project report of summer training june-july-2012

Upload: ravi-panchal

Post on 03-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    1/31

    SUBMITTED BY-IMRAN KHANMECHANICAL DEPTT.RAWAL INSTT OF ENGG & TECH

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    2/31

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    3/31

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    4/31

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    5/31

    Location Village Mujedi,P.O. Neemka,Dist.

    Faridabad,HaryanaGovt. approved date 25.07.1997

    Plant Capacity 430MW (Nominal)

    Plant Configuration 2(GT)+1STGT-143 MW, ST-144MW

    Fuel Used Gas and Naptha

    Gas Source HBJ Pipeline

    Water Source Rampur distributories of Gurgaon canal

    Project Cost Rs.1163.60 Cr. (IV Qtr.96)

    Commissioning Date GT-I : June 1999GT-II : October 1999ST : July 2000

    International Assistance OECF

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    6/31

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    7/31

    The gas plant at faridabad consists of twoblocks.

    The gas plant can run in both forms eitherin open cycle or combined cycle.

    The power output of generator is 156MW.

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    8/31

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    9/31

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    10/31

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    11/31

    1) Turn Gear Motor.2) Cranking Motor.3) Pumps for water cooling.4) Three lube oil pumps.

    *Main pump

    * Auxiliary pump (AC)* Emergency pump(DC)

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    12/31

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    13/31

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    14/31

    This system also includes fuel nozzles, sparkplug ignition system, flame detectors, andcrossfire tubes.

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    15/31

    The three-stage turbine section is the area inwhich the energy in the hot pressurized gasproduced by compressor and combustion

    sections is converted into mechanical energy. The first stage of turbine rotor blade consists of

    96 blades.

    Air cooling arrangements are provided forturbine 1st and 2nd stage.

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    16/31

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    17/31

    The WHRB includes the following: Preheater L.P economizer H.P economizer L.P evaporator H.P evaporator L.P superheated Two H.P superheated L.P & H.P drum L.P & H.P circulating pumps

    Diverter damper Weather protection damper Bypass stack Chimney

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    18/31

    With the use of boiler and then Steam Turbinemakes the plant efficiency better.

    At Faridabad the Steam Turbine comprises ofone High Pressure Turbine and one LowPressure Turbine.

    The output megawatt of Steam Turbine is116.6Mw at 11KV.

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    19/31

    Total station load is dependent on Stationtransformers 220 kV/6.6 kV, 24 MVA each

    There are no UATs on generator terminals

    Power generated at 11.5 kV is stepped updirectly to 220 kV

    Six 220 kV transmission lines connect Kawas to

    four grid substations of GEB

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    20/31

    A turbo generator is a turbine directly

    connected to an electric generator for thegeneration of electric power.

    STATOR WINDING:-

    ROTOR WINDING:-

    IMPORTANT POINTS:

    Gas turbine generator : 134 MVA - 4 Nos

    Steam turbine generator : 140 MVA - 2 Nos

    Air cooled, 3000 RPM, 2 pole, double star. Alston, France make.

    11.5 kV generator terminal voltage.

    Four coolers in the generator for cooling the air.

    http://en.wikipedia.org/wiki/Turbinehttp://en.wikipedia.org/wiki/Electric_generatorhttp://en.wikipedia.org/wiki/Electric_powerhttp://en.wikipedia.org/wiki/Electric_powerhttp://en.wikipedia.org/wiki/Electric_generatorhttp://en.wikipedia.org/wiki/Turbine
  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    21/31

    Prime mover

    Excitation system/AVR

    Generator transformer

    Cooling system

    Bearing

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    22/31

    Diesel generating sets are used in placeswithout connection to the power grid or asemergency power-supply if the grid fails.

    Its capacity is 3MW, speed 1500 rpm and shell

    type core.

    http://en.wikipedia.org/wiki/Electric_power_transmissionhttp://en.wikipedia.org/wiki/Electric_power_transmission
  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    23/31

    We have 4 types of transformers in NTPC

    Generator transformer:-

    Station transformer:-

    MV/LV transformers:-

    Lighting transformers:-

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    24/31

    Following are the main parts of switchyard inNTPC

    2 Main Bus

    1 Transfer bus 18 Bays :

    6 Generator bays

    8 Line bays ( 6 commissioned and 2 future) 2 Station transformer bays

    1 Bus coupler bay

    1 Bus transfer bay

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    25/31

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    26/31

    Generator and transformer protections

    6.6 kV Protections

    Station transformer protections

    Motor protections Transformer protections

    220 kV Protections

    Line protections

    Bus bar protection

    Breaker failure protection

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    27/31

    Zones of protection

    GeneratorProtn.

    Transformer

    Protn.

    Overall Gen.

    Trf. Protn.

    Line Protn.

    Busbar

    Protn.

    Transformer

    Protn.

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    28/31

    SWAS stands for Steam and Water AnalysisSystem.

    SWAS is mainly used to check the healthiness

    of steam turbine and boiler. USE OF SWAS:-

    Analyzers like NOx analyzers, Na analyzers,

    Hydrazine analyzer, Dissolved O2 analyzers,Water pH meters, silica analyzers, Waterconductivity meters.

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    29/31

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    30/31

    ? ?

    ?

    ? ?

  • 7/29/2019 PROJECT REPORT OF SUMMER TRAINING JUNE-JULY-2012

    31/31