Kenya Project Status Dec. 2014
2
Entrance wall; entrance gate design
Entrance wall condition before
3
Entrance wall condition after
EATL Office
Office conditions before
5
The side view of the office block, the entrance view
off the Administration block and the door step
made of marble with painting works complete
Office Block: aluminum cladding complete; AC installation complete, entry staircase done.
6
Reception Area of Office Block - before
7
Office Block – Reception Area
8
Office Block – Reception Area
9
Office Block – Interior staircase - before
10
Office Block – Interior staircase; the
correction of the previous status
11
Office Partitions Inside Office Block - Before
12
Office Block – all interior works complete; tint, and repainting of the office walls
13
Office meeting room before
14
Office meeting room after
Loading Bay
Before.
16
Loading Bay: access and observation platform complete; loading headers & valve
installation complete
Loading Bay
17
Loading Bay
Before.
After.
18
Entry weigh bridge: Before
Entry weighbridge
19
Entry Weigh Bridge & Cabin – After; Painting is complete. Installation of side beams to guard
vehicle is complete.
Entry weighbridge
20
Boundary Wall before
21
Street Lights
Installation of the street lights is complete.
22
Boundary Wall After.
Painting of the boundary wall is complete
23
Generator Room/ Oil Tank: before
Generator Room
24
Generator Room with diesel tank on top; the road is ready.
Generator Room
25
Generator Room with diesel tank on top
Generator Room
26
Before: With no paint and testing of RO & boiler was not done; pipe lines to RO was not
complete
Boiler and RO Plant House
27
Boiler & RO installation complete; water line to boiler and RO complete; insulation of steam
line in progress.
Boiler and RO Plant House
28
Installed RO and Boiler; Heavy fuel and water overhead tanks complete.
Boiler and RO Plant House
29
Weigh bride cabin with internet and
telephone.
30
Wide view for both Genset, Boiler weighbridge 2 plus cabin and water tank. - before
31
Wide view for both Genset, Boiler weighbridge 2 plus cabin and water tank.
32
Before; the weighbridge was not installed
Public Wash Room
33
wash Hand basins, toilets, overhead tanks and shower heads completed
Public Wash Room
34
Pump House
35
Tank farm MCC installed successfully – was moved from the temporary location (transformer
room) to here permanently. Foundation of the pump house is complete and fitting of the Header.
Pump House
36
Entry Guard House Before
37
Entry Guard house – ready with telephone and internet cable for connecting CCTV screen or
desktop to monitor trucks way in and out.
Entry Guard House
38
Exit Guard house – Side View
Exit Guard House
39
Before.
KRA Office & Transformer room
40
Ready with both AC, Telephone and internet point.
KRA Office
41
Transformer Room
42
Tank 1:
Tanks
43
Tank 2: Before
Tanks
44
Tank 3: Before
Tanks
45
Tank 4: Before
Tanks
46
Tanks Side view
Tanks
47
Tanks Side view
Tanks
48
Water Tank & Chimney for the boiler: 100% complete
Tanks
49
Pipe installation at the water tank. Successfully installed
Piping
50
Fire hydrant and product line from tanks to
loading bay
Piping
51
Road Works 100% done
Roads
52
Fire hydrant pipe before
Fire Hydrant pipes before and water line
from the county 100% complete
53
Fire hydrant pipe after
54
Insulation of steam lines complete
Pipe Insulation
55
Pipe Insulation
56
Will be used to trap any oil spillage from the tanks
Dyke Wall
57
To direct water away from the compound
Water Drainage before
58
Water Drainage after
59
Fire Hydrant line from the back side of the tank farm is 75% complete.Water transfer line from Tank 1 to tank 7 is on-going.
60
Installation of the agitators as per the required recommendations is complete in
phase one.