project: tpl 25 sites fire upgrade engineering … c3.13...layer to the flange connections on nozzle...
TRANSCRIPT
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Fire Protection System
Diesel Tank Specification Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Diesel Tank Specification
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Diesel Tank Specification
Revision No. A
13 July 2015 Page 3 of 9
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
DIESEL TANK SPECIFICATION Contents Page 1 Diesel Tank Specification.................................................................................................. 4
1.1 Employer Requirements ............................................................................................... 4 1.2 Specific Design Requirements ..................................................................................... 4 1.3 Nozzle Schedule ........................................................................................................... 5 1.4 Tank Construction And Quality Control ........................................................................ 5 1.5 Testing .......................................................................................................................... 6
1.5.1 Tests On Completion ........................................................................................... 6 2 Design Deliverables .......................................................................................................... 7
2.1 Documents To Be Submitted With The Tender ............................................................ 7 3 Final Documentation ......................................................................................................... 8 4 Battery Limit ...................................................................................................................... 8 5 Exclusions ......................................................................................................................... 8
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Diesel Tank Specification
Revision No. A
13 July 2015 Page 4 of 9
1 DIESEL TANK SPECIFICATION
1.1 Employer Requirements
There are to be individual Diesel Service Tanks of welded steel construction for each
Diesel Engine to be installed. These tanks will be located adjacent to each other
outside the pumphouse, in a bunded area with a sheet roof and cage sides securing
them
The tanks are to have a usable capacity as indicated in the relevant Data Sheets and
allowance shall be made for settlement and sludge as well as freeboard as required.
The tank is to have a washout drain and a low point constructed into the tank base to
facilitate draining and cleaning.
The tank shall include a sight glass type level gauge which shall be of high reliability
and if susceptible to damage it must be possible to isolate the gauge to prevent
drainage of the tank.
1.2 Specific Design Requirements
The tanks design and manufacture shall adhere to the following specific requirements:
1) The tanks shall be designed and constructed in accordance with SANS 10131
Annexure A as a minimum.
2) Tanks shall be provided with access at the top of the tank for inspection and
maintenance.
3) The tank shall fully drain from a low point.
4) Tanks shall be fitted with sight glass type level indicator.
5) Tanks shall be fitted with an earthing point, in order for others to complete the
earthing requirements.
6) Tanks shall be fitted with a name plate depicting the details of the tanks codes of
manufacture and minimum requirements according to the code. The manufacturer
and date of manufacture must also be indicated.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Diesel Tank Specification
Revision No. A
13 July 2015 Page 5 of 9
Tank Material
Tanks shall be constructed from Carbon Steel:
1) The same materials shall be used for nozzle flanges as the construction of the
tank.
2) The tanks shall be painted according to SANS12944 with colors compliant to
SANS10140, SANS1091 and the TPL standard. The TPL standard shall be the
ruling standard.
3) All metal surfaces, shall be prepared according to SANS 064, Code for Preparation
of Steel Surfaces for Painting. All surfaces shall be moisture free, clean and
properly prepared, including descaling and degreasing before the application of the
priming coat.
4) Care shall be taken in the selection of the primer and paint system to be used on
all materials.
1.3 Nozzle Schedule
The following nozzles shall be allowed for in the design.
Inlet Nozzle with closure cap to allow for filling from a mobile bowser.
Suction Nozzle.
Pipe to have interior and exterior flanges to allow the connection for the suction
piping and a Vortex inhibitor.
Vent.
Earthing boss.
High Level Switch socket.
Low level drain.
Flange Specification – to suit the standard and piping connection. To be SANS 1123,
1600 unless otherwise specified.
1.4 Tank Construction and Quality Control
1) The contractor shall supply all materials, consumables and resources in order to
design, manufacture, construct, test and commission the tanks.
2) As a minimum the following shall be allowed for each tank construction:
a. An independent inspector shall be appointed for:
Inspection and approval of tank design
Approval of welding procedures
Approval of material selection
Certification of welder coding and testing
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Diesel Tank Specification
Revision No. A
13 July 2015 Page 6 of 9
Approval of Tank weld map
Non-destructive testing (NDT) of tanks on completion of construction,
including x-ray testing (X-ray % specified by API)
Certificate of compliance for each tank
3) Protection of the shell during erection – the contractor shall install temporary
bracing at the top strake of the tank; this temporary bracing shall be removed after
the tank roof is welded in position.
1.5 Testing
The contractor shall complete all testing prescribed by SANS 10131 or the applicable
standard and in addition the following test shall be conducted.
1.5.1 Tests on Completion
The contractor shall complete a hydraulic test of the tank as a final test on
completion. The testing procedure and final acceptance by the third party inspector
remains the responsibility of the contractor.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Diesel Tank Specification
Revision No. A
13 July 2015 Page 7 of 9
2 DESIGN DELIVERABLES
The design data pack shall include the following.
1) Structural General Arrangement and Detail drawings for each type of tank shall
be submitted timeously in AUTOCAD version 2000 for integration purposes on
drawing layouts and plans.
2.1 Documents to be submitted with the tender
1) A typical general arrangement shall be issued with the tender for evaluation.
Should the design use new / unfamiliar methods (not standard mild steel tank
construction), materials or techniques in the design, details shall be provided in
order to evaluate the proposed solution adequately.
2) The contractor shall complete the tank data sheet and it shall be submitted with
the tender. The data sheet should be read in conjunction with the typical tank
layout.
3) The Quality Control plan shall be issued with tender for evaluation.
4) The contractor shall supply their preferred painting specification with the tender.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Diesel Tank Specification
Revision No. A
13 July 2015 Page 8 of 9
3 FINAL DOCUMENTATION
Data packs shall be provided in an indexed lever arch file, with a scanned electronic
copy for each tank detailing, but not limited to:
Third party inspection reports
Approved tank design
Welding procedures
Weld Map
Welders certificates (welders’ marks to be punch marked to every welded T joint
completed on a tank).
Material certificates (material codes are to be punch marked to every plate
installed on a tank). The client reserves the right to apply a hold point to this task
within the programme.
NDT (Non Destructive Testing) Reports
Certificate of compliance
A template of the Data Book Template can be found in Appendix C.
4 BATTERY LIMIT
The battery limit for the scope of supply is the top of tank concrete base, or tank bedding
layer to the flange connections on nozzle list provided. Except where the washout drain
line runs under or within the foundation and coordination will be required to complete this
work concurrently.
5 EXCLUSIONS
1) The tanks will not be insulated and no insulation attachments are required.
2) Civil Works will be done by others.
3) Electrical and Instrumentation work will be done by others.
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Didier Regnaud Cell No.: 082 818 4965 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Fire Protection System
Water Tank Specification Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Water Tank Specification
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Water Tank Specification
Revision No. A
13 July 2015 Page 3 of 10
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
WATER TANK SPECIFICATION Contents Page 1 Water Tanks Specification ................................................................................................ 4
1.1 Employer Requirements ............................................................................................... 4 1.2 Specific Design Requirements ..................................................................................... 4 1.3 Nozzle Schedule ........................................................................................................... 5 1.4 Tanks Construction And Quality Control ...................................................................... 6 1.5 Testing .......................................................................................................................... 6
1.5.1 Bottom Testing ..................................................................................................... 6 1.5.2 Tests On Completion ........................................................................................... 7
2 Design Deliverables .......................................................................................................... 8 2.1 Documents To Be Submitted With The Tender ............................................................ 8
3 Final Documentation ......................................................................................................... 9 4 Battery Limit ...................................................................................................................... 9 5 Exclusions ......................................................................................................................... 9
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Water Tank Specification
Revision No. A
13 July 2015 Page 4 of 10
1 WATER TANKS SPECIFICATION
1.1 Employer Requirements
There are to be two similar tanks of welded steel construction located adjacent to each
other on site with nozzles as indicated on the supplied layout.
The tanks are to have a usable water capacity as indicated in the relevant Data Sheets
and allowance shall be made for wasted capacity due to the initiation of vortices as well
as freeboard as required.
The Layout and Data Sheets indicate provisional dimensions based on a design using
standard sheets sizes and considering an idea aspect ratio of 1.2:1 height to diameter
ratio.
A vortex inhibitor to be specified by the engineer and fabricated by the main contractor
is to be installed on the suction pipe and the tank manufacturer is to install flanges on
the inside and outside of the tank on the suction line Nozzle.
The tank is to have a washout drain and a low point constructed into the tank base to
facilitate draining and cleaning.
1.2 Specific Design Requirements
The water tanks design and manufacture shall adhere to the following specific
requirements:
1) The tanks shall be designed and constructed in accordance with API 650 Welded
Steel Tanks for Oil Storage.
2) The tanks shall be designed to contain potable Borehole water.
3) Tanks shall be provided with manhole access at the top and bottom of the tank.
4) Tanks shall be fitted with access walkways, including all walkways, stairs, handrails
and kick flats to the top of the tank.
5) The tank shall fully drain from a low point.
6) The tank shall be supplied with an overflow to be piped onto a splash slab at
ground level in an easily observable position. This overflow pipe shall be at least
one size larger than the tank supply pipe.
7) Tanks shall be fitted with float and tape type level indicators such as the Varec
6700 liquid level gauge.
8) Tanks shall be fitted with an earthing point, in order for others to complete the
earthing requirements.
9) Tanks shall be fitted with a name plate depicting the details of the tanks codes of
manufacture and minimum requirements according to the code.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Water Tank Specification
Revision No. A
13 July 2015 Page 5 of 10
Tank Material
Tanks shall be constructed from either Carbon Steel, and the following shall be applied
by the contractor:
1) The same materials shall be used for nozzle flanges as the construction of the
tank.
2) Any Connection to the tank shall be completed using compensation pads and
cleats of the same material specification.
3) The tanks shall be painted according to SANS12944 with colors compliant to
SANS10140, SANS1091 and the TPL standard. The TPL standard shall be the
ruling standard.
a. The paint system for the tank interior must be developed to achieve a
Medium service life (5 to 15 years according to EN 12944) in the
submerged / high humidity environment.
b. The paint system for the tank exterior must be developed to achieve a
Medium service life (5 to 15 years according to EN 12944) in a C3
corrosive environment.
c. The paint system shall comprise of an epoxy primer and a polyurethane
top coat system or better and the system chosen by the Contractor shall be
subject to approval by the Employer.
4) All metal surfaces, whether painted in the workshop, factory or on site, shall be
prepared according to SANS 064, Code for Preparation of Steel Surfaces for
Painting. All surfaces shall be moisture free, clean and properly prepared, including
descaling and degreasing before the application of the priming coat.
5) Care shall be taken in the selection of the primer and paint system to be used on all
materials.
1.3 Nozzle Schedule
The following nozzles shall be allowed for in the design.
Inlet Nozzle at high level.
Suction Nozzle.
Pipe to have interior and exterior flanges to allow the connection for the suction
piping and a Vortex inhibitor.
Vent Nozzle (if not otherwise specified this is to have an area of 1.5 x the area of
the suction outlet).
Manhole – Roof (500 NB).
Manhole – Side (500 NB).
Earthing boss.
Overflow Nozzle.
Low Level Switch socket.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Water Tank Specification
Revision No. A
13 July 2015 Page 6 of 10
High Level Switch socket.
Nozzle with internal and external flange for pilot line, float level switch for
automatic filling valve.
Low level drain.
Flange Specification – to suit the standard and piping connection. To be SANS 1123,
1600 unless otherwise specified.
1.4 Tank Construction and Quality Control
1) The contractor shall supply all materials, consumables and resources in order to
design, manufacture, construct, test and commission the tanks.
2) As a minimum the following shall be allowed for each tank construction:
a. An independent inspector shall be appointed for:
Inspection and approval of tank design
Approval of welding procedures
Approval of material selection
Certification of welder coding and testing
Approval of Tank weld map
Non-destructive testing (NDT) of tanks on completion of construction,
including x-ray testing (X-ray % specified by API)
Certificate of compliance for each tank
3) Protection of the shell during erection – the contractor shall install temporary
bracing at the top strake of the tank; this temporary bracing shall be removed after
the tank roof is welded in position.
1.5 Testing
The contractor shall complete all testing prescribed by API 650 and in addition the
following test shall be conducted.
1.5.1 Bottom Testing
The contractor shall test the bottom plate welds by the vacuum box method as
described below.
Vacuum testing is conveniently performed using a metal testing box 150 mm wide by
750 mm long with a glass window in the top. The open bottom is sealed against the
tank surface by a sponge-rubber gasket. Suitable connections, valves, and gauges
should be provided. Approximately 750 mm of the seam under test is brushed with a
soap solution or linseed oil. In freezing weather, a non-freezing solution may be
necessary. The vacuum box is placed over the coated section of the seam, and a
vacuum is applied to the box. The presence of porosity in the seam is indicated by
bubbles or foam produced by air sucked through the welded seam. A vacuum can be
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Water Tank Specification
Revision No. A
13 July 2015 Page 7 of 10
drawn on the box by any convenient method, such as connection to a gasoline- or
diesel motor intake manifold or to an air ejector or special vacuum pump. The gauge
should register a partial vacuum of at least 35 kPa g.
1.5.2 Tests on Completion
The contractor shall complete a hydraulic test of the tank as a final test on
completion. The testing procedure and final acceptance by the third party inspector
remains the responsibility of the contractor.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Water Tank Specification
Revision No. A
13 July 2015 Page 8 of 10
2 DESIGN DELIVERABLES
The design data pack shall include the following.
1) Foundation drawings for each type of tank shall be submitted with loads for use
by the structural engineer to design the concrete works. A bitumen based layer
works has been allowed for in the civil tenders. Any specific requirements
regarding the bedding materials interface between the concrete works and steel
tanks floor shall be indicated as a part of the tender.
2) Structural General Arrangement and Detail drawings for each type of tank shall
be submitted timeously in AUTOCAD version 2000 for integration purposes on
drawing layouts and plans.
2.1 Documents to be submitted with the tender
1) A typical general arrangement shall be issued with the tender for evaluation.
Should the design use new / unfamiliar methods (not standard mild steel tank
construction), materials or techniques in the design, details shall be provided in
order to evaluate the proposed solution adequately.
2) The contractor shall complete the tank data sheet and it shall be submitted with
the tender. The data sheet should be read in conjunction with the typical tank
layout.
3) The Quality Control plan shall be issued with tender for evaluation.
4) The contractor shall supply their preferred painting specification with the tender.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Water Tank Specification
Revision No. A
13 July 2015 Page 9 of 10
3 FINAL DOCUMENTATION
Data packs shall be provided in an indexed lever arch file, with a scanned electronic
copy for each tank detailing, but not limited to:
Third party inspection reports
Approved tank design
Welding procedures
Weld Map
Welders certificates (welders’ marks to be punch marked to every welded T joint
completed on a tank).
Material certificates (material codes are to be punch marked to every plate
installed on a tank). The client reserves the right to apply a hold point to this task
within the programme.
NDT (Non Destructive Testing) Reports
Certificate of compliance
A template of the Data Book Template can be found in Appendix C.
4 BATTERY LIMIT
The battery limit for the scope of supply is the top of tank concrete base, or tank bedding
layer to the flange connections on nozzle list provided. Except where the washout drain
line runs under or within the foundation and coordination will be required to complete this
work concurrently.
5 EXCLUSIONS
1) The tanks will not be insulated and no insulation attachments are required.
2) Civil Works will be done by others.
3) Electrical and Instrumentation work will be done by others.
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Didier Regnaud Cell No.: 082 818 4965 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Fire Protection System
Water Tank Specification – Panel Type Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Water Tank Specification – Panel Type
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Water Tank Specification
Revision No. A
13 July 2015 Page 3 of 9
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
WATER TANK SPECIFICATION – Panel Type Contents Page 1 Water Tanks Specification ................................................................................................ 4
1.1 Employer Requirements ............................................................................................... 4 1.2 Specific Design Requirements ..................................................................................... 4 1.3 Nozzle Schedule ........................................................................................................... 5 1.4 Tank Construction And Quality Control ........................................................................ 5 1.5 Testing .......................................................................................................................... 6
1.5.1 Works Inspection ................................................................................................. 6 1.5.2 Tests On Completion ........................................................................................... 6
2 Design Deliverables .......................................................................................................... 7 2.1 Documents To Be Submitted With The Tender ............................................................ 7
3 Final Documentation ......................................................................................................... 8 4 Battery Limit ...................................................................................................................... 8 5 Exclusions ......................................................................................................................... 8
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Water Tank Specification
Revision No. A
13 July 2015 Page 4 of 9
1 WATER TANKS SPECIFICATION
1.1 Employer Requirements
There are to be three similar tanks of rectangular steel panel construction located
adjacent to each other on site with nozzles as indicated on the supplied layout.
The tanks are to have a usable water capacity as indicated in the relevant Data Sheets
and allowance shall be made for wasted capacity due to the initiation of vortices as well
as freeboard as required.
The Layout and Data Sheets indicate provisional dimensions based on a design using
standard panel sizes.
A vortex inhibitor to be specified by the engineer and fabricated by the main contractor
is to be installed on the suction pipe and the tank manufacturer is to install flanges on
the inside and outside of the tank on the suction line Nozzle.
The tank is to have a washout drain and a low point constructed into the tank base to
facilitate draining and cleaning.
1.2 Specific Design Requirements
The water tanks design and manufacture shall adhere to the following specific
requirements:
1) The tanks shall be designed and constructed in accordance with SANS 10329.
2) The tanks shall be designed to contain Borehole water.
3) The Tank shall have a roof and be suitably bird proofed.
4) The Tanks as installed shall be in compliance with all ASIB requirements.
5) Tanks shall be provided with manhole access at the top and bottom of the tank.
6) Internal and external Ladders are to be provided.
7) Tanks shall be fitted with access walkways, including all walkways, stairs, handrails
and kick flats to the top of the tank.
8) The tank shall fully drain from a low point.
9) The tank shall be supplied with an overflow to be piped onto a splash slab at
ground level in an easily observable position. This overflow pipe shall be at least
one size larger than the tank supply pipe.
10) Tanks shall be fitted with float and tape type level indicators such as the Varec
6700 liquid level gauge.
11) Tanks shall be fitted with an earthing point, in order for others to complete the
earthing requirements.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Water Tank Specification
Revision No. A
13 July 2015 Page 5 of 9
12) Tanks shall be fitted with a name plate depicting the details of the tanks codes of
manufacture and minimum requirements according to the code.
Tank Material
Tanks shall be constructed from hot-dip galvanized Carbon Steel as per the suppliers
design and in accordance with SANS 10329:
1) The same materials shall be used for nozzle flanges as the construction of the tank
and corrosion protection shall be continuous.
2) Cold Galvanizing shall not be acceptable for non-standard panels and such panels
shall be fabricated before Galvanizing.
1.3 Nozzle Schedule
The following nozzles shall be allowed for in the design.
Inlet Nozzle at high level.
Suction Nozzle.
Pipe to have interior and exterior flanges to allow the connection for the suction
piping and a Vortex inhibitor.
Vent Nozzle (if not otherwise specified this is to have an area of 1.5 x the area of
the suction outlet).
Manhole – Roof (500 NB).
Manhole – Side (500 NB).
Earthing boss.
Overflow Nozzle.
Low Level Switch socket.
High Level Switch socket.
Nozzle with internal and external flange for pilot line, float level switch for
automatic filling valve.
Low level drain.
Flange Specification – to suit the standard and piping connection. To be SANS 1123,
1600 unless otherwise specified.
1.4 Tank Construction and Quality Control
1) The contractor shall supply all materials, consumables and resources in order to
design, manufacture, construct, test and commission the tanks.
2) As a minimum the following shall be allowed for each tank construction:
Certificate of compliance for each tank
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Water Tank Specification
Revision No. A
13 July 2015 Page 6 of 9
1.5 Testing
The contractor shall complete all testing prescribed by SANS 10329.
1.5.1 Works Inspection
As allowed for in SANS 10329, the purchaser shall be allowed to access the suppliers’
works and inspect the material at any reasonable time and reject materials not in
compliance with the Standard or this specification.
1.5.2 Tests on Completion
The contractor shall complete a hydraulic test of the tank as a final test on completion.
The testing procedure and final acceptance by the third party inspector remains the
responsibility of the contractor.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Water Tank Specification
Revision No. A
13 July 2015 Page 7 of 9
2 DESIGN DELIVERABLES
The design data pack shall include the following.
1) Foundation drawings for each type of tank shall be submitted with loads for use
by the structural engineer to design the concrete works. Any specific
requirements regarding the interface between the concrete works and steel tanks
floor shall be indicated as a part of the tender. The intended mounting is
indicated on the Data Sheet.
2) Structural General Arrangement and Detail drawings for each tank shall be
submitted timeously in AUTOCAD version 2000 for integration purposes on
drawing layouts and plans.
2.1 Documents to be submitted with the tender
1) A typical general arrangement shall be issued with the tender for evaluation.
Should the design use new / unfamiliar methods (not standard mild steel tank
construction), materials or techniques in the design, details shall be provided in
order to evaluate the proposed solution adequately.
2) The contractor shall complete the tank data sheet and it shall be submitted with
the tender. The data sheet should be read in conjunction with the typical tank
layout.
3) The Quality Control plan shall be issued with tender for evaluation.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Water Tank Specification
Revision No. A
13 July 2015 Page 8 of 9
3 FINAL DOCUMENTATION
Data packs shall be provided in an indexed lever arch file, with a scanned electronic
copy for each tank detailing, but not limited to:
Third party inspection reports
Approved tank design
Welding procedures
Weld Map
Welders certificates (welders’ marks to be punch marked to every welded T joint
completed on a tank).
Material certificates (material codes are to be punch marked to every plate
installed on a tank). The client reserves the right to apply a hold point to this task
within the programme.
Certificate of compliance
4 BATTERY LIMIT
The battery limit for the scope of supply is the top of tank concrete base to the flange
connections on nozzle list provided.
5 EXCLUSIONS
1) The tanks will not be insulated and no insulation attachments are required.
2) Civil Works will be done by others.
3) Electrical and Instrumentation work will be done by others.
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Didier Regnaud Cell No.: 082 818 4965 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Fire Protection System
Foam Concentrate Tank Specification Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Foam Concentrate Tank Specification
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Foam Concentrate Tank Specification
Revision No. A
13 July 2015 Page 3 of 11
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
FOAM CONCENTRATE TANK SPECIFICATION Contents Page 1 Foam Concentrate Tanks Specification ............................................................................ 4
1.1 Employer Requirements ............................................................................................... 4 1.2 Specific Design Requirements ..................................................................................... 4 1.3 Nozzle Schedule ........................................................................................................... 5 1.4 Tanks Construction And Quality Control ...................................................................... 5 1.5 Testing .......................................................................................................................... 5
1.5.1 Tests On Completion ........................................................................................... 5 2 Design Deliverables .......................................................................................................... 6 3 Documents To Be Submitted With The Tender ................................................................ 6 4 Final Documentation ......................................................................................................... 6 5 Battery Limit ...................................................................................................................... 6 6 Exclusions ......................................................................................................................... 7 Appendix A ................................................................................................................................ 8 Appendix B ................................................................................................................................ 9 Appendix C .............................................................................................................................. 10
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Foam Concentrate Tank Specification
Revision No. A
13 July 2015 Page 4 of 11
1 FOAM CONCENTRATE TANKS SPECIFICATION
1.1 Employer Requirements
There are to be two similar tanks of glassfibre construction located adjacent to each
other on site with nozzles as indicated on the supplied layout.
The tanks are to have a usable foam concentrate capacity as indicated in the relevant
Data Sheets and allowance shall be made for wasted capacity due to settlement and
differing expansion rates; the suction shall be located 100 mm above the tank base to
allow for settlement.
A preliminary design has been completed and the Data Sheet and drawings indicate
this design. It shall be the tank supplier/manufacturers responsibility to design the tank
to suit the stated requirements. Should the dimensions required not be achievable the
engineer/project manager should be advised of this and the design completed in
consultation with the engineer to ensure a usable final product.
The tank shall have a low point drain to facilitate the cleaning of the tank.
1.2 Specific Design Requirements
The concentrate tanks design and manufacture shall adhere to the following specific
requirements:
1) For this project two tanks are required; these are to be of similar size and require
the same nozzles however the location of the nozzles may vary between the two to
suit the installation.
2) The tanks design shall be the responsibility of the supplier/manufacturer and shall
be designed in accordance with the foam manufacturer’s requirements as per the
concentrate storage document and MSDS which can be found in Appendix B.
3) The tanks shall be designed, manufactured and installed in accordance with SANS
53121 (EN 13121). Should this standard not be complied with the designer shall
submit details regarding the standard being used, the deviation from SANS 53121
and the reason for this deviation for approval by the client. Should a more
appropriate standard be available the designer shall advise the employer of this for
consideration
4) The tanks shall be designed to contain Alcoseal 3-6 foam concentrate.
5) All tanks shall be provided with manhole access in the side of the tank.
6) The tank shall fully drain from a low point.
7) Tanks shall be of translucent construction with a level indicator adhered to the
outer surface to facilitate level monitoring.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Foam Concentrate Tank Specification
Revision No. A
13 July 2015 Page 5 of 11
8) Tanks shall be fitted with a name plate depicting the details of the tanks codes of
manufacture, the manufacturer, the date of manufacture and minimum
requirements according to the code.
9) The tank manufacturer shall advise of the requirements for the mounting of the
tank. Provision has been made in the initial specification for the provision of a level
concrete base with bitumen bedding for the tank
10) Tanks shall be constructed from glass-fibre however the selection of reinforcing
fibre, resin and other materials used in the construction shall be specified by the
manufacturer dependent on the most cost effective solution suitable to the duty.
1.3 Nozzle Schedule
The following nozzles shall be allowed for in the design.
Fill Inlet Nozzle at high level with external and internal flange
Supply Suction Nozzle with external and internal flange
Secondary suction nozzle for the circulation of concentrate
Vent Nozzle
Manhole – Side
Low level drain
Roof Access hatch
Circulation inlet nozzle
Test Sample point nozzle.
Flange Specification – SANS1123 - 1600/3
1.4 Tanks Construction and Quality Control
1) The contractor shall supply all materials, consumables and resources in order to
design, manufacture, construct, test and commission the tanks.
2) Each tank shall have such nameplates, approvals and certificates as are required
for the construction of composite atmospheric tanks and tanks for the containment
of the foam concentrate.
1.5 Testing
The contractor shall complete all testing required for approval and certification of the
tanks.
1.5.1 Tests on Completion
The contractor shall complete a hydraulic test of the tank as a final test on completion
to be observed by the clients’ representative. The testing procedure and final
acceptance by the third party inspector remains the responsibility of the contractor.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Foam Concentrate Tank Specification
Revision No. A
13 July 2015 Page 6 of 11
2 DESIGN DELIVERABLES
The design data pack shall include the following.
1) Foundation drawings for each type of tank shall be submitted with loads for use
by the structural engineer to design the concrete works. A bitumen based layer
works has been allowed for in the civil tenders if other requirements are to be
specified this must be advised; the tank manufacturers’ requirements will be
accommodated. Any specific requirements regarding the bedding materials
interface between the concrete works and tank floor shall be indicated as a part
of the tender.
2) Structural General Arrangement and Detail drawings for each tank shall be
submitted timeously in AUTOCAD version 2000 for integration purposes on
drawing layouts and plans.
3 DOCUMENTS TO BE SUBMITTED WITH THE TENDER
1) Should the intended design or installation not comply with the requirements of
SANS 53121 or should a valid alternative be proposed the details of the deviation
or alternative proposed shall be submitted with the tender. Details shall be
provided in order to evaluate the proposed solution adequately.
2) The contractor shall complete the tank data sheet and it shall be submitted with
the tender. The data sheet should be read in conjunction with the typical tank
layout.
3) The Quality Control plan shall be issued with tender for evaluation.
4 FINAL DOCUMENTATION
Data packs shall be provided in an indexed lever arch file, with a scanned electronic
copy for each tank detailing, but not limited to:
Third party inspection reports
Approved tank design
Material certificates
NDT (Non Destructive Testing) Reports
Certificate of compliance
5 BATTERY LIMIT
The battery limit for the scope of supply is the top of tank concrete base, or tank bedding
layer to the flange connections on nozzle list provided.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Foam Concentrate Tank Specification
Revision No. A
13 July 2015 Page 7 of 11
6 EXCLUSIONS
1) Civil Works will be completed by others.
2) Electrical and Instrumentation work will be completed by others.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Foam Concentrate Tank Specification
Revision No. 01
13 July 2015 Page 8 of 11
Appendix A
TYPICAL TANK LAYOUT
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Foam Concentrate Tank Specification
Revision No. 01
13 July 2015 Page 9 of 11
Appendix B
Foam Concentrate
Storage Manual and MSDS
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Foam Concentrate Tank Specification
Revision No. 01
13 July 2015 Page 10 of 11
Appendix C
TANK DATA SHEET
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Didier Regnaud Cell No.: 082 818 4965 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
ALL SITES
Fire Protection System
Piping supply and Installation Specification Issue Date : 6/7/2015 Revision No. : B Project No. : 11992
Date: 6/7/2015
Document Title: TPL Fire Protection System:
Piping Supply and Installation Specification
Author: Edward Standen
Revision Number: B
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Piping Supply and Installation Specification
Revision No. B
29 July 2015 Page 3 of 17
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL
PIPING SUPPLY AND INSTALLATION SPECIFICATION Contents Page Contents Page ........................................................................................................................... 3
1 Piping Supply and Installation Specification ..................................................................... 4
1.1 General Requirements of Project ................................................................................. 4
1.2 Specific technical specifications - Piping ...................................................................... 4
1.2.1 All piping: ......................................................................................................................... 4
1.2.2 Carbon Steel Piping: ...................................................................................................... 6
1.2.3 Galvanised Steel Piping: ............................................................................................... 6
1.2.4 Stainless Steel Piping:................................................................................................... 6
1.2.5 HDPE Piping: .................................................................................................................. 7
1.3 Specific technical specifications - Painting ................................................................. 10
1.3.1 Painting and identification of Piping: ......................................................................... 10
1.4 Specific technical specifications - Protection .............................................................. 10
1.4.1 Winterisation of Piping: ............................................................................................... 10
1.4.2 Heat shielding of Piping: ............................................................................................. 11
1.5 Specific technical specifications - Supports ............................................................... 11
1.5.1 Pipe supports: ............................................................................................................... 11
1.6 Specific technical specifications - Ancillaries ............................................................. 11
1.6.1 Pressure Gauges ......................................................................................................... 11
1.6.2 Fasteners ...................................................................................................................... 12
1.6.3 Gaskets and Seals ....................................................................................................... 12
1.7 Piping Construction .................................................................................................... 12
2 Documentation ................................................................................................................ 14
2.1 Documents to be submitted with the tender ............................................................... 14
2.2 Final Documentation ................................................................................................... 15
3 Obligations of the Contractor .......................................................................................... 16
3.1 Erection Works ........................................................................................................... 16
3.2 Transport of Material on Site ...................................................................................... 16
3.3 Tools for Erection Works ............................................................................................ 16
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Piping Supply and Installation Specification
Revision No. B
29 July 2015 Page 4 of 17
1 PIPING SUPPLY AND INSTALLATION SPECIFICATION
1.1 General Requirements of Project
The piping has been specified according to the following:
Underground pipe runs shall be HDPE, PE100, PN16
Where piping is to protrude above ground the line shall change to Carbon Steel
or Stainless Steel below ground with a flange to flange connection before
turning to exit the ground.
Carbon steel for use on the Hydrant system shall be hot-dip galvanised.
External headers for the Cooling water system shall be hot-dip galvanised.
All above ground piping after a control valve and feeding to equipment with
small bore apertures shall be stainless steel.
All above ground piping on the foam premix system after a control valve shall
be galvanised steel.
All above ground piping containing foam premix before a control valve shall be
black carbon steel.
All above ground piping in the pumphouse and suction lines from the water
tanks shall be galvanised carbon steel.
Any diesel supply lines shall not be galvanised – these lines should be
stainless steel or as specified.
All foam concentrate lines shall be stainless steel.
1.2 Specific technical specifications - Piping
The piping construction, erection, inspection and testing shall adhere to the following
specific requirements:
1.2.1 All piping:
1) All fasteners shall comply with the requirements of SABS 135 - Metallic and other
inorganic coatings as well as SABS 1700 as a minimum.
2) All steel piping shall be fabricated in accordance with the AFC (Approved for
construction) ISO’s. The Contractor shall shop fabricate as much pipework as
possible but shall be responsible for ensuring that sufficient final welds are
completed on site to ensure that piping fits correctly.
a. Pipework must not be under tension when as installed
b. All welds, including those completed on site must be hot-dip galvanized.
Cold galvanizing will only be permitted for minor galvanizing repairs and
where small appurtenances are fitted if the internal weld surface is also
cold galvanized.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Piping Supply and Installation Specification
Revision No. B
29 July 2015 Page 5 of 17
3) The piping shall be installed in accordance with SANS 2001-DP2 and SANS 2001-
DP6 which are required by SANS 10400-T and SANS 10400-W
4) Flanges on parallel pipes shall be offset so as to not interfere with one another.
5) All piping shall be properly supported and piping supports shall be selected and
located to support the weight of the piping, line content, operating weight, hydraulic
testing weight, valves, strainers, equipment and any other imposed loads.
6) Pipe supports shall be installed according to the design specifications to achieve
the following:
a. Structural pipe supports are to be provided at intervals not exceeding 2.5m
for piping up to and including 50mm Nominal bore and all other piping shall
be supported at 4.5m intervals
b. Piping shall not be supported or suspended from other piping.
c. Pipe supports shall guide, anchor and support piping so that thermal
expansions take place in a controlled and predictable manner.
d. Piping supports shall be located such that piping shall not have a sag
exceeding 2mm between any two points, when carrying pressure test or
working fluid.
7) Piping supports, anchors and guides shall be set such that the finished installation
will provide a uniform slope for drainage.
8) Weep holes are required in all pipe risers on bulk tanks.
a. These are to be 8mm diameter
b. Shall drain the pipe below the IF (insulating flange) kits for the cathodic
protection.
9) Should piping supports be welded to structural steel, it shall be the Contractors
responsibility to repaint the structural steel to an approved specification and
standard.
10) The Contractor shall allow for the installation of all instrumentation connections
required.
11) The Contractor shall allow for the installation of all valves as per the schedule in
the commercial tender.
12) All pipelines installed by the Contractor shall be flushed with water until clean, the
Contractor shall allow for flushing prior to final fixing to equipment. With prior
approval at a time convenient to the Employer, the Contractor may use the raw /
potable water system for flushing and testing. All lines shall be drained once
flushing and testing has been completed.
13) The Contractor shall supply all material and equipment to flush the pipe lines.
14) All in-line control valves, orifice plates, temperature probes, safety valves, globe
and butterfly valves as well as any other bore obstructed valve shall only be
installed after the flushing is completed. The Contractor shall allow for the
necessary spacer spool pieces to temporarily replace the above during flushing.
15) Flushing shall not be conducted through items of equipment (for example pumps,
vessels and exchangers) but flush may be dumped in tanks, tanks shall then be
drained and cleaned after flushing.
16) Any connection to equipment shall not exert/transfer pipe stress to the equipment.
This shall be verified by feeler gauges with loose bolts, and recorded in the QCP
before piping is securely fastened.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Piping Supply and Installation Specification
Revision No. B
29 July 2015 Page 6 of 17
17) The Contractor shall ensure that flanges are centered and parallel and allow for the
correct space for gasket with loose bolts, adjustment shall only be conducted to
piping and not to equipment nozzles.
18) If any works conducted by the Contractor are considered unsatisfactory by the
Employer, the Contractor shall rectify the works at their own cost.
1.2.2 Carbon Steel Piping:
1) All the above ground pipelines shall conform to SANS 62 and SANS 719.
SANS 62 medium shall be used up to 150mm
SANS 719 with 4.5mm wall shall be used for 200 and 250mm
SANS 719 with 6mm wall shall be used for pipe 300mm and above.
2) All above ground pipework shall be fabricated flanged pipework and shall comply
with SABS1476 – Fabricated Flanged Steel Pipework.
3) All flanges shall conform to SANS 1123, class 1600/3 unless otherwise specified.
4) All fittings (caps, elbows, tee’s reducers etc.) shall be JIS B2311
5) All black carbon steel below ground shall be protected against corrosion by
“Denso” type protective wrapping in accordance with SANS 10129. The product
specified by the supplier shall be suitable for the application and approved by the
Employer prior to procurement.
1.2.3 Galvanised Steel Piping:
1) Galvanised steel piping shall be constructed as per the requirements for Carbon
Steel.
2) This piping shall be fabricated before hot-dip galvanising.
3) Galvanising shall be completed to SANS 32
1.2.4 Stainless Steel Piping:
1) All Stainless steel piping shall be ASTM A312, 316 grade, schedule 20 to the
specifications indicated on the ISO’s and fabricated in accordance with SABS 1476
where applicable.
2) All fittings (caps, elbows, tee’s reducers etc.) shall be ASTM /ASME SA/A 403 WP
–W (Welded)
3) All flanges shall conform to SANS 1123, class 1600/3 unless otherwise specified.
4) All Stainless steel piping shall be welded according to BS 4677 and as specified in
the Isometric drawings.
5) The Contractor shall allow for pickle and passivation of all stainless steel piping,
whether welded in workshops or on site, in accordance with ASTM A967/A967M-
13. Mild steel contamination on stainless steel piping shall not be accepted.
6) Any welding (of stainless steel pipe) not covered by the above specification shall
be completed entirely with Argon welding (TIG)
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Piping Supply and Installation Specification
Revision No. B
29 July 2015 Page 7 of 17
1.2.5 HDPE Piping:
1) HDPE piping is to be used for long underground runs but shall not protrude
above ground at any point.
2) Black polyethylene pipes that comply with SANS 4427 or current and valid SABS
533 regulations shall be used
3) All HDPE pipe shall be PE100, PN16 unless otherwise stated
4) All PE pipe and fitting connections shall be machine butt welded or electro-fusion
welded
5) All connections between PE and steel pipe shall be flange to flange and only
molded stubs shall be used
6) HDPE pipe shall comply with the ISO standards in terms of manufacture
7) No compression fittings may be used
8) No Screwed fittings may be used
9) Victaulic fittings may be used for blanking off pipe for testing purposes only
10) HDPE fittings shall meet the requirements of SANS 4427
11) All sharp edges around pipes shall be rounded off to a 3mm radius
12) HDPE fittings shall be extruded and manufactured from PE100 material.
13) HDPE fabricated fittings if required shall be manufactured from HDPE PE100 at
least one pressure class higher than the specified main pipe material
14) HDPE pipe must be traceable and have the material class and pipe class
identification. The piping should come delivered with material certificates
indicating the batch, manufacturer, material of manufacture etc.
15) The preferred layout of the heating coils contained in each individual fittings up to
and including mains dimension 160mm should be designed so that only one
complete process cycle is necessary to fully fuse the fitting to the adjoining pipes
or pipeline components as applicable. To enable an easy assembly on site and a
possible preassembly of one end of the fitting, electro-fusion fittings of 200mm
and above may be of a bifilar construction (2 separate fusion zones)
16) Importantly no metallic parts of the heating element should be exposed at any
place and all coils are to be fully imbedded into the body of the fittings for
protection purposes. The surface on the internal diameter of the fitting shall be
smooth, protrusions from electro-fusion coils or terminals on the internal
diameter will not be acceptable.
17) All fittings must have molded-in or stamped-in identification and appropriate
product information.
18) All fittings shall be molded from recognized top quality virgin PE100 resin.
19) The Contractor must provide all product approvals for all piping, molded/extruded
fittings and electro-fusion fittings to be supplied. The Contractor shall advise
what products/manufacturer is proposed and the final product supplier shall be
subject to approval by the Employer.
Handling and Storage
20) Before transporting HDPE pressure pipes the loading surface of the vehicle must
be cleaned and free from projecting nails, screws or other sharp objects.
21) The bottom layer of all pipes must be as far as possible be in contact with the
loading surface throughout their entire length and not project beyond it.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Piping Supply and Installation Specification
Revision No. B
29 July 2015 Page 8 of 17
22) The pipes must be secured from slipping and shall not be pulled over sharp
edges when loading and offloading.
23) Pipes shall not be dragged along the ground.
24) Pipes, fittings and coils shall be stored in such a way that they are completely
protected from direct sunlight. When covered they must be well ventilated to
avoid accumulation of direct heat and resultant deformation. Transparent
coverings shall not be used.
25) The storage location shall be flat and shall, for pipes, support the pipes
throughout their length. Stones and sharp objects shall not be present.
26) Pipes shall not be stacked to a height exceeding 1m.
27) The pipes must be secured at the sides to prevent them from rolling.
28) Contact with harmful materials shall be avoided at all times.
29) As far as possible, coils shall be stored in a horizontal position. The area shall
be free of stones and sharp objects. If stored upright they must be secured to
avoid tilting.
30) Pipes and valves shall be protected against damages caused by impacting,
dropping etc. during transportation and handling.
31) Rubber lined vertical posts shall be spaced on the sides of transporting vehicles
to provide adequate support to the loaded pipes.
32) Pipes which cannot be off-loaded by hand shall only be lifted by means of
suitably approved broad band slings. The use of wire, chains, hooks, crowbars
and similar items shall not be permitted and the pipes, fittings and specials shall
not be handled in such a manner as could cause damage to occur. No
concessions will be made in the above regard and failure on the Contractors
part to comply shall be considered just cause for the Employer to investigate
and require remedial measures including replacing material at the Contractors
cost.
33) When the pipes are to be stored on site it is essential that the storage be as
level as possible and any objects which may cause damage to the pipes shall
be cleared from the laydown.
34) A representative of the manufacturer shall at all times be present to supervise
the off-loading of pipes and fittings during deliveries.
35) The Employer may thoroughly inspect all pipes, fittings and specials delivered
to the site but his acceptance of same as being in good condition shall not
relieve the Contractor of any of his obligations or responsibilities under this
contract
36) Materials inspected and rejected by the Employer shall be removed from the
site and shall be replaced by the Contractor with other approved materials at his
own expense.
Installation:
37) All pipes shall be inspected for defects immediately before installation and faulty
pipes or pipes which have suffered damage which would affect their
serviceability shall not be used in the Works. The cost of such pipes shall be for
the Contractors account.
38) HDPE pipes shall be transported, laid, joined and backfilled in accordance with
the manufacturers written instructions.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Piping Supply and Installation Specification
Revision No. B
29 July 2015 Page 9 of 17
39) Installation including fusion joining work must be directed and supervised by
suitably qualified and experienced persons and the Contractor shall
demonstrate his ability to provide this in his tender.
40) Prior to laying the pipe in a trench, the bed of the trench must be prepared to
provide support throughout the entire length of the pipe. The pipe shall not be
laid directly on cohesive, rocky or stony soil. The trenching and backfilling shall
be completed in accordance with the requirements issued by the Employer.
41) Pipes supplied in coils of up to 63mm diameter may be unrolled with the coil in
the vertical position. For larger diameters an unwinding device shall be used. A
turn-style can be used with the coil laid on it in a horizontal position or with the
coil mounted vertically on a slow moving vehicle. The pipe shall never be
removed from a coil in a spiral manner as this may cause kinking. Should kinking
nevertheless occur the Contractor shall cut the pipe on either side of the kink,
prepare the ends and then use an approved joint after laying. All costs of
dealing with kinking shall be to the Contractors’ expense. A minimum bending
radius of 35 x the diameter shall be observed.
42) Flange connections shall be treated with an approved priming solution, packed
with approved mastic and wrapped with an approved petrolatum tape to the
product manufacturers’ specification.
43) When flanged connections of HDPE pipe are required, the edge on the side of
the backing flange, that fit against the HDPE flange adapter shall be rounded or
chamfered.
44) Flange connections to HDPE pipe may only be completed when the HDPE pipe
is cool to minimize stresses on the pipe due to contraction. Such connections
must fit well when connected cold. Backfilling the pipe will facilitate cooling. In
terms of clause 7.3.1.1 of SANS 1200L however, the pipeline shall only be
backfilled partially to keep the pipe joints open for inspection during the
hydrostatic pressure testing of the pipeline. The trench may be backfilled at the
pipe joints once the hydrostatic pressure testing is completed.
45) Prior to the commencement of installation the Contractor shall have the following
approved documentation:
a. A quality plan which must be submitted to and approved by the Employer
b. Installation plans showing the location, configuration and positioning of the
installation
c. A data book shall be generated by the Contractor and verified by the
contractors’ site manager who shall sign the data book approval sheets.
The data books are submitted by the Contractor to the Employer
d. The data book shall contain but not be limited to the following
i. Weld control sheets showing the data of weld, welding and cooling
time, ambient temperature, pressure and GPS coordinated of the
weld position (accuracy to be 0.5m (or better) in X, Y and 5m (or
better) in Z for every pipe connection, indicating whether it is a butt
weld or electro-fusion coupling
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Piping Supply and Installation Specification
Revision No. B
29 July 2015 Page 10 of 17
1.3 Specific technical specifications - Painting
1.3.1 Painting and identification of Piping:
1) All steel piping shall be painted in the workshop prior to delivery to site.
2) All steel shall be painted in accordance with SANS12944 and the TPL specification
PL407 with colors compliant to SANS10140, SANS1091 and the TPL color
standard. The TPL color standard shall be the ruling standard.
a. TPL requires the following colors
i. Fire Water shall be Signal Red (A11)
ii. Foam Concentrate shall be Royal Blue
iii. Foam Premix shall be Signal Red with White Bands.
b. For Carbon steel the TPL Standard PL407 shall be adhered to; for
galvanized and stainless steel piping the following criteria shall be used to
achieve the same level of protection and quality of covering.
i. The paint system must be developed to achieve a Medium service
life (5 to 15 years according to EN 12944) in a C4 corrosive
environment.
ii. The paint system shall comprise of an epoxy primer and a
polyurethane top coat system or better and the system chosen by
the Contractor shall be subject to approval by the Employer.
3) All metal surfaces, shall be prepared according to SANS 064, Code for Preparation
of Steel Surfaces for Painting. All surfaces shall be moisture free, clean and
properly prepared, including descaling and degreasing before the application of the
priming coat.
4) Care shall be taken in the selection of the primer and paint system to be used on
all materials as well as the preparation of the material surface noting that
galvanised carbon steel and stainless steel piping will require different treatment to
standard black carbon steel.
1.4 Specific technical specifications - Protection
1.4.1 Winterisation of Piping:
1) All piping of 50mm or smaller nominal bore shall be winterized to protect it from
freezing.
2) The temperature is to be prevented from dropping below 4 °C
3) Insulation is to be designed and installed in accordance with SANS 9288 and
SANS 612
4) The piping will be subjected to ambient conditions
5) Cladding should be non-flammable but need not provide protection against heat or
flame exposure
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Piping Supply and Installation Specification
Revision No. B
29 July 2015 Page 11 of 17
1.4.2 Heat shielding of Piping:
1) All piping within bunded areas or within 3m of a fire zone or outside a bund but
within 300mm of the top of the bund shall be protected against heat damage by
the application of Intumescent paint.
2) Any intumescent coating shall be rated for protection for exposure to Hydrocarbon
fuel fires to exposed outdoor equipment. At least a 120 min rating shall be
achieved
3) The coating shall be applied in strict accordance to the manufacturers’
specification including all surface preparation.
4) The selected system may differ depending on the piping material and in the case
of black carbon steel shall provide suitable corrosion protection or else be suitable
for application over a standard paint regime.
5) The final color shall be red, comparable with if not the same as SANS A11 signal
red or the TPL standard unless otherwise agreed.
1.5 Specific technical specifications - Supports
1.5.1 Pipe supports:
1) All pipe racks / support structure will be hot dipped galvanized to SANS 121 after
fabrication and fixed by either welding (to tanks) or bolting (to bases or existing
structure) on site. Site weld (as allowed above) shall be touched up with cold
galvanizing.
2) Proprietary pipe hangers and supports shall be used
3) Pipes shall be positioned to maintain clearance to all other fixed structure, except
the members to which such pipes are clamped. Supports shall be manufactured to
the specifications to be issued by the designers and any deviations shall be
authorized by the Employer.
4) Structural pipe supports are to be provided at intervals not exceeding 2.5 m for the
piping up to 50 mm Nominal Bore (NB) and all other piping shall be supported at
4.5 m intervals as per the Employers requirement.
5) The installation and welding of pipe supports to the fuel storage tanks shall
conform to all requirements of API650.
1.6 Specific technical specifications - Ancillaries
1.6.1 Pressure Gauges
1) Pressure gauges shall be Glycerine filled
2) Pressure gauges shall be capable of taking measurements between 0 kPa and
1600 kPa, or 500 kPa above the maximum working pressure of the proposed
water supply, whichever is the higher or as specified by the Employer.
The scale shall be sub-divided into units not exceeding:
20 kPa, in the case of a maximum scale value up to and including 1000 kPa
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Piping Supply and Installation Specification
Revision No. B
29 July 2015 Page 12 of 17
50 kPa, in the case of a maximum scale value exceeding 1000 kPa, and up to and including 1600 kPa
100 kPa in the case of a maximum scale value exceeding 1600 kPa
3) Any pressure gauge of Ø 150 mm or larger must be mounted to a standalone
instrument stand as per the Employers design.
4) All pressure gauges in the pumphouse shall be remote mounted as per the TPL
specification.
5) All pressure gauges shall be Bourdon type.
6) All pressure gauges shall be specified in accordance with the relevant Data
Sheets.
7) Calibration certificates shall be supplied for all pressure gauges.
1.6.2 Fasteners
Fasteners shall conform, as a minimum, to SANS 1700 including the following:
1) All fasteners used are metric fasteners.
2) Each bolt head is fitted with a flat washer.
3) Each nut is fitted with a flat washer.
4) Each bolt length is sized so that two full threads are visible (minimum).
5) No bolts are cut to the ‘right’ size.
6) All fasteners are new.
7) All fasteners are coated in an anti-seize compound before fastening.
8) Stainless steel fasteners shall be used on all stainless steel pipes.
9) Galvanised bolts shall be used for all galvanised piping connections
10) On black carbon steel pipes outside the pumphouse all bolts shall be galvanised,
stainless steel or suitably protected against corrosion to the satisfaction of the
Employer. The specification to be used shall be noted in the tender return. The
Employer may specify the use of an alternative protection if required.
1.6.3 Gaskets and Seals
1) No gaskets used in the fixed fire protection system shall contain any asbestos.
2) All relevant gaskets shall be full-face pipe flange gaskets made from Aramid fibers
bound with Nitrile Butadine rubber 3 mm thick.
1.7 Piping Construction
1) All piping shall be hydraulic pressure tested to 150% operating pressure for 3
hours. The tenderer shall supply all equipment required to complete the above
stated test. The tenderer shall be responsible for draining of the pipe lines if
required on completion of the leak test without damage or disruption to property.
2) On completion of the hydraulic pressure test the leakage rate shall be tested as per
the requirements in SANS 1200L and any TPL requirements specified.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Piping Supply and Installation Specification
Revision No. B
29 July 2015 Page 13 of 17
3) The hydraulic testing of pipework may be required throughout construction
particularly as buried pipe shall be tested before being buried and as such, before
piping above it is installed.
4) The tenderer shall maintain records of all of the tests as stated above. These
records shall be kept on site and shall be listed in the QCP.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Piping Supply and Installation Specification
Revision No. B
29 July 2015 Page 14 of 17
2 DOCUMENTATION
2.1 Documents to be submitted with the tender
1) The Quality Control plan shall be issued with tender for evaluation.
2) In addition the tenderer shall supply rates for pipe supports fabrication from steel;
these pipe supports shall be bolted to the existing concrete structures and welded
where required to the tanks being protected. The rate shall apply to the finished
product weight. The tenderer shall indicate this in the BOQ.
3) The tenderer shall allow for the supply of proprietary piping supports on a cost
plus basis, the tenderer shall issue rates for the installation of pipe supports
according to the following types; sliding supports, hangers and U bolts. A
representative picture of each is given below.
The tenderer shall indicate these prices in the returned BOQ.
TYPE 1 TYPE 2 TYPE3
4) Paint specification for approval by the Employer.
5) Pickle and Passivation procedure for review by the Employer
6) Typical Rigging Study for piping material for review by the Employer.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Piping Supply and Installation Specification
Revision No. B
29 July 2015 Page 15 of 17
2.2 Final Documentation
Data packs shall be provided in an indexed lever arch file, with a scanned electronic
copy for all piping. The required documentation includes but is not limited to:
Third party inspection reports
Approved piping design
Welding procedures
Weld Map
Welders certificates,
Material certificates
NDT (Non Destructive Testing) Reports
Certificate of compliance
“As-built” redlined ISO’s and GA
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Piping Supply and Installation Specification
Revision No. B
29 July 2015 Page 16 of 17
3 OBLIGATIONS OF THE CONTRACTOR
The Contractor shall comply with all other documentation issued with this by the
Employer.
3.1 Erection Works
In order to comply with South African Safety Regulations, the Contractor shall supply a
rigging study for all lifting and rigging activities, these shall be accessed by the site
engineers and safety personnel and approved before any lifting is carried out.
The Contractor shall advise who will be responsible for the completion of all rigging
studies anticipated to be required during construction.
The Contractor is further required to provide a typical rigging study for the erection of
the piping with the tender submission to ensure that it falls within the standards that the
Employer requires for the site installation works. Where such a study isn’t required a
suitable reason shall be given as to why this requirement hasn’t been complied with.
3.2 Transport of Material on Site
The Contractor shall be responsible for movement of material from the appointed
laydown area to the site for erection. Care shall be taken at all times to ensure that the
material remains in good condition
3.3 Tools for Erection Works
All tools and equipment (incl. cranes, fixed and moveable) required for the completion
of the works shall be supplied by the Contractor and included in the cost..
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Didier Regnaud Cell No.: 082 818 4965 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade
Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Technical Specification
Ball Valves
Issue Date : 13/7/2015
Revision No. : A
Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Technical Specification – Ball Valves
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST
TPL25 – Technical Specification – Ball Valves
Revision No. A
13 July 2015 Page 3 of 7
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186
TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification – Ball Valves
Contents Page
Contents Page ........................................................................................................................... 3 1 Technical Specification – Ball Valve ................................................................................. 4
1.1 Introduction ................................................................................................................... 4 1.2 Scope of this Specification ........................................................................................... 4 1.3 General methods, standards, specifications and approach ......................................... 4
1.3.1 Equipment: ........................................................................................................... 4 1.3.2 Supply: ................................................................................................................. 5
1.4 Valve Actuation ............................................................................................................. 5 1.4.1 Equipment: ........................................................................................................... 5
1.5 Corrosion protection ..................................................................................................... 6 1.6 Installation and Commissioning Requirements ............................................................ 6
2 Documentation supply ...................................................................................................... 6
TRANSNET PIPELINES prepared by: SiVEST
TPL25 – Technical Specification – Ball Valves
Revision No. A
13 July 2015 Page 4 of 7
1 TECHNICAL SPECIFICATION – BALL VALVE
1.1 Introduction
This specification is to apply to the Ball valves to be employed as isolation valves within
the fire protection system. There are valves located in positions where they will be
under suction conditions as well as valves which will experience considerable pressure
at all times. Most valves will be manually controlled however there may be some
valves which will be actuated and this specification will address this.
1.2 Scope of this Specification
The scope of this specification is to address the required manufacture and functional
quality and specifications.
The quantity, performance characteristics and terms of supply of the required
equipment will be specified elsewhere in the request issued to market and will
reference this specification.
1.3 General methods, standards, specifications and approach
The valve selection and supply shall adhere to the following specific requirements:
1.3.1 Equipment:
1) The valves shall be of the NATCO make or similar
2) All valves shall be new and manufactured from all new materials unless otherwise
specified in the enquiry.
3) Valves shall:
Be lockable in the open and closed position.
Comply with the requirements of SANS 1056-1 or be approved by FM or UL
or LPC as indicated on the Data sheets.
All Ball valves shall have flange connections to the piping.
Valves identified in the data sheets for use under low pressure conditions
shall be suitable for use under suction conditions such that air is not
entrained through the valve.
Be suitable for outdoor use and shall not be adversely effected by rainfall or
exposure to sunlight. Where acceptable exceptions such as cosmetic
considerations like faded paint might result from exposure the extent of the
effect should be noted.
Reliably open even after extended periods in open or closed position.
Comply with ISO 5211: 2001 for actuator mounting.
TRANSNET PIPELINES prepared by: SiVEST
TPL25 – Technical Specification – Ball Valves
Revision No. A
13 July 2015 Page 5 of 7
4) All valves must be of high quality and suitable for a long service life of occasional
use. Valves should provide at least 20 years of service, subject to the supplier
specified maintenance regime.
1.3.2 Supply:
1) The Supplier shall provide installation instructions detailing the labor, equipment
and any special procedures, tools, equipment or personnel required for the
installation.
2) The Supplier shall include the provision of all specialist tools, equipment and
services as separate options in the tender return.
3) The material of manufacture of all parts shall be specified on the equipment
drawings or data sheets and this information shall be supplied as a tender return.
Submission of this information does not in any way negate the supplier’s
responsibility to ensure that the specified materials are suitable for the service
required by this or any other documents pertaining to the enquiry.
4) Material certificates are to be provided for every supplied valve. Typical
certificates are to be supplied with the tender return for each valve type.
5) The Supplier is to provide full operating and maintenance and overhaul manuals
including detailed section and exploded diagrams of the valves, parts lists, typical
spares lists and pricing.
6) The Supplier is to provide drawings indicating all relevant dimensions affecting the
installation including space required to perform maintenance; this information is to
be clearly indicated for all required valve sizes.
7) The Supplier shall provide a copy of all manufacturers painting specifications
relevant to the products specified.
1.4 Valve Actuation
Valve actuator selection and supply shall adhere to the following specific requirements:
1.4.1 Equipment:
1) Valve Actuators shall comply with ISO 5211: 2001 for actuator mounting.
2) Electric actuators shall include travel limiting devices, torque overload
measurement device.
3) Actuators shall include an automatic declutchable hand wheel.
4) The actuator gear mechanism shall be totally enclosed and lubricated.
5) The actuator gear mechanism shall be capable of mounting in any orientation.
6) All valves shall be indicating and the actuator shall provide indication of the open
or closed position if not indicated by the valve structure.
7) The sizing of the actuator shall be the responsibility of the purchaser if procured
separately from the valve or the valve supplier if supplied as part of a valve to
match a functional specification.
TRANSNET PIPELINES prepared by: SiVEST
TPL25 – Technical Specification – Ball Valves
Revision No. A
13 July 2015 Page 6 of 7
1.5 Corrosion protection
Mild steel units shall be shot blasted and painted on the exterior for corrosion
protection. The contractor shall supply their paint specification as a part of the tender.
Corrosion protection specification for all equipment supplied shall be as per the
supplier’s recommendation and in accordance with international standards specified for
installations in normal industrial non-coastal environments.
1.6 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the valves:
1) All valves shall be supplied complete and ready for installation including any
special fittings or fixtures required i.e. extended studs for wafer installation of long
valve.
2) The employer shall be advised of all Factory testing and allowed the opportunity to
observe Factory Acceptance Tests if required by the employer.
3) The certification documentation shall accompany the valves which shall be suitably
identified with clear serial number installation.
2 DOCUMENTATION SUPPLY
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
3) Spare parts list
4) 3D model for integration into the plant model
Documents to be supplied with the offer shall include:
1) A general arrangement.
2) Equipment design and construction information for each piece of equipment (sales
documents)
3) Approval documents (and indication of equivalency if required in section 1)
4) Maintenance and operation manuals
5) Performance data to indicate the hydraulic performance of the valve including the
pressure drop at all flow rates (may be graph, chart or equations)
6) The contractor shall complete the pump data sheet and it shall be submitted with
the tender.
7) The Quality Control plan shall be issued with tender for evaluation.
8) Corrosion resistance, corrosion protection specifications and service life
SiVEST Project Management Division
4 Pencarrow Crescent, La Lucia Ridge Office Estate,
Umhlanga Rocks. 4320
PO Box 1899, Umhlanga Rocks. 4320
South Africa
Tel + 27 31 581 1500
Fax +27 31 566 2375
Email [email protected]
www.sivest.co.za
Contact Person: Didier Regnaud
Cell No.: 082 818 4965
Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Technical Specification
Butterfly Valves Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Technical Specification – Butterfly Valves
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Butterfly Valves
Revision No. A
13 July 2015 Page 3 of 7
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification – Butterfly Valves Contents Page
Contents Page ........................................................................................................................... 3
1 Technical Specification – Butterfly Valve .......................................................................... 4
1.1 Introduction ................................................................................................................... 4 1.2 Scope of this Specification ........................................................................................... 4 1.3 General methods, standards, specifications and approach ......................................... 4
1.3.1 Equipment: ........................................................................................................... 4 1.3.2 Supply: ................................................................................................................. 5
1.4 Corrosion protection ..................................................................................................... 5 1.5 Installation and Commissioning Requirements ............................................................ 5
2 Documentation supply ...................................................................................................... 6
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Butterfly Valves
Revision No. A
13 July 2015 Page 4 of 7
1 TECHNICAL SPECIFICATION – BUTTERFLY VALVE
1.1 Introduction
This specification is to apply to the butterfly valves to be employed as isolation valves
within the fire protection system. No valves are located where they will experience
suction condition. Some valves will be regularly exposed to pressure while other won’t
but all valves will be operated very seldom thus reliability and quality is paramount to
ensure that when called upon, they operate correctly. Most valves will be manually
controlled however there are some valves which are to be actuated and this
specification will address this.
1.2 Scope of this Specification
The scope of this Specification is to address the required manufacture and functional
quality and specifications.
The quantity, performance characteristics and terms of supply of the required
equipment will be specified elsewhere in the request issued to market and will
reference this specification.
1.3 General methods, standards, specifications and approach
The valve selection and supply shall adhere to the following specific requirements:
1.3.1 Equipment:
1) The valves shall be of the AMRI ISORIA make or similar.
2) All valves shall be new and manufactured from all new materials unless otherwise
specified in the enquiry.
3) Valves shall:
Be lockable in the open and closed position.
Comply with the requirements of SANS 1849:2008 as a minimum or with EN
593 and ISO 10631 or be approved by FM or UL as indicated on the Data
sheets.
All butterfly valves of DN150 or larger shall be gear operated.
All valves shall be right handed / open through clockwise motion of input;
either lever or hand wheel.
Valves shall be suitable for outdoor use and shall not be adversely effected
by rainfall or exposure to sunlight. Where acceptable exceptions such as
cosmetic considerations like faded paint might result from exposure the
extent of the effect should be noted.
Reliably open/close even after extended periods in open or closed position.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Butterfly Valves
Revision No. A
13 July 2015 Page 5 of 7
Comply with ISO 5211:2010 for actuator mounting.
4) All valves must be of high quality and suitable for a long service life of occasional
use. Valves should provide at least 20 years of service, subject to the supplier
specified maintenance regime.
1.3.2 Supply:
1) The Supplier shall provide installation instructions detailing the labor, equipment
and any special procedures, tools, equipment or personnel required for the
installation.
2) The Supplier shall include the provision of all specialist tools, equipment and
services as separate options in the tender return.
3) The material of manufacture of all parts shall be specified on the equipment
drawings or data sheets and this information shall be supplied as a tender return.
Submission of this information does not in any way negate the supplier’s
responsibility to ensure that the specified materials are suitable for the service
required by this or any other documents pertaining to the enquiry.
4) Material certificates are to be provided for every supplied valve. Typical
certificates are to be supplied with the tender return for each valve type.
5) The Supplier is to provide full operating and maintenance and overhaul manuals
including detailed section and exploded diagrams of the valves, parts lists, typical
spares lists and pricing.
6) The Supplier is to provide drawings indicating all relevant dimensions affecting the
installation including space required to perform maintenance; this information is to
be clearly indicated for all required valve sizes.
7) The Supplier shall provide a copy of all manufacturers painting specifications
relevant to the products specified.
1.4 Corrosion protection
Mild steel units shall be shot blasted and painted on the exterior for corrosion
protection. The contractor shall supply their paint specification as a part of the tender.
Corrosion protection specification for all equipment supplied shall be as per the
supplier’s recommendation and in accordance with international standards specified for
installations in normal industrial non-coastal environments.
1.5 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the valves:
1) All valves shall be supplied complete and ready for installation including any
special fittings or fixtures required i.e. extended studs for wafer installation of long
valve.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Butterfly Valves
Revision No. A
13 July 2015 Page 6 of 7
2) The employer shall be advised of all Factory testing and allowed the opportunity to
observe Factory Acceptance Tests if required by the employer.
3) The certification documentation shall accompany the valves which shall be suitably
identified with clear serial number installation.
2 DOCUMENTATION SUPPLY
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
3) Spare parts list
4) 3D model for integration into the plant model
Documents to be supplied with the offer shall include:
1) A general arrangement.
2) Equipment design and construction information for each piece of equipment (sales
documents)
3) Approval documents (and indication of equivalency if required in section 1)
4) Maintenance and operation manuals
5) Performance data to indicate the hydraulic performance of the valve including the
pressure drop at all flow rates (may be graph, chart or equations)
6) The contractor shall complete the pump data sheet and it shall be submitted with
the tender.
7) The Quality Control plan shall be issued with tender for evaluation.
8) Corrosion resistance, corrosion protection specifications and service life
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Didier Regnaud Cell No.: 082 818 4965 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Technical Specification
Control Valves Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Technical Specification – Control Valves
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Control Valves
Revision No. A
13 July 2015 Page 3 of 10
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification – Control Valves Contents Page Contents Page ........................................................................................................................... 3
1 Technical Specification – Control Valve ........................................................................... 4
1.1 Introduction ................................................................................................................... 4
1.2 Scope of this Specification ........................................................................................... 4
1.3 General methods, standards, specifications and approach ......................................... 4
1.3.1 Equipment: ........................................................................................................... 4
1.3.2 Supply: ................................................................................................................. 5
1.4 Specific technical specifications - Protection ................................................................ 6
1.4.1 Winterisation of valves: ........................................................................................ 6
1.5 Corrosion protection ..................................................................................................... 6
1.6 Installation and Commissioning Requirements ............................................................ 6
2 documentation supply ....................................................................................................... 7
Appendix A ................................................................................................................................ 8
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Control Valves
Revision No. A
13 July 2015 Page 4 of 10
1 TECHNICAL SPECIFICATION – CONTROL VALVES
1.1 Introduction
This specification is to apply to the control valves to be employed to control the
activation of fire protection to individual areas. They shall be electronically activated,
must have a manual override and may be of deluge or pressure controlling
configuration.
The fire system is pressurized up to the control valves so that the valves may rely on
hydraulic pressure in the lines to open and close and will normally remain closed
against pressure for long periods.
There are two liquids to be considered for the specification of the control valves. The
control valves will either operate exposed to only pumped borehole water or to
borehole water and foam premix at 3 or 6 percent mixture rate. The actual mixture rate
may be up to 8 percent.
The valves shall be suitable for fire duty and shall be installed in valve bunkers which
will be open on one side but will have a roof over the valves.
1.2 Scope of this Specification
The scope of this Specification is to address the required manufacture and functional
quality and specifications.
The quantity, performance characteristics and terms of supply of the required
equipment will be specified elsewhere in the request issued to market and will
reference this specification.
1.3 General methods, standards, specifications and approach
The valve selection and supply shall adhere to the following specific requirements:
1.3.1 Equipment:
1) The valves shall be of the Inbal make or similar.
2) All valves shall be new and manufactured from all new materials unless otherwise
specified in the enquiry.
3) Control valves shall:
Have FM, UL or LPC approval for use in fire systems. Valves with alternative
approval may be submitted for consideration.
Be of ‘non-clack’ type.
Have “no moving mechanical parts”.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Control Valves
Revision No. A
13 July 2015 Page 5 of 10
Be axially symmetrical
Be suitable for mounting in the vertical position with a flow direction up
through the valve.
Have the typical wet/dry pilot control valve trim.
Be electrically activated, normally closed and have a manual activation point /
override at the valve.
a. The valves shall be energized to open
b. The manual override shall be able to activate the valve in the event of a
fail closed scenario.
Be remotely, electrically resettable.
Shall fail closed.
Shall be rated for outdoor use and shall not be adversely effected by rainfall
or exposure to sunlight. Where acceptable exceptions such as cosmetic
considerations like faded paint might result from exposure the extent of the
effect should be noted.
Shall reliably open with no outside intervention even after extended periods
of closure
4) Control Valves are to operate on an on/off principle but shall be capable of
modulating the downstream pressure. The operation shall facilitate the
maintenance of the pressure downstream of the valve at a set value whenever the
upstream pressure is greater than that set pressure. The set pressure shall be
adjustable and is to be set during commissioning.
a. There shall be provision to lock out the pressure modulation setting to
prevent erroneous adjustment.
5) All valves must be of high quality and suitable for a long service life of occasional
use. Valves should provide at least 20 years of service, subject to the supplier
specified maintenance regime.
6) Control valves shall have winter-proof coverings to ensure operation even at the
minimum temperatures listed in the data sheet.
1.3.2 Supply:
1) The supplier shall provide installation instructions detailing the labor, equipment
and any special procedures, tools, equipment or personnel required for the
installation.
2) The supplier shall include the provision of all specialist tools, equipment and
services as separate options in the tender return.
3) The material of manufacture of all parts shall be specified on the equipment
drawings or data sheets and this information shall be supplied as a tender return.
Submission of this information does not in any way negate the supplier’s
responsibility to ensure that the specified materials are suitable for the service
required by this or any other documents pertaining to the enquiry.
4) Material certificates are to be provided for every supplied valve. Typical
certificates are to be supplied with the tender return for each valve type.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Control Valves
Revision No. A
13 July 2015 Page 6 of 10
5) The supplier is to provide full operating and maintenance and overhaul manuals
including detailed section and exploded diagrams of the valves, parts lists, typical
spares lists and pricing.
6) The Supplier is to provide drawings indicating all relevant dimensions affecting the
installation including space required to perform maintenance; this information is to
be clearly indicated for all required valve sizes.
7) The Supplier shall provide a copy of all manufacturers painting specifications
relevant to the products specified.
1.4 Specific technical specifications - Protection
1.4.1 Winterisation of valves:
1) Control valves shall be insulated and heated as required to prevent freezing which
would render them inoperable
2) The temperature of restricted areas containing water is to be prevented from
dropping below 4 °C
3) Insulation is to be designed and installed in accordance with SANS 9288 and
SANS 612
1.5 Corrosion protection
Mild steel valve components shall be shot blasted and painted on the exterior for
corrosion protection. The contractor shall supply their paint specification as a part of the
tender.
Corrosion protection specification for all equipment supplied shall be as per the
supplier’s recommendation and in accordance with international standards specified for
installations in normal industrial non-coastal environments.
1.6 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the valves:
1) All valves shall be supplied complete and ready for installation including any
special fittings or fixtures required i.e. extended studs for wafer installation of long
valve.
2) The employer shall be advised of all Factory testing and allowed the opportunity to
observe Factory Acceptance Tests if required by the employer.
3) The certification documentation shall accompany the valves which shall be suitably
identified with clear serial number installation.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Control Valves
Revision No. A
13 July 2015 Page 7 of 10
2 DOCUMENTATION SUPPLY
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
3) Spare parts list
4) 3D model for integration into the plant model
Documents to be supplied with the offer shall include:
1) A general arrangement.
2) Equipment design and construction information for each piece of equipment (sales
documents)
3) Approval documents (and indication of equivalency if required in section 1)
4) Maintenance and operation manuals
5) Performance data to indicate the hydraulic performance of the valve including the
pressure drop at all flow rates (may be graph, chart or equations)
6) The contractor shall complete the pump data sheet and it shall be submitted with
the tender.
7) The Quality Control plan shall be issued with tender for evaluation.
8) Corrosion resistance, corrosion protection specifications and service life
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Control Valves
Revision No. A
13 July 2015 Page 8 of 10
Appendix A
FOAM MSDS and SPECIFICATION
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Didier Regnaud Cell No.: 082 818 4965 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Technical Specification
Fire Pump Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites - Fire Protection System:
Technical Specification - Fire Pump
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 3 of 22
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification - Fire Pump Contents Page
1 Technical Specification - Fire Pump ..................................................................................4
1.1 Introduction ....................................................................................................................4 1.2 Scope of Specifications .................................................................................................4 1.3 Definitions ......................................................................................................................5 1.4 Specification ..................................................................................................................5 1.5 Corrosion protection ................................................................................................... 19 1.6 Installation and Commissioning Requirements .......................................................... 20
2 Documentation supply .................................................................................................... 20
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 4 of 22
1 TECHNICAL SPECIFICATION - FIRE PUMP
1.1 Introduction
This specification is to apply to the duty and standby fire pumps and their control and
monitoring systems to be employed to supply the fire protection system on a Hydro-
carbon fuel handling and storage site.
This specification applies to diesel engine driven, horizontal split case centrifugal
pumps for fire duty, to be installed in an enclosed pumphouse and draw water from a
clean water reservoir.
1.2 Scope of Specifications
This Specification is to address the required quality and functionality of equipment and
systems.
This document forms part of the Works Information and is referenced by that primary
document. The quantity, performance characteristics and terms of supply of the
required equipment will be specified elsewhere in the Works Information.
This technical specification applies to the supply of the following:
Water pump for fire duty
Diesel engine driver
o The pump set including the pump and engine suitably coupled together
and securely mounted to a base plate.
o Skid is to be set level on the foundation and grouted to suppliers’
specification.
Diesel fuel tank
o One per engine
o To suit a duty period of 60 minutes plus 2 hours of operation thus a
total of 3 hours operation.
Engine controller
o Including all piping, valves, gauges and switches for the monitoring and
control of the engine.
o Engines shall be started by:
Pressure switch in discharge line
Direct start button on controller
Remote start signal from fire control panel
o Engines shall have the facility for output pressure regulation through
speed control
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 5 of 22
1.3 Definitions
Fire pump unit Consists of pump, driver and controller
Driver Means of driving the pump i.e. diesel engine or electric motor
Controller Control system for the starting, monitoring and control of the
driver.
Skid Units Fire pump unit mounted on a common, rigid base plate.
Base Plate Sub frame which the Fire pump unit is mounted to at the
factory and which is mounted to the concrete base for final
installation.
1.4 Specification
1) The pump unit and all ancillaries shall comply with the requirements of NFPA 20 as
listed below:
Each driver shall have its own dedicated controller.
The driver shall provide the required power to operate the pump at rater speed
and maximum pump load under any flow conditions.
Pumps shall be provided with a nameplate
A pressure gauge having a dial not less than 89mm in diameter shall be
connected near the discharge casting with a nominal 6mm gauge valve.
A pressure gauge having a dial not less than 89mm in diameter shall be
connected to the suction pipe near the pump with a nominal 6mm gauge valve.
o Where the minimum pump suction pressure is below 1.3 bar under any
flow condition, the suction gauge shall be a compound pressure and
vacuum gauge.
o The gauge shall have a pressure range two times the rated maximum
suction pressure of the pump
The diesel engine drivers shall have cooling water draw from the pump
discharge.
Before shipment from the factory, each pump shall be hydrostatically tested by
the manufacturer for a period of not less than 5 minutes.
o The pressure test shall not be less that one and one half times the sum
of the pumps shutoff head plus its maximum allowable suction head,
but in no case shall it be less than 250 psi (17.24 bar)
Detail design information on the skid units shall be supplied.
For all pumps, each controller shall have its own individual pressure sensing
line.
o This pressure sensing line connection for a pump shall be made
between that pumps discharge check valve and discharge control
valve.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 6 of 22
o The pressure sensing line shall be brass, rigid copper pipe Types K, L
or M, or series 30 stainless steel pipe or tube and the fittings shall be
of ½” nominal size.
o There shall be two check valves installed in the line at least 1.52m
apart with a nominal 2.4mm hole drilled in the clapper to serve as
damping.
Pumps shall furnish not less than 150 percent of rated capacity at not less than
65 percent of total rated head.
The shutoff head shall not exceed 140 percent of rated head.
A listed float-operated automatic air release valve having a nominal ½”
minimum diameter shall be provided by the pump manufacturer or an
authorized representative.
Impeller between bearing design pumps ad driver shall be mounted on a
common grouted base plate.
o The base plate shall be securely attached to a solid foundation in such
a way that proper pump and driver shaft alignment is ensured.
o The base plate with pump and driver mounted on it shall be set level
on the foundation
Pumps and drivers on separately coupled type pumps shall be aligned in
accordance with the coupling and pump manufacturers’ specifications and the
hydraulic institute standard for centrifugal, rotary and reciprocating pumps.
o Factory alignment shall not be relied upon and each pump/driver set
shall be realigned after the pump unit has been leveled on the
foundation and again after the grout has set and foundation bolts have
been tightened and finally after all piping is connected to the unit.
Engines shall have a name plate indicating the listed horsepower rating
available to drive the pump
The horsepower capability of the engine, when equipped for fire pump service,
shall have a 4-hour minimum horsepower rating of not less than 10 percent
greater than the listed horsepower on the engine nameplate
Engines shall be acceptable or horsepower ratings listed by the testing
laboratory for standard SAE conditions
A deduction of 3 percent from engine horsepower rating at standard SAE
conditions shall be made for diesel engines for each 300m of altitude above
91m.
A deduction of 1 percent from engine horsepower rating as corrected to
standard SAE conditions shall be made for diesel engines for every 5.6°C
above 25°C ambient temperature.
After all de-rating factors are considered the engine shall have a 4-hour
minimum horsepower rating equal to or greater than the brake horsepower
required to drive the pump at its rated speed under any conditions listed for
environmental conditions under pump load.
Engines shall be connected to the pump shaft by means of a flexible coupling
or flexible connecting shaft approved for this service by the pump or engine
manufacturer or listed for this service.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 7 of 22
Engines shall be provided with a governor capable of regulating engine speed
within a range of 10 percent between shutoff and maximum load condition of
the pump.
The governor shall be field adjustable and set and secured to maintain rated
pump speed at maximum pump load.
Engines that incorporate an electronic control module (ECM) to accomplish
and control the fuel injection process shall have an alternate ECM permanently
mounted and wired so the engine can produce its full rated power output in the
event of a failure of the primary ECM.
o The transition from the primary ECM to the alternate ECM shall be
accomplished automatically upon failure of the primary ECM, and a
hand/automatic switch without an off position shall be provided.
o A visual indicator shall be provided on the engine instrument panel and
a supervisory signal shall be provided to the controller when the ECM
selector switch is positioned to the alternate ECM.
o ECM’s shall be protected from transient voltage spikes and reverse dc
current.
o The contacts for each circuit shall be rated for both the minimum and
maximum current and voltage
o The total resistance of each ECM circuit through the selector switch
shall be approved by the engine manufacturer
o The selector switch shall be enclosed in a NEMA Type 2 drip proof
enclosure
o The selector switch and enclosure shall be engine mounted
o The selector switch enclosure and / or the selector switch inside shall
be isolated from engine vibration to prevent any deterioration of
contact operation.
o The ECM (or its connected sensors) shall not, for any reason,
intentionally cause a reduction in the engines ability to produce rated
power output.
o Any sensor necessary for the function of the ECM that affects the
engines ability to produce its rated power output shall have a
redundant sensor that shall operate automatically in the event of a
failure of the primary sensor.
o A common supervisory signal shall be provided to the controller in the
event of any of the following:
Fuel injector failure
Low fuel pressure
Any primary sensor failure
o In the standby mode, the engine standby battery shall be used to
power the ECM
o These engines shall not require more than 0.5 ampere from the battery
or battery charger while the engine is not running
Variable speed pressure limiting control or variable speed suction limiting
control systems used on diesel engine for fire pump drive shall be listed for fire
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 8 of 22
pump service and capable of limiting the pump output total rated head or
suction pressure by reducing pump speed.
o Variable speed control systems shall not replace the engine governor.
o In the event of a failure of the variable speeds control system, the
engine shall be fully functional with the governor.
Engines shall be provided with an overspeed shutdown device
o The overspeed device shall be arranged to shut down the engine in a
speed range of 10 to 20 percent above rated engine speed and to be
manually reset.
o A means shall be provided to indicate an overspeed trouble signal to
the automatic engine controller such that the controller cannot be rest
until the overspeed shutdown device is manually reset to normal
operating position.
o Means shall be provided to verifying overspeed switch and circuitry
shutdown function.
Engines shall be provided with a speed sensitive switch to signal engine
running and crank termination.
o Power for this signal shall be taken from a source other than the
engine generator or alternator
All engine instruments shall be placed on a panel secured to the engine or
inside an engine base plate-mounted controller.
o The engine instrument panel shall not be used as a junction box or
conduit for any ac supply
A tachometer shall be provided to indicate revolutions per minute of the engine,
including zero, at all times.
o The tachometer shall be the totalizing type, or an hour meter shall be
provided to record the total time of engine operation.
o Tachometers with digital display shall be permitted to be blank when
the engine is not running.
Engines shall be provided with an oil pressure gauge to indicate lubricating oil
pressure
Engines shall be provided with a temperature gauge to indicate engine coolant
temperature at all times.
All connecting wires for automatic controllers shall be harnessed of flexibly
enclosed, mounted on the engine, and connected in an engine junction box to
terminals numbered to correspond with numbered terminals in the controller.
o All wiring on the engine, including starting circuitry, shall be sized on a
continuous-duty basis.
o Interconnections between the automatic controller and the engine
junction box shall be made using stranded wire sized on a continuous-
duty basis.
o The dc interconnections between the automatic controller and engine
junction box and any ac power supply to the engine shall be routed in
separate conduits.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 9 of 22
Battery cables shall be sized in accordance with the engine manufacturers
recommendations considering the cable length required for the specific battery
location.
Engines shall be equipped with a reliable starting device and shall accelerate
to rated output within 20 seconds.
Electric starting shall be used and the starting device shall take current from
stored batteries.
Each engine shall be provided with two storage battery units
Lead-acid batteries shall be furnished in a dry charge condition with electrolyte
liquid in a separate container.
o Alternate battery types shall be permitted provided they meet the
engine manufacturer’s requirements.
o At 4.5°C, each battery unit shall have twice the capacity sufficient to
maintain the cranking speed recommended by the engine
manufacturer through a 3-minute attempt-to-start cycle, which is six
consecutive cycles of 15 seconds of cranking and 15 seconds of rest
o Batteries shall be sized on a calculated capacity of 72 hours of standby
power followed by three 15-second attempt-to-start cycles per battery
unit, without ac power being available for battery charging.
o Engines with only one cranking motor shall include a main battery
contactor installed between each battery and the cranking motor for
battery isolation.
Main battery contactors shall be rated for the cranking motor
current
Main battery contactors shall be capable of manual
mechanical operation including positive methods such as
spring-loaded, over-center operator to energise the starting
motor in the event of controller circuit failure
o Engines with two cranking motors shall have one cranking motor
dedicated to each battery
Each cranking motor shall meet the cranking requirements of a
single cranking motor system
To activate cranking, each cranking motor shall have an
integral solenoid relay to be operated by the pump set
controller
Each cranking motor integral solenoid relay shall be capable of
being energized from a manual operator listed and rated for
the cranking motor solenoid relay and include spring-loaded,
over-center operation to energise the starting motor in the
event of controller circuit failure.
o Nonessential loads shall not be powered from the engine starting
batteries
o Essential loads, including the engine, controller, and all pump
equipment combined, shall not exceed 0.5 ampere each for a total of
1.5 amperes, on a continuous basis.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 10 of 22
o Storage batteries shall be rack supported above the floor, secured
against displacement, and located where they will not be subject to
excessive temperature, vibration, mechanical injury, or flooding with
water.
o Current carrying parts shall not be less than 305mm above the floor
level.
o Storage batteries shall be readily available for servicing
o Storage batteries shall not be located in front of the engine-mounted
instruments and controls.
The engine cooling system shall be included as part of the engine assembly
and shall be a heat exchanger type that includes a circulating pump driven by
the engine, a heat exchanger and an engine jacket temperature regulating
device.
o A means shall be provided to maintain 49°C at the combustion
chamber
o An opening shall be provided in the circuit for filling the system,
checking coolant level, and adding make-up coolant when required.
o The coolant shall comply with the recommendation of the engine
manufacturer
o The cooling water supply for the heat exchanger system shall be from
the discharge of the pump taken off prior to the discharge check valve.
The cooling water flow required shall be set based on the
maximum ambient cooling water.
Rigid piping shall be used for the cooling water supply
The cooling water connection shall include an indicating
manual shutoff valve, an approved flushing type strainer in
addition to the one that can be part of the pressure regulator, a
pressure regulator, and automatic valve and a second
indicating manual shutoff valve or spring-loaded check valve.
The automatic valve shall permit flow of cooling water to the
engine when it is running.
Energy to operate the automatic valve shall come from
the diesel driver or its batteries and shall not come
from the building
The automatic valve shall be normally closed
A pressure gauge shall be installed in the cooling
water supply system on the engine side of the last
valve in the heat exchanger water supply and bypass
supply
o A rigid bypass line shall be installed around the heat exchanger water
supply
The connection shall include an indicating manual shutoff
valve, an approved flushing type strainer in addition to the one
that can be part of the pressure regulator, a pressure
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 11 of 22
regulator, and a second indicating manual shutoff valve or
spring-loaded check valve.
o An outlet shall be provided for the wastewater line from the heat
exchanger, and the discharge line shall not be less than two sizes
larger than the inlet line.
The outlet shall discharge to the suction reservoir and shall be
provided with a visual flow indicator and temperature indicator.
Fuel tanks shall be designed and constructed in accordance with UL 142 or
other recognized and approved engineering standards
o The fuel supply pipe connection shall be located on a side of the tank
o The engine fuel supply pipe connection shall be located on the tank so
that 5 percent of the tank volume provides a sump volume not usable
by the engine
o Each diesel engine shall have a separate fuel supply including fuel
tank and fuel line.
o A means shall be provided within the tank for low fuel level signal
initiation.
o The fuel tank shall be so located that the fuel supply connection to the
engine is no lower than the level of the engine fuel transfer pump.
o The engine manufacturers fuel pump static head pressure limits shall
not be exceeded when the level of fuel in the tank is at a maximum
Flame-resistant reinforced flexible hose listed for this service with threaded
connections shall be provided at the engine for connection to fuel system
piping.
Fuel system piping shall not be galvanized steel or copper
The fuel return line shall be installed according to the engine manufacturers’
recommendation.
o There shall be no shutoff valve in the fuel return line to the tank
A guard, pipe protection or approved double-walled pipe shall be provided for
all exposed fuel lines.
The type and grade of diesel fuel shall be as specified by the engine
manufacturer.
The required grade of fuel shall be indicated on the engine name plate.
The grade of fuel oil shall be indicated on the fuel tank by letters that are a
minimum 152mm high and in contrasting color to the tank.
Exhaust manifolds and turbochargers shall incorporate provisions to avoid
hazard to the operator or to flammable material adjacent to the engine.
Each engine shall have an independent exhaust system
o A flexible connection with a section of stainless steel, seamless or
welded corrugated (not interlocked), not less than 305mm in length
shall be made between the engine exhaust outlet and exhaust pipe.
o The exhaust pipe shall not be any smaller in diameter that the engine
exhaust outlet and shall be as short as possible
o The exhaust shall be covered with high-temperature insulation or
otherwise guarded to protect personnel from injury
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 12 of 22
o The exhaust pipe and muffler shall be suitable for the use intended and
the exhaust back pressure shall not exceed the engine manufacturers’
recommendation.
All engine controllers shall be suitable for diesel-engine driven fire pump
service.
All controllers shall be completely assembled, wired and tested by the
manufacturer before shipment form the factory
All controllers shall be marked “Diesel Engine Fire Pump Controller” and shall
show plainly the name of the manufacturer, the identifying designation, rated
operating pressure, enclosure type designation and complete electrical rating.
Controllers shall be located on the base plate.
The controller shall be protected in a suitable enclosure so that water escaping
from pumps or pump connections will not damage the controller.
Current carrying parts of the controller shall not be less than 305mm above the
floor level.
All switches required to keep the controller in the automatic position shall be
within locked enclosures having breakable glass panels.
All wiring between the controller and the diesel engine shall be stranded and
sized to carry the charging or control currents as required by the controller
manufacturer.
All wiring shall be protected against mechanical injury
Wiring elements of the controller shall be designed on a continuous-duty basis.
The diesel engine fire pump controller shall not be used as a junction box to
supply other equipment.
No under-voltage, phase loss, frequency sensitive or other devices shall be
field installed that automatically or manually prohibit electrical actuation of the
motor contactor.
Electrical supply conductors for jockey pumps shall not be connected to the
diesel engine fire pump controller.
Diesel engine fire pump controllers shall be permitted to supply essential and
necessary ac and / or dc power to operate pump room dampers and engine oil
heaters and other associated required engine equipment only when provided
with factory-equipped dedicated field terminals and overcurrent protection.
A field connection diagram shall be provided and permanently attached to the
inside of the enclosure.
The field connection terminals shall be plainly marked to correspond with the
field connection diagram furnished.
For external engine connections, the field connection terminals shall be
commonly numbered between the controller and the engine terminals.
Each operating component of the controlled shall be plainly marked with the
identification symbol that appears on the electrical schematic diagram.
o The markings shall be located so as to be visible after installation.
Complete instructions covering the operation of the controlled shall be provided
and conspicuously mounted on the controller.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 13 of 22
All visible indicators shall be plainly visible.
Visible indication shall be provided to indicate that the controller is in the
automatic position. If the visible indicator is a pilot lamp, it shall be accessible
for replacement.
Separate visible indicators and a common audible fire pump alarm capable of
being heard while the engine is running and operable in all positions of the
main switch except the off position shall be provided to immediately indicate
the following conditions:
Critically low oil pressure in the lubrication system. The
controller shall provide means for testing the position of the
pressure switch contacts without causing fire pump alarms
High engine jacket coolant temperature
Failure of engine to start automatically
Shutdown from overspeed.
o The controller shall be equipped to operate circuits for remote
indication of the conditions indicated here.
o No audible signal silencing switch or valve, other than the controller
main switch shall be permitted for this alarm.
Separate visible indicators and a common audible signal capable of being
heard while the engine is running and operable in all positions of the main
switch except the off position shall be provided to immediately indicate the
following conditions:
Battery failure or missing battery. Each controller shall be
provided with a separate visible indicator for each battery.
Battery charger failure. Each controller shall be provided with a
separate visible indicator for battery charger failure and shall
not require the audible signal for battery charger failure.
System overpressure, for engines equipped with variable
speed pressure limiting controls, to actuate at 115% of set
pressure.
ECM selector switch in alternate ECM position (for engines
with ECM control only)
Fuel Injection Malfunction (for engines with ECM only)
Low fuel level. Signal at two thirds tank capacity
Low engine temperature
o The controller shall be equipped to operate circuits for remote
indication of the conditions indicated here.
o No audible signal silencing switch or valve, other than the controller
main switch shall be permitted for these alarms except for the alternate
ECM alarm and the low fuel level alarm.
o The controller shall automatically return to the non-silenced state when
the alarms have been cleared
o The circuit shall be arranged so that the audible signal will be actuated
if the silencing switch or valve is in the silent position when the
supervised conditions are normal.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 14 of 22
A listed pressure recording device shall be installed to sense and record the
pressure in each fire pump controller pressure-sensing line at the input to the
controller.
o The recorder shall be capable of operating for at least 7 days without
being reset or rewound.
o The pressure sensing element of the recorder shall be capable of
withstanding a momentary surge pressure of at least 27.6 bar without
losing its accuracy.
o The pressure recording device shall be spring would mechanically or
driven by electrical means.
o The pressure recording device shall not be solely dependent upon
alternating current electric power as its primary power source
Upon loss of ac electric power the electric-driven recorder shall
be capable of at least 24 hours operation
Two means for recharging storage batteries shall be provided
o One method shall be the generator or alternator furnished with the
engine
o The other method shall be an automatically controlled charger taking
power from an ac source.
The requirements for battery chargers shall be as follows:
o Chargers shall be specifically listed for fire pump service and be part of
the diesel fire pump controller
o The rectifier shall be a semiconductor type
o The charger for a lead-acid battery shall be a type that automatically
reduces the charging rate to less than 500 mA when the battery
reaches a full charge condition.
o The battery charger at its rated voltage shall be capable of deliverying
energy into a fully discharged battery in such a manner that it will not
damage the battery.
o The battery charger shall restore to the battery 100 percent of the
battery’s reserve capacity or ampere-hour rating within 24 hours.
o The charger shall be marked with the reserve capacity or ampere-hour
rating of the largest capacity battery that it can recharge without
causing damage to the battery.
o An ammeter with an accuracy of ±5 percent of the normal charging
rate shall be furnished to indicate the operation of the charger.
o The charger shall be designed such that it will not be damaged or blow
fuses during the cranking cycle of the engine when operated by an
automatic or manual controller.
o The charger shall automatically charge at the maximum rate whenever
required by the state of charge of the battery.
o The battery charger shall be arranged to indicate loss of current output
on the load side of the direct current overcurrent protective device
where not connected through a control panel.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 15 of 22
o The charger (s) shall remain in float mode or switch from equalize to
float mode while the batteries are being charged by the engine driven
alternator or generator.
Automatic controller
o An automatic controller shall be operable also as a non-automatic
controller.
o The controllers primary source of power shall not be ac electric power
o The controller shall have a pressure-actuated switch having adjustable
high- and low-calibrated set-points as part of the controller.
o There shall be no pressure snubber or restrictive orifice employed
within the pressure switch
o This switch shall be responsive to water pressure in the fire protection
system
o The pressure-sensing element of the switch shall be capable of a
momentary surge pressure of 27.6 bar without losing its accuracy.
o Suitable provision shall be made for relieving pressure to the pressure-
actuated switch to allow testing of the operation of the controller and
the pumping unit
o There shall be no shutoff valve in the pressure sensing line
o Pressure switch actuation at the low adjustment setting shall initiate
the pump starting sequence if the pump is not already in operation.
Remote manual pump starting shall be provided from the fire control panels
however such locations shall not be operable to stop the engine. The engines
may only be stopped from the fire pump house.
The controller for each unit of multiple pump units shall incorporate a
sequential timing device to prevent any one driver from starting simultaneously
with any other driver.
o If water requirements call for more than one pumping unit to operate,
the units shall start at intervals of 5 to 10 seconds.
With pumping units operating singly or in parallel, the control conductors
entering or leaving the fire pump controller and extending outside the fire pump
room shall be so arranged as to prevent failure to start due to fault
o Breakage, disconnecting, shorting of the wires or loss of power to
these circuits shall be permitted to cause continuous running of the fire
pump but shall not prevent the controller(s) from starting the fire
pump(s) due to causes other than these external circuits.
This shall be applied equally to control conductors between the
control unit and the Fire Control panel other than the power
supply which is dealt with separately.
o All control conductors within the fire pump that are not fault tolerant
shall be protected against mechanical injury
A test button shall be furnished which will actuate a solenoid valve drain on the
pressure control line in order to start the pump for testing through the pressure
sensing automatic start system.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 16 of 22
o Performance of the regular test shall be recorded as a pressure drop
indication on the pressure recorder.
There shall be a manually operated switch or valve on the control panel for
manual control of the fire pump.
o The switch or valve shall be so arranged that operation of the engine,
when manually started, cannot be affected by the pressure-actuated
switch.
o Failure of any automatic circuits shall not affect the manual operation.
Starting equipment arrangement.
o The starting current shall be furnished by first one battery and then the
other on successive operations of the starter.
Battery changeover shall be made automatically, except for
manual start.
o In the event that the engine does not start after completion of its
attempt-to-start cycle, the controller shall stop all further cranking and
operate a visible indicator ad audible fire pump alarm on the controller.
o In this even the controller should also signal for the backup fire pump
to start.
o The attempt-to-stat cycle shall be fixed and shall consist of six crank
periods of approximately 15-second duration separated by five rest
periods of approximately 15-seconds duration.
o In the event that one battery is inoperative or missing the control shall
lock in on the remaining battery unit during the cranking sequence.
Manual shutdown shall be accomplished by either of the following:
o Operation of the main switch or stop valve inside the controller
o Operation of a stop button or stop valve on the outside of the controller
enclosure as follows
The stop button or stop valve shall cause engine shutdown
through the automatic circuits only if all starting causes have
been returned to normal
The controller shall then return to the full automatic position.
Acceptance Testing and performance.
Hydrostatic tests
Suction and discharge piping shall be hydrostatically tested at not less than 3.4
bar more than the maximum pressure to be maintained in the system.
o This pressure shall be maintained for 2 hours.
The installation contractor shall furnish a certificate for flushing and hydrostatic
test prior to the start of the fire pump field acceptance test.
Field Acceptance tests
The pump manufacturer, engine manufacturer and the controller manufacturer
or their factory authorized representatives shall be present for field acceptance
testing.
All authorities having jurisdiction shall be notified as to the time and place of
the field acceptance test.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 17 of 22
All electrical wiring to the fire pump motors, normal power supply, alternate
power supply and jockey pump shall be completed and checked by the
electrical contractor prior to the initial startup and acceptance test.
A copy of the manufacturers certified pump test characteristic curve shall be
available for comparison of the results of the field acceptance test.
The fire pump as installed shall equal the performance as indicated on the
manufacturers certified shop test characteristic curve within the accuracy limits
of the test equipment.
Field acceptance test procedures
Calibrated test equipment shall be provided to determine net pump pressures,
and the speed.
Calibrated test gauges shall be used and bear a label with the latest date of
calibration. Calibration of test gauges shall be maintained at an accuracy level
of ± 1 percent.
The fire pump shall perform at minimum, rated and peak loads without
objectionable overheating of any component.
Vibrations of the fire pump assembly shall not be of a magnitude to pose
potential damage to any fire pump component
The minimum, rated and peak loads of the fire pumps shall be determined by
controlling the quantity of water discharged through approved test devices.
The acceptance test shall include a flow test of all duty pumps operating
simultaneously.
Pumps with variable speed pressure limiting control shall be tested at
minimum, rated and peak loads, with both the variable speed pressure limiting
control operational and the dire pump operating at rated speed.
For testing the quantity of water discharging from the fire pump assembly shall
be determined and stabilized and immediately thereafter the operating
conditions of the fire pump and driver shall be measured.
Engine-driven units shall show no sign of overload or stress.
The governor of engine drives shall be set that the time of the test to properly
regulate the engine speed at the rated pump speed.
A load start test shall be performed: the fire pump unit shall be started and
brought up to rated speed without interruption under the conditions of a
discharge equal to peak load.
Controller Acceptance test
Fire pump controllers shall be tested in accordance with the manufacturers
recommended test procedure
As a minimum no fewer than six automatic and six manual operations shall be
performed during the acceptance test
The automatic operation sequence of the controller shall start the pump from
all provided starting features.
This sequence shall include pressure switches or remote starting signals
Tests of engine-driven controllers shall be divided between both sets of
batteries.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 18 of 22
The selection, size, and setting of all overcurrent protective deveices, including
fire pump controller circuit breaker, shall be confirmed to be in accordance with
NFPA 20
Both local and remote signals and fire pump alarm conditions shall be
simulated to demonstrate satisfactory operation.
The fire pump shall be in operation for not less than 1 hour total time during all
the controller tests.
For engines with electronic fuel management (ECM) control systems, a
function test of both the primary and the alternate ECM shall be conducted.
Manuals, special tools and spare parts
A minimum of one set of instruction manuals for all major components of the
fire pump system shall be supplied by the manufacturer of each major
component.
o Manuals shall contain the following:
A detailed explanation of the operation of the component
Instructions for routine maintenance
Detailed instructions concerning repairs
Parts list and parts identification
Schematic electrical drawings of controller, transfer switch and
fire pump control panel.
Any special tools and testing devices required for routine maintenance shall be
available for inspection by the authority having jurisdiction at the time of the
field acceptance test and shall be supplied to the employer.
2) The Contractor shall obtain SABS certification that the supplied fire pump units are
suitable for use in fire systems; this shall be in the form of an ASIB fire pump test
and certification. This shall not be required if the pump units including the pump,
engine controller and all relevant components are list by FM (Factory Mutual) or UL
(Underwriters Laboratories) for Fire Duty as required by NFPA 20.
3) The fire pump shall be fitted with an automatic cooling water, crankcase or block
heater system (or combination of these) in order to maintain the engine in a
condition to allow starting and immediate operation at all listed ambient
temperatures. Should any other systems including but not limited to fuel circulation
and heating, and piping insulation be required to facilitate cold starting and
operation this shall also be provided.
a. Should room heating be required as sufficient engine heating cannot be
achieved this shall be clearly noted in the tender return and the heating
requirements stated to allow the design of suitable room heating.
4) Pump impellors must not be more than 90 percent of full size.
5) The base plate is to incorporate lifting lugs for handling of the pump unit.
6) The pump unit base plate shall be finished so as to suit final installation and should
provide a service life at least equivalent to the pump set.
7) The pump unit base plate shall have provision for fastening to the base.
8) Lifting shall be possible from a crawl beam above the pump set and should a
spreader device be required to allow this, this shall be included in the supply (One
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 19 of 22
only per site). The distance from the hook to bottom of the pump set is a maximum
of 3500mm
9) The supplier shall advise on the required mounting and grouting configuration.
10) The supplier shall provide all flanges and couplings required to mate to all coupling
points on the pump and engine including but not limited to:
a. Pump inlet and outlet flanges
b. Cooling water return takeoff connection
c. Diesel fuel supply and return pipe termination connections.
11) A full Factory Acceptance Test (FAT) shall be completed for the Pump, Engine and
System and these shall be witnessed by the Employer.
Diesel Tank
12) The fuel tank size and design shall be approved by the Employer before
construction and shall suit the installation into the planned space adjacent to the
pumphouse. The fuel tanks will be located in a bunded area outside the
pumphouse and covered by a roof with wire mesh walls and doors for access
control.
13) Diesel tank capacity shall include allowance for settlement and sludge as well as
freeboard as required.
14) Diesel tanks are to have a washout drain and a low point constructed into the tank
base to facilitate draining and cleaning.
15) Diesel tanks shall include a sight glass type level gauge of type approved by the
Employer and if susceptible to damage it must be possible to isolate the gauge for
repair.
16) Diesel tanks shall be designed and constructed in accordance with SANS 10131
Annexure A as a minimum.
17) Diesel tanks shall be fitted with an earthing point, in order for others to complete
the earthing requirements.
18) Diesel tanks shall be fitted with a name plate depicting the details of the tank, the
code of manufacture and minimum requirements according to the code. The
manufacturer and date of manufacture must also be indicated
19) Diesel tanks shall be fully corrosion protected with a suitable painting system
applied to both the interior and exterior surfaces.
20) The Diesel fuel tanks shall be insulated and shall be fitted with diesel tank heaters
to maintain the temperature at least 5.6°C above the pour point and cloud point of
the fuel utilized.
21) The fuel lines shall be insulated to maintain the temperature at least 5.6°C above
the pour point and cloud point of the fuel utilized.
1.5 Corrosion protection
Cast Iron pump units shall be shot blasted and painted on the exterior for corrosion
protection. The Contractor shall supply their paint specification as a part of the tender.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 20 of 22
Corrosion protection specification for all equipment supplied shall be as per the
supplier’s recommendation and in accordance with international standards specified for
installations in normal industrial non-coastal environments.
1.6 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the pumps:
1) All pumps shall be aligned in the factory/workshop before delivery to site.
2) The Employer shall be allowed to observe all final factory testing and shall be
advised of testing in advance in order that the Employer may arrange travel and
logistics.
3) The certification documentation shall accompany the pumps and engines which
shall be suitably identified with clear serial number affixed to the components.
4) The tenderer shall complete the connection of the fuel tanks to the engines.
5) The tenderer shall install the auto-start arrangement for the fire pumps and jockey
pump.
6) The Contractor shall complete formal pre-commissioning, cold-commissioning and
hot-commissioning tests. These tests shall be comprehensive and fully confirm the
quality of the installation and the operation of the system. The Employer or
Employers representative must sign off the document after each stage and shall be
afforded the opportunity to observe the commissioning. The Contractor may not
commence the second or third stage of commissioning without the previous stage
having been signed off by the Employer or Employers representative.
The Contractor shall note that many parties shall be involved in the construction in this
area.
2 DOCUMENTATION SUPPLY
Documents to be supplied with the offer shall include:
1) A general arrangement of the pump unit.
2) Approval documents
3) Maintenance and operation manuals
4) Pump curves
5) Completed the pump data sheet.
6) Pump body and component Material of Construction
7) The Quality Control Plan shall be issued with tender for evaluation.
8) Corrosion resistance, corrosion protection specifications and service life
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
13 July 2015 Page 21 of 22
3) Pump requirements for spill back line sizes / flow rate
4) Diesel engine cooling line flow rate
5) Diesel engine fuel consumption
6) Engine fuel pump capacity to assess fuel tank location
7) Required fuel tank size
8) Diesel engine heat output – to determine room cooling requirements
9) Diesel engine air intake requirements – to determine room ventilation requirements
10) Spare parts lists for all equipment.
11) 3D model for integration into the plant AutoCAD model.
12) Full Material of Construction documentation for the pumps
13) Quality Control and Quality Assurance documentation for all equipment.
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Didier Regnaud Tell No.: 031 581 1512 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Technical Specification
Fixed Monitor Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Technical Specification – Fixed monitor
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Fixed Monitor
Revision No. A
13 July 2015 Page 3 of 8
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification – Fixed Monitor Contents Page
1 TECHNICAL SPECIFICATION – FIXED MONITOR .......................................................................... 4
1.1 INTRODUCTION ............................................................................................................................... 4 1.2 SCOPE OF SPECIFICATIONS ................................................................................................................ 4 1.3 GENERAL METHODS, STANDARDS, SPECIFICATIONS AND APPROACH ........................................................... 4 1.4 CORROSION PROTECTION .................................................................................................................. 5 1.5 INSTALLATION AND COMMISSIONING REQUIREMENTS ............................................................................ 5
2 DOCUMENTATION SUPPLY ....................................................................................................... 6
APPENDIX A ....................................................................................................................................... 7
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Fixed Monitor
Revision No. A
13 July 2015 Page 4 of 8
1 TECHNICAL SPECIFICATION – FIXED MONITOR
1.1 Introduction
This specification is to apply to fixed foam canon installations used for the discharge of
aerated low expansion foam on a trajectory from a remote position onto a defined area
for the suppression of hydro-carbon fires.
This specification applies to those monitor systems used to protect piping manifolds
and similar process equipment not fuel storage tank areas.
1.2 Scope of Specifications
The scope of this Specification is to address the required manufacture and functional
quality and specifications.
The quantity, performance characteristics and terms of supply of the required
equipment will be specified elsewhere in the request issued to market and will
reference this specification.
1.3 General methods, standards, specifications and approach
The fixed monitor system addressed by this specification is considered to comprise of a
monitor and discharge system; the discharge system may comprise a nozzle and tube
or necessary configurations. The ruling consideration in determining the extents of the
system will be that the system shall be complete to allow the assembly of all
components and shall require only fitment to a standpipe and supply of liquid flow and
pressure to operate.
The Fixed Monitor system and components shall adhere to the following specific
requirements:
1) The Monitors and nozzles shall all be of the same make and these shall be Akron
or similar.
2) Each component shall be appropriately sized for the flow and discharge
requirements specified in the relevant Data Sheets as referenced in the Tender.
3) The full technical information of each component specified shall be made available
to allow verification of the flow rates, pressure requirements, pressure drops and
discharge distances at the required flow rate. This shall not prejudice the
requirement for the tenderer to specify correctly sized equipment.
4) The monitor shall be FM approved; equipment with equivalent approval through
another body (such as UL or LPC) may be acceptable however the testing
standard or equivalency shall be documented in the submission.
5) The equipment shall be suitable for duty with regular exposure to Alcoseal 3-6
Premix in 3 or 6%.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Fixed Monitor
Revision No. A
13 July 2015 Page 5 of 8
6) The nozzle shall be of the “blabber mouth” type unless the specific flow rate or
discharge range requirement can’t be catered for with such a nozzle in which case
an alternative can be specified for specific instances; such specification shall
however, be subject to approval by the employer.
7) The monitor shall allow full 360° adjustability about the vertical axis
8) The monitor shall allow adjustment from 40° below the horizontal plane to 80°
above the horizontal plane.
9) The equipment shall be suitable for use in all ambient conditions. If operability may
be effected by freezing of water within the system the equipment shall be insulated
or otherwise protected against inoperability cause by low temperatures.
10) The monitor shall be designed such as to reduce as far as possible the hydraulic
losses through it.
11) The monitor adjustment shall be manually lockable, easily unlockable and
adjustable by hand. The full operation should be possible by any reasonably
healthy adult.
12) The equipment shall generate and discharge the foam at a rate suitable for the
extinguishment of hydrocarbon fires when 3% premix of Alcoseal 3-6 is used.
13) The equipment shall generate and discharge the foam at a rate suitable for the
extinguishment of polar solvents and hydrocarbon fires when 6% premix of
Alcoseal 3-6 is used.
14) All components shall comply with NFPA requirements.
1.4 Corrosion protection
All equipment shall be suitable for extended outdoor installation with no resultant loss
of reliability.
Service requirements and typical service life shall be supplied or stated for all
components specified.
Where equipment is painted or otherwise coated for cosmetic or corrosion protection
reasons the protection used shall be specified and the painting or coating specifications
issued for each component.
Corrosion protection specification for all equipment supplied shall be as per the
supplier’s recommendation and in accordance with international standards specified for
installations in normal industrial non-coastal environments.
1.5 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the oscillating monitor system:
1) All equipment shall be delivered assembled and complete. For clarification, the
nozzles does not need to be mounted to the monitor but all equipment must be in a
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Fixed Monitor
Revision No. A
13 July 2015 Page 6 of 8
condition so that the monitor can be mounted directly to the standpipe and the
nozzle mounted to the monitor only, after which the system shall be functional.
2) All fittings, fasteners and seals necessary for the installation of the components of
the system shall be included in the supply. If non-standard gaskets or fasteners
are required to fasten the oscillating flange to the standpipe these shall also be
supplied.
3) The Equipment shall be supplied with full MOC certification.
4) The certification documentation shall accompany the equipment which shall be
suitably identified with clearly marked serial number.
5) The supply shall include full Quality Control and Quality Assurance documentation.
6) The tenderer shall advise of all tests or checks to be completed in the
commissioning of the systems.
2 DOCUMENTATION SUPPLY
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
3) Spare parts list
4) 3D model for integration into the plant model
Documents to be supplied with the offer shall include:
1) A general arrangement.
2) Equipment design and construction information for each piece of equipment (sales
documents)
3) Approval documents (and indication of equivalency if required in section 1)
4) Technical data for each piece of equipment including:
a. Range of operability
i. Flow rate
ii. Pressure
b. Discharge Characteristics
i. Discharge pattern
ii. Pressure drop through equipment
iii. Discharge range, at pressure, flow and elevation (may be specific
to requirements or general but clear information). This must either
indicate requirements are achievable with the parameters advised
in the data sheets or the pressure and flow requirements to meet
the discharge requirements.
c. Corrosion resistance, corrosion protection specifications and service life
5) Maintenance and operation manuals
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. 01
13 July 2015 Page 7 of 8
Appendix A
Alcoseal 3-6
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Edward Standen Cell No.: 072 130 4968 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Technical Specification
Foam Circulation Pump Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Technical Specification - Foam Circulation Pump
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Foam Circulation Pump
Revision No. A
13 July 2015 Page 3 of 8
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification – Foam Circulation Pump Contents Page 1 Technical Specification – Foam Circulation Pump ........................................................... 4
1.1 Introduction ................................................................................................................... 4
1.2 Scope of Specifications ................................................................................................ 4
1.3 General methods, standards, specifications and approach ......................................... 4
1.4 Corrosion protection ..................................................................................................... 5
1.5 Installation and Commissioning Requirements ............................................................ 6
2 Documentation supply ...................................................................................................... 6
Appendix A ................................................................................................................................ 7
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Foam Circulation Pump
Revision No. A
13 July 2015 Page 4 of 8
1 TECHNICAL SPECIFICATION – FOAM CIRCULATION PUMP
1.1 Introduction
This specification is to apply to the foam concentrate circulation and loading pump to
be employed to pump foam concentrate from shipping containers into the storage tanks
as well as to circulate the stored concentrate.
This specification applies to electrically driven pumps for use pumping Alcoseal 3-6
foam concentrate for occasional duty and to be installed in an enclosed pumphouse.
1.2 Scope of Specifications
The scope of this Specification is to address the required manufacture and functional
quality and specifications.
The quantity, performance characteristics and terms of supply of the required
equipment will be specified elsewhere in the request issued to market and will
reference this specification.
1.3 General methods, standards, specifications and approach
The pump systems and ancillary equipment shall adhere to the following specific
requirements:
1) All pumps to be supplied c/w base frames, electrical motor and couplings. Where
the motor is coupled directly to the pump and the pump may be mounted directly to
foundations a separate base frame shall not be required.
2) All pumps to be supplied with coupling guards compliant with OSH Act.
3) Gear pumps of the Desmi, Rotan series have been specified.
4) Diaphragm or Spate pumps are suitable alternatives but may only be used with
approval.
5) Pumps shall be supplied with electric drives.
6) The liquid being pumped is a denser than water, non-Newtonian fluid. The
available specifications can be found in Appendix A.
7) The liquid being handled has aggressive corrosion properties towards some
materials and this should be considered in the specification of the pump. The
pumps shall be of stainless steel construction and have suitable seals, bearings
etc. The pump shall not be subject to excessive corrosion or degradation due to
the properties of the liquid. The available specifications can be found in Appendix
A.
8) All pumps to be supplied with pump design flow rate 20% higher than required flow.
9) All pumps to be supplied with all pump internals, seals and ancillary equipment
required for the pumps sealing (i.e. water pot for mechanical seals).
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Foam Circulation Pump
Revision No. A
13 July 2015 Page 5 of 8
10) Each pump base will be located on top of a concrete plinth fixed via chemical
anchor bolts.
11) The head at zero delivery shall be at least 1.2 times the operating head, where
applicable.
12) Shaft, bearings and housing to be manufactured of corrosion resistant materials
and resistant to the liquid being conveyed.
13) Electrical motors shall be IP55 380V 3 PH 50Hz. Pumps shall be located within a
pump house.
14) The motor brand offered by the tenderer shall be advised with the tender
submission.
15) The pump system design temperature shall be min. -10 °C and max. +65°C. If this
condition isn’t met the range of operation must be stated.
16) Matching flanges shall be supplied for all non-commonly available interfacing
flanges, i.e. flanges joined to the suction and supply flanges of foreign pumps,
valves and other equipment.
17) All bolts, nuts and washers shall be GRADE 8.8 cold galvanized electroplated or
better.
18) The pump unit shall be fitted with an earthing point, in order for others to complete
the earthing requirements.
19) Pumps shall be fitted with a name plate depicting the details of the pump codes of
manufacture and minimum requirements according to the code.
20) The following shall be supplied with the tender as a minimum:
a. Pump unit general arrangement drawing
b. Pump curves
c. Pump datasheets
d. Operating and Maintenance Manuals
e. Spare Parts list
f. Service life (Both hours of operation and life span in years)
21) The tenderer shall provide a QCP for each fabricated / supplied item as a
minimum. The tenderer shall supply a sample QCP with the tender for evaluation.
22) The supplier shall advise on the required mounting and grouting configuration.
23) The pump set is to be supplied with explosion proof coupling guards.
1.4 Corrosion protection
Mild steel pump components shall be shot blasted and painted on the exterior for
corrosion protection.
Corrosion protection specification for all equipment supplied shall be as per the
supplier’s recommendation and in accordance with international standards specified for
installations in normal industrial non-coastal environments.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Foam Circulation Pump
Revision No. A
13 July 2015 Page 6 of 8
1.5 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the pumps:
1) All pumps shall be aligned in the factory/workshop before delivery to site.
2) During factory testing the employer shall be hosted to observe the final testing.
3) The employer shall be advised of all Factory testing and allowed the opportunity to
observe Factory Acceptance Tests if required by the employer.
4) All certification documentation shall accompany the pumps and engines which shall
be suitably identified with clear serial number installation.
2 DOCUMENTATION SUPPLY
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
3) Spare parts list
4) 3D model for integration into the plant model
Documents to be supplied with the offer shall include:
1) A general arrangement.
2) Equipment design and construction information for each piece of equipment (sales
documents)
3) Approval documents (and indication of equivalency if required in section 1)
4) Maintenance and operation manuals
5) Pump curves of specified equipment
6) The contractor shall complete the pump data sheet and it shall be submitted with
the tender.
7) The Quality Control plan shall be issued with tender for evaluation.
8) Corrosion resistance, corrosion protection specifications and service life
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Foam Circulation Pump
Revision No. 01
13 July 2015 Page 7 of 8
Appendix A
FOAM CONCENTRATE INFORMATION
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Edward Standen Cell No.: 072 130 4968 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Technical Specification
Foam Dosing Pump Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Technical Specification - Foam Dosing Pump
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Foam Dosing Pump
Revision No. A
13 July 2015 Page 3 of 9
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification – Foam Dosing Pump Contents Page 1 Technical Specification – Foam Dosing Pump ................................................................. 4
1.1 Introduction ................................................................................................................... 4
1.2 Scope of Specifications ................................................................................................ 4
1.3 General methods, standards, specifications and approach ......................................... 4
1.4 Corrosion protection ..................................................................................................... 6
1.5 Installation and Commissioning Requirements ............................................................ 6
2 Documentation supply ...................................................................................................... 6
Appendix A ................................................................................................................................ 8
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Foam Dosing Pump
Revision No. A
13 July 2015 Page 4 of 9
1 TECHNICAL SPECIFICATION – FOAM DOSING PUMP
1.1 Introduction
This specification is to apply to the foam concentrate dosing system to be employed to
inject a proportional flow of foam concentrate into the water stream of the foam
application systems of a fire protection system when the system is in operation.
The foam dosing system is to induce foam concentrate into the water stream to certain
equipment at a nominal rate of 3% so that the resultant mixture is 3% concentrate and
97% water.
The system shall be suitable for fire duty and shall be installed in a pumphouse and will
draw foam concentrate from dedicated foam concentrate storage tanks within the
pumphouse.
The layout allows for the dosing pump to be isolated from the supply and discharge
lines for maintenance.
The water / premix discharge system shall be permanently pressurized by a jockey
pump, through the dosing system and up to the control valves. This shall pressurize
the downstream side of the dosing system and there shall be sufficient provision in the
specified dosing system to prevent any backflow of water into the foam concentrate
lines.
1.2 Scope of Specifications
The scope of this Specification is to address the required manufacture and functional
quality and specifications.
The quantity, performance characteristics and terms of supply of the required
equipment will be specified elsewhere in the request issued to market and will
reference this specification.
1.3 General methods, standards, specifications and approach
The pump systems and ancillary equipment shall adhere to the following specific
requirements:
1) The equipment shall be FM approved to class 5135.
2) The foam dosing system shall be suitable for accurately dosing the specified foam
concentrate into a pressurized water flow at 3%. The dosing range and accuracy
must comply with the requirements of NFPA.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Foam Dosing Pump
Revision No. A
13 July 2015 Page 5 of 9
3) The dosing system must be capable of dosing at a rate of 6% as an option; if the
system doesn’t offer this option as standard it must be expandable to offer this
switchable option. The system should ideally be FM approved for 6% however
systems that have FM approval for 3% but not 6% may be considered. (The
current design doesn’t require 6% dosing however the client has specified this
requirement because of the potential future need for 6% foam mixture)
4) The foam dosing system must not require outside fuel or power and may be driven
through a water turbine system driven by the water flow.
5) The dosing system must operate to automatically induce the required rate of foam
concentrate over a range of flow rates from less than 10% to 100% of the nominal
flow rate.
6) The equipment must have the provision to either inject the concentrate or return
this to the storage tank.
7) The equipment must be fitted with a flow meter to determine the flow rate of
concentrate through the return line and should be configurable to operate at the
correct back pressure in order to accurately determine the dosing rate. This may
require two pressure relief valves, one as a safety for normal operation and the
other to be set at a lower pressure to simulate the operating back pressure when
the concentrate return system is in operation.
8) The equipment should have the provision to measure the water flow rate through
the water motor.
9) The equipment is to be securely mounted on a base frame which will allow
installation directly to a concrete plinth.
10) The equipment shall have provision for lifting and handling with a crawl beam.
11) The supplier shall advise on the required mounting and grouting configuration.
12) The pump system design temperature shall be min. -10 °C and max. +65°C. If this
condition isn’t met the range of operation must be stated.
13) The supplier shall provide assurance of availability of flanges and couplings
required to mate to all coupling points.
The supplier shall provide pricing for all required flanges or couplings.
The supplier shall, upon the request of the Purchaser, at any point prior to the
commissioning of the installation, supply (at a fair price) any couplings
required by the Purchaser to complete the installation.
Flanges shall be available in both 150 and 300 class.
ANSI B16.5 flanges are preferred.
14) Pumps shall be fitted with a name plate depicting the details of the pump, codes of
manufacture and approvals.
15) The following shall be supplied with the tender as a minimum:
a. Pump unit general arrangement drawing
b. Performance data including:
i. Dosing rate curve across operating range
ii. Hydraulic loss information (Either equation and parameters, chart,
or graph)
c. Pump datasheets
d. Operating and Maintenance Manuals
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Foam Dosing Pump
Revision No. A
13 July 2015 Page 6 of 9
e. Spare Parts List
16) The tenderer shall provide a QCP for each fabricated / supplied item as a
minimum. The tenderer shall supply a sample QCP with the tender for evaluation
17) The equipment shall comply with the requirements of the OSH Act.
1.4 Corrosion protection
As per manufacturers specification and suitable for the installation. All piping and
pipework ancillary equipment should be stainless steel.
1.5 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the pumps:
1) All equipment shall be aligned in the factory/workshop before delivery to site.
2) Factory testing shall be conducted with the Employer. Employers travel costs and
arrangements will be for the employers account.
3) The Equipment shall be supplied with full MOC certification.
4) The certification documentation shall accompany the equipment which shall be
suitably identified with clearly marked serial number.
5) The supply shall include full Quality Control and Quality Assurance documentation.
6) The tenderer shall complete formal pre-commissioning, cold-commissioning and
hot-commissioning tests of the installation. These tests shall be comprehensive
and fully confirm the quality of the installation and the operation of the system. The
project manager must sign off the document after each stage and may also wish to
observe the commissioning. The tenderer may not commence the second or third
stage of commissioning without the previous stage having been signed off by the
project manager or alternative authorization from the project manager.
The tenderer shall note that many parties shall be involved in the construction in this
area and the contractor shall be required to interface with management, who will make
every effort to provide access when required.
2 DOCUMENTATION SUPPLY
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
3) Spare parts list
4) 3D model for integration into the plant model
Documents to be supplied with the offer shall include:
1) A general arrangement.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Foam Dosing Pump
Revision No. A
13 July 2015 Page 7 of 9
2) Equipment design and construction information for each piece of equipment (sales
documents)
3) Approval documents (and indication of equivalency if required in section 1)
4) Maintenance and operation manuals
5) Performance data including:
a. Dosing rate curve across operating range
b. Hydraulic loss information (Either equation and parameters, chart, or
graph)
6) Pump datasheets
7) The contractor shall complete the pump data sheet and it shall be submitted with
the tender.
8) The Quality Control plan shall be issued with tender for evaluation.
9) Corrosion resistance, corrosion protection specifications and service life
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. 01
13 July 2015 Page 8 of 9
Appendix A
FOAM CONCENTRATE INFORMATION
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Edward Standen Cell No.: 072 130 4968 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Technical Specification
Foam Sprayer Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites Fire Protection System:
Technical Specification – Foam Sprayer
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Foam Sprayer
Revision No. A
13 July 2015 Page 3 of 8
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification – Foam Sprayer Contents Page 1 Technical Specification – Foam Sprayer .......................................................................... 4
1.1 Introduction ................................................................................................................... 4 1.2 Scope of Specifications ................................................................................................ 4 1.3 General methods, standards, specifications and approach ......................................... 4 1.4 Corrosion protection ..................................................................................................... 5 1.5 Installation and Commissioning Requirements ............................................................ 5
2 documentation supply ....................................................................................................... 5 Appendix A ................................................................................................................................ 7
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Foam Sprayer
Revision No. A
13 July 2015 Page 4 of 8
1 TECHNICAL SPECIFICATION – FOAM SPRAYER
1.1 Introduction
This specification is to apply to the foam sprayers to be installed to discharge foam
over piping manifolds, electric motor driven pumps and fuel transport tankers and
loading/unloading facilities for the suppression of fires. There are applications requiring
high level nozzles which will provide an even distribution of foam over a large area
through multiple nozzles and other applications requiring low level directional nozzles
to spray foam towards and under equipment.
1.2 Scope of Specifications
The scope of this Specification is to address the required manufacture and functional
quality and specifications.
The quantity, performance characteristics and terms of supply of the required
equipment will be specified elsewhere in the request issued to market and will
reference this specification.
1.3 General methods, standards, specifications and approach
The nozzles addressed by this specification individual items to be used with Alcoseal 3-
6 foam premix to generate and discharge foam.
The Tank Pourer system and ancillary equipment shall adhere to the following specific
requirements:
1) The foam sprayers shall be of the Tyco make or similar.
2) Each component shall be appropriately sized for the flow and discharge
requirements specified in the relevant Data Sheets as referenced in the Tender.
3) The nozzles shall be of metallic construction; either brass or Stainless steel.
4) The nozzles shall be approved or listed by at least one of the following agencies for
the appropriate application:
a. SABS – South African Bureau of Standards
b. UL – Underwriters Laboratories (USA)
c. FM – Factory Mutual (USA)
d. LPC – Loss Prevention Council (Great Britain)
5) The equipment shall be suitable for duty with regular exposure to Alcoseal 3-6
Premix in 3 or 6%.
6) Corrosion protection shall be suitable for extended service life as per section 1.4
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Foam Sprayer
Revision No. A
13 July 2015 Page 5 of 8
1.4 Corrosion protection
All equipment shall be suitable for extended outdoor installation with no resultant loss
of reliability.
Service requirements and typical service life shall be supplied or stated for all
equipment specified.
Where equipment is painted or otherwise coated for cosmetic or corrosion protection
reasons the protection used shall be specified and the painting or coating specifications
issued for each component.
Corrosion protection specification for all equipment supplied shall be as per the
supplier’s recommendation and in accordance with international standards specified for
installations in normal industrial non-coastal environments.
1.5 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the tank pourers:
1) All equipment shall be delivered ready for mounting in place.
2) The certification documentation shall accompany all equipment.
2 DOCUMENTATION SUPPLY
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
3) Spare parts list
4) 3D model for integration into the plant model
Documents to be supplied with the offer shall include:
1) A general arrangement.
2) Equipment design and construction information for each piece of equipment (sales
documents)
3) Approval documents (and indication of equivalency if required in section 1)
4) Technical data for each piece of equipment including:
a. Range of operability
i. Flow rate
ii. Pressure
b. Discharge Characteristics
i. Pressure drop through equipment
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Foam Sprayer
Revision No. A
13 July 2015 Page 6 of 8
ii. Metric discharge factor
c. Corrosion resistance, corrosion protection specifications and service life
5) Maintenance and operation manuals
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. 01
13 July 2015 Page 7 of 8
Appendix A
Alcoseal 3-6
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Edward Standen Cell No.: 072 130 4968 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade
Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Technical Specification
Gate Valves
Issue Date : 13/7/2015
Revision No. : A
Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Technical Specification – Gate Valves
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST
TPL25 – Technical Specification – Gate Valves
Revision No. A
13 July 2015 Page 3 of 8
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186
TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification – Gate Valves
Contents Page
Contents Page ........................................................................................................................... 3 1 Technical Specification – Gate Valve ............................................................................... 4
1.1 Introduction ................................................................................................................... 4 1.2 Scope of this Specification ........................................................................................... 4 1.3 General methods, standards, specifications and approach ......................................... 4
1.3.1 Equipment: ........................................................................................................... 4 1.3.2 Supply: ................................................................................................................. 5
1.4 Valve Actuation ............................................................................................................. 5 1.4.1 Equipment: ........................................................................................................... 5
1.5 Corrosion Protection ..................................................................................................... 6 1.6 Installation and Commissioning Requirements ............................................................ 6
2 Documentation supply ...................................................................................................... 6
TRANSNET PIPELINES prepared by: SiVEST
TPL25 – Technical Specification – Gate Valves
Revision No. A
13 July 2015 Page 4 of 8
1 TECHNICAL SPECIFICATION – GATE VALVE
1.1 Introduction
This specification is to apply to the gate valves to be employed as isolation valves
within the fire protection system. There are valves located in positions where they will
be under suction conditions as well as valves which will experience considerable
pressure at all times.. Most valves will be manually controlled however there are some
valves which are to be actuated and this specification will address this.
1.2 Scope of this Specification
The scope of this Specification is to address the required manufacture and functional
quality and specifications.
The quantity, performance characteristics and terms of supply of the required
equipment will be specified elsewhere in the request issued to market and will
reference this specification.
1.3 General methods, standards, specifications and approach
The valve selection and supply shall adhere to the following specific requirements:
1.3.1 Equipment:
1) The gate valves shall be of the Rapid Drop make or similar.
2) All valves shall be new and manufactured from all new materials unless otherwise
specified in the enquiry.
3) Valves shall:
Be lockable in the open and closed position.
Comply with the requirements of SANS 664, SANS 665 or SANS 191 or be
approved by FM or UL as indicated on the Data sheets.
All gate valves shall be of the OS&Y type.
Valves identified in the data sheets for use under low pressure conditions
shall be suitable for use under suction conditions such that air is not
entrained through the valve.
Be suitable for outdoor use and shall not be adversely effected by rainfall or
exposure to sunlight. Where acceptable exceptions such as cosmetic
considerations like faded paint might result from exposure the extent of the
effect should be noted.
Reliably open even after extended periods in open or closed position.
Comply with ISO 5210 for actuator mounting.
TRANSNET PIPELINES prepared by: SiVEST
TPL25 – Technical Specification – Gate Valves
Revision No. A
13 July 2015 Page 5 of 8
4) All valves must be of high quality and suitable for a long service life of occasional
use. Valves should provide at least 20 years of service, subject to the supplier
specified maintenance regime.
1.3.2 Supply:
1) The Supplier shall provide installation instructions detailing the labor, equipment
and any special procedures, tools, equipment or personnel required for the
installation.
2) The Supplier shall include the provision of all specialist tools, equipment and
services as separate options in the tender return.
3) The material of manufacture of all parts shall be specified on the equipment
drawings or data sheets and this information shall be supplied as a tender return.
Submission of this information does not in any way negate the supplier’s
responsibility to ensure that the specified materials are suitable for the service
required by this or any other documents pertaining to the enquiry.
4) Material certificates are to be provided for every supplied valve. Typical
certificates are to be supplied with the tender return for each valve type.
5) The Supplier is to provide full operating and maintenance and overhaul manuals
including detailed section and exploded diagrams of the valves, parts lists, typical
spares lists and pricing.
6) The Supplier is to provide drawings indicating all relevant dimensions affecting the
installation including space required to perform maintenance; this information is to
be clearly indicated for all required valve sizes.
7) The Supplier shall provide a copy of all manufacturers painting specifications
relevant to the products specified.
1.4 Valve Actuation
Valve actuator selection and supply shall adhere to the following specific requirements:
1.4.1 Equipment:
1) Valve Actuators shall comply with ISO 5210 for actuator mounting.
2) Electric actuators shall include travel limiting devices, torque overload
measurement device.
3) Actuators shall include an automatic declutchable hand wheel.
4) The actuator gear mechanism shall be totally enclosed and lubricated.
5) The actuator gear mechanism shall be capable of mounting in any orientation.
6) All valves shall be indicating and the actuator shall provide indication of the open or
closed position if not indicated by the valve structure.
7) The sizing of the actuator shall be the responsibility of the purchaser if procured
separately from the valve or the valve supplier if supplied as part of a valve to
match a functional specification.
TRANSNET PIPELINES prepared by: SiVEST
TPL25 – Technical Specification – Gate Valves
Revision No. A
13 July 2015 Page 6 of 8
1.5 Corrosion protection
Mild steel units shall be shot blasted and painted on the exterior for corrosion
protection. The contractor shall supply their paint specification as a part of the tender.
Corrosion protection specification for all equipment supplied shall be as per the
supplier’s recommendation and in accordance with international standards specified for
installations in normal industrial non-coastal environments.
1.6 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the valves:
1) All valves shall be supplied complete and ready for installation including any
special fittings or fixtures required i.e. extended studs for wafer installation of long
valve.
2) The employer shall be advised of all Factory testing and allowed the opportunity to
observe Factory Acceptance Tests if required by the employer.
3) The certification documentation shall accompany the valves which shall be suitably
identified with clear serial number installation.
2 DOCUMENTATION SUPPLY
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
3) Spare parts list
4) 3D model for integration into the plant model
Documents to be supplied with the offer shall include:
1) A general arrangement.
2) Equipment design and construction information for each piece of equipment (sales
documents)
3) Approval documents (and indication of equivalency if required in section 1)
4) Maintenance and operation manuals
5) Performance data to indicate the hydraulic performance of the valve including the
pressure drop at all flow rates (may be graph, chart or equations)
TRANSNET PIPELINES prepared by: SiVEST
TPL25 – Technical Specification – Gate Valves
Revision No. A
13 July 2015 Page 7 of 8
6) The contractor shall complete the pump data sheet and it shall be submitted with
the tender.
7) The Quality Control plan shall be issued with tender for evaluation.
8) Corrosion resistance, corrosion protection specifications and service life
SiVEST Project Management Division
4 Pencarrow Crescent, La Lucia Ridge Office Estate,
Umhlanga Rocks. 4320
PO Box 1899, Umhlanga Rocks. 4320
South Africa
Tel + 27 31 581 1500
Fax +27 31 566 2375
Email [email protected]
www.sivest.co.za
Contact Person: Didier Regnaud
Cell No.: 082 818 4965
Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Technical Specification
Jockey Pump Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Technical Specification - Jockey Pump
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Jockey Pump
Revision No. A
13 July 2015 Page 3 of 7
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification – Jockey Pump Contents Page 1 Technical Specification – Jockey Pump ............................................................................4
1.1 Introduction ....................................................................................................................4
1.2 Scope of Specifications .................................................................................................4
1.3 General methods, standards, specifications and approach ..........................................4
1.4 Corrosion protection ......................................................................................................5
1.5 Installation and Commissioning Requirements .............................................................5
2 Documentation supply .......................................................................................................6
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Jockey Pump
Revision No. A
13 July 2015 Page 4 of 7
1 TECHNICAL SPECIFICATION – JOCKEY PUMP
1.1 Introduction
This specification is to apply to the jockey pump to be employed to maintain the
pressure in the piping system up to the discharge control valves.
This specification applies to electrically driven multistage centrifugal pump for regular
duty and to be installed alongside the fire pumps in an enclosed pumphouse.
1.2 Scope of Specifications
The scope of this Specification is to address the required manufacture and functional
quality and specifications.
The quantity, performance characteristics and terms of supply of the required
equipment will be specified elsewhere in the request issued to market and will
reference this specification.
1.3 General methods, standards, specifications and approach
The pump systems and ancillary equipment shall adhere to the following specific
requirements:
1) A vertical multistage centrifugal type pump shall be supplied. The motor shall be
close-coupled.
2) If the pump may be mounted directly to foundations a separate base frame shall
not be required otherwise the pump shall be supplied mounted to a base frame
suitable for mounting to a concrete plinth.
3) All pumps to be supplied with coupling guards and shall be compliant with the OSH
act.
4) All pumps to be supplied with all pump internals, seals and ancillary equipment
required for the pumps sealing (i.e. water pot for mechanical seals).
5) The head at zero delivery shall be at least 1.2 times the operating head, where
applicable.
6) Shaft, bearings and housing to be manufactured of corrosion resistant materials
and resistant to the liquid being conveyed.
7) Electrical motors shall be IP55 380V 3 PH 50Hz.
8) The pump system design temperature shall be min. -10 °C and max. +65°C. If this
condition isn’t met the range of operation must be stated.
9) Matching flanges shall be supplied for all non-commonly available interfacing
flanges, i.e. flanges joined to the suction and supply flanges of foreign pumps,
valves and other equipment.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Jockey Pump
Revision No. A
13 July 2015 Page 5 of 7
10) All bolts, nuts and washers shall be GRADE 8.8 cold galvanized electroplated or
better.
11) The pump unit shall be fitted with an earthing point, in order for others to complete
the earthing requirements.
12) Pumps shall be fitted with a name plate depicting the details of the pump codes of
manufacture and minimum requirements according to the code.
13) The following shall be supplied with the tender as a minimum:
a. Pump unit general arrangement drawing
b. Pump curves
c. Pump datasheets
d. Operating and Maintenance Manuals
e. Spare Parts list
f. Service life (Both hours of operation and life span in years)
14) The tenderer shall provide a QCP for each fabricated / supplied item as a
minimum. The tenderer shall supply a sample QCP with the tender for evaluation.
15) The supplier shall advise on the required mounting and grouting configuration.
16) The pump set is to be supplied with explosion proof coupling guards.
1.4 Corrosion protection
Mild steel pump units shall be shot blasted and painted on the exterior for corrosion
protection.
Corrosion protection specification for all equipment supplied shall be as per the
supplier’s recommendation and in accordance with international standards specified for
installations in normal industrial non-coastal environments.
1.5 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the pumps:
1) All pumps shall be aligned in the factory/workshop before delivery to site.
2) The employer shall be advised of all Factory testing and allowed the opportunity to
observe Factory Acceptance Tests if required by the employer.
3) The certification documentation shall accompany the pumps and engines which
shall be suitably identified with clear serial number installation.
The tenderer shall note that many parties shall be involved in the construction in this
area and the contractor shall be required to interface with management, who will make
every effort to provide access when required.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Jockey Pump
Revision No. A
13 July 2015 Page 6 of 7
2 DOCUMENTATION SUPPLY
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
3) Spare parts list
4) 3D model for integration into the plant model
Documents to be supplied with the offer shall include:
1) A general arrangement.
2) Equipment design and construction information for each piece of equipment (sales
documents)
3) Approval documents (and indication of equivalency if required in section 1)
4) Maintenance and operation manuals
5) Pump curves of specified equipment
6) The contractor shall complete the pump data sheet and it shall be submitted with
the tender.
7) The Quality Control plan shall be issued with tender for evaluation.
8) Corrosion resistance, corrosion protection specifications and service life
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Edward Standen Cell No.: 072 130 4968 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Technical Specification
Level Control Valves Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Technical Specification – Level Control Valves
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Level Control Valves
Revision No. A
13 July 2015 Page 3 of 8
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification – Level Control Valves Contents Page Contents Page ........................................................................................................................... 3
1 Technical Specification – Level Control Valve .................................................................. 4
1.1 Introduction ................................................................................................................... 4
1.2 Scope of this Specification ........................................................................................... 4
1.3 General methods, standards, specifications and approach ......................................... 4
1.3.1 Equipment: ........................................................................................................... 4
1.3.2 Supply: ................................................................................................................. 5
1.4 Specific technical specifications - Protection ................................................................ 5
1.4.1 Winterisation of valves: ........................................................................................ 5
1.5 Corrosion protection ..................................................................................................... 6
1.6 Installation and Commissioning Requirements ............................................................ 6
2 Documentation supply ...................................................................................................... 6
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Level Control Valves
Revision No. A
13 July 2015 Page 4 of 8
1 TECHNICAL SPECIFICATION – LEVEL CONTROL VALVE
1.1 Introduction
This specification is to apply to the float control valves to be employed to control the
water level in the fire water storage tanks. They shall be activated by remote float
valves.
The valves shall control the flow of potable water and will be installed exposed to the
atmosphere.
1.2 Scope of this Specification
The scope of this Specification is to address the required manufacture and functional
quality and specifications.
The quantity, performance characteristics and terms of supply of the required
equipment will be specified elsewhere in the request issued to market and will
reference this specification.
1.3 General methods, standards, specifications and approach
The valve selection and supply shall adhere to the following specific requirements:
1.3.1 Equipment:
1) All valves shall be new and manufactured from all new materials unless otherwise
specified in the enquiry.
2) Control valves shall:
Comply with the requirements of SANS 752 – float valves.
Be of ‘non-clack’ type.
Have “no moving mechanical parts”.
Be axially symmetrical in open and closed position
Be rated for outdoor use and shall not be adversely effected by rainfall or
exposure to sunlight. Where acceptable exceptions such as cosmetic
considerations like faded paint might result from exposure the extent of the
effect should be noted.
Reliably open with no outside intervention even after extended periods of
closure
Be of the remote float actuation type and the valve in the supply line shall be
installed at grade level
Not open immediately as the water level in the tank drops; the close point
should be about 20mm higher than the open point so that the level has to
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Level Control Valves
Revision No. A
13 July 2015 Page 5 of 8
drop 20mm from the high-high level before the valve opens to prevent very
rapid open close cycles.
Small bore pilot lines shall be of stainless steel construction and winterized
The supply system pressure shall be verified and the valve selected to
operate satisfactorily within the system. If the supply pressure is too low
relative to the full tank level for a standard system to operate an alternative
pilot type level control valve should be considered; either altitude type or
electronic float switch may be suitable.
3) All valves must be of high quality and suitable for a long service life of occasional
use. Valves should provide at least 20 years of service, subject to the supplier
specified maintenance regime.
4) Control valves shall have winter-proof coverings to ensure operation even at the
minimum temperatures listed in the data sheet.
1.3.2 Supply:
1) The Supplier shall provide installation instructions detailing the labor, equipment
and any special procedures, tools, equipment or personnel required for the
installation.
2) The Supplier shall include the provision of all specialist tools, equipment and
services as separate options in the tender return.
3) The material of manufacture of all parts shall be specified on the equipment
drawings or data sheets and this information shall be supplied as a tender return.
Submission of this information does not in any way negate the supplier’s
responsibility to ensure that the specified materials are suitable for the service
required by this or any other documents pertaining to the enquiry.
4) Material certificates are to be provided for every supplied valve. Typical
certificates are to be supplied with the tender return for each valve type.
5) The Supplier is to provide full operating and maintenance and overhaul manuals
including detailed section and exploded diagrams of the valves, parts lists, typical
spares lists and pricing.
6) The Supplier is to provide drawings indicating all relevant dimensions affecting the
installation including space required to perform maintenance; this information is to
be clearly indicated for all required valve sizes.
7) The Supplier shall provide a copy of all manufacturers painting specifications
relevant to the products specified.
1.4 Specific technical specifications - Protection
1.4.1 Winterisation of valves:
1) Control valves shall be insulated and heated as required to prevent freezing which
would render them inoperable
2) The temperature of restricted areas containing water is to be prevented from
dropping below 4 °C
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Level Control Valves
Revision No. A
13 July 2015 Page 6 of 8
3) Insulation is to be designed and installed in accordance with SANS 9288 and
SANS 612
1.5 Corrosion protection
Mild steel units shall be shot blasted and painted on the exterior for corrosion
protection. The contractor shall supply their paint specification as a part of the tender.
Corrosion protection specification for all equipment supplied shall be as per the
supplier’s recommendation and in accordance with international standards specified for
installations in normal industrial non-coastal environments.
1.6 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the valves:
1) All valves shall be supplied complete and ready for installation including any
special fittings or fixtures required i.e. extended studs for wafer installation of long
valve.
2) The employer shall be advised of all Factory testing and allowed the opportunity to
observe Factory Acceptance Tests if required by the employer.
3) The certification documentation shall accompany the valves which shall be suitably
identified with clear serial number installation.
The tenderer shall note that many parties shall be involved in the construction in this
area and the contractor shall be required to interface with management, who will make
every effort to provide access when required.
2 DOCUMENTATION SUPPLY
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
3) Spare parts list
4) 3D model for integration into the plant model
Documents to be supplied with the offer shall include:
1) A general arrangement.
2) Equipment design and construction information for each piece of equipment (sales
documents)
3) Approval documents (and indication of equivalency if required in section 1)
4) Maintenance and operation manuals
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Level Control Valves
Revision No. A
13 July 2015 Page 7 of 8
5) Performance data to indicate the hydraulic performance of the valve including the
pressure drop at all flow rates (may be graph, chart or equations)
6) The contractor shall complete the pump data sheet and it shall be submitted with
the tender.
7) The Quality Control plan shall be issued with tender for evaluation.
8) Corrosion resistance, corrosion protection specifications and service life
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Didier Regnaud Cell No.: 082 818 4965 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Technical Specification
Low Level Pourer Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Technical Specification – Low Level Pourers
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Low Level Pourer
Revision No. A
13 July 2015 Page 3 of 8
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification – Low Level Pourer Contents Page
1 TECHNICAL SPECIFICATION – LOW LEVEL POURER .................................................................... 4
1.1 INTRODUCTION ............................................................................................................................... 4 1.2 SCOPE OF SPECIFICATIONS ................................................................................................................ 4 1.3 GENERAL METHODS, STANDARDS, SPECIFICATIONS AND APPROACH ........................................................... 4 1.4 CORROSION PROTECTION .................................................................................................................. 5 1.5 INSTALLATION AND COMMISSIONING REQUIREMENTS ............................................................................ 5
2 DOCUMENTATION SUPPLY ....................................................................................................... 6
APPENDIX A ....................................................................................................................................... 7
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Low Level Pourer
Revision No. A
13 July 2015 Page 4 of 8
1 TECHNICAL SPECIFICATION – LOW LEVEL POURER
1.1 Introduction
This specification is to apply to the Low Level Pourer equipment required to discharge
foam onto some areas of the plant for the suppression of hydro-carbon fires.
This specification applies to those low level pourer systems used to protect bund areas
including those around storage tanks as well as spill basins and possibly areas of
piping manifolds.
1.2 Scope of Specifications
The scope of this Specification is to address the required manufacture and functional
quality and specifications.
The quantity, performance characteristics and terms of supply of the required
equipment will be specified elsewhere in the request issued to market and will
reference this specification.
1.3 General methods, standards, specifications and approach
The low level pourers addressed by this specification are considered to be single
components which will be mounted to structure and remain as dedicated protection in
that area and will require only connection to the premix supply to operate.
The Low Level Pourer system and ancillary equipment shall adhere to the following
specific requirements:
1) The low level pourers shall be of the Angus make or similar.
2) Each component shall be appropriately sized for the flow and discharge
requirements specified in the relevant Data Sheets as referenced in the Tender.
3) The Low Level Pourers shall be approved or listed by at least one of the following
agencies for the appropriate application:
a. SABS – South African Bureau of Standards
b. UL – Underwriters Laboratories (USA)
c. FM – Factory Mutual (USA)
d. VdS – Verband der Saeliversicherer (Germany)
e. AFNOR – Association Francaise de Normalisation (France)
f. B.S. – British Standards (Great Britain)
g. LPC – Loss Prevention Council (Great Britain)
h. C.S.A. – Canadian Standards Association (Canada)
i. ULC – Underwriters Laboratories Canada (Canada)
j. SAA – Australian Standards (Australia)
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Low Level Pourer
Revision No. A
13 July 2015 Page 5 of 8
4) The equipment shall be suitable for duty with regular exposure to Alcoseal 3-6
Premix in 3 or 6%.
5) The equipment shall be suitable for use in all ambient conditions. If operability may
be effected by freezing of water within the system the equipment shall be insulated
or otherwise protected against inoperability cause by low temperatures. Where a
low drain from a weep hole would prevent restriction of operation due to freezing
this will be an acceptable solution.
6) The equipment shall generate and discharge the foam at a rate suitable for the
extinguishment of hydrocarbon fires when 3% premix of Alcoseal 3-6 is used.
7) The equipment shall generate and discharge the foam at a rate suitable for the
extinguishment of polar solvents and hydrocarbon fires when 6% premix of
Alcoseal 3-6 is used.
8) Corrosion protection shall be suitable for extended service life as per section 1.4
1.4 Corrosion protection
All equipment shall be suitable for extended outdoor installation with no resultant loss
of reliability.
Service requirements and typical service life shall be supplied or stated for all
equipment specified.
Where equipment is painted or otherwise coated for cosmetic or corrosion protection
reasons the protection used shall be specified and the painting or coating specifications
issued for each component.
Corrosion protection specification for all equipment supplied shall be as per the
supplier’s recommendation and in accordance with international standards specified for
installations in normal industrial non-coastal environments.
1.5 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the low level pourers:
1) All equipment shall be delivered assembled and complete ready for mounting in
place and connection of the supply pipe.
2) The Equipment shall be supplied with full MOC certification.
3) The certification documentation shall accompany the equipment which shall be
suitably identified with clearly marked serial number.
4) The supply shall include full Quality Control and Quality Assurance documentation.
5) The tenderer shall advise of all tests or checks to be completed in the
commissioning of the systems.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Low Level Pourer
Revision No. A
13 July 2015 Page 6 of 8
2 DOCUMENTATION SUPPLY
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
3) Spare parts list
4) 3D model for integration into the plant model
Documents to be supplied with the offer shall include:
1) A general arrangement.
2) Equipment design and construction information for each piece of equipment (sales
documents)
3) Approval documents (and indication of equivalency if required in section 1)
4) Technical data for each piece of equipment including:
a. Range of operability
i. Flow rate
ii. Pressure
b. Discharge Characteristics
i. Pressure drop through equipment
c. Corrosion resistance, corrosion protection specifications and service life
5) Maintenance and operation manuals
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. 01
13 July 2015 Page 7 of 8
Appendix A
Alcoseal 3-6
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Edward Standen Cell No.: 072 130 4968 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SiTES
Technical Specification
Oscillating Monitor Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Technical Specification – Oscillating monitor
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Oscillating Monitor
Revision No. A
13 July 2015 Page 3 of 9
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification – Oscillating Monitor Contents Page
1 TECHNICAL SPECIFICATION – OSCILLATING MONITOR .............................................................. 4
1.1 INTRODUCTION ............................................................................................................................... 4 1.2 SCOPE OF SPECIFICATIONS ................................................................................................................ 4 1.3 GENERAL METHODS, STANDARDS, SPECIFICATIONS AND APPROACH ........................................................... 4 1.4 CORROSION PROTECTION .................................................................................................................. 5 1.5 INSTALLATION AND COMMISSIONING REQUIREMENTS ............................................................................ 6
2 DOCUMENTATION SUPPLY ....................................................................................................... 6
APPENDIX A ....................................................................................................................................... 8
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Oscillating Monitor
Revision No. A
13 July 2015 Page 4 of 9
1 TECHNICAL SPECIFICATION – OSCILLATING MONITOR
1.1 Introduction
This specification is to apply to oscillating foam canon installations used for the
discharge of aerated low expansion foam on a trajectory from a remote position onto a
defined area for the suppression of hydro-carbon fires.
This specification applies to those monitor systems used to protect piping manifolds
and similar process equipment not fuel storage tank areas.
1.2 Scope of Specifications
The scope of this specification is to address the required manufacture and functional
quality and specifications.
The quantity, performance characteristics and terms of supply of the required
equipment will be specified elsewhere in the request issued to market and will
reference this specification.
1.3 General methods, standards, specifications and approach
The oscillating monitor system addressed by this specification is considered to
comprise of an oscillating mechanism, monitor and discharge system; the discharge
system may comprise a nozzle and tube or necessary configurations. The ruling
consideration in determining the extents of the system will be that the system shall be
complete to allow the assembly of all components and shall require only fitment to a
standpipe and supply of liquid flow and pressure to operate.
The Oscillating Monitor system and ancillary equipment shall adhere to the following
specific requirements:
1) The Monitors, nozzles and oscillating mechanism shall all be of the same make
and these shall be Akron or similar.
2) Each component shall be appropriately sized for the flow and discharge
requirements specified in the relevant Data Sheets as referenced in the Tender.
3) The full technical information of each component specified shall be made available
to allow verification of the flow rates, pressure requirements, pressure drops and
discharge distances at the required flow rate. This shall not prejudice the
requirement for the tenderer to specify correctly sized equipment.
4) The Oscillating Flange system shall be FM approved; equipment with equivalent
approval through another body (such as UL or LPC) may be acceptable however
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Oscillating Monitor
Revision No. A
13 July 2015 Page 5 of 9
the testing standard or equivalency shall be documented in the submission; such
alternative shall however, be subject to approval by the employer.
5) The monitor shall be FM approved; equipment with equivalent approval through
another body (such as UL or LPC) may be acceptable however the testing
standard or equivalency shall be documented in the submission; such alternative
shall however, be subject to approval by the employer.
6) The equipment shall be suitable for duty with regular exposure to Alcoseal 3-6
Premix in 3 or 6%.
7) The nozzle shall be of the “blabber mouth” type unless the specific flow rate or
discharge range requirement can’t be catered for with such a nozzle in which case
an alternative can be specified for specific instances; such specification shall
however, be subject to approval by the employer.
8) The oscillation settings available on the oscillating system shall, at a minimum, be
adjustable between the range of 0° to 120° about the vertical axis
9) The monitor shall allow full 360° adjustability about the vertical axis
10) The monitor shall allow adjustment from 40° below the horizontal plane to 80°
above the horizontal plane.
11) The equipment shall be suitable for use in all ambient conditions. If operability may
be effected by freezing of water within the system the equipment shall be insulated
or otherwise protected against inoperability caused by low temperatures.
12) The monitor shall be designed such as to reduce as far as possible the hydraulic
losses through it.
13) The monitor adjustment shall be manually lockable, easily unlockable and
adjustable by hand. The full operation should be possible by any reasonably
healthy adult.
14) The equipment shall generate and discharge the foam at a rate suitable for the
extinguishment of hydrocarbon fires when 3% premix of Alcoseal 3-6 is used.
15) The equipment shall generate and discharge the foam at a rate suitable for the
extinguishment of polar solvents and hydrocarbon fires when 6% premix of
Alcoseal 3-6 is used.
16) All components shall comply with NFPA requirements.
1.4 Corrosion protection
All equipment shall be suitable for extended outdoor installation with no resultant loss
of reliability.
Service requirements and typical service life shall be supplied or stated for all
components specified.
Where equipment is painted or otherwise coated for cosmetic or corrosion protection
reasons the protection used shall be specified and the painting or coating specifications
issued for each component.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Oscillating Monitor
Revision No. A
13 July 2015 Page 6 of 9
Corrosion protection specification for all equipment supplied shall be as per the
supplier’s recommendation and in accordance with international standards specified for
installations in normal industrial non-coastal environments.
1.5 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the oscillating monitor system:
1) All equipment shall be delivered assembled and complete. For clarification, the
monitor does not need to be mounted to the oscillating flange but all equipment
must be in a condition so that the oscillating flange can be mounted directly to the
standpipe, the monitor can be mounted directly to the oscillating flange and the
nozzle mounted to the monitor only after which the system shall be functional.
2) All fittings, fasteners and seals necessary for the installation of the components of
the system shall be included in the supply. If non-standard gaskets or fasteners
are required to fasten the oscillating flange to the standpipe these shall also be
supplied.
3) The Equipment shall be supplied with full MOC certification.
4) The certification documentation shall accompany the equipment which shall be
suitably identified with clearly marked serial number.
5) The supply shall include full Quality Control and Quality Assurance documentation.
6) The tenderer shall advise of all tests or checks to be completed in the
commissioning of the systems.
2 DOCUMENTATION SUPPLY
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
3) Spare parts list
4) 3D model for integration into the plant model
Documents to be supplied with the offer shall include:
1) A general arrangement.
2) Equipment design and construction information for each piece of equipment (sales
documents)
3) Approval documents (and indication of equivalency if required in section 1)
4) Technical data for each piece of equipment including:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Oscillating Monitor
Revision No. A
13 July 2015 Page 7 of 9
a. Range of operability
i. Flow rate
ii. Pressure
b. Discharge Characteristics
i. Discharge pattern
ii. Pressure drop through equipment
iii. Discharge range, at pressure, flow and elevation (may be specific
to requirements or general but clear information). This must either
indicate requirements are achievable with the parameters advised
in the data sheets or the pressure and flow requirements to meet
the discharge requirements.
c. Corrosion resistance, corrosion protection specifications and service life
5) Maintenance and operation manuals
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. 01
13 July 2015 Page 8 of 9
Appendix A
Alcoseal 3-6
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Edward Standen Cell No.: 072 130 4968 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TARLTON
Technical Specification
Overhead Crawl and Hoist Issue Date : 23/9/2015 Revision No. : A Project No. : 11992
Date: 23/9/2015
Document Title: All Sites - Fire Protection System:
Technical Specification – Overhead Crawl and Hoist
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Overhead Crawl and Hoist Technical Specification
Revision No. A
23 September 2015 Page 3 of 9
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
All Sites
Technical Specification – Overhead Crawl and Hoist Contents Page
1 Technical Specification - Fire Pump ..................................................................................4
1.1 Introduction ....................................................................................................................4 1.2 Scope of Specifications .................................................................................................4 1.3 Definitions ..................................................................... Error! Bookmark not defined. 1.4 Specification ................................................................. Error! Bookmark not defined. 1.5 Corrosion protection ..................................................... Error! Bookmark not defined. 1.6 Installation and Commissioning Requirements ............ Error! Bookmark not defined.
2 Documentation supply ...................................................... Error! Bookmark not defined.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
23 September 2015 Page 4 of 9
1 TECHNICAL SPECIFICATION – OVERHEAD CRAWL AND HOIST
1.1 Introduction
This specification is to apply to the overhead crawl beam and electric hoist to be
installed in the Fire Pump House for the handling of the Fire Pump sets for installation
and maintenance.
1.2 Scope of Specifications
This specification is to address the required quality and functionality of equipment and
systems.
This document forms part of the Works Information. The quantity and terms of supply
of the required equipment will be specified elsewhere in the Works Information.
This technical specification applies to the supply of the following:
10 Tonne electrically operated trolley
10 Tonne electrically operated hoist
2 DESIGN SPECIFIC REQUIREMENTS
The hoist system will consist of an electric chain hoist with a hook and matching electric
geared trolley. The electric geared trolley shall be suitable for operation on a beam with
a flange width of 165mm.
The pendant type control will have a length of 5m.
3 DESIGN STANDARDS
The design, manufacture, installation and testing of the cranes and hoists must be in
accordance with the latest edition of the following International Standards:
3.1) BS EN 14492-2 Cranes – Power Driven Hoists
3.2) SANS 10375: Inspection, testing and examination of overhead cranes.
4 EQUIPMENT SPECIFICATION
4.1) The hoists shall be certified by the Contractor upon completion of the
installation. The Contractor shall supply all test weights for the purposes of
the certification & testing.
4.2) All gearboxes shall have a service factor of 2.
4.3) The maintenance cranes shall be fitted with pendant controls.
4.4) The motorized crane must be provided with a power supply isolation switch
within 6 meters of the downshop leads starting point.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
23 September 2015 Page 5 of 9
The contractor must supply and install the cable tray to connect the
downshop leads to the isolation switch.
4.5) Gantry Cranes
All gantry cranes must include the following components as a minimum:
4.5.1) Brakes
4.5.1.1) All brakes must be suitably sized to perform effective braking on all
systems.
4.5.1.2) All brakes must be fitted with a fail-safe system, requiring power to
release the brake to allow movement. That case in the event of a loss
of power the brakes will engage automatically.
4.5.2) Lifting Hook
4.5.2.1) Hooks must be solid, heat treated and fitted with a safety latch as well
as pre-marked to allow for stretch measurement.
4.5.3) Buffers
4.5.3.1) Buffers should either be spring loaded or feature an equivalent
alternative.
4.5.3.2) They should be fitted to both ends of the crawl system.
4.5.3.3) All buffers must have the ability to stop either the bridge or trolley when
travelling under no power at 20% of rated load speed.
4.5.4) Power Supply
4.5.4.1) There will be a 430V supply available.
4.5.5) Electrical Requirements
4.5.5.1) The tenderer must install all the required wiring for the crane unit.
4.5.5.2) Electrical equipment shall be located or enclosed so that under normal
operating conditions energized components are not exposed to
accidental contact.
4.5.5.3) Energized components of electrical equipment must be protected from
direct contact with oil, grease and moisture.
4.5.5.4) If guards are provided for energized components they should have the
strength to resist deformation and subsequently avoid contact with the
energized component.
4.5.5.5) The crane unit shall be fitted with fixed earthing points, in order for
others to complete the earthing requirements.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
23 September 2015 Page 6 of 9
4.5.5.6) Electrical boxes shall be fitted with a name plate depicting the details of
the electrical equipment inside.
4.5.5.7) The downshop power supply and control leads shall be of the catenary
type with adequate trolley cable carriers to adequately support the
cable.
NOTE: All electrical wiring shall conform to TPL Standards and where there
is not a TPL standard the wiring shall conform to International
Standards.
4.5.6) Crane Control
4.5.6.1) Trolley and Hoist shall be operated through the use of a pendant
control.
4.5.6.2) Arrangement of pendant controls must conform to industry standards.
4.5.6.3) Pendant to be supported from wire rope/chain so as to protect electrical
cables from strain. Length of pendant plus rope/chain must be of
suitable length to prevent dragging on the ground.
4.5.6.4) Trolley and hoist operating procedures (Trolley direction, start/stop,
speed etc.) must be displayed on the pendant.
4.5.7) Safety Devices
Various safety devices shall be fitted in order to prevent over loading of the
Hoist:
4.5.7.1) Load limiting devices shall be installed. This will prevent any loads
which exceed the maximum carrying capacity of the crane to be
hoisted.
4.5.7.2) Safety of the hoist shall be in the form of limit switches to limit the
maximum and minimum height to which the load block can be raised
and lowered.
4.5.7.3) Deceleration devices to automatically reduce the speed of the trolley
and hoist when they approach the end of their runway. This will be
implemented through the use of limit switches.
4.5.7.4) Anti-fall devices must also be installed to the crane unit.
4.5.7.5) Audio and visual alerts must be installed for end travel limit switches.
4.5.8) Runway Sweeps
4.5.8.1) The trolley must have sweeps to remove any material off the run way.
4.5.9) Signage
4.5.9.1) All relevant warning signs must be provided along with clearly visible
load limits on the trolley, hoist and load hooks.
4.5.10) Warning Devices
4.5.10.1) A strobe light and siren must be provided to warn of moving or
suspended loads.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
23 September 2015 Page 7 of 9
5 INSTALLATION
The contractor shall carry out the following as a minimum for the installation of the crane: 5.1) Installation of the trolley and hoist and all ancillary systems.
5.2) Installation of all required electrical hardware.
6 COMMISSIONING
The contractor shall perform the following as a minimum for the commissioning of the hoist system: 6.1) The contractor shall check and supply all lubrication, also checking for
overfilling, and fill where necessary before commissioning commences.
6.2) Commissioning
6.3) Supply and installation of commissioning spares as required.
6.4) Testing the correct operation of all breaking systems to within acceptable
operating parameters.
6.5) Testing the correct operation of all safety devices to within acceptable
operating parameters, such as deceleration devices etc.
6.6) Testing the correct operation of the trolley and hoist and ensuring that there is
no excess vibration, noise, misalignment etc.
6.7) All testing will initially be carried out under no load conditions and progress
with increasing loads if successful until the maximum load capacity is
reached.
6.8) Testing will then be carried out under overload conditions, 110%, and ensure
that all systems are in working order.
6.9) During the testing period all required adjustments will be made so as to
conform to the technical specifications.
NOTE: Weights required for testing will be supplied by the contractor. If water weights are used, the contractor will be responsible for the supply of water.
7 DOCUMENTS TO BE SUBMITTED WITH TENDER
7.1) General Arrangement and Detail Drawings shall be submitted in for
evaluation and integration purposes.
7.2) The Quality Control plan shall be issued with the tender for evaluation.
7.3) The contractor must specify their preferred crane rail.
7.4) A programme indicating manufacturing / procurement, workshop assembly,
transport to site, site erection and testing from date of receipt of order.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. A
23 September 2015 Page 8 of 9
8 DOCUMENTS TO BE PROVIDED FOLLOWING CONTRACT AWARD
Data packs shall be provided in a lever arch file, with a scanned electronic copy, but not limited to:
8.1) Detail drawings of all equipment supplied.
8.2) Installation and Maintenance manuals.
8.3) Spare parts list.
8.4) Installation certificate of compliance.
9 INCLUSIONS
The contractor will supply but not limited to the following equipment:
9.1) The supply and install of the electric trolley and hoist and the necessary
controls and safety devices.
9.2) The contractor to supply and install downshop leads on all electrical trolleys
and hoists on their total travel length.
9.3) All conduit and wiring works from the field isolator positioned 1m above
ground level at the end of the building.
9.4) Commissioning & Verification – the contractor shall allow for the test weights
required for this testing and verification.
9.5) Transport to site.
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Didier Regnaud Tell No.: 031 581 1512 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Technical Specification
Tank Pourer Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites Fire Protection System:
Technical Specification – Tank Pourer
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Tank Pourer
Revision No. A
13 July 2015 Page 3 of 8
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification – Tank Pourer Contents Page 1 Technical Specification – Tank Pourer ............................................................................. 4
1.1 Introduction ................................................................................................................... 4 1.2 Scope of Specifications ................................................................................................ 4 1.3 General methods, standards, specifications and approach ......................................... 4 1.4 Corrosion protection ..................................................................................................... 5 1.5 Installation and Commissioning Requirements ............................................................ 5
2 Documentation supply ...................................................................................................... 6 Appendix A ................................................................................................................................ 7
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Tank Pourer
Revision No. A
13 July 2015 Page 4 of 8
1 TECHNICAL SPECIFICATION – TANK POURER
1.1 Introduction
This specification is to apply to the Tank Pourer equipment required to discharge foam
into atmospheric hydro-carbon storage tanks for the suppression of fires.
1.2 Scope of Specifications
The scope of this Specification is to address the required manufacture and functional
quality and specifications.
The quantity, performance characteristics and terms of supply of the required
equipment will be specified elsewhere in the request issued to market and will
reference this specification.
1.3 General methods, standards, specifications and approach
The tank pourers addressed by this specification are considered to be single
components which will be mounted to the tanks and remain as dedicated protection in
that area and will require only connection to the premix supply to operate.
The Tank Pourer system and ancillary equipment shall adhere to the following specific
requirements:
1) The tank pourers shall be of the Angus make or similar.
2) Each component shall be appropriately sized for the flow and discharge
requirements specified in the relevant Data Sheets as referenced in the Tender.
3) The Tank Pourers shall be approved or listed by at least one of the following
agencies for the appropriate application:
a. SABS – South African Bureau of Standards
b. UL – Underwriters Laboratories (USA)
c. FM – Factory Mutual (USA)
d. VdS – Verband der Saeliversicherer (Germany)
e. AFNOR – Association Francaise de Normalisation (France)
f. B.S. – British Standards (Great Britain)
g. LPC – Loss Prevention Council (Great Britain)
h. C.S.A. – Canadian Standards Association (Canada)
i. ULC – Underwriters Laboratories Canada (Canada)
j. SAA – Australian Standards (Australia)
4) The equipment shall be suitable for duty with regular exposure to Alcoseal 3-6
Premix in 3 or 6%.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Tank Pourer
Revision No. A
13 July 2015 Page 5 of 8
5) The equipment shall prevent the leaking of vapors or condensate out of the tank or
rainwater or condensate into the tank. This is normally achieved with a frangible
seal.
6) The equipment must be easy to maintain and commission; it must not be
necessary to remove the equipment to perform any regular maintenance or repairs
including the replacement of frangible seals.
7) The equipment shall be suitable for use in all ambient conditions. If operability may
be effected by freezing of water within the system the equipment shall be insulated
or otherwise protected against inoperability cause by low temperatures. There
shall be a weep hole and the bottom of the supply pipe so there will be a free drain
out the supply and no standing water in the supply is to be considered.
8) The equipment shall generate and discharge the foam at a rate suitable for the
extinguishment of hydrocarbon fires when 3% premix of Alcoseal 3-6 is used.
9) The equipment shall generate and discharge the foam at a rate suitable for the
extinguishment of polar solvents and hydrocarbon fires when 6% premix of
Alcoseal 3-6 is used.
10) Corrosion protection shall be suitable for extended service life as per section 1.4
1.4 Corrosion protection
All equipment shall be suitable for extended outdoor installation with no resultant loss
of reliability.
Service requirements and typical service life shall be supplied or stated for all
equipment specified.
Where equipment is painted or otherwise coated for cosmetic or corrosion protection
reasons the protection used shall be specified and the painting or coating specifications
issued for each component.
Corrosion protection specification for all equipment supplied shall be as per the
supplier’s recommendation and in accordance with international standards specified for
installations in normal industrial non-coastal environments.
1.5 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the tank pourers:
1) All equipment shall be delivered assembled and complete ready for mounting in
place and connection of the supply pipe.
2) Equipment shall be installed to tanks through fastening to a nozzle welded to the
tank shell and the equipment shall have all necessary extensions and flanges to
facilitate this.
3) The Equipment shall be supplied with full MOC certification.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Tank Pourer
Revision No. A
13 July 2015 Page 6 of 8
4) The certification documentation shall accompany the equipment which shall be
suitably identified with clearly marked serial number.
5) The supply shall include full Quality Control and Quality Assurance documentation.
6) The tenderer shall advise of all tests or checks to be completed in the
commissioning of the systems.
2 DOCUMENTATION SUPPLY
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
3) Spare parts list
4) 3D model for integration into the plant model
Documents to be supplied with the offer shall include:
1) A general arrangement.
2) Equipment design and construction information for each piece of equipment (sales
documents)
3) Approval documents (and indication of equivalency if required in section 1)
4) Technical data for each piece of equipment including:
a. Range of operability
i. Flow rate
ii. Pressure
b. Discharge Characteristics
i. Pressure drop through equipment
c. Corrosion resistance, corrosion protection specifications and service life
5) Maintenance and operation manuals
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. 01
13 July 2015 Page 7 of 8
Appendix A
Alcoseal 3-6
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Edward Standen Cell No.: 072 130 4968 Email: [email protected]
TRANSNET PIPELINES
Project: TPL 25 Sites Fire Upgrade Engineering Design PYP/W1/6/21/1186
TPL25 SITES
Technical Specification
Water Sprayer Issue Date : 13/7/2015 Revision No. : A Project No. : 11992
Date: 13/7/2015
Document Title: TPL25 Sites: Fire Protection System:
Technical Specification – Water Sprayer
Author: Edward Standen
Revision Number: A
Checked by: Trevor Albertyn
Approved by: Didier Regnaud
For: SiVEST Project Management Division
Signature:
Approved by:
For: Transnet Pipelines
Signature:
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Water Sprayer
Revision No. A
13 July 2015 Page 3 of 7
FIRE PROTECTION SYSTEM UPGRADE
Project PYP/W1/6/21/1186 TPL 25 SITES ENGINEERING (SiVEST Project No. 11992)
TPL25 SITES
Technical Specification – Water Sprayer Contents Page 1 Technical Specification – Foam Sprayer .......................................................................... 4
1.1 Introduction ................................................................................................................... 4 1.2 Scope of Specifications ................................................................................................ 4 1.3 General methods, standards, specifications and approach ......................................... 4 1.4 Corrosion protection ..................................................................................................... 4 1.5 Installation and Commissioning Requirements ............................................................ 5
2 documentation supply ....................................................................................................... 5 Appendix A ................................................................................................................................ 6
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Water Sprayer
Revision No. A
13 July 2015 Page 4 of 7
1 TECHNICAL SPECIFICATION – WATER SPRAYER
1.1 Introduction
This specification is to apply to the water sprayers to be installed to discharge water
onto fuel storage tanks in order to cool these when exposed to adjacent fires. There
are requirements for fan and cone spray patterns with various discharge coefficients.
1.2 Scope of Specifications
The scope of this Specification is to address the required manufacture and functional
quality and specifications.
The quantity, performance characteristics and terms of supply of the required
equipment will be specified elsewhere in the request issued to market and will
reference this specification.
1.3 General methods, standards, specifications and approach
The nozzles addressed by this specification are for use with water only.
The water sprayer system and ancillary equipment shall adhere to the following specific
requirements:
1) The water sprayers shall be of the Tyco make or similar.
2) Each component shall be appropriately sized for the flow and discharge
requirements specified in the relevant Data Sheets as referenced in the Tender.
3) The range offered in tender must cater for both fan and cone discharge patterns
with discharge coefficients of 25 and 45 for both styles.
4) The nozzles shall be of metallic construction; either brass or Stainless steel.
5) The nozzles shall be approved or listed by at least one of the following agencies for
the appropriate application:
a. SABS – South African Bureau of Standards
b. UL – Underwriters Laboratories (USA)
c. FM – Factory Mutual (USA)
d. LPC – Loss Prevention Council (Great Britain)
6) Corrosion protection shall be suitable for extended service life as per section 1.4
1.4 Corrosion protection
All equipment shall be suitable for extended outdoor installation with no resultant loss
of reliability.
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Technical Specification – Water Sprayer
Revision No. A
13 July 2015 Page 5 of 7
Service requirements and typical service life shall be supplied or stated for all
equipment specified.
Where equipment is painted or otherwise coated for cosmetic or corrosion protection
reasons the protection used shall be specified and the painting or coating specifications
issued for each component.
Corrosion protection specification for all equipment supplied shall be as per the
supplier’s recommendation and in accordance with international standards specified for
installations in normal industrial non-coastal environments.
1.5 Installation and Commissioning Requirements
The contractor shall allow for the following as a minimum for the supply, installation and
commissioning of the tank pourers:
1) All equipment shall be delivered ready for mounting in place.
2) The certification documentation shall accompany all equipment.
2 DOCUMENTATION SUPPLY
Documents to be supplied upon award of the supply contract shall include:
1) Installation and maintenance manual
2) AUTOCAD General Arrangement drawings
3) Spare parts list
4) 3D model for integration into the plant model
Documents to be supplied with the offer shall include:
1) A general arrangement.
2) Equipment design and construction information for each piece of equipment (sales
documents)
3) Approval documents (and indication of equivalency if required in section 1)
4) Technical data for each piece of equipment including:
a. Range of operability
i. Flow rate
ii. Pressure
b. Discharge Characteristics
i. Pressure drop through equipment
ii. Metric discharge factor
iii. Discharge patterns
c. Corrosion resistance, corrosion protection specifications and service life
5) Maintenance and operation manuals
TRANSNET PIPELINES prepared by: SiVEST TPL25 – Fire Pump Technical Specification
Revision No. 01
13 July 2015 Page 6 of 7
Appendix A
Alcoseal 3-6
SiVEST Project Management Division 4 Pencarrow Crescent, La Lucia Ridge Office Estate, Umhlanga Rocks. 4320 PO Box 1899, Umhlanga Rocks. 4320 South Africa Tel + 27 31 581 1500 Fax +27 31 566 2375 Email [email protected] www.sivest.co.za Contact Person: Edward Standen Cell No.: 072 130 4968 Email: [email protected]