Agenda Points 1. Station layout to be discussed and finalized 2. Size ( outer dimensions) of concrete barrel at MIV floor and Turbine floor 3. Cooling water system : Location of Inlet and outlet tappings 4. Size of MIV hatch from assembly considerations 5. Extent of approach of cranes ( BFV cavern and power house cavern) 6. Upstream extent of MIV inlet pipe and size of niche 7. Upstream & downstream extents of BFV inlet & outlet pipe (price implication for additional length beyond 2mtrs) 8. Runner removal scheme- size, location, height of passage/hatch size 9. Turbine pit entrance- size and location 10. Bottom level, size and location of dewatering gallery 11. Size and location of Material removal hatch over the head stock valve in dewatering gallery 12. Turbine floor may be lowered by 2 mtrs. 13. Tail race flood level to be informed by MS. 14. Spacing of columns to be discussed 15. Location of thrust collar for penstock valve and MIV

Upload: lalit-choudhary

Post on 07-Apr-2016

16 views

Category:

Documents


9 download

TRANSCRIPT

Page 1: Project review & Design coordination.docx

Agenda Points

1. Station layout to be discussed and finalized

2. Size ( outer dimensions) of concrete barrel at MIV floor and Turbine floor

3. Cooling water system : Location of Inlet and outlet tappings

4. Size of MIV hatch from assembly considerations

5. Extent of approach of cranes ( BFV cavern and power house cavern)

6. Upstream extent of MIV inlet pipe and size of niche

7. Upstream & downstream extents of BFV inlet & outlet pipe (price implication for additional length beyond 2mtrs)

8. Runner removal scheme- size, location, height of passage/hatch size

9. Turbine pit entrance- size and location

10. Bottom level, size and location of dewatering gallery

11. Size and location of Material removal hatch over the head stock valve in dewatering gallery

12. Turbine floor may be lowered by 2 mtrs.

13. Tail race flood level to be informed by MS.

14. Spacing of columns to be discussed

15. Location of thrust collar for penstock valve and MIV