project planning
TRANSCRIPT
AIM: To study and perform Project Planning
Theory:
Project Planning
There are several reasons to use considerable care when planning projects:
The primary purpose of planning is to establish a set of directions in enough detail to tell the project team exactly what must be done
The purpose of planning is to facilitate later accomplishment
The Work Breakdown Structure
The Work Breakdown Structure (WBS) can take a variety of forms that serve a variety of purposes. The WBS often appears as an outline with Level I tasks on the left and successive levels appropriately indented. The WBS may also picture a project subdivided into hierarchical units of tasks, subtasks, work packages, etc.
The WBS is an important document and can be tailored for use in a number of different ways:
It may illustrate how each piece of the project contributes to the whole in terms of performance, responsibility, schedule, and budget
It may list the vendors or subcontractors associated with specific tasks It may serve as the basis for making cost estimates or estimates of task duration It may be used to document that all parties have signed off on their various commitments to the
project
General steps for designing and using the WBS:
1. Using information from the action plan, list the task breakdown in successively finer levels of detail. Continue until all meaningful tasks or work packages have been identified
2. For each such work package, identify the data relevant to the WBS. List the personnel and organizations responsible for each task.
3. All work package information should be reviewed with the individuals or organizations who have responsibility for doing or supporting the work in order to verify the accuracy of the WBS
4. The total project budget should consist of four elements: direct budgets from each task; an indirect cost budget for the project; a “contingency” reserve for unexpected emergencies; and any residual, which includes the profit derived from the project
5. The project master schedule integrates the many different schedules relevant to the various parts of the project
6. The project manager can examine actual resource use, by work element, work package, task, up to the full project level. The project manager can identify problems, harden the estimates of final cost, and make sure that relevant corrections have been designed and are ready to implement
7. The project schedule may be subjected to the same comparisons as the project budget. Actual progress is compared to scheduled and corrective action can be taken
DELIVERABL E DEFINITION TABLE
DELIVERABLE STRUCTURE STANDARDS APPROVAL NEEDED BY
RESOURCES REQUIRED
Problem Definition and
Scope
Document As defined in project
methodology
Project Manager Project team and Office tools
Feasibility Study Document AS defined in project
methodology
Project Manager Project team and Office tools
Project Charter Document As defined in project
methodology
Project Manager Project Manager, Project team and office
toolsResource and
budget assessment
Document As defined in project
methodology
Project sponsor and
Project Manager
Project Manager, Project team, Project sponsors and office
toolsRequirement
AnalysisDocument As defined in
project methodology
Project Manager Customer, System Analyst and
Office toolsRisk management
and SchedulingDocument As defined in
Project methodology
Project Manager System Analyst and Project Team
Physical and Technical Designs
Document As defined in Project
methodology
Project Manager Programmer, System Analyst and Case tools
User Interface Prototype As defined inUser Interface
Guidelines
Project Sponsor and Project
Manager
Programmer and Integrated
Development Environment(Netbeans)
Application System
Files and Database
As defined inProject
methodology
Project Sponsor and
Project Manager
Programmers, System Analyst, Networking
Specialist and Server(Xampp Server)
Testing Plan Document As defined inProject
Methodology
Project manager System Analyst and Office tools
Testing Results Document As defined inTest Plan
Project Manager Programmer, System Analyst and Office tools
Final Report and Presentation
Document As defined inProject
methodology
Project manager,External
examiner
Project Sponsor, Project Manager, System and
Project teamProject Evaluation
andLessons learned
Document As defined inProject
methodology
Project manager Project team and knowledge
management systemDELIVERABLE STRUCTURE CHART
InitializationInitialization
Work breakdown Structure
Define Project GoalDefine Project Goal
Work Package
Work Package for R-Tree Implementation:
1. Statement of Work:
Retrieval of images using content based retrieval and implementation of
r-tree algorithm.
2. Resource Requirement:
Labor 4 for 16 weeks 1 manager, 1 programmer, 1 database designer, 1 GUI
designer, 1 tester. Material
Software Requirement:XAMP server, Web host
Hardware Requirement:Computers
Facility: Internet, place.
3. Time: 16 weeks 24th August to 10th April
4. Cost: 1 Manager : 10hrs 5000 1 Programmer : 100hrs 10000 1 Database designer : 25hrs 2000 1 GUI designer : 15hrs 1000 1 tester :20hrs 1500
TOTAL 19500 10% TAX 1950
5. Responsibility:
Name Designation Responsibility
Roopali Lolage Manager To keep a track on project work and guide for changes to be made.
ShyamMahishi Programmer To code in ASP.netSagar Awasare Database designer To design database Rajesh Mothe GUIdesigner To design GUI
6. Output/Outcome:Fast retrieval of images on web.
7. Input:Design, Programming codes,Algorithms,Image
8. Quality Assurance:
The images are retrieved at a faster rate using r-tree algorithm in comparison to linear search of images.Content based retrieval of images helps retrieval of images with similar characteristics like color, structure etc.
9. Others:This project can be sold to clients on the contract basis.
RESPONSIBILITY MATRIX
Responsibility CodesP :- Primary ResponsibilityS :- Secondary ResponsibilityN :- Must be notifiedA :- Must give approval
PROJECT TASK OR ACTIVITY
PROJECT MANAGER(ROOPALI LOLAGE)
SHYAM MAHISHI SAGAR AWASARE RAJESH MOTHE
PROJECT COORDINATION
P
PROJECT DEVELOPMENT
A
PROJECT DESIGN A N S SGUI DESIGN N,A PDATABASE DESIGN
N,A P
DEFINING PROJECT GOAL
N,A P S
SOFTWARE PURCHASE
N P
RISK MANAGEMENT
A P S S
REQUIREMENT ANALYSIS
N P P P
FEASIBILITY STUDY
A S P
PROJECT CHARTER
N,A P P P
FINAL REPORT AND PRESENTATION
A,N P S