted to a closed period, and a closed period cannot be re-opened.
View accounting, journal entries associated with transactions, and accounting events byaccessing the Sub ledger Accounting user interface from the View Transactions window andvarious statuses (e.g.Final Accounted, Draft Accounted, Errored can be selected).
5. Open the Next Inventory Period
-
8/10/2019 Projects eAM JD.pdf
18/24
COLLABORATE 12 Jeannie Dobney Page 18
Prior the first day of data entry, open the next inventory period using the Inventory AccountingPeriods window.
Attention: This process needs to be completed for each defined Inventory Organization.
Detail on Inventory Close TroubleshootingScreen shots of most of the Application level steps follow this table
Process Step What to do
Review All Pending / StuckTransactions
Run Period Close Pending Transactions Report to check for
A. Unreceipted PO InformationB. Open Work Order s-C. Uncosted Transactions
Resubmit Pending
Transactions
1. Resubmit from Pending Transactions form in eAM
- View Material Transactions2. Resubmit from Pending Transactions form in Inventory- View Pending Transactions
Run Accounting andTransfer to GL
Create Accounting from Cost Management SLA
Open New Period Open New Period
Resubmit PendingTransactions
1. Resubmit from Pending Transactions form in EAM- View Material Transactions
2. Resubmit from Pending Transactions form in Inventory- View Pending Transactions
Run Accounting and
Transfer to GL
Create Accounting - Cost Management SLA
Close Inventory Period Inventory Close
Run Accounting andTransfer to GL
Create Accounting - Cost Management SLA
Reconcile InventoryControl Account
Period Close Reconciliation report to GL
Check for UnpostedJournals
Post All Unposted Journals
-
8/10/2019 Projects eAM JD.pdf
19/24
COLLABORATE 12 Jeannie Dobney Page 19
Identify Issues Preventing Inventory Close (Pending Transactions)There are several ways to identify transactions that have got stuck (so -called Pending Transactions):
1. From the Period Close screen
2. Overview Report (Period Close Pending Transactions Report)
3. Review reports (for each transaction type see reports mentioned under 1 below)4. Inquiry screens (for each transaction type)
Each of these is described briefly in the following pages.
Regardless of how the issues are identified, the objective is to:- identify and resolve the underlying problems that have been found and then- Resubmit the transactions.
1. Using the Period Clos e Screen to f ind Pending Transac t ions
From the Inventory Accounting Periods window, select Pending to go to the Pending Transactionswindow. From this window, you can select the Open button to link to specific windows, reports, orpages to view pending, errored, or uncosted transactions. The windows, reports, or pages that youlink to are determined by your cursor position when you select Open .
The following table describes details of the links to windows and reports:
Type of Transaction Links to Windows/Reports/PagesUnprocessed Material Interfacetransactions
Inventory Transactions Open Interface window
Unprocessed Material transactions Inventory Pending Transactions window
Uncosted Material transactions View Material Transactions window
Pending Receiving transactions Receiving Transactions window
Pending WIP Costing transactions WIP Pending Resource Transactions window
Pending WIP Move transactions WIP Pending Move Transactions window
Incomplete eAM work orders EAM Work Orders Self-Service page
Pending Shipping transactions Report for Pending Shipping transactions.
-
8/10/2019 Projects eAM JD.pdf
20/24
COLLABORATE 12 Jeannie Dobney Page 20
2. Using the Period Clos e Pending Transac t ions Repor t to f ind i ssues
Run Period Close Pending Transactions Report (from Cost Mgmt SLA Responsibility)
If there are unprocessed transactions, then one of the following messages appears:
Pending receiving transactions for this periodWhen you use Purchasing, this message indicates you have unprocessed purchasingtransactions in the RCV_TRANSACTIONS_ INTERFACE table. These transactions include
purchase order receipts and returns for inventory. If this condition exists, you will receive awarning but will be able to close the accounting period. These transactions are not in yourreceiving value. However, after you close the period, these transactions cannot be processedbecause they have a transaction date for a closed period.Unprocessed material transactions exist for this periodThis message indicates you have unprocessed material transactions in theMTL_MATERIAL_TRANSACTIONS_TEMP table. You are unable to close the period with thiscondition. Please see your system administrator. Inventory considers entries in this table as partof the quantity movement. Closing the period in this situation is not allowed because the resultantaccounting entries would have a transaction date for a closed period, and never be picked up bythe period close or general ledger transfer process.Pending material transactions for this period
This message indicates you have unprocessed material transactions in theMTL_TRANSACTIONS_INTERFACE table. If this condition exists, you will receive a warning butwill be able to close the accounting period. These transactions are not in your inventory value.However, after you close the period, these transactions cannot be processed because they havea transaction date for a closed period.Uncosted material transactions exist for this periodThis message indicates you have material transactions in the MTL_MATERIAL_TRANSACTIONStable with no accounting entries (Standard Costing) and no accounting entries and no costs(Average Costing). You are unable to close the period with this condition. These transactions arepart of your inventory value. Closing the period in this situation is not allowed because theresultant accounting entries would have a transaction date for a closed period, and never bepicked up by the period close or general ledger transfer process.
Pending move transactions for this period
-
8/10/2019 Projects eAM JD.pdf
21/24
COLLABORATE 12 Jeannie Dobney Page 21
This message indicates you have unprocessed shop floor move transactions in theWIP_MOVE_TXN_INTERFACE table. If this condition exists, you will receive a warning but willbe able to close the accounting period. These transactions are not in your work in process value.However, after you close the period, these transactions cannot be processed because they havea transaction date for a closed period.Pending WIP costing transactions exist in this periodThis message indicates you have unprocessed resource and overhead accounting transactions inthe WIP_COST_TXN_INTERFACE table. You are unable to close the period with this condition.These transactions are in your work in process value, and awaiting further processing. Closingthe period in this situation is not allowed because the resulting accounting entries would have atransaction date for a closed period, and never be picked up by the period close or general ledgertransfer process.Note that there is a helpful MOS Note # 462657.1, explaining how to approach problem solvingfor unprocessed resource and overhead accounting transactions in theWIP_COST_TXN_INTERFACE table. The note applies to 11i but may be helpful in any case.
4. Using Inqui ry Forms to F ind and Resolve Pending Transac t ions
To find Material Transaction s that have either not been costed or have errors, use the MaterialTransactions Inquiry form
Remove the Transaction Dates and select Error (or No) in the Costed field
If the inquiry returns a row, there will only ever be 1 row as the cost manager for an organization stopsas soon as it finds the first transaction that errors.
To manually submit the transaction for costing:
click Tools ~ Select All
and then
click Tools ~ Submit All
-
8/10/2019 Projects eAM JD.pdf
22/24
COLLABORATE 12 Jeannie Dobney Page 22
The error transaction will be re-processed the next time the Cost Manager runs (scheduled for every 5minutes)
To find pending Resource t ransac t ions , use the Pending Transactions form and select Error in theProcess Flag field
Click Find to retrieve the errored transactions
-
8/10/2019 Projects eAM JD.pdf
23/24
COLLABORATE 12 Jeannie Dobney Page 23
To resubmit:
Click Tools ~ Submit All
Save
You will see that this action resets the status to Pending and the next time the cost manager runsthese will be re-tried.
Resolving Pending Transactions If Cost Manager is Inactive
The most obvious reason for any Pending Transactions is that the Cost Manager (or other transactionmanagers) are inactive. To check and resolve this:
Inventory ResponsibilityN > -- SetUp -- Transactions -- Interface Managers
See if the Cost Manager is Inactive. If yes, then launch the Cost Manager .
-
8/10/2019 Projects eAM JD.pdf
24/24
If it is inactive, highlight the manager and select Tools ~ Launch Manager
Once the Request completes, it will invoke Cost Workers to process the records.
Notes and References
1 The author wishes to express her gratitude to Wesfamers Resources Ltd for allowing her to sharetheir learning with the wider user community.2 Don't Get Lost in the Labyrinth of Supplier Cost Flows into Projects by Dina Rotem & John Sasali,presented at OAUG 2008 conference and available from the OAUG Conference paper database.3 Refer also to Dinas blog entry on this http://www.projectp.com/weblog/tag/oracle-project-manufacturing/ 4 Oracle provide a reference manual on Cost Management, however if you are new to this area thatmay not be a good starting point! Doug Volz (www.volzconsulting.com ) is an excellent source ofhelpful plain English material. There is also an excellent MOS Note 865438.1: How to resolve CostingErrors & Problems for those struggling with pending transactions.5 Understanding the transactional flow between Purchasing, Inventory and Work in Process andProjects by Phil Miller and available from the OAUG Conference paper repository (refer specifically tothe PowerPoint presentation).6 Refer to the Appendix for further detail on this topic7 The author regrets that she has misplaced the source of this helpful diagram.8 We logged an SR asking for the detail and Oracle provided us details of the views upon which theException report is based however we had to read a lot of SQL before we decoded the meaning of1 and 2...9 To get a sense of this complexity, have a look at Dina Rotems excellent paper Don't Get Lost inthe Labyrinth of Supplier Cost Flows into Projects , referenced earlier and available through the OAUGconference database.10 Doug Volzs website is www.volzconsulting.com 11 This diagram is from an original presentation by Oracles Brian Devlin.
http://www.projectp.com/weblog/tag/oracle-project-manufacturing/http://www.projectp.com/weblog/tag/oracle-project-manufacturing/http://www.projectp.com/weblog/tag/oracle-project-manufacturing/http://www.projectp.com/weblog/tag/oracle-project-manufacturing/http://www.volzconsulting.com/http://www.volzconsulting.com/http://www.volzconsulting.com/http://www.volzconsulting.com/http://www.volzconsulting.com/http://www.volzconsulting.com/http://www.volzconsulting.com/http://www.volzconsulting.com/http://www.projectp.com/weblog/tag/oracle-project-manufacturing/http://www.projectp.com/weblog/tag/oracle-project-manufacturing/