project management report final updated

Upload: harjot-kaur

Post on 06-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Project Management Report Final Updated

    1/15

    Project ManagementReportFaculty of Business and Law

    2011

  • 8/3/2019 Project Management Report Final Updated

    2/15

    Faculty of Business and Law

    2

    Table of Contents

    1. Introduction to task 1 .................................................................................................................. 3

    1.1. The Network Diagram ........................................................................................................ 3

    1.2. Determining the timing of activities and the total float ........................................................ 4

    1.3. Determination of project duration and its critical path ......................................................... 5

    1.4. Determining the earliest finish date of the given project ...................................................... 5

    1.5. Effect of delayed activities in the project duration............................................................... 5

    1.5.1. Delay in activity B by 2 days ...................................................................................... 5

    1.5.2. Delay in activity P by 2 days....................................................................................... 5

    1.5.3. Delay in activity O by 1 day........................................................................................ 5

    1.6. Limitations of network diagrams ........................................................................................ 5

    2. Introduction to task 2 ................................................................................................................. 6

    2.1. Project management process.................................................................................................. 6

    2.1.1. Step I: Concept and Initiation...................................................................................... 7

    2.1.2. Step II: Design and Development................................................................................ 9

    2.1.3. Step III: Implementation ........................................................................................... 10

    2.1.4. Step IV: Commission / Termination .......................................................................... 11

    2.2. Problems concerned with project management ...................................................................... 11

    2.2.1. Leadership problems ...................................................................................................... 11

    2.2.2. Administration problems ............................................................................................ 13

    2.2.3. Control problems ............................................................................................................ 13

    Bibliography.................................................................................................................................... 15

  • 8/3/2019 Project Management Report Final Updated

    3/15

    Faculty of Business and Law

    3

    1. Introduction to task1

    Juron Ltd. is a leading merchandiser in the sports market and is well known for supplying

    quality products including training shoes, t-shirts, tennis racquets and soccer balls.

    The company has received a fresh order of supplying a new range of soccer boots to the

    sector.

    1.1.The Network DiagramThe Network Diagram as per table 1

    Figure 1.1 Source: Author (2011)

  • 8/3/2019 Project Management Report Final Updated

    4/15

    Faculty of Business and Law

    4

    1.2.Determining the timing of activities and the total floatThe timing of an activity can be judged through understanding the status of completion of the

    preceding activity. For example in the above activity chart, B succeeds A (Aronson, 2008).

    Therefore (A) (B).

    This indicates that activity B can be initiated only once activity A finishes. So A is critical for

    B. Thus the timing for B would start after the completion of A and all such other activities

    critical for starting activity B. Here, we have taken only activity A to be the critical activity

    for B. However in real life scenarios there are numerous activities to be undertaken and

    completed before the next specified activity begins. Therefore the timing for such activity

    starts only once all preceding activities have been taken up and completed (Aronson, 2008).

    Total float is the time of delay that can be allowed in a specific activity after its earliest start

    date so as to not let this delay affect the project duration. This means that even if the specified

    activity starts after earliest start + total float days the projects still finishes on time (Gupta,

    2008).

    Mathematically,

    Total float = Early start Late finish

  • 8/3/2019 Project Management Report Final Updated

    5/15

    Faculty of Business and Law

    5

    1.3. Determination of project duration and its critical pathThe duration of the project can be determined by calculating the early finish time of the last

    activity. The last day of the project determines project completion and the number of days

    taken to reach there since the beginning is the duration of the project (Harold, 2009).

    Critical path is such a chain of activities, which if delayed, would affect the duration of the

    project. The critical activities of the above scenario include the following chain in the same

    sequence:

    In other words the shortest duration of the project is called the critical path and thus the total

    float of all activities that is, of the entire path equals zero (Heerkens, 2007).

    1.4.Determining the earliest finish date of the given projectEarliest finish of the project = Earliest start of the last activity + duration of the last activity

    (Kerzner, 2009).

    If the project starts on the 16th

    ofJanuary, it finishes on the 82nd

    day of its start. Considering a

    five day working week, its finishes on the 12th

    of May.

    1.5.Effect of delayed activities in the project duration1.5.1. Delay in activity B by 2 daysIf activity B is delayed by 2 days the, it would not affect the duration of the project because it

    has a float of 4 days, which means even if it get delayed by 4 days, it would not affect the

    timely completion of the project.

    1.5.2. Delay in activity P by 2 daysSince activity P is a critical activity the project will get delayed by 2 days.

    1.5.3. Delay in activity O by 1 daySince activity O is a critical activity the project will get delayed by 1 day.

    1.6.Limitations of network diagrams

  • 8/3/2019 Project Management Report Final Updated

    6/15

    Faculty of Business and Law

    6

    a) There could be potentially hundreds of thousands of activities involved in projectsthat need to be measured do determine the criticality of the project duration. Network

    diagrams lack that scalability required to design such activity chart.

    b) If done without usage of software, the diagrams can go haywire- requiring largeamount of time, energy and other resources in the process.

    c) Once out of control and unruly, these diagrams become useless until redone all overagain, utilising all the energy once again only to realise it may be required to be re-

    done (Walker, 2010).

    2. Introduction to task 2J

    imaga Ltd, started in 2005, is a SME involved in the business of specialisation in the designand supply of promotional brochures and serve mainly the local authorities, other SMEs, and

    sometimes by large global organisations.

    The stated problem

    Jimaga Ltd, is undergoing an expansion strategy of opening of a new office building which

    will target at and respond to business from large global organisations.

    The project is to be completed at the given time and within the given budget

    2.1. Project management process

    The task involves managing the entire project of opening the new building ofJimaga Ltd. The entire

    task is broken down into four basic phases of project management (Lock, 2007). These include:

    Step I: Concept or initiation

    Concept or initiation, where the project starts off by the managers doing the feasibility study

    of the need that the project will fulfil. This step will look into the budget provided for the

    opening of the new building and the timeline that has been decided.

    Step II: Design and development

    Design and development, where the plans for implementation of the project will be scheduled

    and timelines and costs of each activity involved will be decided.

  • 8/3/2019 Project Management Report Final Updated

    7/15

    Faculty of Business and Law

    7

    Step III: Implementation

    The implementation phase, where the project will be implemented as the plan agreed, that is

    the building will be thrown opne for official use and the shortcomings and smooth operations

    will be looked at

    Step IV: Commission or termination

    This is the commission or termination phase where the building has opened and is

    functioning smoothly and the project will thus close formally.

    Diagrammatically the project life cycle can de depicted as per the following figure:

    Project life cycle

    Figure 1.4 Source: (Meredith, 2008)

    2.1.1. Step I: Concept and InitiationThe following steps are to be taken in concept phase:

    y Data gathering

  • 8/3/2019 Project Management Report Final Updated

    8/15

    Faculty of Business and Law

    8

    Data gathering is done on the following parameters and the results have been depicted in

    the following table:

    Data gathering table

    Data gathering points Data

    Number of employees who will use the building 100

    Processes that will be carried out of the building y Salesy Operations

    Functionality required from the building y Sales orientedy Operations oriented

    The time by which the project needs to be

    completed

    50 days

    The budget or the cost within which the project

    is to be completed

    8750

    Figure 1.5 Source Author (2011)

    y Identifying needThe building is to be thrown open for use in 50 days from now and is to be completed

    within the budget of 8750.

    yEstablishing of goals and objectives, understanding the basic economics, drawingfeasibility of the projects, knowing stakeholders, finding out the required skill set and

    identifying and putting together the potential team are the next crucial steps to be

    undertaken to carry on the project.

    a) The objectives of the project are clearly stated in the need that has beenidentified.

    b) The management and the global sales and operations team are the stakeholders ofthe project.

    c) The team required to carry on the project includes:1) Cleaners2) Painters3) Electrical fitters4) Other fitters5) Final cleaners

  • 8/3/2019 Project Management Report Final Updated

    9/15

    Faculty of Business and Law

    9

    6) Security surveysd) The feasibility study will be done on basis of the following questions being asked

    and the feasibility will depend on the responses:

    Project Feasibility Study

    Feasibility characteristics Response

    How realistic is it to expect that the

    project can meet the

    stated objectives?

    The project is to open the building for

    office use, thus realistic

    How realistic are the project scope,

    budget and time

    requirements?

    The building is to be thrown open in 50

    days in 8750, so realistic

    Are sufficient funds available to

    complete the project?

    Yes the funds are sufficient

    Does the organisation have thetechnical expertise to

    accomplish the project?

    Since it is outsourced to technicians

    who are easy to find, so required

    technical skills are easily available

    Figure 1.7 Source Author (2011)

    y Guestimate resourcesFollowing resources will be required to complete the project

    1. Manpower2. Material3. Money

    y Identifying alternatives, presenting proposal and obtaining approval for next phase area few more steps to be taken care of in this phase (Taha, 2007).

    2.1.2. Step II: Design and Development

    y Appoint key team membersAt present the company employs

    i) 1 General Manager,ii) 2 Assistant Managers,iii)3 Administration staff,

  • 8/3/2019 Project Management Report Final Updated

    10/15

    Faculty of Business and Law

    10

    iv)5 sales staff, andv) 6 warehouse staff.And the task mentions that the staffing structure would be the mirror structure of the

    existing structure.

    y Develop scope baseline, Work breakdown structure, budget and activity chartScope Baseline, WBS and Activity Chart

    Figure 1.8 Source Author (2011)

    y Conducting studies, assessing risks, confirming justification, presenting project briefand obtaining approval to proceed are some of the other qualitative aspects of the step

    that would require to be carried out (Murthy, 2007).

    2.1.3. Step III: Implementationy Setup has to take place in the sense that once the development phase is over and the

    entire layout of the project has been made, the implementation begins, where the

    actual work starts and the laid out activities are carried out in the pre-determined

    sequence.

    y The team has to be kept motivated throughout the implementation of the project. It isduring the implementation phase that the key personal decide to leave the project in

    between. Most plausible reasons of doing so involve dissatisfaction with work, feeling

    Activity Nomenclature Dependence Duration Budget

    Cleaning A - 10 days 1000

    Electrical

    fittings

    B A 14 days 2500

    Other fittings C A 5 days 2750

    Set-up D B, C 10 days 500

    Final touch

    up

    E D 4 days 500

    Cleaning F F 7 days 1500

  • 8/3/2019 Project Management Report Final Updated

    11/15

    Faculty of Business and Law

    11

    over-burdened, de-motivated due to company policies or else some personal reasons.

    Thus, the manager requires people skills here to make things happen fro his team in

    every sense of the word.

    y Detail technical requirements are set and have to be implemented as per specification.Since technical requirements are critical to functioning of the business, it is utmost

    important to take care of the working of these technicalities.

    y Procurement of goods and services and direct monitoring when required, will have tobe implemented. Other than that regular forecast and controlling measures will have

    to be carried out. Forecast and control involve scope of the project, quality, time and

    cost.

    y Resolution of problems will also have to be carried out as and when they occur.

    2.1.4. Step IV: Commission / Terminationy Finalise product(s)

    Now when the building is complete and ready in time to be fully functional, it has to

    be reviewed according to the standard of quality which have been set earlier.

    y Review and acceptance by the administration and the facilities department of thecompany will have to be done. The officials of facilities survey the entire structure to

    understand whether the completed project meets all requirements and is comfortable

    enough from operational point of view.

    y Documents are prepared for completion of the project and for commissioning of thesame. The building layout and its safety standards are displayed to the facilities

    department.

    y The reusable resources used in the project are released from the project and updationare made with the internal operations management department.

    2.2. Problems concerned with project management

    2.2.1.Leadership problems

    a) Key staff leaving the project: In times when key staff leaves the project, it becomesvery difficult to carry on with such critical activities that cannot be carried out without

    are expertise and know-how. These types of manpower problems do not have any

  • 8/3/2019 Project Management Report Final Updated

    12/15

    Faculty of Business and Law

    12

    contingency plans for them, since contingency here would means having an expert in

    back-up which is additional cost with no output. Also there is all probability that this

    resource would never be used (Wysocki, 2011).

    b) Motivational levels go down: While the project is at its peak time and all resourceshave been applied to take the project to its full swing, some of the workers and

    managers might get over-burdened with the stressful situation of short deadlines and

    scare resources, thus affecting their level of motivation of carrying out work any

    longer. The managers role here, is that of a mentor, who helps de-motivated staff to

    look at the bigger picture and find ways to keep them going. The manager can use the

    principle of Maslows Hierarchy of Needs to keep the employees motivated (Pride,

    Hughes and Kapoor, 2011).

    Maslows Hierarchy of Needs

    Figure 1.9 Source: (Lock, 2007)

    c) Information received too late so corrective action takes time: Lets imagine a scenariowhere workers suddenly stop coming to work one day. The information reaches the

    project manager and he tries to find out the main problem. Now he comes to know

    that the workers have not been working to their fullest capacity since the last 3 days

    and have decided to leave the project now since they have been demanding higher

    wages and their supervisors have been turning a deaf ear towards them. This is a

    classic example of a scenario where the information has reached the manager too late.

  • 8/3/2019 Project Management Report Final Updated

    13/15

    Faculty of Business and Law

    13

    3 days have already passed since the workers have not worked and this is the 4th

    day.

    In case it takes 2 more days to solve their issues, 6 days are lost in the process. Had

    the information reached the manager on the first day itself, it would have been easier

    to tackle it and would also have not resulted in lost output (Walker, 2010).

    2.2.2. Administration problems

    a) Some estimates overlooked: There may be instances were estimates of items havebeen overlooked. This involves especially large projects with lots of fine processes

    and materials required which could get missed out at the project cost/budget

    estimation level. Although they might seem small at their individual levels, once

    added up, they tend to become a substantial amount and could affect the overall

    project cost significantly (Daft, 2011).

    b) Policies or legislation of implementation change: Internal policies of the managementcould change during the project duration. Other than this external policy and

    legislative environment could also change due to which the project could get affected-

    delayed or else completely abandoned. These typical scenarios will have to be thought

    about and contingency plans will have to be made before-hand so as to cope up with

    tem with ease.

    c) Cost of materials change thus budget of project gets affected: All materials are not bought together at the onset of a project, but are ordered and bought as and when

    required for specific activities. This involves a problem of price change. That is prices

    of materials if change, will affect the budget of the project. Therefore, a +-10%

    contingency in costs should always be kept so as to swallow the changes in prices

    (Dow, 2010).

    d) Contingency not available, so project gets affected: When cases arise of nocontingency available, for example lead time of supply of material not taken into

    consideration and order arriving 3 days after the material lasted out, affects the

    timeline of the project, specially if such errors occur (Meredith, 2008).

    2.2.3. Control problems

    a) Meeting quality specifications: All along the project, timely delivery and budget arethe more important constraints for the delivery manager. In such cases, quality might

    be sacrificed for timely delivery of the project or else in a bid to stay within the

  • 8/3/2019 Project Management Report Final Updated

    14/15

    Faculty of Business and Law

    14

    budgeted costs. These constraints are contrary to the constraint of quality. Now the

    challenge before the project manager is to fulfil all constraints (Lock, 2007).

    Quality is a qualitative constraint and thus its measurement is tough. The project

    manager will have to develop benchmarks against which quality can be judged. Apart

    from this, each activity could have different benchmark standard of quality,

    depending on its type. The manager will have to take care of all these aspects when

    measuring quality (Harold, 2009).

    b) Control plans need constant updating and revision in terms of being accurate andrealistic. But this update has to be undertaken only by managers authorised to do so.

    Ensuring that progress, expenditure and scope of the performance are all as per the

    expectations of the client is the biggest hurdle in completion of the project.

    Information regarding these parameters has to be collected electronically, manually,

    through meetings and on-site survey (Heerkens, 2007).

  • 8/3/2019 Project Management Report Final Updated

    15/15

    Faculty of Business and Law

    15

    Bibliography

    Aronson, J.E. (2008) Operations Research: Methods, Models, And Applications, Texas:

    Information Age Pub Inc.

    Daft, R.L. (2011) Understanding Management, 7th

    edition, Mason: South-Western Cengage

    Learning.

    Dow, W. (2010)Project Management Communications Bible, John Wiley and Sons:

    Chicago.

    Gupta, P.K. (2008) Operations Research, New Delhi: S Chand & Company ltd.

    Harold, K. (2009)Project management : Case Studies, 3rd

    edition, Hoboken: Wiley.

    Heerkens, G. (2007)Project management : 24 lessons to help you master any project, New

    York: McGraw-Hill.

    Kerzner, H. (2009)Project Management A Systems Approach to Planning, Scheduling, andControlling, New Jersey: John Wiley & Sons.

    Lock, D. (2007)Project Management, Burlington: Ashgate.

    Meredith, J.R. (2008)Project management : a managerial approach, 7th

    edition, Hoboken,

    N.J: John Wiley.

    Murthy, R. (2007) Operations Research, New Delhi: New Age International.

    Pride, W.M., Hughes, R.J. and Kapoor, J.R. (2011)Business, 11th edition, Mason: South-

    Western Cengage Learning.

    Taha, H. (2007) Operations Research : An Introduction, Upper Saddle River, N.J.: Pearson

    Education.

    Walker, E. (2010) The Problems with Project Management, Chicago: McGraw Hill Prof.

    Wysocki, R.K. (2011)Effective Project Management : Traditional, Agile, Extreme, 6th

    edition, Indianapolis: Wiley.