project management

47
McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved. 17 17 Project Management

Upload: yeo-diaz

Post on 01-Jan-2016

22 views

Category:

Documents


2 download

DESCRIPTION

17. Project Management. Learning Objectives. Discuss the behavioral aspects of projects in terms of project personnel and the project manager. Discuss the nature and importance of a work breakdown structure in project management. Give a general description of PERT/CPM techniques. - PowerPoint PPT Presentation

TRANSCRIPT

McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved.

1717

Project Management

17-2

Learning ObjectivesLearning Objectives

Discuss the behavioral aspects of projects in terms of project personnel and the project manager.

Discuss the nature and importance of a work breakdown structure in project management.

Give a general description of PERT/CPM techniques.

Construct simple network diagrams.

17-3

Learning ObjectivesLearning Objectives

List the kinds of information that a PERT or CPM analysis can provide.

Analyze networks with deterministic times. Analyze networks with probabilistic times. Describe activity “crashing” and solve

typical problems.

17-4

Unique, one-time operations designed to Unique, one-time operations designed to accomplish a specific set of objectives in a accomplish a specific set of objectives in a limited time frame.limited time frame.

Build A

A Done

Build B

B Done

Build C

C Done

Build D

Ship

JAN FEB MAR APR MAY JUN

On time!

ProjectsProjects

17-5

Project ManagementProject Management

How is it different? Limited time frame Narrow focus, specific objectives Less bureaucratic

Why is it used? Special needs Pressures for new or improves products or

services

17-6

Project ManagementProject Management

What are the Key Metrics Time Cost Performance objectives

What are the Key Success Factors? Top-down commitment Having a capable project manager Having time to plan Careful tracking and control Good communications

17-7

Project ManagementProject Management

What are the Major Administrative Issues? Executive responsibilities

Project selection Project manager selection Organizational structure

Organizational alternatives Manage within functional unit Assign a coordinator Use a matrix organization with a project leader

17-8

Project ManagementProject Management

What are the tools? Work breakdown structure Network diagram Gantt charts Risk management

17-9

Planning and SchedulingPlanning and Scheduling

MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

Locate new facilities

Interview staff

Hire and train staff

Select and order furniture

Remodel and install phones

Move in/startup

Gantt Chart

17-10

Deciding which projects to implement

Selecting a project manager

Selecting a project team

Planning and designing the project

Managing and controlling project resources

Deciding if and when a project should be terminated

Key DecisionsKey Decisions

17-11

Project ManagerProject Manager

Responsible for:

Work QualityHuman Resources TimeCommunications Costs

17-12

Temptation to understate costs

Withhold information

Misleading status reports

Falsifying records

Comprising workers’ safety

Approving substandard work

Ethical IssuesEthical Issues

17-13

Project Life CycleProject Life Cycle

Concept

FeasibilityFeasibility

PlanningPlanning

ExecutionExecution

TerminationTermination

Man

agem

ent

17-14

Work Breakdown StructureWork Breakdown Structure

Project XProject X

Level 1

Level 2

Level 3

Level 4

Figure 17.2

17-15

PERT and CPMPERT and CPM

PERT: Program Evaluation and Review Technique

CPM: Critical Path Method

Graphically displays project activities Estimates how long the project will take Indicates most critical activities Show where delays will not affect project

17-16

The Network DiagramThe Network Diagram

Network (precedence) diagram – diagram of project activities that shows sequential relationships by the use of arrows and nodes.

Activity-on-arrow (AOA) – a network diagram convention in which arrows designate activities.

Activity-on-node (AON) – a network diagram convention in which nodes designate activities.

Activities – steps in the project that consume resources and/or time.

Events – the starting and finishing of activities, designated by nodes in the AOA convention.

17-17

The Network Diagram (cont’d)The Network Diagram (cont’d)

Path Sequence of activities that leads from the starting

node to the finishing node

Critical path The longest path; determines expected project

duration

Critical activities Activities on the critical path

Slack Allowable slippage for path; the difference the

length of path and the length of critical path

17-18

Project Network – Activity on Project Network – Activity on ArrowArrow

1

2

3

4

5 6

Locatefacilities

Orderfurniture

Furnituresetup

InterviewHire andtrain

Remodel

Move in

Figure 17.4

AOA

17-19

Project Network – Activity on Project Network – Activity on NodeNode

1

2

3

5

6

Locatefacilities

Orderfurniture

Furnituresetup

Interview

RemodelMove in

4

Hire andtrain

7S

Figure 17.4

AON

17-20

Network ConventionsNetwork Conventions

a

b

c ab

c

a

b

c

d

a

b

c

Dummyactivity

17-21

Time EstimatesTime Estimates

Deterministic

Time estimates that are fairly certain

Probabilistic

Estimates of times that allow for variation

17-22

Example 1Example 1

1

2

3

4

5 6

8 weeks

6 weeks

3 weeks

4 weeks9 weeks

11 weeks

1 week

Locate

facilities

Order

furniture Fu

rnitu

re

setup

InterviewHire

and train

Remodel Move in

DeterministicDeterministictime estimatestime estimates

Figure 17.5

17-23

Example 1 SolutionExample 1 Solution

P a t h L e n g t h( w e e k s )

S l a c k

1 - 2 - 3 - 4 - 5 - 61 - 2 - 5 - 61 - 3 - 5 - 6

1 82 01 4

206

Critical PathCritical Path

17-24

Network activities ES: early start EF: early finish LS: late start LF: late finish

Used to determine Expected project duration Slack time Critical path

Computing AlgorithmComputing Algorithm

17-25

Probabilistic Time EstimatesProbabilistic Time Estimates

Optimistic time

Time required under optimal conditions

Pessimistic time

Time required under worst conditions

Most likely time

Most probable length of time that will be required

17-26

Probabilistic EstimatesProbabilistic Estimates

Activitystart

Optimistictime

Most likelytime (mode)

Pessimistictime

to tptm te

Figure 17.8

Beta Distribution

17-27

Expected TimeExpected Time

te = to + 4tm +tp

6

te = expected timeto = optimistic timetm = most likely timetp = pessimistic time

17-28

VarianceVariance

(tp – to)2

36

= varianceto = optimistic timetp = pessimistic time

17-29

Example 5Example 5

1-3-4a

3-4-5d

3-5-7e

5-7-9f

2-4-6b

4-6-8h

2-3-6g 3-4-6

i

2-3-5c

Optimistictime

Most likelytime

Pessimistictime

17-30

Example 5 Time EstimatesExample 5 Time Estimates

2.83a

4.00d

5.0e

7.0f

4.00b

6.0h

3.33g 4.17

i

3.17c

Tabc = 10.0Tdef = 16.0Tghi = 13.50

17-31

Path ProbabilitiesPath Probabilities

Z = Specified time – Path meanPath standard deviation

Z indicates how many standard deviationsof the path distribution the specified tineis beyond the expected path duration.

17-32

17Weeks

Weeks

Weeks

Weeks

10.0

16.0

13.5

1.00

1.00

a-b-c

d-e-f

g-h-i

Example 6Example 6

17-33

Time-cost Trade-offs: CrashingTime-cost Trade-offs: Crashing

Crash – shortening activity duration

Procedure for crashing Crash the project one period at a time

Only an activity on the critical path

Crash the least expensive activity

Multiple critical paths: find the sum of crashing the least expensive activity on each critical path

17-34

Time-Cost Trade-Offs: CrashingTime-Cost Trade-Offs: Crashing

TotalcostTotalcost

ShortenShorten

ShortenShorten

Cumulativecost of crashing

Cumulativecost of crashing

Expected indirect costsExpected indirect costs

Optimum

CRASHCRASH

Figure 17.11

17-35

6a

4d

5c

10b

9 e

2f

Example 7Example 7

17-36

Advantages of PERTAdvantages of PERT

Forces managers to organize

Provides graphic display of activities

Identifies Critical activities

Slack activities1

2

3

4

5 6

17-37

Limitations of PERTLimitations of PERT

Important activities may be omitted

Precedence relationships may not be correct

Estimates may include a fudge factor

May focus solelyon critical path

1

2

3

4

5 6

142 weeks

17-38

Goldratt’s Critical ChainGoldratt’s Critical Chain

Goldratt’s insight on project management Time estimates are often pessimistic Activities finished ahead of schedule often go

unreported With multiple projects, resources needed for one

project may be in use on another

17-39

Computer aided design (CAD) Groupware (Lotus Notes) CA Super Project Harvard Total Manager MS Project Sure Track Project Manager Time Line

Project Management SoftwareProject Management Software

17-40

Imposes a methodology

Provides logical planning structure

Enhances team communication

Flag constraint violations

Automatic report formats

Multiple levels of reports

Enables what-if scenarios

Generates various chart types

Advantages of PM SoftwareAdvantages of PM Software

17-41

Risk: occurrence of events that have undesirable consequences

Delays

Increased costs

Inability to meet specifications

Project termination

Project Risk ManagementProject Risk Management

17-42

Identify potential risks

Analyze and assess risks

Work to minimize occurrence of risk

Establish contingency plans

Risk ManagementRisk Management

17-43

SummarySummary

Projects are a unique set of activities

Projects go through life cycles

PERT and CPM are two common techniques

Network diagrams

Project management software available

17-44

Video: Work BreakdownVideo: Work Breakdown

17-45

Video: Project Materials/DelaysVideo: Project Materials/Delays

17-46

Video: Project SchedulingVideo: Project Scheduling

17-47

Video: PERT/CPMVideo: PERT/CPM