project-specific guidelines scoping document for the ...€¦ · project-specific guidelines...
TRANSCRIPT
PROJECT-SPECIFIC GUIDELINES SCOPING DOCUMENT
FOR THE
PREPARATION OF AN ENVIRONMENTAL IMPACT STATEMENT
RECEIPT AND PROCESSING OF McARTHUR RIVER ORE AT THE McCLEAN
LAKE OPERATION
AREVA RESOURCES CANADA
These guidelines have been prepared to meet the requirements for Project-Specific Guidelines for
the Saskatchewan environmental impact assessment process under the Environmental
Assessment Act and for the federal environmental impact assessment process under the Canadian
Environmental Assessment Act. The document has been prepared by the Saskatchewan Ministry
of the Environment (MOE) and the Canadian Nuclear Safety Commission (CNSC) to assist
AREVA Resources Canada Incorporated with the environmental impact assessment of the
proposed Receipt and Processing of McArthur River Ore at the McClean Lake Operation Project.
Anyone wishing to obtain additional information or provide comments on any aspect of the
environmental assessment being conducted on the project may do so through the following MOE
or CNSC staff contacts:
Lynn Kelley, Environmental Assessment Branch, Saskatchewan Environment
3211 Albert Street, REGINA, SK. S4S 5W6
Phone: (306) 787-7147; Fax: (306) 787-0930; E-mail: [email protected]
or
Nicole Frigault, Canadian Nuclear Safety Commission
280 Slater Street, P.O. Box 1046, Station B
OTTAWA, ONT. K1P 5S9
Phone: (613) 995-7948; Fax: (613) 943-9652; E-mail: [email protected]
October 2010
E-DOC: 3539014 2
3
TABLE OF CONTENTS
1.0 INTRODUCTION ........................................................................................................................................... 4 2.0 ENVIRONMENTAL ASSESSMENT PROCESS .......................................................................................... 5
2.1 Federal and Provincial Cooperation in the Environmental Assessment .......................................................... 5 2.2 Requirement for Provincial Environmental Impact Assessment ...................................................................... 5 2.3 Federal Environmental Assessment ................................................................................................................. 6 2.3.1 Application of the CEAA ............................................................................................................................. 6
2.3.2 Federal Coordination ............................................................................................................................. 7
2.3.3 Scope of Project ............................................................................................................................. 7
2.3.4 Factors ............................................................................................................................. 8
2.4 Scope of the Factors ............................................................................................................................. 8 2.4.1 Spatial Boundaries ............................................................................................................................. 9
2.4.2 Temporal Boundaries ............................................................................................................................. 9
2.5 Determining the Type of Screening EA Process .............................................................................................. 9 3.0 Project-Specific Guidelines for the Environmental Impact Assessment for the proposed receipt and
Processing of MCArthur River ore at the The MCClean Lake Operation ...................................................................... 9 4.0 EIS EXECUTIVE SUMMARY .................................................................................................................... 11 5.0 PROJECT DESCRIPTION ........................................................................................................................... 11
5.1 Project Concept ........................................................................................................................... 11 5.2 Ore Loading, Transport, Receiving, Milling and Waste Management .......................................................... 12 5.2.1 Ore Loading and Transport ...............................................................................................................................
12
5.2.2 Ore Receiving and Milling ........................................................................................................................... 13 5.2.3 Waste Management ........................................................................................................................... 14
6.0 DESCRIPTION OF EXISTING ENVIRONMENT ..................................................................................... 16 6.1 Environmental Database ........................................................................................................................... 16 6.2 Climate, Meteorology and Air Quality .......................................................................................................... 17 6.3 Geology and Hydrogeology ........................................................................................................................... 17 6.4 Surface Hydrology and Water Quality .......................................................................................................... 17 6.5 Aquatic and Terrestrial Ecosystems .............................................................................................................. 17 6.6 Heritage Resources ........................................................................................................................... 18
8.0 PUBLIC AND OCCUPATIONAL HEALTH AND SAFETY ..................................................................... 18 9.0 PUBLIC AND ABORIGINAL INVOLVEMENT ........................................................................................ 19
9.1 Federal Process Requirements ..................................................................................................................... 20 9.2 Proponent Led Public Engagement .............................................................................................................. 20
10.0 IMPACT ASSESSMENT ............................................................................................................................. 21 10.1 General Concepts ........................................................................................................................... 21 10.2 Cumulative Impacts ........................................................................................................................... 22 10.3 Project-Specific Impacts ........................................................................................................................... 22 10.4 Effects of the Environment on the Project ..................................................................................................... 24
11.0 Mitigation and Contingency Planning ........................................................................................................... 24 12.0 MONITORING AND FOLLOW-UP PROGRAMS ..................................................................................... 25
12.1 Monitoring Program ........................................................................................................................... 25 12.2 Follow-Up Program ........................................................................................................................... 26
13.0 DECOMMISSIONING, RECLAMATION AND ABANDONMENT ......................................................... 26 13.1 Conceptual Decommissioning Plan ............................................................................................................... 26 13.2 Reclamation ........................................................................................................................... 26 13.3 Abandonment and Institutional Control......................................................................................................... 27
14.0 SUMMARY .................................................................................................................................................. 27 15.0 REFERENCES .............................................................................................................................................. 27 APPENDIX A - SIMPLE SCREENINGS DETERMINATION ................................................................................. 28 APPENDIX B - PUBLIC PARTICIPATION DETERMINATION ........................................................................... 31
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 4
1.0 INTRODUCTION
The McClean Lake Operation (McClean Lake) is an open-pit uranium mine and mill located in
northern Saskatchewan. The main facilities currently at McClean Lake are a series of completed
open pit mines near Sue Lake (Sue site), the JEB Mill and support facilities (the JEB site) located
near the previously mined-out JEB pit, which has been converted to the JEB Tailings
Management Facility (TMF), various supporting facilities for activities such as water treatment,
and site infrastructure such as roads, electricity distribution and the camp facilities. McClean
Lake is owned by AREVA Resources Canada Inc. (AREVA - 70%), Denison Mines Corp
(22.5%) and OURD Canada Co. Ltd. (7.5%). There is currently a lack of ore for processing at
the JEB Mill, as McClean Lake mining activities ceased in 2008, and high grade ore from Cigar
Lake originally scheduled to commence production in 2007 is unavailable. Cigar Lake has
experienced development delays and is now anticipated to send the first production of uranium
ore slurry (ore slurry) to the JEB Mill in 2013.
In November 2009, AREVA submitted a proposal (Reference 1) to the Saskatchewan Ministry of
Environment-Environmental Assessment Branch (MOE) and the Canadian Nuclear Safety
Commission (CNSC) to transport ore slurry from the McArthur River Mine (McArthur River) to
be milled at McClean Lake (the Project). The transportation of ore slurry would be conducted
using the existing public provincial highway system linking the operations. No construction
activities are associated with this proposal, as both McArthur River and McClean Lake have the
necessary infrastructure in place to support the proposal. This would keep the JEB Mill at
McClean Lake operational while it awaits longer-term ore feed from the nearby Cigar Lake
deposit.
McArthur River is a partnership between Cameco Corporation (operator and 69.805% owner)
and AREVA (30.195%). The McArthur River site consists of an underground mine, one full
service shaft and two ventilation shafts along with numerous surface facilities. This Project will
not result in any changes to infrastructure at McArthur River; it will simply enable AREVA to
process a portion of its share of McArthur River ore at McClean Lake, with the remainder
continuing to be processed at the Key Lake Mill, also a Cameco-AREVA partnership.
The scope of the project was revised in a letter from AREVA April 8, 2010 (Reference 2), and as
now defined by AREVA, the Project is for the production of up to 9 million lbs uranium ore
concentrate (U3O8) at McClean Lake from McArthur River Mine ore slurry. As proposed, this
will occur over a three-year period and will result in approximately two transportation units
leaving daily from McArthur River travelling to McClean Lake for 300 days during the 12
months in advance of successful production from Cigar Lake, and will continue into the first two
years of ramp up during initial production from Cigar Lake to ensure a continuous supply to
McClean Lake.
For the purposes of the environmental assessment (EA), AREVA is the operator of the Project.
AREVA has been informed that the project will require an EA under both The Environmental
Assessment Act (provincial, herein referred to as The Act) and the federal Canadian
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 5
Environmental Assessment Act (CEAA). AREVA is required to conduct an environmental
impact assessment (EIA) and prepare an environmental impact statement (EIS) for technical and
public review. This Project-Specific Guidelines Scoping Document (hereafter referred to as
Project-Specific Guidelines) has been developed with input from provincial and federal experts
to assist AREVA with the conduct of the EIA and the preparation of the EIS.
Several previous environmental assessments have been completed that are relevant to this project
(site characterization). These assessments include:
McClean Lake Mine and Mill (1993 Joint Panel) - the initial approval for the overall
McClean Lake Project, which included the JEB Mill and the overall waste management
system;
Cigar Lake Project (1997 Joint Panel) - the assessment and approval to process Cigar Lake
high grade ore slurry through the JEB Mill Expansion including deposition of tailings to the
JEB TMF & the assessment and approval of the activity of transporting high grade ore slurry
to McClean Lake; and
McArthur River (1997 Joint Panel) - Assessment and approval of the activity of transporting
high grade ore slurry from McArthur River Mine to the Key Lake Operation along highway
914.
The proposed project consists of activities that represent an incremental change to the overall
licensed facility, as the facility has already undergone an EA for the construction and operation of
a high grade circuit and ore receiving infrastructure. Although McArthur River ore has different
physical and chemical properties than ore from Cigar Lake, the milling process and associated
waste management is not anticipated to change.
2.0 ENVIRONMENTAL ASSESSMENT PROCESS
2.1 Federal and Provincial Cooperation in the Environmental Assessment
Under the Canada-Saskatchewan Agreement on Environmental Assessment Cooperation (2005)
federal and provincial EA processes, directed respectively by the CEAA and The Act, are
coordinated for projects with joint federal and provincial jurisdiction, where not limited by
individual statutory or process requirements of the respective processes. Information
requirements of both federal and provincial agencies have been included in these guidelines so
that the information in the EIS should be sufficient to address the environmental concerns of both
the Government of Saskatchewan and the Government of Canada.
Under the agreement, MOE is the lead agency and contact for the coordinated assessment
process. Working with MOE on this project is the CNSC which is the Federal Environmental
Assessment Coordinator (FEAC) and the Responsible Authority (RA) under CEAA.
2.2 Requirement for Provincial Environmental Impact Assessment
The proposal represents a change not consistent with the current EA approvals for McArthur
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 6
River and McClean Lake. Under Section 16(2) of The Act, upon notification of such a proposed
change, determination from the MOE is required. Ministerial decision options under section
16(2) of The Act are:
(a) approve the proposed change and impose any terms and conditions
that are considered advisable;
(b) refuse to approve the change in the development; or
(c) direct the proponent to seek approval for the proposed change in the
manner prescribed in sections 9 to 15 of The Act.
The MOE has determined that application of option (c) is appropriate. AREVA was notified of
this determination in a letter dated 22 March, 2010. As a consequence, AREVA is required to
conduct an EIA of the project and submit an EIS to the MOE.
Should the proposed project be found environmentally acceptable on the basis of the EIS, the
MOE would consider the proponent‟s applications for the necessary modification to the
approvals, permits, and licences that regulate operation of the facilities. The proponent would
also be expected to obtain all necessary approvals, permits, and licences from other regulatory
agencies, as applicable.
The province also has a constitutional obligation to consult with affected Aboriginal peoples
before any decision is made that may adversely impact the ability to successfully exercise Treaty
or Aboriginal rights, particularly the right to hunt, fish and trap. The province will utilize the
EIS, and any other relevant sources of information, to inform itself of the project and any
cumulative impacts of the development on traditional uses, and therefore on Treaty and
Aboriginal rights, to determine the level of provincial Crown consultation required. Mitigation
proposed within the EIS may provide accommodation for any rights affected by the proposed
project.
Consideration of these matters would take place in conjunction with the environmental
regulatory processes that follow the completion of the EA process and issuance of approvals,
licences, and permits that are required prior to the commencement of construction and operation
of a project.
2.3 Federal Environmental Assessment
2.3.1 Application of the CEAA
AREVA‟s proposal would require amending the existing Uranium Mine Operating Licence for
McClean Lake. The amendment of a licence is a power exercised under the authority set out in
subsection 24(2) of the Nuclear Safety and Control Act (NSCA). Subsection 24(2) is listed as a
„trigger‟ under the Law List Regulations established under the CEAA; therefore, there is a
„trigger‟ pursuant to paragraph 5(1)(d) of the CEAA for the proposed project.
The physical works for this proposal are the facilities and associated infrastructure related to the
receipt of ore slurry and the operation of the high grade ore circuit at McClean Lake. The receipt
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 7
and processing of McArthur River ore at McClean Lake is considered a proposed operation in
relation to the physical works. Therefore, the proposed undertakings constitute a „project‟ as
defined in section 2 of the CEAA.
There are no other CEAA „triggers‟, such as funding, being a proponent or disposing of an
interest in land to support the project, pursuant to subsection 5(1) of the CEAA, that involve the
CNSC.
The project is not of a type identified in the Comprehensive Study List Regulations of the CEAA.
Furthermore, the CNSC is not aware of any potential environmental effects and public concerns
to date associated with this project do not warrant referral to a mediator or review panel pursuant
to section 25 of the CEAA. Furthermore, there are no identified exclusions from the conduct of
an EA for this project pursuant to section 7 and Schedule 1 of the Exclusion List Regulations of
the CEAA, nor do any previous EAs apply.
Therefore, pursuant to subsection 18(1) of the CEAA, the CNSC is required to ensure the
conduct of a screening EA and the preparation of a screening report before the proposed licence
amendment can be considered by the CNSC in accordance with the NSCA. AREVA has been
notified of this requirement by the CNSC. The CNSC is delegating the conduct of the EA
technical studies pursuant to subsection 17(1) of the CEAA to AREVA.
2.3.2 Federal Coordination
The CNSC is the only RA for the project, and must ensure that the EA is conducted in
accordance with the provisions of the CEAA. This includes determining the scope of the project,
the factors to be considered in the assessment and the scope of those factors.
Pursuant to the Federal Coordination Regulations under the CEAA, the following federal
departments/agencies with an interest related to their mandate are participating in the review of
this project and, under the CEAA, are Federal Authorities (FAs) in relation to the project:
Fisheries and Oceans Canada (DFO); Environment Canada (EC); Natural Resources Canada
(NRCan); and Health Canada (HC).
2.3.3 Scope of Project
Pursuant to section 15 of CEAA, the Scope of the Project for the proposal to transport ore slurry
from McArthur River to be processed in the JEB Mill at McClean Lake includes:
Loading the ore slurry into IP-2 containers using the existing loadout infrastructure at
McArthur River;
Transport of the ore slurry in “B-train” units consisting of two trailers, each carrying
two IP-2 containers, along existing Provincial Highways 914, 165, 2, and 102/905
(revised scope includes approximately two transportation units leaving McArthur
River per day);
Off-loading the ore slurry at the JEB Mill using existing infrastructure;
Processing the ore at the JEB Mill using existing circuits (including the operation of
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 8
the high grade ore circuit);
Disposal of tailings generated by processing the McArthur River ore at the existing
JEB TMF; and
Management of waste water and other wastes associated with the operation of the JEB
Mill and disposal of tailings in accordance with existing processes and procedures.
No construction activities are associated with this project and milling of the ore slurry at
McClean Lake would be carried out under the operating limits and conditions of the existing
licence and licence documents.
2.3.4 Factors
The scope of the screening assessment under the CEAA must include all the factors identified in
paragraphs 16(l)(a) to (d) of the CEAA and, as provided for under paragraph 16(l)(e), any other
matter that the CNSC requires to be considered. Paragraphs 16(l) (a) to (d) require that the
following factors be included in the screening:
The environmental effects of the project, including the environmental effects of
malfunctions or accidents that may occur in connection with the project and any
cumulative environmental effects that are likely to result from the project in
combination with other projects or activities that have been or will be carried out;
The significance of the effects identified above;
Comments from the public that are received in accordance with the CEAA and its
regulations; and
Measures that are technically and economically feasible and that would mitigate any
significant adverse environmental effects of the project.
2.4 Scope of the Factors
The proposed scope of the factors to be considered by the RA in the screening EA includes the
following list of environmental components likely to be affected. Additional information on
these factors can be found in Section 6 of this document:
Climate, Meteorology and Air Quality;
Geology and Hydrogeology;
Surface Hydrology and Water Quality;
Aquatic and Terrestrial Ecosystems;
Heritage Resources; and
Socio-Economic Issues.
Both the spatial and temporal boundaries will remain flexible during the assessment to allow the
full extent of a likely environmental effect to be considered in the screening as further
information becomes available. For instance, should the results of modelling demonstrate that
there is dispersion of a contaminant that is likely to cause an environmental effect beyond the
boundaries identified, it will be taken into consideration in the assessment.
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 9
2.4.1 Spatial Boundaries
The spatial boundaries used in the EA encompass the geographical areas of the environment that
may be potentially affected by the project, or are relevant to the assessment of cumulative
environmental effects.
Site Study Area
The site study area is the proposed project footprint (i.e. where project activities would be
undertaken – including mine site infrastructure and provincial highways - such as loading
facilities at McArthur River, the JEB Mill, JEB TMF, other applicable McClean Lake facilities,
and applicable provincial highways).
Local Study Area
The local study area is where measurable changes to the environment resulting from the proposed
activities may be anticipated. The geographic boundary will depend on the factor being
considered e.g., a local study area defined for the aquatic environment will differ from that
defined for the atmospheric environment.
Regional Study Area
The regional study area is where the potential effects of this project may interact with the effects
of other projects (including abandoned, operating and/or proposed mines), resulting in the
potential for cumulative effects. The geographic boundary for the regional study areas are also
specific to the factor being considered.
2.4.2 Temporal Boundaries
The temporal boundaries will encompass the entire lifespan of the project (three years from the
start of operation).
2.5 Determining the Type of Screening EA Process
Criteria are used to determine whether screening EAs at the CNSC can follow a simple or
complex track; depending on the potential risk that the proposal would have on the environment
and the anticipated level of public interest. Taking into consideration the criteria and supporting
rationale (Appendix A), the proposed Project was determined to follow the “simple” screening
track. Although it was determined to be a simple screening, the province is the lead agency and
thus the CNSC will support and assist in all provincial public participation processes outlined in
section 9.0.
3.0 PROJECT-SPECIFIC GUIDELINES FOR THE ENVIRONMENTAL IMPACT
ASSESSMENT FOR THE PROPOSED RECEIPT AND PROCESSING OF MCARTHUR
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 10
RIVER ORE AT THE THE MCCLEAN LAKE OPERATION
These guidelines reflect the requirements and issues that have been raised by federal and
provincial officials and their respective acts and regulations regarding the project and identify the
information that should be included in the EIS.
AREVA‟s November 2009 Project Description and subsequent revision letter from April 2010,
noted the following points about the project:
The project would involve existing infrastructure for loading the IP-2 drop-proof slurry
transport containers at McArthur River and off-loading at the McClean Lake JEB Mill. No
construction is required;
The IP-2 units have been in satisfactory service for transport of ore slurry from McArthur
River to the Key Lake Mill for approximately 10 years;
The transport units will consist of truck and two trailers, each carrying two IP-2 containers
(approximately two transportation units leaving McArthur River per day);
The haul route will be from south of the McArthur River mine loadout along Provinical
Highway 914, past Key Lake Mill to the intersection with Provincial Highway 165 south of
Pinehouse Lake. Proceeding east and south on 165 to Highway 2, then north and northeast
on Highway 102 through LaRonge and Missinipe, and from a point a few kilometers west of
Southend north on Highway 905 to McClean Lake.;
Ore will be processed into yellowcake in the McClean Lake JEB Mill, which was designed to
accept ore grading up to 30% U3O8, and is permitted to accept ore from Cigar Lake, which is
similar in grade to McArthur River ore. No modifications to the mill circuits are
contemplated and ore will be processed using existing procedures and in accordance with
operating licence and conditions; and
Tailings will be disposed of in the existing JEB TMF with no changes to operational
procedures.
The EIA should focus on potential environmental impacts which may result from the proposed
hauling of ore slurry from McArthur River to McClean Lake. Processing of the ore at the
McClean Lake JEB Mill, and tailings disposal at the JEB TMF are minor components of the
project as no changes to the licenced operations are anticipated. Information provided in the EIS
which is related to the potential impacts of the ore haul and processing should be complete and in
sufficient detail to allow assessment of the potential impacts. In the event that the project
receives EA approval, the regulatory processes that follow the completion of the EA process and
issue the approvals, licences, and permits that are required prior to the commencement of
operation may require more detailed technical information.
Existing information on environmental parameters which will not be affected by the proposed
project, or information which is cited to provide context for the discussion of potential impacts,
may be referenced and provided in summary form.
These guidelines should not be considered as either exhaustive or restrictive, as concerns other
than those already identified could arise during the investigations associated with the EIA.
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 11
Reference to the MOE General Guidelines for Conducting an Environmental Impact Assessment
and to guidance materials provided by the Canadian Environmental Assessment Agency
(http://www.ceaa-acee.gc.ca/012/newguidance_e.htm ) is recommended. In addition, MOE and
the CNSC are prepared to provide advice and assistance throughout the EIA with regard to the
identification of environmental concerns and appropriate assessment methodologies.
4.0 EIS EXECUTIVE SUMMARY
An executive summary of the EIS is required. It should briefly summarize and cross-reference
the EIS under the following topic areas:
Description of the project;
Purpose of and need for the project;
Environmental effects of the project, including the potential
spills/malfunctions/accidents;
Any cumulative environmental effects that are likely to result from the project in
combination with other projects or activities that have been or will be carried out;
Technically and economically feasible mitigation measures;
The significance of the environmental impacts; and
Comments from the public and AREVA‟s responses.
The executive summary, which can be under separate cover, should avoid the use of technical
terms and jargon. To enhance involvement of northern Saskatchewan residents, First Nations
and Métis in the public participation process, the executive summary should be translated into
each aboriginal language, Cree and Dené, and made accessible in video and/or audio form.
5.0 PROJECT DESCRIPTION
5.1 Project Concept
The EIS should provide a comprehensive description of the proposed project, including the
purpose of and need for the project. A description of how current operations will change as a
result of the implementation of the proposed project, if approved, is needed so that the changes
that would occur at McArthur River and McClean Lake, and along the proposed haul route, and
the potential environmental impacts of the project, can be placed in context with the existing
environmental conditions.
All stages of the project, such as loading, transporting, off-loading, processing, tailings and waste
disposal, and any associated maintenance should be described. The EIS should clearly identify
where the proposed project differs from the existing approvals at McArthur River and McClean
Lake. This information is to be supported by technical data in sufficient detail and scope to
determine whether the potential environmental impacts of the proposed project differ from those
of the existing licensed activities. Any differences should be assessed for significance.
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 12
Generally, the EIS should include the following information:
Ownership of the project and project components;
Location, using local and regional maps with identifiable features;
Status and map of surface lease and active mineral dispositions relevant to the project;
The need for the project;
Description of proposed project (including project life, dimensions, plans);
Alternative means of accomplishing the project. A recently proposed road link between
McArthur River and Cigar Lake should be discussed, if applicable (including AREVA‟s
plans to start using this new road as soon as it becomes available);
Contingency plans if the Cigar Lake operation does not begin production as currently
anticipated in 2013;
Materials and power requirements;
Sourcing of materials;
Anticipated schedule for implementation;
Estimated manpower and skill requirements;
Conventional/radiological occupational health and safety considerations;
Emergency measures/contingency plans and procedures;
Technical issues and new technologies specific to the project;
A description of the potentially affected environment;
Potential contaminant releases due to accidental spills of ore slurry along the haul road
and their impact to human health and the environment; and
Technically and economically feasible monitoring and mitigation measures.
5.2 Ore Loading, Transport, Receiving, Milling and Waste Management
5.2.1 Ore Loading and Transport
The EIS should contain a description of the procedures necessary to transport ore slurry from
McArthur River to the McClean Lake JEB Mill. It is noted that the project description is
thorough and includes much of this information and may be sufficient for the purpose of the EIS.
This description should include:
Loading procedures at the existing McArthur River loading facility;
Radiation protection and analysis of expected radiation exposures of drivers of ore
slurry trucks;
A description of emergency response plans for on-road incidents, including
emergency response team location(s) or mustering point(s), worst-case response
times, procedures for emergency road closure, procedures for protection of water
supplies, and interaction with or assistance from local fire departments. Exposure
projections associated with emergency conditions should reference the maximum
uranium concentrations anticipated;
Detailed discussion of past experience using IP-2 containers to haul ore slurry
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 13
between the McArthur River Mine and Key Lake Mill, including frequency and
impact of major and minor incidents;
Details on road standards and procedures followed for past projects compared to
proposed standards and procedures to be followed for this project In particular, the
conditions of the portions of the haul route maintained by Cameco (914 extension), on
which the IP-2 units have traveled for more than 10 years should be compared to the
remainder of the haul route, with respect to general road conditions, surface stability,
safe speeds etc.;
Details on driver training, including radiation and emergency response training;
The trip is estimated to take 17 hours each way. The EIS should provide information
on the number of drivers per unit and scheduling, including assurance of appropriate
rest and information on the staging of transport, including details regarding fuel stop
requirements and allowances for in-trip vehicle maintenance;
Details on driver protection including the driver‟s radiation exposure, the need for
radiation protection for the cab if the driver remains in the cab for rest periods or
unplanned delays, including but not limited to vehicle breakdown and winter storm,
and comparison of driver exposure levels compared to those for the haul between
McArthur River and Key Lake; and
Procedures to be followed when winter storms, road washouts, forest fires etc. make
all or part of the route impassable.
The EIS should contain a comprehensive description of the ore haul with reference to current
regulatory standards for transportation of radioactive substances. The description should discuss:
Container design and safety criteria;
Trucks, haul cycles, and safety procedures, including traffic control measures for the
route, dust control, and severe weather driving restrictions;
Radiological and non-radiological occupational health and safety procedures and
training for truck drivers;
Potential for vehicle and wildlife collisions;
Noise disturbance effects on wildlife distribution and habitat use;
Contingency and emergency management planning for the prevention of, and
response to, accidents and ore spills; and
Any additional safety procedures or spill control measures required for stream
crossing sites.
5.2.2 Ore Receiving and Milling
Currently, McClean Lake has only been assessed and approved to process high grade ore from
Cameco‟s Cigar Lake Mine. Both the Cigar Lake ore deposit and the McArthur River ore
deposit are high-grade deposits. The 1995 Cigar Lake EIS provided details on off-loading of ore
slurry and processing of high-grade uranium ore at the JEB Mill. Because uranium grades and
physical properties of ore from Cigar Lake and McArthur River are similar, the proponent
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 14
anticipates that receipt and processing of ore from McArthur River will be carried out in a
manner very similar to the procedures anticipated in the 1995 EIS for receipt and processing of
Cigar Lake ore. While reference may be made to the 1995 document, the EIS for the current
project should clearly identify any changes in process, equipment, or procedures needed to
process ore from McArthur River as opposed to Cigar Lake.
Information provided in the EIS should address:
Off-loading procedures at the JEB Mill off-load facility;
Container washing procedures, including treatment and disposal of wash water;
Ore storage and blending procedures;
A comparison of the physical and chemical properties of Cigar Lake ore and
McArthur River ore, including previously assessed, and if identified, new
contaminants of concern;
Proposed changes to mill practices necessitated by chemical or physical
characteristics of the McArthur River ore;
Implications for current environmental and/or worker health and safety as well as
radiation protection programs; and
Expected doses to workers from receiving, off-loading and milling ore slurry from
McArthur River.
5.2.3 Waste Management
The EIS should include detailed information regarding any changes in quality, quantity, and
potential environmental impacts associated with management programs for all wastes which
would be generated, specifying the waste streams that will remain on-site and the waste streams
that will be moved to another facility relative to past McClean Lake operations and planned for
Cigar Lake. Any anticipated change in mill processing that may be necessary if levels of
contaminants of concern (e.g. Cu, Sn, Ni, As, Co, Cd) are higher in the McArthur River ore than
in the Cigar Lake ore, should be discussed, including any long-term significant impacts to the
JEB TMF.
The EIS should focus on changes at McClean Lake necessitated by the project. Relevant
information related to any potential changes to the treatment of liquid effluent, sewage, surface
drainage, atmospheric emissions, and tailings disposal management should be addressed.
Tailings Disposal
The project proposal states that no changes to the existing tailings preparation process in the JEB
Mill or to the JEB TMF are required to accommodate the milling of the McArthur River ore at
McClean Lake. However, for the purposes of the EA the EIS should provide the basis for the
statement in the project proposal including:
Evaluation of impacts of this project on the capacity of the JEB TMF;
The yearly and cumulative expected volumes of tailings to be generated from this
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 15
project; and
Contingency plans for unexpected variation in volume, hydraulic performance, and
predicted geochemical properties of the tailings.
Any anticipated changes resulting from the proposed project related to environmental protection
procedures during operations, water balance, and containment of potential contaminants in the
tailings disposal system following reclamation and decommissioning should be described.
Liquid Effluent
Any anticipated changes in water balances should be provided. Any water anticipated to not meet
Saskatchewan’s Mineral Industry Environmental Protection Regulation limits, the Metal Mining
Effluent Regulations (MMER) of the federal Fisheries Act and/or CNSC licence requirements
will require treatment prior to release.
The EIS should demonstrate that the project will not lead to contaminants and loadings in aquatic
receiving systems in excess of those predicted from currently licensed activities. The EIS should
identify locations (e.g., Universal Transverse Mercators (UTMs)) where objectives/guidelines are
not met to provide an indication of the potential migration of effects beyond those expected from
currently licensed activities.
The EIS should address any anticipated changes to:
Quantity and quality of liquid effluents;
Treatment processes, including total loadings for treatment and process chemicals;
Quantity, quality and final disposal of slimes, sludges and precipitates from sumps,
sedimentation ponds and treated water holding ponds (monitoring ponds) and facility
features and handling procedures to minimize spills and environmental effects from
disposal; and
Anticipated radiation dose to any human receptor resulting from radiological
contaminants in the liquid effluents.
Atmospheric Emissions
The EIS should address any anticipated changes to:
Quality and quantity of all airborne emissions (e.g., SOx, NOx, dust, radon and
radionuclides) emanating from the mill;
Operational monitoring programs for air quality parameters; and
Anticipated radiation dose to any human receptor resulting from radiological
contaminants in atmospheric emissions.
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 16
6.0 DESCRIPTION OF EXISTING ENVIRONMENT
6.1 Environmental Database
The project will be carried out over several locations, including the McArthur River ore loading
facility, Provincial Highways 914, 165, 2, and 102/905, the JEB Mill, JEB TMF, and associated
infrastructure and other waste management systems at McClean Lake.
The EIS should contain a description, in terms of local and regional scales, of the existing
environment which may be reasonably affected by the transporting and accident scenarios along
the haul route. A similar description should be provided for the receiving and processing of
McArthur River ore slurry at McClean Lake and all associated processes, including waste
management, and the extent that changes are anticipated as a result of the project.
The database should include a complete and accurate description of the current status of those
environmental parameters that are regulated by federal and provincial agencies at McClean Lake
that may be affected by the project.
All environmental data that are included in the EIS should be collected using accepted
methodologies and be available to the MOE and the CNSC. These methodologies should be
consistent in order to allow comparative use of the data and facilitate ecosystem management.
Engineering or geoscience components of the EIA should be conducted in accordance with the
Engineering and Geoscience Professions Act of Saskatchewan.
Should changes/additions to the existing database be needed as a result of the project, the
database in the EIS should provide a sound basis for not only the EIA of the project, but also the
operational environmental monitoring and post-operational decommissioning, reclamation, and
abandonment. The environmental data should contribute to, and be in a form compatible with,
the existing environmental effects monitoring database for the assessment of potential effects on
a regional scale.
Therefore, the data in the EIS should satisfy the following criteria:
(i) That the baseline data accurately describe the existing environment that may be
affected by the project as proposed;
(ii) Any new data should provide a sound basis for comparative monitoring and the
development of sound decommissioning, reclamation and abandonment
procedures. This would include the establishment of reference and potential
exposure stations that will allow for the assessment of any impacts that may occur
as a result of the project; and
(iii) That the EIS be self-supporting, in terms of data availability and presentation.
Existing data on environmental parameters that will not be affected by the proposed project, but
are cited to provide context for the discussion of potential impacts, may be referenced or
provided in summary form.
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 17
6.2 Climate, Meteorology and Air Quality
The current databases of climatic, meteorological, and air quality information, including dust,
radon and gamma radiation data for McClean Lake should be referenced. If available, similar
information from any meteorological stations along the haul route should be referenced. Any use
of off-site data must be thoroughly discussed and qualified with an understanding of local and
regional variability and the geographic locations of on-site and off-site meteorological stations.
Specific information regarding emissions from haul trucks over the course of the project and
implications of the additional traffic load that this project would mean to the proposed haul route
should be included.
6.3 Geology and Hydrogeology
The EIS should contain a description of the regional geology and hydrogeology of the McArthur
River and McClean Lake sites and the haul route sufficient to discuss the implications of the
proposed project. Relevant information on surficial geology/geomorphology should be discussed
in terms of any potential effects on the project (e.g., ground stability, slumping, and acid/metal
release).
Geological features such as faults, fractures, shears, seismic activity or hydrogeologic
characteristics (e.g., artesian conditions), that may have an impact on the project should be
identified and their significance described.
The EIS should discuss any anticipated changes in the current hydrologic conditions, where
appropriate e.g., tailing storage and settling ponds. Any anticipated changes in quantity, quality,
and flow rates of groundwater likely to be affected by the proposed project should be provided.
6.4 Surface Hydrology and Water Quality
Regional scale data on watershed areas, drainage patterns, characteristics of water bodies
(streams, rivers, lakes or ponds), flow rates, bathymetry, water volume (lakes and ponds), and
water quality should be included to a level of detail sufficient to assess consequences of potential
accidents or malfunctions. Particular attention should be paid to community water intakes from
surface water bodies along the haul route, including the number and locations of water intakes,
distance from the haul route, quality and quantity of intake waters, and any other surface water
that may interact with water intakes through groundwater.
6.5 Aquatic and Terrestrial Ecosystems
The EIS should provide relevant information on aquatic and terrestrial ecology along the haul
route to the extent that is required to assess consequences of potential accidents or malfunctions.
Information on aquatic and terrestrial species designated as “rare”, “endangered”, “threatened”
and “species of special concern” under the Species at Risk Act and the Saskatchewan Wildlife Act
should be included. Refer to the Committee on the Status of Endangered Wildlife in Canada
(COSEWIC) - www.cosewic.gc.ca. Relevant data on potentially affected soil and vegetation,
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 18
including lichen, rare and endangered flora located along associated roads and rights-of-way
should be described. Analyses of selected soil and vegetation parameters should provide
information to describe any changes that may result from an accidental spill/malfunction.
The EIS should identify the species within the terrestrial and aquatic environments that are
important components of food chains leading to, and used by, people living in the region. Any
anticipated changes to the status of these species in the impact area in regards to their relative
abundance and any measured levels of contaminants in their tissues, especially heavy metals and
radionuclides, should be documented.
6.6 Heritage Resources
In the EIS, the proponent should note that following their review of the proposal, the Heritage
Resources Branch of the Saskatchewan Ministry of Tourism, Parks, Culture and Sport has
indicated that since no new construction is required, they see no potential impact to heritage
resources. The proponent should confirm these conclusions with local First Nations and Métis
during the conduct of the EIA.
7.0 SOCIO-ECONOMIC ISSUES
The EIS should provide a description of employment, skill levels, training/retraining, jobs
targeted for Northerners and contractor opportunities associated with the project. Commitments
to potential local, regional, and Saskatchewan suppliers should be noted.
It is noted that, in the proposal, AREVA re-affirms its commitment to hiring northern contractors
and creating opportunities for northern businesses, thus ensuring further economic benefits for
local people. Any existing or new measures to be taken in order for AREVA to fulfill this
commitment should be described.
8.0 PUBLIC AND OCCUPATIONAL HEALTH AND SAFETY
The EIS should address both conventional and radiological public and worker health and safety.
The EIS documentation should include:
Calculations of annual radiation exposures to truck drivers, loadout and off-load employees;
Calculations of annual radiation exposures to residents of the communities along the haul
routes;
Potential non-radionuclide hazards to workers in airborne dust and programs that are, or will
be in place to monitor these hazards;
Potential radiation doses to mill workers as a result of any anticipated changes to current
milling operations;
A statement of any radiological design changes that will be required as a result of this project;
Details on how the current source term throughout the facility will be affected as a result of
this project; and
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 19
Any changes as a result of the proposed project to engineered controls, programs, Action
Levels, and a Radiation Protection Code of Practice proposed to control worker radiation
doses and intake of radioactive prescribed substances.
The EIS should discuss any anticipated changes to existing radiation protection programs
including changes to the routine radiological monitoring schedule, changes to the dosimetry
monitoring strategy, changes in radioactive contamination control programs, and changes in
training programs. The EIS should discuss the development of any additional training modules
for environmental instrumentation, protection, and awareness and how AREVA‟s commitment to
the ALARA (As Low As Reasonably Achievable) principle of radiation protection will be
implemented.
Programs should meet the regulatory requirements of The Occupational Health and Safety Act,
The Occupational Health and Safety Regulations, The Saskatchewan Mines Regulations (2003)
and the NSCA Radiation Protection Regulations.
The EIS should include information on worker health and safety as a result of malfunctions and
accidents.
9.0 PUBLIC AND ABORIGINAL INVOLVEMENT
Local and regional residents and interested organizations should be fully informed of the
proposal to transport ore from McArthur River to McClean Lake. Potentially affected Aboriginal
peoples must be provided with the information they need with respect to the project and its
potential impacts. The proponent must ensure that it engages with Aboriginal peoples who may
be affected by the project and who have asserted or established Aboriginal rights, Aboriginal title
or treaty rights. It is noted that, in the proposal, AREVA commits to a stakeholder engagement
program as part of the EA.
The EIS should describe the proponent‟s program for consultation with northern residents,
residents from First Nations, Métis and other northern communities. Public involvement and any
concerns raised should be documented in the EIS and their significance evaluated. The
documentation should provide information regarding the demographics of the communities that
were part of the public involvement program and the level of consultation that took place with
these communities.
The program should promote a broader understanding of both the potential impacts of the project
and the monitoring programs and results. Efforts should be made to involve the public in issue
identification (e.g., contribution of traditional knowledge to the determination of Valued
Ecosystem Components (VECs)), and problem resolution. Elements of the plans for public
information/engagement should provide a basis for discussion of enhancement of regional
business and employment opportunities. This information should include a concise description
of AREVA‟s public engagement program.
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 20
As interest in the proposed project may extend beyond the project area, AREVA should be
prepared to provide project information to, and address issues identified by, persons residing
outside of the project area.
MOE will use the information provided by the proponent on their stakeholder engagement
efforts, along with the information provided regarding the potential of the proposed activities to
affect Treaty or Aboriginal rights to inform its decisions regarding Crown Duty to Consult
obligations with respect to the proposal.
9.1 Federal Process Requirements
A public registry for the project assessment has been established. This includes identification of
the project assessment in the Canadian Environmental Assessment Registry (CEAR), which can
be accessed on the Internet web site of the agency (www.ceaa.gc.ca). The CEAR reference
number for the project is 10-01-53814.
In accordance with section 18(3) of the CEAA, the CNSC is responsible for determining the need
for and level of public participation for a project. Based on the public participation criteria and
rationale (Appendix B), it was determined that the proposed project requires public participation.
The CNSC will perform the following public participation activities:
Post notice of commencement of EA on both the CNSC website and the CEAR within 2
weeks of a determination (completed);
Post notice of availability of the draft Project-Specific Guidelines Scoping Document and
allow a 30-day review and comment period (completed); and,
Post notice of availability of draft EA Screening Report and allow a 30-day review and
comment period.
As the MOE is the lead for this EA, the project is also subject to the provincial public
participation process. The CNSC will support the provincially-led public review of the EA
Project-Specific Guidelines, EIS, and Technical Review Comments by posting a notice of
availability of all documents on the CNSC website and the CEAR. Additionally, the public and
Aboriginal groups will be provided an opportunity to comment on the CNSC EA Screening
Report. The CNSC and MOE may consider a joint public review period for the EIS, Technical
Review Comments, and EA Screening Report.
The CNSC is satisfied that the public participation processes to be implemented by the proponent
and the province with the support of the CNSC will be sufficient. The public participation
process will provide the public with a variety of opportunities to be informed and provide input
at all stages of the study. The process will also allow the public to react to proposals in order to
influence recommendations and decisions and to be informed of all decisions.
9.2 Proponent Led Public Engagement
Regional residents or organizations should be fully informed of the proposed project. It is stated
in the project proposal that AREVA intends to carry out the following public engagement
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 21
activities:
Identify interested or „key‟ stakeholders, and their communication and information needs.
A stakeholder list will be developed and maintained throughout the EA and regulatory
processes;
Inform all stakeholders about the progress of the project, with respect to milestones and
key activities, and the means of raising questions and comments;
Provide opportunities for stakeholders to exchange information, and identify and discuss
any concerns they may have;
Document and maintain a record of all communication processes and outcomes;
Identify and document issues, comments and concerns raised by stakeholders related to
the project and AREVA in general, as they arise;
Develop and document all appropriate responses to address stakeholder comments,
issues, concerns and questions as they arise; and
Ensure comments and responses are available to the public through the reporting
requirements associated with the EA and regulatory process to illustrate how issues have
been addressed through the various regulatory processes.
10.0 IMPACT ASSESSMENT
10.1 General Concepts
The EIA process must address the factors identified in the introduction and provide the
information necessary to determine the likelihood of significant adverse effects and whether the
benefits to the Province of the proposed activity justify the environmental costs.
The environmental effects of the project, and their significance, must be described, including the
environmental effects of malfunctions or accidents that may occur in connection with the project.
Any cumulative environmental effects that are likely to result from the project in combination
with other projects or activities that have been, or will be, carried out must be evaluated.
Residual environmental impacts which cannot be mitigated during operation and
decommissioning should be identified and their significance discussed. Environmental effects
are defined in CEAA as:
(a) any change that the project may cause in the environment, including any change it
may cause to a listed wildlife species, its critical habitat or the residences of individuals of that
species, as those terns are defined in subsection 2(1) of the Species at Rick Act,
(b) any effect of any such change referred to in paragraph (a) on
(i) health and socio-economic conditions,
(ii) physical and cultural heritage,
(iii) the current use of lands and resources for traditional purposes by aboriginal
persons, or
(iv) any structure, site or thing that is of historical, archaeological, paleontological
or architectural significance, or
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 22
(c) any change to the project that may be caused by the environment, whether any such
change occurs within or outside Canada.
10.2 Cumulative Impacts
The EIS should discuss whether existing environmental conditions, including other uranium
developments in the area, such as the Midwest and Caribou projects, will influence the project.
The discussion should address whether the project-specific effects of the proposed project,
combined with the impacts from existing and planned developments in the region will result in,
or contribute to, any regional or cumulative environmental effects.
The Canadian Environmental Assessment Agency guidance documents Operational Policy
Statement OPS-EPO/3-1999 Addressing Cumulative Environmental Effects Under the Canadian
Environmental Assessment Act, and Cumulative Effects Assessment Practitioners Guide should
also be consulted regarding the scope of cumulative impacts to be evaluated in the EIS.
10.3 Project-Specific Impacts
The EIS should document and evaluate the significance of any negative impacts of the project on
the environment. To provide context, the EIS should discuss whether historic exploration and
industrial development activities have influenced the current status of the environment, fisheries,
wildlife, or resource use at McArthur River or McClean Lake or along the proposed haul route.
The EIS should focus on the significance of incremental effects resulting from changes to the
currently licensed activities needed to support the project.
Impact predictions should be categorized according to defined criteria, and should be as specific
and quantitative as possible.
The EIS should assess the potential effects of any incremental environmental changes on human
health or the use of lands, waters and resources for traditional purposes by aboriginal persons and
on the quality of any country foods that may be harvested. Potential entry of contaminants of
concern in liquid and airborne waste streams, (e.g., radionuclides, heavy metals), into food chains
and the terrestrial or aquatic environment should be described to the extent that they are above
levels predicted for currently licensed activities.
The EIS should discuss the proposed project with respect to greenhouse gases and other climate
change parameters.
The quantity and quality of treated effluents are critical issues for environmental protection. The
EIS should address any changes anticipated in effluent quality or quantity at McArthur River
and/or McClean Lake as a result of the project. If the project is anticipated to change the
currently licensed activities and/or operating limits and conditions, the EIS should include the
following:
Any anticipated incremental changes in quality and quantity of effluents to be released to
the environment as a result of the project, and their contribution to current assessments of
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 23
waste loadings and dispersion in the aquatic receiving system(s). The dispersion of the
effluent plume should be used to identify potential exposure sites for monitoring. The
EIS should identify where contaminant levels would, and would not, meet Saskatchewan
Surface Water Quality Objectives and Canadian Water Quality Guidelines downstream
from the facility and provide an evaluation of any environmental impacts;
Any changes to existing points for control, monitoring and final discharge to the
environment;
Any anticipated incremental changes to short and long term aquatic environmental effects
of continued loading of chemical parameters on receiving waters and predicted mixing
effect zone as a result of the project;
An estimate of the spatial extent of sediment contamination in a worst case scenario due
to an accident and/or malfunction, by providing suspended particle concentrations and
water to particle partitioning coefficients for each contaminant, and the range of settling
velocities ascribed to suspended particles in each of the receiving water bodies identified;
Potential incremental impacts to benthic invertebrates, fish, wildlife and plants based on
contaminant transport modeling results;
Use of abiotic and biotic monitoring programs in evaluating the aquatic and terrestrial
environmental effects of this project. This should include the selection of potential
reference and exposure locations;
To the extent that they are relevant to the assessment of potential incremental
environmental effects, results of any studies currently being undertaken of in-lake and in-
stream water quality/sediment conditions and biota, and the merits of developing
procedures, including biological or statistical indices/measures, for the tracking of
changes to aquatic health;
Predictions of maximum contaminant concentrations and total contaminant loadings to
streams or other water bodies in worst case scenario of an accidental/malfunction ore spill
along the haul route; and
Potential impacts to water quality, sediment quality, fish and fish habitats in streams and
other water bodies in a worst case scenario due to an accidental/malfunction ore spill
along the haul route.
Potential impacts at any stream crossing location along access roads should be identified and
appropriate mitigative measures proposed. The Saskatchewan Watershed Authority (SWA)
noted in their review of the project proposal that the trucks will cross more than two hundred
streams, pass by nearly four hundred other water bodies and pass through several communities.
The assessment of risk as a consequence of an accidental ore spill should consider spills in or
near communities, community water sources, and water bodies in general.
SWA also noted several licensed surface and groundwater projects along the haul route, and the
potential for unlicensed water withdrawals. The proponent should contact Bart Oegema at 306-
694-3957, SWA‟s contact for emergency planning, to obtain existing receptor survey information
for the corridor on either side of the proposed haul route.
Contaminant loadings and predictions of contaminant concentrations to the terrestrial
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 24
environment adjacent to the haul route in a worst case scenario (i.e. spill to a wetland or other
known sensitive habitat within 100 m of the haul route with known sensitive terrestrial receptors
of concern, such as a rare amphibian, plant, bird and mammal) as a consequence of an ore spill
due to malfunctions/accidents, should be provided. Seasonal scenarios (i.e. spring, summer, fall
and winter) and effects to terrestrial receptors and emergency clean-up techniques should be
addressed.
The potential interaction of an accidental ore spill with human receptors through direct contact
(i.e. inhalation, skin contact) and indirect contact (i.e. ingestion of impacted drinking water
(groundwater and surface water sources), country foods) both within existing communities and
individual residences along the haul route and as a consequence of chancing upon an accident in
remote sections of the haul route should be provided.
The potential impacts from all contaminant sources should be combined to provide a cumulative
impact assessment. If the project is anticipated to change currently licensed activities or
operating limits and conditions, an assessment of post-decommissioning contaminant loadings to
the environment should be discussed in the context of criteria for the design of operational
monitoring programs and decommissioning, reclamation, and abandonment planning.
10.4 Effects of the Environment on the Project
The assessment must also take into account how the environment could adversely affect the
project; for example severe weather. Guidance can be found on the CEAA website: The
Federal-Provincial-Territorial Committee on Climate Change and Environmental Assessment
2003. Incorporating Climate Change Considerations in Environmental Assessment: General
Guidance for Practitioners http://www.ceaa-acee.gc.ca/default.asp?lang=En&n=A41F45C5-1
This part of the assessment will be conducted in a step-wise fashion, similar to that described for
the foregoing assessment of the project effects. The possible important interactions between the
natural hazards and the project will be first identified, followed by an assessment of the effects of
those interactions, the available mitigation measures, and the significance of any remaining likely
adverse effects on the project.
11.0 MITIGATION AND CONTINGENCY PLANNING
The EIS must identify and describe technically and economically feasible mitigation measures
that may be applied to each likely adverse environmental effect. All mitigation measures
described throughout the EIS must be documented in the mitigation section.
The EIS should also document mitigation and contingency plans which would be implemented in
the event of any potential containment failures, spills, malfunctions, accidents or inadvertent
waste releases associated with the project. The proponent should identify commitments for
adaptive management measures to be implemented should monitoring or follow-up programs
identify unreasonable or unforeseen environmental impacts.
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 25
Any changes to mitigation, monitoring and conceptual de-commissioning at McArthur River
and/or McClean Lake should be discussed. The EIS should discuss any changes necessary to
existing adaptive management, mitigation measures and current contingency planning at
McClean Lake to manage activities associated with the project.
Although the detailed mitigation and contingency plans would be designed in consultation with
regulatory agencies through regulatory processes and would be subject to periodic review during
operations, the EIS should document mitigation and contingency plans which would be
implemented in the event of containment failures, spills, malfunctions, accidents, or inadvertent
waste releases.
If needed as a result of modification to the currently licensed activities, a hazard analysis or other
risk-based approach should be used to identify situations where mitigative measures may be
needed. If an engineering or administrative control solution is not technically or economically
feasible, then a contingency plan should be developed.
12.0 MONITORING AND FOLLOW-UP PROGRAMS
As a result of the various EA approvals in conjunction with Federal and Provincial operating
licences, both McArthur River and McClean Lake initiated and maintain monitoring and/or EA
follow-up programs that are subject to regular reporting requirements.
The EIS should identify the need for, and requirements of, any follow-up assessment or
monitoring programs beyond those currently in place as they relate to the proposed project.
12.1 Monitoring Program
The EIS should discuss any changes to the existing monitoring programs at McArthur River and
McClean Lake as a result of the project, including:
Monitoring programs for any potential environmental impacts, including potential
contaminant loadings to plant and animal species, that are considered relevant VECs;
Monitoring programs to confirm ground water and surface water quality in the vicinity of
the JEB TMF;
Commitments for operational response procedures to be followed should monitoring
programs identify environmental changes or unforeseen/unacceptable impacts (e.g.,
changes to mill process or effluent treatment); and
The Tailings Optimization and Validation Program (TOVP) for the JEB, which occurs
every 5 years.
Monitoring should not only ensure compliance with regulatory requirements but should also
allow the systematic audit of the EIA process, specifically the accuracy of predictions and the
adequacy of proposed mitigation measures. The monitoring programs, in verifying the
environmental impact predictions, should confirm the design criteria for reclamation and
abandonment objectives and planning procedures.
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 26
If changes to the existing monitoring programs are required, the program should incorporate and
build upon the work undertaken in fulfillment of the environmental effects monitoring
requirements of the Metal Mining Effluent Regulations of the federal Fisheries Act.
Development of monitoring programs should be made with reference to Saskatchewan
Environment‟s guidelines document: “Environmental Monitoring Guidelines (For Operational
Monitoring at Uranium and Gold Mining and Milling Operations in Saskatchewan) and to the
Saskatchewan Environment and Public Safety, Mines Pollution Control Branch, March 31,
1989".
12.2 Follow-Up Program
If changes to the existing federal follow-up program are required as a result of the project, the
program should include a detailed scope of the change in program together with schedule and
reporting milestones. Changes to the existing follow-up program plan should be described in the
EIS in sufficient detail to allow independent judgement as to the likelihood that it will deliver the
type, quantity and quality of information required to reliably verify predicted effects (or absence
of them), confirm EIS assumptions and confirm effectiveness of mitigation. The EIS should
include a description of the objectives of the follow-up program, the elements of the plan
required to achieve the objectives, the implementation plan and reporting commitments.
The CNSC would ensure the implementation of any required follow-up program through the
licensing and compliance process. The CEAA follow-up may be a component of the larger
monitoring program, but should be specifically defined and presented.
13.0 DECOMMISSIONING, RECLAMATION AND ABANDONMENT
Although changes to the detailed plans for decommissioning, reclamation, and abandonment
would be developed in consultation with regulatory agencies through regulatory processes, and
would be subject to periodic review during operations, the EIS should provide descriptions of
any changes to these plans resulting from the project.
13.1 Conceptual Decommissioning Plan
The EIS should briefly describe the existing conceptual decommissioning plans for McArthur
River and McClean Lake, and outline any changes necessitated by the proposed project.
13.2 Reclamation
Reclamation planning concepts which should be included in the EIS are described in MOE‟s
Northern Mine Decommissioning and Reclamation Guidelines, EPB 381. These guidelines
include criteria for cleanup of soils contaminated by chemical or radioactive materials.
For the purposes of the EA, the EIS should provide any changes required to the existing
reclamation plan as a result of the project. Supporting documentation for proposed changes to
existing reclamation programs that are necessitated by the proposed project and incremental to
those currently in place for McArthur River and McClean Lake should be included in the EIS.
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 27
13.3 Abandonment and Institutional Control
The EIS should include any changes necessitated by the ore haul project to the proposed criteria
for abandoning the McClean Lake and McArthur River sites and associated infrastructure.
Provisions for the long-term institutional control should be discussed, including, but not limited
to:
Record keeping or archiving that fully describes past operations, decommissioning plans
and assessments, final configurations, and release verification;
Post-abandonment site monitoring and verification;
The need for passive site management;
Land controls; and
Long term financial liabilities for monitoring, care, and maintenance, or contingency
remediation.
14.0 SUMMARY
The EIS should provide a concise, complete statement of the anticipated net environmental costs
and benefits of the proposed transport of ore slurry from McArthur River Mine to be processed in
the JEB Mill at McClean Lake, in both the short and long-terms. The discussion should include,
if possible, any intangible costs and benefits that cannot be expressed in economic terms. To
satisfy federal and provincial requirements, this statement must include conclusions specifically
on whether the project is likely to cause significant adverse effects on the environment.
15.0 REFERENCES
1. Letter, T. Van Lambalgen (AREVA) to M. Leblanc (CNSC), “Application by AREVA
Resources Canada Inc. (“AREVA”) to Amend McClean Lake Operating licence for the
Receipt and Processing of McArthur River ore at the McClean Lake Operation”.
November 5, 2009. E-DOC: 3457365
2. Letter, T. Van Lambalgen (AREVA) to L. Casterton (CNSC) & L. Kelley (SMOE),
“Receipt and Processing McArthur River Ore at the McClean Lake Operation: Change to
Purpose and Project Schedule Revised”. April 8, 2010. E-DOC: 3533777
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 28
APPENDIX A - SIMPLE SCREENINGS DETERMINATION
Record of Determination
Criteria Evaluation Questions for Simple
Screenings
Yes/True Uncertain No/False
1. The site is well characterized, as are its
programs.
2. The proposed project is related to an existing
licensed facility.
3. The proposed project represents an incremental
change to the overall facility.
4. The environmental performance of the existing
licensed activities meets CNSC expectations.
5. The proposed project is based on technology
that is known to the proponent and CNSC staff.
6. The proposed project would only require
mitigation measures with which the proponent
has a demonstrated familiarity, and/or that are
considered standard technology within the
industry.
7. The proposed project does not introduce
project-environment interactions that cannot be
mitigated with standard or proven technology.
8. Based on potential project-environment
interactions, the proposed project is not likely
to pose any significant adverse effects on the
health of workers and the public, cumulative
effects, or those that may arise as a result of
accidents or malfunctions.
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 29
Rationale and additional comments to support determination:
1. The site is well characterized as it has been subject to a number of EAs. The
construction and operation of the McClean Lake Mine and Mill was approved in
1993 by the Joint Federal-Provincial Panel on Uranium Mining Developments in
northern Saskatchewan. In 1997, the Cigar Lake Project was approved by the Joint
Panel, which included the approval to expand the McClean Lake Mill (JEB Mill),
process high grade ore from Cigar Lake and deposition of tailings in the JEB
Tailings Management Facility. Other EAs (e.g., Mining Sue E ore proposal) have
been conducted for mining and milling activities that have been undertaken at the
McClean Lake site, which have contributed to site characterization.
2. The proposed project is located on an existing licensed facility.
3. The proposed project consists of activities (i.e., the receipt and processing of high
grade ore) that represent an incremental change to the overall licensed facility. This
is considered an incremental change as the facility has already undergone and EA
for the construction and operation of a high grade circuit and ore receiving
infrastructure. Although McArthur River ore has different physical and chemical
properties than ore from Cigar Lake, the milling process and associated waste
management is not anticipated to change.
4. CNSC staff conducted a review of the Environmental Protection Program area to
assess the adequacy with respect to the CNSC S-296 standard, Environmental
Protection Polices, Programs and Procedures for a Class I Nuclear Facility and
Uranium Mines and Mills. It was concluded that the environmental policy,
identification of environmental aspects, the use of objectives and targets, roles and
responsibilities, communication, emergency preparedness and response, and
documentation processes meet expectations.
AREVA is required to submit a Monthly Environment Report to satisfy the
conditions of Saskatchewan Ministry of the Environment (MOE) Approval to
operate Pollutant Control Facilities IO-205 (expires August 31, 2010), Approval to
Temporarily Close It-39 Midwest project, Permit to operate Waterworks #‟s
00050626-01-00, 00050627-01-00, 00050628-01-00 (expires December 31, 2013);
CNSC Operating Licence UMOL-MINEMILL-McCLEAN.00/2017 (expires June
30, 2017); and the Metal Mining Effluent Regulations (MMER).
5. CNSC staff is familiar with the technology being presented in this project as it has
already been subject to an EA and has been licensed with satisfactory performance.
All project activities are based on technology that is known to AREVA and no
construction activities are associated with this project. The project is proposed to
be carried out using existing ore receiving, processing and waste management
infrastructure.
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 30
6. The receipt and processing of high grade ore from Cigar Lake has already been
assessed for McClean Lake. Although the physical and chemical properties of
McArthur River Ore are different than Cigar Lake ore, the waste outputs are not
expected to change. Therefore, AREVA is familiar with all mitigation measures
required for the project activities and these mitigation measures are considered
standard technology within the industry. Mitigation & operational procedures
under the existing licence are not expected to change as a result of this project.
7. Any new project-environment interactions are expected to be adequately mitigated
with standard and/or proven technology. However, as the outputs associated with
the receipt and processing of McArthur River ore are not expected to change from
what was previously assessed, no new project-environment interactions are
anticipated.
8. At this stage of the EA, it appears that this project is not likely to cause significant
adverse effects on the health of workers and the public; cumulative effects; or those
that may arise as a result of accidents or malfunctions. The EA will identify all
potential project-environment interactions and confirm that the project is not likely
to cause significant adverse effects.
As a result of the scan above, is a simple screening appropriate in the circumstances?
YES or NO
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 31
APPENDIX B - PUBLIC PARTICIPATION DETERMINATION
Evaluation of Criteria
Assessment Criteria None Low Moderate High
1. There is an indication of existing or likely
public interest in :
a. the type of project
b. the location of the project or
c. the ways the project might affect the
community.
2. The stakeholders who may be interested have a
history of being involved.
3. The project could generate conflict between
environmental and social or economic values of
concern to the public
4. The project could be perceived as having the
potential for significant adverse environmental
effects (including cumulative environmental
effects and effects of malfunctions and accidents).
5. There is potential to learn from community
knowledge or Aboriginal traditional knowledge.
6. The direct and indirect environmental effects of
the project and their significance are uncertain.
7. The project has not been subject to other public
participation processes of appropriate scope and
coverage that would meet CNSC objectives.
Count number of check marks in each column 1 3 3 0
Multiply by: x 0 x 1 x 2 x 3
Total for each column is: 0 3 6 0
Add totals for an overall score of: 9
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 32
Rationale for determination
Criterion 1.
a) AREVA conducted a number of focused group meetings with northern community members
and leaders (including Métis), businesses, organizations and regulators. Most questions and
concerns were in relation to transportation logistics and safety risks associated with the ore slurry
haul from McArthur River Mine to the McClean Lake Operation, with fewer comments and
concerns submitted in relation to receiving and processing of high grade ore. Furthermore, the
Northern Saskatchewan Environmental Quality Committee (NSEQC) issued a resolution (e-docs
#3543483) expressing concerns around the transportation logistics involved in AREVA‟s
proposal. Therefore, there is an indication of existing public interest in the type of project.
b) During the public hearing held on April 30, 2009 regarding the licence renewal for the
McClean Lake Operation, five oral interventions and one written intervention were submitted.
This is an indication of existing public interest in the location of the project. Comments and
concerns raised at AREVA-led focused group meetings, as well as the NSEQC resolution, are
also indications of existing public interest in the location of the project.
c) As a result of AREVA-led focused group meetings, the public has an interest in the project, as
transportation logistics may affect local communities. This view was also expressed in the
NSEQC‟s resolution. The receiving and processing of high grade ore would be contained
entirely on the existing McClean Lake site and is not anticipated to affect local communities.
This sentiment was reflected in the few comments and concerns submitted during focused group
meetings in regard to receiving and processing high grade ore. However, as transportation is a
key activity in this project, the public does have an interest in the project as a whole and in the
ways that the project may affect local communities.
Criterion 2.
Five oral interventions and one written intervention were presented by stakeholders during the
April 2009 McClean Lake Operation licence renewal hearing. This is an indication that
stakeholders who may have an interest in activities related to the McClean Lake Operation have a
history of being involved. Similarly, the CNSC and SMOE are currently conducting a
cooperative EA concerning AREVA‟s proposed Caribou Project at McClean Lake. Three
submissions were received on the Project-Specific Guidelines and no comments were submitted
on the EA Screening Report. Although few comments were received, there is still an indication
of stakeholders having a history of being involved.
Criterion 3.
The receiving and processing of high grade ore is not anticipated to generate conflict between
environmental and social or economic values of concern to the public as previous EAs have been
conducted regarding this activity (e.g., Cigar Lake Joint Panel 1997, Construction of Cigar Lake
Mine 2004 and the Sue E Project 2005). The transportation of high grade ore slurry from
McArthur River to Key Lake was also assessed by a Joint Panel in 1997 (McArthur River
Project). However, AREVA‟s proposed transportation to McClean Lake was not assessed, and
based on preliminary focused group meetings led by AREVA, there is a potential the project
could generate conflict between environmental and social or economic values of concern to the
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 33
public. This sentiment was also expressed in the NSEQC‟s resolution.
Criterion 4.
The public and Aboriginal groups were involved in the 1997 Joint Panel processes for both Cigar
Lake and McArthur River. The receiving and processing of high grade ore from Cigar Lake at
the McClean Lake Operation were considered in this Panel. This Panel process, in conjunction
with the comments received during AREVA-led focused group meetings does not indicate that
the public could perceive the project as having potential for significant adverse environmental
effects associated with receiving and processing of high grade ore. Although the 1997 Joint
Panel (McArthur River Project) assessed both cumulative environmental effects and effects of
malfunctions and accidents associated with transportation of high grade ore slurry on provincial
highway 914, a number of concerns were raised regarding transportation logistics at AREVA-led
focused group meetings. The concerns may reflect the change in transportation route, as the
route proposed by AREVA has not been previously assessed. Therefore, although the Joint Panel
determined there were no significant environmental effects in relation to transportation of high
grade ore slurry along provincial highway 914, the transportation logistics associated with
AREVA‟s proposed project could be perceived as having the potential for significant adverse
environmental effects.
Criterion 5.
Local communities and Aboriginal groups were involved in previous EAs and on-going licensing
performance reviews of both sites and were provided the opportunity to share relevant
community and traditional knowledge. However, as the proposed transportation route was not
considered in any previous EA, there may be a potential to learn from community and Aboriginal
traditional knowledge.
Criterion 6.
Receiving and processing of high grade ore from Cigar Lake was assessed in the 1997 Joint
Panel (Cigar Lake Project). Although the ore from McArthur River has different physical and
chemical properties, there is no uncertainty with potential direct or indirect environmental
effects. Direct and indirect environmental effects associated with transportation of high grade
ore was assessed in the 1997 Joint Panel (McArthur River project). Therefore, there is minimal
uncertainty regarding direct and indirect environmental effects relating to transportation.
However, the McArthur River Project did not include the socio-economic environment
associated with AREVA‟s new proposed transportation route. Therefore, there is the potential
for uncertainty in regards to direct and indirect socio-economic environment effects associated
with the project.
Criterion 7.
The project will be subject to the Province of Saskatchewan‟s public participation processes.
This includes public consultation on the EA Project-Specific Guidelines, the EIS and the
Technical Review Comments. Technical Review Comments are issues identified by the SMOE,
CNSC staff and identified FAs during their review of the EIS, and are to be addressed by
AREVA. AREVA will make all necessary revisions based on the Technical Review Comments,
Project-Specific Guidelines Scoping Document - Receipt And Processing of McArthur River Ore at the McClean
Lake Operation
E-DOC: 3539014 34
and a revised EIS will be submitted. The revised EIS and Technical Review Comments are
subject to the provincial public review process. The CNSC will co-ordinate with the provincial
public participation processes, and post appropriate notices concerning public participation on
the Canadian Environmental Assessment Registry and the CNSC website. Furthermore, the
CNSC will conduct a public review period on the EA Screening Report, which may occur
concurrently with the public review of the EIS and Technical Review Comments. CNSC staff
will revise the EA Screening Report based on comments received, prior to submission to the
Commission for decision.
Additional reasons, if any, why public participation is or is not appropriate for
this project:
1.
2.
As a result of the scan above, is public participation appropriate in the circumstances of this
screening-level EA?
Yes or No
If yes, indicate the level of participation required, based on the tabulated score.
None
0 to 2
Low
3 to 7
Moderate
8 to 14
High
15 to 21