project management planning: time and cost › fileadmin › src › docs › ... · top down and...
TRANSCRIPT
PROJECT MANAGEMENT Planning: time and cost
Anna Ilmer (0622286)
Manuel Leupold (0922303)
Planning: Time and cost 1 Anna Ilmer & Manuel Leupold
Anna Ilmer & Manuel Leupold Planning: Time and cost 2
Roberts, Paul (2007): Guide to project management. Achieving lasting benefit through effective change. London: Profile Books Ltd, p. 111 – 131.
Agenda
1. Overview
2. Estimating Techniques
3. Development of a resource plan
4. Flexibility of resource plans and the consequences
Planning: Time and cost 3 Anna Ilmer & Manuel Leupold
1. Overview: Products and tasks
• Products are results of sequences of tasks
• Product Lifecycle:
Draft
Review
Amend
Approve
Anna Ilmer & Manuel Leupold Planning: Time and cost 4
Estimate
“An estimate is a probability assessment based on skill and experience of the time and resources required for the delivery of a specified product that has been considered at length during product-based planning.” (Roberts 2007: 112)
Anna Ilmer & Manuel Leupold Planning: Time and cost 5
2. Estimating techniques
• Without any references to any stored data or prior experience top down & bottom up Delphi technique analogy
• Require estimation data from previous projects work distribution standard project / product
Planning: Time and cost 6 Anna Ilmer & Manuel Leupold
Top down and bottom up
• Top down: Created at the beginning of the project
„takes the whole project and
applies an overall timescale and cost.” (Roberts 2007: 112)
• No possibility for detail planning
• High level nature
• May contain risky assumptions
• Focus on TIME / COST / QUALITY
Planning: Time and cost 7 Anna Ilmer & Manuel Leupold
Top down and bottom up
• Bottom-up: more detailed than Top-down
• Breaks a product into a set of smaller product
Anna Ilmer & Manuel Leupold Planning: Time and cost 8
Top down and bottom up
Anna Ilmer & Manuel Leupold Planning: Time and cost 9
Feasibility study report
Need analysis report
Tested ,implememnted
solution Design report
Developed solution
TIME
COST
QUALITY
Stage 1 8 weeks
Stage 2 8 weeks
Stage 3 10 weeks
Stage 4 15 weeks
Stage 5 15 weeks
20.000 $ 25.000 $ 45.000 $ 65.000 $ 5.000 $
Gathered data
Drafted report
Reviewed report
Amended report
Approved report
QUALITY
COST 3.000 $ 8.000 $ 2.000 $ 4.000 $ 2.000 $
1 week 2 weeks 2 weeks 1 week 1 week TIME
Presented report
1.000 $
1 week
The Delphi technique
• Named after the greek oracle, wich was consulted before all major undertakings
• Experts estimate the effort (or budget) for products other experts review the estimation and give an anonymously feedback
the first experts are encouraged to revise t their earlier estimates in the light of these o other views
Planning: Time and cost 10 Anna Ilmer & Manuel Leupold
Analogy
“Comparing the project, or aspects of it, with something similar is one way in which estimates can be developed.” (Roberts 2007: 114)
Anna Ilmer & Manuel Leupold Planning: Time and cost 11
Workdistribution
• May be used only for similar projects
• Use of experience and reliable data from former projects
• Show the distribution of effort or budget across the standard project lifecycle or across different types of resource
Planning: Time and cost 12 Anna Ilmer & Manuel Leupold
Workdistribution
Anna Ilmer & Manuel Leupold Planning: Time and cost 13
Project total 100%
Need Analysis 25%
Solution Design
25%
Solution implementati
on 10%
Project initiation
5%
Solution Dev. 35 %
Project total 100%
Sales 35%
Operations 15%
IT 35%
Management 5%
Third parties 10 %
Standard project/product
• Matrix for working out effort for future project
• Based on data from repeatedly carried out projects
• For repeatable work, which varies in size and complexity
• For accurate estimation, size and complexity should be measurable
Anna Ilmer & Manuel Leupold Planning: Time and cost 14
Standard project/ product
COMPLEXITY SIZE
LOW MEDIUM HIGH
SMALL 1 2 3
MEDIUM 3 5 9
LARGE 5 10 15
Anna Ilmer & Manuel Leupold Planning: Time and cost 15
3.Development of a resource plan
• Resource management
• Timescale identification
Product flow diagram / PERT diagram
Gantt Chart
• Cost estimate
Resource plan
Resource plan with financial information
Anna Ilmer & Manuel Leupold Planning: Time and cost 16
Resource management
• Capital
Office Equipment, computer hardware
• Non-human ressources
Travels, advanced education, expenses
• Human resources
Skills, experience, effort, productivity
Anna Ilmer & Manuel Leupold Planning: Time and cost 17
Human resources - Productivity
• People will not be 100% productive.
• Productivity does not always increase when more people are allocated to a task.
• People have different productivity rates.
• Productivity increases are usually temporary.
Anna Ilmer & Manuel Leupold Planning: Time and cost 18
Dependable productivity estimates
• Let people estimate their own work.
• Make planning assumptions clear.
• Agree product descriptions.
• Look at metrics from previous work.
• Negotiate penalty/reward clauses.
Anna Ilmer & Manuel Leupold Planning: Time and cost 19
Timescale identification
Anna Ilmer & Manuel Leupold Planning: Time and cost 20
Timescale identification
Anna Ilmer & Manuel Leupold Planning: Time and cost 21
Cost estimate
Anna Ilmer & Manuel Leupold Planning: Time and cost 22
4.Flexibility of resource plans and the
consequences
Anna Ilmer & Manuel Leupold Planning: Time and cost 23
Anna Ilmer & Manuel Leupold Planning: Time and cost 24