project risk management basics: cost and schedule · pdf filethrough management of life cycle...

49
1 Project Risk Management Basics: Cost and Schedule Impacts CSVA 2011 Conference Toronto, Ontario Nov 14 -16, 2011 Robert E. Rocco

Upload: ngobao

Post on 06-Mar-2018

221 views

Category:

Documents


4 download

TRANSCRIPT

1

Project Risk Management Basics:Cost and Schedule Impacts

CSVA 2011 ConferenceToronto, OntarioNov 14 -16, 2011

Robert E. Rocco

Contents

• Background

• Fundamentals

• Process

• Tools/Supporting Documentation

• Risk Register

• Introduction to Quantitative Analysis

• Contingency Management

• Questions

Risk Management Background

What is Risk?

• A risk is something that may happen, and if it does, will have either apositive or negative impact on the project

• Risk is an uncertain event that, if it occurs, has an effect on at leastone project objective (e.g., time, cost, scope, quality – PMI 2004)

Consideration: There are one or more active conditions that influence the risk’sprobability of occurrence and one or more response conditions that influencethe risk’s impact

What is Risk Management?

• An intuitive process

• A “good management practice” tool to enhance the chances for anendeavor’s success

• A systematic, disciplined process that satisfies strategic objectivesthrough management of life cycle risks

Experienced Project Manager

• Risk Management?

• I’ve Always Done That!

• What do they want me to do differently?

Benefits of Risk Management

• Prioritizes risks for Senior Managers to focus

• Provides managers with the means to decide where best to invests theprogram’s time and money

• Complies with owner’s and funding agency’s requirements,(e.g.: validating funding requirements)

• A rational method for calculating realistic and defendable contingencybudgets (cost and schedule)

• Forces the team to think collectively and collaboratively in mitigatingrisks, proactively

• Ensures that procurement and contract terms and conditions reflect theclient’s risk appetite and project objectives

Core to AECOM Program Management

• AECOM’s Risk Management practice is guided by:– “Practice Standard for Project Risk Management” Project

Management Institute (PMI)– ISO 31000:2009 “Risk Management - Principles and Guidelines”– Practical experience managing over 200 capital programs with total

Capex of over US$340 billion

• AECOM has applied Risk Management to capital programs with Capexvalues of approximately US$100 billion.

Risk Management Experience in Capital Programs

Program Value (US $ millions)Second Avenue Subway, New York, USA $16,000PATH Permanent World Trade Center Terminal, New York, USA $2,000Dallas Area Rapid Transit Airport Extension, Dallas, USA $300Dallas Area Rapid Transit Extension-Rowlett, Dallas, USA $300Lincoln Center Redevelopment, New York, USA $750San Diego International Airport Terminal Expansion, San Diego, USA $1,000Amtrak Vent Structures, New York, USA $100Central Corridor Light Rail Transit, Minneapolis, USA $1,000Route 9A West Reconstruction, New York, USA $100Tappan Zee Bridge Environmental Review, New York, USA $5,000Central Subway, Phase 2, San Francisco, USA $1,500Water Improvement Program, PUC, San Francisco, USA $4,500National Network of Highways Program, Trinidad and Tobago $4,000Afghanistan Infrastructure and Rehabilitation Program, Afghanistan $150Doha Port Qatar, Qatar $7,000Capital District Infrastructure Project, Abu Dhabi, UAE $20,000Saadiyat Island Cultural District, Abu Dhabi, UAE $20,000Abu Dhabi Metro, Abu Dhabi, UAE $5,000

The Fundamentals

The Fundamentals

DECISIONSACTIVITIES

FAVORABLEOUTCOMES(Opportunities)

UNFAVORABLEOUTCOMES

(Risks)Exposure to loss

SuccessfulProject

MAXIMIZEOPPORTUNITIES

MINIMIZERISKS

DECISIONSACTIVITIES

FAVORABLEOUTCOMES(Opportunities)

UNFAVORABLEOUTCOMES

(Risks)Exposure to loss

SuccessfulProject

MAXIMIZEOPPORTUNIT

IESMINIMIZE

RISKS

The Fundamentals

MAXIMIZEOPPORTUNITIES

MINIMIZERISKS

–– Within Budget

– Within Schedule

– Meets QualityObjectives

– No SignificantAdverse Reaction

–– Meet PoliticalObjectives

– Contribute toEconomic Growth

– Meet TransportationNeeds

– Satisfy EnvironmentalObjectives

The Process

Risk Management Process

IDENTIFY RISK

ESTABLISHLIKEHOOD

&CONSEQUENCE

(Assessment)

RANK RISKS(Evaluation)

ESTABLISHMITIGATION

PLANS &OWNERSHIP(Allocation)

MANAGE RISK- Mitigate

- Assess Efforts- Measure Progress

- Status- Reset Priorities, goals

Two Approaches to Risk Assessment

• Qualitative– May be used initially to set up a Project

Risk Program

• Quantitative– Necessary to provide contingency

requirements (cost and schedule) andisolate individual risk contributions

Supporting Elements of RM Process

Guidance

RiskPlan

Guidance

RiskPlan

Process

RiskManagement

Training,Processes,Procedures

Initial Activities

Supporting Elements of RM Process

Guidance

RiskPlan

Process

RiskManagement

Training,Processes,Procedures

Initial Activities

RiskAssessmentCommittee

(RAC)

Ongoing Activities for Project Life

Workshops

Brainstorming

Supporting Elements of RM Process

Identify, Assess,Mitigate Plans,

Ownership

EvaluateMitigation Effort,

Focus, Goals,Priorities

Supporting Elements of RM Process

Guidance

RiskPlan

Process

RiskManagement

Training,Processes.Procedures

Initial Activities

RiskAssessmentCommittee

(RAC)

Ongoing Activities for Project Life

Workshops

Brainstorming

AssessmentGroup Reports• MeasuredReduction ofRisk

• Action Items

• Cost/ScheduleConfidence Levels

• Cost Contingencyand schedule floatmanagement

Output

POTENTIALRISKS

ASSESSMENT

EVALUATION

MITIGATION PLANS

STRATEGIC TECHNICAL COST/SCHEDULE

Means To Execute- Project

Understanding- Business

Practices- Organization- Resources- Viability- Precondition

Project Execution- Design- Construction- Construction

Management

Cost and ScheduleMeasure

- Confidence Level- Cost Contingency- Schedule Float

RISK REGISTER

Risk Identification

MANAGEMENT

Tools for Risk Identification

• Interviews

• Project Team workshops

• Brainstorming

• Project documents review

• Risk Breakdown Structure

• Check lists

• Cause and effect diagrams

• Questionnaire

• SWOT analysis

• Industry knowledge base

• Influence diagrams

• Post-project review / lessonslearned / historical information

• Root-cause analysis

• Force field analysis

• List of assumptions andconstrains

• Delphi technique (anonymouspolling)

Risk Assessment

• The objective here is to communicate the “expected impact” that willhappen if no proactive mitigation plan is implemented in theprogram/project. And the steps are as follows:– Select impacted variable per risk factor

(e.g.: cost, schedule, quality, etc.)– Calculate expected consequences per risk factor

Expected Value (EV) = Likelihood x Consequence

Risk Assessment

LIKELIHOOD DESCRIPTION OF FREQUENCYOF EVENT

PROBABILITY SCALEVALUE

Almost CertainEvent occurs many times duringperiod of project or single event hashigh likelihood of occurrence

>70% 5

OftenEvent occurs several times duringperiod of project or single event hasmoderate likelihood of occurrence

40 – 70% 4

Likely Event could occur during period ofproject

20 – 40% 3

Possible Event is unlikely to occur, but it ispossible during period of project

10 – 20% 2

RareEvent is so unlikely that it can beassumed not to occur during periodof project.

0 – 10% 1

Risk Assessment

CONSEQUENCE

DESCRIPTION OF EFFECT OF EVENTCOST

(INMILLIONS)

SCHEDULE SAFETYPROJECT PERCEPTION/POLITICAL REACTION

SCALEVALUE

Catastrophic Adds up to$250

Adds 12months

Multiple publicaccidents

Public perception very poor.Project seriously jeopardized.Serious political consequence to-- Owner

5

Major Adds up to$100

Adds 6months

Single publicaccident andmultiple workforceaccidents

Project jeopardized. Requiresconsiderable effort to regrouppublic/political support

4

Moderate Adds up to$50

Adds 4months

Single publicaccident ormultiple workforceaccidents

Some concern for projectviability. Some politicalconsequence experienced byOwner. Moderate effort requiredto re-establish viability.

3

MinorAdds up to

$25Adds 2months

Single workforceaccident

Minor concern for projectviability and effect on Ownerpolitically

2

Insignificant Adds up to$10

Adds 1month

Little possibility ofaccident

Little or no concern for projectviability and effect on Ownerpolitically

1

Traditional Practice of Risk Ranking

CONSEQUENCE

PROBABILITYINSIGNIFICANT

(1) MINOR (2) MODERATE(3) MAJOR (4) CATASTROPHIC

(5)

RARE (1) 1 2 3 4 5

POSSIBLE (2) 2 4 6 8 10

LIKELY (3) 3 6 9 12 15

OFTEN (4) 4 8 12 16 20

ALMOST CERTAIN (5) 5 10 15 20 25

Risk Allocation

• Mitigate

• Transfer (e.g.: Share, Insurance)

• Accept

• Avoid

Identify party best able to implement the allocation

Manage Risk

• Primary Risk MitigationThis is the risk mitigation accomplished by implementing the riskmitigations placed in the Risk Register.

• Secondary MitigationThese are the items identified in advance by the project aspossible areas in which to reduce scope in an effort to savemoney or time to replenish contingency (cost and/or schedule)that is being used more rapidly than planned.

Tools/SupportingDocumentation

Risk ManagementPlan

Risk Identification• Workshops

• Informal process

Risk Assessmentand Evaluation

Risk ManagementRisk Mitigation Meetings

Risk Assessment Committee• Approve Allocations• Direct, evaluate mitigations• Change L,C• Secondary Mitigations

Risk Register• Risks• Mitigation Strategies• Allocation

- Mitigate- Transfer- Accept- Avoid

• Status

Risk: OwnershipMitigation Strategies

Allocations

Risk MitigationReport

Risk Mitigation Status logsSupporting documentation

Risk Program Documents

ContingencyManagement

• Reporting• Remedies

Risk Mitigation Meetings

• Risk Mitigation Meetings

– Regular interval (monthly)

– Includes key project personnel

– Establish priority risks and place on the agenda

– Minutes capture essential risk / mitigation discussions

Sample Risk MitigationMeeting Minutes

Risk Mitigation Status Log

Assessment CommitteeMeeting

Risk Register

Sample Risk Register

Quantitative Analysis

Risk Analysis

• Provides confidence level for cost estimate and schedule

• Rational approach to establish cost contingency and schedule float

• Means to manage contingency and float

• Addresses oversight agency requirements

Risk Analysis Input

1.Cost Estimate

a. Contractor Costs (pre-Award Contingency)– Labor– Material– Equipment– Indirects– Profit– Risk

b.Owner Costs

2.Risk Events (post-Award Contingency)

3.Schedule

Cost Estimate Uncertainties Matrix

Risk Events

Risk Events

Risk Analysis Output

$800,000,000 $900,000,000

Distribution (start of interval)

0

50

100

150

200

250

300

350

Hits

0% $810,627,650

5% $840,271,115

10% $846,859,238

15% $850,794,197

20% $854,591,438

25% $857,802,894

30% $860,865,828

35% $864,141,857

40% $867,547,188

45% $870,261,462

50% $873,195,250

55% $876,545,038

60% $879,671,838

65% $883,051,476

70% $887,757,789

75% $892,516,291

80% $898,605,014

85% $905,911,420

90% $913,495,632

95% $926,525,787

100% $978,143,363

Cum

ulat

ive

Freq

uenc

y

CCLRT ProjectEntire Plan : Cost

2200 2400 2600

Distribution (start of interval)

0

50

100

150

200

250

300

Hits

0% 2194

5% 2280

10% 2292

15% 2302

20% 2313

25% 2322

30% 2330

35% 2340

40% 2350

45% 2363

50% 2375

55% 2389

60% 2404

65% 2420

70% 2435

75% 2462

80% 2494

85% 2523

90% 2557

95% 2606

100% 2763

Cum

ulat

ive

Freq

uenc

y

CCLRT ProjectEntire Plan : Duration

Risk Analysis Output

7%

8%

9%

10%

10%

13%

14%

16%

20%

91%CC 65701 - CCLRT Project Schedule

0780 - SCC 70 Light Rail

0630 - SCC 40 Materials

0450 - SCC 10 Materials

0770 - SCC 60 ROW

0710 - SCC 50 Materials

0790 - SCC 80 Owner Cos ts

0550 - SCC 30 Labor

0700 - SCC 50 Labor

0750 - SCC 50 Risk

CCLRT ProjectCost Sensitivity

Increase confidence of$3.833 billion estimate by18%. (from 59% to 77%)

Reduce P90 by $160million. (from $4.18 to

$4.02 billion)

Mitigation & Effect

Unmitigated

Contingency Management

Contingency Management Includes:

• Recording actual values of remaining contingency on a month bymonth basis

• Forecasting contingency values into the future based on possibleopportunities and risks

• Identifying options to address any significant variations in contingencyusage

• Implementing the options to restore contingency usage to plannedlevels

472.495

515.371492.150

$200

$250

$300

$350

$400

$450

$500

$550Q

1

Q2

Q3

Q4

Q1

Q2

Q3

Q4

Q1

2010 2011 2012

Cost Contingency Drawdown Forecast

Planned Drawdown Minimum Contingency Buffer Actual Drawdown

Updated PlannedCurve

Contingency Management

472.495

515.371492.150

$200

$250

$300

$350

$400

$450

$500

$550

Q1

Q2

Q3

Q4

Q1

Q2

Q3

Q4

Q1

2010 2011 2012

Cost Contingency Drawdown Forecast

Planned Drawdown Minimum Contingency Buffer Actual Drawdown

Hold Point90% Bid

50%Constructed

Q1 2012 $220M

Forecast

Contingency Management

Tools and Resources

• Software– @RISK

• A Palisade Corporation Windows-based tool, which is an ‘add-on’ toMicrosoft Excel

• It is AECOM Standard software for conducting cost risk analysis andmodeling

– Oracle Primavera Risk (Formerly PERTMASTER) / @RISK forProject• Oracle Primavera Risk Analysis (Formerly PERTMASTER) or @RISK for

Projects are both AECOM standard tools used for conducting schedulerisk analysis and modeling

• References– (2009) “Practice Standard for Project Risk Management” published

by the Project Management Institute (PMI)– ISO 31000:2009 “Risk Management-Principles and Guidelines”

[email protected]

Optional Presentation TitlePhoto Slide

Presenter’s Name

Project Risk Management Basics: Questions and Answers