project update goat island park ph. 2 town of cramerton december 19 th, 2013

9
Project Update Project Update Goat Island Park Ph. 2 Goat Island Park Ph. 2 Town of Cramerton Town of Cramerton December 19 th , 201

Upload: lester-watson

Post on 18-Dec-2015

217 views

Category:

Documents


1 download

TRANSCRIPT

Project UpdateProject UpdateGoat Island Park Ph. 2Goat Island Park Ph. 2

Town of CramertonTown of Cramerton

December 19th, 2013

Overall Master Plan – Phase 2

Master Plan – Phase 2Phase 2-Amenities Pedestrian Bridge(3) Cornhole Boards(2) Table TennisDog ParkPlaygroundObservation Platform

Phase 2-Amenities Pedestrian Bridge(3) Cornhole Boards(2) Table TennisDog ParkPlaygroundObservation Platform

Bridge Design

Bridge Approach80’ span

Capstone Style Prefabricated Bridge165’ Center Span, Painted Black with Decorative Lighting

Capstone Style Prefabricated Bridge165’ Center Span, Painted Black with Decorative Lighting

Bridge Approach120’ spanPrefabricated Bridge

165’ span

Bridge Approach Detail

Permitting

FERC PERMIT:

US ARMY CORP OF ENGINEERS(USACOE) PERMIT (404):

NCDENR DIVISION OF WATER RESOURCES, WATER QUALITY PERMITTING (401):

NCDENR DIVISION OF ENERGY MINERAL AND LAND RESOURCES, LAND QUALITY SECTION, EROSION AND

SEDIMENT CONTROL

COAST GUARD PERMIT

“NO-RISE” CERTIFICATION:

BUILDING PERMIT – GASTON COUNTY

Cost Estimate

SCHEDULE

Project Team Meeting January 9, 2014

Complete Design January 31, 2014

Advertise for Construction Bids February 5, 2014

Open Construction Bids February 28, 2014

Award Construction Contract March 20, 2014

Begin Construction April 5, 2014

Complete Construction December 15, 2014

Questions or Comments?

Goat Island ProjectGoat Island Project