project martha apxr ground settlement assessment
TRANSCRIPT
R APPENDIX R
Ground Settlement Assessment (Engineering Geology Limited)
25 May 2018
Prepared for:
Oceana Gold (New Zealand) Ltd
P O Box 190
WAIHI 3641
OCEANA GOLD (NEW ZEALAND) LTD
PROJECT MARTHA
ASSESSMENT OF GROUND SETTLEMENT
8332
EXECUTIVE SUMMARY
1. Oceana Gold New Zealand Ltd (OGNZL) proposes to develop a new mining project
named Project Martha for extending the mine life by developing open pit and
underground mining comprising:
The Martha underground mine including the Rex lode
The Martha Phase 4 pit (MP4)
2. The groundwater level in Project Martha will have to be lowered to RL500m1 to allow
for the development of the Martha underground mine. This is approximately 200m below
the existing consented dewatering level to RL700m of the Correnso underground mine.
Dewatering will be achieved by the installation of stage pumping chambers within the
mine that pump into the Correnso dewatering system at RL780m.
3. This report addresses the potential effects on ground settlement of the dewatering to
RL500m, together with rebound that can be expected following closure when pumping
ceases and groundwater levels rise. Settlement caused by dewatering arises as a result of
lowering the groundwater and depressurisation of the water within the defects and pores
within the ground. This results in increased stresses within the ground and compression
resulting in settlement.
4. Monitoring of groundwater levels and settlement has been undertaken over a period of 28
years (1989-2017). The results indicate a very strong correlation between groundwater
level and settlement.
5. This report builds on previous assessments proposed for dewatering required for the
Martha, Favona, Trio and Correnso Mines. Settlement predictions have generally been
shown to be accurate. Where there has been a difference between predictions and
measured settlement, this has been explained in this report.
6. Over the life of the current mining operations, settlements due to dewatering at Waihi
have been small. No damage to property or infrastructure has been attributed to
settlement induced by mine dewatering.
7. The basement rock of the area surrounding Waihi is andesite and it extends to
considerable depth. An almost continuous cap of low permeability, highly weathered and
altered andesite is present on the surface of the andesite. The andesite rocks are overlain
by a series of younger volcanic deposits which are highly variable in thickness and
composition. A thin layer, up to about 8m thick, of geologically young ash soils,
alluvium and completely weathered rhyolitic tephra blankets much of the younger
volcanic deposits.
8. Groundwater drawdown associated with dewatering of Project Martha area is expected to
be confined to the andesite bedrock. Groundwater levels in the overlying younger
volcanic deposits are generally not expected to be affected. Minimal changes to the
shallow groundwater system have resulted to date from 28 years of dewatering and none
are expected. Full groundwater drawdown occurs in the mineralised veins. Partial
drawdown occurs in the andesite rock mass, with drawdown reducing with distance from
the veins.
1 Levels are expressed as mine datum, which is approximately 1,000m below mean sea level (i.e. RL1,000m mine
datum is approximately sea level).
9. Settlements due to the proposed dewatering have been assessed using two approaches.
Firstly, an observational approach based on extrapolation of historic settlements
assuming a simple linear relationship between settlement and time. Secondly, using
numerical modelling. The numerical modelling covers dewatering since 1989 and allows
assessment of tilt arising from the differential drawdown in groundwater about the veins.
The numerical modelling demonstrates that settlements predicted using the observational
approach are conservative and that ground surface tilts due to dewatering to RL500 will
be acceptable.
10. Broad settlements due to the proposed dewatering to the target level of RL500m have
been inferred from the observed settlements measured around Waihi arising from
dewatering from the Martha Pit from RL975m to RL770m, which occurred over the
period December 1999 to November 2017. Estimated settlements are summarised in
Table 1 for both dewatering to RL700m to allow for development of the Trio and
Correnso underground mine, which has already been consented, and from RL700m to
RL500m to allow development of Project Martha. Additional settlement arising from
dewatering now sought to be consented ranges from 24mm in Zone 1 to 140mm in Zone
7. Zones 1 to 7 represent different areas around Waihi in which settlements would be
expected to be similar. The Land Use Consent granted in 1997 refers to these zones. The
original zone boundaries are shown in attached Figure 15. We have reviewed and updated
the zonation taking into consideration the monitoring data since 1997. The recommended
new zone boundaries are shown in Figure 16.
11. Estimated settlements arising due to the proposed dewatering from RL700m to RL500m
are considered acceptable and expected to occur within the andesite rock mass below the
ground surface. Differential settlements, which are normally the concern for buildings
and shallow buried services, if they occur, are expected to be very small (less than 1 in
1,000). This is because settlements are associated with the andesite rock mass and not the
overlying younger volcanic deposit or surficial soils, and so damage potential is
considered negligible.
12. We expect there will be a lag between dewatering and settlement occurring. This is
because the andesite rock mass generally has low permeability and it will take time for
the pore pressures within the rock mass to decrease.
13. When dewatering is no longer required, groundwater levels are expected to return to
approximately their original levels. This will result in rebound of the ground. We
estimate that rebound will be approximately 50 percent of the settlement that occurs
during dewatering.
14. The Waihi area has already been subjected to ground dewatering to RL540m and for a
longer duration during historical underground mining undertaken between 1893 and 1952
than will be required for the existing projects including the period of Project Martha. The
historical dewatering will have resulted in pre-consolidation of the ground so that
settlements associated with the current phase of mining would generally be expected to
be of the same order or less than those that the area experienced between 1893 and 1952.
15. We recommend that the trigger levels in the Dewatering and Settlement Monitoring Plan
(and within the resource consent) be reset considering the settlements expected because
of the additional dewatering. The recommended revised trigger levels are provided in
Table 2.
CONTENTS
Page No.
1.0 INTRODUCTION ............................................................................................................. 1
2.0 BASIS OF ASSESSMENT OF SETTLEMENT ............................................................ 2
3.0 GROUND SETTLEMENT AT MARTHA MINE ......................................................... 2
4.0 SITE GEOLOGY .............................................................................................................. 3
5.0 PIT DEWATERING AND GROUNDWATER LEVELS ............................................. 4
5.1. Historical Dewatering ..................................................................................................... 4
5.2. Dewatering 1989-2017 .................................................................................................... 4
5.3. Dewatering associated with Project Martha ................................................................ 6
6.0 GROUND SETTLEMENT MEASUREMENTS ........................................................... 7
7.0 METHODS FOR ASSESSING SETTLEMENT ........................................................... 9
8.0 SETTLEMENT ESTIMATES ....................................................................................... 10
8.1. Observational Method .................................................................................................. 10
8.2. Numerical Modelling .................................................................................................... 11
8.3. Comments on Settlement Estimates ............................................................................ 13
9.0 EXCEPTIONS TO PREDICTIONS ............................................................................. 14
9.1. Gladstone Road ............................................................................................................. 14
9.2. Slevin Street................................................................................................................... 14
9.3. Favona Underground Mine ......................................................................................... 14
10.0 REBOUND ....................................................................................................................... 15
11.0 MITIGATION AND RECOMMENDATIONS ............................................................ 15
12.0 CONCLUSIONS.............................................................................................................. 16
REFERENCES
TABLES 1 TO 3
FIGURES 1 TO 24
APPENDIX A TWO DIMENSIONAL DECOUPLED SEEPAGE AND DEFORMATION
NUMERICAL MODELLING
Our Ref: 8332 25 May 2018 Page 1
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
25 May 2018
1.0 INTRODUCTION
Oceana Gold New Zealand Ltd (OGNZL) proposes to develop a new mining project
named Project Martha for extending the mine life by developing open pit and
underground mining comprising,
The Martha underground mine including the Rex lode
The Martha Phase 4 pit (MP4)
The project components are shown in Figure 1. Project Martha provides OGNZL with
the opportunity to continue mining operations in Waihi for further 11 years beyond the
existing life of mine (Correnso underground mine).
At its greatest depth Project Martha extends to RL500m2 (up to 620 metres below the
ground surface). This is 200m below the consented level for Correnso. Dewatering will
be achieved by the installation of stage pumping chambers within the mine that pump
into the Correnso dewatering system at RL780m. Water will continue to be pumped to
the Water Treatment Plant for treatment and discharge in full accordance with existing
conditions of consent.
This report addresses the potential effects on ground settlement of the additional
dewatering to RL500m, together with rebound that can be expected following closure
when pumping ceases and groundwater levels rise.
This report builds on the previous reports prepared for dewatering required for the
Extended Martha, Favona, Trio and Correnso Mines, the predictions for which have
generally been shown to be accurate. Where there has been a difference between
predictions and measured settlement, this has been explained within this report.
In this report, the term “settlement” applies to the wide spread and relatively minor
vertical displacement of the ground surface caused by dewatering. The term “tilt” refers
2 Levels are expressed as mine datum, which is approximately 1,000m below mean sea level (i.e. RL1,000m
mine datum is approximately sea level).
OCEANA GOLD (NEW ZEALAND) LTD
PROJECT MARTHA
ASSESSMENT OF GROUND SETTLEMENT
8332
Our Ref: 8332 25 May 2018 Page 2
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
to where there are differential settlements (i.e. differences in settlement over short
distances).
2.0 BASIS OF ASSESSMENT OF SETTLEMENT
Estimates of settlement have been based on the following data:
a) Settlement data over a period of 28 years (1989-2017) from surveys undertaken
in the area around the Martha Pit as required by condition 11 of the now-expired
Mining Licence 32 2388, condition 3 of the now-expired Water Permit 971286
and conditions 5 to 7 of resource consent 124860;
b) Groundwater level measurements over a period of 28 years (1989-2017) carried
out in boreholes around the Martha Pit and dewatering water levels in the
Martha Pit and Correnso underground;
c) Assessment of the likely groundwater conditions reported by GWS Ltd (Ref.1);
and
d) Geology of the immediate mine area from earlier reports and the current
geological model as recently updated by OGNZL.
3.0 GROUND SETTLEMENT AT MARTHA MINE
Settlement caused by dewatering arises as a result of lowering of the groundwater and
depressurisation of the water within the defects and pores within the ground. This
results in increased stresses within the ground. Various other physical processes can
also give rise to settlement. They include shrink and swell as a result of changes in
moisture content.
The amount of settlement due to dewatering/depressurisation of the groundwater
depends on the following:
a) The increase in the compressive stresses within the ground, which depends on
the difference between the initial and final groundwater levels;
b) The compressibility of the ground which is a natural property, and which varies
depending on the type of soil and rock; and
c) The thicknesses of the different types of soil and rock that underlie a site which
are depressurised.
The rate of settlement depends on the permeability of the ground (i.e. on how quickly
soils can drain). Permeability is a measure of how easily water flows through a
material. The presence of holes, tunnels and other discontinuities in the ground aid the
draining of water from the ground and hence increase the rate of settlement.
Our Ref: 8332 25 May 2018 Page 3
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
Monitoring indicates a strong correlation between settlement and the depth of
dewatering. Dewatering is necessary so that mining can be undertaken in dry
conditions. Dewatering commenced at the Martha Pit in 1989. The water level in the pit
was reduced from RL1100m to about RL790m in April 2015 when the pit was
temporarily closed for operation due to pit wall instability blocking access to the base
of the pit. Since then the mine has been dewatered from the Correnso underground
mine. A graph of the depth of dewatering is shown in Figure 2.
Dewatering has also been undertaken since 2005 for the Favona underground mine,
located south east of the Martha Pit. Monitoring indicates ground settlement in the
vicinity of the Favona Mine is also strongly correlated to dewatering.
Over the life of the current mining operations, settlements due to dewatering at Waihi
have been small, but have been observed over a large area. The largest settlements have
occurred close to the Martha Pit because of dewatering of the more compressible
surface soils. These settlements occurred early in the life of the project. Settlements
have largely been in line with what was predicted, except for Favona. The reasons for
the differences are explained later in this report.
Other than in connection with an incident in 2012 described below, no damage to
property or infrastructure has been attributed to settlement induced by mine dewatering.
This is not surprising because damage from settlement usually only occurs where there
are high differential settlements (i.e. large differences in settlement over a short
distance, also known as tilt). Settlement due to dewatering at Waihi is now primarily a
result of settlement of deeper materials, not surface soils, so differential settlements
(tilt) tend to be very small.
An incident occurred in 2012 when damage to some houses in Gladstone Road to the
east of the Martha Pit was reported. Differential settlements were the cause of the
damage. Investigations confirmed the settlement was a result of dewatering of younger
volcanic deposits, and this was due to a deep geotechnical drillhole (CGD008) not
being properly grouted rather than mine dewatering. Following re-grouting of the
drillhole (CGD008) the original ground water levels were restored.
4.0 SITE GEOLOGY
The geology of the area is quite complex, but a better understanding has been possible
as knowledge has increased in conjunction with mining and exploration drilling.
Figures 3 to 6 show geological maps and sections of the area around Martha Pit,
including the various mineralised vein systems. Figure 3 includes the geological map of
the area around the Martha Pit and the location of the cross-sections radiating out from
the pit. The cross-sections are given in Figures 4 to 6 and show that the mineralised
andesite extends down to at least RL500m below the Martha Pit.
Figure 7 is a plan that shows the vein system, workings and drillhole locations between
the Martha and Favona system. Figure 8 is an indicative geological cross section from
Martha Pit through the Correnso, Trio and Favona systems along the same orientation
as Sections A-A' and B-B' in Figure 7. The section shows that andesite, the basement
Our Ref: 8332 25 May 2018 Page 4
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
rock, outcrops on the former Martha Hill, to the north of the Martha Pit and on Union
Hill. The andesite basement rock extends to depths greater than 600m. The andesite
rocks are extensively modified in places by weathering and hydrothermal alteration. An
almost continuous cap of low permeability, highly weathered and altered andesite
(upper andesite) is present on the surface of the mineralised (quartz) andesite. The
andesites are overlain by a series of younger volcanic deposits which are highly
variable in thickness and composition. The younger volcanic deposits consist of
rhyolitic tephras and ignimbrites in the form of flows, breccias and tuffs. Occasionally,
paleosols (buried soils) and sedimentary deposits such as alluvium and boulder
alluvium are present at the top of successive eruption sequences. The younger volcanic
deposits underlie much of Waihi Township and outcrop to the east and south of the
Martha Pit. A thin layer, up to about 8m thick, of geologically young ash soils,
alluvium and completely weathered rhyolitic tephras blankets much of the younger
volcanic deposits.
The younger volcanic deposits are more compressible than the underlying andesite
which means they have the potential to settle more when subjected to the same increase
in stress. Much of the dewatering induced settlement immediately adjacent to Martha
Mine is associated with these deposits.
5.0 PIT DEWATERING AND GROUNDWATER LEVELS
5.1. Historical Dewatering
Extensive underground mining was undertaken at the Martha Mine from 1893
until 1952. The workings were generally in the area of the Martha Pit but
extended to a much greater depth. Dewatering was required down to the full
depth of workings, approximately RL540m. Dewatering for Project Martha is
another 40m deeper (RL500m). The historic dewatering occurred over many
years, much longer than the recent phase of mining (1989-2018). By the time the
recent phase of mining commenced in 1989 the groundwater levels had returned
to pre-mining levels.
5.2. Dewatering 1989-2017
Dewatering occurred from Martha Pit from 1989 until 4 May 2015. Since then it
has been undertaken from the Correnso underground mine.
Dewatering of the Martha Pit occurred progressively. It was achieved by
installing pumps into the main shafts associated with historical underground
mining. A record of the mine dewatering level over the life of the mine is shown
in Figure 2.
The dewatering has been carried out at different rates during the period and
sometimes the water level has been held constant. The average rate of drawdown
in the pit from 1989 to 2000 was about 16m per year. Between 2001 and 2003
the groundwater level at the pit was maintained between RL940 - RL960. It was
then lowered progressively to about RL890 from about May 2003 to April 2006
and was held close to this until June 2009. The pit was dewatered further to
Our Ref: 8332 25 May 2018 Page 5
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
RL875 between June 2009 and December 2010. The average rate of drawdown in
this period was about 10m per year. The rate of dewatering was then increased to
about 60m per year from January 2010 and the water level was reduced from
RL875m to RL807 in November 2011. It was lowered progressively to about
RL790 from November 2011 to May 2015. After this the dewatering has occurred
from the Correnso underground mine. The dewatering level has lowered to
RL770 as at November 2017.
Monitoring of dewatering levels was undertaken from the bottom of Martha Pit
until April 2015. Dewatering levels since then are based on pump levels in
Correnso.
Monitoring wells, referred to as piezometers, have been installed at various
locations surrounding the pit to monitor the effect of dewatering on groundwater
levels as shown in Figure 9. The piezometers have been installed at different
depths to enable the monitoring of groundwater levels or water pressures in the
different geological units (alluvium, younger volcanic deposits and andesite
rock). There were no piezometers installed in the Golden Link Project Area prior
to 2011. As part of the investigations for the Golden Link Project, seven
boreholes, P90 to P95 and CGD008 were drilled and their locations are shown in
Figure 9. Piezometers were installed in different geological units to measure
groundwater levels.
GWS (Ref.1) provides a detailed review of the site hydrogeology and the effect of
pit dewatering on groundwater levels. Generally dewatering has resulted
comparatively in much greater changes in groundwater levels in the deeper
andesite rock than in the overlying weathered andesite, younger volcanic deposits
and alluvium as shown in Figures 10 and 11. In Figure 10, piezometer P2-1 and
P2-2 are in andesite and in Figure 11, piezometer P8-1 is located in andesite.
A shallow groundwater system associated with volcanic ash, alluvium and
completely weathered rhyolitic tephra is present at shallow depth. Monitoring
indicates that it is unaffected by dewatering of the pit except immediately
adjacent to the Martha Pit. Shallow groundwater levels are controlled, principally,
by rainfall infiltration, low surface permeability and natural and assisted drainage
to surface water systems. The response of piezometer P2-4 in Figure 10 is typical
of the response of the shallow groundwater systems.
Younger volcanic deposits are located within the shallow groundwater system.
Monitoring of groundwater levels indicates drainage primarily towards the open
pit where the younger volcanic deposits are close to the Pit. The response of
piezometer P2-3 in Figure 10 and P8-3 in Figure 11 is typical. Drawdown is
evident in the early stages of pit dewatering before a steady-state situation was
reached in about 1996. This contrasts with the continuing drop in groundwater
levels in the deeper andesite rock. Groundwater level changes and the associated
consolidation of the varying thickness of the younger volcanic deposits, which are
weaker and more compressible than the andesite, is responsible for much of the
settlement that occurred in the early stages of dewatering close to the Martha Pit.
The settlement was in accordance with predictions.
Our Ref: 8332 25 May 2018 Page 6
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
Groundwater levels in the mineralised andesite are directly affected by
dewatering in Martha Pit. Groundwater levels in the vein system respond rapidly
to mine dewatering with a slower response in the rock body (i.e. within the rock
mass away from the veins) due to its low permeability. The veins have good
connection due to both the high permeability nature and the historical mining.
Monitoring indicates that the amount of groundwater drawdown in the andesite
reduces with distance from the Pit. It also indicates that groundwater levels in the
previously mined and mineralised andesite are very similar to the level of
dewatering in the Pit, and that groundwater levels change quickly in response to
changes in the Pit dewatering level. However, at increasing distance from the Pit,
beyond the limits of historical underground mining and mineral vein system,
groundwater drawdown occurs much more slowly, before it reaches an
equilibrium between drainage and recharge. This is because of the lower
permeability of the unmined and non-mineralised rock, which means it takes
longer to drain.
Dewatering effects associated with the Martha Pit are abruptly attenuated to the
north and west of the mine because of faulting. Dewatering extends to the south-
west and east of Martha Pit. There is a connection between Martha, Correnso and
Trio groundwater systems. The Favona groundwater system was originally
hydrologically separate from Martha-Correnso-Trio groundwater system. Now
the construction of Favona to Trio inclines provides a connection of the two
systems above RL823m (Ref.1).
Monitoring in the andesite is limited by the depth to which the piezometers have
been installed. The deepest that a piezometer has been installed is at RL965m
(P92 in East Waihi) while the Project Martha underground mines will be
developed down to RL500m.
5.3. Dewatering associated with Project Martha
The Martha Underground mine extends to RL500m. Therefore, the water level
will need to be lowered at least 200m below the currently consented level
(RL700m). Dewatering will be achieved by the installation of stage pumping
chambers within the mine that pump into the existing Correnso dewatering
system located at RL780m. Water will continue to be piped to the Water
Treatment Plant for treatment and discharge in full accordance with existing
conditions of consent.
The observed response of veins within the Martha groundwater system (which
does not include the separate Favona groundwater system) to dewatering at
Martha Mine means that the RL500m water level will also be developed in veins
beneath Waihi, including Waihi East (Ref.1). The existing multi-level
piezometers in Waihi East shown in Figures 12 and 13 are considered a good
indication of the potential response to the additional dewatering at the location
and over much of the developed Waihi area. The groundwater levels in boreholes
P90 to P95 and P100 to P102 located in the Waihi East area are shown in Figures
12 and 13. These groundwater levels were recorded in November 2017. The
groundwater level of the Martha vein system at that time is estimated to be
Our Ref: 8332 25 May 2018 Page 7
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
approximately RL750m. The deepest piezometers in the boreholes are in the
upper andesite and show significant under drainage.
Observation of groundwater levels and modelling by GWS (Ref.1) indicate
dewatering the Martha vein system from the current elevation (approximately
RL770m) to RL500m is not expected to significantly affect groundwater
pressures within the younger volcanics. This is consistent with the long-term
groundwater monitoring data which shows shallow groundwater pressures have
remained relatively unchanged while dewatering has been on going. The
groundwater pressures in the veins and other open rock defects connected to the
veins are expected to drop immediately in response to lowering of the
groundwater level required for the Martha Underground. The groundwater
pressures in the andesite rock mass are indicated to respond to the deeper
dewatering.
The weathering profile depth within Andesite rock does vary locally, resulting in
a variation in thickness of the low permeability material that perches the shallow
groundwater system. However, monitoring and modelling indicates that it is
always thick enough to maintain a perched water level in the overlying younger
volcanics (Ref.1).
6.0 GROUND SETTLEMENT MEASUREMENTS
Ground settlement measurements have been made around the Martha Pit and
throughout Waihi since 1989. Six monthly surveys have been undertaken as required
by condition 11 of the Mining Licence, condition 9 of Water Permit 971286 and
conditions 5 to 7 of resource consent 124860. The locations of the settlement markers
where settlement measurements are made are shown in Figure 14.
Land Use Consent (No.97/98-015, Condition 3.30g) granted in 1999 refers to Figure 8
of the evidence presented by Dr R Semple to the Environment Court in 1998. Seven
zones (Zones 1 to 7) are identified in Figure 8 and a copy of this figure is attached
(refer to Figure 15). The seven zones are intended to represent different areas in which
settlements would be expected to be similar. The zone boundaries were based on
settlement monitoring up to 1997, site geology and distance from the pit. Generally,
settlements within the different zones have been relatively consistent. However, there
are some settlement markers that don’t fit with the zones they are currently associated
with. Consequently, we have reviewed and updated the zonation taking into
consideration monitoring data since 1997. The recommended new zonation map is
shown in Figure 16. The same number of zones has been retained, and in many
locations the zone boundaries have not been changed. The new zones are primarily
based on examination of settlement data, but local geology has also been considered.
The monitoring data show that some of the settlement markers indicate greater
settlements than their original zone category. This is more significant for settlements to
the South and East of Waihi. This area is likely to be affected more by the Favona
underground mine rather than the Martha, Trio and Correnso system. We have reshaped
the boundaries of Zones 1, 2, 3, 4 and 5 in this area to provide consistency against the
monitoring results to November 2017. We have also modified the boundaries of Zones
Our Ref: 8332 25 May 2018 Page 8
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
5 and 6 slightly around the Martha Pit. The new zoning around the pit provides a better
transition and avoids localised, isolated zones. No changes have been made to the
boundary of Zone 7.
The results of settlement monitoring for Zones 1 to 7 are presented in Figures 17 to 23
respectively. The settlement data indicate that there have been varying amounts of
settlement but always over a large area and not resulting in unacceptable differential
settlement (tilt). Settlement markers along the southern and south eastern perimeter of
the pit have shown the greatest settlement. Generally, settlements decrease with
distance from Martha Pit. Settlements near the perimeter of the pit are within the range
of 30-290mm. Greater settlements have been recorded on the southern and eastern sides
of the Pit compared to the northern and western sides. This difference is due to the
presence of a greater thickness of the more compressible younger volcanic deposits on
the southern and eastern sides.
Comparison of settlements with groundwater levels indicates a correlation. The amount
of settlement is generally proportional to the drop in groundwater level. This is
apparent in Figure 24 where settlement at 4A, which is relatively close to Martha Pit,
has a similar trend to the groundwater level measured in the base of the pit. This same
trend is evident in Figures 21 and 22 which show settlements in Zones 5 and 6 that are
close to the pit.
The rate of settlement closer to the Martha Pit was generally higher during the initial
stages of Pit dewatering and has reduced with time. Settlement markers in Zone 5
(Figure 21) and Zone 6 (Figure 22) show this. The curves are generally steeper in the
early stages of mining, indicating a higher rate of settlement, than later. This is
attributed to the higher compressibility of the younger volcanic deposits and the
groundwater drawdown in these materials that occurred in the early stage of the mine
life. In the early stages of the mine life Martha Pit dewatering resulted in changes in
groundwater levels in both the younger volcanic deposits and underlying andesite rock.
This can be seen in Figure 10. The changes in groundwater level in the ignimbrite (P2-
3) were smaller than in the andesite, and equilibrium was reached in a shorter period.
However, ignimbrite is more compressible than andesite and this is the reason why
there were higher rates of settlements observed initially.
Settlements show a slower response to pit dewatering at increasing distance from the
Martha Pit and underground mines, as shown by settlement measurements in Zones 2, 3
and 4 (refer to Figures 18, 19 and 20 respectively). At these locations settlements are
much smaller and the rate of settlement is more uniform with time. Observations are in
line with predictions. Smaller settlements are expected because groundwater drawdown
away from the Martha Pit and underground mines is less and the rate of settlement is
more uniform with time due to the slow rate of depressurisation of the andesite rock
mass.
Settlements have continued to occur, albeit at very slow rates (typically 0.1-1mm year)
during periods when mine water levels have not changed significantly (July 1998 to
January 2000 and November 2006 to November 2010). We consider the most likely
explanation is ongoing drainage of the mineralised andesite rock mass, with slow
depressurisation occurring due to the low permeability of the rock mass away from the
quartz vein system. The proposed further dewatering to RL500m will have minimal
Our Ref: 8332 25 May 2018 Page 9
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
effect on any ongoing settlement in the upper andesite or younger volcanics. However,
it will result in additional depressurisation of the mineralised andesite rock mass. There
was a significant change in pit water level from November 2010 to November 2011. In
general, settlement markers (refer Figures 17 to 23) either showed no noticeable or only
a very small increase in the rate of settlement. Where there was a change in rate of
settlement it occurred either immediately or within one month following the change in
pit water level. However, the rates of settlement reduced to their original levels in
approximately six months.
The settlement measurements show cyclic patterns in some cases (refer to Figures 17 to
23). The cyclic variation is typically in the range of 5 to 15mm. The cyclical pattern is
believed to be either due to seasonal effects resulting in differences between base and
intermediate benchmark levels or due to errors in determining intermediate benchmark
levels. Most settlements are measured from intermediate benchmark levels that are in
turn checked against base benchmarks located away from the influence of mining
activity. It is possible that seasonal effects (e.g. changes in groundwater levels resulting
in differential settlements between the base and intermediate benchmarks or
shrink/swell of the surficial soils on which the benchmarks are located) could result in
seasonal differences between the base and intermediate benchmarks. The differences
could also be due to errors in survey measurement. The cyclical variations are relatively
small and are close to the level of accuracy expected from survey measurements.
Condition 7 of resource consent 124860 (and previously condition 10 of the Water
Permit 971286) requires that tilt be assessed based on the six-monthly settlement
survey data and reported in the Annual Dewatering and Settlement Monitoring report
(Ref.2). Tilt gradients are generally very low, less than 1:1,000, which is well below the
gradient that would give rise to concern for structures. Locations where tilt gradients
are greater than 1:1000 are discussed in Section 9.
7.0 METHODS FOR ASSESSING SETTLEMENT
Open-pit mining at the Martha Mine commenced in 1987. Prior to commencement of
mining, and subsequently again in 1997, theoretical predictions of the future ground
settlements because of mine dewatering were made. Since then, throughout the life of
the mine, ground settlements have been measured at 6 monthly intervals at 399
locations in Waihi. The large number of settlement observations, spanning some 28
years, provides a very reliable database for estimating likely future settlements
associated with further dewatering. In fact, the monitoring undertaken at Waihi makes
it one of the best monitored sites in New Zealand and provides an excellent database for
predicting future settlements.
The proposed dewatering will result in an approximately 250m drop in the current
groundwater levels in the andesite basement rock. Minimal effects on the shallow
groundwater system and younger volcanic materials are predicted by GWS (Ref.1).
This conclusion is based on review of monitoring data during mining of Martha Pit and
the different underground mines and theoretical seepage analyses. Consequently,
settlements caused by dewatering within the area of Project Martha will primarily be
associated with the changes in groundwater levels in the andesite basement rock.
Our Ref: 8332 25 May 2018 Page 10
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
Estimates of settlement in the andesite have been made using two approaches. The first
is an observational approach in which the settlement observations to date are used as a
basis for predicting what might occur with the proposed dewatering. The second is a
theoretical approach involving numerical modelling of seepage and deformation.
8.0 SETTLEMENT ESTIMATES
8.1. Observational Method
Estimates of settlements arising from further dewatering can be inferred from
settlements recorded during the dewatering of the Martha Pit and the different
underground mines. This is possible because:
(i) There is strong correlation between groundwater levels and observed settlement
and
(ii) Studies by GWS Ltd (Ref.1) indicate that the dewatering to RL500m will not
have any significant effect on the groundwater levels in the overlying younger
volcanic deposits and much of the upper andesite immediately underlying the
younger volcanic deposits, these being the layers most sensitive to dewatering
and responsible for much of the settlement that has occurred to date.
The initial dewatering of the Martha Pit from January 1989 through to 1996-1999
caused depressurisation of some of the younger volcanic deposits and the andesite units
as shown in Figure 10. After 1996, most of the piezometers in the younger volcanic
deposits have shown no reaction to further dewatering of the mine. Piezometric levels
have remained steady despite further dewatering of the pit suggesting that most of the
observed settlement after 1996 was due to depressurisation of the andesite rock mass.
From December 1999 to November 2017, the water level in the Martha Pit was lowered
by 205m from approximately RL975m to RL770m. The settlement measured during
this time can be assumed to be due to settlement within the andesite rock mass. This
period was selected because the water level was steady in the pit at about RL975m from
June 1998 to December 1999 and at about RL770m from December 2011 to November
2017. It can be assumed that steady conditions were established at the start and end of
the 205m drawdown.
As previously explained settlements measured around Waihi are grouped into seven
zones (Zones 1 to 7). Observed settlements in each zone are presented in Figures 17 to
23. The average settlement for each zone over the period December 1999 to November
2017 is shown in their respective figure and is also summarised in Table 1. The average
settlements due to 205m drawdown are estimated from the slopes of the settlement
curves ignoring any obvious outliers.
The greatest average settlement occurred in Zone 7. It was approximately 143mm. This
Zone is located near the Martha Pit. The higher rate of settlement in this area is likely
due to greater depressurisation of the andesite rock mass and possibly also due to
subsidence associated with the underlying historical Royal Lode workings.
Our Ref: 8332 25 May 2018 Page 11
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
Settlements in Zones 4, 5 and 6 over the period December 1999 to November 2017
averaged 38mm, 68mm and 96mm respectively. The distance from Martha Pit has a
significant effect on the magnitude of the settlement observed. Areas further away from
the Pit would have had less depressurisation of the underlying andesite rock mass and
therefore less settlement. Zone 4 is further from Martha Pit than Zones 5 and 6. Zone
5 has more points farther from the Pit than Zone 6.
Average settlements in Zones 1, 2 and 3 are between 24mm and 27mm. These areas are
least affected by drawdown.
As a check we have compared estimated settlements for the Trio Project (Ref.3) against
the measured settlements associated with dewatering from RL875 to RL770 (approx.
January 2011 to November 2017). The comparison showed that the estimated
settlements are consistent with the monitored settlements. This confirms the
observational method is a reliable predictor of future settlements.
Estimates of future settlement that will occur because of dewatering from the present
level of RL770 to RL700 for the Trio and Correnso Projects have been inferred from
the above observations. They have been made by scaling the observed settlements
arising from the 205m reduction in water level from December 1999 to November
2017. Estimates based on this approach are summarised in Table 1. Estimates of
settlements vary from 12mm in Zone 1 to 47mm in Zone 6. In Zone 7, settlement of
70mm is estimated. As noted above, the dewatering to RL700m for the Correnso
Project has already been consented. The dewatering has continued from November
2017 and therefore some of these settlements have already occurred.
Estimates of additional settlements due to dewatering from RL700m to RL500m to
allow for development of Project Martha are inferred from observations of historical
settlements from December 1999 to November 2017. The estimated settlements are
summarised in Table 1. Settlements range from 24mm in Zone 1 to 140mm in Zone 7.
Estimates of settlements in Zones 3, 4, 5 and 6 range from 26mm to 94mm. These
estimates are average estimates for the zones. At some locations settlements within
each zone will be less and at others more.
The rate of drawdown of the groundwater level in the Martha Pit that started after
November 2010 for the Trio Project is higher than the previous drawdown rates and
associated with observations used to estimate the expected settlement as shown in
Figures 17 to 23. It shows that the rate of drawdown has some effect on the rate of
settlement, but it is not that significant. The average rate of dewatering from RL700m
to RL500m will be at a faster rate than historical. However, the rate of drawdown is not
expected to significantly affect the magnitude of the settlement based on observations
to date and the numerical modelling. There could be a lag between dewatering and
settlement occurring. This is because the andesite rock mass is of generally low
permeability and it takes time for the pore pressures within the rock mass (i.e.
groundwater level) to decrease.
8.2. Numerical Modelling
Two-dimensional de-coupled numerical modelling of seepage and deformation has
been undertaken of an area to the east of Martha Pit. This area covers settlement Zones
Our Ref: 8332 25 May 2018 Page 12
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
4 and 5. The modelling provided estimates of settlements due to dewatering to RL770m
associated with mining since 1989 and with the proposed additional dewatering to
RL500m associated with Project Martha. The analyses have been undertaken using
GeoStudio 2D finite element analysis (FEA) programs, SEEP/W (Ref.7) and
SIGMA/W (Ref.8). The SEEP/W model of the ground and groundwater parameters was
provided by GWS. Some small adjustments were made to the model for deformation
modelling. The soil stiffness values were obtained from a geotechnical model
developed by PSM (Ref.4). The assumptions and results of the modelling are presented
in Appendix A.
The scope of modelling included:
i. Modelling of seepage and drawdown associated with dewatering of both single
and multiple veins to various levels using SEEP/W.
ii. Deformation analyses using SIGMA/W with changes in stress due to
dewatering to different levels predicted by the SEEP/W modelling.
iii. Comparison of the results of the numerical modelling with monitored
settlements
Modelling was undertaken for three stages of dewatering:
i. Stage 1: Drawdown to the midpoint of the weathered andesite (RL975m at
deepest).
ii. Stage 2: RL975m to RL770m (current level)
iii. Stage 3: RL770m to RL500m
The average modelled settlements for Stage 1 are 23mm for both single and multiple
veins. The average modelled settlements for Stage 2 are 89mm for a single vein and
152mm for multiple veins. For Stage 3 the average modelled settlements are 26mm for
a single vein and 66m for multiple veins.
Results of the modelling from the first two stages were compared with monitored
settlements. The average modelled settlements for Stage 1 are generally smaller than
monitored settlements (23mm compared to average monitored settlements of between
25mm and 45mm). The Stage 2 modelled settlements are greater. The average
modelled settlements for Stage 2 are 89mm for a single vein and 152mm for multiple
veins compared to average monitored settlements in Zones 4 and 5 of 38 and 68mm
respectively. The differences between modelled and monitored settlements could be
due to the assumption of a single stiffness value for the andesite rock mass. It is
possible that the rock mass has a lower modulus at higher elevations with increasing
modulus with depth.
The modelling indicates additional settlements due to Stage 3 dewatering (RL770m to
RL500m) are considerably less than for Stage 2 (average modelled settlements of
26mm for a single vein and 66mm for multiple veins compared to 89mm and 152mm
respectively for Stage 2). This is because groundwater drawdown and associated
incremental stress in the rock mass is localised around the veins. It results in arching
effects and lower settlements than if the rock mass was fully dewatered. Also, with
Stage 3 the depth of rock mass that is affected by drawdown is less than Stage 2.
Our Ref: 8332 25 May 2018 Page 13
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
The modelling allows estimation of ground surface tilts. The estimated maximum tilts
are associated with the multiple vein model and for Stages 1, 2 and 3 are 1 in 8,000, 1
in 4,600 and 1 in 3,800 respectively. The incremental change in tilt from Stage 2 to
Stage 3 is very small and consistent with the relatively small increment in settlement
predicted by numerical modelling. The measured tilts above the Correnso underground
mine (which is largely within Zones 4 and 5) are generally smaller than the maximum
tilt predicted by numerical modelling (1 in 4,600). This indicates the numerical model
is conservative. The estimated maximum tilt following dewatering to RL500m (1 in
3,800) is considerably less than 1 in 1,000 which is the current trigger for notification
of the Waikato Regional Council and for instigating additional monitoring.
8.3. Comments on Settlement Estimates
Estimates of the additional settlement due to dewatering from RL700m to RL500m (i.e.
Martha Project) by the observational method in Zones 4 and 5 are greater than those by
numerical modelling. The observational method gives values of 38-66mm. Estimates
from modelling for dewatering from RL770m to RL500m (70m more than associated
with Martha Project) are 26mm for a single vein and 66mm for multiple veins. For
dewatering from RL975 m to RL770m the monitored settlements are lower than
modelled, indicating that numerical modelling is conservative. Assuming the same
applies to dewatering to RL500m it is conservative to adopt settlements from the
observational approach for estimating the additional settlements associated with Project
Martha. We consider that estimates based on the observational method are reliable
because they are based on 28 years of monitoring. The numerical modelling estimates
rely on assessed values of rock deformation modulus and the extent of drainage within
the rock mass. There is considerable uncertainty associated with these assumptions.
However, the numerical modelling does provide valuable insight with respect to the
comparative difference between the different stages of dewatering and estimates of tilt
that arise due to greater drawdown at the veins.
Local variations in settlement can be expected, as has been evident with current
monitoring. The proposed dewatering could also result in an extension of the current
zone of influence of dewatering. Settlements within the new areas of influence are
likely to be very small based on monitoring of settlements within the current zone of
influence.
The proposed dewatering to RL500m is expected to result in groundwater drawdown in
the andesite rock mass, with no or minor impact on groundwater within the overlying
younger volcanic deposits and shallow groundwater system. Predicted settlements in
Zones 1 to 5 are small and are not expected to have any significant effect. Predicted
settlements in Zones 6 and 7 are greater but still no damage to existing structures or
infrastructure is expected.
Settlements at the ground surface are generally expected to follow those predicted in
the andesite rock mass. Differential settlements (tilt), which are normally the concern
for buildings and shallow buried services, are expected to be very small (less than 1 in
1,000) because settlements are associated with the andesite rock mass and not the
overlying younger volcanic deposits or surficial soils, and so damage potential is
considered negligible.
Our Ref: 8332 25 May 2018 Page 14
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
The total magnitude of the settlements is small and not considered significant because,
as noted above, differential settlements are normally the concern for buildings and
buried services. It is of interest to note that the Waihi area has already been subject to
groundwater dewatering to a similar depth and greater duration during historical
underground mining between 1893 and 1952 than required for the Project Martha. The
historical dewatering will have resulted in pre-consolidation of the ground so that
settlements associated with the current phase of mining would generally be expected to
be of the same order or less than those that the area experienced between 1893 and
1952.
In some areas the total magnitude of settlement arising because of dewatering to
RL500m will exceed the trigger levels derived for the Correnso Project. As
recommended in Section 11, new trigger levels have been set to account for the effects
of dewatering to greater depths for Project Martha.
9.0 EXCEPTIONS TO PREDICTIONS
Generally, settlements have been in-line with expectations. Where they have not they
have been investigated and, in all cases, there have been explanations. They are
discussed in the following sections.
9.1. Gladstone Road
An incident occurred in 2012 when damage to some houses in Gladstone Road to the
east of the Martha Pit was reported. Differential settlements were the cause of the
damage. Investigations confirmed the settlement was a result of dewatering of the
younger volcanic deposits in this area, and this was due to a deep geotechnical drillhole
(CGD008) not being properly grouted. Settlement was not directly related to mine
dewatering. Following re-grouting of the drillhole the ground water was re-stored to the
original levels and the land re-bounded close to original levels.
9.2. Slevin Street
Since May 2015 the tilt between marks 20C and 20D (Slevin Street) has been greater
than 1:1,000. OGNZL believes the settlement is not related to dewatering associated
with the current project, but to the weak nature of the ground and unfilled stopes that
underlie the area (Ref.2). The area is near a high hazard zone identified by GNS
Science (Ref.5). Slevin Park is a swampy area, historically infilled with weak material
and slumping/subsidence has occurred previously. No damage to any residences has
occurred. The closest residence to the affected area is 95m away.
9.3. Favona Underground Mine
Settlements at the Favona underground mine have been greater than originally
predicted and have exceeded 1 in 1,000 at three locations. The locations are directly
above the underground workings on farmland owned by OGNZL. No buildings have
been affected. The original settlement estimates only considered settlements in the
younger volcanic deposits (Ref.6). If allowance is made for settlement in the geologic
Our Ref: 8332 25 May 2018 Page 15
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
units that underlie the younger volcanic deposits (i.e. unweathered ignimbrite, dacite
units and both the upper and mineralised andesite rocks) then the observed settlements
are considered realistic.
10.0 REBOUND
Dewatering for Project Martha Area will eventually stop once underground mining in
the project area has ceased. The area will then be allowed to re-flood. The re-flooding
will occur naturally but will be accelerated by the addition of water pumped from the
Ohinemuri River. Re-flooding will result in the groundwater levels in the andesite and
the younger volcanic materials rising back close to their original levels. Rebound will
occur as rising groundwater re-saturates the ground, resulting in a reduction in effective
stress within the ground. As already noted, historical underground mining at Martha Pit
involved dewatering of the ground to about RL540m; approximately 40m above the
targeted RL500m for the Martha Underground. Following the cessation of mining in
1952 groundwater levels rose. Rebound will have occurred but was not monitored. We
are unaware of any damage arising from re-watering.
Rebound of the ground to its original level because of rising groundwater levels is not
expected. We estimate that rebound could be approximately 50% of the settlement that
has occurred during modern mining. We consider that no damage is expected because
of rebound.
11.0 MITIGATION AND RECOMMENDATIONS
Predicted settlements associated with additional dewatering to RL500m in Zones 1 to 5
are small and are not expected to have any significant effect. Predicted settlements in
Zones 6 and 7 are greater but still no damage to existing structures or infrastructure is
expected. This is because settlements are associated with settlement in the deeper
andesite rock mass which underlies the younger volcanic deposits that blanket much of
the area. Numerical modelling for Martha East (Zones 4 and 5) indicates incremental
settlements and tilts associated with Project Martha are small and well within
acceptable limits. Monitoring to date confirms this is the case, even in Zone 6.
Consequently no mitigation measures are considered necessary. We recommend
monitoring of settlement as required by the expired Mining Licence and resource
consent 124860 should continue. Figure 14 shows that settlement markers within the
area of the Martha Underground mine are closely spaced and therefore we believe it is
not necessary to install any additional settlement markers for Project Martha.
We recommend that the trigger levels be reset considering the settlements expected
because of the additional dewatering. The recommended revised trigger levels are
provided in Table 2. The recommended trigger levels are based on estimates of the
average settlement predicted for each zone. There is variation in observed settlements
within each zone as can be seen in the settlement observations shown for each zone in
Figures 17 to 23. There are a few reasons for this. They include the variation in
thickness and compressibility of the different geologic units, variations in groundwater
levels, the accuracy of the settlement surveys, variations in ground levels due to
shrink/swell effects, local disturbance or damage to settlement markers and changes to
Our Ref: 8332 25 May 2018 Page 16
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
groundwater levels due to new mining projects that have occurred following definition
of the zones. The zones should be interpreted as only providing broad definitions of
settlement response. Variations in settlements over distance are more likely to change
gradually and so in reality the zones are not hard boundaries.
We also recommend that similar conditions as for the Correnso Underground be
adopted to ensure that the groundwater regime affecting ground settlements is not
adversely impacted. These include:
i) No stoping above defined levels in the andesite. This is to preserve the integrity
of the top of the andesite that acts to maintain the perched groundwater level in
the younger volcanics.
ii) Grouting of all future surface-drilled holes to a depth below the top of the
andesite.
iii) Avoiding intercepting existing drillholes with mine workings.
iv) Grouting drillholes from underground where underground development
intercepts holes that are making water or geological defects with significant and
sustained water flows.
12.0 CONCLUSIONS
1. Dewatering of Project Martha will require a reduction in groundwater from the
consented level of RL700m to RL500m. Dewatering is proposed to be achieved
by the installation of stage pumping chambers within the Martha Underground
that pump into the Correnso dewatering system at RL780m. Water will continue
to be pumped to the Water Treatment Plant for treatment and discharge in full
accordance with existing conditions of consent. Now dewatering is being
undertaken down to RL700m for the Correnso Project. This dewatering is
already authorised by existing resource consents. The groundwater level will
then be lowered to RL500m for Project Martha. Drawdown is expected to be
confined to the andesite rock. Groundwater levels in the overlying younger
volcanic deposits are generally not expected to be affected. No changes to the
shallow groundwater system are expected.
2. Settlements due to the groundwater drawdown to the target level of RL500m
have been estimated by inference from observed settlement measurements and
numerical modelling. The settlements inferred from observed settlements are
greater than predicted by numerical modelling. They have been adopted as best
estimates. They are likely to be conservative based on comparison with the
results from numerical modelling. The numerical modelling provides useful
insight into the comparative settlements associated with different stages of
dewatering and provides estimates of ground surface tilt.
3. The inferred settlements have been based on the observed settlement measured
around Waihi arising from dewatering from the Martha Pit from levels RL975m
to RL770m which occurred over the period December 1999 to November 2017.
Settlements due to dewatering from RL770m to RL700m to allow for the
development of the Correnso underground mine are estimated to range from
12mm in Zone 1 to 47mm in Zone 6. Zone 7, which is around the pit, is
Our Ref: 8332 25 May 2018 Page 17
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
expected to have settlement of about 70mm. Additional settlement arising from
the dewatering now sought to be consented for Project Martha (to RL500m)
ranges from 24mm in Zone 1 to 94mm in Zone 6. Zone 7 is expected to have
additional settlement of about 140mm.
4. Estimated settlements are small and are expected to occur within the andesite
rock mass below the ground surface. Differential settlements (tilt), which are
normally the concern for buildings as well as buried services, are expected to be
very small and so damage potential is considered negligible.
5. We expect there will be a lag between dewatering and settlement occurring.
This is because the andesite rock mass generally has low permeability and it
will take time for the pore pressures within the rock mass to decrease.
6. When dewatering is no longer required, groundwater levels are expected to
return to their original levels. This will result in rebound of the ground. We
estimate that rebound will be approximately 50 percent of the settlement that
occurs during dewatering.
7. We recommend that the trigger levels be reset considering the settlements
expected because of the additional dewatering. The recommended revised
trigger levels are provided in Table 2.
Report prepared by
ENGINEERING GEOLOGY LTD
C Wu (Geotechnical Engineer) T Matuschka (CPEng)
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
REFERENCES
1. GWS (2018) ‘Project Martha Assessment of Groundwater Effects’.
2. OGNZL (2017) 'Dewatering and Settlement Monitoring Report 2017' Ref. WAI-200-
REP-007-003.
3. EGL (2012) 'Newmont Waihi Gold, Golden Link Project Area, Assessment of Ground
Settlement' Ref.6808.
4. PSM (2010) ‘Martha Mine East Layback Pit 66D, PSM125.R39’.
5. GNS Science (2008) ‘Waihi Subsidence Assessment’ GNS Science Consultancy Report
2006/235.
6. URS (2003) 'Favona Underground Mine - Assessment of Groundwater Issues', 14
March 2003.
7. GEO-SLOPE International Ltd (2007) ‘Seepage Modeling with SEEP/W: An
Engineering Methodology’, GEO-SLOPE International Ltd.
8. GEO-SLOPE International Ltd (2007) ‘Stress and Deformation Modeling with
SIGMA/W: An Engineering Methodology’, GEO-SLOPE International Ltd.
8332 Ground Settlement Assess Report_Project Martha 25 May 2018.docx
TABLE 1. SETTLEMENT ESTIMATES – OBSERVATIONAL METHOD
Zone
Typical Settlement
Response to
Dewatering from
RL975m to
RL770m (Dec 1999
to Nov 2017) (mm)
Estimated Settlement
Response to Dewatering
of Correnso Project from
RL770m to RL700m 1
(mm)
Estimated Settlement
Response to
Dewatering of Project
Martha from RL700m
to RL500m (mm)
1 24 12 24
2 24 12 24
3 27 13 26
4 38 19 38
5 68 33 66
6 96 47 94
7 143 70 140
1
The dewatering from RL770m to RL700m began in November 2017 and
therefore some of the estimated settlement has already occurred
TABLE 2. RECOMMENDED NEW TRIGGER LEVELS FOR SETTLEMENT (mm)
Zone Recommended New Trigger Levels for Settlement (mm)
1 55
2 65
3 95
4 160
5 260
6 340
7 540
LEGEND
As-Built Pit Crest(August 2018)
MP4 Pit Crest
MMZ Boundary
Expired MiningLicence Boundary
Extended Project LandUse Consent Boundary
Cambridge RoadRealignment
Martha Underground
Date: 14 April 2018
File:D:\...\Project Martha & Zone Boundaries-d.cdr
Figure 1
Project Martha and Regulatory Boundaries
NN
0 200 400 600 800 1000m
700.0
720.0
740.0
760.0
780.0
800.0
820.0
840.0
860.0
880.0
900.0
920.0
940.0
960.0
980.0
1000.0
1020.0
1040.0
1060.0
1080.0
1100.0
1120.0
9-Dec-87
8-Dec-88
8-Dec-89
8-Dec-90
8-Dec-91
7-Dec-92
7-Dec-93
7-Dec-94
7-Dec-95
6-Dec-96
6-Dec-97
6-Dec-98
6-Dec-99
5-Dec-00
5-Dec-01
5-Dec-02
5-Dec-03
4-Dec-04
4-Dec-05
4-Dec-06
4-Dec-07
3-Dec-08
3-Dec-09
3-Dec-10
3-Dec-11
2-Dec-12
2-Dec-13
2-Dec-14
2-Dec-15
1-Dec-16
1-Dec-17
1-Dec-18
Gro
un
dw
ater
Lev
el R
L (m
)
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Mine Dewatering Level
Ref. No: 8332Date: Jan 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure 2
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Engineering Geology Ltd Unit 7C, 331 Rosedale Rd, PO Box 301054, Albany Ph (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTD PROJECT MARTHA
Geological Plan
Ref. No: 8332 Date: Jan 2018 Drawn: OGNZL
Engineering Geology Ltd Unit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure 3
Engineering Geology Ltd Unit 7C, 331 Rosedale Rd, PO Box 301054, Albany Ph (09) 4862546 Fax (09) 4862556
Engineering Geology Ltd Unit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
AQF – Quartz Andesite A – Upper Andesite HBX – Hydrothermal Breccia CSH – Contact Shear (between BDAC and HBX or A) BDAC – Black Hill Dacite RT – Rhyolitic Tuff IS/ISC/ISS – Sandy Ignibrites IW – Welded Ignimbrite ASH - Ash REG – Regolith RHHY – Ruahorehore rhyolite
Engineering Geology Ltd Unit 7C, 331 Rosedale Rd, PO Box 301054, Albany Ph (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTD PROJECT MARTHA
Geological Cross Sections A and B
Ref. No: 8332 Date: Jan 2018 Drawn: OGNZL
Engineering Geology Ltd Unit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure 4
Engineering Geology Ltd Unit 7C, 331 Rosedale Rd, PO Box 301054, Albany Ph (09) 4862546 Fax (09) 4862556
Engineering Geology Ltd Unit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
AQF – Quartz Andesite A – Upper Andesite HBX – Hydrothermal Breccia CSH – Contact Shear (between BDAC and HBX or A) BDAC – Black Hill Dacite RT – Rhyolitic Tuff IS/ISC/ISS – Sandy Ignibrites IW – Welded Ignimbrite ASH - Ash REG – Regolith RHHY – Ruahorehore rhyolite
Section A
Section B
Engineering Geology Ltd Unit 7C, 331 Rosedale Rd, PO Box 301054, Albany Ph (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTD PROJECT MARTHA
Geological Cross Sections C and D
Ref. No: 8332 Date: Jan 2018 Drawn: OGNZL
Engineering Geology Ltd Unit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure 5
Engineering Geology Ltd Unit 7C, 331 Rosedale Rd, PO Box 301054, Albany Ph (09) 4862546 Fax (09) 4862556
Engineering Geology Ltd Unit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
AQF – Quartz Andesite A – Upper Andesite HBX – Hydrothermal Breccia CSH – Contact Shear (between BDAC and HBX or A) BDAC – Black Hill Dacite RT – Rhyolitic Tuff IS/ISC/ISS – Sandy Ignibrites IW – Welded Ignimbrite ASH - Ash REG – Regolith RHHY – Ruahorehore rhyolite
Section C
Section D
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Geological Cross Sections E and F
Ref. No: 8332Date: Jan 2018Drawn: OGNZL
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure 6
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
AQF – Quartz AndesiteA – Upper AndesiteHBX – Hydrothermal BrecciaCSH – Contact Shear (betweenBDAC and HBX or A)BDAC – Black Hill DaciteRT – Rhyolitic TuffIS/ISC/ISS – Sandy IgnibritesIW – Welded IgnimbriteASH - AshREG – RegolithRHHY – Ruahorehore rhyolite
Section E
Section F
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Plan of Martha, Union and Favona Systems
Ref. No: 8332Date: Feb 2018Drawn: OGNZL
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure 7
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Indicative Geological Section from Martha to Favona
Ref. No: 8332Date: Feb 2018Drawn: OGNZL
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure 8
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Location of Groundwater Monitoring Piezometers and Water Table Contours
Ref. No: 8332Date: Jan 2018Drawn: GWS LTD
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure 9
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Notes from GWS Ltd Letter Reportdated 8 Jan 2018
Water table elevation were plotted at the monitoring well location. The elevation are shown as yellow numberswith wells with uncertain values shown as orange numbers.
Water elevation data from shallow monitoring wells was averaged over the last 12 months (Jan-Dec 2017) giventhe seasonal fluctuations evident in therecords and plotted at the monitoringwell location.
Inferred contours of the water table at10m intervals were drawn having regardto the topography. These contoursare shaded yellow.
700.0
720.0
740.0
760.0
780.0
800.0
820.0
840.0
860.0
880.0
900.0
920.0
940.0
960.0
980.0
1000.0
1020.0
1040.0
1060.0
1080.0
1100.0
1120.0
09
-De
c-8
7
08
-De
c-8
8
08
-De
c-8
9
08
-De
c-9
0
08
-De
c-9
1
07
-De
c-9
2
07
-De
c-9
3
07
-De
c-9
4
07
-De
c-9
5
06
-De
c-9
6
06
-De
c-9
7
06
-De
c-9
8
06
-De
c-9
9
05
-De
c-0
0
05
-De
c-0
1
05
-De
c-0
2
05
-De
c-0
3
04
-De
c-0
4
04
-De
c-0
5
04
-De
c-0
6
04
-De
c-0
7
03
-De
c-0
8
03
-De
c-0
9
03
-De
c-1
0
03
-De
c-1
1
02
-De
c-1
2
02
-De
c-1
3
02
-De
c-1
4
02
-De
c-1
5
01
-De
c-1
6
01
-De
c-1
7
01
-De
c-1
8
Gro
un
dw
ater
Lev
el R
L (m
)
Mine Dewatering Level
P2-1 in Andesite - Tip Level RL974.26m
P2-2 in Andesite - Tip Level RL1034.56m
P2-3 in Ignimbrite - Tip Level RL1073m
P2-4 in Boulder Alluvium - Tip Level RL1101m
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Piezometer Readings in Borehole P2
Ref. No: 8332Date: Jan 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure 10
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
700.0
720.0
740.0
760.0
780.0
800.0
820.0
840.0
860.0
880.0
900.0
920.0
940.0
960.0
980.0
1000.0
1020.0
1040.0
1060.0
1080.0
1100.0
1120.0
09
-De
c-8
7
08
-De
c-8
8
08
-De
c-8
9
08
-De
c-9
0
08
-De
c-9
1
07
-De
c-9
2
07
-De
c-9
3
07
-De
c-9
4
07
-De
c-9
5
06
-De
c-9
6
06
-De
c-9
7
06
-De
c-9
8
06
-De
c-9
9
05
-De
c-0
0
05
-De
c-0
1
05
-De
c-0
2
05
-De
c-0
3
04
-De
c-0
4
04
-De
c-0
5
04
-De
c-0
6
04
-De
c-0
7
03
-De
c-0
8
03
-De
c-0
9
03
-De
c-1
0
03
-De
c-1
1
02
-De
c-1
2
02
-De
c-1
3
02
-De
c-1
4
02
-De
c-1
5
01
-De
c-1
6
01
-De
c-1
7
01
-De
c-1
8
Gro
un
dw
ater
Lev
el R
L (m
)
Mine Dewatering Level
P8-1 in Andesite - Tip Level RL975.66m
P8-3 in Ignimbrite - Tip Level RL1092.9m
P8-4 in Boulder Alluvium - Tip Level RL1111.8m
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Piezometer Readings in Borehole P8
Ref. No: 8332Date: Jan 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure 11
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
940
960
980
1000
1020
1040
1060
1080
1100
1120
0 20 40 60 80 100 120 140 160
Pie
zom
ete
r Ti
p R
L (m
)
Head of Water (m)
P90
P91
P92
P93
P94
P95
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Piezometer Readings in Boreholes P90 - P95
Ref. No: 8332Date: Jan 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure 12
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
940
960
980
1000
1020
1040
1060
1080
1100
1120
0 20 40 60 80 100 120 140 160
Pie
zom
ete
r Ti
p R
L (m
)
Head of Water (m)
P100
P101
P102
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Piezometer Readings in Boreholes P100 - P102
Ref. No: 8332Date: Jan 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure 13
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
P
9
0
P
9
1
P
9
2
P
9
3
P
9
4
P
9
5
-1000E
0E
1000E
2000E
3000E
4000E
5000E
-2000E
2000N
1000N
0N
-1000N
3000N
T
R
I
O
F
A
V
O
N
A
M
O
O
N-
L
I
G
H
T
C
O
R
R
E
N
S
O
DAYBREAK
E
M
P
I
R
E
BM19B
19BB
17CB
17BB
17AB
34GC
2.04B
18EE
34H
18IB
18C
34AD
2.10
34BE
34C
BM34
11AC
10BC
18AB
10AB
2.11
18B
1.28B
2.08
2.09B
BM16
BM17A
34I
2.06
-280
-274
-258
-220
-183
-178
-161
-154
-152
-152
-150
-149
-138
-136
-130
-129
-125
-119
-118
-115
-114
-113
-112
-112
-107
-106
-103
-101
-94
19CB
A10B
20C
A11D
16BC
BM25
25E
10DB
21O
21DC
25D
25A
10CB
2.03
18F
34EB
12CE
2.02
1.28A
18G
20D
25B
34D
13AC
2A
25F
BM12
21N
25G
BM18
13BC
25CB
25H
25I
12DC
12AC
24I
15A
AP22A
24DC
20AC
21C
24L
15BC
20E
22F
24J
24E
12BC
24K
11BB
24AC
24B
BM13
1.10A
24G
24F
24H
21EB
4DB
BM24
BM2
21M
2BC
24CD
4B
20F
20BB
BM21
21BC
21K
30C
AP3
7CB
BM9B
26EE
26F
-255
-143
-139
-137
-131
-128
-125
-124
-123
-122
-122
-121
-120
-118
-118
-117
-116
-116
-114
-113
-113
-111
-111
-110
-110
-110
-109
-108
-108
-108
-107
-104
-103
-103
-102
-102
-101
-100
-99
-98
-97
-96
-95
-95
-94
-94
-94
-93
-92
-92
-92
-92
-91
-91
-91
-90
-90
-90
-89
-89
-88
-86
-84
-83
-83
-82
-80
-80
-79
-76
-74
-70
-69
-69
-68
-47
-39
23AB
2.14A
23C
22C
23B
BANK1
2HB
2.25
BARRY3
23D
22G
2.24
23E
BM23
MATAURA1
STAFORD
2.16
BARRY2
2.13
22E
22BC
2.15
23F
22H
MORTON
22M
22I
GW
CUBA
22L
21P
22A
2.28
22D
22J
1.06
2GB
21FB
2.26
BM22
21L
1.09B
21AC
2.29
30BB
26BE
BM15
21Q
SM822
21I
22K
26CE
21GC
2.31B
21J
15DB
7BB
27E
27KB
2.30
21HC
3.04
26AE
4.07
27N
3.01
4.08
27H
27G
4.05
3.02
4.09
27J
BM30
27F
26G
26H
27I
26PB
3.11A26R
30AB
3.09
27DC
26I
26Q
3.10A
BM26
27M
3.13
27L
27AB
27O
3.6A
2.41
34FC
2.19B
2.18
2.20
2.23
2.17A
BARRY8
2.21
1.05
2.22
15C
2.27
2.34
2.36
2.40B
4.02
2.33
4.03B
BM31
31BC
4.04
4.01C
31AC
29DB
26JB
26MB
31CC
3.25
29AC
29CE
3.24
29B
-124
-104
-103
-103
-102
-102
-100
-100
-99
-99
-98
-97
-97
-96
-94
-92
-92
-90
-90
-89
-86
-86
-84
-84
-83
-82
-81
-81
-81
-81
-78
-78
-78
-77
-76
-75
-74
-73
-70
-69
-68
-67
-66
-66
-64
-63
-63
-63
-60
-60
-58
-56
-55
-55
-54
-54
-54
-53
-50
-50
-49
-47
-45
-43
-42
-41
-41
-41
-40
-39
-38
-37
-37
-36
-36
-32
-32
-31
-31
-31
-31
-30
-30
-30
-29
-27
-27
-26
-23
-22
-22
-19
-19
-13
-8
-118
-113
-109
-101
-99 -94
-92
-87
-87
-86
-86
-84
-79
-74
-70
-56
-52
-47
-46
-45
-44
-41
-38
-36
-33
-33
-31
-25
-25
-23
-23
-17
-17
-12
-9
1.11B
2CE
14DB
1.07
A33C
14CB
2FC
14EA
1.08
14BC
4A
2DA
4EC
2EB
14FB
1K
3.03
7AC
1.12
1.04
1JB
BM14
1I
1SC
BM7
BM4
4FB
1C
3.12
33A
14AC
3.14
33F
33E
6A
1B
1FB
3.07
1O
1HC
1EB
33DB
1NB
1LC
BM6
1GB
1MD
1A
5C
3.15
1PA
1.01
AP2
33GA
1RA
1.14
BM1
33B
1QC
BM293.22A
3.05
33C
5BC
5AC
BM5
1.16
1D
-104
-76
-69
-55
-53
-51
-50
-50
-47
-46
-45
-42
-42
-41
-41
-40
-35
-34
-33
-33
-32
-28
-28
-27
-27
-27
-26
-26
-26
-25
-25
-24
-24
-23
-21
-21
-21
-20
-20
-19
-18
-18
-17
-17
-16
-15
-14
-13
-12
-12
-12
-12
-11
-11
-11
-10
-10
-9
-6
-4
-4
-3
-3
-3
-2
-2
-2
-1
AP100
1.26
2.05
31MD
31ND
31LC
1.25
31KC
31FC
2.35
31JD
31HC
31IC
1.21
31GC
1.22
31DD31PC
31QC
31EC
1VA
1.20A
1.24
1.23
31OD
AP2A
1.13
1.27B
1UA
27CD
3.30
1TB
3.26B
3.29
3.28A
1.17B
1.15
AP1
AP6
-93
-79
-79
-69
-66
-61
-58
-54
-53
-51
-47
-46
-46
-44
-44
-41
-36-36
-33
-30
-23
-22
-20
-20
-18
-18
-18
-12
-9
-9
-8
-5
-3
-3
-3
-2
-1
0
0
BLOCK-N
F16B
F11C
F26
F27B
F10B
F09A
F12C
F15C
F28B
F14C
F13C
F30B
F31B
F08A
F29B
F33
F32B
ITXCIVB
F04
F06
F02
F03
F05
FP1
TRIG24
TRIG22
-147
-145
-144
-140
-135
-128
-128
-126
-124
-122
-120
-119
-114
-113
-112
-111
-110
-106
-97
-96
-95
-94
-94
-92
-71
-41
-33
F22
BLOCK-S
-172
-166
F17B
F21
-184
-183
3.23
3.27B
3.21
3.16
3
4
4
12
57
AP20No2
1
BM20 Dist'd
18HC
New mark
1.02B
2.44 Dist'd
-475
F18 Dist'd
F23 Dist'd
F24 Dist'd
F20 Dist'd
-238
-230
-210
-204
F25 Dist'd
-178
F07 Dist'd
-148
1.02C
New Mark
Lost
1.03
Lost
1.03B
New Mark
26OB
New Mark26NC
New Mark
BM20A
-271
-332
2.09C
New mark
28AD
New mark
28AC
Lost
BARRY1
-102
BA
RR
Y4B
-103
F35B
BA
RR
Y6
BARRY5
-98
BARRY7
F34C
-130
ENGINEERING GEOLOGY LTD
OCEANA GOLD NZ LIMITED - WAIHI
Project Martha
Proposed Settlement Zones
Settlement in millimetres
Zone 7
Settlement
Zone 6
Settlement
Zone 5
Settlement
Zone 4
Settlement
Zone 3
Settlement
Zone 2
Settlement
Zone 1
Settlement
Zone
Figure 16
(2019)
Martha
55
65
95
160
260
340
540
500.0
600.0
700.0
800.0
900.0
1000.0
1100.0
1200.0
-0.10
-0.08
-0.06
-0.04
-0.02
0.00
0.02
0.04
May-1
988
May-1
989
May-1
990
May-1
991
May-1
992
May-1
993
May-1
994
May-1
995
May-1
996
May-1
997
May-1
998
May-1
999
May-2
000
May-2
001
May-2
002
May-2
003
May-2
004
May-2
005
May-2
006
May-2
007
May-2
008
May-2
009
May-2
010
May-2
011
May-2
012
May-2
013
May-2
014
May-2
015
May-2
016
May-2
017
Min
e D
ew
ate
rin
g R
L (
m)
Sett
lem
en
t (m
)
1TB AP1 AP2A 1UA 1VA 31ND
31OD 31PC 31QC 2.05 31FC 31JD
31DD 31EC 31GC 31HC 31IC 31KC
31LC 31MD 1.17B 1.20A 1.24 1.27B
1.25 1.22 1.23 1.13 2.35 28AD
3.16 3.23 3.26B 3.27B 3.28A 3.29
3.30 BM28/2 3.21 1.15 27CD ITXCIVB
Avg. Settlement Mine Dewatering Level
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Ground Settlement - Zone 1
Ref. No: 8332Date: Feb 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure 17
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
500.0
600.0
700.0
800.0
900.0
1000.0
1100.0
1200.0
-0.10
-0.08
-0.06
-0.04
-0.02
0.00
0.02
0.04
May-1
988
May-1
989
May-1
990
May-1
991
May-1
992
May-1
993
May-1
994
May-1
995
May-1
996
May-1
997
May-1
998
May-1
999
May-2
000
May-2
001
May-2
002
May-2
003
May-2
004
May-2
005
May-2
006
May-2
007
May-2
008
May-2
009
May-2
010
May-2
011
May-2
012
May-2
013
May-2
014
May-2
015
May-2
016
May-2
017
Min
e D
ew
ate
rin
g R
L (
m)
Sett
lem
en
t (m
)
14BC 14CB 14DB 1A 1B 1C
1D 1GB 1HC 1I 1JB 1K
1NB 1O 1XB 33A 33B 33C
33DB 33E 33F 33GA 4EC 4FB
5AC 5BC 5C 5DA 6A AP2
BM1 BM14 BM29 BM4 BM5 BM6
BM7 7AC 1MC 1.01 1EB 1QC
3.07 1RA 1SC 3.22A 14EA 1LC
1.02C 1.03 1.04 1.12 14FB 1FB
3.03 3.05 3.07 3.12 3.14 3.15
1.14 1.16 Avg. Settlement Mine Dewatering Level
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Ground Settlement - Zone 2
Ref. No: 8332Date: Feb 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
Figure 18
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
500.0
600.0
700.0
800.0
900.0
1000.0
1100.0
1200.0
-0.10
-0.08
-0.06
-0.04
-0.02
0.00
0.02
0.04
May-1
988
May-1
989
May-1
990
May-1
991
May-1
992
May-1
993
May-1
994
May-1
995
May-1
996
May-1
997
May-1
998
May-1
999
May-2
000
May-2
001
May-2
002
May-2
003
May-2
004
May-2
005
May-2
006
May-2
007
May-2
008
May-2
009
May-2
010
May-2
011
May-2
012
May-2
013
May-2
014
May-2
015
May-2
016
May-2
017
Min
e D
ew
ate
rin
g R
L (
m)
Sett
lem
en
t (m
)
29AC 29CE BM31 2FC 2.33 29B
29DB 4.03B 2.34 2.40B 26OB 3.24
4.04 31CC 31BC 31AC 4.01C 2.36
1.08 1.21 1.22 1.25 1.07 2CE
2DA 2EB 26NC 3.25 4.02 4A
14BC 14CB 14DB 14EA 14FB 15DB
A33C Avg. Settlement Mine Dewatering Level
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Ground Settlement - Zone 3
Ref. No: 8332Date: Feb 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
Figure 19
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
500.0
600.0
700.0
800.0
900.0
1000.0
1100.0
1200.0
-0.30
-0.25
-0.20
-0.15
-0.10
-0.05
0.00
0.05
May-1
988
May-1
989
May-1
990
May-1
991
May-1
992
May-1
993
May-1
994
May-1
995
May-1
996
May-1
997
May-1
998
May-1
999
May-2
000
May-2
001
May-2
002
May-2
003
May-2
004
May-2
005
May-2
006
May-2
007
May-2
008
May-2
009
May-2
010
May-2
011
May-2
012
May-2
013
May-2
014
May-2
015
May-2
016
May-2
017
Min
e D
ew
ate
rin
g R
L (
m)
Sett
lem
en
t (m
)
7BB 1.06 1.09B 2.13 2.14A 2.15 2.16
2.21 2.24 2.25 2.26 2.28 2.29 2.30
2.31B 21AC 21GC 21HC 22A 22BC 22C
22D 22E 23AB 23B 26AE 26BE 26CE
26G 26H 26I 27AB 27DC 27E 27F
27G 27H 27I 27J 27KB 27L 27M
27N 27O 2GB 2HB 3.01 3.02 3.04
3.09 3.10A 3.11A 3.13 3.6A 30AB 30BB
4.05 4.07 4.08 4.09 BM15 BM22 BM23
BM26 BM30 21FB 21J 21L 21I 21Q
21P 22G 22H 22I 22J 22K 22L
22M 23D 23C 23E 23F GW MATAURA1
Morton SM822 Stafford Bank1 Barry1 Barry2 Barry3
Cuba 1.05 1.11B 1.26 2.18 2.19B 2.20
2.22 2.23 2.27 2.41 15C 26F BM2
AP100 Barry4B Barry5 Barry6 Barry7 Barry8 Avg. Settlement
Mine Dewatering Level
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Ground Settlement - Zone 4
Ref. No: 8332Date: Feb 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
Figure 20
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
500.0
600.0
700.0
800.0
900.0
1000.0
1100.0
1200.0
-0.30
-0.25
-0.20
-0.15
-0.10
-0.05
0.00
0.05
May-1
988
May-1
989
May-1
990
May-1
991
May-1
992
May-1
993
May-1
994
May-1
995
May-1
996
May-1
997
May-1
998
May-1
999
May-2
000
May-2
001
May-2
002
May-2
003
May-2
004
May-2
005
May-2
006
May-2
007
May-2
008
May-2
009
May-2
010
May-2
011
May-2
012
May-2
013
May-2
014
May-2
015
May-2
016
May-2
017
Min
e D
ew
ate
rin
g R
L (
m)
Sett
lem
en
t (m
)
4B 4DB 7CB 10CB 10DB 11BB
12AC 12BC 12CE 12DC 13AC 13BC
15A 18F 18G 18HC 2.03 20AC
20BB 20C 21BC 21C 21DC 24B
24CD 24DC 25A 25B 25CB 2A
2BC 34D 34EB A10B A11D AP22A
AP3 BM9B BM12 BM13 BM18 BM21
BM25 24AC 1.10A 1.28A 16BC 30C
20D 20E 20F 21K 21O 21N
21M 24E 24F 24G 24H 24I
24J 24K 24L 25D 25E 25F
25G 25H 25I 22F 26EE 26PB
15BC 2.02 21EB 2.17A BM16 BM24
18B 26Q 26R Avg. Settlement Mine Dewatering Level
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Ground Settlement - Zone 5
Ref. No: 8332Date: Feb 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
Figure 21
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
500.0
600.0
700.0
800.0
900.0
1000.0
1100.0
1200.0
-0.50
-0.45
-0.40
-0.35
-0.30
-0.25
-0.20
-0.15
-0.10
-0.05
0.00
0.05
Ma
y-1
98
8
Ma
y-1
98
9
Ma
y-1
99
0
Ma
y-1
99
1
Ma
y-1
99
2
Ma
y-1
99
3
Ma
y-1
99
4
Ma
y-1
99
5
Ma
y-1
99
6
Ma
y-1
99
7
Ma
y-1
99
8
Ma
y-1
99
9
Ma
y-2
00
0
Ma
y-2
00
1
Ma
y-2
00
2
Ma
y-2
00
3
Ma
y-2
00
4
Ma
y-2
00
5
Ma
y-2
00
6
Ma
y-2
00
7
Ma
y-2
00
8
Ma
y-2
00
9
Ma
y-2
01
0
Ma
y-2
01
1
Ma
y-2
01
2
Ma
y-2
01
3
Ma
y-2
01
4
Ma
y-2
01
5
Ma
y-2
01
6
Ma
y-2
01
7
Min
e D
ew
ate
rin
g R
L (
m)
Sett
lem
en
t (m
)
10AB 17AB 17BB 18AB 18C 18EE
2.04B 2.06 2.08 34BE 34C 34H
34I BM17A BM34 34AD 18IB 1.28B
10BC 11AC 2.09C 2.10 2.11 34GC
19CB 34FC BM20 BM20A Avg. Settlement Mine Dewatering Level
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Ground Settlement - Zone 6
Ref. No: 8332Date: Feb 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
Figure 22
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
500.0
600.0
700.0
800.0
900.0
1000.0
1100.0
1200.0
-0.50
-0.45
-0.40
-0.35
-0.30
-0.25
-0.20
-0.15
-0.10
-0.05
0.00
0.05M
ay-1
988
May-1
989
May-1
990
May-1
991
May-1
992
May-1
993
May-1
994
May-1
995
May-1
996
May-1
997
May-1
998
May-1
999
May-2
000
May-2
001
May-2
002
May-2
003
May-2
004
May-2
005
May-2
006
May-2
007
May-2
008
May-2
009
May-2
010
May-2
011
May-2
012
May-2
013
May-2
014
May-2
015
May-2
016
May-2
017
Min
e D
ew
ate
rin
g R
L (
m)
Sett
lem
en
t (m
)
Settlement Zone 7
17CB 19BB BM19B Avg. Settlement Mine Dewatering Level
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Ground Settlement - Zone 7
Ref. No: 8332Date: Feb 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
Figure 23
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
500.0
600.0
700.0
800.0
900.0
1000.0
1100.0
1200.0
-0.30
-0.25
-0.20
-0.15
-0.10
-0.05
0.00
0.05
May
-19
88
May
-19
89
May
-19
90
May
-19
91
May
-19
92
May
-19
93
May
-19
94
May
-19
95
May
-19
96
May
-19
97
May
-19
98
May
-19
99
May
-20
00
May
-20
01
May
-20
02
May
-20
03
May
-20
04
May
-20
05
May
-20
06
May
-20
07
May
-20
08
May
-20
09
May
-20
10
May
-20
11
May
-20
12
May
-20
13
May
-20
14
May
-20
15
May
-20
16
May
-20
17
Min
e D
ew
ate
rin
g R
L (m
)
Sett
lem
en
t (m
)
4A
Mine Dewatering Level
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Ground Settlement of Marker 4A and Mine Dewatering Level
Ref. No: 8332Date: Feb 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure 24
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
File: 8332 Appendix A Final.docx.doc
APPENDIX A
TWO DIMENSIONAL DECOUPLED SEEPAGE AND DEFORMATION
NUMERICAL MODELLING
Our Ref:8332 25 May 2018 Page 1
File: 8332 Appendix A Final.docx
APPENDIX A
TWO DIMENSIONAL DECOUPLED SEEPAGE AND DEFORMATION
NUMERICAL MODELLING
1.0 INTRODUCTION
This memorandum summarises the assumptions and results of two-dimensional (2D)
seepage and deformation numerical modelling of the area to the east of the Martha Pit,
referred to as Waihi East. The modelling was undertaken to enable estimates of settlements
due to dewatering to RL770m associated with mining since 1989 and with Project Martha
which will involve dewatering down to RL500m from the currently consented level of
RL700m.
The analyses have been undertaken using Geostudio 2D finite element analysis (FEA)
programs, SEEP/W and SIGMA/W (Refs. 1 and 2). The SEEP/W model of the ground and
groundwater parameters was provided by GWS Ltd (Ref.3). Some small adjustments were
made to the model for deformation modelling.
2.0 SCOPE OF WORK
The scope of work has included:
i. Modelling of seepage and drawdown associated with dewatering of both single and
multiple veins to various levels using SEEP/W.
ii. Deformation analyses using SIGMA/W with changes in stress due to dewatering to
different levels predicted by the SEEP/W modelling.
iii. Comparison of the results of the numerical modelling with monitored settlements
3.0 SOIL PROFILE AND GROUND MODEL
Figure A1 provides the model geometry and the associated boundary conditions. The
location of this section is also shown in Figure A1. The model was constructed as four
layers. From the surface these layers were: younger volcanic rocks, weathered andesite,
and undisturbed andesite comprising higher permeability (K) andesite and lower K
andesite. The higher K and lower K andesite are both referred to as andesite rock mass in
this document. The seepage modelling parameters within the GWS model have not been
altered. The depth of andesite extended to RL400 in the GWS model. We have extended
down to RL255. This is conservative for estimating deformations.
The parameters summarised in Table A1 have been adopted for SIGMA/W deformation
analyses. These parameters are generally consistent with the parameters adopted in PSM's
report (Ref.1). The only difference is we have adopted a Young's modulus of 2,000MPa for
the weathered andesite. This number is only important for modelling settlements from
January 1989 to December 1999. The settlements since December 1999 are believed to be
mostly associated with the undisturbed andesite rock mass.
Our Ref:8332 25 May 2018 Page 2
File: 8332 Appendix A Final.docx
TABLE A1 Material Deformation Parameters
Unit Unit Weight
(kN/m3)
Young's Modulus
(MPa)
Poisson's
Ratio
Younger Volcanics 25 8000 0.2
Weathered Andesite 20 2000 0.2
Andesite -Undisturbed (both
Higher K and Lower K)
27 8700 0.2
4.0 MODELLING AND RESULTS
Decoupled seepage and deformation analyses using SEEP/W and SIGMA/W have been
undertaken for three stages of groundwater drawdown. The SEEP/W model initially
calculates the change in pressure at each stage of groundwater drawdown. The SIGMA/W
model then calculates the ground deformation that is caused by the change in pressure.
4.1. Seepage Modelling
The SEEP/W model was used to undertake steady state seepage analyses for three stages of
groundwater dewatering. The stages of the modelling are shown in Figure A2 and detailed
described below.
Stage 1. Undertake groundwater dewatering to the Weathered Andesite (at approximately
RL975 at it deepest). This approximately represents dewatering from January
1989 to December 1999.
Stage 2. Undertake groundwater dewatering from RL975 to RL770. This approximately
represents dewatering from December 1999 to November 2017.
Stage 3. Undertake groundwater dewatering from RL770 to RL500. This approximately
represents dewatering from November 2017 to 2031 (estimate ending time for
Project Martha).
The average rate of groundwater drawdown for Stage 3 is greater than previous. However,
we assume that dewatering of the andesite rock mass will achieve steady state conditions
with the proposed drawdown rates that are shown in Figure A2.
Drawdown analyses for both single vein and multiple veins have been carried out. The
results are presents in Figure A3 to A8. Figures A3 to A5 show the results of modelling for
a single vein for Stages 1, 2 and 3 respectively. Figures A6 to A8 show the results of
modelling for multiple veins.
4.2. Settlement Modelling
The SIGMA/W modelling has been undertaken to calculate the deformation induced by the
pressure change associated with each stage of groundwater dewatering. The results are
shown in Figures A9 to A14. Figures A9 to A11 show the results of modelling for a single
vein for Stages 1, 2 and 3 respectively. Figures A12 to A14 show the results of modelling
for multiple veins.
Seven settlement zones have been identified in the Waihi area in which measured
settlements are relatively consistent. The modelling covers a section through Martha East
Our Ref:8332 25 May 2018 Page 3
File: 8332 Appendix A Final.docx
which is covered mostly by Zones 4 and 5. Comparisons of the predicted settlements
against measured settlements in Zones 4 and 5 are shown in Figures A15 and A16
respectively. Figures A17 and A18 show the ground surface settlements profiles for Stages
2 and Stage 3 of the model respectively. Results are shown for both single and multiple
veins. The estimated average settlements are summarised in Table 2. These are the average
of the settlements across the whole profile being modelled.
TABLE A2 Estimated Settlements
Stage
Single Vein Multiple Veins
Average
Settlement
(mm)
Cumulative
Settlement
(mm)
Average
Settlement
(mm)
Cumulative
Settlement
(mm)
1 23 23 23 23
2 89 112 152 175
3 26 138 66 241
The average modelled settlements for Stage 1 are 23mm. The average modelled
settlements for Stage 2 are 89mm for a single vein and 152mm for multiple veins. For
Stage 3 the average modelled settlements are 26mm for a single vein and 66mm for
multiple veins. The cumulative settlements are also provided in Table 2.
The modelling allows estimation of maximum ground surface tilts. They are summarised
in Table 3. They have been obtained by selecting the maximum tilt from the surface
profiles shown in Figures A17 and A18.
TABLE A3 Maximum Tilts
Stage Tilts
Single Vein Multiple Veins
1 1 in 8,000 1 in 8,000
2 1 in 10,000 1 in 9,000
3 1 in 30,000 1 in 18,000
1 and 2 1 in 5,500 1 in 4,600
1, 2 and 3 1 in 4,600 1 in 3,800
The estimated maximum tilts are associated with the multiple vein model and for Stages 1,
2 and 3 are 1 in 8,000, 1 in 4,600 and 1 in 3,800 respectively. Figure A17 show the
incremental change in tilt from Stage 2 to Stage 3 is small. The measured tilts above the
Correnso underground mine (which is largely within Zones 4 and 5) are generally smaller
than the maximum tilt predicted by numerical modelling of Stages 1 and 2 (1 in 4,600).
This indicates the numerical model is conservative.
5.0 DISCUSSION
The estimated settlements at the ground surface due to groundwater dewatering from
RL975 to RL770 (Stage 2) are summarised in Table 2. They are 89mm for a single vein
and 152mm for multiple veins. The monitored settlements in Zones 4 and 5 are lower, 38
to 68mm on average. The possible explanations for this difference are:
Our Ref:8332 25 May 2018 Page 4
File: 8332 Appendix A Final.docx
1. The adopted rock mass stiffness (Young's modulus) for the undisturbed andesite may
be too low especially for andesite at greater depth.
2. The andesite rock mass has not fully depressurised to steady state condition.
Irrespective of the above reasons the results indicate that application of the numerical
model to estimate deformation induced by dewatering from RL770 to RL500 (Stage 3) is
likely to be conservative.
The results shown in Figures A17 and A18 and Table 2 indicate that the estimated ground
surface surficial settlements in Stage 3 are significantly less than Stage 2. This is because
of two reasons,
1. Soil arching effect reflects less surficial settlement due to deeper and more localised
groundwater dewatering
2. The effective depth of andesite rock mass that are affected by drawdown reduces with
increase in drawdown depth. The effective thickness affected by groundwater
drawdown for Stages 2 and 3 are 720m (RL975 to RL255) and 515m (RL770 to
RL255) respectively.
The tilts arising from settlement due to dewatering summarised in Table 3 show that the
incremental tilt due to dewatering to RL500m are small. The maximum tilt for multiple
veins is 1 in 3,800 which is well below the level that would give rise to any concerns with
damage to structures or infrastructure.
6.0 SUMMARY
The numerical modelling provides useful insight into the comparative settlements
associated with different stages of dewatering and provides estimates of ground surface tilt.
The results show that settlements due to groundwater dewatering from RL770m to
RL500m (Stage 3) are lower compared to dewatering from RL975m to RL770m (Stage 2).
This is because groundwater drawdown and associated incremental stress in the rock mass
is localised around the veins. It results in arching effects and lower settlements than if the
rock mass was fully dewatered. Also, with dewatering from RL770m to RL500m the depth
of rock mass that is affected by drawdown is less than Stage 2.
The numerical modelling allows estimation of ground surface tilts. The estimated
maximum tilt following dewatering to RL500m is 1 in 3,800. This is well below the level
that would give rise to any concerns with damage to structures or infrastructure. It is also
considerably less than 1 in 1,000 which is the current trigger for notification of the
Waikato Regional Council and for instigating additional monitoring.
The modelled section is for Waihi East which is largely covered by settlement Zones 4 and
5. However, the comparative results between Stage 2 and 3 would apply to the other
settlement zones.
SEEP/W Model
SIGMA/W Model
SEEP/W and SIGMA/W Model Figure A1
400.0
500.0
600.0
700.0
800.0
900.0
1000.0
1100.00
9-D
ec-
87
08
-De
c-8
8
08
-De
c-8
9
08
-De
c-9
0
08
-De
c-9
1
07
-De
c-9
2
07
-De
c-9
3
07
-De
c-9
4
07
-De
c-9
5
06
-De
c-9
6
06
-De
c-9
7
06
-De
c-9
8
06
-De
c-9
9
05
-De
c-0
0
05
-De
c-0
1
05
-De
c-0
2
05
-De
c-0
3
04
-De
c-0
4
04
-De
c-0
5
04
-De
c-0
6
04
-De
c-0
7
03
-De
c-0
8
03
-De
c-0
9
03
-De
c-1
0
03
-De
c-1
1
02
-De
c-1
2
02
-De
c-1
3
02
-De
c-1
4
02
-De
c-1
5
01
-De
c-1
6
01
-De
c-1
7
01
-De
c-1
8
01
-De
c-1
9
30
-No
v-2
0
30
-No
v-2
1
30
-No
v-2
2
30
-No
v-2
3
29
-No
v-2
4
29
-No
v-2
5
29
-No
v-2
6
29
-No
v-2
7
28
-No
v-2
8
28
-No
v-2
9
28
-No
v-3
0
28
-No
v-3
1
27
-No
v-3
2
27
-No
v-3
3
27
-No
v-3
4
Gro
un
dw
ater
Lev
el R
L (m
)Monitored Dewatering Level
Inferred Dewatering Level of Project Martha
Stage 3
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Mine Dewatering Level
Ref. No: 8332Date: May 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Figure A2
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, Albany, Auckland
Stage 1 Stage 2
SEEP/W Model
SEEP/W Steady State Pressure Head Distribution, Unit: metre
Single Vein Drawdown Stage 1 SEEP/W Model and Results Figure A3
SEEP/W Model
SEEP/W Steady State Pressure Head Distribution, Unit: metre
Single Vein Drawdown Stage 2 SEEP/W Model and Results Figure A4
SEEP/W Model
SEEP/W Steady State Pressure Head Distribution, Unit: metre
Single Vein Drawdown Stage 3 SEEP/W Model and Results Figure A5
SEEP/W Model
SEEP/W Steady State Pressure Head Distribution, Unit: Metre
Multi Veins Drawdown Stage 1 SEEP/W Model and Results Figure A6
SEEP/W Model
SEEP/W Steady State Pressure Head Distribution, Unit: metre
Multi Veins Drawdown Stage 2 SEEP/W Model and Results Figure A7
SEEP/W Model
SEEP/W Steady State Pressure Head Distribution, Unit: metre
Multi Veins Drawdown Stage 3 SEEP/W Model and Results Figure A8
SIGMA/W Single Stage Vertical Settlements, Unit: metre
SEEP/W Steady State Pressure Head Distribution, Unit: metre (for reference)
Single Vein Drawdown Stage 1 SIGMA/W Settlements Figure A9
SIGMA/W Single Stage Vertical Settlements, Unit: metre
SEEP/W Steady State Pressure Head Distribution, Unit: metre (for reference)
Single Vein Drawdown Stage 2 SIGMA/W Settlements Figure A10
SIGMA/W Single Stage Vertical Settlements, Unit: metre
SEEP/W Steady State Pressure Head Distribution, Unit: metre (for reference)
Single Vein Drawdown Stage 3 SIGMA/W Settlements Figure A11
SIGMA/W Single Stage Vertical Settlements, Unit: metre
SEEP/W Steady State Pressure Head Distribution, Unit: metre (for reference)
Multi Veins Drawdown Stage 1 SIGMA/W Settlements Figure A12
SIGMA/W Single Stage Vertical Settlements, Unit: metre
SEEP/W Steady State Pressure Head Distribution, Unit: metre (for reference)
Multi Veins Drawdown Stage 2 SIGMA/W Settlements Figure A13
SIGMA/W Single Stage Vertical Settlements, Unit: metre
SEEP/W Steady State Pressure Head Distribution, Unit: metre (for reference)
Multi Veins Drawdown Stage 3 SIGMA/W Settlements Figure A14
500.0
600.0
700.0
800.0
900.0
1000.0
1100.0
1200.0
-0.30
-0.25
-0.20
-0.15
-0.10
-0.05
0.00
0.05
May-1
988
May-1
989
May-1
990
May-1
991
May-1
992
May-1
993
May-1
994
May-1
995
May-1
996
May-1
997
May-1
998
May-1
999
May-2
000
May-2
001
May-2
002
May-2
003
May-2
004
May-2
005
May-2
006
May-2
007
May-2
008
May-2
009
May-2
010
May-2
011
May-2
012
May-2
013
May-2
014
May-2
015
May-2
016
May-2
017
May-2
018
May-2
019
May-2
020
May-2
021
May-2
022
May-2
023
May-2
024
May-2
025
May-2
026
May-2
027
May-2
028
May-2
029
May-2
030
May-2
031
May-2
032
May-2
033
May-2
034
Min
e D
ew
ate
rin
g R
L (
m)
Sett
lem
en
t (m
)
7BB 1.06 1.09B 2.13 2.14A2.15 2.16 2.21 2.24 2.252.26 2.28 2.29 2.30 2.31B21AC 21GC 21HC 22A 22BC22C 22D 22E 23AB 23B26AE 26BE 26CE 26G 26H26I 27AB 27DC 27E 27F27G 27H 27I 27J 27KB27L 27M 27N 27O 2GB2HB 3.01 3.02 3.04 3.093.10A 3.11A 3.13 3.6A 30AB30BB 4.05 4.07 4.08 4.09BM15 BM22 BM23 BM26 BM3021FB 21J 21L 21I 21Q 21P 22G 22H 22I 22J 22K 22L 22M 23D 23C 23E 23F GW MATAURA1 MortonSM822 Stafford Bank1 Barry1 Barry2Barry3 Cuba 1.05 1.11B 1.262.18 2.19B 2.20 2.22 2.232.27 2.41 15C 26F BM2AP100 Barry4B Barry5 Barry6 Barry7Barry8 Avg. Settlement SIGMA/W Single Vein Avg SIGMA/W Multiple Veins Avg Mine Dewatering LevelInferred Dew Lvl for Martha
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Comparison of SIGMA/W Settlement with Observed Settlement - Zone 4
Ref. No: 8332Date: May 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
Figure A15
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
500.0
600.0
700.0
800.0
900.0
1000.0
1100.0
1200.0
-0.30
-0.25
-0.20
-0.15
-0.10
-0.05
0.00
0.05
May-1
988
May-1
989
May-1
990
May-1
991
May-1
992
May-1
993
May-1
994
May-1
995
May-1
996
May-1
997
May-1
998
May-1
999
May-2
000
May-2
001
May-2
002
May-2
003
May-2
004
May-2
005
May-2
006
May-2
007
May-2
008
May-2
009
May-2
010
May-2
011
May-2
012
May-2
013
May-2
014
May-2
015
May-2
016
May-2
017
May-2
018
May-2
019
May-2
020
May-2
021
May-2
022
May-2
023
May-2
024
May-2
025
May-2
026
May-2
027
May-2
028
May-2
029
May-2
030
May-2
031
May-2
032
May-2
033
May-2
034
Min
e D
ew
ate
rin
g R
L (
m)
Sett
lem
en
t (m
)
4B 4DB 7CB 10CB 10DB
11BB 12AC 12BC 12CE 12DC
13AC 13BC 15A 18F 18G
18HC 2.03 20AC 20BB 20C
21BC 21C 21DC 24B 24CD
24DC 25A 25B 25CB 2A
2BC 34D 34EB A10B A11D
AP22A AP3 BM9B BM12 BM13
BM18 BM21 BM25 24AC 1.10A
1.28A 16BC 30C 20D 20E
20F 21K 21O 21N 21M
24E 24F 24G 24H 24I
24J 24K 24L 25D 25E
25F 25G 25H 25I 22F
26EE 26PB 15BC 2.02 21EB
2.17A BM16 BM24 18B 26Q
26R Avg. Settlement SIGMA/W Single Vein Avg SIGMA/W Multiple Veins Avg Mine Dewatering Level
Inferred Dew Lvl for Martha
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
OCEANA GOLD (NEW ZEALAND) LTDPROJECT MARTHA
Comparison of SIGMA/W Settlement with Observed Settlement - Zone 5
Ref. No: 8332Date: May 2018Drawn: CW
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
Figure A16
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054, AlbanyPh (09) 4862546 Fax (09) 4862556
Engineering Geology LtdUnit 7C, 331 Rosedale Rd, PO Box 301054,
SIGMA/W Vertical Surficial Settlements, Unit: metre
SIGMA/W Model
SIGMA/W Surficial Settlements (Cumulative) Figure A17
SIGMA/W Vertical Surficial Settlements, Unit: metre
SIGMA/W Model
SIGMA/W Surficial Settlements Stage 3 Figure A18