project reviews 20100414 1 0

26
Post Project Reviews Gavin Berry April 2010 [email protected]

Upload: gavin-berry

Post on 01-Jul-2015

256 views

Category:

Business


4 download

DESCRIPTION

Project Reviews - Why, what and how

TRANSCRIPT

Page 1: Project Reviews   20100414 1 0

Post Project ReviewsGavin Berry

April 2010

[email protected]

Page 2: Project Reviews   20100414 1 0

... experience

Programme Manager

Achieving Delivery

Systems Development best practices (SDLC)

Business Transformation

Client facing

Business methods and processes

• Establishing PMO: Developed, implemented and lead PMO Change operation, with appropriate procedures and commercials to provide internal improvements and profitable revenue stream.

• Large Programmes : Lead various programmes across multiple disciplines of up to 250 people.

• Best practices & Metrics : Developed and introduced an extensive metrics basis to development programmes to evidence the trends and results.

• Relationship Management : Rescued crashing projects – largely through success in relating to diverse and demanding stakeholders, both internal projects and external vendor.

• International : Worked across four continents and the various established cultures to deliver both business and technology change successfully.

• Conversions / Migrations : Extensive experience in migrating tranches of business and converting systems - largely in the financial sector. Both as an internal initiative and as an external vendor.

• Contracts : Successfully lead and represented major financial organisations in establishing and amending contractual terms.

• Business Process Re-engineering: Lead the successful establishing of business structures and processes to match strategic goals.

• Technical skill : Background of development from single address assembler through OOD.

• Sales : Represented third party outsourcing and software development organisations in sales related initiatives.

Gavin Berry

Page 3: Project Reviews   20100414 1 0

AgendaWhat is the case for Post Project ReviewsWhat have we (Industry) achieved in the last

10 yearsWhat is missing – and Reviews? Input to Post Project ReviewsWhen to have ReviewsHow to get the most out of ReviewsSome hints & ideas on the How T0Some Case Studies - Time PermittingQuestions

Page 4: Project Reviews   20100414 1 0

What is the case for Post Project Reviews: ResearchBoth Gartner and Forrester report that benefits realisation is not

occurring - (75% of programmes deliver no benefit; less than 30% measure benefits – Reiss 2004)

40% of projects fail to achieve their business case within 1 year - The Conference Board survey (2001)

51% [ERP] implementations unsuccessful - Robbins-Gioia survey (2001)

average project overrun of 40% pa - McManus, Wood-Harper (2004)

61% of projects fail - The KPMG Canada Survey (1997)

7 out of 10 IT projects fail - The OASIG study (1995)

ONLY 16.2% of projects complete on schedule and budget - The CHAOS report (1995)

ONLY 29% of projects complete on schedule and budget - The CHAOS report (2004)

Page 5: Project Reviews   20100414 1 0

What is the case for Project Reviews: Research FindingsSuccessful projects require:

User / Business involvementSupport from the top ExecutivesClear objectives and requirements that tie into

the business caseEffective project managementGood people Good disciplines and practices

Page 6: Project Reviews   20100414 1 0

What have we doneImproved Governance emphasising business

& executive involvement – PMI & Prince IIMore professional project management

through improved PM processes such as:

Gated process as outlined by Cooper, Edgett and Kleinschmidt

Page 7: Project Reviews   20100414 1 0

Report card – it has improved

B u t N O T e n o u g h

Page 8: Project Reviews   20100414 1 0

A key missing pieceCHAOS (2004) highlights that measuring &

achieving business benefits have lagged other improvements

Dilemma on how to Achieve Business Benefits

Page 9: Project Reviews   20100414 1 0

A key Missing piece – Project ReviewsOnly mitigation is project reviews looking at:

Why we are doing the project Review project Benefits against the Business Plan

How does the project deliver the benefits Review project scope against the business case

rationaleWhere do the benefits come from

Review the business case model

Page 10: Project Reviews   20100414 1 0

Paradigm ShiftTraditional View:

Project review to check the way the project was run

More Useful View:Project review to check we are [still] getting

what we want

Page 11: Project Reviews   20100414 1 0

Input to Project Reviews - StrategicIf the purpose for the project is business

benefit – we MUST have clearly articulated Benefits Case as a key referenceA model of costs and revenue, clearly showing

each component (Capex, amortisation etc; project resource costs; Sources of Revenue, assumptions and margins etc)

Business commitment to adjust business planTraceability between project scope and

business caseThis is a grid against which the project will

be reviewed

Page 12: Project Reviews   20100414 1 0

Input to Project Reviews - TacticalAssumption & Risk Register s

Not only must we assess the risks of delivery of the project, but also any risk to the current operation

Delivery plan & progress reportsCan we be sure that an accurate position is being

reflected in the formal reporting.PMO/GPO best practices / methodology

Are we sure that the various project artefacts have been produced and stored? This includes various hygiene factors.

Can we be sure that the organisations operating capability is protected (capital and people)?

Page 13: Project Reviews   20100414 1 0

When to complete ReviewsEvery time we change the target:

Change in BudgetChange in TimelineChange in scope

At regular pre-determined milestonesReviews have an inherent cost– like all other

costs – reviews must be deployed cost-effectively

On completionMeasure consistently against your agreed definition [of success] - Dr Walter Fernandez and Mr. Graeme Thomas

Page 14: Project Reviews   20100414 1 0

How to complete reviewsPreparation:

Agree with major stakeholders what aspects are to be emphasised in the review – Project Board / Steering Committee

Develop target groups on whom to focus the review

Develop a set of questions (matrix) that will address agreed review topics

Structure a collection approach for each group

Page 15: Project Reviews   20100414 1 0

Example Question MatrixSection Question Weig

htingSpon

sorS/

Holder

Team

Benefits 1 Are the Expected benefits quantified? H X

Benefits 2 Has a Benefits Realisation Plan (BRP) been developed? H X

Benefits 3 Have there been any changes in the expected benefits - if so what & why? H X

Benefits 4 Have any primary benefits been achieved as yet? H X

Budget / Cost 1 Was the project delivered within the allocated budget? H X

Communication 1 Was the level of communication between you and the Project Manager effective? X X

Communication 2 Were you kept sufficiently informed of the project’s progress? X X

Communication 3 How would you rate the level of communication within the project team? X X

Communication 4 Were the clients generally aware of new or modified work practices well in advance? X X

Deliverables 1 Were the project requirements clearly understood? H X X

Deliverables 2 Is the system/product operating as expected? H X

Deliverables 3 Was a Business Continuity Plan developed? X

Deliverables 4 Has a Service Statement been developed? X

Deliverables 5 Is the technical solution operating as expected? X

Implementation 1 Do you think the project was ready to go live when it did? H X X X

Implementation 2 Did the implementation process go according to plan? X X

Implementation 3 Was a contingency plan in place? X X

Implementation 4 Has the project been formally signed off by you and the Steering Committee? H X

Page 16: Project Reviews   20100414 1 0

How to complete reviewsCollection:

Collect and produce the analysis of the review over a short period of time (target 2 weeks)

Be open with c0ntributors on purpose and any actions

Provide for a mechanism to resolve uncertain responses

Output:Present to the Governance board firstOnce key actions have been agreed – present

to the contributors

Page 17: Project Reviews   20100414 1 0

Some hints & ideas on the How toAgree policy on Benefit realisation:

Full value in following financial year, orImmediate pro-rated benefit in first year

Business and their governance process then follow through on the realisation commitment.

Deferral and workaround log for any scope aspects that cannot be built and the business workaround to overcome the shortcoming. Doubles as benefit shortfall log.

Implementation Questionnaire for completion immediately after system implementation by line users. Measures any implementation disruption

Page 18: Project Reviews   20100414 1 0

Some hints & ideas on the How toCycle through the following for collection of

feedback on similar questions from IT teams:PM Conducts a “Lessons Learnt” sessionAnonymous questionnaires completedIndependent agent conducts “Lessons Learnt”

sessionsQuestionnaire for heads of business areas

post implementationReport Back sessions to both team members

and governance groups on outcome of “Lessons Learnt”

Page 19: Project Reviews   20100414 1 0

Review OutputConfirmation of the extent to which the project

deliveries will meet/have met expectations – by Review section e.g.:

Benefits Budget / Cost Communication Deliverables Implementation Issues / Other Overall Success Planning & Timelines

Quality Resources Risks Scope & ObjectivesSupportTraining

Documentation of lessons learned in the process – covering:Organisational ability to initiate & govern -

ORGANISATIONMethodology – how appropriate - PROCESSHuman capital – skills, capabilities and morale - PEOPLE

Page 20: Project Reviews   20100414 1 0

Reviews by Case – Organisation viewApple organisationNature of business: Hugely successful third party administration

outfit , predominantly in utilities and financial sector, FTSE100Business Culture: Directed by the financials, highly regulated

environmentProject Outline:

Contracted with world’s largest Life Assurer (WLLA) to support a financial product that was unknown and unsupported with a view to future business;

WLLA pushed Apples to implement capability for distribution window Systems settled down after 6 months – widespread data integrity

issues Any remedial activity would be unfunded Spend projected to exceed total revenue from WLLA Governance through main board

Page 21: Project Reviews   20100414 1 0

Reviews by Case – Organisation viewBanana organisationNature of business: Large Life assurer – no longer

tradingBusiness Culture: Politically driven, listed – but poor

performer, major shareholding by very successful organisation in different industry

Project Outline:Replacement Life Administration system for >1000 life

productsLack of confidence in own IT favoured off-the–shelf solutionProposal pitched to get support for desired optionApproved joint venture with successful US companyGovernance through committee

Page 22: Project Reviews   20100414 1 0

Reviews by Case – Organisation viewCherry organisationNature of business: Large Life assurerBusiness Culture: Results focussed, Listed in

financial services group, executive required to have personal holdings

Project Outline:Absorption of business from acquisition of

larger Life companyGovernance through accountable individuals

Page 23: Project Reviews   20100414 1 0

Reviews by Case – Organisation viewDate organisation Nature of business: Large Life assurerBusiness Culture: Traditional, Listed –

mediocre performer, culturally alignedProject Outline:

Continued development of strategic administration platform through regular releases (circa 4 per year)

Governance by business executive

Page 24: Project Reviews   20100414 1 0

How Reviews were done

Reference-Bus Case Rigorous (BlackHat) Lobbied vague Fit for purpose Thorough

Reference-Benefits Rigorous (Full model) No Quants Fit for Purpose Moderate

Reference-RAIDS Rigorous Unmonitored Moderate Rigorous

Reference-Plans Moderate Thorough Thorough Rigorous

When Reviewed Monthly / Milestone

Crisis / Challenge

Monthly / Concerned c/o

Crisis / Challenge

How Reviewed PM view PC SC view c/o personal Q’s 3rd Party/PM

Action Taken Unfettered Constrained Unfettered Uncertain

Page 25: Project Reviews   20100414 1 0

Questions

Page 26: Project Reviews   20100414 1 0

References Reiss 2004 – Overview of best practice.pdf Cooper et al 2000 – Making Programme management more effective

(Cooper, Edgett & Kleinschmidt, 2000).pdf The Conference Board Survey (2001) Robbins-Gioia survey (2001) The OASIG study (1995) McManus, Wood-Harper (2004) The CHAOS report (1995) The CHAOS report (2004) The KPMG Canada Survey (1997) Dr Walter Fernandez and Mr Graeme Thomas Dorsey 2009 – International journal on Governmental Financial Management -

using periodic audits to prevent catastrophic project failure.pdf Chris Sauer, Andrew Gemino, and Blaize Horner Reich (2007) - The impact of

size and volatility on IT project performance