project portfolio management considering resources - impossible - presentation joerg...
DESCRIPTION
Project Portfolio Management considering Resources! Impossible? Joerg Leute's presentation at Gartner PPM and IT Governance Summit 2013, LondonTRANSCRIPT
PROJECT PORTFOLIO MANAGEMENT CONSIDERING RESOURCES! IMPOSSIBLE?
Gartner PPM and IT Governance Summit 2013 | London
19.06.2013 Gartner PPM and IT Governance Summit 2013 | London 2
RESOURCE MANAGEMENT – A TYPICAL SETTING FROM A CUSTOMER IN THE BANKING SECTOR
Setting
• 50 projects are competing for around 110 IT-developers
• Extreme bottlenecks in some dev teams
• Strategical and legal topics with hard deadlines
• Dynamic portfolio with pressure from technical innovation, new trends, security concerns and new product ideas
The task: Set up a project portfolio with
• The right topics
• At the right time
• With the optimal usage of the resource
CHALLENGE 1: MISSING VISIBILITY OF PROJECT-IMPACT ON RESOURCES
19.06.2013 Gartner PPM and IT Governance Summit 2013 | London 4
MISSING VISIBILITY
CHALLENGE 2: THE MISMATCH OF CURRENT PORTFOLIO-APPROACHES WITH RESOURCES
19.06.2013 Gartner PPM and IT Governance Summit 2013 | London 6
HOW TO RANK PROJECTS?
19.06.2013 Gartner PPM and IT Governance Summit 2013 | London 7
WITH FINANCIALS?
20.000 €
70.000 €
10.000 €
50.000 €
19.06.2013 Gartner PPM and IT Governance Summit 2013 | London 8
MISMATCH
CHALLENGE 3: ARTIFICIAL INTELLIGENCE
19.06.2013 Gartner PPM and IT Governance Summit 2013 | London 10
AUTO OPTIMIZE THIS (SIMPLE EXAMPLE)
n
in
nn
t t RoletyAvailabili
RoleDemand
iRisk
lignmentStrategicA
Cost
Benefits11 )(
)(*
)*1(
1**
19.06.2013 Gartner PPM and IT Governance Summit 2013 | London 11
EFFICIENT FRONTIER
19.06.2013 Gartner PPM and IT Governance Summit 2013 | London 12
OPTIMIZING THE WRONG THINGS
AND THAT LED TO
19.06.2013 Gartner PPM and IT Governance Summit 2013 | London 14
AND THAT LED TO
• Piles of Excel outside the actual PPM tool
• Disappointments : „it took us so long to get the operative resource management processes to work – why can‘t we use it for strategical decisions then?“
• Still bottlenecks
• Still unused capacities
• Still people knowing it better
PROJECT PORTFOLIO MANAGEMENT CONSIDERING RESOURCES IMPOSSIBLE?
TOOLS: ARTIFICIAL INTELLIGENCE IS NOT THE SOLUTION
The Law of Requisite Variety
To control a system of a certain complexity, we need another system with a greater complexity.*
* “If a system is to be stable the number of states of its control mechanism must be greater than or equal to the number of states in the system being controlled.” Ashby, William Ross, An Introduction to Cybernetics, Chapman & Hall, London, 1956, p. 124
THE MEISTERPLAN HYPOTHESES
1. The human brain is by far more complex than a set of project plans.
2. IT should do what IT does best: calculate.
3. An experienced person that is supported by a responsive IT tool will be able to create masterly plans. Meisterplans.
quick live demonstration
to demonstrate the benefits of this approach
19.06.2013 Gartner PPM and IT Governance Summit 2013 | London 20
Prioritize Prioritize Prioritize
Identify Generic
Roles
Determine the
Quantity of Each
Role
Identify Bottleneck Resource /
People
Match High-level
Demand to Supply
Time-sequence Projects
Send to PMO for Resource Allocation
SO: ALL TASKS ARE CHECKED
A Realistic Stream of Work is Capacity Constrained
Concept Document
Go/No Go
Business Case
Proposed Portfolio
Portfolio Analyzed
Portfolio Approved
• Not yet another PPM-Tool - Business Intelligence for Resources.
• Specializes on resource issues • Interactive and Intuitive • Reads and consolidates data from
common PPM-software (including Excel) • In the cloud or on premise
19.06.2013 Gartner PPM and IT Governance Summit 2013 | London 22
Joerg Leute
Tel. +49 7071 3667-7401 www.meisterplan.com
twitter.com/meisterplaner
facebook.com/MEISTERPLAN