project governance: avoiding “administrivia” lisa kosanovich project manager center for...
TRANSCRIPT
Project Governance:Avoiding “Administrivia”
Lisa KosanovichProject Manager
Center for Instructional DesignBrigham Young University
Copyright Information
Copyright Lisa Kosanovich 2005.
This work is the intellectual property of the author. Permission is granted for this material to be shared for non-commercial, educational purposes, provided that this copyright statement appears on the reproduced materials and notice is given that the copying is by permission of the author. To disseminate otherwise or to republish requires written permission from the author.
“Administrivia”-
• “Who is the Boss?” • Design problems are being resolved in a
vacuum• Complete project status and issues do not reside
with one person or in a collective whole• Project Plans need “revamping” on a regular
basis to clarify when the project will finish and what ‘really’ remains to be done, few know when their work should be done
reactive approach to problems that arise
Project Governance- proactive approach to projects
• TEAM: Define Team Roles and their functions
• SCOPE: Change Management and a Scope Steward
• COMMUNICATION: Communication Framework
• SCHEDULE: Scheduling Tools and Principles
Managing by project governance
Manage = Monitor, Investigate, Take Action, & Report
Monitor the Project Scope
Monitor the Schedule
Investigate the Project Team
Investigate the Schedule
Take Action on the
Communications
Investigate the Project Scope
Take Action on the Schedule
Take Action on the
Project Team
Take Action on the
Project Scope
Report on the Project Scope
Report on the Project Team
Report on the Schedule
Report on theCommunications
Monitor the Project Team
Monitor the Communications
Investigate the Communications
Establish Governance Monitor Investigate Take Action Report
Establish the Project Scope Governance
Establish the Project Team Governance
Establish the Project Schedule Governance
Establish the Communication Governance
Scope
Team
Schedule
Communication
Team
• No one is the “boss”• Everyone has a key role to contribute throughout
the life of the project• Example:
– Designer: steward of the scope for the project, technical design and resolution
– Sponsor: Define what is needed, make decisions on behalf of the user
– Production Staff: Provide technical solutions, build product
– Project Manager: steward over project information
Scope
Size* Small Medium Large
What type (e.g. Spelling corrections, unseen changes)
(e.g. features of graphics
(e.g. Any change that increases the schedule of budget by 10%)
Who is involved Individual Team member
Sponsor and Entire Team
Team, Sponsor, Director of Organization
Change** Matrix
*Consultation with the ‘steward of the scope’ will clarify what size a requested change is.
**Changes should be based on a constraint matrix
Scope
Constraint/Flexibility Matrix
Least Moderate Most
Scope √
Schedule √
Resources √
Directs change decisions that are made, in an attempt to protect that which is most constrained
Communication• Team listserv, alias, or group email
• Weekly Team Email
• Meetings:– Brainstorming– Consensus gathering– Changes that need negotiation– Issues that will require more than one
conversation within the team– Almost NEVER for status
Schedule
• Define tasks at the level where issues occur and status is most meaningful
• Do not plan past your next point of knowledge
• Use the best tool for the job– Waterfall vs. iterative– Task driven vs. date driven– Checklist vs. Schedule
Schedule
• Date Driven:– Biweekly meetings during
design phase of a project– Schedule is most
constrained therefore dates will be drawn out by which to achieve certain features
– Decisions need to be made even though research or work may not yet be complete
• Task Driven:– Scope is most constrained
therefore work will continue until all features are achieved
– Many resources or outside vendors are involved, requiring coordination of deliverables
– Many dependencies exist within the project requiring coordination for timely completion
Managing by project governance
Manage = Monitor, Investigate, Take Action, & Report
Monitor the Project Scope
Monitor the Schedule
Investigate the Project Team
Investigate the Schedule
Take Action on the
Communications
Investigate the Project Scope
Take Action on the Schedule
Take Action on the
Project Team
Take Action on the
Project Scope
Report on the Project Scope
Report on the Project Team
Report on the Schedule
Report on theCommunications
Monitor the Project Team
Monitor the Communications
Investigate the Communications
Establish Governance Monitor Investigate Take Action Report
Establish the Project Scope Governance
Establish the Project Team Governance
Establish the Project Schedule Governance
Establish the Communication Governance
Scope
Team
Schedule
Communication
Project Management
1.0Establish the Project
Context
1.1Review Project
Information
1.1.
1R
evie
w th
e P
roje
ct D
ocum
enta
tion
1.2Establish the
Planning Structure
1.2.
1C
reat
e th
e P
lann
ing
Tea
m
1.2.
2E
stab
lish
the
Pro
ject
Gov
erna
nce
Fra
mew
ork
Obtain confirmation and Support to Proceed
Confirm Project Context
1.1.2
2.0Plan the Project
2.1 Define the Project Scope
2.1.
1C
reat
e th
e D
efin
ition
Doc
umen
t
2.2 Create the Preliminary Resourced Schedule
2.3 Complete the Plan
2.1.
2 D
eter
min
e th
e P
lann
ing
and
Man
agem
ent A
ppro
ach
2.1.
4C
reat
e th
e W
ork
Bre
akdo
wn
Str
uctu
re
(Sco
pe)
2.2.1 Create the Preliminary
Project Schedule
2.2.2 Identify
Associated Resources
2.2.
3 In
tegr
ate
Sch
edul
es
2.3.1 Reconcile the Plan
and Project Objectives
2.3.3Create the Risk
Management Plan
2.3.42.3.2
Obtain Confirmation and Support to Proceed
2.3.
5F
inal
ize
the
Pla
n
Validate Scope and Approach
Obtain Confirmation and
Support of Proposed Changes
Obtain Confirmation and Support of the Plan
2.3.6
3.0Execute the Project
3.1 Manage the Project
3.1.
1 B
asel
ine
the
Pro
ject
3.1.2 Monitor, Investigate, Take Action, &
Report (MITAR) on Project Performance
3.1.3 Manage the Project Scope
3.1.4 Manage the Project Team
3.1.5 Manage the Resourced Schedule
3.1.6 Manage Communications
3.1.7
3.2 Close-Out the Project
3.2.
1 T
rans
fer
Ste
war
dshi
p
3.2.
2 C
lose
the
Pro
ject
Validate Project
Completion
Confirm Project
Close-Out
3.2.3
2.1.3
Faculty discusses need with Instructional Designer
Management Meeting Initial Team Meeting
Manage the Project
Transfer Product Stewardship Project Close Meeting
Project Management Process
· Discuss needed design documentation for final approval
· Estimate Time· Define
resources available for content support
· Define Faculty Availablity
· Approve project· Assign team
members· Assign hour
allotment· Prioritize
workload
· Establish Project Governance:
- Roles- Communication - Scope of Project- Schedule tracking
· Monitor Milestonees
· Send weekly progress reports
· Schedule additional meetings
· Review and deliver final product
· Discuss implementation strategy
· Discuss product support and maintenance
· Discuss evaluation strategy
· Discuss successes, challenges and lessons learned
· Celebrate project completion
© Brigham Young University 2004