project management lectures
DESCRIPTION
Here is the lecture of Project ManagementTRANSCRIPT
![Page 1: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/1.jpg)
Project:
Projects are not ongoing operations in a company.
Projects are not routine activities
Projects are
o Temporary
o Defined purpose
o Defined Beginning and End
o Human and other resources
A project is a temporary endeavor undertaken to create a unique product, service, or result.
The temporary nature of projects indicates that a project has a definite beginning and end. The end is
reached when the project’s objectives have been achieved or when the project is terminated because its
objectives will not or cannot be met, or when the need for the project no longer exists.
Project Management:
Planning, organizing, directing, and controlling of resources for a specific time period to meet a specific set of one-time objective.
Project management is the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.
Application of skills and methods to deliver projects
1. On time
2. On budget
3. Up to specification
We manage projects on daily basis
For Example: Getting to University on time.
6:00 – alarm
6:05 – washroom
6:15 – prayer
6:25 – shave
6:35 – shower
6:50 – Dressing
7:00 – Breakfast
![Page 2: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/2.jpg)
7:20 – Drive to work
8:00 – on time
So we all have inherent knowledge of skills and methods of project management. Difference is in the
magnitude
Project management versus Crisis management?
Criteria for a successful project:
Well defined scope: must be clearly defined
Sponsor: must have a sponsor with the need, authority and budget
Will: will to succeed. The sponsor must have some need which is being fulfilled by the project.
Approval: formal approval
Though following factors are important but not mandatory for a successful project
Technical skills
Special equipment
Detail team knowledge
PMI = Project management institute, it is an International, non-profit group of volunteers focused on
project management best practices
PMBoK = Project management body of knowledge
PMP = Project management professional
How does PMBoK define PM?
1. Scope
2. Time
3. Cost
4. Quality
5. Human resources
6. Communication
7. Risk
8. Procurement
9. Stakeholder
10. Integration of all above areas
![Page 3: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/3.jpg)
Project, Program, Portfolio and Operational Management
Program: Collection of projects
Portfolio Management: deals with a Suite of programs which fulfills an organizational requirement. It is
about long term vision of an organization.
Operational Management: Day to day execution of business.
Portfolio Management:
Large focus
Could be several programs
Program Management:
Related projects having a common theme
May have a business unit focus
Co-ordinates resources and dependencies across Projects
Project Management Process Groups:
Initiating: Project validation
o Project/phase definition
o Preliminary budget approved
o Project charter is created (with initial scope)
o Stakeholders’ registry is started
![Page 4: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/4.jpg)
o Project manager is assigned.
o Project validation and approval
Planning: covers all knowledge areas
o On-going activity.
o Project management plan is created which addresses all knowledge areas
o Separate management plans may be created for large complex projects
o Secret to success lies in good planning
o For example: good scope we have good WBS. Good WBS we have good schedule, good
scope – good budget,
Executing: actual work
o Actual work is done (least management activity)
o PM focuses on supporting the team i.e. removing the road blocks. Help the team to
work in an effective and efficient manner for example: provide training if required, etc.
Monitoring & Controlling: facilitate the team by removing road blocks, project tracking etc.
o Tracking progress: track actuals for example: amount of work done vs amount of work
expected to be done
o Updating plan: update plan with respect to the performance
o Reporting performance: report back to stake holders and actions taken to keep your
plan on track
Closing: returning resources back to the pool
o Ending a project
o Gaining final acceptance
o Lessons learned: what worked and what didn’t. Information should be shared across the
organization by publishing
o Reusable material
Project Management Process Groups Explained
Project Initiation:
1. Definition of project or phase
2. Initial scope defined (high level)
3. Assign a project manager.
![Page 5: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/5.jpg)
4. Develop project charter
Includes business vision,
timeline,
budget and
cost benefit analysis
identification of possible risks
5. Identify stakeholders
Create stakeholder register
After getting approval to proceed PM will move on to planning phase
Project Planning:
Knowledge Area Planning Process Output
Project integration mgt Develop project mgt plan Project management plan
Project scope management Plan scope managementCollect requirementsDefine scopeCreate WBS
Scope management planRequirements Doc and RTMProject scope statementScope baseline
Project time management Plan schedule managementDefine activitiesSequence activitiesEstimate activity resourcesEstimate activity durationsDevelop schedule
Project cost management Plan for cost managementEstimate costDetermine budget
Project quality management Plan for quality managementPerform quality assurance (doing right things)Control quality (doing things right)
Project human resource mgt Plan for human resource managementAcquire project teamDevelop project teamManage project team
Project communications mgt Plan for communications
![Page 6: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/6.jpg)
Manage communicationsControl communications
Project risk management Plan for risksIdentify risksPerform analysisPlan risk responsesControl risks
Project procurement mgt Plan for procurementConduct procurementsControl procurementsClose procurements
Project stakeholder mgt Identify stake holdersPlan for stakeholder mgtManage stakeholder mgtControl stakeholder engagement
PM Processes VS Project Life cycle:
Analysis: what are the expectations of stake holders and business?
Design
Execution / actual construction
Finalization
Project Management, stake holders and governance
Project Manager:
100% responsible for successful delivery of the project i.e. on time, on budget, up to the
specification and quality. PM achieves this target with the help of a team
Neither a business expert nor an IT expert of current technologies!
PM knowledge: PMBok guide
PM performance: Application of PM knowledge
Skills Required by a PM:
1. Leadership
2. Team building
3. Motivation
4. Communication (introvert versus extrovert)
![Page 7: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/7.jpg)
5. Influencing
6. Decision maker
7. Political awareness
8. Negotiation (with team, business, etc.)
9. Trust building
10. Conflict management
11. Coach
Stakeholders:
Anyone with an interest in the project
Senior management, middle management, operational staff.
Affected department
Interested department
Others (pros or cons)
Internal and External (suppliers, customers etc.)
Key stakeholders: sponsor, acceptor, Subject matter expert (SME) and users
Stake holder Analysis includes a chart having following data items
1. Name
2. Department
3. Position
4. Representation
5. Objectives
6. Objective priority
7. Role in project
Governance:
From senior management view point
Project oversight: Is it achieving business plan expectations?
Project acceptance: initial approval after initiation.
Project guidance: ongoing support i.e. framework for making project decisions
PMI Code of Ethics
Responsibility
![Page 8: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/8.jpg)
Respect
Fairness
Honesty
Project Organizational Structures
Organizational Environmental Factors:
Culture. Is it a risk-taking or risk-adverse organization?
Government regulations
Geographic distribution.
Infrastructure. Access to tools/resources?
Human resources?
Market conditions. Sellers’ market or buyers’ market
Political climate with-in an organization, our ability to make decisions etc.
Organizational structures:
Functional Organization
o Big Boss
Functional Managers (HR, Marketing, Sales, Operations, Finance, IT)
Functional manager designates someone i.e. unskilled + part-time PM
Project team is built from a functional area
Part-time team members
Little PM control on team members
Low subject matter expertise (in some areas)
Matrix (weak, balance and strong)
o Weak Matrix:
Project team is built from multiple functions
Part time team members
Un skilled + Part-time PM
Low PM control on team members
High subject matter expertise
o Balanced Matrix:
Project team is built from multiple functions
![Page 9: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/9.jpg)
Part-time team members
Skilled + Full-time PM
Low PM control on team members
High subject matter expertise
o Strong Matrix:
Project team is built from multiple functions
Part-time team members
Dedicated project management group (PMO) having skilled full time PMs
Better PM control on team members
High subject matter expertise
Project
o Dedicated skilled PMs
o Dedicated skilled staff
o Full control on team members
o High subject matter expertise by hiring part-time subject matter experts (cannot affect
more than 25% of the total project)
![Page 10: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/10.jpg)
Project Integration Management1. Develop project charter
2. Develop project management plan
3. Direct and manage project work
4. Monitor and control project work
5. Perform integrated change control
6. Close project or phase
Project Scope Management1. Plan scope management (new process introduced in scope management in PMBoK Guide 5)
2. Collect Requirements: what and why the business wants?
3. Define scope: define what project will do.
4. Create WBS: decomposition of scope into work packages.
![Page 11: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/11.jpg)
5. Validate Scope
6. Control Scope
Plan Scope Management:
Input:
1. Project management plan
2. Project charter: high level scope.
Tools & Techniques:
1. Meetings
Output:
Scope management plan (change control, process of approval etc)
Requirements management plan (how will we track and manage changes. RTM
required)
Collect Requirements:
o Input:
Project Charter
Scope Management Plan
o Tools and Techniques:
Interviews, focus groups, surveys, etc (PMI mentions many more)
o Output:
Requirements documentation
Requirements traceability matrix
Define scope:
o Input:
Project charter
Requirements document
o Tools & Techniques:
Product analysis: mentions all deliverables, alternative evaluation
o Output:
Project scope statement: includes what is in scope and what is not in scope as
well as acceptance criteria i.e. everything we need to do and provide as a result
of this project. It must be comprehensive and unambiguous.
![Page 12: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/12.jpg)
Create WBS:
o Input:
Project scope statement
o Tools & Techniques:
Decomposition
o Output:
Scope baseline: this is the document through which we can measure the change
and progress of our project
WBS: manageable work packages
WBS dictionary: document that provides more details about work package. E.g.
accounting info, assumptions, constraints, schedule requirement etc.
Validate Scope: gaining acceptance from the business about the deliverables. Bear in mind that
Inspection and validation of deliverables occurs in quality management not in scope validation.
You have to define timeline, turn around process (one set of comments required from multiple
reviewers), interim acceptance process for scope validation.
o Input:
Requirement Document and RTM
Verified deliverables, work performance data
o Tools and Techniques:
Inspection, group decision making i.e. working with the acceptor
o Output:
Accepted deliverables, reworked deliverables, change requests and defect
reports
Try to get personal acceptance document from the acceptor.
Control Scope: Manage change and integrate change. Impact on schedule, cost, risk, team etc.
o Input:
Requirements document, RTM, work performance data / team status reports
and time sheets
o Tools and Techniques:
Variance analysis (e.g. why team members work on unauthorized work etc.)
o Output:
Work performance information (Tracking the scope/time/budget)
![Page 13: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/13.jpg)
Change requests (check change request form. All changes must be formally
approved)/ Corrective actions
Report on change which includes updated plan, schedule, budget, etc. Update
the baseline.
Project Time Management:
1. Schedule management plan: plan how we are going to manage our schedule. How we
are going to track our progress weekly and report our progress weekly
2. Define activities: (WBS, Activities, Work packages)
3. Sequence activities
4. Estimate activity resources
![Page 14: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/14.jpg)
5. Estimate activity durations
6. Develop schedule
7. Control schedule
a) Plan schedule management:
Input:
1. Project charter
2. Project management plan
3. Project assets
Tools & Techniques:
1. Analytical techniques
2. Meetings
Output:
1. Schedule management plan (process for planning).
a. Upfront planning
b. Rolling wave planning
b) Define activities:
Input:
1. Scope base line
2. WBS
3. WBS dictionary
Tools & Techniques:
Decomposition: eg WBS: scope -> deliverable -> activities/work package (assignable
level. Must not be given to more than one person for 2 weeks)
Outputs:
1. Activity list
2. Activity attributes
3. Mile stones (combination of activities for reporting)
c) Sequence Activities:
Input:
Activity list, milestone list, activity attributes
![Page 15: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/15.jpg)
Tools & Techniques:
Precedence diagramming method e.g.
o Finish-to-finish, finish-to-start, start to start, start to finish.
o Mandatory, discretionary, external, internal
Output:
Project schedule network diagrams
d) Estimate activity resources:
Input: Activity list, resource calendar (human, supplies, equipment) e.g. who is available?
Tools & Techniques: Bottom up estimating e.g. each task is broken down into smaller steps
and estimate about each step
Output: Activity resource requirement, resource break-down structure.
e) Estimate activity duration:
Input: Activity list
Tools and Techniques: Estimating techniques e.g. analogous, parametric, three point
(optimistic, pessimistic and most likely)
Output: Activity duration estimation.
f) Develop schedule:
Input: Activity list, resources, estimates, dependencies
Tools & Techniques: Critical path method, resource optimization techniques, schedule
compression
Output: project schedule
g) Control Schedule:
Input:
Project/schedule management plan
Work performance data: time sheets (accurate and timely), status reports
Tools and techniques:
Performance reviews :
o detailed and accurate time sheets
o Trend analysis (for all team members)
o Critical path analysis (a sequence of tasks that impact the end-date)
o Crashing / fast tracking
![Page 16: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/16.jpg)
Resource optimization: Adjusting resources/Estimates/Assignments. Initial planning and
resource leveling= adjust over and under allocation. might need rescheduling
Out puts:
Schedule forecast: on schedule, ahead or behind etc. corrective actions
Project Cost Management:
Plan Cost Management: develop plan for Cost management
Input: Project management plan, project charter and organizational process assets
Tools & Techniques: Analytical methods, meetings
Outputs: Cost management plan.
Estimate Costs:
Input: Project schedule, scope baseline, risk register
Tools & Techniques: Estimating Techniques, Risk analysis (learning costs, delays, I don’t know!
etc.), Cost of quality
Outputs: Activity cost estimates
Determine Budget: project cost spread over time
Input: Activity cost management, cost management plan
Tools & Techniques: cost aggregation
Output: cost baseline, project funding requirement.
Control Costs:
Input: cost management plan, work performance data
Tools & Techniques: performance reviews, forecasting, earned value management
Output: cost forecasts, change requests.
Performance Reviews:
On time, on budget
Ahead of time, below budget
Ahead of time, over budget
On time, above budget
On time, below budget
Late, over budget
Late below budget
![Page 17: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/17.jpg)
Earned value management:
Combines scope, schedule and budget
Provides a true project health indicator
Uses past to predict the future
As reliable as the FACTS
EV Basics:
Planned value: base line
Actual cost: cost incurred
Earned value: cost of value delivered
Project Human Resource Management
![Page 18: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/18.jpg)
1. Plan human resource managementInput:
Project management plan Activity resource requirements
Tools & Techniques: Project organization charts (who reports to whom), RACI chart (responsible,
accountable, consulted and informed), 7 to 10 members would make an optimal team
Networking (the ability to deal with human resources and with other managers)Output:
Human resource management plan2. Acquire project team
Input: HR Plan Organizational process assets
Tools & Techniques: Pre assignment Negotiation (re-planning required) Acquisitions Virtual teams (required more efforts from PM side)
Output: Project staff assignment Resource calendars (availability and vacations )
3. Develop project teamInput:
HR plan Staff assignments
Tools & Techniques: Interpersonal skills Training Ground rules Team building
Tuckman Model: Forming Storming Norming Performing Adjourning
Recognition & rewards
![Page 19: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/19.jpg)
AssessmentsOutput:
Team performance assessments 4. Manage project team
Input: HR plan Staff assignments Assessments Performance Reports
Tools & Techniques: Observation and conversation Interpersonal skills Performance appraisals Conflict management
o Withdraw / avoido Smooth / accommodate : find a way that makes everyone happyo Compromise / reconcile: mediate at greater level of detail to get a common
approacho Force / direct:o Collaborate / solve problem
Output: Change request and other planning document updates
Project Quality Management Plan quality management
![Page 20: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/20.jpg)
Perform quality assurance (inspections, reviews, doing the right thing)
Control quality (doing things right)
Plan Quality Management:
Input: Project Management Plan, Stakeholders, Risks, Requirements documentation
Tools & Techniques: 7 quality tools, benchmarking, experiments, sampling, cost benefit
analysis.
7 Quality Tools:
cause and effect diagrams
flow charts
check sheets (whatever has done or left with comments, documents review
check sheets)
pareto diagrams (x: cause, y: occurrence)
histograms
control charts (upper and lower limits of weekly timesheets)
scatter diagrams
Output: quality management plan (stake holders’ quality expectations?)
Perform Quality Assurance: (following standards)
Inputs: Quality Plan, Quality Metrics, Quality Control Measurement
Tools & Techniques: Quality Audits, Process Analysis (Right Things)
Outputs: Change requests, Project deliverable updates
Control Quality:
Inputs: Quality management plan, quality metrics, deliverables
Tools & Techniques: Sampling, inspections, walk-throughs, peer reviews
Outputs: deliverables updates, verified deliverables
Quality?
Quality versus grade
Customer satisfaction
Prevention over inspection
Continuous improvement
Management responsibility
![Page 21: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/21.jpg)
Cost of quality
Project Communications Management:
Plan communications management: planning upfront
o Inputs: PM plan and stake holder register (who, what and when)
o Tools and techniques (How): Communications requirements analysis,
communication technology, Models and methods.
o Outputs: communication management plan i.e. this kind of information would
be produced on daily/weekly/monthly bases and who is getting what kind of
information among stakeholders. Communication channels if everyone can
communicated to everyone else in the team: n (n-1)/2. Decision about
communications technology i.e. urgency, availability, ease of use and
security/privacy issues. Style for personal, formal, informal communications etc.
Manage communications: actual delivery (sharing project details with stakeholders)
o Inputs: communications management plan, work performance reports
o Tools and techniques: communications, performance reporting – status reports
on weekly bases etc.
o Outputs: project communications.
Control communications (ensure it happens in an organized fashion)
o Inputs: Project and communications management plan, Project
communications, issue logs
o Tools & Techniques: Information Management system/Project communications
tool
o Outputs: Work performance information.
![Page 22: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/22.jpg)
Project Monthly status reports:Project Name:
Reporting period:
Prepared by:
Major accomplishment this month:
Accomplishment 01
Accomplishment 02
Financial status: (graph representation would be great)
Total Budget:
Spending to date:
Estimate to complete:
![Page 23: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/23.jpg)
Variance
Project schedule:
Efforts invested to date
Remaining efforts
%age completion
Snap shot of Gant Chart with only milestones visible would be great.
Major Issues:
Issue one
Issue two
Meetings:
Critical
Managed
Scheduled
Managed attendees
Managed agenda
minutes
Issue Management Log
Project Name:
Issue Name Date Opened Due Date Current Status
![Page 24: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/24.jpg)
Warning Signs:
1. un skilled project manager
2. key stake holders disagree with project priorities and don’t engage in appropriate
debate to solve their issues
3. senior leaders don’t make decisions in time or stop showing their presence in meeting
when required
4. customer representatives starts changing their minds / retract statements made during
earlier discussions
5. key members working on critical path tasks start missing deadlines in order to juggle
with priorities
6. Team members regularly use extra time defined in the project without any apparent
reason
7. Inadequate time and resources have been placed in order to understand current
business processes completely
8. Project manager is unaware of the project goals / senior leadership has not shared its
vision with the lower staff. No one is willing to take the ownership of the product being
produced.
9. Lack of enthusiasm of senior management
10. Placing too heavy a focus on project management
11. Sponsor doesn’t give appropriate time to the project
![Page 25: Project Management Lectures](https://reader036.vdocuments.us/reader036/viewer/2022062809/5695d13a1a28ab9b0295aa50/html5/thumbnails/25.jpg)
Project Integration Management
1. Develop project charter
2. Develop project management plan
3. Direct and manage project work
4. Monitor and control project work
5. Perform integrated change control
6. Close project or phase
Integrate all knowledge areas.