project no.: 17028 mississippi state university ... · project no.: 17028 mississippi state...

124
PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING COMMISSIONING OF THERMAL MARCH 2018 AND MOISTRE PROTECTION – 070800 1 OF 12 SECTION 07 08 00 - COMMISSIONING OF THERMAL AND MOISTURE PROTECTION PART 1 - GENERAL 1.1 INTRODUCTION A. As defined in Section 50 91 00 Commissioning Requirements, the commissioning process requires that selected elements of the Building Envelope be laboratory and field tested to confirm that construction achieves the Owner’s needs and objectives and that the assembly performs in the manner for which it was intended. This specification identifies the assemblies’ testing requirements prior to delivery of materials as well as field tests required. The scope of commissioning testing (i.e. area and amount to be tested), responsibilities, failed test result requirements and testing documentation are defined in this specification. B. Included are the following documents which shall become a part of this section. 1. CxGBS Field Test No. 01, Flashing / Weep Test 2. CxGBS Field Test No. 03, Roof and Roof Drain Test 3. CxGBS Field Test No. 04, Water Leakage Test for Subterranean Drainage 4. CxGBS Field Test No. 05, Testing of Sealants / Joints 5. CxGBS Field Test No. 06, Testing of Penetrations Through Air/Water Barriers 6. CxGBS Field Test No. 07, HVAC Roof Curb Test 1.2 OVERVIEW A. The attached CxGBS Field Test Procedures detail step-by-step procedures to be directed and witnessed by the CxA and executed by the Contractor. The commissioning test requirements for selected configuration of the building envelope assembly contain the following: 1. The contractors/CxA responsible to execute the tests, under the direction of the CxA 2. A list of integral components being tested 3. Functions to be tested 4. Required conditions of the test 5. Special procedures 6. Required methods of testing 7. Acceptance criteria 8. Sampling strategies allowed 9. Failed test action 10. Re-testing requirements and resultant scope changes 11. Operable openings 1.3 PREREQUISITES C. The Construction Checklists, applicable to the area and components being tested, are required to be completed and signed by the responsible contractor and checked off by the CxA prior to commissioning testing. D. Flashing/Weep Test: The exterior wythe of masonry has been installed up to no more than 16” above the flash/weep elevation and allowed to set no less than forty-eight (48) hours. PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION 3.1 COMMISSIONING TESTING OF FREE STANDING MOCK-UPS OF EXTERIOR WALL ASSEMBLY A. Where any of the building components listed within this specification as requiring field testing, are a part of a mock-up to be constructed separately from the building, for the purpose of studying appearance, construction technique or building product, that mock-up shall be tested as though it is a part of the building. 3.2 COMMISSIONING TESTING OF MOCK-UP OF EXTERIOR WALL ASSEMBLY

Upload: others

Post on 04-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

COMMISSIONING OF THERMAL MARCH 2018 AND MOISTRE PROTECTION – 070800 1 OF 12

SECTION 07 08 00 - COMMISSIONING OF THERMAL AND MOISTURE PROTECTION

PART 1 - GENERAL 1.1 INTRODUCTION

A. As defined in Section 50 91 00 Commissioning Requirements, the commissioning process requires that selected elements of the Building Envelope be laboratory and field tested to confirm that construction achieves the Owner’s needs and objectives and that the assembly performs in the manner for which it was intended. This specification identifies the assemblies’ testing requirements prior to delivery of materials as well as field tests required. The scope of commissioning testing (i.e. area and amount to be tested), responsibilities, failed test result requirements and testing documentation are defined in this specification.

B. Included are the following documents which shall become a part of this section. 1. CxGBS Field Test No. 01, Flashing / Weep Test

2. CxGBS Field Test No. 03, Roof and Roof Drain Test

3. CxGBS Field Test No. 04, Water Leakage Test for Subterranean Drainage

4. CxGBS Field Test No. 05, Testing of Sealants / Joints

5. CxGBS Field Test No. 06, Testing of Penetrations Through Air/Water Barriers

6. CxGBS Field Test No. 07, HVAC Roof Curb Test

1.2 OVERVIEW

A. The attached CxGBS Field Test Procedures detail step-by-step procedures to be directed and witnessed by the CxA and executed by the Contractor. The commissioning test requirements for selected configuration of the building envelope assembly contain the following: 1. The contractors/CxA responsible to execute the tests, under the direction of the CxA 2. A list of integral components being tested 3. Functions to be tested 4. Required conditions of the test 5. Special procedures 6. Required methods of testing 7. Acceptance criteria 8. Sampling strategies allowed 9. Failed test action 10. Re-testing requirements and resultant scope changes 11. Operable openings

1.3 PREREQUISITES

C. The Construction Checklists, applicable to the area and components being tested, are required to be completed and signed by the responsible contractor and checked off by the CxA prior to commissioning testing.

D. Flashing/Weep Test: The exterior wythe of masonry has been installed up to no more than 16” above the flash/weep elevation and allowed to set no less than forty-eight (48) hours.

PART 2 - PRODUCTS

NOT USED

PART 3 - EXECUTION 3.1 COMMISSIONING TESTING OF FREE STANDING MOCK-UPS OF EXTERIOR WALL

ASSEMBLY

A. Where any of the building components listed within this specification as requiring field testing, are a part of a mock-up to be constructed separately from the building, for the purpose of studying appearance, construction technique or building product, that mock-up shall be tested as though it is a part of the building.

3.2 COMMISSIONING TESTING OF MOCK-UP OF EXTERIOR WALL ASSEMBLY

Page 2: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

COMMISSIONING OF THERMAL MARCH 2018 AND MOISTRE PROTECTION – 070800 2 OF 12

A. If no free standing mock-up is constructed, a mock-up of the exterior wall assembly will be constructed as a part of the building in order to test elements of the building envelope. This mock-up will be initially tested and, if required, re-tested until accepted. This test will be completed prior to any further construction of that element of the building.

3.3 COMMISSIONING TESTING OF BUILDING ENVELOPE

A. Integral Components or Assemblies to be Field Tested 1. Roof system

2. Air/water barriers

3. Joint sealants

4. Weep system at masonry cavity walls

5. Utility penetrations

6. Louvers

7. Subterranean drainage

B. Parties Responsible to Execute Commissioning Testing 1. The General Contractor (GC) shall have the overall responsibility for Field Testing. The GC

shall coordinate all testing activity with the responsible Sub-Contractor, the CxA, and the Owner’s Representative.

2. Selected Sub-Contractors shall be responsible for the testing related to their respective disciplines and areas of work. These Sub-Contractors shall arrange for, provide all labor and equipment for and perform tests as directed and witnessed by the CxA.

3. In the event of a test “failure,” the responsible Sub-Contractor shall correct all deficiencies and arrange for re-testing with the GC. (Reference each of the Tests for the re-testing requirements and resultant scope change. Also reference Section 019100 – 3.04 NON-CONFORMANCE AND APPROVAL OF TESTS for re-testing requirements and resultant scope change.)

3.4 RANDOM COMMISSIONING TESTING OF EXTERIOR WALL CAVITIES

A. Reference CxGBS Field Test No. 01, Flashing / Weep Test for testing requirements

B. Parties Responsible to Execute Commissioning Testing 1. Contractor and/or Masonry Contractor, under the direction of the CxA, will introduce

continuous flow of water into cavity at a rate of two (2) gallons per minute for a minimum of ten (10) minutes per ten (10) lineal feet.

2. CxA to witness, direct and document testing.

C. Issues with Exterior Wall Cavities 1. The Masonry Contractor and/or responsible contractor shall, at his expense, remove, repair

and replace cavity wall components found to be in variance with the contract documents.

3.5 COMMISSIONING TESTING OF ROOF ASSEMBLIES

A. Reference CxGBS Field Test No. 03, Roof Drain

B. Parties Responsible to Execute Commissioning Testing 1. Contractor and/or Roofing Contractor, under the direction of the CxA, will, sequentially and

simultaneously, plug all primary roof drains and flood the roof areas to the point that secondary roof drains or area scuppers are tested and carry off water. After checking for leaks, proper operation of the secondary drains/scuppers, the plug is to be released and allow the primary drain to remove the accumulate water, again checking for leaks and proper operation of the drains and piping

2. CxA to witness, direct and document testing.

C. Issues with Roof, Roofing Accessories and Roof Drainage 1. The Roofing Contractor shall, at his expense, remove, repair and replace roofing found to be

in variance with the contract documents.

D. Reference CxGBS Field Test No. 07, HVAC Roof Curb Test 1. HVAC roof curbs must be tested prior to and after installation of HVAC equipment using a

modified AAMA 501.2 procedure.

3.6 COMMISSIONING TESTING OF SUBTERRANEAN DRAINAGE

A. Reference CxGBS Field Test No. 04, Water Leakage Test for Subterranean Drainage

Page 3: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

COMMISSIONING OF THERMAL MARCH 2018 AND MOISTRE PROTECTION – 070800 3 OF 12

B. Parties Responsible to Execute Commissioning Testing 1. Drainage Contractor, under the direction of the CxA, will introduce water into the foundation

drainage system. 2. CxA to witness, direct and document testing

C. Issue with Subterranean Drainage System 1. The Drainage Contractor shall, at his expense, remove, repair and replace drainage system

components found to be in variance with the contract documents.

3.7 COMMISSIONING TESTING OF SEALANT JOINTS

A. Reference CxGBS Field Test No. 05, Testing of Sealants / Joints

B. Parties Responsible to Execute Commissioning Testing 1. Sealant Contractor and the CxA will initially review the various types of joints required for the

project and identify the specified sealant product to be installed at that type of joint. 2. CxA to witness, direct and document testing

C. Issue with Joints and Sealants 1. The Sealant Contractor shall, at his expense, remove, repair and replace joint treatment

found to be in variance with the contract documents.

3.8 COMMISSIONING TESTING OF AIR/WEATHER BARRIER

C. Reference CxGBS Field Test No. 06, Air / Weather Barrier Test

D. Parties Responsible to Execute Commissioning Testing 1. Installing Contractor, under the direction of the CxA, will introduce continuous flow of water

onto the air/weather barrier for a minimum of twenty (20) minutes per ten (10) lineal feet. 2. CxA to witness, direct and document testing

D. Issue with Joints and Sealants 1. The Installing Contractor shall, at his expense, remove, repair and replace joint treatment

found to be in variance with the contract documents.

3.9 TABLE 1: ADDITIONAL COMMISSIONING TESTING REQUIREMENTS

The following testing requirements in Table 1 are an addition to and do not replace any testing requirements elsewhere in the specification.

Table 1: Additional Testing Requirements

Function / Mode

Test Method Manual,

Monitoring, Either or

Both3

Required Seasonal

Test1

General

1. Sections of exterior wall will be constructed as stand-alone mock-up units or constructed in place and serve as mockups which may remain as part of the installation. The mockups will serve to perfect installation practices prior to the construction of the exterior walls. The mockups shall contain each component of the exterior wall assembly as it will be installed on the remaining building exterior. The mockup shall be tested as an assembly focusing on intersections between assembly components generally following AAMA 501.2 test method and ASTM E 783.

Manual

In addition to, or as part of (1) above, the following modes or tests are required:

2. Random testing of building exterior generally following AAMA 501.2 test method as directed by the CxA.

Manual

3. Flood testing of selected roof assemblies. Manual

Page 4: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

COMMISSIONING OF THERMAL MARCH 2018 AND MOISTRE PROTECTION – 070800 4 OF 12

CxGBS FIELD TEST No. 01 FLASHING/WEEP FIELD TEST PROCEDURE at EXTERIOR MASONRY VENEER WALLS for INSTALLED FLASHING and WEEP HOLE EFFICACY. A. Purpose: To observe during the construction process that the flashing and weep hole assembly

installed in masonry veneer cavity walls successfully allows water to exit the cavity. Positive tests results are required to confirm the adequacy of the design and the construction installation technique prior to proceeding.

B. CxGBS: CxGBS will select the locations to be tested in accordance with the following guidelines. Locations:

1. At the lowest base line of the wall assembly 2. At intermittent shelf angles 3. At the head of building penetrations 4. At all other locations where flashing and weep holes are required

C. Scope: 1. Observe a minimum of 10% of the length of each type of horizontal condition

2. Observe a minimum of 10% of the number of each type of building penetrations 3. Observe a minimum of (2) two locations at all sides of the building. 4. If a test receives a “NOT PASSED” grade reference Para. E-5. 5. CxGBS to direct and witness testing execution

D. Contractor: It shall be the responsibility of the contractor and his sub-contractors to coordinate and conduct all aspects of the test execution including but not limited to: 1. Scheduling of work to comply with test requirements 2. Advanced notification (two week minimum) to CxGBS of schedule related to work to

be tested 3. Provide access, equipment, labor and utilities as required for each test 4. Administer test as directed and witnessed by the CxA and take any corrective action

to correct defects in materials, construction methods or workmanship revealed as a result of the testing process.

E. Conditions: Test after the exterior wythe of masonry has been installed up to no more than 16” above the flash/weep elevation and allowed to set no less than 48 hours.

F. Test: 1. Spray the cavity from above with a continuous flow of water delivered at a rate of two (2) gallons per minute for a minimum of ten (10) minutes per ten (10)

lineal feet. (20 gal. per 10’-0” of cavity) 2. Give reasonable assurance that water finds its way out through the weep holes and

that no standing water remains in the cavity. 3. A test has “PASSED” if no leakage is observed from the inside of the building

envelope and if all water drains from the cavity within 2 hours after the water supply has been terminated.

4. A test has “NOT PASSED” if water remains in the cavity after the 2 hour period. 5. A “NOT PASSED” test automatically requires that an ADDITIONAL 10% of previously

untested wall be tested. The portion of a wall that received a “NOT PASSED” grade must be repaired and then re-tested.

G. Report: CxGBS will document the results of each test on CxGBS Field Reports and circulate the report to the Owner’s Representative, A/E and the project team.

End of CxGBS FIELD TEST No. 01 Flashing/Weep Testing

Page 5: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

COMMISSIONING OF THERMAL MARCH 2018 AND MOISTRE PROTECTION – 070800 5 OF 12

CxGBS FIELD TEST No. 03 ROOF and ROOF DRAIN TEST FIELD TEST PROCEDURE for TESTING ROOFS, ROOF DRAINS and RELATED OVERFLOW DRAINS and SCUPPERS

A. Purpose: To visually observe and document prior to occupancy that the roof drainage system operates as intended. Positive tests results are required. Negative test results generate a full investigation as to the cause of failure plus the required repair and corrections necessary to prevent reoccurrence of any issues. Retesting of failed elements is required.

B. Scope: The roofing area will be flooded to include at least one drain as well as the area affected by that drain’s functionality. Water will not accumulate to a live load weight exceeding twenty (20) pounds before beginning to overflow into the overflow drains/scuppers. 1. The entire roof will be tested. 2. At roofs with more than 10 primary drains per section/elevation, sampling may occur.

C. CxGBS: CxGBS is to manage and witness all testing operations. 1. CxGBS will select the locations to be tested in accordance with the following

guidelines: a. At each “Type” of drain. Roof drain, spillway, scupper, etc. b. At each roof level

2. CxGBS will determine, according to the guidelines above, the specific locations to be tested on site and annotate where each test is conducted in their field report.

NOTE: Reduced construction documents will be the basis for these reference documents.

D. Contractor: It shall be the responsibility of the General Contractor and his sub-contractors to coordinate and conduct all aspects of the testing process including but not limited to: 1. Scheduling of work to comply with test requirements

Note: CxGBS encourages the General Contractor to take advantage of rain

events in conducting roof drain testing. CxGBS will make every attempt to accommodate the execution of testing when rain is predicted.

2. Advanced notification (two week minimum) to CxGBS of schedule related to work to be tested. (see Note above regarding testing at rain events)

3. Provide signed checklists prior to test. 4. Provide access, labor and utilities as required for each test 5. Take any corrective action to repair defects in materials, construction methods or

workmanship revealed as a result of the testing process. Document the corrective action and make arrangements for retesting with CxGBS

6. Administer test.

E. Conditions: Test condition only after confirmation by signed Construction Checklist that the roof and drainage system is complete and ready for this test procedure. 1. Coordinate construction when possible to allow for roof drain testing to be performed

prior to the installation of interior finishes.

F. Equipment: The following “Test” equipment is to be available at all testing events. 1. Furnished by the Contractor

a. Water sources (hose bibs) and ¾” ID hose (with on/off control) of sufficient length to access all roof locations as outlined in Para. C.

b. Drain plugs

G. Testing: The following “Test Procedure” shall be observed as closely as is reasonably possible. Any modification to this procedure shall only occur at the direction of the CxGBS representative directing and observing the testing. 1. Pretest the roof drain in the selected roof area by running water into the main and

overflow drains for two (2) minutes and around the drains for an additional two (2) minutes. Verify that no water is entering the interior of the space below.

2. Plug the main roof drain in the test area. 3. Flood the area to the point that water flows into the overflow drain or into the scupper

serving the area. Continue water delivery for two (2) minutes to confirm that the sub-system is draining and that water is not accumulating in locations other than in the drainage path.

Page 6: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

COMMISSIONING OF THERMAL MARCH 2018 AND MOISTRE PROTECTION – 070800 6 OF 12

4. Observe that all overflows drain water to “daylight” that will be easily seen by personnel in the area.

5. An observer on the indoor side of the roof, using a flashlight if necessary, shall check for any water leakage and shall note where it occurs.

6. Release the drain plug at the main drain and confirm that all water is drained from the test area.

7. During the release, an observer on the indoor side of the roof, using a flashlight if necessary, shall check for any water leakage and shall note where it occurs.

8. A test area has “PASSED” if water drains from the test area via both through the overflow drainage system (being visible as an overflow drain) and then out the main roof drain and no water is visible at the interior side of the test area within (15) fifteen minutes after the test.

9. A test has “NOT PASSED” if water does not drain from the test area via both through the overflow drainage system (overflow drain or scupper) and then out the main roof drain or penetrates into the interior in the area of the test.

10. The drainage system that received a “NOT PASSED” grade must be repaired and then re-tested. If 100% of the roof was not observed on the first test, A “NOT PASSED” test automatically requires that an ADDITIONAL 10% of the roof drains be tested.

G. CxGBS Responsibility: 1. CxGBS will observe and document the results of each test on “CxGBS Field Reports”

and circulate the report to the Owner’s Representative, A/E, and the project team. 2. Observe retest and document as required.

H. Contractor responsibility: 1. In the event of a “Not Passed” report the General Contractor shall investigate the

issue and determine the sub-contractor or group of sub-contractors required to make the necessary corrections

2. Contractors shall take corrective action to repair defects in materials, construction methods or workmanship revealed as a result of the testing process. Document the corrective action and make arrangements for retesting with CxGBS

3. Repair any interior damage caused by the “Not Passed” test 4. Perform re-test if required.

End of CxGBS FIELD TEST No. 03 ROOF DRAIN TEST

Page 7: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

COMMISSIONING OF THERMAL MARCH 2018 AND MOISTRE PROTECTION – 070800 7 OF 12

CxGBS Field Test No. 04, Water Leakage Test for Subterranean Drainage

FIELD TEST PROCEDURE for WATER LEAKAGE at FOUNDATION WALL PENETRATIONS.

A. Purpose: To visually observe and document during the construction process that the adhesion of sealants perform successfully. Positive tests results are required to confirm the adequacy of the design and the construction installation technique prior to proceeding.

B. Scope: The area to be tested shall include foundation surfaces, geo-tech sock, gravel bed, foundation drains and foundation penetrations. 1. Test the entire foundation system to check all drains except for foundations with a

number of drains where sampling may be feasible. 2. Test all penetrations through the foundation walls.

C. CxGBS: CxGBS is to direct and witness testing executions. 1. CxGBS will select the locations to be tested in accordance with the following

guidelines: a. “Type” of drain b. Foundation level c. Locations where water intrusion would cause damage

2. CxGBS will determine, according to the guidelines above, the specific locations to be tested on site and annotate where each test is conducted in the field report.

NOTE: Reduced construction documents will be the basis for these reference documents.

D. Contractor: It shall be the responsibility of the contractor and his sub-contractors to coordinate and conduct all aspects of the test execution including but not limited to: 1. Scheduling of work to comply with test requirements 2. Advanced notification (two week minimum) to CxGBS of schedule related to work to

be tested 3. Provide access, equipment, labor and utilities as required for each test. 4. Administer test as directed and witnessed by the CxA. Take any corrective action to

repair defects in materials, construction methods or workmanship revealed as a result of the testing process. Document the corrective action and make arrangements for retesting with CxGBS

E. Conditions: Test location only after the installation of waterproofing, drainage mat, protection board, geo-tech sock and gravel bed. 1. Testing shall be completed prior to back-filling

F. Equipment: The following “Test” equipment is to be available at all testing events. 1. Furnished by the Contractor

a. Water sources (hose bibs) and ¾ ID hose of sufficient length to access all openings as outlined in Para. C.

G. Testing: The following “Test Procedure” shall be observed as closely as is reasonably possible. Any modification to this procedure shall only occur at the direction of the CxGBS representative directing and observing the testing. 1. Hose test the foundation drain system prior to back-filing, starting at the high point of

the pipe. 2. Hose test all penetrations through the foundation walls. 3. A test area has “PASSED” if the water drains from the test area through the

foundation drain and no water is visible at the interior side of the test area within fifteen (15) minutes after the test.

4. A test has “NOT PASSED” if water does not drain from the test area through the foundation drain or penetrates into a non-designated testing area.

5. The drainage system that receives a “NOT PASSED” grade must be repaired and then re-tested. If 100% of the foundation was not checked on the first test, a “NOT PASSED” test automatically requires that an ADDITIONAL 10% of the foundation drains be tested.

H. Report: CxGBS will document the results of each test via a CxGBS Field Report and circulate the report to the Owner’s Representative, A/E and the project team.

End of CxGBS FIELD TEST No. 04 Subterranean Drainage Test

Page 8: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

Project #15017 Mississippi State University Mississippi State, MS GS #113-141 Animal & Dairy Sciences Building

September 2016 – Section #070800 Commissioning of Thermal Page 8 of 12 and Moisture Protection

CxGBS Field Test No. 05, Testing of Sealants/Joints

FIELD TEST PROCEDURE for SEALANTS AND JOINTS.

A. Purpose: To visually observe and document during the construction process that the adhesion of sealants perform successfully. This field test does not evaluate the performance of a sealant joint as a weatherseal, but rather only evaluates the characteristics of the adhesive bond relative to the cohesive strength of the sealant in a particular installation. Since any failures that result from use of this test method are intentionally induced, they do not necessarily mean that the sealant joint will not perform as a weatherseal. Positive tests results are required to confirm the adequacy of the design and the construction installation technique prior to proceeding.

B. Scope: The area to be tested shall include any windows, doors, vents/grilles, mechanical penetrations, or intersection of materials featuring the use of sealants/adhesives on the building envelope. 1. Test all envelope penetrations featuring sealants.

C. CxGBS: CxGBS is to direct and witness testing executions. 1. CxGBS will select the locations to be tested in accordance with the following guidelines:

a. “Type” of opening in the building envelope b. “Type” of material used on c. Locations where water intrusion would cause damage

2. CxGBS will determine, according to the guidelines above, the specific locations to be tested on site and annotate where each test is conducted in the field report.

NOTE: Reduced construction documents will be the basis for these reference documents.

D. Contractor: It shall be the responsibility of the contractor and his sub-contractors to coordinate and conduct all aspects of the test execution including but not limited to: 1. Scheduling of work to comply with test requirements 2. Advanced notification (two week minimum) to CxGBS of schedule related to work to be tested 3. Provide access, equipment, labor and utilities as required for each test. 4. Administer test as directed and witnessed by the CxA. Take any corrective action to repair

defects in materials, construction methods or workmanship revealed as a result of the testing process. Document the corrective action and make arrangements for retesting with CxGBS

E. Conditions: Test location only after the sealant is fully cured (typically within 7 to 21 days after application). 2. The nondestructive methods are most effective while the sealant is in a state of extension due

to mild or low temperatures. They are least effective during high temperature when the sealant is in a compressed condition.

F. Equipment: The following “Test” equipment is to be available at all testing events. 1. Furnished by the Contractor

a. Sharp knife and materials and applications for the immediate repair of the sealant bead.

G. Testing: Standard Field Adhesion Test: The following “Test Procedure” shall be observed as closely as is reasonably possible. Any modification to this procedure shall only occur at the direction of the CxGBS representative directing and observing the testing.

6. Deconstructive Procedure: Test joint sealants according to Method A, Field-Applied Sealant Joint Hand Pull Tab, in Appendix X1 in ASTM C 1193 or Method A, Tail Procedure, in ASTM C 1521. a. Make a knife cut across the joint. b. Make cuts along each side of the joint approximately 3” (75 mm) long. c. Place a 1” (25mm) mark on the sealant tab. d. Grasp a 2” (50mm) piece of sealant firmly just beyond the 1” (25 mm) mark and pull at a

90° angle. e. If dissimilar substrates are being sealed, check the adhesion of sealant to each substrate

separately. This is accomplished by extending the cut along one side of the joint, checking adhesion to the opposite side, and then repeating for the other surface.

f. Inspect the joint for complete fill. The joint should not have voids and joint dimensions should match those shown in the weathersealing details.

g. The destructive procedure requires immediate repair of the sealant bead. 7. Non-Deconstructive Procedure:

a. The nondestructive procedure places strain on the sealant and a stress on the adhesive bond.

b. Though termed nondestructive, this procedure may result in an adhesive failure of a deficient sealant bead, but should not cause a cohesive failure in the sealant. The results of this procedure should be either adhesive failure or no failure.

Page 9: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

Project #15017 Mississippi State University Mississippi State, MS GS #113-141 Animal & Dairy Sciences Building

September 2016 – Section #070800 Commissioning of Thermal Page 9 of 12 and Moisture Protection

c. The non-destructive procedure can be used for continuous inspection of 100 % of the joint(s) or for any areas where deficient conditions, which are inconsistent with the practices of Guide C 1193, are suspected.

8. A test area has “PASSED” if no voids are discovered in the joint and the sealant was applied at the specified thickness.

9. A test has “NOT PASSED” if void are discovered, the adhesive fails, or improper application of sealant is discovered.

10. A “NOT PASSED” test automatically requires that an ADDITIONAL 10% of the openings sealants be tested. The sealant portions that received a “NOT PASSED” grade must be repaired and then re-tested.

H. Report: CxGBS will document the results of each test via a CxGBS Field Report and circulate the report to the Owner’s Representative, A/E and the project team.

End of CxGBS FIELD TEST No.05 SEALANTS/JOINTS TEST

Page 10: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

Project #15017 Mississippi State University Mississippi State, MS GS #113-141 Animal & Dairy Sciences Building

September 2016 – Section #070800 Commissioning of Thermal Page 10 of 12 and Moisture Protection

CxGBS FIELD TEST No. 06 AIR/WEATHER BARRIER TEST FIELD TEST PROCEDURE at INSTALLED AIR/WEATHER BARRIER AND PENETRATIONS. A. Purpose: To observe during the construction process that the air/weather barrier is installed properly and

successfully allows water to drain through the wall cavity. Positive tests results are required to confirm the adequacy of the design and the construction installation technique prior to proceeding.

B. CxGBS: CxGBS will select the locations to be tested in accordance with the following guidelines. Locations:

1. At lappings (if sheet applied) 2. At penetrations of the barrier

C. Scope: 1. Observe a minimum of 10% of the length of each type of horizontal condition 2. Observe a minimum of 10% of the number of each type of building penetrations 3. Observe a minimum of (2) two locations at all sides of the building. 4. If a test receives a “NOT PASSED” grade reference Para. E-5. 5. CxGBS to direct and witness testing execution

D. Contractor: It shall be the responsibility of the contractor and his sub-contractors to coordinate and conduct all aspects of the test execution including but not limited to: 1. Scheduling of work to comply with test requirements 2. Advanced notification (two week minimum) to CxGBS of schedule related to work to be tested 3. Provide access, equipment, labor and utilities as required for each test 4. Administer test as directed and witnessed by the CxA and take any corrective action to correct

defects in materials, construction methods or workmanship revealed as a result of the testing process.

E. Conditions: Test after the air/weather barrier has been installed per manufacturer’s instructions and prior to installation of other exterior wall layers.

F. Test: 1. Spray the air/weather barrier with a continuous flow of water delivered for a minimum of twenty (20) minutes per ten (10) lineal feet.

2. Give reasonable assurance that water drains downward across barrier. 3. A test has “PASSED” if no leakage is observed from the inside of the building envelope within

10 minutes after the water supply has been terminated. 4. A test has “NOT PASSED” if water is observed from the inside of the building envelope within

10 minutes after the water supply has been terminated. 5. A “NOT PASSED” test automatically requires that an ADDITIONAL 10% of previously untested

wall be tested. The portion of a wall that received a “NOT PASSED” grade must be repaired and then re-tested.

G. Report: CxGBS will document the results of each test on CxGBS Field Reports and circulate the report to the Owner’s Representative, A/E and the project team.

End of CxGBS FIELD TEST No. 06 Air/Weather Barrier Test

Page 11: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

Project #15017 Mississippi State University Mississippi State, MS GS #113-141 Animal & Dairy Sciences Building

September 2016 – Section #070800 Commissioning of Thermal Page 11 of 12 and Moisture Protection

CxGBS FIELD TEST No. 07 HVAC ROOF CURB TEST FIELD TEST PROCEDURE for WATER LEAKAGE at INSTALLED ROOF CURBS Windows, louvers, window wall, storefront assemblies, curtain wall, skylights, penetrations etc. including the juncture of these assemblies with the building envelope. NOTE: This CxGBS “FIELD TEST PROCEDURE for WATER LEAKAGE at INSTALLED ROOF CURBS” is similar to “American Architectural Manufacturers Association” (AAMA) document “AAMA 501-2-03, Quality Assurance and Diagnostic Water Leakage Field Check of installed Storefronts, Curtain walls and Sloped Glazing Systems.”

A. Purpose: To visually observe and document during the construction process that the installation

and assembly for the opening to be tested at exterior walls successfully prohibits water from penetrating

the assembly to the interior space. Positive tests results are required to confirm the adequacy of the

design and the construction installation technique prior to proceeding.

B. Scope: The area to be tested shall include, perimeter sealant (opening to building envelope),

adjacent building envelope components, typical splices, frame intersections, and all operable

components within the test area shall be isolated and exempt from the test procedure.

1. Test a minimum of 20% of roof curbs.

C. CxGBS: CxGBS is to direct and witness testing executions.

1. CxGBS will select the locations to be tested in accordance with the following guidelines:

a. Locations where water intrusion would cause damage

2. CxGBS will determine, according to the guidelines above, the specific locations to be

tested on site and annotate where each test is conducted in the field report.

NOTE: Reduced construction documents will be the basis for the reference documents in the field report.

D. Contractor: It shall be the responsibility of the contractor and his sub-contractors to

coordinate and conduct all aspects of the test execution including but not limited to:

1. Scheduling of work to comply with test requirements

2. Advanced notification (two week minimum) to CxGBS of schedule related to work to be

tested

3. Provide access, equipment, labor and utilities as required for each test. Utilities include

water at each location with enough pressure at the site to conduct the test to standard.

4. Administer test as directed and witnessed by the CxA. Take any corrective action to repair

defects in materials, construction methods or workmanship revealed as a result of the

testing process. Document the corrective action and make arrangements for retesting

with CxGBS

E. Conditions:

1. Test locations after completion of roofing and flashings but prior to installation of HVAC

equipment and after installation of HVAC equipment..

2. Testing shall be completed prior to installing interior finishes and closures. Vision access

to the interior surface of spandrel and/or insulated panels is critical to complete testing.

F. Equipment:

1. The following “Test” equipment is to be available at all testing events.

Furnished by the Contractor

a. Water source (hose bibs) and ¾” ID hose of sufficient length to access all openings as

outlined in Para. C. Minimum acceptable water pressure at each test location is 30 psi at

full flow.

2. Furnished by CxGBS

a. The test shall be conducted using a Type B-25, #6.030 brass nozzle with a ½” FPT. The

nozzle shall be connected to a ¾” ID coupling and shall be provided with a control valve

and a pressure gauge between the valve and the nozzle. The water pressure to the nozzle

shall be adjusted to produce 30 to 35 psi. at the nozzle inlet.

G. Testing: The following “Test Procedure” shall be observed as closely as is reasonably possible.

Any modification to this procedure shall only occur at the direction of the CxGBS representative

directing and observing the testing.

1. The designated test area shall be the whole perimeter of each selected roof curb.

Page 12: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

Project #15017 Mississippi State University Mississippi State, MS GS #113-141 Animal & Dairy Sciences Building

September 2016 – Section #070800 Commissioning of Thermal Page 12 of 12 and Moisture Protection

2. The designated test area shall evaluate sections of the framing and joint assembly. The

referenced nozzle shall be held at a distance of 1 ft +/- 1” from the location under test.

Each component of the test area shall be evaluated for a period of one (1) minute per foot

by slowly moving the nozzle back and forth over the test section while maintaining the

nozzle at a downward angle.

3. Working from the exterior, the wall test section shall be selectively wetted as directed by

the CxA.

4. A test area has “PASSED” if no water is visible at the interior side of the test area.

5. A test has “NOT PASSED” if water penetrates into the interior in the area of the test.

6. A “NOT PASSED” test automatically requires that an ADDITIONAL 10% of the assembly

be tested. The portion of a wall that received a “NOT PASSED” grade must be repaired

and then re-tested.

H. Report: CxGBS will document the results of each test via a CxGBS Field Report and circulate the

report to the Owner’s Representative, A/E and the project team.

End of CxGBS FIELD TEST No. 06 HVAC ROOF CURBS

END OF SECTION 07 08 00

Page 13: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SELF-ADHERING SHEET WATERPROOFING – 071326 1 OF 7

SECTION 071326 - SELF-ADHERING SHEET WATERPROOFING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Modified bituminous sheet waterproofing. 2. Molded-sheet drainage panels.

B. Related Requirements:

1. Section 334600 “Subdrainage” for elevator pit drainage system.

1.3 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1. Review waterproofing requirements including surface preparation, substrate condition and pretreatment, minimum curing period, forecasted weather conditions, special details and sheet flashings, installation procedures, testing and inspection procedures, and protection and repairs.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include construction details, material descriptions, and tested physical and performance properties of waterproofing.

2. Include manufacturer's written instructions for evaluating, preparing, and treating substrate.

B. Shop Drawings: Show locations and extent of waterproofing and details of substrate joints and cracks, sheet flashings, penetrations, inside and outside corners, tie-ins with adjoining waterproofing, and other termination conditions.

Page 14: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SELF-ADHERING SHEET WATERPROOFING – 071326 2 OF 7

C. Samples: For each exposed product and for each color and texture specified, including the following products:

1. 8-by-8-inch square of waterproofing and flashing sheet. 2. 4-by-4 inch square of drainage panel.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Installer.

B. Field quality-control reports.

C. Sample Warranties: For special warranties.

1.6 QUALITY ASSURANCE

A. Installer Qualifications: An entity that employs installers and supervisors who are trained and approved by waterproofing manufacturer.

B. Mockups: Build mockups to verify selections made under Sample submittals and to set quality standards for installation.

1. Build for each typical waterproofing installation including accessories to demonstrate surface preparation, crack and joint treatment, corner treatment, and protection.

a. Size: 100 sq. ft. in area. b. Description: Each type of wall installation.

2. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless Architect specifically approves such deviations in writing.

3. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Deliver liquid materials to Project site in original packages with seals unbroken, labeled with manufacturer's name, product brand name and type, date of manufacture, and directions for storing and mixing with other components.

B. Store liquid materials in their original undamaged packages in a clean, dry, protected location and within temperature range required by waterproofing manufacturer.

C. Remove and replace liquid materials that cannot be applied within their stated shelf life.

D. Store rolls according to manufacturer's written instructions.

E. Protect stored materials from direct sunlight.

Page 15: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SELF-ADHERING SHEET WATERPROOFING – 071326 3 OF 7

1.8 FIELD CONDITIONS

A. Environmental Limitations: Apply waterproofing within the range of ambient and substrate temperatures recommended by waterproofing manufacturer. Do not apply waterproofing to a damp or wet substrate.

1. Do not apply waterproofing in snow, rain, fog, or mist.

B. Maintain adequate ventilation during preparation and application of waterproofing materials.

1.9 WARRANTY

A. Manufacturer's Warranty: Manufacturer's standard materials-only warranty in which manufacturer agrees to furnish replacement waterproofing material for waterproofing that does not comply with requirements or that fails to remain watertight within specified warranty period.

1. Warranty Period: Three years from date of Substantial Completion.

B. Installer's Special Warranty: Specified form, on warranty form at end of this Section, signed by Installer, covering Work of this Section, for warranty period of two years.

1. Warranty includes removing and reinstalling protection board, drainage panels, and all other components of the system.

PART 2 - PRODUCTS

2.1 MATERIALS, GENERAL

A. Source Limitations for Waterproofing System: Obtain waterproofing materials molded-sheet drainage panels from single source from single manufacturer.

2.2 MODIFIED BITUMINOUS SHEET WATERPROOFING

A. Modified Bituminous Sheet: Minimum 60-mil nominal thickness, self-adhering sheet consisting of 56 mils of rubberized asphalt laminated on one side to a 4-mil- thick, polyethylene-film reinforcement, and with release liner on adhesive side; formulated for application with primer or surface conditioner that complies with VOC limits of authorities having jurisdiction.

1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

a. Carlisle Coatings & Waterproofing Inc; CCW MiraDRI 860/861. b. Grace Construction Products; W.R. Grace & Co. -- Conn; Bituthene 4000. c. Henry Company; Blueskin WP 100/200. d. Nervastral, Inc; BITU-MEM. e. Tamko Building Products, Inc; TW-60.

Page 16: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SELF-ADHERING SHEET WATERPROOFING – 071326 4 OF 7

2. Physical Properties:

a. Tensile Strength, Membrane: 250 psi minimum; ASTM D 412, Die C, modified. b. Ultimate Elongation: 300 percent minimum; ASTM D 412, Die C, modified. c. Low-Temperature Flexibility: Pass at minus 20 deg F; ASTM D 1970. d. Crack Cycling: Unaffected after 100 cycles of 1/8-inch movement; ASTM C 836. e. Puncture Resistance: 40 lbf minimum; ASTM E 154. f. Water Absorption: 0.2 percent weight-gain maximum after 48-hour immersion at

70 deg F; ASTM D 570. g. Water Vapor Permeance: 0.05 perms maximum; ASTM E 96/E 96M, Water

Method. h. Hydrostatic-Head Resistance: 200 feet minimum; ASTM D 5385.

3. Sheet Strips: Self-adhering, rubberized-asphalt strips of same material and thickness as sheet waterproofing.

2.3 MOLDED-SHEET DRAINAGE PANELS

A. Nonwoven-Geotextile-Faced, Molded-Sheet Drainage Panel: Composite subsurface drainage panel consisting of a studded, nonbiodegradable, molded-plastic-sheet drainage core; with a nonwoven, needle-punched geotextile facing with an apparent opening size not exceeding No. 70 sieve laminated to one side of the core and a polymeric film bonded to the other side; and with a vertical flow rate of 9 to 15 gpm per ft..

1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

a. American Hydrotech, Inc; Hydrodrain 400. b. Carlisle Coatings & Waterproofing Inc; CCW MiraDRAIN 6000. c. Grace Construction Products; W.R. Grace & Co. -- Conn; Hydroduct 220.

2.4 AUXILIARY MATERIALS

A. General: Furnish auxiliary materials recommended by waterproofing manufacturer for intended use and compatible with sheet waterproofing.

1. Furnish liquid-type auxiliary materials that comply with VOC limits of authorities having jurisdiction.

B. Primer: Liquid waterborne primer recommended for substrate by sheet-waterproofing material manufacturer.

C. Surface Conditioner: Liquid, waterborne surface conditioner recommended for substrate by sheet-waterproofing material manufacturer.

D. Liquid Membrane: Elastomeric, two-component liquid, cold fluid applied, of trowel grade or low viscosity.

E. Substrate Patching Membrane: Low-viscosity, two-component, modified asphalt coating.

Page 17: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SELF-ADHERING SHEET WATERPROOFING – 071326 5 OF 7

F. Metal Termination Bars: Aluminum bars, approximately 1 by 1/8 inch thick, predrilled at 9-inch centers.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements and other conditions affecting performance of the waterproofing.

1. Verify that concrete has cured and aged for minimum time period recommended in writing by waterproofing manufacturer.

2. Verify that substrate is visibly dry and within the moisture limits recommended in writing by manufacturer. Test for capillary moisture by plastic sheet method according to ASTM D 4263.

3. Verify that compacted subgrade is dry, smooth, sound, and ready to receive waterproofing sheet.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 SURFACE PREPARATION

A. Clean, prepare, and treat substrates according to manufacturer's written instructions. Provide clean, dust-free, and dry substrates for waterproofing application.

B. Mask off adjoining surfaces not receiving waterproofing to prevent spillage and overspray affecting other construction.

C. Remove grease, oil, bitumen, form-release agents, paints, curing compounds, and other penetrating contaminants or film-forming coatings from concrete.

D. Remove fins, ridges, mortar, and other projections and fill honeycomb, aggregate pockets, holes, and other voids.

E. Prepare, fill, prime, and treat joints and cracks in substrates. Remove dust and dirt from joints and cracks according to ASTM D 4258.

F. Corners: Prepare, prime, and treat inside and outside corners according to ASTM D 6135.

1. Install membrane strips centered over vertical inside corners. Install 3/4-inch fillets of liquid membrane on horizontal inside corners and as follows:

a. At footing-to-wall intersections, extend liquid membrane in each direction from corner or install membrane strip centered over corner.

G. Prepare, treat, and seal vertical and horizontal surfaces at terminations and penetrations through waterproofing and at drains and protrusions according to ASTM D 6135.

Page 18: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SELF-ADHERING SHEET WATERPROOFING – 071326 6 OF 7

3.3 MODIFIED BITUMINOUS SHEET-WATERPROOFING APPLICATION

A. Install modified bituminous sheets according to waterproofing manufacturer's written instructions and recommendations in ASTM D 6135.

B. Apply primer to substrates at required rate and allow it to dry. Limit priming to areas that will be covered by sheet waterproofing in same day. Reprime areas exposed for more than 24 hours.

C. Apply and firmly adhere sheets over area to receive waterproofing. Accurately align sheets and maintain uniform 2-1/2-inch- minimum lap widths and end laps. Overlap and seal seams, and stagger end laps to ensure watertight installation.

1. When ambient and substrate temperatures range between 25 and 40 deg F, install self-adhering, modified bituminous sheets produced for low-temperature application. Do not use low-temperature sheets if ambient or substrate temperature is higher than 60 deg F.

D. Horizontal Application: Apply sheets from low to high points of decks to ensure that laps shed water.

E. Apply continuous sheets over already-installed sheet strips, bridging substrate cracks, construction, and contraction joints.

F. Seal edges of sheet-waterproofing terminations with mastic.

G. Install sheet-waterproofing and auxiliary materials to tie into adjacent waterproofing.

H. Repair tears, voids, and lapped seams in waterproofing not complying with requirements. Slit and flatten fishmouths and blisters. Patch with sheet waterproofing extending 6 inches beyond repaired areas in all directions.

I. Immediately install protection course with butted joints over waterproofing membrane.

1. Molded-sheet drainage panels may be used in place of a separate protection course to vertical applications when approved by waterproofing manufacturer and installed immediately.

3.4 MOLDED-SHEET DRAINAGE-PANEL INSTALLATION

A. Place and secure molded-sheet drainage panels, with geotextile facing away from wall or deck substrate, according to manufacturer's written instructions. Use adhesives or other methods that do not penetrate waterproofing. Lap edges and ends of geotextile to maintain continuity. Protect installed molded-sheet drainage panels during subsequent construction.

3.5 FIELD QUALITY CONTROL

A. Engage a site representative qualified by waterproofing membrane manufacturer to inspect substrate conditions, surface preparation, membrane application, flashings, protection, and drainage components, and to furnish daily reports to Architect.

Page 19: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SELF-ADHERING SHEET WATERPROOFING – 071326 7 OF 7

3.6 PROTECTION, REPAIR, AND CLEANING

A. Do not permit foot or vehicular traffic on unprotected membrane.

B. Protect waterproofing from damage and wear during remainder of construction period.

C. Correct deficiencies in or remove waterproofing that does not comply with requirements; repair substrates, reapply waterproofing, and repair sheet flashings.

D. Clean spillage and soiling from adjacent construction using cleaning agents and procedures recommended by manufacturer of affected construction.

END OF SECTION 071326

Page 20: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning
Page 21: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 COLD FLUID-APPLIED WATERPROOFING – 071416 1 OF 6

SECTION 071416 - COLD FLUID-APPLIED WATERPROOFING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Liquid Flashing Membrane 2. Joint & Seam Filler

1.3 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1. Review waterproofing requirements including, but not limited to, the following:

a. Surface preparation specified in other Sections. b. Minimum curing period. c. Forecasted weather conditions. d. Special details and sheet flashings. e. Repairs.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include construction details, material descriptions, and tested physical and performance properties of waterproofing.

2. Include manufacturer's written instructions for evaluating, preparing, and treating substrate.

B. Shop Drawings:

1. Show locations and extent of waterproofing. 2. Include details for substrate joints and cracks, sheet flashings, penetrations, inside and

outside corners, tie-ins with adjoining waterproofing, and other termination conditions.

Page 22: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 COLD FLUID-APPLIED WATERPROOFING – 071416 2 OF 6

C. Samples: For each exposed product and for each color and texture specified, including the following products:

1. Liquid Flashing 2. Joint & Seam Filler

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Installer.

B. Field quality-control reports.

C. Sample Warranties: For special warranties.

1.6 QUALITY ASSURANCE

A. Installer Qualifications: An entity that employs installers and supervisors who are trained and approved by waterproofing manufacturer.

B. Mockups: Build mockups to verify selections made under Sample submittals and to set quality standards for installation.

1. Build mockup for each typical waterproofing installation including accessories to demonstrate surface preparation, crack and joint treatments, inside and outside corner treatments, and protection. Use manufacturer's application instructions.

a. Size: Coordinate with building envelope mock-up. Provide for each window and door type.

b. Description: Each type of wall installation.

2. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless Architect specifically approves such deviations in writing.

3. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

1.7 FIELD CONDITIONS

A. Environmental Limitations: Apply waterproofing within the range of ambient and substrate temperatures recommended in writing by waterproofing manufacturer.

1. Do not apply waterproofing to a damp or wet substrate, when relative humidity exceeds 85 percent, or when temperatures are less than 5 deg F above dew point.

2. Do not apply waterproofing in snow, rain, fog or mist, or when such weather conditions are imminent during application and curing period.

B. Maintain adequate ventilation during application and curing of waterproofing materials.

Page 23: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 COLD FLUID-APPLIED WATERPROOFING – 071416 3 OF 6

1.8 WARRANTY

A. Manufacturer's Special Warranty: Manufacturer agrees to repair or replace waterproofing that fails in materials or workmanship within specified warranty period.

1. Warranty Period: Five years from date of Substantial Completion.

B. Installer's Special Warranty: Specified form, on warranty form at end of this Section, signed by Installer, covering Work of this Section, for warranty period of two years.

1. Warranty includes removing and reinstalling waterproofing components.

PART 2 - PRODUCTS

2.1 MATERIALS, GENERAL

A. Source Limitations for Waterproofing System: Obtain waterproofing materials from single source from single manufacturer.

2.2 LIQUID MEMBRANE FLASHING

A. Basis of Design Product - subject to compliance with requirements, provide PROSOCO R-

GUARD FASTFLASH or equal product.

1. A gun-grade waterproofing, adhesive and detailing compound for use as a liquid flashing membrane in rough openings of exterior walls. The single-component, Silyl-Terminated-Poly-Ether (STPE) combines the best of silicone and polyurethane properties and is easy to gun, spread and tool to produce a highly durable, seamless, elastomeric flashing membrane. R-GUARD FastFlash® allows same day installation of windows, doors and other wall assembly, waterproofing or air barrier components. Use FastFlash® to fill joints and seams, in the field, to counter flash waterproofing and air barrier components, and to seal around penetration or protect countersunk fasteners. FastFlash® may also be used to adhere and gasket mechanically fastened building components. FastFlash® is suitable for use in all climates and bonds directly to damp or dry surfaces and cures under a variety of weather conditions. Use R-GUARD FastFlash® as part of a continuous, building-wide air barrier system, or to complement conventional waterproofing or air barrier components.

B. TYPICAL TECHNICAL DATA

1. FORM: brick red, gun-grade sealant 2. SPECIFIC GRAVITY: 1.45 to 1.55 3. pH: Not applicable 4. WEIGHT/GALLON: 12.5 pounds per gallon 5. TOTAL SOLIDS: 99 percent 6. VOC: 30 grams per Liter, maximum. Complies with all known national, state and district

AIM VOC regulations. 7. FLASH POINT: greater than 200 degrees Fahrenheit

Page 24: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 COLD FLUID-APPLIED WATERPROOFING – 071416 4 OF 6

8. FREEZE POINT: Not applicable 9. SHELF LIFE: 1 year in unopened, factory-sealed container

C. LIMITATIONS

1. Not for use as a structural sealant. 2. Not for use in place of appropriate through-wall flashing. 3. Not for use below grade or in locations which are continuously immersed in water.

2.3 JOINT & SEAM FILLER

A. Basis of Design Product - subject to compliance with requirements, provide PROSOCO R-

GUARD JOINT & SEAM FILLER or equal product.

1. Fills openings and creates transitions where flexible reinforcement is required to bridge gaps and provide continuous support of fluid-applied flashing membranes, waterproofing or air barrier components. R-GUARD Joint & Seam Filler is a high modulus, single component, fiber-reinforced Silyl-Terminated-Poly-Ether (STPe) gun-grade detailing compound suitable for all climates. Joint & Seam Filler bonds directly to damp or dry surfaces and eliminates the need for reinforcing tapes at sheathing joints, inside and outside corners.

B. TYPICAL TECHNICAL DATA

1. FORM: pale red, gun-grade sealant 2. SPECIFIC GRAVITY: 1.40 to 1.50 3. pH: Not applicable 4. WEIGHT/GALLON: 11.8 pounds per gallon 5. TOTAL SOLIDS: 99 percent 6. VOC: 30 grams per Liter, maximum. Complies with all known national, state and district

AIM VOC regulations. 7. FLASH POINT: No data 8. FREEZE POINT: No data 9. SHELF LIFE: 1 year in unopened, factory-sealed container

C. LIMITATIONS

1. Not for use as a liquid flashing membrane. 2. Not for use in place of appropriate through-wall flashing. 3. Not for use below grade or in locations which are continuously immersed in water.

2.4 AUXILIARY MATERIALS

A. General: Provide auxiliary materials recommended in writing by waterproofing manufacturer for intended use and compatible with one another and with waterproofing.

Page 25: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 COLD FLUID-APPLIED WATERPROOFING – 071416 5 OF 6

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements and other conditions affecting performance of the Work.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Clean, prepare, and treat substrates according to manufacturer's written instructions. Provide clean, dust-free, and dry substrates for waterproofing application.

B. Mask off adjoining surfaces not receiving waterproofing to prevent spillage and overspray affecting other construction.

3.3 PREPARATION AT TERMINATIONS, PENETRATIONS, AND CORNERS

A. Prepare surfaces at terminations and penetrations through waterproofing and at expansion joints, drains, sleeves, and corners according to waterproofing manufacturer's written instructions and to recommendations in ASTM C 898/C 898M and ASTM C 1471.

3.4 JOINT, SEAMS AND CRACK TREATMENT

A. Prepare, treat, rout, and fill joints and cracks in substrate according to waterproofing manufacturer's written instructions and to recommendations in ASTM C 898/C 898M and ASTM C 1471. Before coating surfaces, remove dust and dirt from joints and cracks according to ASTM D 4258.

1. Comply with ASTM C 1193 for joint-sealant installation. 2. Treat joints ranging from 1/4 inch to 1 inch with backer road before applying Joint &

Seam Filler. 3. Joints larger than 1 inch must be structurally improved or addressed with an appropriate

transition membrane.

3.5 JOINT & SEAM FILLER APPLICATION

A. Apply waterproofing according to manufacturer's written instructions and to recommendations in ASTM C 898/C 898M and ASTM C 1471. Applicable to preparation, protections, transitions, curing & drying, coverage and cleanup.

B. Start installing waterproofing in presence of manufacturer's technical representative.

Page 26: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 COLD FLUID-APPLIED WATERPROOFING – 071416 6 OF 6

3.6 LIQUID FLASHING MEMBRANE APPLICATION

A. Apply waterproofing according to manufacturer's written instructions and to recommendations in ASTM C 898/C 898M and ASTM C 1471. Applicable to preparation, protections, transitions, curing & drying, coverage and cleanup.

B. Start installing waterproofing in presence of manufacturer's technical representative.

3.7 FIELD QUALITY CONTROL

A. Testing Agency: Engage a qualified testing agency to perform tests and inspections:

1. Testing agency shall verify thickness of waterproofing during application for each 100 LF of installed waterproofing or part thereof.

B. Manufacturer's Field Service: Engage a site representative qualified by waterproofing membrane manufacturer to inspect substrate conditions, surface preparation, membrane application, flashings, protection, and drainage components and to furnish daily reports to Architect.

C. If test results or inspections show waterproofing does not comply with requirements, remove and replace or repair the waterproofing as recommended in writing by manufacturer, and make further repairs after retesting and inspecting until waterproofing installation passes.

D. Prepare test and inspection reports.

3.8 PROTECTION

A. Protect waterproofing from damage and wear during remainder of construction period.

B. Correct deficiencies in or remove waterproofing that does not comply with requirements; repair substrates and reapply waterproofing.

C. Clean spillage and soiling from adjacent construction using cleaning agents and procedures recommended in writing by manufacturer of affected construction.

END OF SECTION 071416

Page 27: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 THERMAL INSULATION – 072100 1 OF 5

SECTION 072100 - THERMAL INSULATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Extruded polystyrene foam-plastic board. 2. Glass-fiber blanket insulation. 3. Spray polyurethane foam insulation. 4. Thermal break strips at wall framing.

B. Related Sections:

1. Section 042113 "Brick Masonry" for insulation specified in this section and installed in cavity walls and masonry cells.

2. Section 075216 "Styrene-Butadiene-Styrene (SBS) Modified Bituminous Membrane Roofing" for insulation specified as part of roofing construction.

3. Section 078446 "Fire-Resistive Joint Systems" for insulation installed as part of a perimeter fire-resistive joint system.

4. Section 092900 "Gypsum Board" for installation in metal-framed assemblies of insulation specified by referencing this Section.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

1.4 INFORMATIONAL SUBMITTALS

A. Product Test Reports: Based on evaluation of comprehensive tests performed by a qualified testing agency, for each product.

B. Evaluation Reports: For foam-plastic insulation, from ICC-ES.

1.5 QUALITY ASSURANCE

A. Surface-Burning Characteristics: As determined by testing identical products according to ASTM E 84 by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.

Page 28: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 THERMAL INSULATION – 072100 2 OF 5

1.6 DELIVERY, STORAGE, AND HANDLING

A. Protect insulation materials from physical damage and from deterioration due to moisture, soiling, and other sources. Store inside and in a dry location. Comply with manufacturer's written instructions for handling, storing, and protecting during installation.

B. Protect foam-plastic board insulation as follows:

1. Do not expose to sunlight except to necessary extent for period of installation and concealment.

2. Protect against ignition at all times. Do not deliver foam-plastic board materials to Project site until just before installation time.

3. Quickly complete installation and concealment of foam-plastic board insulation in each area of construction.

PART 2 - PRODUCTS

2.1 EXTRUDED POLYSTYRENE FOAM-PLASTIC BOARD

A. Extruded Polystyrene Board Insulation: ASTM C 578 of type and minimum compressive strength indicated below with maximum flame-spread and smoke development indexes of 75 and 450, respectfully, per ASTM E 84.

1. Basis of Design Product: Subject to compliance with requirements, provide Owens Corning: R-5 Foamular 250 or comparable product by one of the following:

a. Diversifoam Products b. Dow Chemical Company (The)

2. Thickness: 1 inch.

3. Type: Tongue & Groove

4. Fire Propagation Characteristics: Passes NFPA 285 testing as part of an approved assembly.

B. Adhesive for Bonding Insulation: Product with demonstrated capability to bond insulation securely to substrates without damaging insulation and substrates.

C. Vapor Retarder Tape: Pressure sensitive moisture resistant faced tape recommended by insulation manufacturer for sealing joints, ruptures and penetrating items in insulation board.

1. Tape equal to JointsealR Foam Tape by Owens Corning. 2. Tape all joints, ruptures, punctures, penetrations and fasteners.

Page 29: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 THERMAL INSULATION – 072100 3 OF 5

2.2 GLASS-FIBER BLANKET INSULATION

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

1. CertainTeed Corporation. 2. Johns Manville. 3. Owens Corning.

B. Recycled Content: Postconsumer recycled content plus one-half of preconsumer recycled content not less than 25 percent.

C. Unfaced, Glass-Fiber Blanket Insulation: ASTM C 665, Type I; with maximum flame-spread and smoke-developed indexes of 25 and 50, respectively, per ASTM E 84; passing ASTM E 136 for combustion characteristics.

D. Sustainability Requirements: Provide glass-fiber blanket insulation as follows:

1. Free of Formaldehyde: Insulation manufactured with 100 percent acrylic binders and no formaldehyde.

2. Low Emitting: Insulation tested according to ASTM D 5116 and shown to emit less than 0.05-ppm formaldehyde.

2.3 SPRAY POLYURETHANE FOAM INSULATION

A. Closed-Cell Polyurethane Foam Insulation: ASTM C 1029, Type II, with maximum flame-spread and smoke-developed indexes of 75 and 450, respectively, per ASTM E 84.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. BASF Corporation. b. Dow Chemical Company (The). c. Gaco Western Inc. d. Henry Company.

2. Minimum density of 1.5 lb/cu. ft., thermal resistivity of 6.2 deg F x h x sq. ft./Btu x in. at 75 deg F.

a. Aged R-value per inch thickness: 5

3. Apply to building areas with exposure to an unprotected and variable thermal environment, not otherwise protected by an adequate insulating barrier. Examples include but are not necessarily limited to: a. Underside of uninsulated elevated exterior building floor slabs above soffits. b. Other areas indicated on the drawings.

Page 30: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 THERMAL INSULATION – 072100 4 OF 5

2.4 INSULATION FASTENERS

A. Power actuated carbon steel fasteners and retainer washer with recessed seat for screw head.

1. Attach directly to metal stud framing. 2. Tape all joints between insulation boards and fasteners / washers with pressure sensitive

tape.

2.5 THERMAL BREAK STRIPS

A. Insulation strips to be applied onto exterior steel stud framing behind wood blocking at wall openings, as shown on drawings:

1. Aerogel composite strips with self-adhesive backing, ¼” thickness. 2. Apply stripping as required to cover full width of adjacent wood blocking. 3. Provide strips equal to Thermablok Thermal Strips. Other equal products include but are

not limited to Advanced Insolutions, Inc. Proloft.

2.6 ACCESSORIES

A. Insulation for Miscellaneous Voids:

1. Glass-Fiber Insulation: ASTM C 764, Type II, loose fill; with maximum flame-spread and smoke-developed indexes of 5, per ASTM E 84.

2. Spray Polyurethane Foam Insulation: ASTM C 1029, Type II, closed cell, with maximum flame-spread and smoke-developed indexes of 75 and 450, respectively, per ASTM E 84.

PART 3 - EXECUTION

3.1 PREPARATION

A. Clean substrates of substances that are harmful to insulation or that interfere with insulation attachment.

3.2 INSTALLATION, GENERAL

A. Comply with insulation manufacturer's written instructions applicable to products and applications indicated.

B. Install insulation that is undamaged, dry, and unsoiled and that has not been left exposed to ice, rain, or snow at any time.

C. Extend insulation to envelop entire area to be insulated. Cut and fit tightly around obstructions and fill voids with insulation. Remove projections that interfere with placement.

Page 31: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 THERMAL INSULATION – 072100 5 OF 5

D. Provide sizes to fit applications indicated and selected from manufacturer's standard thicknesses, widths, and lengths. Apply single layer of insulation units to produce thickness indicated unless multiple layers are otherwise shown or required to make up total thickness.

3.3 INSTALLATION OF CAVITY-WALL INSULATION

A. Foam-Plastic Board Insulation: Power actuated carbon steel fasteners and retaining washers as recommended by manufacturer. Fit courses of insulation between wall ties and other obstructions, with edges butted tightly in both directions. Press units firmly against inside substrates.

1. Tape all fasteners, joints, ruptures, and penetrations with pressure sensitive tape. 2. This installation will serve as a component of the wall air & weather barrier.

3.4 INSTALLATION OF INSULATION FOR FRAMED CONSTRUCTION

A. Apply insulation units to substrates by method indicated, complying with manufacturer's written instructions. If no specific method is indicated, bond units to substrate with adhesive or use mechanical anchorage to provide permanent placement and support of units.

B. Glass-Fiber or Mineral-Wool Blanket Insulation: Install in cavities formed by framing members according to the following requirements:

1. Use insulation widths and lengths that fill the cavities formed by framing members. If more than one length is required to fill the cavities, provide lengths that will produce a snug fit between ends.

2. Place insulation in cavities formed by framing members to produce a friction fit between edges of insulation and adjoining framing members.

3. For metal-framed wall cavities where cavity heights exceed 96 inches, support unfaced blankets mechanically.

C. Spray-Applied Insulation: Apply spray-applied insulation according to manufacturer's written instructions. Do not apply insulation until installation of pipes, ducts, conduits, wiring, and electrical outlets in walls is completed and windows, electrical boxes, and other items not indicated to receive insulation are masked. After insulation is applied, make flush with face of studs by using method recommended by insulation manufacturer.

D. Miscellaneous Voids: Install insulation in miscellaneous voids and cavity spaces where required to prevent gaps in insulation using the following materials:

1. Spray Polyurethane Insulation: Apply according to manufacturer's written instructions.

3.5 PROTECTION

A. Protect installed insulation and vapor barriers from damage due to harmful weather exposures, physical abuse, and other causes. Provide temporary coverings or enclosures where insulation is subject to abuse and cannot be concealed and protected by permanent construction immediately after installation.

END OF SECTION 072100

Page 32: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning
Page 33: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 STANDING-SEAM METAL ROOF PANELS – 074113 1 OF 10

SECTION 074113 - STANDING-SEAM METAL ROOF PANELS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes standing-seam metal roof panels.

B. Related Sections:

1. Section 076200 “Sheet Metal Flashing and Trim” for items to be installed as part of work in this section.

1.3 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1. Meet with Owner, Architect, Owner's insurer if applicable, metal panel Installer, metal panel manufacturer's representative, structural-support Installer, and installers whose work interfaces with or affects metal panels, including installers of roof accessories and roof-mounted equipment.

2. Review and finalize construction schedule and verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays.

3. Review methods and procedures related to metal panel installation, including manufacturer's written instructions.

4. Examine support conditions for compliance with requirements, including alignment between and attachment to structural members.

5. Review structural loading limitations of deck during and after roofing. 6. Review flashings, special details, drainage, penetrations, equipment curbs, and condition

of other construction that affect metal panels. 7. Review governing regulations and requirements for insurance, certificates, and tests and

inspections if applicable. 8. Review temporary protection requirements for metal panel systems during and after

installation. 9. Review procedures for repair of metal panels damaged after installation. 10. Document proceedings, including corrective measures and actions required, and furnish

copy of record to each participant.

Page 34: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 STANDING-SEAM METAL ROOF PANELS – 074113 2 OF 10

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for each type of panel and accessory.

B. Shop Drawings:

1. Include fabrication and installation layouts of metal panels; details of edge conditions, joints, panel profiles, corners, anchorages, attachment system, trim, flashings, closures, and accessories; and special details.

2. Accessories: Include details of the flashing, trim, and anchorage systems, at a scale of not less than 1-1/2 inches per 12 inches.

C. Samples for Initial Selection: For each type of metal panel indicated with factory-applied color finishes.

1. Include similar Samples of trim and accessories involving color selection.

D. Samples for Verification: For each type of exposed finish required, prepared on Samples of size indicated below.

1. Metal Panels: 12 inches long by actual panel width. Include clips, fasteners, closures, and other metal panel accessories.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Installer.

B. Product Test Reports: For each product, for tests performed by a qualified testing agency.

C. Field quality-control reports.

D. Sample Warranties: For special warranties.

1.6 CLOSEOUT SUBMITTALS

A. Maintenance Data: For metal panels to include in maintenance manuals.

1.7 QUALITY ASSURANCE

A. Installer Qualifications: An entity that employs installers and supervisors who are trained and approved by manufacturer.

Page 35: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 STANDING-SEAM METAL ROOF PANELS – 074113 3 OF 10

B. UL-Certified, Portable Roll-Forming Equipment: UL-certified, portable roll-forming equipment capable of producing metal panels warranted by manufacturer to be the same as factory-formed products. Maintain UL certification of portable roll-forming equipment for duration of work.

C. Mockups: Build mockups to verify selections made under Sample submittals and to demonstrate aesthetic effects and set quality standards for fabrication and installation.

1. Build mockup of typical roof area and eave, including fascia, and soffit as shown on Drawings; approximately 12 feet square by full thickness, including attachments, underlayment, and accessories.

2. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless Architect specifically approves such deviations in writing.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Deliver components, metal panels, and other manufactured items so as not to be damaged or deformed. Package metal panels for protection during transportation and handling.

B. Unload, store, and erect metal panels in a manner to prevent bending, warping, twisting, and surface damage.

C. Stack metal panels horizontally on platforms or pallets, covered with suitable weathertight and ventilated covering. Store metal panels to ensure dryness, with positive slope for drainage of water. Do not store metal panels in contact with other materials that might cause staining, denting, or other surface damage.

D. Retain strippable protective covering on metal panels during installation.

E. Copper Panels: Wear gloves when handling to prevent fingerprints and soiling of surface.

1.9 FIELD CONDITIONS

A. Weather Limitations: Proceed with installation only when existing and forecasted weather conditions permit assembly of metal panels to be performed according to manufacturers' written instructions and warranty requirements.

1.10 COORDINATION

A. Coordinate sizes and locations of roof curbs, equipment supports, and roof penetrations with actual equipment provided.

B. Coordinate metal panel installation with rain drainage work, flashing, trim, construction of soffits, and other adjoining work to provide a leakproof, secure, and noncorrosive installation.

Page 36: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 STANDING-SEAM METAL ROOF PANELS – 074113 4 OF 10

1.11 WARRANTY

A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components of metal panel systems that fail in materials or workmanship within specified warranty period.

1. Failures include, but are not limited to, the following:

a. Structural failures including rupturing, cracking, or puncturing. b. Deterioration of metals and other materials beyond normal weathering.

2. Warranty Period: Two years from date of Substantial Completion.

B. Special Warranty on Panel Finishes: Manufacturer's standard form in which manufacturer agrees to repair finish or replace metal panels that show evidence of deterioration of factory-applied finishes within specified warranty period.

1. Exposed Panel Finish: Deterioration includes, but is not limited to, the following:

a. Color fading more than 5 Hunter units when tested according to ASTM D 2244. b. Chalking in excess of a No. 8 rating when tested according to ASTM D 4214. c. Cracking, checking, peeling, or failure of paint to adhere to bare metal.

2. Finish Warranty Period: 20 years from date of Substantial Completion.

C. Special Weathertightness Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace standing-seam metal roof panel assemblies that fail to remain weathertight, including leaks, within specified warranty period.

1. Warranty Period: 20 years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Structural Performance: Provide metal panel systems capable of withstanding the effects of the following loads, based on testing according to ASTM E 1592:

1. Deflection Limits: For wind loads, no greater than 1/180 of the span.

B. Air Infiltration: Air leakage of not more than 0.06 cfm/sq. ft. when tested according to ASTM E 1680 or ASTM E 283 at the following test-pressure difference:

1. Test-Pressure Difference: 1.57 lbf/sq. ft.

Page 37: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 STANDING-SEAM METAL ROOF PANELS – 074113 5 OF 10

C. Water Penetration under Static Pressure: No water penetration when tested according to ASTM E 1646 or ASTM E 331 at the following test-pressure difference:

1. Test-Pressure Difference: 2.86 lbf/sq. ft.

D. Hydrostatic-Head Resistance: No water penetration when tested according to ASTM E 2140.

E. Wind-Uplift Resistance: Provide metal roof panel assemblies that comply with UL 580 for wind-uplift-resistance class indicated.

1. Uplift Rating: UL 90.

F. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes by preventing buckling, opening of joints, overstressing of components, failure of joint sealants, failure of connections, and other detrimental effects. Base calculations on surface temperatures of materials due to both solar heat gain and nighttime-sky heat loss.

1. Temperature Change (Range): 120 deg F, ambient; 180 deg F, material surfaces.

2.2 STANDING-SEAM METAL ROOF PANELS

A. General: Provide factory-formed metal roof panels designed to be installed by lapping and interconnecting raised side edges of adjacent panels with joint type indicated and mechanically attaching panels to supports using concealed clips in side laps. Include clips, cleats, pressure plates, and accessories required for weathertight installation.

1. Steel Panel Systems: Unless more stringent requirements are indicated, comply with ASTM E 1514.

B. Clipless, Integral-Standing-Seam Metal Roof Panels: Formed with integral ribs at panel edges and a flat pan between ribs; designed for sequential installation by mechanically attaching panels to supports using screw fasteners located under concealed side of panels and lapping and interconnecting side edges of adjacent panels.

1. Metallic-Coated Steel Sheet: Zinc-coated (galvanized) steel sheet complying with

ASTM A 653/A 653M, G90 coating designation, or aluminum-zinc alloy-coated steel sheet complying with ASTM A 792/A 792M, Class AZ50 coating designation; structural quality. Prepainted by the coil-coating process to comply with ASTM A 755/A 755M.

a. Nominal Thickness: 24 Gauge. b. Exterior Finish: Two-coat fluoropolymer. c. Color: As selected by Architect from manufacturer's full range.

2. Panel Coverage: 18 inches. 3. Panel Height: 1.5 inches.

Page 38: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 STANDING-SEAM METAL ROOF PANELS – 074113 6 OF 10

2.3 UNDERLAYMENT MATERIALS

A. Self-Adhering, High-Temperature Underlayment: Provide self-adhering, cold-applied, sheet underlayment, a minimum of 30 mils thick, consisting of slip-resistant, polyethylene-film top surface laminated to a layer of butyl or SBS-modified asphalt adhesive, with release-paper backing. Provide primer when recommended by underlayment manufacturer.

1. Thermal Stability: Stable after testing at 240 deg F; ASTM D 1970. 2. Low-Temperature Flexibility: Passes after testing at minus 20 deg F; ASTM D 1970. 3. Products: Subject to compliance with requirements, available products that may be

incorporated into the Work include, but are not limited to, the following:

a. Carlisle Residential, a division of Carlisle Construction Materials; WIP 300HT. b. Grace Construction Products, a unit of W. R. Grace & Co.; Grace Ice and Water

Shield HT. c. Henry Company; Blueskin PE200 HT. d. Owens Corning; WeatherLock Metal High Temperature Underlayment.

2.4 MISCELLANEOUS MATERIALS

A. Panel Accessories: Provide components required for a complete, weathertight panel system including trim, copings, fasciae, mullions, sills, corner units, clips, flashings, sealants, gaskets, fillers, closure strips, and similar items. Match material and finish of metal panels unless otherwise indicated.

1. Closures: Provide closures at eaves and ridges, fabricated of same metal as metal panels. 2. Backing Plates: Provide metal backing plates at panel end splices, fabricated from

material recommended by manufacturer. 3. Closure Strips: Closed-cell, expanded, cellular, rubber or cross linked, polyolefin-foam or

closed-cell laminated polyethylene; minimum 1-inch- thick, flexible closure strips; cut or premolded to match metal panel profile. Provide closure strips where indicated or necessary to ensure weathertight construction.

B. Flashing and Trim: Provide flashing and trim formed from same material as metal panels as required to seal against weather and to provide finished appearance. Locations include, but are not limited to, eaves, rakes, corners, bases, ridges, drip edges, and fillers. Finish flashing and trim with same finish system as adjacent metal panels.

C. Gutters: Comply with Section 076200 “Sheet Metal Flashing and Trim.”

D. Downspouts: Comply with Section 076200 “Sheet Metal Flashing and Trim.”

E. Panel Fasteners: Self-tapping screws designed to withstand design loads.

F. Panel Sealants: Provide sealant type recommended by manufacturer that are compatible with panel materials, are nonstaining, and do not damage panel finish.

1. Sealant Tape: Pressure-sensitive, 100 percent solids, gray polyisobutylene compound sealant tape with release-paper backing. Provide permanently elastic, nonsag, nontoxic, nonstaining tape 1/2 inch wide and 1/8 inch thick.

Page 39: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 STANDING-SEAM METAL ROOF PANELS – 074113 7 OF 10

2. Joint Sealant: ASTM C 920; elastomeric polyurethane or silicone sealant; of type, grade, class, and use classifications required to seal joints in metal panels and remain weathertight; and as recommended in writing by metal panel manufacturer.

2.5 FABRICATION

A. General: Fabricate and finish metal panels and accessories at the factory, by manufacturer's standard procedures and processes, as necessary to fulfill indicated performance requirements demonstrated by laboratory testing. Comply with indicated profiles and with dimensional and structural requirements.

B. Provide panel profile, including major ribs and intermediate stiffening ribs, if any, for full length of panel.

C. Fabricate metal panel joints with factory-installed captive gaskets or separator strips that provide a weathertight seal and prevent metal-to-metal contact, and that minimize noise from movements.

D. Sheet Metal Flashing and Trim: Fabricate flashing and trim to comply with manufacturer's recommendations and recommendations in SMACNA's "Architectural Sheet Metal Manual" that apply to design, dimensions, metal, and other characteristics of item indicated.

1. Form exposed sheet metal accessories that are without excessive oil canning, buckling, and tool marks and that are true to line and levels indicated, with exposed edges folded back to form hems.

2. Seams for Other Than Aluminum: Fabricate nonmoving seams in accessories with flat-lock seams. Tin edges to be seamed, form seams, and solder.

3. Sealed Joints: Form non-expansion, but movable, joints in metal to accommodate sealant and to comply with SMACNA standards.

4. Conceal fasteners and expansion provisions where possible. Exposed fasteners are not allowed on faces of accessories exposed to view.

5. Fabricate cleats and attachment devices from same material as accessory being anchored or from compatible, noncorrosive metal recommended in writing by metal panel manufacturer.

a. Size: As recommended by SMACNA's "Architectural Sheet Metal Manual" or metal panel manufacturer for application, but not less than thickness of metal being secured.

2.6 FINISHES

A. Protect mechanical and painted finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping.

B. Appearance of Finished Work: Variations in appearance of abutting or adjacent pieces are acceptable if they are within one-half of the range of approved Samples. Noticeable variations in same piece are unacceptable. Variations in appearance of other components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast.

Page 40: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 STANDING-SEAM METAL ROOF PANELS – 074113 8 OF 10

C. Steel Panels and Accessories:

1. Two-Coat Fluoropolymer: AAMA 621. Fluoropolymer finish containing not less than 70 percent PVDF resin by weight in color coat. Prepare, pretreat, and apply coating to exposed metal surfaces to comply with coating and resin manufacturers' written instructions.

2. Concealed Finish: Apply pretreatment and manufacturer's standard white or light-colored acrylic or polyester backer finish consisting of prime coat and wash coat with a minimum total dry film thickness of 0.5 mil.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances, metal panel supports, and other conditions affecting performance of the Work.

1. Examine primary and secondary roof framing to verify that rafters, purlins, angles, channels, and other structural panel support members and anchorages have been installed within alignment tolerances required by metal roof panel manufacturer.

2. Examine solid roof sheathing to verify that sheathing joints are supported by framing or blocking and that installation is within flatness tolerances required by metal roof panel manufacturer.

a. Verify that air- or water-resistive barriers have been installed over sheathing or backing substrate to prevent air infiltration or water penetration.

B. Examine roughing-in for components and systems penetrating metal panels to verify actual locations of penetrations relative to seam locations of metal panels before installation.

C. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Miscellaneous Supports: Install subframing, furring, and other miscellaneous panel support members and anchorages according to ASTM C 754 and metal panel manufacturer's written recommendations.

3.3 UNDERLAYMENT INSTALLATION

A. Self-Adhering Sheet Underlayment: Apply primer if required by manufacturer. Comply with temperature restrictions of underlayment manufacturer for installation. Apply at locations indicated below, wrinkle free, in shingle fashion to shed water, and with end laps of not less than 6 inches staggered 24 inches between courses. Overlap side edges not less than 3-1/2 inches. Extend underlayment into gutter trough. Roll laps with roller. Cover underlayment within 14 days.

1. Apply over the entire roof surface.

Page 41: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 STANDING-SEAM METAL ROOF PANELS – 074113 9 OF 10

B. Flashings: Install flashings to cover underlayment to comply with requirements specified in Section 076200 "Sheet Metal Flashing and Trim."

3.4 METAL PANEL INSTALLATION

A. General: Install metal panels according to manufacturer's written instructions in orientation, sizes, and locations indicated. Install panels perpendicular to supports unless otherwise indicated. Anchor metal panels and other components of the Work securely in place, with provisions for thermal and structural movement.

1. Shim or otherwise plumb substrates receiving metal panels. 2. Flash and seal metal panels at perimeter of all openings. Fasten with self-tapping screws.

Do not begin installation until air- or water-resistive barriers and flashings that will be concealed by metal panels are installed.

3. Install screw fasteners in predrilled holes. 4. Locate and space fastenings in uniform vertical and horizontal alignment. 5. Install flashing and trim as metal panel work proceeds. 6. Locate panel splices over, but not attached to, structural supports. Stagger panel splices

and end laps to avoid a four-panel lap splice condition. 7. Align bottoms of metal panels and fasten with blind rivets, bolts, or self-tapping screws.

Fasten flashings and trim around openings and similar elements with self-tapping screws. 8. Provide weathertight escutcheons for pipe- and conduit-penetrating panels.

B. Fasteners:

1. Steel Panels: Use stainless-steel fasteners for surfaces exposed to the exterior; use galvanized-steel fasteners for surfaces exposed to the interior.

C. Metal Protection: Where dissimilar metals contact each other or corrosive substrates, protect against galvanic action as recommended in writing by metal panel manufacturer.

D. Clipless Metal Panel Installation: Fasten metal panels to supports with screw fasteners at each lapped joint at location and spacing recommended by manufacturer.

E. Accessory Installation: Install accessories with positive anchorage to building and weathertight mounting, and provide for thermal expansion. Coordinate installation with flashings and other components.

1. Install components required for a complete metal panel system including trim, copings, corners, seam covers, flashings, sealants, gaskets, fillers, closure strips, and similar items. Provide types indicated by metal roof panel manufacturers; or, if not indicated, types recommended by metal roof panel manufacturer.

F. Flashing and Trim: Comply with performance requirements, manufacturer's written installation instructions, and SMACNA's "Architectural Sheet Metal Manual." Provide concealed fasteners where possible, and set units true to line and level as indicated. Install work with laps, joints, and seams that will be permanently watertight and weather resistant.

1. Install exposed flashing and trim that is without buckling and tool marks, and that is true to line and levels indicated, with exposed edges folded back to form hems. Install sheet metal flashing and trim to fit substrates and achieve waterproof and weather-resistant performance.

Page 42: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 STANDING-SEAM METAL ROOF PANELS – 074113 10 OF 10

2. Expansion Provisions: Provide for thermal expansion of exposed flashing and trim. Space movement joints at a maximum of 10 feet with no joints allowed within 24 inches of corner or intersection. Where lapped expansion provisions cannot be used or would not be sufficiently weather resistant and waterproof, form expansion joints of intermeshing hooked flanges, not less than 1 inch deep, filled with mastic sealant (concealed within joints).

G. Gutters: Comply with Section 076200 “Sheet Metal Flashing and Trim.”

H. Downspouts: Comply with Section 076200 “Sheet Metal Flashing and Trim.”

I. Pipe Flashing: Form flashing around pipe penetration and metal roof panels. Fasten and seal to metal roof panels as recommended by manufacturer.

3.5 ERECTION TOLERANCES

A. Installation Tolerances: Shim and align metal panel units within installed tolerance of 1/4 inch in 20 feet on slope and location lines as indicated and within 1/8-inch offset of adjoining faces and of alignment of matching profiles.

3.6 FIELD QUALITY CONTROL

A. Manufacturer's Field Service: Engage a factory-authorized service representative to test and inspect metal roof panel installation, including accessories. Report results in writing.

B. Remove and replace applications of metal roof panels where tests and inspections indicate that they do not comply with specified requirements.

C. Additional tests and inspections, at Contractor's expense, are performed to determine compliance of replaced or additional work with specified requirements.

D. Prepare test and inspection reports.

3.7 CLEANING AND PROTECTION

A. Remove temporary protective coverings and strippable films, if any, as metal panels are installed, unless otherwise indicated in manufacturer's written installation instructions. On completion of metal panel installation, clean finished surfaces as recommended by metal panel manufacturer. Maintain in a clean condition during construction.

B. Replace metal panels that have been damaged or have deteriorated beyond successful repair by finish touchup or similar minor repair procedures.

END OF SECTION 074113

Page 43: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED MARCH 2018 BITUMINOUS MEMBRANE ROOFING – 075216 1 OF 11

SECTION 075216 - STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED BITUMINOUS MEMBRANE ROOFING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Styrene-butadiene-styrene (SBS)-modified bituminous membrane roofing. 2. Roof insulation.

B. Related Requirements:

1. Section 076200 "Sheet Metal Flashing and Trim" for metal roof flashings and counterflashings.

2. Section 079200 "Joint Sealants" for joint sealants, joint fillers, and joint preparation. 3. Section 224200 "Plumbing Specialties" for roof drains.

1.3 DEFINITIONS

A. Roofing Terminology: Definitions in ASTM D 1079 and glossary of NRCA's "The NRCA Roofing and Waterproofing Manual" apply to work of this Section.

1.4 PREINSTALLATION MEETINGS

A. Preinstallation Roofing Conference: Conduct conference at Project site.

1. Meet with Owner, Architect, Owner's insurer if applicable, testing and inspecting agency representative, roofing Installer, roofing system manufacturer's representative, deck Installer, and installers whose work interfaces with or affects roofing, including installers of roof accessories and roof-mounted equipment.

2. Review methods and procedures related to roofing installation, including manufacturer's written instructions.

3. Review and finalize construction schedule, and verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays.

4. Examine deck substrate conditions and finishes for compliance with requirements, including flatness and fastening.

5. Review structural loading limitations of roof deck during and after roofing.

Page 44: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED MARCH 2018 BITUMINOUS MEMBRANE ROOFING – 075216 2 OF 11

6. Review base flashings, special roofing details, roof drainage, roof penetrations, equipment curbs, and condition of other construction that affects roofing system.

7. Review governing regulations and requirements for insurance and certificates if applicable.

8. Review temporary protection requirements for roofing system during and after installation.

9. Review roof observation and repair procedures after roofing installation.

1.5 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Shop Drawings: For roofing system. Include plans, elevations, sections, details, and attachments to other work, including:

1. Base flashings and membrane terminations. 2. Tapered insulation, including slopes. 3. Crickets, saddles, and tapered edge strips, including slopes. 4. Insulation fastening patterns for corner, perimeter, and field-of-roof locations.

C. Samples for Verification: For the following products:

1. Cap sheet, of color required. 2. Flashing sheet, of color required.

1.6 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Installer and manufacturer.

B. Manufacturer Certificates: Signed by roofing manufacturer certifying that roofing system complies with requirements specified in "Performance Requirements" Article.

1. Submit evidence of complying with performance requirements.

C. Field quality-control reports.

D. Sample Warranties: For manufacturer's special warranties.

1.7 CLOSEOUT SUBMITTALS

A. Maintenance Data: For roofing system to include in maintenance manuals.

1.8 QUALITY ASSURANCE

A. Manufacturer Qualifications: A qualified manufacturer that is UL listed for membrane roofing system identical to that used for this Project.

Page 45: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED MARCH 2018 BITUMINOUS MEMBRANE ROOFING – 075216 3 OF 11

B. Installer Qualifications: A qualified firm that is approved, authorized, or licensed by roofing system manufacturer to install manufacturer's product and that is eligible to receive manufacturer's special warranty.

1.9 DELIVERY, STORAGE, AND HANDLING

A. Deliver roofing materials to Project site in original containers with seals unbroken and labeled with manufacturer's name, product brand name and type, date of manufacture, approval or listing agency markings, and directions for storing and mixing with other components.

B. Store liquid materials in their original undamaged containers in a clean, dry, protected location and within the temperature range required by roofing system manufacturer. Protect stored liquid material from direct sunlight.

1. Discard and legally dispose of liquid material that cannot be applied within its stated shelf life.

C. Protect roof insulation materials from physical damage and from deterioration by sunlight, moisture, soiling, and other sources. Store in a dry location. Comply with insulation manufacturer's written instructions for handling, storing, and protecting during installation.

D. Handle and store roofing materials, and place equipment in a manner to avoid permanent deflection of deck.

1.10 FIELD CONDITIONS

A. Weather Limitations: Proceed with installation only when existing and forecasted weather conditions permit roofing system to be installed according to manufacturer's written instructions and warranty requirements.

1.11 WARRANTY

A. Special Warranty: Manufacturer agrees to repair or replace components of roofing system that fail in materials or workmanship within specified warranty period.

1. Special warranty includes membrane roofing, base flashings, roof insulation, fasteners, cover boards, roofing accessories, and other components of roofing system.

2. Warranty Period: 20 years from date of Substantial Completion. No dollar limit on system warranty.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include the following:

1. Johns Manville. 2. Firestone Building Products

Page 46: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED MARCH 2018 BITUMINOUS MEMBRANE ROOFING – 075216 4 OF 11

3. Soprema, Inc. 4. Siplast.

B. Source Limitations: Obtain components including roof insulation and fasteners for roofing system from manufacturer approved by membrane roofing manufacturer.

C. The following manufacturers are approved:

1. Johns Manville.

a. Membrane Nail Based Ply: Dynabase b. Membrane Base Ply: Dynabase (mopping only) c. Membrane Top Ply: Dynaglass FR (mopping only) d. Base Ply Flashing: Dynaweld 180 S (moping only) e. Top Ply Flashing: Dynaweld Caper (torching only)

2. Firestone Building Products

a. Membrane Nail Based Ply: SBS Base b. Membrane Base Ply: SBS Base c. Membrane Top Ply: SBS Glass FR d. Base Ply Flashing: SBS Glass Torch Base' e. Top Ply Flashing: SBS Glass FR Torch

3. Soprema, Inc.

a. Membrane Nail Based Ply: Elastophene 180 sanded b. Membrane Base Ply: Elastophene 180 sanded (mopping only) c. Membrane Top Ply: Elastophene FR GR (mopping only) d. Base Ply Flashing: Elastophene 180 PS (moping only) e. Top Ply Flashing: Sopralast Supralene Flam 250 GR (torching only)

4. Siplast

a. Membrane Nail Based Ply: Paradiene 20 b. Membrane Base Ply: Paradiene 20 (mopping only) c. Membrane Top Ply: Paradiene 30 FR (mopping only) d. Base Ply Flashing: Paradiene 20 (moping only) e. Top Ply Flashing: Veral Aluminum (torching only)

2.2 PERFORMANCE REQUIREMENTS

A. General Performance: Installed roofing and base flashings shall withstand specified uplift pressures, thermally induced movement, and exposure to weather without failure due to defective manufacture, fabrication, installation, or other defects in construction. Roofing and base flashings shall remain watertight.

1. Accelerated Weathering: Roofing system shall withstand 2000 hours of exposure when tested according to ASTM G 152, ASTM G 154, or ASTM G 155.

2. Impact Resistance: Roofing system shall resist impact damage when tested according to ASTM D 3746 or ASTM D 4272.

Page 47: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED MARCH 2018 BITUMINOUS MEMBRANE ROOFING – 075216 5 OF 11

B. Material Compatibility: Roofing materials shall be compatible with one another and adjacent materials under conditions of service and application required, as demonstrated by roofing manufacturer based on testing and field experience.

C. Roofing System Design: Tested by a qualified testing agency to resist the following tested differential ultimate pressures:

1. Corner Uplift Pressure: 255 lbf / sq. ft. 2. Perimeter Uplift Pressure: 150 lbf / sq. ft. 3. Field-of-Roof Uplift Pressure: 90 lbf / sq. ft.

D. Products Qualified Product List" for low-slope roof products.

E. Exterior Fire-Test Exposure: ASTM E 108 or UL 790, Class A; for application and roof slopes indicated; testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.

2.3 ROOFING SHEET MATERIALS

A. Base Sheet: ASTM D 4601, Type II, nonperforated, asphalt-impregnated and -coated, glass-fiber sheet, dusted with fine mineral surfacing on both sides.

B. Roofing Membrane Sheet: ASTM D 6163, Grade S, Type I or II, SBS-modified asphalt sheet (reinforced with glass fibers); smooth surfaced; suitable for application method specified.

C. Granule-Surfaced Roofing Cap Sheet: ASTM D 6163, Grade G, Type I or II, SBS-modified asphalt sheet (reinforced with glass fibers); granule surfaced; suitable for application method specified, and as follows:

1. Granule Color: White.

2.4 BASE FLASHING SHEET MATERIALS

A. Backer Sheet: ASTM D 4601, Type II, asphalt-impregnated and -coated, glass-fiber sheet, dusted with fine mineral surfacing on both sides.

B. Granule-Surfaced Flashing Sheet: ASTM D 6163, Grade G, Type I or II, SBS-modified asphalt sheet (reinforced with glass fibers); granule surfaced; suitable for application method specified, and as follows:

1. Granule Color: White.

C. Metal-Foil-Surfaced Flashing Sheet: ASTM D 6298, glass-fiber-reinforced SBS-modified asphalt sheet (reinforced with glass fibers); metal-foil surfaced; suitable for application method specified, and as follows:

1. Foil Surfacing: Aluminum.

Page 48: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED MARCH 2018 BITUMINOUS MEMBRANE ROOFING – 075216 6 OF 11

2.5 AUXILIARY ROOFING MATERIALS

A. General: Auxiliary materials recommended by roofing system manufacturer for intended use and compatible with roofing.

B. Asphalt Primer: ASTM D 41/D 41M.

C. Roofing Asphalt: ASTM D 6152, SEBS modified.

D. Asphalt Roofing Cement: ASTM D 4586, asbestos free, of consistency required by roofing system manufacturer for application.

E. Mastic Sealant: Polyisobutylene, plain or modified bitumen; nonhardening, nonmigrating, nonskinning, and nondrying.

F. Fasteners: Factory-coated steel fasteners and metal or plastic plates complying with corrosion-resistance provisions in FM Global 4470, designed for fastening roofing components to substrate; tested by manufacturer for required pullout strength, and acceptable to roofing system manufacturer.

G. Roofing Granules: Ceramic-coated roofing granules, No. 11 screen size with 100 percent passing No. 8 sieve and 98 percent of mass retained on No. 40 sieve, color to match roofing.

H. Miscellaneous Accessories: Provide those recommended by roofing system manufacturer.

2.6 ROOF INSULATION

A. General: Preformed roof insulation boards manufactured or approved by roofing manufacturer, selected from manufacturer's standard sizes suitable for application, of thicknesses indicated.

B. Polyisocyanurate Board Insulation: ASTM C 1289, Type II, Class 1, Grade 3, felt or glass-fiber mat facer on both major surfaces.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. Atlas Roofing Corporation. b. Carlisle SynTec Incorporated. c. GAF Materials Corporation. d. Johns Manville. e. Siplast.

C. Tapered Insulation: Provide factory-tapered insulation boards fabricated to slope of 1/4 inch per 12 inches unless otherwise indicated. Provide minimum insulation thickness of 3 inches. Provide average R-value of R-30.

D. Provide preformed saddles, crickets, tapered edge strips, and other insulation shapes where indicated for sloping to drain. Fabricate to slopes indicated.

Page 49: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED MARCH 2018 BITUMINOUS MEMBRANE ROOFING – 075216 7 OF 11

2.7 INSULATION ACCESSORIES

A. General: Roof insulation accessories recommended by insulation manufacturer for intended use and compatibility with roofing.

B. Fasteners: Factory-coated steel fasteners and metal or plastic plates complying with corrosion-resistance provisions in FM Global 4470, designed for fastening roof insulation to substrate, and acceptable to roofing system manufacturer.

C. Insulation Cant Strips: ASTM C 728, perlite insulation board.

D. Wood Nailer Strips: Comply with requirements in Section 061000 "Rough Carpentry."

E. Tapered Edge Strips: ASTM C 728, perlite insulation board.

F. Cover Board: ASTM C 1177/C 1177M, glass-mat, water-resistant gypsum substrate, 1/4 inch thick.

1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

a. CertainTeed Corporation; GlasRoc Sheathing. b. Georgia Pacific Corporation; Dens Deck. c. National Gypsum Company; Gold Bond eXP Extended Exposure Sheathing. d. USG Corporation; Securock Glass Mat Roof Board.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements and other conditions affecting performance of the Work:

1. Verify that roof openings and penetrations are in place, curbs are set and braced, and roof-drain bodies are securely clamped in place.

2. Verify that wood cants, blocking, curbs, and nailers are securely anchored to roof deck at penetrations and terminations and that nailers match thicknesses of insulation.

3. Verify that deck is securely fastened with no projecting fasteners and with no adjacent units in excess of 1/16 inch out of plane relative to adjoining deck.

4. Verify that minimum concrete drying period recommended by roofing system manufacturer has passed.

5. Verify that concrete substrate is visibly dry and free of moisture. Test for capillary moisture by plastic sheet method according to ASTM D 4263.

a. Test for moisture by pouring 1 pint of hot roofing asphalt on deck at start of each day's work and at start of each roof area or plane. Do not proceed with Work of this Section if test sample foams or can be easily and cleanly stripped after cooling.

6. Verify that concrete-curing compounds that impair adhesion of roofing components to roof deck have been removed.

Page 50: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED MARCH 2018 BITUMINOUS MEMBRANE ROOFING – 075216 8 OF 11

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Clean substrate of dust, debris, moisture, and other substances detrimental to roofing installation according to roofing system manufacturer's written instructions. Remove sharp projections.

B. Prevent materials from entering and clogging roof drains and conductors and from spilling or migrating onto surfaces of other construction. Remove roof-drain plugs when no work is taking place or when rain is forecast.

C. Prime surface of concrete deck with asphalt primer at a rate of 3/4 gal./100 sq. ft., and allow primer to dry.

3.3 INSTALLATION, GENERAL

A. Comply with roofing system manufacturer's written instructions.

B. Asphalt Heating: Heat and apply SEBS-modified roofing asphalt according to roofing system manufacturer's written instructions.

C. Substrate-Joint Penetrations: Prevent roofing asphalt and adhesives from penetrating substrate joints, entering building, or damaging roofing system components or adjacent building construction.

3.4 INSULATION INSTALLATION

A. Install one lapped base-sheet course and mechanically fasten to substrate according to roofing system manufacturer's written instructions.

B. Install tapered insulation under area of roofing to conform to slopes indicated.

C. Install insulation with long joints of insulation in a continuous straight line, with end joints staggered between rows, abutting edges and ends between boards. Fill gaps exceeding 1/4 inch with insulation.

1. Cut and fit insulation within 1/4 inch of nailers, projections, and penetrations.

D. Install insulation under area of roofing to achieve required thickness. Where overall insulation thickness is 2.7 inches or greater, install two or more layers with joints of each succeeding layer staggered from joints of previous layer a minimum of 6 inches in each direction.

E. Trim surface of insulation where necessary at roof drains so completed surface is flush and does not restrict flow of water.

F. Install tapered edge strips at perimeter edges of roof that do not terminate at vertical surfaces.

Page 51: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED MARCH 2018 BITUMINOUS MEMBRANE ROOFING – 075216 9 OF 11

G. Mechanically Fastened Insulation: Install each layer of insulation and secure to deck using mechanical fasteners specifically designed and sized for fastening specified board-type roof insulation to deck type.

1. Fasten insulation to resist uplift pressure at corners, perimeter, and field of roof.

H. Install cover boards over insulation with long joints in continuous straight lines with end joints staggered between rows. Offset joints of insulation below a minimum of 6 inches in each direction. Loosely butt cover boards together and fasten to roof deck. Tape joints if required by roofing system manufacturer.

1. Fasten cover boards to resist uplift pressure at corners, perimeter, and field of roof.

3.5 ROOFING INSTALLATION, GENERAL

A. Install roofing system according to roofing system manufacturer's written instructions and applicable recommendations in ARMA/NRCA's "Quality Control Guidelines for the Application of Polymer Modified Bitumen Roofing" and as follows:

1. Deck Type: C (concrete or nonnailable). 2. Adhering Method: M (mopped). 3. Base Sheet: One. 4. Number of Glass-Fiber Base-Ply Sheets: One. 5. Number of SBS-Modified Asphalt Sheets: One. 6. Surfacing Type: M (mineral-granule-surfaced cap sheet).

B. Start installation of roofing in presence of manufacturer's technical personnel.

C. Install roofing membrane sheets parallel with slope.

D. Coordinate installation of roofing system so insulation and other components of the roofing system not permanently exposed are not subjected to precipitation or left uncovered at the end of the workday or when rain is forecast.

1. Provide tie-offs at end of each day's work to cover exposed roofing sheets and insulation with a course of coated felt set in roofing cement or hot roofing asphalt, with joints and edges sealed.

2. Complete terminations and base flashings, and provide temporary seals to prevent water from entering completed sections of roofing system.

3. Remove and discard temporary seals before beginning work on adjoining roofing.

3.6 BASE-SHEET INSTALLATION

A. Install lapped base-sheet course, extending sheet over and terminating beyond cants. Attach base sheet as follows:

1. Adhere to substrate in a solid mopping of hot roofing asphalt.

Page 52: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED MARCH 2018 BITUMINOUS MEMBRANE ROOFING – 075216 10 OF 11

3.7 BASE-PLY SHEET INSTALLATION

A. Install glass-fiber base-ply sheets according to roofing system manufacturer's written instructions starting at low point of roofing system. Align glass-fiber base-ply sheets without stretching. Extend sheets over and terminate beyond cants.

1. Shingle side laps of glass-fiber base-ply sheets uniformly to ensure that required number of glass-fiber base-ply sheets covers substrate at any point. Shingle in direction to shed water.

2. Embed each glass-fiber base-ply sheet in a continuous void-free mopping of hot roofing asphalt to form a uniform membrane without glass-fiber base-ply sheets touching.

3.8 SBS-MODIFIED BITUMINOUS MEMBRANE INSTALLATION

A. Install modified bituminous roofing sheet and cap sheet according to roofing manufacturer's written instructions, starting at low point of roofing system. Extend roofing membrane sheets over and terminate beyond cants, installing as follows:

1. Adhere to substrate in a solid mopping of hot roofing asphalt applied at not less than 425 deg F.

2. Unroll roofing sheets and allow them to relax for minimum time period required by manufacturer.

B. Laps: Accurately align roofing sheets, without stretching, and maintain uniform side and end laps. Stagger end laps. Completely bond and seal laps, leaving no voids.

1. Repair tears and voids in laps and lapped seams not completely sealed. 2. Apply roofing granules to cover exuded bead at laps while bead is hot.

C. Install roofing sheets so side and end laps shed water.

3.9 FLASHING AND STRIPPING INSTALLATION

A. Install base flashing over cant strips and other sloped and vertical surfaces, at roof edges, and at penetrations through roof, and secure to substrates according to roofing system manufacturer's written instructions and as follows:

1. Prime substrates with asphalt primer if required by roofing system manufacturer. 2. Flashing-Sheet Application: Torch apply flashing sheet to substrate.

B. Extend base flashing up walls or parapets a minimum of 8 inches above roofing membrane and 4 inches onto field of roofing membrane.

C. Install roofing cap-sheet stripping where metal flanges and edgings are set on roofing according to roofing system manufacturer's written instructions.

Page 53: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

STYRENE-BUTADIENE-STYRENE (SBS) MODIFIED MARCH 2018 BITUMINOUS MEMBRANE ROOFING – 075216 11 OF 11

D. Roof Drains: Set 30-by-30-inch-metal flashing in bed of asphaltic adhesive on completed roofing membrane. Cover metal flashing with roofing cap-sheet stripping, and extend a minimum of 6 inches beyond edge of metal flashing onto field of roofing membrane. Clamp roofing membrane, metal flashing, and stripping into roof-drain clamping ring.

1. Install stripping according to roofing system manufacturer's written instructions.

3.10 FIELD QUALITY CONTROL

A. Final Roof Inspection: Arrange for roofing system manufacturer's technical personnel to inspect roofing installation on completion.

1. Notify Architect and Owner 48 hours in advance of date and time of inspection.

B. Roofing system will be considered defective if it does not pass tests and inspections.

1. Additional testing and inspecting, at Contractor's expense, will be performed to determine if replaced or additional work complies with specified requirements.

3.11 PROTECTING AND CLEANING

A. Protect roofing system from damage and wear during remainder of construction period. When remaining construction does not affect or endanger roofing, inspect roofing for deterioration and damage, describing its nature and extent in a written report, with copies to Architect and Owner.

B. Correct deficiencies in or remove roofing system that does not comply with requirements, repair substrates, and repair or reinstall roofing system to a condition free of damage and deterioration at time of Substantial Completion and according to warranty requirements.

C. Clean overspray and spillage from adjacent construction using cleaning agents and procedures recommended by manufacturer of affected construction.

END OF SECTION 075216

Page 54: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning
Page 55: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SHEET METAL FLASHING AND TRIM – 076200 1 OF 12

SECTION 076200 - SHEET METAL FLASHING AND TRIM

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Manufactured through-wall flashing with counterflashing. 2. Manufactured reglets with counterflashing. 3. Formed roof-drainage sheet metal fabrications. 4. Formed low-slope roof sheet metal fabrications. 5. Formed wall sheet metal fabrications.

B. Related Requirements:

1. Section 061000 "Rough Carpentry" for wood nailers, curbs, and blocking. 2. Section 077200 "Roof Accessories" for set-on-type curbs, equipment supports, roof

hatches, vents, and other manufactured roof accessory units. 3. Section 077120 “Aluminum Cornice and Decorative Trim” for factory extruded

aluminum cornice profiles.

1.3 COORDINATION

A. Coordinate sheet metal flashing and trim layout and seams with sizes and locations of penetrations to be flashed, and joints and seams in adjacent materials.

B. Coordinate sheet metal flashing and trim installation with adjoining roofing and wall materials, joints, and seams to provide leakproof, secure, and noncorrosive installation.

1.4 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1. Review construction schedule. Verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays.

2. Review special roof details, roof drainage, roof-penetration flashing, equipment curbs, and condition of other construction that affect sheet metal flashing and trim.

3. Review requirements for insurance and certificates if applicable. 4. Review sheet metal flashing observation and repair procedures after flashing installation.

Page 56: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SHEET METAL FLASHING AND TRIM – 076200 2 OF 12

1.5 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for each manufactured product and accessory.

B. Shop Drawings: For sheet metal flashing and trim.

1. Include plans, elevations, sections, and attachment details. 2. Detail fabrication and installation layouts, expansion-joint locations, and keyed details.

Distinguish between shop- and field-assembled work. 3. Include identification of material, thickness, weight, and finish for each item and location

in Project. 4. Include details for forming, including profiles, shapes, seams, and dimensions. 5. Include details for joining, supporting, and securing, including layout and spacing of

fasteners, cleats, clips, and other attachments. Include pattern of seams. 6. Include details of termination points and assemblies. 7. Include details of expansion joints and expansion-joint covers, including showing

direction of expansion and contraction from fixed points. 8. Include details of roof-penetration flashing. 9. Include details of edge conditions, including eaves, ridges, valleys, rakes, crickets, and

counterflashings as applicable. 10. Include details of special conditions. 11. Include details of connections to adjoining work. 12. Detail formed flashing and trim at scale of not less than 3 inches per 12 inches.

C. Samples for Initial Selection: For each type of sheet metal and accessory indicated with factory-applied finishes.

D. Samples for Verification: For each type of exposed finish.

1. Sheet Metal Flashing: 12 inches long by actual width of unit, including finished seam and in required profile. Include fasteners, cleats, clips, closures, and other attachments.

2. Trim, Metal Closures, Expansion Joints, Joint Intersections, and Miscellaneous Fabrications: 12 inches long and in required profile. Include fasteners and other exposed accessories.

3. Unit-Type Accessories and Miscellaneous Materials: Full-size Sample. 4. Anodized Aluminum Samples: Samples to show full range to be expected for each color

required.

1.6 INFORMATIONAL SUBMITTALS

A. Qualification Data: For fabricator.

B. Product Certificates: For each type of coping and roof edge flashing that is SPRI ES-1 tested and FM Approvals approved.

C. Product Test Reports: For each product, for tests performed by a qualified testing agency.

Page 57: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SHEET METAL FLASHING AND TRIM – 076200 3 OF 12

D. Sample Warranty: For special warranty.

1.7 CLOSEOUT SUBMITTALS

A. Maintenance Data: For sheet metal flashing and trim, and its accessories, to include in maintenance manuals.

1.8 QUALITY ASSURANCE

A. Fabricator Qualifications: Employs skilled workers who custom fabricate sheet metal flashing and trim similar to that required for this Project and whose products have a record of successful in-service performance.

1. For copings and roof edge flashings that are SPRI ES-1 tested and FM Approvals approved, shop shall be listed as able to fabricate required details as tested and approved.

B. Mockups: Build mockups to verify selections made under Sample submittals, to demonstrate aesthetic effects, and to set quality standards for fabrication and installation.

1. Build mockup of typical roof edge, including gutter, fascia and fascia trim, approximately 10 feet long, including supporting construction cleats, seams, attachments, underlayment, and accessories.

2. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless Architect specifically approves such deviations in writing.

3. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

1.9 DELIVERY, STORAGE, AND HANDLING

A. Do not store sheet metal flashing and trim materials in contact with other materials that might cause staining, denting, or other surface damage. Store sheet metal flashing and trim materials away from uncured concrete and masonry.

B. Protect strippable protective covering on sheet metal flashing and trim from exposure to sunlight and high humidity, except to extent necessary for period of sheet metal flashing and trim installation.

1.10 WARRANTY

A. Special Warranty on Finishes: Manufacturer agrees to repair finish or replace sheet metal flashing and trim that shows evidence of deterioration of factory-applied finishes within specified warranty period.

1. Exposed Panel Finish: Deterioration includes, but is not limited to, the following:

a. Color fading more than 5 Hunter units when tested according to ASTM D 2244.

Page 58: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SHEET METAL FLASHING AND TRIM – 076200 4 OF 12

b. Chalking in excess of a No. 8 rating when tested according to ASTM D 4214. c. Cracking, checking, peeling, or failure of paint to adhere to bare metal.

2. Finish Warranty Period: 20 years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. General: Sheet metal flashing and trim assemblies shall withstand wind loads, structural movement, thermally induced movement, and exposure to weather without failure due to defective manufacture, fabrication, installation, or other defects in construction. Completed sheet metal flashing and trim shall not rattle, leak, or loosen, and shall remain watertight.

B. Sheet Metal Standard for Flashing and Trim: Comply with NRCA's "The NRCA Roofing Manual" and SMACNA's "Architectural Sheet Metal Manual" requirements for dimensions and profiles shown unless more stringent requirements are indicated.

C. FM Approvals Listing: Manufacture and install copings and roof edge flashings that are listed in FM Approvals' "RoofNav" and approved for windstorm classification per structure classification. Identify materials with name of fabricator and design approved by FM Approvals.

D. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes to prevent buckling, opening of joints, overstressing of components, failure of joint sealants, failure of connections, and other detrimental effects. Base calculations on surface temperatures of materials due to both solar heat gain and nighttime-sky heat loss.

1. Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces.

E. Expansion Provisions: Where lapped or bayonet-type expansion provisions in work cannot be used or would not be sufficiently water/weatherproof, form expansion joints of intermeshing hooked flanges, not less than 1 inch deep, filled with mastic sealant (concealed within joints).

2.2 SHEET METALS

A. General: Protect mechanical and other finishes on exposed surfaces from damage by applying strippable, temporary protective film before shipping.

B. Aluminum Sheet: ASTM B 209, alloy as standard with manufacturer for finish required, with temper as required to suit forming operations and performance required; with smooth, flat surface.

1. Color Anodic Finish, Coil Coated: AAMA 611, AA-M12C22A42/A44, Class I, 0.018 mm or thicker.

a. Color: As selected by Architect from full range of industry colors and color densities.

Page 59: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SHEET METAL FLASHING AND TRIM – 076200 5 OF 12

b. Color Range: Noticeable variations in same piece are not acceptable. Variations in appearance of adjoining components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast.

2. Exposed Coil-Coated Finish:

a. Two-Coat Fluoropolymer: AAMA 2605. Fluoropolymer finish containing not less than 70 percent PVDF resin by weight in color coat. Prepare, pretreat, and apply coating to exposed metal surfaces to comply with coating and resin manufacturers' written instructions.

3. Color: As selected by Architect from manufacturer's full range. 4. Concealed Finish: Pretreat with manufacturer's standard white or light-colored acrylic or

polyester backer finish, consisting of prime coat and wash coat with minimum total dry film thickness of 0.5 mil.

2.3 UNDERLAYMENT MATERIALS

A. Felt: ASTM D 226/D 226M, Type II (No. 30), asphalt-saturated organic felt; nonperforated.

B. Slip Sheet: Rosin-sized building paper, 3 lb/100 sq. ft. minimum.

2.4 MISCELLANEOUS MATERIALS

A. General: Provide materials and types of fasteners, solder, protective coatings, sealants, and other miscellaneous items as required for complete sheet metal flashing and trim installation and as recommended by manufacturer of primary sheet metal or manufactured item unless otherwise indicated.

B. Fasteners: Wood screws, annular threaded nails, self-tapping screws, self-locking rivets and bolts, and other suitable fasteners designed to withstand design loads and recommended by manufacturer of primary sheet metal or manufactured item.

1. General: Blind fasteners or self-drilling screws, gasketed, with hex-washer head.

a. Exposed Fasteners: Heads matching color of sheet metal using plastic caps or factory-applied coating. Provide metal-backed EPDM or PVC sealing washers under heads of exposed fasteners bearing on weather side of metal.

b. Blind Fasteners: High-strength aluminum or stainless-steel rivets suitable for metal being fastened.

c. Spikes and Ferrules: Same material as gutter; with spike with ferrule matching internal gutter width.

2. Fasteners for Aluminum Sheet: Aluminum or Series 300 stainless steel.

C. Sealant Tape: Pressure-sensitive, 100 percent solids, polyisobutylene compound sealant tape with release-paper backing. Provide permanently elastic, nonsag, nontoxic, nonstaining tape 1/2 inch wide and 1/8 inch thick.

Page 60: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SHEET METAL FLASHING AND TRIM – 076200 6 OF 12

D. Elastomeric Sealant: ASTM C 920, elastomeric silicone polymer sealant; of type, grade, class, and use classifications required to seal joints in sheet metal flashing and trim and remain watertight.

E. Butyl Sealant: ASTM C 1311, single-component, solvent-release butyl rubber sealant; polyisobutylene plasticized; heavy bodied for hooked-type expansion joints with limited movement.

F. Epoxy Seam Sealer: Two-part, noncorrosive, aluminum seam-cementing compound, recommended by aluminum manufacturer for exterior nonmoving joints, including riveted joints.

G. Bituminous Coating: Cold-applied asphalt emulsion according to ASTM D 1187.

H. Asphalt Roofing Cement: ASTM D 4586, asbestos free, of consistency required for application.

2.5 MANUFACTURED SHEET METAL FLASHING AND TRIM

A. Through-Wall, Ribbed, Sheet Metal Flashing: Manufacture through-wall sheet metal flashing for embedment in masonry, with ribs at 3-inch intervals along length of flashing to provide integral mortar bond. Manufacture through-wall flashing with snaplock receiver on exterior face to receive counterflashing.

1. Copper: 10-oz. weight minimum for fully concealed flashing; 16 oz. weight elsewhere.

a. Equal to Keystone Flashing Company b. FAMCO (Fresh Air Manufacturing Company) c. Peterson Aluminum Corporation

B. Reglets: Units of type, material, and profile required, formed to provide secure interlocking of separate reglet and counterflashing pieces, and compatible with flashing indicated with factory-mitered and -welded corners and junctions and with interlocking counterflashing on exterior face, of same metal as reglet.

1. Equal to FRY Reglet Architectural Metals. 2. Material: Aluminum, 0.024 inch. 3. Surface-Mounted Type: Provide with slotted holes for fastening to substrate, with

neoprene or other suitable weatherproofing washers, and with channel for sealant at top edge.

4. Masonry Type: Provide with offset top flange for embedment in masonry mortar joint. 5. Accessories:

a. Flexible-Flashing Retainer: Provide resilient plastic or rubber accessory to secure flexible flashing in reglet where clearance does not permit use of standard metal counterflashing or where Drawings show reglet without metal counterflashing.

b. Counterflashing Wind-Restraint Clips: Provide clips to be installed before counterflashing to prevent wind uplift of counterflashing's lower edge.

6. Finish: As selected by Architect from manufacturer's full range.

Page 61: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SHEET METAL FLASHING AND TRIM – 076200 7 OF 12

2.6 FABRICATION, GENERAL

A. General: Custom fabricate sheet metal flashing and trim to comply with details shown and recommendations in cited sheet metal standard that apply to design, dimensions, geometry, metal thickness, and other characteristics of item required. Fabricate sheet metal flashing and trim in shop to greatest extent possible.

1. Fabricate sheet metal flashing and trim in thickness or weight needed to comply with performance requirements, but not less than that specified for each application and metal.

2. Obtain field measurements for accurate fit before shop fabrication. 3. Form sheet metal flashing and trim to fit substrates without excessive oil canning,

buckling, and tool marks; true to line, levels, and slopes; and with exposed edges folded back to form hems.

4. Conceal fasteners and expansion provisions where possible. Do not use exposed fasteners on faces exposed to view.

B. Fabrication Tolerances: Fabricate sheet metal flashing and trim that is capable of installation to a tolerance of 1/4 inch in 20 feet on slope and location lines indicated on Drawings and within 1/8-inch offset of adjoining faces and of alignment of matching profiles.

C. Expansion Provisions: Form metal for thermal expansion of exposed flashing and trim.

1. Form expansion joints of intermeshing hooked flanges, not less than 1 inch deep, filled with butyl sealant concealed within joints.

2. Use lapped expansion joints only where indicated on Drawings.

D. Sealant Joints: Where movable, nonexpansion-type joints are required, form metal to provide for proper installation of elastomeric sealant according to cited sheet metal standard.

E. Fabricate cleats and attachment devices from same material as accessory being anchored or from compatible, noncorrosive metal.

F. Seams: Fabricate nonmoving seams with flat-lock seams. Tin edges to be seamed, form seams, and solder.

G. Seams for Aluminum: Fabricate nonmoving seams with flat-lock seams. Form seams and seal with epoxy seam sealer.

H. Do not use graphite pencils to mark metal surfaces.

2.7 LOW-SLOPE ROOF SHEET METAL FABRICATIONS

A. Roof Edge Flashing and Fascia Cap: Fabricate in minimum 96-inch long, but not exceeding 12-foot long sections. Furnish with 6-inch wide, joint cover plates. Shop fabricate interior and exterior corners.

1. Joint Style: Butted with expansion space and 6-inch wide, concealed backup plate. 2. Fabricate from the Following Materials:

a. Aluminum: 0.050 inch thick.

Page 62: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SHEET METAL FLASHING AND TRIM – 076200 8 OF 12

B. Copings: Fabricate in minimum 96-inch long, but not exceeding 12-foot long, sections. Fabricate joint plates of same thickness as copings. Furnish with continuous cleats to support edge of external leg and drill elongated holes for fasteners on interior leg. Miter corners, solder or weld watertight. Shop fabricate interior and exterior corners.

1. Coping Profile: As indicated on drawings and according to SMACNA's "Architectural Sheet Metal Manual."

2. Joint Style: Butted with expansion space and 6-inch wide, concealed backup plate. 3. Fabricate from the Following Materials:

a. Aluminum: 0.050 inch thick.

C. Base Flashing: Shop fabricate interior and exterior corners. Fabricate from the following materials:

1. Aluminum: 0.040 inch thick.

D. Counterflashing: Shop fabricate interior and exterior corners. Fabricate from the following materials:

1. Aluminum: 0.032 inch thick.

E. Flashing Receivers: Fabricate from the following materials:

1. Aluminum: 0.032 inch thick.

2.8 WALL SHEET METAL FABRICATIONS

A. Through-Wall Flashing: Fabricate continuous flashings in minimum 96-inch long, but not exceeding 12-foot long, sections, under copings, and at shelf angles. Fabricate discontinuous lintel, sill, and similar flashings to extend 6 inches beyond each side of wall openings; and form with 2-inch high, end dams. Fabricate from the following materials:

1. Copper: 16 oz./sq. ft.

2.9 ALUMINUM COMPOSITE MATERIAL

A. Basis of Design: Reynobond by Alcoa

B. Thickness: 6mm

C. Panel installation type: Dry-seal installation system

D. Finish: Modified Polyester, 15 year warranty

E. Colors: To be selected from Manufacturers full line, including metallics.

Page 63: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SHEET METAL FLASHING AND TRIM – 076200 9 OF 12

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances, substrate, and other conditions affecting performance of the Work.

1. Verify compliance with requirements for installation tolerances of substrates. 2. Verify that substrate is sound, dry, smooth, clean, sloped for drainage, and securely

anchored. 3. Verify that air- or water-resistant barriers have been installed over sheathing or backing

substrate to prevent air infiltration or water penetration.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 UNDERLAYMENT INSTALLATION

A. Felt Underlayment: Install felt underlayment, wrinkle free, using adhesive to minimize use of mechanical fasteners under sheet metal flashing and trim. Apply in shingle fashion to shed water, with lapped joints of not less than 2 inches.

B. Apply slip sheet, wrinkle free, before installing sheet metal flashing and trim.

3.3 INSTALLATION, GENERAL

A. General: Anchor sheet metal flashing and trim and other components of the Work securely in place, with provisions for thermal and structural movement. Use fasteners, solder, protective coatings, separators, sealants, and other miscellaneous items as required to complete sheet metal flashing and trim system.

1. Install sheet metal flashing and trim true to line, levels, and slopes. Provide uniform, neat seams with minimum exposure of solder, welds, and sealant.

2. Install sheet metal flashing and trim to fit substrates and to result in watertight performance. Verify shapes and dimensions of surfaces to be covered before fabricating sheet metal.

3. Space cleats not more than 12 inches apart. Attach each cleat with at least two fasteners. Bend tabs over fasteners.

4. Install exposed sheet metal flashing and trim with limited oil canning, and free of buckling and tool marks.

5. Torch cutting of sheet metal flashing and trim is not permitted. 6. Do not use graphite pencils to mark metal surfaces.

Page 64: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SHEET METAL FLASHING AND TRIM – 076200 10 OF 12

B. Metal Protection: Where dissimilar metals contact each other, or where metal contacts pressure-treated wood or other corrosive substrates, protect against galvanic action or corrosion by painting contact surfaces with bituminous coating or by other permanent separation as recommended by sheet metal manufacturer or cited sheet metal standard.

1. Coat concealed side of uncoated-aluminum sheet metal flashing and trim with bituminous coating where flashing and trim contact wood, ferrous metal, or cementitious construction.

2. Underlayment: Where installing sheet metal flashing and trim directly on cementitious or wood substrates, install underlayment and cover with slip sheet.

C. Expansion Provisions: Provide for thermal expansion of exposed flashing and trim. Space movement joints at maximum of 10 feet with no joints within 24 inches of corner or intersection.

1. Form expansion joints of intermeshing hooked flanges, not less than 1 inch deep, filled with sealant concealed within joints.

2. Use lapped expansion joints only where indicated on Drawings.

D. Fasteners: Use fastener sizes that penetrate substrate not less than recommended by fastener manufacturer to achieve maximum pull-out resistance.

E. Conceal fasteners and expansion provisions where possible in exposed work and locate to minimize possibility of leakage. Cover and seal fasteners and anchors as required for a tight installation.

F. Seal joints as required for watertight construction.

1. Use sealant-filled joints unless otherwise indicated. Embed hooked flanges of joint members not less than 1 inch into sealant. Form joints to completely conceal sealant. When ambient temperature at time of installation is between 40 and 70 deg F, set joint members for 50 percent movement each way. Adjust setting proportionately for installation at higher ambient temperatures. Do not install sealant-type joints at temperatures below 40 deg F.

2. Prepare joints and apply sealants to comply with requirements in Section 079200 "Joint Sealants."

G. Soldered Joints: Clean surfaces to be soldered, removing oils and foreign matter. Pre-tin edges of sheets with solder to width of 1-1/2 inches; however, reduce pre-tinning where pre-tinned surface would show in completed Work.

1. Do not solder metallic-coated steel and aluminum sheet. 2. Do not use torches for soldering. 3. Heat surfaces to receive solder, and flow solder into joint. Fill joint completely.

Completely remove flux and spatter from exposed surfaces. 4. Stainless-Steel Soldering: Tin edges of uncoated sheets, using solder for stainless steel

and acid flux. Promptly remove acid flux residue from metal after tinning and soldering. Comply with solder manufacturer's recommended methods for cleaning and neutralization.

5. Copper Soldering: Tin edges of uncoated sheets, using solder for copper.

Page 65: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SHEET METAL FLASHING AND TRIM – 076200 11 OF 12

6. Copper-Clad Stainless-Steel Soldering: Tin edges of uncoated sheets, using solder for copper-clad stainless steel.

3.4 ROOF FLASHING INSTALLATION

A. General: Install sheet metal flashing and trim to comply with performance requirements, sheet metal manufacturer's written installation instructions, and cited sheet metal standard. Provide concealed fasteners where possible, and set units true to line, levels, and slopes. Install work with laps, joints, and seams that are permanently watertight and weather resistant.

B. Roof Edge Flashing: Anchor to resist uplift and outward forces according to recommendations in FM Global Property Loss Prevention Data Sheet 1-49 for FM Approvals' listing for required windstorm classification.

C. Copings: Anchor to resist uplift and outward forces according to recommendations in FM Global Property Loss Prevention Data Sheet 1-49 for specified FM Approvals' listing for required windstorm classification.

D. Pipe or Post Counterflashing: Install counterflashing umbrella with close-fitting collar with top edge flared for elastomeric sealant, extending minimum of 4 inches over base flashing. Install stainless-steel draw band and tighten.

E. Counterflashing: Coordinate installation of counterflashing with installation of base flashing. Insert counterflashing in reglets or receivers and fit tightly to base flashing. Extend counterflashing 4 inches over base flashing. Lap counterflashing joints minimum of 4 inches. Secure in waterproof manner by means of snap-in installation and sealant or lead wedges and sealant unless otherwise indicated.

3.5 WALL FLASHING INSTALLATION

A. General: Install sheet metal wall flashing to intercept and exclude penetrating moisture according to cited sheet metal standard unless otherwise indicated. Coordinate installation of wall flashing with installation of wall-opening components such as windows, doors, and louvers.

3.6 ERECTION TOLERANCES

A. Installation Tolerances: Shim and align sheet metal flashing and trim within installed tolerance of 1/4 inch in 20 feet on slope and location lines indicated on Drawings and within 1/8-inch offset of adjoining faces and of alignment of matching profiles.

3.7 CLEANING AND PROTECTION

A. Clean exposed metal surfaces of substances that interfere with uniform oxidation and weathering.

B. Clean and neutralize flux materials. Clean off excess solder.

Page 66: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 SHEET METAL FLASHING AND TRIM – 076200 12 OF 12

C. Clean off excess sealants.

D. Remove temporary protective coverings and strippable films as sheet metal flashing and trim are installed unless otherwise indicated in manufacturer's written installation instructions. On completion of sheet metal flashing and trim installation, remove unused materials and clean finished surfaces as recommended by sheet metal flashing and trim manufacturer. Maintain sheet metal flashing and trim in clean condition during construction.

E. Replace sheet metal flashing and trim that have been damaged or that have deteriorated beyond successful repair by finish touchup or similar minor repair procedures.

END OF SECTION 076200

Page 67: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ALUMINUM CORNICE AND DECORATIVE TRIM – 077120 1 OF 10

SECTION 077120 - ALUMINUM CORNICE AND DECORATIVE TRIM

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Provide labor, material, and equipment necessary for furnishing a complete installation of pre-designed aluminum cornice & decorative trims.

B. Section Includes:

1. Cornices & Formed Decorative Trim 2. Gutters and Downspouts 3. Soffit Panels & Trim

C. Related Requirements:

1. Section 061000 "Rough Carpentry" for wood nailers, curbs, and blocking. 2. Section 074113 “Standing-Seam Metal Roof” for installation of cornice and trim integral

with roofing.

1.3 COORDINATION

A. Coordinate cornice and trim layout and seams with sizes and locations of penetrations to be flashed, and joints and seams in adjacent materials.

B. Coordinate cornice and trim installation with adjoining roofing and wall materials, joints, and seams to provide leakproof, secure, and noncorrosive installation.

1.4 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1. Review construction schedule. Verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays.

2. Review special roof details, roof drainage, roof-penetration flashing, equipment curbs, and condition of other construction that affect cornice and trim.

3. Review requirements for insurance and certificates if applicable. 4. Review cornice and trim observation and repair procedures after installation.

Page 68: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ALUMINUM CORNICE AND DECORATIVE TRIM – 077120 2 OF 10

1.5 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for each manufactured product and accessory.

B. Shop Drawings: For sheet metal flashing and trim.

1. Include plans, elevations, sections, and attachment details. 2. Detail fabrication and installation layouts, expansion-joint locations, and keyed details.

Distinguish between shop- and field-assembled work. 3. Include identification of material, thickness, weight, and finish for each item and location

in Project. 4. Include details for forming, including profiles, shapes, seams, and dimensions. 5. Include details for joining, supporting, and securing, including layout and spacing of

fasteners, cleats, clips, gussets and other attachments. Include pattern of seams. 6. Include details of termination points and assemblies. 7. Include details of expansion joints and expansion-joint covers, including showing

direction of expansion and contraction from fixed points. 8. Include details of edge conditions, including eaves, ridges, valleys, rakes, crickets, and

counterflashings as applicable. 9. Include details of special conditions. 10. Include details of connections to adjoining work. 11. Detail formed flashing and trim at scale of not less than 3 inches per 12 inches (1:5).

C. Samples for Initial Selection: For each type of sheet metal and accessory indicated with factory-applied finishes.

D. Samples for Verification: For each type of exposed finish.

1. Cornice: 12 inches long by actual width of unit, including finished seam and in required profile. Include fasteners, cleats, clips, closures, gussets and other attachments.

2. Trim, Metal Closures, Soffit Panels. Expansion Joints, Joint Intersections, and Miscellaneous Fabrications: 12 inches long and in required profile. Include fasteners and other exposed accessories.

3. Gutters and Downspouts: 12 inches long by actual width of unit, including finished seam and in required profile. Include fasteners, cleats, clips, closures, gussets and other attachments.

4. Finish & Color Selection: Furnish manufacturer's technical data for specified finish and color chart showing full range of colors available.

1.6 INFORMATIONAL SUBMITTALS

A. Qualification Data: For fabricator.

B. Product Test Reports: For each product, for tests performed by a qualified testing agency.

C. Sample Warranty: For special warranty.

Page 69: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ALUMINUM CORNICE AND DECORATIVE TRIM – 077120 3 OF 10

1.7 CLOSEOUT SUBMITTALS

A. Maintenance Data: For cornice, decorative trim, gutters & downspouts, soffit panels and its accessories, to include in maintenance manuals.

1.8 QUALITY ASSURANCE

A. Where pre-engineered manufactured products are specified, other field fabricated or shop/field fabricated substitutions will not be accepted. However, where shop/field fabrications are indicated pre-engineered systems will be considered with Architect approval.

B. Obtain all components and related accessories from one single source manufacturer.

C. Follow manufacturer's guidelines & shop drawings for installing pre-designed cornice & decorative trims. If cornice or trims join a roof system then follow primary roofing manufacturer's printed instructions for installing associated roof material for flashing decorative trims to roof.

D. Mockups: Build mockups to verify selections made under Sample submittals, to demonstrate aesthetic effects, and to set quality standards for fabrication and installation.

1. Build mockup of typical roof edge and eave, including gutter, downspout, and soffit panel approximately 4 feet long, including supporting construction cleats, seams, gussets, attachments, and accessories.

2. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless Architect specifically approves such deviations in writing.

1.9 DELIVERY, STORAGE, AND HANDLING

A. Do not store materials in contact with other materials that might cause staining, denting, or other surface damage. Store materials away from uncured concrete and masonry and in a clean dry location.

B. Protect strippable protective covering on sheet metal flashing and trim from exposure to sunlight and high humidity, except to extent necessary for period of sheet metal flashing and trim installation.

C. Do not install finished materials with scars or abrasions.

1.10 FIELD CONDITIONS

A. Coordinate work of this Section with adjoining work for proper sequencing to ensure protection from inclimate weather and to protect materials and their finish against damage.

B. Do not install cornice & decorative trims during inclimate weather. When installing in cold climates warm sealant to at least 50 degrees Fahrenheit prior to application.

Page 70: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ALUMINUM CORNICE AND DECORATIVE TRIM – 077120 4 OF 10

1.11 WARRANTY

A. Special Warranty on Finishes: Manufacturer agrees to repair finish or replace materials that show evidence of deterioration of factory-applied finishes within specified warranty period.

1. Exposed Panel Finish: Deterioration includes, but is not limited to, the following:

a. Color fading more than 5 Hunter units when tested according to ASTM D 2244. b. Chalking in excess of a No. 8 rating when tested according to ASTM D 4214. c. Cracking, checking, peeling, or failure of paint to adhere to bare metal.

2. Finish Warranty Period: 20 years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Provide aluminum cornice, decorative trims, gutters & downspouts, soffit panels & trim and accessories as manufactured by Perimeter Systems, a division of Southern Aluminum Finishing Company, Inc. 139 Chatham Street Sanford, North Carolina 27330 1-800-334-9823 or equal.

2.2 ALUMINUM CORNICE & DECORATIVE TRIM

A. Decorative cornice profiles shall be manufactured from 0.040" mill finished aluminum, 10'-0" lengths, in shapes as indicated by manufacturer's printed literature and as indicated on drawings.

1. All profiles containing radius bends shall be press formed with radius dies on a CNC Press to provide repeated true and accurate profiles.

2. All cornice trims shall be factory punched with elongated fastening holes. 3. All exposed surfaces of cornice profiles shall be finished as specified in this section. 4. All cornice trims to be formed to fit the inside of the cornice profiles.

B. Support Brackets, attachments brackets and retainer brackets shall be manufactured from 0.125" x 1.00" extruded aluminum bar, helliarc welded construction (where necessary), factory punched for fasteners.

C. Mounting Gussets shall be manufactured from 22 gauge, galvanized steel, G90 coating.

D. Provide Perimeter Systems' Designer Series Commercial, or equal.

2.3 ALUMINUM GUTTER & DOWNSPOUT SYSTEM -

A. Concealed Gutter Liner

1. Gutter System "Extruded Profiles ", Assembly Model 100 or equal.

Page 71: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ALUMINUM CORNICE AND DECORATIVE TRIM – 077120 5 OF 10

2. Concealed Gutter Liner shall be formed from 0.040" mill finished aluminum, alloy 3003, temper H-14, in 10'-0" lengths. Liner shall be:

a. Factory punched with fastening holes elongated to allow for thermal movement. b. Factory punched with fastening holes at its ends for field riveting.

3. Support Bracket Assembly shall be formed from 0.125" x 1.00" aluminum, alloy 3003, temper H-14, heliarc welded construction, factory punched for fasteners.

4. Interior Straps shall be formed from 0.125" x 1.00" aluminum alloy 3003, temper H-14.

5. Joint splices shall be formed from 0.040" aluminum, alloy 3003, temper H-14, formed to fit the concealed liner's exterior, and factory punched for field riveting.

6. Retention clips shall be formed from 26 gauge stainless spring steel, type 304-2B finish. Retention clips shall be factory punched for field fastening.

B. Mouldings

1. Gutter soffit shall be formed from 0.040" aluminum, alloy 3003, temper H-14. Soffits shall be factory notched for lap joining.

2. Gutter fascia moulding and splices shall be Extruded Aluminum, alloy 6063-T5, model 100.

3. Gutter fascia top closure shall be Extruded Aluminum, alloy 6063-T5, model 700. 4. Gutter fascia top closure concealed splice connector shall be formed from 0.040"

aluminum, alloy 3003, temper H-14.

2.4 ALUMINUM DOWNSPOUTS (DRAINWARE)

A. Downspout & Elbows, provide downspout Model Number DS-EX in sizes and locations as indicated on plans. Downspouts shall be manufactured from extruded aluminum, alloy 6063-T5 finished to match gutter fascia mouldings. Downspout elbows shall have heliarc welded joints.

B. Outlets, at all downspout locations provide aluminum outlets to connect liner to downspout.

C. Wall Brackets, provide Style 1 Wall brackets at 60" maximum spacing (minimum 2 brackets). Brackets shall be formed from 0.125" x 1.00" aluminum, alloy 3003, temper H14, finished to match downspout.

2.5 ALUMINUM SOFFIT PANELS & TRIM

A. Pre-formed aluminum soffit system, Vented Trims and accessories in shapes as indicated by manufacturer's printed literature and as indicated on drawings. Types to include:

1. Form Flat Soffit Panel, Non-Vented 1/2 inch Deep and 12 inches wide. 2. 4" Vented Trim

Page 72: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ALUMINUM CORNICE AND DECORATIVE TRIM – 077120 6 OF 10

B. Aluminum Panels: ASTM B209, Aluminum Association specification sheet 3003-H14/3105-H14 for painted finish and 5005-H34 for anodized finish.

1. Thickness: 0.032 inch.

C. Form panels and trims in longest practical lengths, true to shape, accurate in size, square, and free from distribution or manufacturing defects.

D. Fabricate panels with an interlocking leg (male/female interlocking joint design).

2.6 ACCESSORIES

A. Mitered Corners, provide factory mitered corners for all cornice profiles (excluding soffits). Cornice profiles shall be precision saw cut, helliarc tack welded to produce a picture frame joint.

B. Mitered Corners, provide factory mitered corners for concealed liners. Mitered corners shall have a water tight continuous heliarc welded joint.

C. Sculptured End Caps, provide factory mitered end caps for cornice. Cornice profiles shall be precision saw cut, helliarc tack welded to produce a picture frame joint.

D. Provide heliarc welded liner end caps at all terminations and wall abutments.

E. Cornice Returns, if shown on drawings, provide cornice returns at eaves & rake terminations in lengths as indicated on plans.

F. Rake & Gable Trims, as shown on drawings, provide rake and gable trims in profiles as indicated complete with concealed splices, attachment brackets (if required).

1. Provide factory mitered corners, precision saw cut, helliarc tack welded to produce a picture frame joint.

G. VHB Assist / Isolator Tape shall be 45 mill, 1" width, synthetic composition, double sided and high adhesion.

H. Hardware for fastening cornice members shall be stainless steel, type 304, #8-32 x 0.75" machine screws with nylon core hex lock nuts.

I. Hardware for mounting gussets shall be selected based on minimum pull strength of 100 lbs / fastener. Fastener material & type must be compatible with building substrates and in conformance with local building codes.

J. Fasteners for Soffit Panels & Trim: Concealed, non-corrosive stainless steel nails or screws.

K. Provide manufacturer's expansion joints at 40' intervals. Expansion joints shall consist of an aluminum splice connector, bond breaker tape, and adhesive backed elastomeric membrane.

Page 73: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ALUMINUM CORNICE AND DECORATIVE TRIM – 077120 7 OF 10

2.7 FINISHES

A. General: Apply coatings to exposed aluminum components after fabrication for maximum coating performance and to prevent crazing, abrasion, and damage to finished surfaces.

B. Pretreatment: Aluminum components shall be pretreated with solutions to remove organic and inorganic surface soils, remove residual oxides, followed by a chrome phosphate conversion coating to which organic coatings will firmly adhere.

C. Coating Type: High Performance Coating, two-coat, shop applied, 70% Polyvinylidene Fluoride (PVDF) coating based on Elf Arkema Chemicals, Inc. Kynar 500 or Ausimont U.S.A., Inc. Hylar 5000 resin, meeting AAMA 2605 specification.

D. Color: Select from manufacturer's full range of 56 EZ Mix colors.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances, substrate, and other conditions affecting performance of the Work.

1. Verify compliance with requirements for installation tolerances of substrates. 2. Verify that substrate is sound, dry, smooth, clean, sloped for drainage, and securely

anchored. 3. Verify that air- or water-resistant barriers have been installed over sheathing or backing

substrate to prevent air infiltration or water penetration.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION, GENERAL

A. General: The pre-designed cornice and decorative trims shall be installed in strict accordance With manufacturer's printed instructions and shop drawings.

B. Prior to the installation of the commercial gutter system, soffits, extenders, and associated cornice profiles shall be installed.

C. Anchor materials and other components of the Work securely in place, with provisions for thermal and structural movement. Use fasteners, solder, protective coatings, separators, sealants, and other miscellaneous items as required to complete system.

1. Install system true to line, levels, and slopes. Provide uniform, neat seams with minimum exposure of solder, welds, and sealant.

2. Install system to fit substrates and to result in watertight performance. Verify shapes and dimensions of surfaces to be covered before fabricating.

3. Torch cutting is not permitted.

Page 74: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ALUMINUM CORNICE AND DECORATIVE TRIM – 077120 8 OF 10

4. Do not use graphite pencils to mark metal surfaces. 5. Install cornice profiles and decorative trims with concealed splice plates over brackets

and/or framing substrates as shown on shop drawings. In accordance with shop drawings;

a. Coordinate and align spacing of expansion reveal joints with associated trims (stack joints).

b. Plan spacing of joints so there is no sections of fascia shorter than 48" in length. c. Check horizontal alignment of fascia during installation and adjust as required.

D. Metal Protection: Where dissimilar metals contact each other, or where metal contacts pressure-treated wood or other corrosive substrates, protect against galvanic action or corrosion by painting contact surfaces with bituminous coating or by other permanent separation as recommended by sheet metal manufacturer or cited sheet metal standard.

1. Coat concealed side of uncoated-aluminum sheet metal flashing and trim with bituminous coating where flashing and trim contact wood, ferrous metal, or cementitious construction.

2. Underlayment: Where installing sheet metal flashing and trim directly on cementitious or wood substrates, install underlayment and cover with slip sheet.

E. Expansion Provisions: Provide for thermal expansion of exposed material per manufacturers written requirements.

F. Fastening:

1. Cornice trims shall be nailed through elongated holes with 1-1/2" stainless steel nails. Support brackets, retaining brackets and attachment brackets shall be installed with #10 x 2" stainless steel wood screws at locations and spacing as shown on shop drawings.

2. Wood Substrates: Cornice trims must be order with factory punched elongated holes. Cornice trims shall be fastened with #8 x 1-1/2" stainless wood screws. Support brackets, retaining brackets and attachment brackets shall be installed with #10 x 2" stainless steel wood screws at locations and spacing as shown on shop drawings.

3. Steel Gussets: VHB Assist / Isolator tapes shall be adhered at all fastening locations to separate dissimilar metals. Field drill cornice trims w/ .1875" diameter drill bit at all fastening locations. Fasten cornice members with stainless steel, type 304, #8-32 x 0.75" machine screws with nylon core hex lock nuts.

4. Aluminum miter connections: Field drill cornice trims w/ .1875" diameter drill bit at all fastening locations. Fasten cornice members with stainless steel, type 304, #8-32 x 0.75" machine screws with nylon core hex lock nuts.

G. Seal joints as required for watertight construction per manufacturers written instructions.

H. Splice Joints: Install cornice profiles and decorative trims with concealed splice plates over brackets and/or framing substrates as shown on shop drawings. In accordance with shop drawings;

1. Coordinate and align spacing of expansion reveal joints with associated trims (stack joints).

2. Plan spacing of joints so there is no sections of fascia shorter than 48" in length. 3. Check horizontal alignment of fascia during installation and adjust as required. 4. Remove cornice moulding fastening and locking flanges to accommodate splice plates.

Page 75: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ALUMINUM CORNICE AND DECORATIVE TRIM – 077120 9 OF 10

I. Mitered Corners, provide factory mitered corners for all cornice profiles (excluding soffits). Cornice profiles shall be precision saw cut, helliarc tack welded to produce a picture frame joint.

3.3 LINER INSTALLATION

A. General: The commercial gutter system shall be installed in strict accordance with manufacturer's printed instructions. Deviations from the instructions are not allowed. Use manufacturer's hardware to install gutter and moulding components.

B. Support Brackets: Layout support brackets to provide 1/2" slope in 20 linear feet. Install support brackets with #10 x 1-1/2" stainless steel wood screws.

C. Liner: Install concealed gutter liner onto support brackets and fasten to substrates with #10 x 1-1/2" stainless steel wood screws.

D. Liner Splices: Install concealed gutter liner splices at all liner joints. Rivet and seal liner joints and splices with high grade exterior sealant furnished by gutter manufacturer.

E. Expansion Joints: Install elastomeric expansion joints as shown on plans and/or shop drawings. Maximum expansion joint spacing shall be 40' centers.

F. Locate and install downspouts outlets or concealed drains before proceeding with liner installation.

G. Install interior straps & washers to the liners rear edge and align with mating support brackets. Fasten straps to support brackets and substrates with #10 x 1-1/2" stainless steel wood screws.

H. Install top closure retention clips at all strap and bracket locations. Secure into position with #10 x .75" stainless screws and nylon core hex lock nuts.

3.4 MOULDINGS & FASCIA INSTALLATION

A. General: Plan moulding lengths to minimize or equally space joints. Gutters with multiple mouldings shall have their joints align "stacked".

B. Install mouldings with manufacturer's hardware.

C. Prior to installation; Saw cut mouldings to length and prepare "dress" ends for a splice connection. Dress their ends by removing fastening and interlocking joint flanges for a distance of 3".

D. Follow manufacturer's printed instructions for installing mouldings. Insert concealed splice plates at their ends to join them. Allow 3/8" between sections of mouldings for thermal movement.

Page 76: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ALUMINUM CORNICE AND DECORATIVE TRIM – 077120 10 OF 10

E. Mitered Corners, provide factory mitered corners for all cornice profiles (excluding soffits). Cornice profiles shall be precision saw cut, helliarc tack welded to produce a picture frame joint.

3.5 DOWNSPOUT INSTALLATION

A. General: Drainage for this commercial grade gutter system is to be accomplished with concealed internal drains furnished and installed by this contractor. Connection and piping shall be furnished by other trades, however, it is this contractors responsibility to coordinate the installation.

B. Provide concealed drain with 4" threaded outlet. Drain shall be manufactured from aluminum and furnished with a removable leaf grate. Provide drains with horizontal and/or angular outlets as shown on plans.

3.6 SOFFIT PANELS & TRIM INSTALLATION

A. General: The aluminum soffit system shall be installed in strict accordance with manufacturer's printed instructions and shop drawings.

B. Fastening: Concealed, non-corrosive stainless steel nails or screws.

C. Install soffit system plumb, level and true to framing substrates as shown on shop drawings, manufacturer’s instructions, SMACNA manual and/or standard practices.

3.7 ERECTION TOLERANCES

A. Installation Tolerances: Shim and align sheet metal flashing and trim within installed tolerance of 1/4 inch in 20 feet on slope and location lines indicated on Drawings and within 1/8-inch offset of adjoining faces and of alignment of matching profiles.

3.8 CLEANING AND PROTECTION

A. Installation of materials and systems shall be installed in strict accordance with manufacturer's printed instructions and shop drawings.

B. Clean off excess sealants.

C. Remove temporary protective coverings and strippable films as materials are installed unless otherwise indicated in manufacturer's written installation instructions. On completion of installation, remove unused materials and clean finished surfaces as recommended by the manufacturer. Maintain in clean condition during construction.

D. Replace materials that have been damaged or that have deteriorated beyond successful repair by finish touchup or similar minor repair procedures.

END OF SECTION 077120

Page 77: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ROOF ACCESSORIES – 077200 1 OF 5

SECTION 077200 - ROOF ACCESSORIES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Roof hatches. 2. Gravity Roof Vents

B. Related Sections:

1. Section 055000 "Metal Fabrications" for metal vertical ladders, ships' ladders, and stairs for access to roof hatches.

2. Section 075216 "(SBS) Modified Bituminous Membrane Roofing" for roof flashing.

1.3 COORDINATION

A. Coordinate layout and installation of roof accessories with roofing membrane and base flashing and interfacing and adjoining construction to provide a leakproof, weathertight, secure, and noncorrosive installation.

B. Coordinate dimensions with rough-in information or Shop Drawings of equipment to be supported.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of roof accessory.

1. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes.

B. Shop Drawings: For roof accessories.

1. Include plans, elevations, keyed details, and attachments to other work. Indicate dimensions, loadings, and special conditions. Distinguish between plant- and field-assembled work.

C. Samples: For each exposed product and for each color and texture specified, prepared on Samples of size to adequately show color.

Page 78: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ROOF ACCESSORIES – 077200 2 OF 5

1.5 INFORMATIONAL SUBMITTALS

A. Coordination Drawings: Roof plans, drawn to scale, and coordinating penetrations and roof-mounted items. Show the following:

1. Size and location of roof accessories specified in this Section. 2. Method of attaching roof accessories to roof or building structure. 3. Required clearances.

B. Sample Warranties: For manufacturer's special warranties.

1.6 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For roof accessories to include in operation and maintenance manuals.

1.7 WARRANTY

A. Special Warranty on Painted Finishes: Manufacturer's standard form in which manufacturer agrees to repair finishes or replace roof accessories that show evidence of deterioration of factory-applied finishes within specified warranty period.

1. Fluoropolymer Finish: Deterioration includes, but is not limited to, the following:

a. Color fading more than 5 Hunter units when tested according to ASTM D 2244. b. Chalking in excess of a No. 8 rating when tested according to ASTM D 4214. c. Cracking, checking, peeling, or failure of paint to adhere to bare metal.

2. Finish Warranty Period: 20 years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. General Performance: Roof accessories shall withstand exposure to weather and resist thermally induced movement without failure, rattling, leaking, or fastener disengagement due to defective manufacture, fabrication, installation, or other defects in construction.

2.2 ROOF HATCH

A. Roof Hatches: Metal roof-hatch units with lids and insulated double-walled curbs, welded or mechanically fastened and sealed corner joints, continuous lid-to-curb counterflashing and weathertight perimeter gasketing, straight sides, and integrally formed deck-mounting flange at perimeter bottom.

1. Equal Bilco Type E Roof Hatch by The Bilco Company.

Page 79: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ROOF ACCESSORIES – 077200 3 OF 5

B. Type and Size: Single-leaf lid, 36 by 36 inches.

C. Loads: Minimum 40-lbf/sq. ft. external live load and 20-lbf/sq. ft. internal uplift load.

D. Hatch Material: Aluminum sheet.

1. Thickness: Manufacturer's standard thickness for hatch size indicated. 2. Finish: Two-coat fluoropolymer. 3. Color: As selected by Architect from manufacturer's full range.

E. Construction:

1. Insulation: Glass-fiber board.

a. R-Value: 12.0 according to ASTM C 1363.

2. Nailer: Factory-installed wood nailer continuous around hatch perimeter. 3. Hatch Lid: Opaque, insulated, and double walled, with manufacturer's standard metal

liner of same material and finish as outer metal lid. 4. Curb Liner: Manufacturer's standard, of same material and finish as metal curb. 5. On ribbed or fluted metal roofs, form flange at perimeter bottom to conform to roof

profile. 6. Fabricate curbs to minimum height of 12 inches above roofing surface unless otherwise

indicated. 7. Sloping Roofs: Where slope or roof deck exceeds 1:48, fabricate curb with perimeter

curb height that is tapered to accommodate roof slope so that top surfaces of perimeter curb are level. Equip hatch with water diverter or cricket on side that obstructs water flow.

F. Hardware: Spring operators, hold-open arm, galvanized-steel spring latch with turn handles, galvanized-steel butt- or pintle-type hinge system, and padlock hasps inside and outside.

1. Provide two-point latch on lids larger than 84 inches. 2. Provide remote-control operation.

G. Ladder-Assist Post: Roof-hatch manufacturer's standard device for attachment to roof-access ladder.

1. Operation: Post locks in place on full extension; release mechanism returns post to closed position.

2. Height: 42 inches above finished roof deck. 3. Material: Aluminum. 4. Post: 1-5/8-inch diameter pipe. 5. Finish: Manufacturer's standard baked enamel or powder coat.

a. Color: As selected by Architect from manufacturer's full range.

Page 80: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ROOF ACCESSORIES – 077200 4 OF 5

2.3 GRAVITY ROOF VENTS

A. Roof Relief Vents: Metal Gravity Roof Vent with flashing flange for enclosed space at perimeter of flat roof.

1. Equal to Greenheck GRSF-8, All-aluminum construction with integral bird-screen and built-in flashing flange.

B. Type and Size: 8 inch diameter vent, with 20.5 inch diameter weather resistant hood.

2.4 GENERAL FINISH REQUIREMENTS

A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for recommendations for applying and designating finishes.

B. Appearance of Finished Work: Noticeable variations in same piece are not acceptable. Variations in appearance of adjoining components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, to verify actual locations, dimensions, and other conditions affecting performance of the Work.

B. Verify that substrate is sound, dry, smooth, clean, sloped for drainage, and securely anchored.

C. Verify dimensions of roof openings for roof accessories.

D. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION

A. General: Install roof accessories according to manufacturer's written instructions.

1. Install roof accessories level; plumb; true to line and elevation; and without warping, jogs in alignment, buckling, or tool marks.

2. Anchor roof accessories securely in place so they are capable of resisting indicated loads. 3. Use fasteners, separators, sealants, and other miscellaneous items as required to complete

installation of roof accessories and fit them to substrates. 4. Install roof accessories to resist exposure to weather without failing, rattling, leaking, or

loosening of fasteners and seals.

Page 81: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 ROOF ACCESSORIES – 077200 5 OF 5

B. Metal Protection: Protect metals against galvanic action by separating dissimilar metals from contact with each other or with corrosive substrates by painting contact surfaces with bituminous coating or by other permanent separation as recommended by manufacturer.

1. Coat concealed side of uncoated aluminum roof accessories with bituminous coating where in contact with wood, ferrous metal, or cementitious construction.

2. Underlayment: Where installing roof accessories directly on cementitious or wood substrates, install a course of underlayment and cover with manufacturer's recommended slip sheet.

3. Bed flanges in thick coat of asphalt roofing cement where required by manufacturers of roof accessories for waterproof performance.

C. Roof-Hatch Installation:

1. Verify that roof hatch operates properly. Clean, lubricate, and adjust operating mechanism and hardware.

2. Attach safety railing system to roof-hatch curb. 3. Attach ladder-assist post according to manufacturer's written instructions.

D. Seal joints with elastomeric or butyl sealant as required by roof accessory manufacturer.

3.3 REPAIR AND CLEANING

A. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and repair galvanizing according to ASTM A 780/A 780M.

B. Touch up factory-primed surfaces with compatible primer ready for field painting according to Section 099113 "Exterior Painting."

C. Clean exposed surfaces according to manufacturer's written instructions.

D. Clean off excess sealants.

E. Replace roof accessories that have been damaged or that cannot be successfully repaired by finish touchup or similar minor repair procedures.

END OF SECTION 077200

Page 82: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning
Page 83: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 APPLIED FIREPROOFING – 078100 1 OF 9

SECTION 078100 - APPLIED FIREPROOFING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following:

1. Concealed sprayed fire-resistive materials for unrestrained assemblies.

B. Related Sections include the following:

1. Division 5 Section "Structural Steel" for surface conditions required for structural steel receiving sprayed fire-resistive materials.

2. Division 7 Section "Thermal Insulation" for fire-safing insulation.

1.3 DEFINITIONS

A. Concealed Sprayed Fire-Resistive Materials: Applied to surfaces that are concealed from view behind other construction when the Work is completed.

1.4 SUBMITTALS

A. Product Data: For each type of product indicated.

B. Shop Drawings: Structural framing plans indicating the following:

1. Locations and types of surface preparations required before applying sprayed fire-resistive material.

2. Extent of sprayed fire-resistive material for each construction and fire-resistance rating, including the following:

a. Applicable fire-resistance design designations of a qualified testing and inspecting agency acceptable to authorities having jurisdiction.

b. Minimum thicknesses needed to achieve required fire-resistance ratings of structural components and assemblies.

c. Designation of restrained and unrestrained conditions based on definitions in ASTM E 119, Appendix X3 as determined by a qualified professional engineer.

3. Treatment of sprayed fire-resistive material after application.

Page 84: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 APPLIED FIREPROOFING – 078100 2 OF 9

C. Product Certificates: Signed by manufacturer of sprayed fire-resistive material certifying that the products furnished comply with requirements.

D. Installer Certificates: Signed by manufacturer certifying that installers comply with specified requirements.

E. Qualification Data: For firms and persons specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.

F. Compatibility and Adhesion Test Reports: For primers and other coatings applied to structural steel. Provide reports from a qualified independent testing and inspecting agency engaged by Contractor. Confirm that primers and coatings proposed for application in shop or field are compatible with fire-resistive material. Instruct laboratory to determine compatibility according to requirements specified in "Quality Assurance" Article.

G. Product Test Reports: Indicate that physical properties of proposed sprayed fire-resistive materials comply with specified requirements based on comprehensive testing of current product formulations by a qualified testing and inspecting agency according to requirements specified in "Quality Assurance" Article.

H. Research/Evaluation Reports: Evidence of sprayed fire-resistive material's compliance with building code in effect for Project, from a model code organization acceptable to authorities having jurisdiction.

1.5 QUALITY ASSURANCE

A. Installer Qualifications: Engage an experienced installer certified, licensed, or otherwise qualified by sprayed fire-resistive material manufacturer as having the necessary experience, staff, and training to install manufacturer's products according to specified requirements. A manufacturer's willingness to sell its sprayed fire-resistive materials to Contractor or to an installer engaged by Contractor does not in itself confer qualification on the buyer.

B. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in the jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of sprayed fire-resistive materials that are similar to those indicated for this Project in material, design, and extent.

C. Testing Agency Qualifications: An independent testing and inspecting agency with the experience and capability to conduct the testing indicated without delaying the Work, as documented according to ASTM E 699.

Page 85: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 APPLIED FIREPROOFING – 078100 3 OF 9

D. Testing of Fire-Resistive Materials: By a qualified testing and inspecting agency engaged by Contractor or manufacturer according to the following requirements:

1. Testing is performed on specimens of sprayed fire-resistive materials that comply with laboratory testing requirements specified in Part 2 and are otherwise identical to installed fire-resistive materials, including application of accelerant, sealers, topcoats, tamping, troweling, rolling, and water overspray, if any of these are used in final application.

E. Testing for Compatibility and Adhesion: Engage a qualified testing and inspecting agency to prepare compatibility and adhesion test reports required in "Submittals" Article based on testing that complies with the following requirements:

1. Verify that manufacturer of fire-resistive material has not found primers or coatings to be incompatible with fire-resistive material based on its own laboratory testing or field experience.

F. Source Limitations: Obtain each type of sprayed fire-resistive material from one source and by a single manufacturer.

G. Fire-Test-Response Characteristics: Provide sprayed fire-resistive materials and assemblies identical to those tested for the following fire-test-response characteristics per test method indicated below by UL or another testing and inspecting agency acceptable to authorities having jurisdiction. Identify packages (bags) containing sprayed fire-resistive material with appropriate markings of applicable testing and inspecting agency.

1. Fire-Resistance Ratings: As indicated by reference to fire-resistive designs listed in UL's "Fire Resistance Directory," or in the comparable publication of another testing and inspecting agency acceptable to authorities having jurisdiction, for sprayed fire-resistive material serving as direct-applied protection, tested per ASTM E 119.

2. Surface-Burning Characteristics: As indicated for each sprayed fire-resistive product required, tested per ASTM E 84.

H. Provide products containing no detectable asbestos as determined according to the method specified in 40 CFR, Part 763, Subpart E, Appendix E, Section 1, "Polarized Light Microscopy."

1.6 DELIVERY, STORAGE, AND HANDLING

A. Deliver products to Project site in original, unopened packages with intact and legible manufacturers' labels identifying product and manufacturer; date of manufacture; shelf life, if applicable; and fire-resistance ratings applicable to Project.

B. Use materials with limited shelf life within period indicated. Remove from Project site and discard materials whose shelf life has expired.

C. Store materials inside, under cover, aboveground, so they are kept dry until ready for use. Remove from Project site and discard materials that have deteriorated.

Page 86: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 APPLIED FIREPROOFING – 078100 4 OF 9

1.7 PROJECT CONDITIONS

A. Environmental Limitations: Do not apply sprayed fire-resistive material when ambient or substrate temperatures are 40 deg F or lower, unless temporary protection and heat is provided to maintain temperatures at or above this level for 24 hours before, during, and for 24 hours after product application.

B. Ventilation: Ventilate building spaces during and after application of sprayed fire-resistive material. Use natural means or, where this is inadequate, forced-air circulation until fire-resistive material dries thoroughly.

1.8 SEQUENCING

A. Sequence and coordinate application of sprayed fire-resistive materials with other related work specified in other Sections to comply with the following requirements:

1. Provide temporary enclosures for interior applications to prevent deterioration of fire-resistive material due to exposure to unfavorable environmental conditions.

2. Avoid unnecessary exposure of fire-resistive material to abrasion and other damage likely to occur during construction operations subsequent to its application.

3. Do not apply fire-resistive material to metal roof deck substrates until roofing has been completed; prohibit roof traffic during application and drying of fire-resistive material.

4. Do not begin applying fire-resistive material until clips, hangers, supports, sleeves, and other items penetrating fire protection are in place.

5. Defer installing ducts, piping, and other items that would interfere with applying fire-resistive material until application of fire protection is completed.

6. Do not install enclosing or concealing construction until after fire-resistive material has been applied, inspected, tested, and corrections have been made to defective applications.

1.9 WARRANTY

A. General Warranty: The special warranty specified in this Article shall not deprive Owner of other rights Owner may have under other provisions of the Contract Documents and shall be in addition to, and run concurrent with, other warranties made by Contractor under requirements of the Contract Documents.

B. Special Warranty: Submit a written warranty, executed by Contractor and cosigned by Installer, agreeing to repair or replace sprayed fire-resistive materials that fail within the specified warranty period.

1. Failures include, but are not limited to, cracking, flaking, eroding in excess of specified requirements; peeling; and delaminating of sprayed fire-resistive materials from substrates due to defective materials and workmanship within the specified warranty period.

2. Not covered under the warranty are failures due to damage by occupants and Owner's maintenance personnel, exposure to environmental conditions other than those investigated and approved during fire-response testing, and other causes not reasonably foreseeable under conditions of normal use.

Page 87: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 APPLIED FIREPROOFING – 078100 5 OF 9

C. Warranty Period: 2 years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 CONCEALED SPRAYED FIRE-RESISTIVE MATERIALS (TYPICAL APPLICATIONS)

A. General: For concealed applications of sprayed fire-resistive materials, provide manufacturer's standard products complying with requirements indicated for material composition and physical properties representative of installed products.

B. Available Products:

1. Cementitious Sprayed Fire-Resistive Material:

a. Grace, W. R. & Co.--Conn., Construction Products Div.; Monokote Type MK-6s. b. Isolatek International Corp., Cafco Products; Cafco 300. c. Southwest Vermiculite Co., Inc.; 5GP.

C. Material Composition: As follows:

1. Cementitious sprayed fire-resistive material consisting of factory-mixed, dry formulation of gypsum or portland cement binders and lightweight mineral or synthetic aggregates mixed with water at Project site to form a slurry or mortar for conveyance and application.

D. Physical Properties: Minimum values, unless otherwise indicated, or higher values required to attain designated fire-resistance ratings, measured per standard test methods referenced with each property as follows:

1. Dry Density: 15 lb/cu. ft. for average and individual densities regardless of density indicated in referenced fire-resistance design, or greater if required to attain fire-resistance ratings indicated, per ASTM E 605 or AWCI Technical Manual 12-A, Section 5.4.5, "Displacement Method."

2. Thickness: Provide minimum average thickness required for fire-resistance design indicated according to the following criteria, but not less than 0.375 inch, per ASTM E 605:

a. Where the referenced fire-resistance design lists a thickness of 1 inch or greater, the minimum allowable individual thickness of sprayed fire-resistive material is the design thickness minus 0.25 inch.

b. Where the referenced fire-resistance design lists a thickness of less than 1 inch but more than 0.375 inch, the minimum allowable individual thickness of sprayed fire-resistive material is the greater of 0.375 inch or 75 percent of the design thickness.

c. No reduction in average thickness is permitted for those fire-resistance designs whose fire-resistance ratings were established at densities of less than 15 lb/cu. ft..

Page 88: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 APPLIED FIREPROOFING – 078100 6 OF 9

3. Bond Strength: 150 lbf/sq. ft. minimum per ASTM E 736 under the following conditions:

a. Field test sprayed fire-resistive material that is applied to flanges of wide-flange, structural-steel members on surfaces matching those that will exist for remainder of steel receiving fire-resistive material.

b. If surfaces of structural steel receiving sprayed fire-resistive material are primed or otherwise painted for coating materials, perform series of bond tests specified in UL's "Fire Resistance Directory." Provide bond strength indicated in referenced UL fire-resistance criteria, but not less than 150 lbf/sq. ft. Minimum per ASTM E 736.

c. Minimum thickness of sprayed fire-resistive material tested in laboratory shall be 0.75 inch.

4. Compressive Strength: 5.21 lbf/sq. in. as determined in the laboratory per ASTM E 761. Minimum thickness of sprayed fire-resistive material tested shall be 0.75 inch and minimum dry density shall be as specified, but not less than 15 lb/cu. ft..

5. Corrosion Resistance: No evidence of corrosion per ASTM E 937. 6. Deflection: No cracking, spalling, or delamination per ASTM E 759. 7. Effect of Impact on Bonding: No cracking, spalling, or delamination per ASTM E 760. 8. Air Erosion: Maximum weight loss of 0.025 g/sq. ft. in 24 hours per ASTM E 859. For

laboratory tests, minimum thickness of sprayed fire-resistive material is 0.75 inch, maximum dry density is 15 lb/cu. ft., test specimens are not prepurged by mechanically induced air velocities, and tests are terminated after 24 hours.

9. Fire-Test-Response Characteristics: Provide sprayed fire-resistive materials with the following surface-burning characteristics as determined by testing identical products per ASTM E 84 by UL or another testing and inspecting agency acceptable to authorities having jurisdiction:

a. Flame-Spread Index: 10 or less. b. Smoke-Developed Index: 0.

10. Fungal Resistance: No observed growth on specimens per ASTM G 21. 11. Return Air Plenum: Acceptable for use in plenum space.

2.2 AUXILIARY FIRE-RESISTIVE MATERIALS

A. General: Provide auxiliary fire-resistive materials that are compatible with sprayed fire-resistive materials and substrates and are approved by UL or another testing and inspecting agency acceptable to authorities having jurisdiction for use in fire-resistive designs indicated.

B. Substrate Primers: For use on each substrate and with each sprayed fire-resistive product, provide primer that complies with one or more of the following requirements:

1. Primer's bond strength complies with requirements specified in UL's "Fire Resistance Directory" for coating materials based on a series of bond tests per ASTM E 736.

2. Primer is identical to those used in assemblies tested for fire-test-response characteristics of sprayed fire-resistive material per ASTM E 119 by UL or another testing and inspecting agency acceptable to authorities having jurisdiction.

Page 89: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 APPLIED FIREPROOFING – 078100 7 OF 9

C. Adhesive for Bonding Fire-Resistive Material: Product approved by manufacturer of sprayed fire-resistive material.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, with Installer present, to determine whether they are in satisfactory condition to receive sprayed fire-resistive material. A substrate is in satisfactory condition if it complies with the following:

1. Substrates comply with requirements in the Section where the substrate and related materials and construction are specified.

2. Substrates are free of oil, grease, rolling compounds, incompatible primers, loose mill scale, dirt, or other foreign substances capable of impairing bond of fire-resistive material with substrate under conditions of normal use or fire exposure.

3. Objects penetrating fire-resistive material, including clips, hangers, support sleeves, and similar items, are securely attached to substrates.

4. Substrates are not obstructed by ducts, piping, equipment, and other suspended construction that will interfere with applying fire-resistive material.

B. Conduct tests according to fire-resistive material manufacturer's written recommendations to verify that substrates are free of oil, rolling compounds, and other substances capable of interfering with bond.

C. Do not proceed with installation of fire-resistive material until unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Clean substrates of substances that could impair bond of fire-resistive material, including oil, grease, rolling compounds, incompatible primers, and loose mill scale.

B. Prime substrates where recommended in writing by fire-resistive material manufacturer, unless compatible shop primer has been applied and is in satisfactory condition to receive fire-resistive material.

C. For exposed applications, repair substrates to remove any surface imperfections that could affect uniformity of texture and thickness in finished surface of sprayed fire-resistive material. Remove minor projections and fill voids that would telegraph through fire-resistive products after application.

D. Cover other work subject to damage from fallout or overspray of fire-resistive materials during application. Provide temporary enclosure as required to confine spraying operations, protect the environment, and ensure maintenance of adequate ambient conditions for temperature and ventilation.

Page 90: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 APPLIED FIREPROOFING – 078100 8 OF 9

3.3 INSTALLATION, GENERAL

A. Comply with fire-resistive material manufacturer's written instructions for mixing materials, application procedures, and types of equipment used to convey and spray on fire-resistive material, as applicable to particular conditions of installation and as required to achieve fire-resistance ratings indicated.

B. Apply sprayed fire-resistive material that is identical to products tested as specified in Part 1 in "Product Test Reports" in "Submittals" Article, with respect to rate of application, accelerator use, sealers, topcoats, tamping, troweling, water overspray, or other materials and procedures affecting test results.

C. Where sealers are used, apply products that are tinted to differentiate them from the sprayed fire-resistive material over which they are applied.

3.4 INSTALLATION, CONCEALED SPRAYED FIRE-RESISTIVE MATERIALS

A. Apply concealed sprayed fire-resistive material in thicknesses and densities not less than those required to achieve fire-resistance ratings designated for each condition, but apply in greater thicknesses and densities if specified in Part 2 "Concealed Sprayed Fire-Resistive Materials" Article.

3.5 CLEANING, PROTECTING, AND REPAIR

A. Cleaning: Immediately after completing spraying operations in each containable area of Project, remove material overspray and fallout from surfaces of other construction and clean exposed surfaces to remove evidence of soiling.

B. Cure exposed cementitious sprayed fire-resistive material according to product manufacturer's written recommendations to prevent premature drying.

C. Protect fire-resistive material, according to advice of product manufacturer and Installer, from damage resulting from construction operations or other causes so fire protection will be without damage or deterioration at the time of Substantial Completion.

D. Coordinate application of fire-resistive material with other construction to minimize the need to cut or remove fire protection. As installation of other construction proceeds, inspect fire-resistive material and patch any damaged or removed areas.

E. Repair or replace work that has not been successfully protected.

3.6 FIELD QUALITY CONTROL

A. Testing Agency: Owner will engage a qualified independent testing and inspecting agency to perform field tests and inspections and to prepare test reports.

1. Testing and inspecting agency will interpret tests and state in each report whether tested work complies with or deviates from requirements.

Page 91: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 APPLIED FIREPROOFING – 078100 9 OF 9

B. Testing Services: Testing and inspecting of completed applications of sprayed fire-resistive material shall take place in successive stages, in areas of extent and using methods as follows. Do not proceed with application of sprayed fire-resistive material for the next area until test results for previously completed applications of sprayed fire-resistive material show compliance with requirements. Tested values must equal or exceed values indicated and required for approved fire-resistance design.

1. Thickness for Floor, Roof, and Wall Assemblies: For each 1000-sq. ft. area, or partial area, on each floor, from the average of 4 measurements from a 144-sq. in. sample area, with sample width of not less than 6 inches per ASTM E 605.

2. Thickness for Structural Frame Members: From a sample of 25 percent of structural members per floor, taking 9 measurements at a single cross section for structural frame beams or girders, 7 measurements of a single cross section for joists and trusses, and 12 measurements of a single cross section for columns per ASTM E 605.

3. Density for Floors, Roofs, Walls, and Structural Frame Members: At frequency and from sample size indicated for determining thickness of each type of construction and structural framing member, per ASTM E 605 or AWCI Technical Manual 12-A, Section 5.4.5, "Displacement Method."

4. Bond Strength for Floors, Roofs, Walls, and Structural Framing Members: For each 10,000-sq. ft. area, or partial area, on each floor, cohesion and adhesion from one sample of size indicated for determining thickness of each type of construction and structural framing member, per ASTM E 736.

5. If testing finds applications of sprayed fire-resistive material are not in compliance with requirements, testing and inspecting agency will perform additional random testing to determine extent of noncompliance.

C. Remove and replace applications of sprayed fire-resistive material where test results indicate that it does not comply with specified requirements for cohesion and adhesion, for density, or for both.

D. Apply additional sprayed fire-resistive material per manufacturer's written instructions where test results indicate that thickness does not comply with specified requirements.

E. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements.

END OF SECTION 078100

Page 92: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning
Page 93: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 PENETRATION FIRESTOPPING – 078413 1 OF 8

SECTION 078413 - PENETRATION FIRESTOPPING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Penetrations in fire-resistance-rated walls. 2. Penetrations in horizontal assemblies.

B. Related Sections:

1. Section 078446 "Fire-Resistive Joint Systems" for joints in or between fire-resistance-rated construction, at exterior curtain-wall/floor intersections, and in smoke barriers.

1.3 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

B. Product Schedule: For each penetration firestopping system. Include location and design designation of qualified testing and inspecting agency.

1. Where Project conditions require modification to a qualified testing and inspecting agency's illustration for a particular penetration firestopping condition, submit illustration, with modifications marked, approved by penetration firestopping manufacturer's fire-protection engineer as an engineering judgment or equivalent fire-resistance-rated assembly.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For qualified Installer.

B. Product Test Reports: Based on evaluation of comprehensive tests performed by a qualified testing agency, for penetration firestopping.

Page 94: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 PENETRATION FIRESTOPPING – 078413 2 OF 8

1.6 CLOSEOUT SUBMITTALS

A. Installer Certificates: From Installer indicating that penetration firestopping systems have been installed in compliance with requirements and manufacturer's written instructions.

1.7 QUALITY ASSURANCE

A. Installer Qualifications: A firm experienced in installing penetration firestopping similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful performance. Qualifications include having the necessary experience, staff, and training to install manufacturer's products per specified requirements. Manufacturer's willingness to sell its penetration firestopping products to Contractor or to Installer engaged by Contractor does not in itself confer qualification on buyer.

1.8 PROJECT CONDITIONS

A. Environmental Limitations: Do not install penetration firestopping when ambient or substrate temperatures are outside limits permitted by penetration firestopping manufacturers or when substrates are wet because of rain, frost, condensation, or other causes.

B. Install and cure penetration firestopping per manufacturer's written instructions using natural means of ventilations or, where this is inadequate, forced-air circulation.

1.9 COORDINATION

A. Coordinate construction of openings and penetrating items to ensure that penetration firestopping is installed according to specified requirements.

B. Coordinate sizing of sleeves, openings, core-drilled holes, or cut openings to accommodate penetration firestopping.

C. Notify Owner's testing agency at least seven days in advance of penetration firestopping installations; confirm dates and times on day preceding each series of installations.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Fire-Test-Response Characteristics:

1. Perform penetration firestopping system tests by a qualified testing agency acceptable to authorities having jurisdiction.

Page 95: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 PENETRATION FIRESTOPPING – 078413 3 OF 8

2. Test per testing standards referenced in "Penetration Firestopping Systems" Article. Provide rated systems complying with the following requirements:

a. Penetration firestopping systems shall bear classification marking of a qualified testing agency.

1) UL in its "Fire Resistance Directory."

2.2 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

1. Grace Construction Products. 2. Hilti, Inc. 3. Johns Manville. 4. 3M Fire Protection Products. 5. Specified Technologies, Inc. 6. Tremco, Inc.; Tremco Fire Protection Systems Group. 7. USG Corporation.

2.3 PENETRATION FIRESTOPPING SYSTEMS

A. Provide penetration firestopping that is produced and installed to resist spread of fire according to requirements indicated, resist passage of smoke and other gases, and maintain original fire-resistance rating of construction penetrated. Penetration firestopping systems shall be compatible with one another, with the substrates forming openings, and with penetrating items if any.

B. Penetrations in Fire-Resistance-Rated Walls: Provide penetration firestopping with ratings determined per ASTM E 814 or UL 1479, based on testing at a positive pressure differential of 0.01-inch wg.

1. Fire-resistance-rated walls include smoke-barrier walls and fire rated partitions. 2. F-Rating: Not less than the fire-resistance rating of constructions penetrated.

C. Penetrations in Horizontal Assemblies: Provide penetration firestopping with ratings determined per ASTM E 814 or UL 1479, based on testing at a positive pressure differential of 0.01-inch wg.

1. Horizontal assemblies include floors. 2. F-Rating: At least 1 hour, but not less than the fire-resistance rating of constructions

penetrated. 3. T-Rating: At least 1 hour, but not less than the fire-resistance rating of constructions

penetrated except for floor penetrations within the cavity of a wall.

D. Exposed Penetration Firestopping: Provide products with flame-spread and smoke-developed indexes of less than 25 and 450, respectively, as determined per ASTM E 84.

Page 96: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 PENETRATION FIRESTOPPING – 078413 4 OF 8

E. Accessories: Provide components for each penetration firestopping system that are needed to install fill materials and to maintain ratings required. Use only those components specified by penetration firestopping manufacturer and approved by qualified testing and inspecting agency for firestopping indicated.

1. Permanent forming/damming/backing materials, including the following:

a. Slag-wool-fiber or rock-wool-fiber insulation. b. Sealants used in combination with other forming/damming/backing materials to

prevent leakage of fill materials in liquid state. c. Fillers for sealants.

2. Temporary forming materials. 3. Substrate primers. 4. Collars. 5. Steel sleeves.

2.4 FILL MATERIALS

A. Cast-in-Place Firestop Devices: Factory-assembled devices for use in cast-in-place concrete floors and consisting of an outer metallic sleeve lined with an intumescent strip, a radial extended flange attached to one end of the sleeve for fastening to concrete formwork, and a neoprene gasket.

B. Latex Sealants: Single-component latex formulations that do not re-emulsify after cure during exposure to moisture.

C. Firestop Devices: Factory-assembled collars formed from galvanized steel and lined with intumescent material sized to fit specific diameter of penetrant.

D. Intumescent Putties: Nonhardening dielectric, water-resistant putties containing no solvents, inorganic fibers, or silicone compounds.

E. Intumescent Wrap Strips: Single-component intumescent elastomeric sheets with aluminum foil on one side.

F. Mortars: Prepackaged dry mixes consisting of a blend of inorganic binders, hydraulic cement, fillers, and lightweight aggregate formulated for mixing with water at Project site to form a nonshrinking, homogeneous mortar.

G. Silicone Foams: Multicomponent, silicone-based liquid elastomers that, when mixed, expand and cure in place to produce a flexible, nonshrinking foam.

H. Silicone Sealants: Single-component, silicone-based, neutral-curing elastomeric sealants of grade indicated below:

1. Grade: Pourable (self-leveling) formulation for openings in floors and other horizontal surfaces, and nonsag formulation for openings in vertical and sloped surfaces, unless indicated firestopping limits use of nonsag grade for both opening conditions.

Page 97: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 PENETRATION FIRESTOPPING – 078413 5 OF 8

2.5 MIXING

A. For those products requiring mixing before application, comply with penetration firestopping manufacturer's written instructions for accurate proportioning of materials, water (if required), type of mixing equipment, selection of mixer speeds, mixing containers, mixing time, and other items or procedures needed to produce products of uniform quality with optimum performance characteristics for application indicated.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates and conditions, with Installer present, for compliance with requirements for opening configurations, penetrating items, substrates, and other conditions affecting performance of the Work.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Surface Cleaning: Clean out openings immediately before installing penetration firestopping to comply with manufacturer's written instructions and with the following requirements:

1. Remove from surfaces of opening substrates and from penetrating items foreign materials that could interfere with adhesion of penetration firestopping.

2. Clean opening substrates and penetrating items to produce clean, sound surfaces capable of developing optimum bond with penetration firestopping. Remove loose particles remaining from cleaning operation.

3. Remove laitance and form-release agents from concrete.

B. Priming: Prime substrates where recommended in writing by manufacturer using that manufacturer's recommended products and methods. Confine primers to areas of bond; do not allow spillage and migration onto exposed surfaces.

C. Masking Tape: Use masking tape to prevent penetration firestopping from contacting adjoining surfaces that will remain exposed on completion of the Work and that would otherwise be permanently stained or damaged by such contact or by cleaning methods used to remove stains. Remove tape as soon as possible without disturbing firestopping's seal with substrates.

3.3 INSTALLATION

A. General: Install penetration firestopping to comply with manufacturer's written installation instructions and published drawings for products and applications indicated.

Page 98: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 PENETRATION FIRESTOPPING – 078413 6 OF 8

B. Install forming materials and other accessories of types required to support fill materials during their application and in the position needed to produce cross-sectional shapes and depths required to achieve fire ratings indicated.

1. After installing fill materials and allowing them to fully cure, remove combustible forming materials and other accessories not indicated as permanent components of firestopping.

C. Install fill materials for firestopping by proven techniques to produce the following results:

1. Fill voids and cavities formed by openings, forming materials, accessories, and penetrating items as required to achieve fire-resistance ratings indicated.

2. Apply materials so they contact and adhere to substrates formed by openings and penetrating items.

3. For fill materials that will remain exposed after completing the Work, finish to produce smooth, uniform surfaces that are flush with adjoining finishes.

3.4 IDENTIFICATION

A. Wall Identification: Permanently label walls containing penetration firestopping systems with the words "FIRE AND/OR SMOKE BARRIER - PROTECT ALL OPENINGS," using lettering not less than 3 inches (76 mm) high and with minimum 0.375-inch (9.5-mm) strokes.

1. Locate in accessible concealed floor, floor-ceiling, or attic space at 15 feet (4.57 m) from end of wall and at intervals not exceeding 30 feet (9.14 m).

B. Penetration Identification: Identify each penetration firestopping system with legible metal or plastic labels. Attach labels permanently to surfaces adjacent to and within 6 inches (150 mm) of penetration firestopping system edge so labels are visible to anyone seeking to remove penetrating items or firestopping systems. Use mechanical fasteners or self-adhering-type labels with adhesives capable of permanently bonding labels to surfaces on which labels are placed. Include the following information on labels:

1. The words "Warning - Penetration Firestopping - Do Not Disturb. Notify Building Management of Any Damage."

2. Contractor's name, address, and phone number. 3. Designation of applicable testing and inspecting agency. 4. Date of installation. 5. Manufacturer's name. 6. Installer's name.

3.5 FIELD QUALITY CONTROL

A. Where deficiencies are found or penetration firestopping is damaged or removed because of testing, repair or replace penetration firestopping to comply with requirements.

B. Proceed with enclosing penetration firestopping with other construction only after inspection reports are issued and installations comply with requirements.

Page 99: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 PENETRATION FIRESTOPPING – 078413 7 OF 8

3.6 CLEANING AND PROTECTION

A. Clean off excess fill materials adjacent to openings as the Work progresses by methods and with cleaning materials that are approved in writing by penetration firestopping manufacturers and that do not damage materials in which openings occur.

B. Provide final protection and maintain conditions during and after installation that ensure that penetration firestopping is without damage or deterioration at time of Substantial Completion. If, despite such protection, damage or deterioration occurs, immediately cut out and remove damaged or deteriorated penetration firestopping and install new materials to produce systems complying with specified requirements.

3.7 PENETRATION FIRESTOPPING SCHEDULE

A. Where UL-classified systems are indicated, they refer to system numbers in UL's "Fire Resistance Directory" under product Category XHEZ.

B. Firestopping with No Penetrating Items FS-1:

1. UL-Classified Systems: C-AJ-0011, all applications. 2. F-Rating: 2 hours for all applications. 3. T-Rating: 2 hours for all applications. 4. Type of Fill Materials: As required to achieve rating.

C. Firestopping for Metallic Pipes, Conduit, or Tubing FS-2:

1. UL-Classified Systems: C-AJ-1088, Concrete. WL-1166, Gypsum Board. 2. F-Rating: 2 hours for all applications. 3. T-Rating: 0 hours for all applications. 4. Type of Fill Materials: As required to achieve rating.

D. Firestopping for Nonmetallic Pipe, Conduit, or Tubing FS-3:

1. UL-Classified Systems: C-AJ-2171, Concrete. WL2166, Gypsum Board. 2. F-Rating: 2 hours for all applications. 3. T-Rating: 0 hours for all applications. 4. Type of Fill Materials: As required to achieve rating.

E. Firestopping for Electrical Cables FS-4:

1. UL-Classified Systems: C-AJ-3236, Concrete. WL-3198 Gypsum Board. 2. F-Rating: 2 hours for all applications. 3. T-Rating: 0 hour for C-AJ-3236 and 1 hour for WL-3198. 4. Type of Fill Materials: As required to achieve rating.

F. Firestopping for Insulated Pipes FS-5:

1. UL-Classified Systems: C-AJ-5116, Concrete. WL-5087-Gypsum Board 2. F-Rating: 2 hours for all applications. 3. T-Rating: 3/4 hour. 4. Type of Fill Materials: As required to achieve rating.

Page 100: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 PENETRATION FIRESTOPPING – 078413 8 OF 8

G. Firestopping for Miscellaneous Electrical Penetrants FS-6:

1. UL-Classified Systems: C-AJ-6012, Concrete. R-11636-M, Gypsum Board 2. F-Rating: 2 hours for all applications. 3. T-Rating: 0 hour. 4. Type of Fill Materials: As required to achieve rating.

H. Firestopping for Miscellaneous Mechanical Penetrants FS-7:

1. UL-Classified Systems: C-AJ-7008, Concrete. WL-7006, Gypsum Board 2. F-Rating: 2 hours for all applications. 3. T-Rating: 1/2 hour for C-AJ-7008 and 1 hour WL-7006. 4. Type of Fill Materials: As required to achieve rating

I. Firestopping for Groupings of Penetrants FS-8:

1. UL-Classified Systems: C-AJ-8012, Concrete. WL-8007, Gypsum Board 2. F-Rating: 2 hours for all applications. 3. T-Rating: 0 hours for all applications. 4. Type of Fill Materials: As required to achieve rating.

END OF SECTION 078413

Page 101: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 FIRE-RESISTIVE JOINT SYSTEMS – 078446 1 OF 6

SECTION 078446 - FIRE-RESISTIVE JOINT SYSTEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Joints in or between fire-resistance-rated constructions. 2. Joints at exterior curtain-wall/floor intersections.

B. Related Sections:

1. Section 078413 "Penetration Firestopping" for penetrations in fire-resistance-rated walls, horizontal assemblies, and smoke barriers.

2. Section 092216 "Non-Structural Metal Framing" for firestop tracks for metal-framed partition heads.

1.3 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

B. Product Schedule: For each joint firestopping system. Include location, illustration of firestopping system, and design designation of qualified testing agency.

1. Engineering Judgments: Where Project conditions require modification to a qualified testing agency's illustration for a particular joint firestopping system condition, submit illustration, with modifications marked, approved by joint firestopping system manufacturer's fire-protection engineer as an engineering judgment or equivalent fire-resistance-rated assembly.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For qualified Installer.

Page 102: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 FIRE-RESISTIVE JOINT SYSTEMS – 078446 2 OF 6

B. Product Test Reports: Based on evaluation of comprehensive tests performed by a qualified testing agency, for fire-resistive joint systems.

1.6 CLOSEOUT SUBMITTALS

A. Installer Certificates: From Installer indicating that joint firestopping systems have been installed in compliance with requirements and manufacturer's written instructions.

1.7 QUALITY ASSURANCE

A. Installer Qualifications: A firm experienced in installing fire-resistive joint systems similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful performance. Qualifications include having the necessary experience, staff, and training to install manufacturer's products per specified requirements. Manufacturer's willingness to sell its fire-resistive joint system products to Contractor or to Installer engaged by Contractor does not in itself confer qualification on buyer.

1.8 PROJECT CONDITIONS

A. Environmental Limitations: Do not install fire-resistive joint systems when ambient or substrate temperatures are outside limits permitted by fire-resistive joint system manufacturers or when substrates are wet due to rain, frost, condensation, or other causes.

B. Install and cure fire-resistive joint systems per manufacturer's written instructions using natural means of ventilation or, where this is inadequate, forced-air circulation.

1.9 COORDINATION

A. Coordinate construction of joints to ensure that fire-resistive joint systems are installed according to specified requirements.

B. Coordinate sizing of joints to accommodate fire-resistive joint systems.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Fire-Test-Response Characteristics:

1. Perform joint firestopping system tests by a qualified testing agency acceptable to authorities having jurisdiction.

Page 103: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 FIRE-RESISTIVE JOINT SYSTEMS – 078446 3 OF 6

2. Test per testing standards referenced in "Joint Firestopping Systems" Article. Provide rated systems complying with the following requirements:

a. Joint firestopping systems shall bear classification marking of a qualified testing agency.

1) UL in its "Fire Resistance Directory."

2.2 FIRE-RESISTIVE JOINT SYSTEMS

A. Where required, provide fire-resistive joint systems that are produced and installed to resist spread of fire according to requirements indicated, resist passage of smoke and other gases, and maintain original fire-resistance rating of assemblies in or between which fire-resistive joint systems are installed. Fire-resistive joint systems shall accommodate building movements without impairing their ability to resist the passage of fire and hot gases.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. Fire Trak Corp. b. Grace Construction Products. c. Hilti, Inc. d. Johns Manville. e. 3M Fire Protection Products. f. Specified Technologies, Inc. g. Tremco, Inc.; Tremco Fire Protection Systems Group. h. USG Corporation.

B. Joints in or between Fire-Resistance-Rated Construction: Provide joint firestopping systems with ratings determined per ASTM E 1966 or UL 2079.

1. Fire-Resistance Rating: Equal to or exceeding the fire-resistance rating of the wall, floor, or roof in or between which it is installed.

C. Joints at Exterior Curtain-Wall/Floor Intersections: Provide joint firestopping systems with rating determined per ASTM E 2307.

1. F-Rating: Equal to or exceeding the fire-resistance rating of the floor assembly. 2. Provide smoke seals.

D. Exposed Fire-Resistive Joint Systems: Provide products with flame-spread and smoke-developed indexes of less than 25 and 450, respectively, as determined per ASTM E 84.

E. Accessories: Provide components of fire-resistive joint systems, including primers and forming materials, that are needed to install fill materials and to maintain ratings required. Use only components specified by fire-resistive joint system manufacturer and approved by the qualified testing agency for systems indicated.

Page 104: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 FIRE-RESISTIVE JOINT SYSTEMS – 078446 4 OF 6

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates and conditions, with Installer present, for compliance with requirements for joint configurations, substrates, and other conditions affecting performance of the Work.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Surface Cleaning: Clean joints immediately before installing fire-resistive joint systems to comply with fire-resistive joint system manufacturer's written instructions and the following requirements:

1. Remove from surfaces of joint substrates foreign materials that could interfere with adhesion of fill materials.

2. Clean joint substrates to produce clean, sound surfaces capable of developing optimum bond with fill materials. Remove loose particles remaining from cleaning operation.

3. Remove laitance and form-release agents from concrete.

B. Priming: Prime substrates where recommended in writing by fire-resistive joint system manufacturer using that manufacturer's recommended products and methods. Confine primers to areas of bond; do not allow spillage and migration onto exposed surfaces.

C. Masking Tape: Use masking tape to prevent fill materials of fire-resistive joint system from contacting adjoining surfaces that will remain exposed on completion of the Work and that would otherwise be permanently stained or damaged by such contact or by cleaning methods used to remove stains. Remove tape as soon as possible without disturbing fire-resistive joint system's seal with substrates.

3.3 INSTALLATION

A. General: Install fire-resistive joint systems to comply with manufacturer's written installation instructions and published drawings for products and applications indicated.

B. Install forming materials and other accessories of types required to support fill materials during their application and in position needed to produce cross-sectional shapes and depths required to achieve fire ratings indicated.

1. After installing fill materials and allowing them to fully cure, remove combustible forming materials and other accessories not indicated as permanent components of fire-resistive joint system.

Page 105: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 FIRE-RESISTIVE JOINT SYSTEMS – 078446 5 OF 6

C. Install fill materials for fire-resistive joint systems by proven techniques to produce the following results:

1. Fill voids and cavities formed by joints and forming materials as required to achieve fire-resistance ratings indicated.

2. Apply fill materials so they contact and adhere to substrates formed by joints. 3. For fill materials that will remain exposed after completing the Work, finish to produce

smooth, uniform surfaces that are flush with adjoining finishes.

3.4 IDENTIFICATION

A. Identify fire-resistive joint systems with preprinted metal or plastic labels. Attach labels permanently to surfaces adjacent to and within 6 inches of joint edge so labels will be visible to anyone seeking to remove or penetrate joint system. Use mechanical fasteners or self-adhering-type labels with adhesives capable of permanently bonding labels to surfaces on which labels are placed. Include the following information on labels:

1. The words "Warning - Fire-Resistive Joint System - Do Not Disturb. Notify Building Management of Any Damage."

2. Contractor's name, address, and phone number. 3. Designation of applicable testing agency. 4. Date of installation. 5. Manufacturer's name. 6. Installer's name.

3.5 FIELD QUALITY CONTROL

A. Inspecting Agency: Owner will engage a qualified testing agency to perform tests and inspections according to ASTM E 2393 .

B. Where deficiencies are found or fire-resistive joint systems are damaged or removed due to testing, repair or replace fire-resistive joint systems so they comply with requirements.

C. Proceed with enclosing fire-resistive joint systems with other construction only after inspection reports are issued and installations comply with requirements.

3.6 CLEANING AND PROTECTING

A. Clean off excess fill materials adjacent to joints as the Work progresses by methods and with cleaning materials that are approved in writing by fire-resistive joint system manufacturers and that do not damage materials in which joints occur.

Page 106: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 FIRE-RESISTIVE JOINT SYSTEMS – 078446 6 OF 6

B. Provide final protection and maintain conditions during and after installation that ensure fire-resistive joint systems are without damage or deterioration at time of Substantial Completion. If damage or deterioration occurs despite such protection, cut out and remove damaged or deteriorated fire-resistive joint systems immediately and install new materials to produce fire-resistive joint systems complying with specified requirements.

3.7 FIRE-RESISTIVE JOINT SYSTEM SCHEDULE

A. Where UL-classified systems are indicated, they refer to system numbers in UL's "Fire Resistance Directory" under product Category XHBN or Category XHDG.

B. Wall-to-Wall, Fire-Resistive Joint Systems FRJS-1:

1. UL-Classified Systems: WW-D-0040. 2. Assembly Rating: 1 and 2 hours. 3. Nominal Joint Width: ¾ inch. 4. Movement Capabilities: Class II - 17 percent compression or extension.

C. Head-of-Wall, Fire-Resistive Joint Systems FRJS-2:

1. UL-Classified Systems: HW-D-0091. 2. Assembly Rating: 1 and 2 hours. 3. Nominal Joint Width: 1 inch maximum. 4. Movement Capabilities: Class II and Class III – 25 percent compression or extension.

D. Bottom-of-Wall, Fire-Resistive Joint Systems FRJS-3:

1. UL-Classified Systems: BW-S-0001. 2. Assembly Rating: 1 and 2 hours. 3. Nominal Joint Width: ¾ inch maximum. 4. L-Rating at Ambient: Less than 1 cfm/lf. 5. L-Rating at 400 deg F: Less than 1 cfm/lf.

END OF SECTION 078446

Page 107: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 JOINT SEALANTS – 079200 1 OF 10

SECTION 079200 - JOINT SEALANTS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Silicone joint sealants. 2. Urethane joint sealants. 3. Latex joint sealants. 4. Solvent-release-curing joint sealants. 5. Acoustical joint sealants.

B. Related Sections:

1. Section 042200 "Concrete Unit Masonry" for masonry control and expansion joint fillers and gaskets.

2. Section 078446 "Fire-Resistive Joint Systems" for sealing joints in fire-resistance-rated construction.

3. Section 088000 "Glazing" for glazing sealants. 4. Section 092900 “Gypsum Board” for sealing perimeter joints. 5. Section 093000 "Tiling" for sealing tile joints.

1.3 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.4 ACTION SUBMITTALS

A. Product Data: For each joint-sealant product indicated.

B. Samples for Initial Selection: Manufacturer's color charts consisting of strips of cured sealants showing the full range of colors available for each product exposed to view.

C. Samples for Verification: For each kind and color of joint sealant required, provide Samples with joint sealants in 1/2-inch wide joints formed between two 6-inch long strips of material matching the appearance of exposed surfaces adjacent to joint sealants.

Page 108: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 JOINT SEALANTS – 079200 2 OF 10

D. Joint-Sealant Schedule: Include the following information:

1. Joint-sealant application, joint location, and designation. 2. Joint-sealant manufacturer and product name. 3. Joint-sealant formulation. 4. Joint-sealant color.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For qualified Installer.

B. Product Test Reports: For each kind of joint sealant, for tests performed by manufacturer and witnessed by a qualified testing agency.

C. Preconstruction Laboratory Test Schedule: Include the following information for each joint sealant and substrate material to be tested:

1. Joint-sealant location and designation. 2. Manufacturer and product name. 3. Type of substrate material. 4. Proposed test. 5. Number of samples required.

D. Preconstruction Laboratory Test Reports: From sealant manufacturer, indicating the following:

1. Materials forming joint substrates and joint-sealant backings have been tested for compatibility and adhesion with joint sealants.

2. Interpretation of test results and written recommendations for primers and substrate preparation are needed for adhesion.

E. Preconstruction Field-Adhesion-Test Reports: Indicate which sealants and joint preparation methods resulted in optimum adhesion to joint substrates based on testing specified in "Preconstruction Testing" Article.

F. Product Certificates: For each kind of joint sealant and accessory, from manufacturer.

G. Warranties: Sample of special warranties.

1.6 QUALITY ASSURANCE

A. Installer Qualifications: Manufacturer's authorized representative who is trained and approved for installation of units required for this Project.

B. Product Testing: Test joint sealants using a qualified testing agency.

1. Testing Agency Qualifications: Qualified according to ASTM C 1021 to conduct the testing indicated.

Page 109: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 JOINT SEALANTS – 079200 3 OF 10

C. Mockups: Install sealant in mockups of assemblies specified in other Sections that are indicated to receive joint sealants specified in this Section. Use materials and installation methods specified in this Section.

D. Source Limitations: Obtain each kind of joint sealant from single source from single manufacturer.

1.7 PRECONSTRUCTION TESTING

A. Preconstruction Field-Adhesion Testing: Before installing sealants, field test their adhesion to Project joint substrates as follows:

1. Locate test joints where indicated on Project or, if not indicated, as directed by Architect. 2. Conduct field tests for each kind of sealant and joint substrate. 3. Notify Architect seven days in advance of dates and times when test joints will be

erected. 4. Arrange for tests to take place with joint-sealant manufacturer's technical representative

present.

a. Test Method: Test joint sealants according to Method A, Field-Applied Sealant Joint Hand Pull Tab, in Appendix X1.1 in ASTM C 1193 or Method A, Tail Procedure, in ASTM C 1521.

1) For joints with dissimilar substrates, verify adhesion to each substrate separately; extend cut along one side, verifying adhesion to opposite side. Repeat procedure for opposite side.

5. Report whether sealant failed to adhere to joint substrates or tore cohesively. Include data on pull distance used to test each kind of product and joint substrate. For sealants that fail adhesively, retest until satisfactory adhesion is obtained.

6. Evaluation of Preconstruction Field-Adhesion-Test Results: Sealants not evidencing adhesive failure from testing, in absence of other indications of noncompliance with requirements, will be considered satisfactory. Do not use sealants that fail to adhere to joint substrates during testing.

1.8 FIELD CONDITIONS

A. Do not proceed with installation of joint sealants under the following conditions:

1. When ambient and substrate temperature conditions are outside limits permitted by joint-sealant manufacturer or are below 40 deg F.

2. When joint substrates are wet. 3. Where joint widths are less than those allowed by joint-sealant manufacturer for

applications indicated. 4. Where contaminants capable of interfering with adhesion have not yet been removed

from joint substrates.

Page 110: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 JOINT SEALANTS – 079200 4 OF 10

1.9 WARRANTY

A. Special Installer's Warranty: Manufacturer's standard form in which Installer agrees to repair or replace joint sealants that do not comply with performance and other requirements specified in this Section within specified warranty period.

1. Warranty Period: Two years from date of Substantial Completion.

B. Special Manufacturer's Warranty: Manufacturer's standard form in which joint-sealant manufacturer agrees to furnish joint sealants to repair or replace those that do not comply with performance and other requirements specified in this Section within specified warranty period.

1. Warranty Period: Five years from date of Substantial Completion.

C. Special warranties specified in this article exclude deterioration or failure of joint sealants from the following:

1. Movement of the structure caused by structural settlement or errors attributable to design or construction resulting in stresses on the sealant exceeding sealant manufacturer's written specifications for sealant elongation and compression.

2. Disintegration of joint substrates from natural causes exceeding design specifications. 3. Mechanical damage caused by individuals, tools, or other outside agents. 4. Changes in sealant appearance caused by accumulation of dirt or other atmospheric

contaminants.

PART 2 - PRODUCTS

2.1 MATERIALS, GENERAL

A. Compatibility: Provide joint sealants, backings, and other related materials that are compatible with one another and with joint substrates under conditions of service and application, as demonstrated by joint-sealant manufacturer, based on testing and field experience.

B. Colors of Exposed Joint Sealants: As selected by Architect from manufacturer's full range.

2.2 SILICONE JOINT SEALANTS

A. Mildew-Resistant, Single-Component, Acid-Curing Silicone Joint Sealant: ASTM C 920, Type S, Grade NS, Class 25, for Use NT.

1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

a. BASF Building Systems; Omniplus. b. Dow Corning Corporation; 786 Mildew Resistant. c. May National Associates, Inc.; Bondaflex Sil 100 WF. d. Tremco Incorporated; Tremsil 200 Sanitary.

Page 111: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 JOINT SEALANTS – 079200 5 OF 10

2.3 URETHANE JOINT SEALANTS

A. Single-Component, Nonsag, Traffic-Grade, Urethane Joint Sealant: ASTM C 920. Type S, Grade NS, Class 25, for Use T.

1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

a. BASF Building Systems; Sonolastic NP1. b. May National Associates, Inc.; Bondaflex PUR 40 FC. c. Pacific Polymers International, Inc.; Elasto-Thane 230 Type II. d. Tremco Incorporated; Vulkem 116.

2.4 LATEX JOINT SEALANTS

A. Latex Joint Sealant: Acrylic latex or siliconized acrylic latex, ASTM C 834, Type OP, Grade NF.

1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

a. BASF Building Systems; Sonolac. b. Bostik, Inc.; Chem-Calk 600. c. Tremco Incorporated; Tremflex 834.

2.5 ACOUSTICAL JOINT SEALANTS

A. Acoustical Joint Sealant: Manufacturer's standard nonsag, paintable, nonstaining latex sealant complying with ASTM C 834. Product effectively reduces airborne sound transmission through perimeter joints and openings in building construction as demonstrated by testing representative assemblies according to ASTM E 90.

1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

a. Pecora Corporation; AC-20 FTR and AIS-919. b. USG Corporation; SHEETROCK Acoustical Sealant.

2.6 JOINT SEALANT BACKING

A. General: Provide sealant backings of material that are nonstaining; are compatible with joint substrates, sealants, primers, and other joint fillers; and are approved for applications indicated by sealant manufacturer based on field experience and laboratory testing.

B. Cylindrical Sealant Backings: ASTM C 1330, Type C (closed-cell material with a surface skin), and of size and density to control sealant depth and otherwise contribute to producing optimum sealant performance.

Page 112: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 JOINT SEALANTS – 079200 6 OF 10

C. Bond-Breaker Tape: Polyethylene tape or other plastic tape recommended by sealant manufacturer for preventing sealant from adhering to rigid, inflexible joint-filler materials or joint surfaces at back of joint. Provide self-adhesive tape where applicable.

2.7 MISCELLANEOUS MATERIALS

A. Primer: Material recommended by joint-sealant manufacturer where required for adhesion of sealant to joint substrates indicated, as determined from preconstruction joint-sealant-substrate tests and field tests.

B. Cleaners for Nonporous Surfaces: Chemical cleaners acceptable to manufacturers of sealants and sealant backing materials, free of oily residues or other substances capable of staining or harming joint substrates and adjacent nonporous surfaces in any way, and formulated to promote optimum adhesion of sealants to joint substrates.

C. Masking Tape: Nonstaining, nonabsorbent material compatible with joint sealants and surfaces adjacent to joints.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine joints indicated to receive joint sealants, with Installer present, for compliance with requirements for joint configuration, installation tolerances, and other conditions affecting joint-sealant performance.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply with joint-sealant manufacturer's written instructions and the following requirements:

1. Remove all foreign material from joint substrates that could interfere with adhesion of joint sealant, including dust, paints (except for permanent, protective coatings tested and approved for sealant adhesion and compatibility by sealant manufacturer), old joint sealants, oil, grease, waterproofing, water repellents, water, surface dirt, and frost.

2. Clean porous joint substrate surfaces by brushing, grinding, mechanical abrading, or a combination of these methods to produce a clean, sound substrate capable of developing optimum bond with joint sealants. Remove loose particles remaining after cleaning operations above by vacuuming or blowing out joints with oil-free compressed air. Porous joint substrates include the following:

a. Concrete. b. Masonry. c. Unglazed surfaces of ceramic tile.

3. Remove laitance and form-release agents from concrete.

Page 113: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 JOINT SEALANTS – 079200 7 OF 10

4. Clean nonporous joint substrate surfaces with chemical cleaners or other means that do not stain, harm substrates, or leave residues capable of interfering with adhesion of joint sealants. Nonporous joint substrates include the following:

a. Metal. b. Glass. c. Glazed surfaces of ceramic tile.

B. Joint Priming: Prime joint substrates where recommended by joint-sealant manufacturer or as indicated by preconstruction joint-sealant-substrate tests or prior experience. Apply primer to comply with joint-sealant manufacturer's written instructions. Confine primers to areas of joint-sealant bond; do not allow spillage or migration onto adjoining surfaces.

C. Masking Tape: Use masking tape where required to prevent contact of sealant or primer with adjoining surfaces that otherwise would be permanently stained or damaged by such contact or by cleaning methods required to remove sealant smears. Remove tape immediately after tooling without disturbing joint seal.

3.3 INSTALLATION OF JOINT SEALANTS

A. General: Comply with joint-sealant manufacturer's written installation instructions for products and applications indicated, unless more stringent requirements apply.

B. Sealant Installation Standard: Comply with recommendations in ASTM C 1193 for use of joint sealants as applicable to materials, applications, and conditions indicated.

C. Install sealant backings of kind indicated to support sealants during application and at position required to produce cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability.

1. Do not leave gaps between ends of sealant backings. 2. Do not stretch, twist, puncture, or tear sealant backings. 3. Remove absorbent sealant backings that have become wet before sealant application and

replace them with dry materials.

D. Install bond-breaker tape behind sealants where sealant backings are not used between sealants and backs of joints.

E. Install sealants using proven techniques that comply with the following and at the same time backings are installed:

1. Place sealants so they directly contact and fully wet joint substrates. 2. Completely fill recesses in each joint configuration. 3. Produce uniform, cross-sectional shapes and depths relative to joint widths that allow

optimum sealant movement capability.

Page 114: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 JOINT SEALANTS – 079200 8 OF 10

F. Tooling of Nonsag Sealants: Immediately after sealant application and before skinning or curing begins, tool sealants according to requirements specified in subparagraphs below to form smooth, uniform beads of configuration indicated; to eliminate air pockets; and to ensure contact and adhesion of sealant with sides of joint.

1. Remove excess sealant from surfaces adjacent to joints. 2. Use tooling agents that are approved in writing by sealant manufacturer and that do not

discolor sealants or adjacent surfaces. 3. Provide concave joint profile per Figure 8A in ASTM C 1193, unless otherwise

indicated.

G. Acoustical Sealant Installation: At sound-rated assemblies and elsewhere as indicated, seal construction at perimeters, behind control joints, and at openings and penetrations with a continuous bead of acoustical sealant. Install acoustical sealant at both faces of partitions at perimeters and through penetrations. Comply with ASTM C 919 and with manufacturer's written recommendations.

3.4 FIELD QUALITY CONTROL

A. Field-Adhesion Testing: Field test joint-sealant adhesion to joint substrates as follows:

1. Extent of Testing: Test completed and cured sealant joints as follows:

a. Perform 10 tests for the first 1000 feet of joint length for each kind of sealant and joint substrate.

b. Perform one test for each 1000 feet of joint length thereafter or one test per each floor per elevation.

2. Test Method: Test joint sealants according to Method A, Field-Applied Sealant Joint Hand Pull Tab, in Appendix X1 in ASTM C 1193 or Method A, Tail Procedure, in ASTM C 1521.

a. For joints with dissimilar substrates, verify adhesion to each substrate separately; extend cut along one side, verifying adhesion to opposite side. Repeat procedure for opposite side.

3. Inspect tested joints and report on the following:

a. Whether sealants filled joint cavities and are free of voids. b. Whether sealant dimensions and configurations comply with specified

requirements. c. Whether sealants in joints connected to pulled-out portion failed to adhere to joint

substrates or tore cohesively. Include data on pull distance used to test each kind of product and joint substrate. Compare these results to determine if adhesion complies with sealant manufacturer's field-adhesion hand-pull test criteria.

Page 115: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 JOINT SEALANTS – 079200 9 OF 10

4. Record test results in a field-adhesion-test log. Include dates when sealants were installed, names of persons who installed sealants, test dates, test locations, whether joints were primed, adhesion results and percent elongations, sealant material, sealant configuration, and sealant dimensions.

5. Repair sealants pulled from test area by applying new sealants following same procedures used originally to seal joints. Ensure that original sealant surfaces are clean and that new sealant contacts original sealant.

B. Evaluation of Field-Adhesion-Test Results: Sealants not evidencing adhesive failure from testing or noncompliance with other indicated requirements will be considered satisfactory. Remove sealants that fail to adhere to joint substrates during testing or to comply with other requirements. Retest failed applications until test results prove sealants comply with indicated requirements.

3.5 CLEANING

A. Clean off excess sealant or sealant smears adjacent to joints as the Work progresses by methods and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which joints occur.

3.6 PROTECTION

A. Protect joint sealants during and after curing period from contact with contaminating substances and from damage resulting from construction operations or other causes so sealants are without deterioration or damage at time of Substantial Completion. If, despite such protection, damage or deterioration occurs, cut out and remove damaged or deteriorated joint sealants immediately so installations with repaired areas are indistinguishable from original work.

3.7 JOINT-SEALANT SCHEDULE

A. Joint-Sealant Application: Exterior joints in horizontal traffic surfaces.

1. Joint Locations:

a. Control and expansion joints in brick pavers. b. Isolation and contraction joints in cast-in-place concrete slabs. c. Tile control and expansion joints. d. Joints between different materials listed above.

2. Urethane Joint Sealant: Single component, nonsag, traffic grade. 3. Joint-Sealant Color: As selected by Architect from manufacturer's full range of colors.

B. Joint-Sealant Application: Exterior joints in vertical surfaces and horizontal nontraffic surfaces.

1. Joint Locations:

a. Construction joints in cast-in-place concrete. b. Joints between cast stone units. c. Control and expansion joints in unit masonry.

Page 116: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 JOINT SEALANTS – 079200 10 OF 10

d. Joints between different materials listed above. e. Perimeter joints between materials listed above and frames of doors, windows, and

louvers.

2. Joint Sealant: Silicone, nonstaining, nonsag, Class 50. 3. Joint-Sealant Color: As approved by Architect from custom colors to match adjacent

material appearance. 4. Joint-Sealant Texture: As approved by Architect from custom textures to match adjacent

material appearance.

C. Joint-Sealant Application: Interior joints in vertical surfaces and horizontal nontraffic surfaces.

1. Joint Locations:

a. Control and expansion joints on exposed interior surfaces of exterior walls. b. Perimeter joints of exterior openings where indicated. c. Vertical joints on exposed surfaces of interior unit masonry and concrete. d. Perimeter joints between interior wall surfaces and frames of interior doors,

windows and elevator entrances.

2. Joint Sealant: Latex, Acrylic based. 3. Joint-Sealant Color: As selected by Architect from manufacturer's full range of colors.

D. Joint-Sealant Application: Mildew-resistant interior joints in vertical surfaces and horizontal nontraffic surfaces.

1. Joint Sealant Location:

a. Joints between plumbing fixtures and adjoining walls, floors, and counters.

2. Joint Sealant: Mildew resistant, single component, nonsag, neutral curing, Silicone. 3. Joint-Sealant Color: Match As selected by Architect from manufacturer's full range of

colors.

E. Joint-Sealant Application: Interior acoustical joints in vertical surfaces and horizontal nontraffic surfaces.

1. Joint Location:

a. Acoustical joints where indicated.

2. Joint Sealant: Acoustical. 3. Joint-Sealant Color: As selected by Architect from manufacturer's full range.

END OF SECTION 079200

Page 117: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 EXPANSION CONTROL – 079500 1 OF 8

SECTION 079500 - EXPANSION CONTROL

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Interior expansion control systems. 2. Exterior wall expansion control systems.

B. Related Requirements:

1. Section 074113 “Standing Seam Metal Roof Panels” for flashing and integration into metal roofing.

2. Section 078446 "Fire-Resistive Joint Systems" for liquid-applied joint sealants in fire-resistive building joints.

3. Section 079200 "Joint Sealants" for liquid-applied joint sealants and for elastomeric sealants without metal frames.

1.3 ACTION SUBMITTALS

A. Shop Drawings: For each expansion control system specified. Include plans, elevations, sections, details, splices, blockout requirement, attachments to other work, and line diagrams showing entire route of each expansion control system. Where expansion control systems change planes, provide isometric or clearly detailed drawing depicting how components interconnect.

B. Samples: For each exposed expansion control system and for each color and texture specified, full width by 6 inches long in size.

C. Samples for Initial Selection: For each type of expansion control system indicated.

1. Include manufacturer's color charts showing the full range of colors and finishes available for each exposed metal and elastomeric seal material.

D. Product Schedule: Prepared by or under the supervision of the supplier. Include the following information in tabular form:

1. Manufacturer and model number for each expansion control system. 2. Expansion control system location cross-referenced to Drawings.

Page 118: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 EXPANSION CONTROL – 079500 2 OF 8

3. Nominal joint width. 4. Movement capability. 5. Classification as thermal or seismic. 6. Materials, colors, and finishes. 7. Product options. 8. Fire-resistance ratings.

1.4 INFORMATIONAL SUBMITTALS

A. Product Test Reports: For each fire barrier provided as part of an expansion control system, for tests performed by a qualified testing agency.

1.5 QUALITY ASSURANCE

A. Mockups: Build mockups to demonstrate aesthetic effects and to set quality standards for materials and execution.

1. Build mockup of typical expansion joint cover assembly as shown on Drawings. 2. Approval of mockups does not constitute approval of deviations from the Contract

Documents contained in mockups unless Architect specifically approves such deviations in writing.

3. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

PART 2 - PRODUCTS

2.1 SYSTEM DESCRIPTION

A. General: Provide expansion control systems of design, basic profile, materials, and operation indicated. Provide units with capability to accommodate variations in adjacent surfaces.

1. Furnish units in longest practicable lengths to minimize field splicing. Install with hairline mitered corners where expansion control systems change direction or abut other materials.

2. Include factory-fabricated closure materials and transition pieces, T-joints, corners, curbs, cross-connections, and other accessories as required to provide continuous expansion control systems.

B. Coordination: Coordinate installation of exterior wall and soffit expansion control systems with roof expansion control systems to ensure that wall transitions are watertight. Roof expansion joint assemblies are specified elsewhere.

2.2 PERFORMANCE REQUIREMENTS

A. Seismic Performance: Expansion joint cover assemblies shall withstand the effects of earthquake motions determined according to ASCE/SEI 7.

Page 119: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 EXPANSION CONTROL – 079500 3 OF 8

B. Fire-Resistance Ratings: Where indicated, provide expansion control systems with fire barriers identical to those of systems tested for fire resistance per UL 2079 or ASTM E 1966 by a testing and inspecting agency acceptable to authorities having jurisdiction.

C. Hose Stream Test: Wall-to-wall and wall-to-ceiling systems shall be subjected to hose stream testing.

2.3 INTERIOR EXPANSION CONTROL SYSTEMS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

1. Balco, Inc. 2. Construction Specialties, Inc. 3. MM Systems Corporation.

B. Source Limitations: Obtain expansion control systems from single source from single manufacturer.

C. Wall-to-Wall: EJ-1

1. Basis-of-Design Product: Balco: Model GCWW-2 2. Design Criteria:

a. Nominal Joint Width: 2 inch b. Movement Capability: -50 percent/+50 percent. c. Fire-Resistance Rating: Provide expansion control system and fire-barrier

assembly with a rating not less than that of adjacent construction.

3. Type: Ribbed seal.

a. Seal Material: Manufacturer's standard.

1) Color: As selected by Architect from manufacturer's full range.

D. Ceiling-to-Wall: EJ-2

1. Basis-of-Design Product: Balco: Model ASVSC-2 2. Design Criteria:

a. Nominal Joint Width: 2 inch b. Movement Capability: -/+100 percent. c. Fire-Resistance Rating: Provide expansion control system and fire-barrier

assembly with a rating not less than that of adjacent construction.

3. Type: Ribbed seal.

a. Seal Material: Manufacturer's standard.

1) Color: As selected by Architect from manufacturer's full range.

Page 120: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 EXPANSION CONTROL – 079500 4 OF 8

2.4 EXTERIOR WALL EXPANSION CONTROL SYSTEMS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

1. Balco, Inc. 2. Construction Specialties, Inc. 3. MM Systems Corporation. 4. Tremco Incorporated.

B. Source Limitations: Obtain expansion control systems from single source from single manufacturer.

C. Wall-to-Wall: EJ-3

1. Basis-of-Design Product: Balco: Model FCWW-2 2. Design Criteria:

a. Nominal Joint Width: 2 inch. b. Movement Capability: -50 percent/+50 percent. c. Type of Movement: Thermal. d. Provide expansion control system and weather-barrier assembly.

3. Type: Cover plate.

a. Metal: Aluminum.

1) Finish: Color anodic, Class II or Manufacturer's standard to be selected by architect.

D. Roof-to-Wall: EJ-4

1. Basis-of-Design Product: Balco: Model BRBG-2SE 2. Design Criteria:

a. Nominal Joint Width: 2 inch b. Movement Capability: 100 percent. c. Type of Movement: Thermal. d. Fire-Resistance Rating: Provide expansion control system and fire-barrier

assembly with a rating not less than that of adjacent construction.

3. Type: Straight Flange Bellow, EPDM/Steel.

a. Metal: Galvanized Steel.

Page 121: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 EXPANSION CONTROL – 079500 5 OF 8

2.5 ACCESSORIES

A. Moisture Barriers: Manufacturer's standard moisture barrier consisting of a continuous, waterproof membrane within joint and attached to substrate on sides of joint below the primary cover.

1. Provide at all exterior locations and interior locations on exterior walls and slabs on grade.

B. Precompressed Wall Seal:

1. Basis-of-Design Product: Balco model BCSW-200 & 300. 2. Size: 2 inch North Building and 3 inch South Building in 5 foot lengths. 3. Type: Open Cell Hydrophobic Polymer Impregnated Polyurethane Foam with factory

applied Colorable Silicone Facing. 4. Movement Capability: -50 percent/+50 percent.

C. Fire Barrier System:

1. Basis-of-Design Product: Balco model MBF2H. 2. Size: 2 inch North Building and 3 inch South Building in 7 foot lengths. 3. Rating: 2 Hour.

2.6 MATERIALS

A. Aluminum: ASTM B 221, Alloy 6063-T5 for extrusions; ASTM B 209, Alloy 6061-T6 for sheet and plate.

1. Apply manufacturer's standard protective coating on aluminum surfaces to be placed in contact with cementitious materials.

B. Elastomeric Seals: ASTM E 1783; preformed elastomeric membranes or extrusions to be installed in metal frames.

C. Compression Seals: ASTM E 1612; preformed elastomeric extrusions having an internal baffle system and designed to function under compression.

D. Fire Barriers: Any material or material combination, when fire tested after cycling, designated to resist the passage of flame and hot gases through a movement joint and to meet performance criteria for required fire-resistance rating.

E. Moisture Barrier: Flexible elastomeric material, EPDM, minimum 45 mils thick.

F. Nonmetallic, Shrinkage-Resistant Grout: ASTM C 1107/C 1107M, factory-packaged, nonmetallic aggregate grout, noncorrosive, nonstaining, mixed with water to consistency suitable for application and a 30-minute working time.

Page 122: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 EXPANSION CONTROL – 079500 6 OF 8

G. Accessories: Manufacturer's standard anchors, clips, fasteners, set screws, spacers, and other accessories compatible with material in contact, as indicated or required for complete installations.

2.7 GENERAL FINISH REQUIREMENTS

A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for recommendations for applying and designating finishes.

B. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping.

C. Appearance of Finished Work: Noticeable variations in same piece are not acceptable. Variations in appearance of adjoining components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast.

2.8 ALUMINUM FINISHES

A. Color Anodic Finish: AAMA 611, AA-M12C22A32/A34, Class II, 0.010 mm or thicker.

1. Color: As selected by Architect from full range of industry colors and color densities.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine surfaces where expansion control systems will be installed for installation tolerances and other conditions affecting performance of work.

1. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Prepare substrates according to expansion control system manufacturer's written instructions.

B. Coordinate and furnish anchorages, setting drawings, and instructions for installing expansion control systems. Provide fasteners of metal, type, and size to suit type of construction indicated and to provide for secure attachment of expansion control systems.

C. Cast-In Frames: Coordinate and furnish frames to be cast into concrete.

3.3 INSTALLATION

A. Comply with manufacturer's written instructions for storing, handling, and installing expansion control systems and materials unless more stringent requirements are indicated.

Page 123: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 EXPANSION CONTROL – 079500 7 OF 8

B. Metal Frames: Perform cutting, drilling, and fitting required to install expansion control systems.

1. Install in true alignment and proper relationship to joints and adjoining finished surfaces measured from established lines and levels.

2. Adjust for differences between actual structural gap and nominal design gap due to ambient temperature at time of installation. Notify Architect where discrepancies occur that will affect proper expansion control system installation and performance.

3. Cut and fit ends to accommodate thermal expansion and contraction of metal without buckling of frames.

4. Repair or grout blockout as required for continuous frame support using nonmetallic, shrinkage-resistant grout.

5. Install frames in continuous contact with adjacent surfaces.

a. Shimming is not permitted.

6. Locate anchors at interval recommended by manufacturer, but not less than 3 inches from each end and not more than 24 inches o.c.

7. Install floor joints with required slab recesses and grout fill to flush with finished material on both sides.

C. Seals in Metal Frames: Install elastomeric seals and membranes in frames to comply with manufacturer's written instructions. Install with minimum number of end joints.

1. Provide in continuous lengths for straight sections. 2. Seal transitions according to manufacturer's written instructions. Vulcanize or heat-weld

field-spliced joints as recommended by manufacturer. 3. Installation: Mechanically lock seals into frames or adhere to frames with adhesive or

pressure-sensitive tape as recommended by manufacturer.

D. Compression Seals: Apply adhesive or lubricant adhesive as recommended by manufacturer to both frame interfaces and sides of slabs before installing compression seals.

E. Terminate exposed ends of expansion control systems with field- or factory-fabricated termination devices.

F. Fire-Resistance-Rated Assemblies: Coordinate installation of expansion control system materials and associated work so complete assemblies comply with assembly performance requirements.

1. Fire Barriers: Install fire barriers to provide continuous, uninterrupted fire resistance throughout length of joint, including transitions and field splices.

G. Moisture Barrier: Provide at all exterior joints and where indicated on Drawings.

Page 124: PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY ... · project no.: 17028 mississippi state university mississippi state, ms gs #113-141, phase ii poultry science building commissioning

PROJECT NO.: 17028 MISSISSIPPI STATE UNIVERSITY MISSISSIPPI STATE, MS GS #113-141, PHASE II POULTRY SCIENCE BUILDING

MARCH 2018 EXPANSION CONTROL – 079500 8 OF 8

3.4 PROTECTION

A. Do not remove protective covering until finish work in adjacent areas is complete. When protective covering is removed, clean exposed metal surfaces to comply with manufacturer's written instructions.

B. Protect the installation from damage by work of other Sections. Where necessary due to heavy construction traffic, remove and properly store cover plates or seals and install temporary protection over expansion control systems. Reinstall cover plates or seals prior to Substantial Completion of the Work.

END OF SECTION 079500