projectplanningandcontrol-120331060550-phpapp02

Upload: khajaimad

Post on 14-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    1/34

    Project Planning and Control

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    2/34

    What is a project plan?

    A project plan is a model of the process that theproject team intends to follow to realise the project

    objectives. It brings together a number of importantaspects of this process including its scope, timing,cost, and associated risks.

    The project plan can be viewed as a type ofcontract between the project team members andother stakeholders. It defines the process by whichthe objectives will be achieved, and theresponsibilities in carrying out this process.

    Project plans also underpin a number of other key

    project management functions including estimatingand forecasting, options analysis and decision-making, and performance monitoring and control.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    3/34

    Who is responsible for planning?

    Everyone in the project team should be

    involved in developing the plan. Itshould be a collaborative effort.

    The project manager should provide

    leadership in this area but may delegatesome of the administrative aspects and

    detailed analysis to a project support

    role. On larger projects there may be one or

    more dedicated planners.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    4/34

    What are the benefits of planning?

    It is more likely to lead to success and

    is more cost-effective than a just do itapproach.

    It develops greater mutual

    understanding and more commitment toachieving the objectives within theproject team.

    It provides an early warning system

    so that problems are identified whilethere is still time to do something aboutthem.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    5/34

    Key elements of a plan

    Products What products must the projectdeliver? What are the quality requirementsassociated with the products?

    Activities What activities are needed todeliver the products?

    Resources What resources are needed tocarry out the activities?

    Schedule In what sequence should we carryout the activities? How long will the activities

    take to complete? Are the required resourcesavailable? How long will the project take overall?

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    6/34

    Budget What are the time-phased

    resource requirements and financial

    costs? How much will the project costoverall?

    Risks Are we taking unnecessary risks?

    Is the level of risk exposurecommensurate with the risk appetite? Are

    there any opportunities that could be

    exploited? Assumptions What are the underlying

    assumptions associated with the plan?

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    7/34

    The planning process:

    What is the process for developing aplan?

    There are four key stages in developing arobust plan:

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    8/34

    STAGE 1

    Identify, structure and define the products

    needed to achieve the project objectives.

    Break down the work needed to deliver the

    products into discrete work packages.

    Define the responsibilities of the

    individuals or teams who will deliver the

    work packages.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    9/34

    STAGE 2

    Identify the activities and resources

    needed to deliver the work packages.Construct a schedule that takes account ofthe logical dependencies betweenactivities, and the availability of resources.

    STAGE 3

    Estimate the quantity of resources andfinancial costs associated with each work

    package, and use this information inconjunction with the schedule to developtime-phased budgets.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    10/34

    STAGE 4

    Identify and analyse the risks associated

    with each work package and evaluate arange of options for handling them. Select

    the most cost-effective combination of risk

    management actions and incorporate

    them into the plan.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    11/34

    Stage 1 Defining scope andresponsibilities

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    12/34

    Objectives

    To ensure that all the work and productsneeded to achieve the project objectivesare included in the plan.

    To develop a hierarchical framework for

    integrating the key planning and controlfunctions (scope, quality, cost, time, risk)at different levels of management.

    To specify the organisation andresponsibilities for managing the work anddelivering the products.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    13/34

    Fundamental principles:

    Break down the project work into cohesive

    work packages Define the required results (i.e., the

    products) before considering how to

    achieve them. Encourage collaborative planning and

    commitment to achieving results by

    negotiating and agreeing responsibilities atan early stage.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    14/34

    Process description

    Identify and structure the products needed to achieve theproject objectives using a Product Breakdown Structure

    (PBS). Define the products and specify their purpose,quality requirements and acceptance criteria, usingProduct Descriptions (PD).

    Break down the work needed to deliver the products intodiscrete work packages using a Work BreakdownStructure (WBS). Define the work packages and specifytheir products, quality requirements, acceptance criteria,assumptions, risks, and opportunities, using WorkPackage Descriptions (WPD).

    Specify the organisation that will carry out and managethe work contained in the WBS, using an Organisational

    Breakdown Structure (OBS). Define the responsibilitiesof individuals or teams in the OBS (with respect toelements of the WBS) using a Responsibility AssignmentMatrix (RAM).

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    15/34

    Stage 2 Scheduling and time/resourceanalysis

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    16/34

    Objectives

    To identify the activities needed to deliver

    each work package, and sequence them

    according to their logical dependencies.

    To estimate the time and resources

    needed to carry out the activities in the

    specified sequence.

    To construct a schedule that takes

    account of logical dependencies andresource availability.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    17/34

    Fundamental principles:

    The time and resources needed to

    complete each activity usually depend onthe sequence in which the activities arecarried out.

    Since the time and resources needed tocomplete an activity are usuallyinterdependent, it makes sense toestimate both of these at the same time.

    Scheduling must take account of resourceavailability.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    18/34

    Process description

    Identify the activities needed to deliver each workpackage. Also identify any key events (milestones)

    associated with the delivery of products, importantdecisions, or external dependencies. Sequence theactivities and milestones according to their logicaldependencies, to create an activity network.

    Estimate the time and resources needed to completeeach activity and record the underlying assumptions as aBasis of Estimate (BoE).

    Develop an initial schedule that takes account of thelogical dependencies between activities. Calculate theTotal Float for each activity and identify the CriticalPath(s). If the initial schedule does not meet the required

    timescales then investigate alternative schedules orconsider making tradeoffs. Analyse the time-phasedresource requirements and, if necessary, adjust theschedule to take account of resource availability or toimprove resource utilisation.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    19/34

    Stage 3 Cost estimating andbudgeting

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    20/34

    Objectives

    To develop a hierarchical framework for

    planning and controlling resourceconsumption and financial costs.

    To estimate the quantities and financial

    costs of the resources needed to delivereach work package.

    To develop time-phased budgets as a

    basis for performance monitoring andcontrol.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    21/34

    Fundamental principles

    Since budgets are normally constrained,we need to monitor actual costs againstplanned costs on a regular basis to ensurethat timely corrective action can be taken if

    there is a significant variance. Making good progress against the

    schedule is often not enough to guaranteesuccess. It is also important to monitor the

    planned and actual resource consumption(or financial costs) in relation to theprogress made.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    22/34

    Stage 4 Risk analysis and response

    planning

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    23/34

    Objectives

    To identify the risks associated with each

    work package.

    To determine the overall risk exposure and

    the contribution of individual risks.

    To prioritise risks for further management.

    To develop cost-effective risk

    management actions (responses) and

    incorporate them into the plan.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    24/34

    Fundamental principles:

    Once the plan has been developed it

    should still be considered a draft until itsrisk content has been analysed. Thisanalysis may lead to the plan being

    modified to include risk managementactions.

    Plans should be risk-efficient (i.e., shouldinclude no more risk than is necessary to

    provide a given level of return), and therisk exposure should be commensuratewith the risk appetite.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    25/34

    Monitoring and control

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    26/34

    Objectives - Fundamental

    principles

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    27/34

    To inform decision-making processes at alllevels in the organisation.

    Apply the principles of closed-loop control tomonitor project in the organisation, and to takeany corrective action. To review theperformance against the plan at regularintervals, and needed corrective actions to

    ensure that objectives are achieved. Take anycorrective action needed to achieve the plan

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    28/34

    To identify problems and emergent risksearly enough objectives while there is still

    time to do something about them. Monitor trends in performance over aperiod of time as the project progresses

    To communicate regular progress to the

    project team and other stakeholders aswell as the spot performance withrespect to an activity in order thatconfidence and baseline is maintained.

    This allows us to distinguish betweencommitment and reality and the focustowards the project is maintained

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    29/34

    Project control cycle

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    30/34

    Identify the objectives and constraints, and develop aplan. Review and baseline the plan. Obtain authorisationto proceed.

    Do some work. Measure performance and update the original estimatesand forecasts. Update the schedule and budget forecaststo take account of the latest information.

    Investigate the causes of any significant variations with

    respect to the baseline. Review the associated risks andassumptions. If necessary, develop options for takingcorrective action.

    Agree on any corrective action that is required andupdate the plans (via Change Control if the baseline ischanged).

    Confirm that the objectives have been achieved and thatthe required products have been delivered.

    Obtain formal sign-off if appropriate.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    31/34

    Performance monitoring

    techniques

    Schedule analysis Monitor variations in the forecast schedulewith respect to the baseline, as well as changes to the criticalpath(s) and remaining float of activities.

    Budget analysis Monitor variations in the forecast budget withrespect to the baseline.

    Milestone trend charts Monitor the forecast dates and actualdates of key milestones as a function of time.

    Earned Value Management (EVM)Monitor earned - value andactual cost against planned value/cost

    Risk analysisMonitor confidence values or probabilitydistributions associated with key elements of the schedule orbudget, as a function of time.

    Buffer management fever charts Monitor the consumption ofschedule and budget contingency buffers as a function of time.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    32/34

    Techniques for planning larger projects

    Staged planning The project is split into a number ofdiscrete stages. An outline plan is developed for theproject as a whole, together with more detailed plans for

    each stage. The plans for each stage are usuallydeveloped towards the end of the preceding stage. Thisapproach is a useful way of limiting risk exposure whenthere is uncertainty about the requirements, the work tobe performed, the available resources, or the project

    environment. Hierarchical planning Planning and control is carried

    out in a hierarchical fashion so that lower level plans andtheir associated control systems are nested withinelements of the higher-level plans.

    Rolling Wave planning Only the near-term workpackages are planned in detail, while the far-term workpackages (sometimes called Planning Packages) areplanned in outline only.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    33/34

    Principles of effective planning and control

    Divide-and-conquer Manage complexity by breakingdown the various elements of the plan in a structuredway. But dont forget to keep track of the dependenciesbetween elements as you go.

    Integrated approachDont plan and control thevarious project functions in isolation (e.g., scope, quality,cost, time, risk), as they are all interdependent. Instead,adopt a more integrated approach by bringing themtogether at key control points on the WBS (e.g., workpackages or control accounts).

    Keep it simple, systematically Only add more detailto the plan where the cost of doing so and the increasedcomplexity it brings with it is justified by the amount of

    information it provides. Team collaborationDont forget that the plan

    represents the teams vision for achieving the objectives.So make sure they are involved in its development andany subsequent changes during the monitoring and

    control process.

  • 7/27/2019 projectplanningandcontrol-120331060550-phpapp02

    34/34

    RECAP Activity A task, operation, or process consuming time

    and possibly other resources.

    Baseline A snapshot of a plan (or element of a plan)that is used as a point of reference.

    Budget The agreed cost or quantification of resourcesneeded to complete an activity by a set time.

    Critical Path A sequence of activities through anactivity network where each activity in the sequence haszero or negative total float.

    Duration The estimated or actual time required tocomplete an activity.

    Milestone A key event selected for its importance inthe project.

    Product The measurable output of an activity.

    Resource Anything other than time that is necessaryfor carrying out an activity.