project proponentenvironmentclearance.nic.in/writereaddata/formb/ec/eia...project: chapandey stone...
TRANSCRIPT
ENVIRONMENTAL MANAGEMENT
PLAN
FOR
Chapandey Stone Mines At
Village-Chapandey, Tahsil-sahibganj, District-
Sahibganj, Jharkhand
Area: 5.948 Ha Production: 165204.04 TPA
PROJECT PROPONENT :
Sanjay Bhalotia
Environment Consultant :
COGNIZANCE RESEARCH INDIA PVT LTD
(Accredited by QCI/NABET)
Gt-20, Sector-117, Noida, U.P
Website: http://www.cognizanceindia.com
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
2
INTRODUCTION
ENVIRONMENT MANAGEMENT PLAN
The environmental management plan consists of the set of mitigation,
management, monitoring and institutional measures to be taken during the
implementation and operation of the project, to eliminate adverse
environmental impacts or reduce them to acceptable levels. Environment
management plan details the quality control measures which are proposed for
this project to achieve the production of near about 165204.04 TPA of stone.
EIA Notification 2006 amended on 15th January 2016 stated that for B2
Category Project below 5 ha is required Form I M, PFR & Approved Mining
Plan.
The Proposed project is for Chapandey Stone Mines of Sri Sanjay Bhalotia over
an area of 5.948 Hectares is located in Village-Chapandey, Tahsil-sahibganj,
District- Sahibganj, Jharkhand. The lease was granted in the favor of Sanjay
mining and minerals trading partner M/s Sanjay Bhalotia dated 09.08.2005 for
the period of 10 years.
The Mining Plan was prepared and by office of the deputy directors mine
santhal pargana circle Dumka via letter no. 347 dated 31.07.2017.
The proposed rate of production is 165204.04 TPA of Stone. The lease area
comprises of Government waste land. The estimated project cost is Rs. 50
Lakh. The expected life of mine is 10 years.
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
3
The present environmental management plan addresses the components of
environment, which are likely to be affected by the different operations in a
mine area.
The aims of EMP are:
• Overall conservation of environment.
• Minimization of waste generation and pollution.
• Proper use of natural resources and water.
• Safety, welfare and good health of the work force and populace.
• Ensure effective operation of all control measures.
• Monitoring of cumulative and long time impacts.
Ensure effective operation of all control measures
The Environmental Management Plan (EMP) has been formulated and
integrated with the mine planning to mitigate the adverse impacts which are
likely to be caused due to the mining operation and for overall scientific
development of local habitat. The EMP has, therefore, been developed
considering its implementation and monitoring of environmental protection
measures during mining operations.
0. AIR ENVIRONMENT MANAGEMENT
Mitigative measures suggested for air emission control will be based on the
baseline ambient air quality monitoring data. From the point of view of
maintenance of an acceptable ambient air quality in the region, it is desirable
that the air quality needs to be monitored on a regular basis to check it vis-à-
vis the NAAQS prescribed by MoEF & CC and in cases of non-compliance,
appropriate mitigative measures will be adopted. In order to minimize impacts
of mining on air and to maintain it within the prescribed limits of CPCB/
SPCB, an Environmental Management Plan (EMP) has been prepared. This will
help in resolving all environmental and ecological issues likely to cause due to
mining in the area. During the course of mining no toxic substances are
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
4
released into the atmosphere as such there seems to be no potential threat to
health of human beings. In the mining activities, the source of gaseous
emissions is engines of vehicles, Operation of mining machinery/ loading
operations, drilling and blasting. The reasons may be quality of fuel, improper
operation of the engine, etc; proper maintenance of engines will improve
combustion process and brings reduction in pollution.
1.1 Control of Gaseous Pollution
In mining activities, the only source of gaseous emissions is from blasting and
the engines of Heavy earth moving machines (HEMM). Blasting of explosive
results in increase of nitrogen oxides, which are dispersed by the wind.
Controlled blasting and optimization of use of explosive energy will help in
reducing the above emissions. The emissions from the diesel engines of the
machinery can be controlled by proper maintenance and monitoring of
machines.
1.2 Control of Dust Pollution
The main pollutant in air is PM10, which is generated due to various mining
activities. Information on air quality studied by line source modeling
techniques predicted that the mining activity will not affect the air quality in a
significant manner. In mining operations, loading, transportation and
unloading operations may cause deterioration in air quality due to handling
dry materials. There is no other source of air pollution as there is no boiler, DG
Set or furnace. Only source of air pollution is re-suspension dust from the
movement of tripper/dumper/trucks to and from the mining site.
Study on emission sources and quantification of pollutant concentration by
means of dispersion modeling is required to access the environmental impact of
a mine. On the basis of the predicted increments to air pollutant
concentrations, an effective mitigation and environmental plan can be devised
for sensitive areas.
1.2.1 Fugitive Dust- Modeling
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
5
Air quality modeling was done using line source model as published by USEPA
“Emission Factor Documentation for AP-42”, in section 13.2.2, for
transportation though unpaved roads. Emission factors to be used in Line
source dispersion equation is adopted from formula as given below:
E=k * (s/12)a * (W/3)b /(M/0.2c) ……………………………………….…………(1)
Where
E = Emission Rate (lb/VMT)
s = Surface material Silt Content (%) = 10%
W=Mean Vehicle Weight (tonnes) = 10 tonnes
M= Surface material moisture content (%) = 2.5%
K, a, b & c are empirical constants with values given as below:
Constant PM10
k 2.6
a 0.8
b 0.4
c 0.3
During Mine operation
Proposed Capacity of mine/annum : 165204.04 tpa
No. of working days : 300 days
Proposed Capacity of mine/day : 550 TPD
Trucks/Trippers Capacity : 10 tonnes
No. of tractor trolleys deployed/day : 55 trippers/trucks
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
6
No. of tractor trolleys deployed/hour : 6 trippers/trucks
Thus for vehicles of 10 tonners, the Emission Rate using equation (1) is:
E = 0.53491Kg/VKT
E = 0.0009 g/s/m
Concentration of the fugitive dust was calculated using the formula given in
“Workbook of Dispersion Modeling” by Turner. The Concentration of the
fugitive Dust is given below:
C = (2/π) 1/2 (E / σz υ) Exp- [(h2) / (2 σz2)] x 106 ------------------- (2)
Where
C = Hourly Concentration in microgram/ m3
E = Emission Rate = 0.0009 g/s/m
υ = Wind Speed = 5.2 m/s
h = 0 m
Modeling was done for an infinite line source assuming unpaved road. For
conservative calculation wind was assumed to blow at a velocity of 5.2 m/s
perpendicular to the road. The results for 24 hourly concentration values are
given in the Fig:
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
7
It is observed that the ground level concentration (GLC) decreases from 11.31
µg/m3 at 25 m from the centre line of the road to 1.07 µg/m3 at 500 m from
the centre line of the road. These values have been predicted for a dry unpaved
road. In controlled way by water sprinkling ground level concentration (GLC)
decreases from 2.94 µg/m3 at 25 m from the centre line of the road to 0.28
µg/m3 at 500 m from the centre line of the road.
However to reduce the impact of dust pollution the following steps have been
taken during various mining activities.
1.3 During drilling operations
I. Sharp drill bits will be used for drilling and regrinding is done periodically to
reduce generation of dust.
II. The drill machines will be kept leakage free and equipped with wet drilling
arrangements.
11.31
8.16
5.04
2.73
1.82 1.35
1.07
2.94
2.12
1.31 0.71 0.47 0.35 0.28 0.00
2.00
4.00
6.00
8.00
10.00
12.00
0 100 200 300 400 500
Co
ncn
tra
tio
n i
n µ
g/m
3
Downwind Distance in m
Concentration of Fugitive Dust vs Distance
24 hr avg Unscientific
24 hr avg Scientific
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
8
III. Drill operator and his helper will be equipped with personal protective
equipment (ear plugs/ear muffs).
1.4 During blasting operation
All essential steps will be taken to prevent any person entering in the mine site
during blasting operations. The drill holes will be charged by certified blaster
and in supervision of Mining Engineer/ Mines Manager. The holes will be
blasted by certified blaster. Before blasting the warning siren will be blown and
men and machinery will be taken out from the safety zone. During blasting all
the statutory requirements as per MMR- 1961 will be strictly followed.
I. The use of ‘water ampoules’ will be done to arrest dust.
II. Blasting will be done in controlled manner with the use of latest technology
like use of millisecond delay detonators, cord relay to control and prevent the
dust to get air borne and to limit the fly rocks within 50–60 m.
III. Over charging of blast holes will be avoided.
IV. Rock Breakers will be used to avoid secondary blasting.
V. With the good blasting system, dozing of broken rocks will be less and hence
dust due to dozing will be less.
VI. Competent persons carry out blasting and all the precautions lay under
MMR, 1961 Act are followed. Time to time scientific studies regarding ground
vibration, noise level, flying rocks and other blasting hazards will be conducted
through experts of the subjects.
1.5 During loading operation
I) Latest loading equipment like hydraulic excavators will be used with
dumpers. This reduces the number of buckets to fill from height and thus have
comparatively less dust generation. The propagation of this dust is confined to
loading point only and does not affect any person both the
Operators of excavator and dumpers who will sit in closed chamber and will be
equipped with dust mask.
II) Skilled operators will operate excavators.
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
9
III) Avoid overloading of dumpers and consequent spillage on the roads.
IV) The operator’s cabin in the drills, dumpers will be provided with dust free
enclosure and persons working at high dust prone areas will be provided with
dust mask.
1.6 During Transport operation
Transportation
Traffic analysis is carried out by understanding the existing carrying capacity
of the connecting main roads in the area. Then depending on the capacity of
the mine, the number of trippers that will be added to the present scenario will
be compared to the carrying capacity.
During Mine operation
Proposed Capacity of mine/annum : 165204.04 tpa
No. of working days : 300 days
Proposed Capacity of mine/day : 550 TPD
Trucks/Trippers Capacity : 10 tonnes
No. of tractor trolleys deployed/day : 55 trippers/trucks
No. of tractor trolleys deployed/hour : 6 trippers/trucks
Existing and Modified Traffic Scenario & LOS
Road V C Existing V/C Ratio LOS
Existing near NH-18
intersection 1000 15000 0.066 B
Modified near NH-18
intersection 1012 15000 0.066 B
Source: IRC 64-1990
V= Volume of Vehicles in PCU’s/day & C= Capacity of Highway in
PCU’s/ day
V/C LOS Performance
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
10
0.0 - 0.2 A Excellent
0.2 - 0.4 B Very Good
0.4 - 0.6 C Good / Average / Fair
0.6 - 0.8 D Poor
0.8 - 1.0 E Very Poor
Reference: ENVIS Technical Report, IISc, Bangalore
Results
From the above analysis it can be seen that the V/C ratio is not going to
change i.e. it is constant 0.066 with LOS being “A” which is ‘Excellent, as per
classification. So the additional load on the carrying capacity of the concerned
roads is not likely to have any adverse affect.
I) All the haulage roads including the main ramp be kept wide, leveled,
compacted and properly Maintained and watered regularly during the shift
operation to prevent generation of dust due to Movement of dumpers, and
other vehicles.
II) Mineral carrying trucks will be effectively covered by Tarpaulin to avoid
escape of fines to atmosphere.
III) Regular Compaction and grading of haul roads to clear accumulation of
loose material.
IV) Air quality will be regularly monitored both in the core zone and the buffer
zone.
1.7 Plantation work carried out
In order to reduce air pollution in the surroundings, green belt will be
developed around mines office, mine approach road. The plantation will be
done around the lease boundary.
1.8 Monitoring of air pollution
Periodic air quality survey will be carried out to monitor the changes
consequent upon mining activities as per the norms of Jharkhand State
Pollution Control Board.
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
11
1. 9 WATER ENVIRONMENT
The applied area represents a part of hillock with moderate slope with rock
mass of Granite Gneiss.. The highest contour is of 650m from Mean Sea
Level and the lowest contour is of 654m from MSL.
1. The water table is 30-35m below the ground level.
2. The area is more or less undulating and working will be done in this area
above ground water table.
3. Adequate number of diesel pumps will be kept standby. During rainy
season water from the pit, if available, will be sampled and the results
will be submitted when required.
2.1 Rainfall and Climate:
The area receives rainfall by South-West monsoon. Rainy season sets in the
middle of June and lasts till September. The normal average rainfall) in the
district is 1575 mm
The district is characterized by humid to sub-humid climate. During summer
the hot spell prevails from March to middle of June. Rainy season started from
middle of June to end to September. Winter starts from the middle of November
and continues till the end of February. The district experiences great heat from
March to May, when the maximum temperature reaches upto 44.40 c. December
being the coldest month when the minimum temperatures fall down up to 6.80
c.
Ground Water:
Rajmahal Trap is the major rock type in the district. The other geological
formations of the district are alluvium and Laterite. The alluvium occurs in the
northern and eastern boundary of the district, which is composed mainly of sand
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
12
and sub ordinate clay. Laterites are mainly of insitu origin and have been formed
by sub-aerial eroson of underlying basalts under favorable climatic conditions.
Laterites provide a productive ground water reservoir due to its very good porous
and permeable in nature. Rajmahal traps having a large thickness of basaltic
lava flows occurs in the major part of the district. The different units of the lava
flows are the main water bearing horizons in basaltic formation. The basic
properties such as the ability to receive recharge, holding capacity of water to
take into storage and transmit it as ground water by gravity are different for
different litho units of the trappean flows. The massive basaltic unit is hard and
compact in nature with negligible primary porosity and permeability. But the
process of weathering and development of secondary porosity such as joints and
fractures makes it to act as good ground water reservoir. The vesicular units
have abundant vesicles that contribute towards hydrogeological properties and
thus have high degree of porosity and permeability to serve as potential aquifers.
The ground water occurs in near surface in weathered, joined and fractured
basalts zone under water table conditions. The water bearing zone occurring
between depths of 15-40 m are either interflow weathered shear zones and
directly connected to shallow aquifer in widely spaced major joints and fractures
and forms semi confined aquifer. Below the depth of 40 m, where the fracture
porosity is insignificant, the weathered flow contacts are completely cut-off from
lower aquifer on account of intervening high impermeable massive basalts and
intertrappean beds and thus give rise to confining conditions. Mining of stone
does not have any significant impact on the water quality, as the neither mining
nor intercept with the ground water level neither there is any surface water body
near the site. The contractor will adhere to all guidelines and rules for proper
and scientific method of mining during the period of excavating the stone.
2.2 Impact on Water Quality:
Surface and ground water is not affected due to mining activity of this mine.
There is no perennial source within the leasehold. There is no cause of
contamination of water, as no industrial effluent is discharged and there is also
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
13
no quarry discharge water from mine. The proposed working RL of the quarry
by the end of this plan period will be at much higher level from the water table,
as such, there will be no impact on ground water body due to this mining.
2.3 Measures for minimizing adverse effects on water regime:
As stated earlier, surface water and ground water sources are not affected due
to this project. Water quality of surface as well as ground water is not affected
due to mining activities. There will be no quarry discharge water from the
proposed pit. But during rainy season, there may be a chance of surface water
pollution due to contamination of suspended and dissolved solids those are
mostly expected from the outer slopes during monsoon. Construction of
channel to guide the rain water from higher to lower contour will serve the
purpose.
2.4 Mitigation measures
Surface Water Management
I. As such no surface water body exists within the lease area; no adverse
impacts are envisaged on the same.
II. Proper mitigative measures will be taken up to control the pollutants within
prescribed standards and limiting the emissions to site only.
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
14
III. Garland drains will be provided to prevent the entry of rainwater into the
mining pit.
Ground Water Management
I. Mining will not intersect the ground water table of the area. So it will not
disturb water environment.
II. Natural pits will be used for rainwater conservation and harvesting.
III. Rain water harvesting practices shall be done which will lead to ground
water recharge.
IV. At the end of the life of mine artificial water reservoir has been proposed.
Waste Water Management
No waste water is generated from the mining activity of minor minerals as the
project only involves lifting/excavation of Stone and transportation directly to
the consumers.
Water Conservation
The project do not consume any process water except for drinking, dust
suppression and plantation. Plantation is proposed, which will increase the
water holding capacity and help in recharging of ground water. Artificial
rainwater harvesting is proposed for the present project
The proposed mining operation is Semi-mechanized and does not affect any
pollution at the remarkable scale.
An ambient water quality monitoring network will be designed for assessment
of the baseline status of ambient water quality. The parameters to be
monitored are given as below:
(1) PH—
(2) E.C. ---
(3) Ca- Concentration
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
15
(4) Mg-Concentration
(5) Na- Concentration
(6) K- Concentration
(7) HCO3—Concentration of bi-carbonate
(8) Cl- Concentration of Chloride
(9) Total hardness as CaCo3
2. NOISE ENVIRONMENT
3.1 Impact on environment
Noise generated at the mine is due to mining operations, trippers transportation
activities, drilling and blasting (if required). The noise generated by the mining
activity dissipates within the mine. There is no major impact of the mining
activity on the nearby villages. However, pronounced effect of above noise levels
will be felt only near the active working area if blasting will be done.
Noise at lower levels (sound pressure) is quite acceptable and does not have any
bad effect on human beings, but when it is abnormally high- it incurs some
maleficent effects.
In this case the impact of noise on the nearby settlements is negligible. Since
there is no involvement of major machinery, the impact of noise levels will be
minimal.
3.2 Noise and Vibration Environment Management
There is drilling and blasting for mineral extraction. Noise due to drilling,
blasting & transportation will cause some problem to the inhabitants of this
area because there is human settlement in close proximity to the link roads in
lease area. Effective steps will be taken to keep the noise level well below the
DGMS prescribed limit of 85 dBA.
3.3 Noise Abatement and Control
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
16
I. All the machineries including transport vehicles will be properly maintained
to minimize generation of noise.
II. Silencers in the machineries will be provided to reduce generation of noise.
III. Drilling with sharp edges bits will minimize generation of noise.
IV. Control blasting will be done with proper charge of explosive to minimize
noise during blasting.
V. Attenuation between source and receive points will be incased.
VI. Dense plantation in mining area will also reduce propagation of noise
outside the core zone.
VII. Optimal blast hole geometry charge will be reused.
VIII. Rock breakers will be used instead of secondary blasting.
IX. Blasting will be avoided under unfavorable atmospheric conditions
X. Periodical monitoring of noise will be done to adopt corrective actions
wherever needed.
XI. Plantation will be taken up along the approach roads. The plantation
minimizes propagation of noise and also arrests dust.
3.4 Vibration Abatement
The blasting operations in the proposed mine will be carried out by deep hole
drilling and blasting using delay detonators, which reduce the ground
vibrations. Further, the ground vibrations will be controlled by using shock
tubes with nonelectric delay detonators. The measures that are generally
followed and currently proposed for abatement of ground vibration, air blast
and fly rocks are detailed below:
I. Blasting will be performed strictly as per the guidelines specified under
MMR,1961;
II. Proper design of blast with correct spacing, burden and optimum
charge/delay;
III. Supervision of drilling and blasting operations to ensure blast design
geometry as per planning;
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
17
IV. Sub-drilling will be kept adequate to eliminate toe formation;
V Blasting operations will be carried out only during day time as per DGMS
guidelines;
VI. Proper warning signals will be used;
VII. Adequate safe distance from habitation as per standards from centre of
blasting will be maintained;
VIII. Drilling parameters like burden, depth, diameter and spacing will be
properly designed to ensure proper blast;
IX. Effective stemming of the explosives will be done in the drill holes
3.5 Mitigation measures
The impact on ambient noise levels will only be due to transportation and
excavation of material and following mitigation measures will be taken for the
same.
i. On-site
a) Well maintained vehicle will be used which will be a check on noise level.
b) Plantation of trees along the barrier zone of 7.5m wide will be done to
dampen the noise.
c) Blasting only if required will be done by licensed vendors.
d) All the miners will be provided with Personal Protective Equipments such as
ear-muffs etc.
ii. Off-site
The off-site receptors are not significantly affected as noise generated by such
small mining activities are insignificant but some disturbances due to vehicle
movement may not be avoidable. However the following measures have been
envisaged:
a) The vehicles will be maintained in good running condition so that noise will
be reduced to minimum possible level.
b) Awareness will be imparted prior to mining operations that smoke silencers
remain in a good conditions not to generate noise.
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
18
c) In addition, drivers will be instructed to make minimum use of horns at the
village area.
d) To the extent feasible, route heavy truck supporting mining activities away
from residences and other sensitive receptors.
4. SOLID WASTE AND TOP SOIL MANAGEMENT
4.1 Nature of waste:
As the area has exposed quarry the generation of intercalated waste is
minimum. However the waste generated will be used for construction and
maintenance of the haul road and transport road and no stacking of waste or
mineral rejects is proposed. No dumping will be done as the material produced
is send to the consumer and the rejects are also dispatched for consumer use
as a filler material for construction activities
4.2 Waste Management
There is no material which can be called as waste. This area is a virgin area
and there O.B. is gritty soil, during mining operation this soil will be
temporarily dumped with suitable precaution and this will be backfilled in the
exhausted quarry as per conceptual plan period.
Top Soil Management
The top soil will be first removed by dozer and it will be transported to a
separate top soil stack yard at the statutory barrier of 7.5 m. of the lease area.
All the top soil extracted from the mine area in first year, will be used in
plantation in the second year onwards. And all the top soil that has been
extracted during the second year will be stacked in the same stack yard and
will be used for plantation in the third year.
4.3 Land Reclamation
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
19
The total mining lease area is 5.095 ha. The area shall be reclaimed by
backfilling and plantation will be 0.848 ha and 1.509 ha area is left as water
reservoir.
5.0 BIOLOGICAL STUDY:
Biodiversity is a generic term that can be related to many environments and
species, for example, forests, freshwater, marine and temperate environments,
the soil, crop plants, domestic animals, wild species and micro-organisms. On
the other hand, biological diversity comprises the variability of species, genus
and ecosystems and is broadly divided in to two types i.e. the floral diversity
and faunal diversity.
Conservation of global biodiversity is important to sustaining human life at
local and global scales because humans are dependent on the healthy
functionality of other life forms. Many argue that biodiversity must be
preserved because all species have intrinsic value.
Before starting any Environmental management study, it is necessary to
identify the baseline of relevant environmental parameters which are likely to
be affected as a result of operation of the proposed project. A similar approach
has been adopted for conducting the study on Biological Environment for
this Project. Both terrestrial and aquatic ecosystems have been studied to
Pattern of Utilization Existing Plan period Conceptual stage
Ha Ha Ha
Quarry 1.041 2.357
2.357
(1.509ha area shall be left
as water resevoir and
0.848 ha as Dead bench
Plantation)
Road 0.027 0.023 0.023
Safety Zone Plantation 0.00 0.256 0.256
OB Dump 0.219 0 0
Forest Barrier 3.808 3.312 3.312
Total 5.095 5.948 5.948
Unused Area 0.853 0.000 0.00
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
20
understand the biological environment.
5.1 Flora and Fauna of Core Zone
The core zone comprises of barren stony waste land, where mining operation is
proposed. The trees nearby the mining site are naturally occurring but are very
few in number but are not present in core zone of proposed lease area. No
ecologically sensitive plant species has been reported from this area. The
faunal variety is poor. Mammalian fauna is almost restricted to domestic
species like cattle, dogs, cats etc. Bird species also do not exhibit much
diversity. Local birds are noticed crossing over the banks in search of food. No
fixed pattern in migratory behavior is noticed.
Flora
The core zone of proposed mining project comprises barren stony. Most of the
areas nearby the project site are waste land. No major trees were recorded from
the mining lease area except some grasses after monsoon along with some
others vegetation which are listed in Table.
Floral Species Observed in the Core Zone
S. No. Botanical Name Family Common Name
Herbs & Grasses
1
Achyranthus aspera
Amaranthaceae Cotton weed
2 Cynodon dactylon Poaceae Doob
3 Eleusine indica Poaceae Indian goose grass
4 Sorghastrum nutans
Poaceae Yellow Indian
Grass
Shrubs & Climbers
1. Carissa opaca Apocynaceae Karounda
2. Zizyphus numularia
Rhamnaceae Ber
Fauna
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
21
Core zone of the proposed mine area is devoid of any major plant species, so
mammals and avifauna were not observed during the study period. There is no
any aquatic habitat in the core zone, so aquatic flora and fauna also does not
exist in the respective area. On the other hand, no any bird’s nest in the core
zone was observed.
5.2 Flora and Fauna of Buffer Zone
Flora
Table Phytoplankton of Aquatic Habitats present in the Buffer Zone
Name of the Groups Name of the Taxa
Cyanophyceae
Anabaena sp.
Merismopedia sp.
Oscillatoria sp.
Bacillariophyceae
Achnanthes sp.
Achnanthes minutissima
Melosira granulata
Euglenophyceae Euglena acus
Trachelomonas armata
Table Tree Species Recorded from the Buffer Zone of Present Mining Area
Sl.
No. Botanical Name Local Name Family
1. Albizia odoratissima Jang Siris Fabaceae
2. Azadirachta indica Neem Meliaceae
3. Bauhinia purpurea Koenar Fabaceae
4. Emblica officinalis Amla Phyllanthaceae
5. Eugenia heyneana Katjamun Myrtaceae
6. Eugenia jambolana Jamun Myrtaceae
7. Ficus religiosa Pipal Moraceae
8. Gmelina arborea Gamhar Rubiaceae
9. Madhuca latifolia Mahua Sapotaceae
10. Mangifera indica Mango Anacardiaceae
11. Morus alba Tut Moraceae
12. Tamarindus indica Imli Fabaceae
EMP PROJECT: CHAPANDEY STONE MINES
APPLICANT: SRI SANJAY BHALOTIA
22
Fauna
Table List of Zooplankton collected from Aquatic Habitats present in the
Buffer Zone
Name of the
Groups Name of the Taxa
Protozoa Arcella sp.
Centropyxis sp.
Rotifera
Brachionus angularis
Brachionus falcatus
Filinia longiseta
Keratella cochlearis
Ostracoda Cypris sp.
Table: Fish Fauna of present in some surrounding habitats of Buffer Zone
Family Scientific Name Local
Name
IUCN
Status
Order- Cyprinidontiforms
Family: Cyprinidae
Amblypharyngodon mola
Mourola LC
Puntius ticto Punti LC
Labeo rohita Rohu LC
Order- Perciformes
Family: Channidae
Channa punctata Garai LC
Order- Siluriformes
Family: Mystus cavassius Tengra LC
23
EMP PROJECT: ICHADAG STONE DEPOSIT
APPLICANT: SRI ANKIT KUMAR SHARDA
Bagridae
Source: Present Survey data.
IUCN Status=LC: Least Concern, NE: Not Evaluated, EN: Endangered, NT: Near Threatened
Table: Faunal Species observed in the Buffer Zone of Present Mining Area
S. No
Scientific Name
English Name Schedule
Status (WPA-
1972)
IUCN Status
Mammals
1 Bandicota indica Bandicoot Rat V LC
2 Rousettus leschenaulti
Fulvous Fruit Bat
V
LC
3 Mus booduga Indian Field Mouse V LC
4 Pteropus giganteus
Indian Flying Fox Bat
V
LC
Avian Fauna
1
Acridotheres fuscus
Jungle Myna
IV
LC
2
Acridotheres tristis
Common Myna
IV
LC
3 Columba livia Rock Pigeon IV LC
4
Corvus macrorhynchos
Jungle Crow
IV
LC
5 Coturnix coturnix Common Quail IV LC
6 Passer domesticus House Sparrow IV LC
7
Turdoides caudata
Common Babbler
IV
LC
Reptiles
1 Bungarus caeruleus
Common Krait
IV
NA
Lizards
1 Agama buberculatus
Rock Lizard
-
DD
2 Hemidactylus Indian House Gecko - DD
24
EMP PROJECT: ICHADAG STONE DEPOSIT
APPLICANT: SRI ANKIT KUMAR SHARDA
flaviviridus
Source: Present Survey Data and Data supported by Department of
Forest, Jharkhand.
IUCN Status: LC: Least Concern, VU: Vulnerable, NE: Not Evaluated, EN: Endangered, NT: Near Threatened.
Management Scheme/Plan (point wise) of flora and fauna of the buffer
zone (up to 10 km radius) & core zone of the mine area.
Species belongs to Schedule-I category as per Wildlife Protection Act (1972) are
not found within 10 km. So, there is no need of Management plan. However, all
care will be taken for protection of others flora & fauna also, if any in the lease
hold area.
6. GREEN BELT DEVELOPMENT
The proposed green belt in the lease area is to be developed taking into
consideration the availability of area as the efficiency of green belt in pollution
control mainly depends on tree species, its width, distance from pollution
sources, side of the habitat from working place and tree height. The proposed
green belt has been designed to control PM10, gaseous pollutants, noise,
surface run off and soil erosion etc. While considering the above aspects due
care will be taken for selecting the suitable characteristics plant species such
as fast growing, locally suitable plant species, resistant to specific pollutant
and those which would maintain the regional ecological balance, soil and
hydrological conditions.
Greenbelt development programme will be designed within the natural
constraints of the site and in particular species selection reflects flora known to
be resistant to the local conditions. A Greenbelt development is necessary for:
1. Landscaping and providing shelter
2. Improvement in site conditions
3. Surface air purification by providing oxygen and letting SPM to settle on the
leaves.
25
EMP PROJECT: ICHADAG STONE DEPOSIT
APPLICANT: SRI ANKIT KUMAR SHARDA
4. To attenuate noise generated by movement of vehicles and other machinery.
Lessee will provide the plantation all along the pit boundary, mine office and all
along the roads.
6.1 Plantation Program
Under the afforestation plan, plantation in nearby villages and connecting
roads will be undertaken. The implementation for development of greenbelt will
be of paramount importance as it will not only add up as an aesthetic feature
but will also act as a pollution sink. The species to be grown in the areas
should be dust tolerant and fast growing species so that a permanent greenbelt
is created. Plantation in the barrier zone and roads is necessary as these areas
will contain fine particulates resulting from mining operation and vehicle
movement Plantation will also be carried out as social forestry programme in
village, school and the areas allocated by the Panchayat/State authorities.
Native plants like Neem, Peepal, Mango and other local species will be planted.
A suitable combination of trees that can grow fast and also have good leaf cover
shall be adopted to develop the greenbelt. It is proposed to native species along
with some fruit bearing and medicinal trees during the plan period.
Plantation
No of trees to be uprooted due to Mining operation: 1766 Trees will be planted in
the Dead Benches and the Safety Zone area during the life of the Mine.
26
EMP PROJECT: ICHADAG STONE DEPOSIT
APPLICANT: SRI ANKIT KUMAR SHARDA
Species for Plantation
S.No Plant Name Species
1 Neem Azadirachta indica
2 Jamun Syzygium cumini
3 Sisam Dalbergia Sissoo
4 Peepal Ficus religiosa
5 Amaltas Cassia fistula
6 Kadam Neolamarckia cadamba
The following characteristics will be taken into consideration while selecting
plant species for green belt development and tree plantation.
I. They will be local indigenous and drought resistant species.
II. They will be fast growing and tall trees.
III. They will be perennial and evergreen.
IV. They will should have thick canopy cover.
V. The planting will be around the site to prevent lateral pollution dispersion.
VI. The trees will maintain regional ecological balance and conform to soil and
hydrological conditions. Indigenous species will be preferred.
VII. Species will be planted as per CPCB guidelines and native species will be
selected.
6.2 GENERAL GUIDELINES FOR GREEN BELT DEVELOPMENT
i. Trees growing up to 5 m or more in height will be planted all around the mine
boundary.
27
EMP PROJECT: ICHADAG STONE DEPOSIT
APPLICANT: SRI ANKIT KUMAR SHARDA
ii. Plantation of trees will be done along road side and lease boundary.
iii. Trees will be planted along roadsides, to arrest auto-exhaust and noise
pollution, and in such a way that there is no direct line of sight to the
installation when viewed from a point outside the foliage perimeter.
iv. Since tree trunks are normally devoid of foliage (upto 3 m), it will be
appropriate to have shrubbery in form of such trees to give coverage to trunk
portion of these trees.
v. Fast growing trees with thick perennial foliage will be grown, as it will take
many years for trees to grow to their full height.
In order to facilitate the proper growth of vegetation, limited measures involving
preparation of seedbed with suitable amount of fertilizers and treatment with
mulches will be taken. The topsoil will be used for green belt development &
revegetation. Vegetation cover in and around the mine workings generally
helps in:
Stabilizing erodible slopes to minimize pollution
Control of dust.
Enhancement of aesthetic value.
Reducing noise.
For revegetation, the plants and saplings suitable for the existing soils and site
conditions may be considered. Fast growing local plant species will be planted,
which can adapt to the local climate.
This has to be done in consultation with local forest department.
7. MONITORING SCHEDULE AND ITS IMPLEMENTATION
S. No. Attributes Parameters Frequency
1
Ambient Air
Quality
PM2.5, SO2 , NO2
24 hourly samples twice a
week for three months at 3
locations
28
EMP PROJECT: ICHADAG STONE DEPOSIT
APPLICANT: SRI ANKIT KUMAR SHARDA
S. No. Attributes Parameters Frequency
3
Water
quality
Physical, Chemical
and Bacteriological
parameters at 2
ground water and 2
surface water
locations.
Grab samples will be collected
once during study period.
4
Soil quality
Soil samples will be
collected at strategic
locations.
Grab samples will be collected
once during study period.
5
Ecology
Existing terrestrial
and aquatic flora and
fauna in 10-Km
radius.
Through field studies once
during study period.
Secondary data will also be
collected.
6
Noise levels
Noise levels in dB (A)
at 10 locations will be
monitored.
Noise levels in and around the
project area will be monitored
every hour for 24 hours at
each location once during
study period.
7
Land use
Trend of land use
change for different
categories
Based on data collected from
secondary sources like census
abstracts of census of India
2011 and satellite imagery.
8 Geology Geological history Data will be collected from
secondary sources
9
Hydrogeolo
gy
Drainage area and
pattern, nature of
streams, aquifer
characteristics,
Hydro-geological data based
on primary and secondary
sources
29
EMP PROJECT: ICHADAG STONE DEPOSIT
APPLICANT: SRI ANKIT KUMAR SHARDA
S. No. Attributes Parameters Frequency
recharge and
discharge areas
10
Socio-
Economic
aspects
Socio-economic
characteristics: i.e.
demographic
structures, population
dynamics,
infrastructure
resources, health
status, economic
resources.
The data on demographic
profile in the study area will be
collected from primary and
secondary sources like census
abstracts of census of India
2011
8. COST OF EMP IMPLEMENTATION
A yearly cost of implementation of mitigation measures envisaged as mentioned
below for the project works out to be:
SI. No. Measures Capital cost (in
Rs.)
Total Recurring Cost
(in Rs.)
1
Pollution Control
i) Dust Suppression
ii) Garland drain & ground dump
- 1,00,000 /-
1,00,000 /-
2
Pollution Monitoring
i) Air pollution
ii) Water pollution
- 50,000 /-
50,000 /-
3 Green Belt 2,00,000 /- 1,00,000 /-
4 Reclamation of mined out area 50,000 /- 50,000 /-
Total 2,50,000 /- 4,50,000 /-
***************