project monitoring and control. introduction goal: ensuring that the project is on time and on...
TRANSCRIPT
Project Monitoring and Control
Introduction
• Goal: ensuring that the project is on time and on budget and/or highlight any deviation from the plan
• Areas– Scope– Schedule– Costs– Risks– Quality– Human Resources
Monitoring
• Scope– Scope creep… request for changes,
rework, …
• Risks– Risk monitoring and control
• Human Resources– Informal talks, set goals, …
Monitoring (II)
• Time and Costs?
• Monitoring the schedule– Baselining– “Actual” values
• Monitoring costs– Earned Value
Basic Concepts
• Baselining– (values at t1, all values at t2, …)
• Planned versus real Values– (Planned Start, Planned Effort, Planned
End, …)– (Actual Start, Actual Effort, Actual End, …)
Planned Value
• The cumulative cost of the approved costs
• PV(t) = planned value at time t
• BAC = Budget at completion
t
BAC
PV(t)
PlannedEnd
Actual Cost
• The actual cumulative cost of the work done so far + estimation to end
t
AC(t)
ActualEnd
Earned Value
• Measures real achieved results (in terms on earnings)
• The sum of the approved cost estimates for activities completed up to a specified date
• At the end of the project, EV = PV
t
Computing Earned Value
• Rule 1. Earned value should be determined by physically examining products
• Rule 2.– Finished activities:
• Planned Value
– Unstarted activities• 0
– For unfinished activities earned value is usually just a guess
• 50/50 Rule (50 at start and 100 at end)• 20/80 Rule (20 at start and 100 at end)• 0/100 Rule (0 at start and 100 at end)
Example
Analysis at date, some values
• Expresses project progress (in terms on monetary values)
• Used to compute performances
• Some simple values– CV = EV - AC– SV = EV - PV
– a = T - Ta– b = T - Tb– c
BAC
AC
EV
T
CPV
ab
TaTb
c
Cost Performance Index (CPI)
• Compares budgeted cost of work performed to actual cost
• Indicated the efficiency of the project– CPI = EV/AC
How much we are actually getting for each euro we thought we would spend.
Schedule Performance Index (SPI)
• Compares work performed to work planned
– SPI = EV/PV
• How fast does the project progress w.r.t. how fast we expected it to be?
Interpreting EV-indicators
• Typically indicators are stable after 20% of the project
• CPI > 1 project is on budget
• CPI < 1 project is over budget
• SPI > 1 project is ahead of time
• SPI < 1 project is behind schedule
To Complete Performance Index
• The efficiency that must be achieved to complete the remaining work with the remaining money
– TCPI = (BAC - EV) / (BAC - AC)