project final report - cordis · concept model through to prototype testing, technical deployment...

46
PROJECT FINAL REPORT 1. Grant Agreement number: 262552 2. Project acronym: MARINET 3. Project title: Marine Renewables Infrastructure Network 4. Funding Scheme: FP7 Infrastructures 5. Period covered: from 01 April 2011 to 30 Sept 2015 6. Name of the scientific representative of the project's co-ordinator 1 , Title and Organisation: Tony Lewis , UCC-MaREI (formerly HMRC). 7. Tel: 0035321 4864368 8. Fax: 00214864443 9. E-mail: [email protected] 10. Project websiteError! Bookmark not defined. address: http://www.marinet.eu/ 1 Usually the contact person of the coordinator as specified in Art. 8.1. of the Grant Agreement.

Upload: others

Post on 24-Dec-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

PROJECT FINAL REPORT

1. Grant Agreement number: 262552

2. Project acronym: MARINET

3. Project title: Marine Renewables Infrastructure Network

4. Funding Scheme: FP7 Infrastructures

5. Period covered: from 01 April 2011 to 30 Sept 2015

6. Name of the scientific representative of the project's co-ordinator1, Title and Organisation: Tony Lewis , UCC-MaREI (formerly HMRC).

7. Tel: 0035321 4864368

8. Fax: 00214864443

9. E-mail: [email protected]

10. Project websiteError! Bookmark not defined. address: http://www.marinet.eu/

1 Usually the contact person of the coordinator as specified in Art. 8.1. of the Grant Agreement.

Page 2: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

4.1 Final publishable summary report

4.1.1 Executive Summary (1p)

In accordance with the EU’s unilateral 2020 target for its 28 Member States to reduce overall greenhouse gas

emissions, the ocean energy sector is creating an entirely new industry to provide clean, green electricity

where security of supply is far greater than fossil fuels, since resources are readily available within the EU’s

borders. Ocean derived renewable energy is still in the early stages of development but already shows huge

potential for making a significant contribution to energy generation and job creation. However, if Member

States conduct R&D of green technologies separately, duplication and a lack of knowledge sharing could

considerably slow down progress. The Marine Renewables Infrastructure Network (MaRINET) aimed to

coordinate these efforts and speed up the EU’s bid to protect its economies and reduce global warming.

MaRINET is a network of (European) research infrastructures that specialise in marine renewable energy,

which is defined as energy derived from ocean resources as well as offshore wind. MaRINET consists of 45

infrastructures that are operated by 30 research centres around Europe. Nine million Euro in EU funding

enabled the network to offer both academic and industry groups periods of free-of-charge access to their

infrastructures, to improve the infrastructures by conducting research, to standardise the testing methods and

promote training and networking. The ultimate aim was to support the acceleration of the development of

marine renewable energy by harnessing the full capabilities of these infrastructures.

A cornerstone of the MaRINET initiative was to provide transnational access to world-class facilities for

researchers and developers of marine energy systems. Researchers and developers have been granted access

to supported facilities that would not necessarily be available in their home state, or might be too expensive

for SMEs to access normally.

Under WP2, a crucial step in arriving at a standardised set of best practises has been the successful in ‘round

robin’ testing using a standardised scale model tidal device. The process enabled cross comparison between

the performances of a device, irrespective of the infrastructure in which it was being tested. To achieve this,

the scale tidal device developed by the French Research Institute for Exploitation of the Sea (IFREMER) was

tested in two re-circulating flume tanks in France and Italy and two tow-tanks in Italy and the UK. Implementing

an identical test programme at all four facilities. The round robin was the first of its kind to analyse tidal energy

and quantify the effects that different simulated environments can have on test device performance.

Consequently, MaRINET will be able to produce a test tank calibration factor to enable the desired cross

comparison.

The programme of research carried out within MaRINET under WP4 was productive. New approaches for

offshore wave climate / tidal current / wind site assessments have been investigated and documented.

Technical research with direct impact for the offshore industry development has been performed (e.g.

standardised PTO testing methods and advanced mooring concepts), and scientific results have been

successfully introduced to the Marine Energy Research Community in various paper publications and

conference presentations. The environmental impact of Marine Energy has been quantitatively evaluated and

monitoring techniques have been documented in a comprehensive data base.

Page 3: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

MaRINET has been present at most EU offshore renewable energy conferences and held two User Workshops;

Rome in November 2013 and Nantes during Oct 2015, bringing together user groups and infrastructures

managers. MaRINET related research has led to over 60 scientific papers and conference presentations,

including seven key articles published in a special issue of the International Journal on Marine Energy (IJOME

12, 2015). The full content of this edition is devoted to user groups who have participated in, or who have

benefited from infrastructure access through MaRINET.

Page 4: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

4.1.2 Summary of Marinet Project and Objectives

Overview

With abundant Wind, waves, currents — the open seas are awash with untapped energy. In theory, offshore

conversion systems could play a key role in the EU’s shift towards a more sustainable energy mix. In practice,

installed capacity remains limited, and only a fraction of the innovative concepts that could help to power

more European households from renewable marine sources have matured towards deployable technologies.

MaRINET integrates world-class infrastructures and expertise in a drive to bridge the R&D gap between an

inspired idea and a marketable product. Progress in this technology area required a streamlined approach to

R&D. access to guidelines in the shape of the project’s Structured Development Plan, a blueprint for

construction born from an EU Seventh Framework Programme (FP7), developed by NASA and accepted

worldwide through the International Energy Agency (IEA). Though differing slightly for each type of

technology, development follows the same five stages, starting with the technical analysis of a small-scale

concept model through to prototype testing, technical deployment and its final implementation as a

commercial unit. Each of these stages is correlated with one of the standard “TRL’s” or Technology Readiness

Levels which are now a universally recognised method of benchmarking the development status of devices or

technologies.

The 29 partners involved in MaRINET were focused on accelerating the flow of promising ideas and providing

first-rate research and development (R&D) capacity and support to facilitate their commercialisation. Europe’s

Marine Renewable Energy community is developing a raft of innovative technologies, which include wave

energy and tidal stream converters as well as wind turbine designs for deep water deployment and combined

wind- and wave-powered devices. These diverse applications are currently at different stages of development

and they aim to harness renewable sources that are disparate in nature. A correspondingly wide array of test

infrastructures, with diverse capability, is required to take them forward. With 48 highly specialised research

facilities equipped for transnational access, the project partners set out to deliver 700 weeks of access time to

support outstanding R&D efforts. Partner infrastructures ranged from the laboratory scale to large open sea

test sites. The partners’ transnational access (TNA) programme, underpinned by a centralised application

procedure, directed prospective external users towards the installations that are best suited to their needs.

Transnational Access opportunities were offered in five areas: wave energy research, tidal energy research,

offshore-wind energy research, cross-cutting or common issues, and databases and environmental data. They

enabled successful applicants to advance their research at first-rate facilities and, just as importantly, to

benefit from the partners’ outstanding expertise and know-how. They also promote a coherent, standardised

approach based on tried-and-tested methodologies and protocols as a further means of boosting the impact

of R&D investments.

Page 5: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

Key Features of Marinet

• 12 countries

• 29 world-class research institutions

• 45 facilities

• 4 years, from 2011-2015

• €11.1m programme

▫ of which €9m EC-funded

Who Was Involved

29 Founding Partners, coordinated by UCC, with associate partners NCKU (Taiwan), and various other

intersted parties in EU, US, Canada

Page 6: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

The main features of MaRINET TNA at a glance were:

• Unique free-of-charge access to facilities and expertise:

~700 weeks, 300 projects, 800 users

8 Short Courses - 200 trainees

20 Staff Exchanges

Round Robin Testing and standardisation

New global network - all MRE infrastructures working together

• Accelerating technology & industry development?

• Facilities oversubscribed

• Training courses oversubscribed

• International reach and interest

• Positive User group feedback

• Round robin testing in both wave and tidal

• All active Facilities and staff better networked

Page 7: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

4.1.3 Science and Technology Results of the Marinet Project

4.1.3.1 WP 2 Ocean Energy System Testing – Standardisation and Best

Practice

Introduction

The overarching objective of this coordination activity under Marinet was to advance the standardisation and

harmonisation of research methods for wave energy, tidal energy, offshore wind energy and cross cutting

energy technologies. To maximise value and synergistic interactions with ongoing initiatives, the activities

within this work package referred to and made use of, where possible, deliverables with other external actions

in progress, such as the FP7 funded project EQUIMAR and the work of Annexe 2 of the International Energy

Associations Implementing Agreement and IEC TC114. This approach has avoided duplication of effort and

ensured effective engagement and uptake of outputs/ deliverables from these programmes, noting that some

of the Participants in this Task were also involved in these other activities.

Marine renewables testing centres are not uniformly configured or constructed, so the deliverables from WP2

were designed to complement deliverables from other projects by:

developing an understanding of the impact the specific test centre geometrical layout and configuration has had on the testing results;

quantification of the range of errors introduced and the sensitivity of the individual components making up the testing procedure;

development of specific corrective algorithms to be applied to the results from different test centre configurations in order to facilitate benchmarking;

delivery of Quality Management practices to be adopted in the processing and presentation of data when corrective algorithms have been applied

The work was broken down under 4 main tasks with 29 deliverables, consisting of 11 EC and 18 internal reports

undertaken by project partners as follows:

Task 2.1 Wave Energy – Standardization (Lead: HMRC; Participants: AAU, ECN, UNEXE, EMEC, EVE, UEDIN, SEAI, WavEC, UoP, IPT)

Task 2.2 Tidal Energy – Standardization (Lead: Uni_Strath, UEDIN; Participants: EMEC, QUB, TTC, IFREMER, INSEAN)

Task 2.3 Off-Shore Wind Energy – Standardization (Lead: RISOE, LUH; Participants: ECNeth, UNIFI-CRIACIV, Uni_Stutt, NTNU)

Task 2.4 Power Take-off, Electrical Power Conversion Systems and other cross cutting issues (Lead: Fh-IWES; Participants: NAREC, Technalia_RBTK, SINTEF, UNI-TUS)

Page 8: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

The listed deliverable outputs from the various subtasks per reporting period under the above were as follows

(together with lead Authors) where it can be noted that many of the EC contracted deliverables take the form

of good practice/guidance manuals and databases:

Period 1 Deliverables (4 EC & 8 Internal)

D2.12 Collation of Wave Simulation Methods ECN

D2.13 Collation of Model construction Methods SEI

D2.1 EC Wave instrumentation database EMEC

D2.14 Wave data Presentation and Storage Review UoP

D2.15 Tidal flow characterisation parameter review UEdin

D2.2 EC Collation of Tidal Test Options TTC

D2.16 Tidal Test Parameter Draft Overview IFREMER

D2.17 Tidal Measurement Best Practice QUB

D2.18 Tidal Data Analysis Best Practice UoS

D2.3 EC Review of Relevant PTO Systems Fh-IWES

D2.4 EC Collation of Off-shore Wind-Wave dynamics RISOE

D2.19 Collation of Dynamic loads SINTEF

Period 2 Deliverables (3 EC & 7 Internal)

D2.20 Draft Standardisation Report Wave Simulation incorporating wind/wave joint simulations HMRC (draft)

D2.21 Review of Mooring Testing Systems EXE

D2.5 EC Report on Instrumentation Best Practice AaU

D2.6 EC Report on Off-shore Wind Systems Monitoring Practice and Normalisation Procedures LUH

D2.22 Data Presentation Draft Standards WAVEC

D2.23 Review of Tow Tanks limitations CNRINSEAN

D2.7 EC Tidal Measurement Best Practice Manual QUB

D2.24 Planning Completed for Comparative Model Tests UEdin

D2.25 Review Best Practice for electrical PTO systems NAREC

D2.26 Collation European Grid Codes for Testing TECNALIA

Period 3 Deliverables (4 EC & 3 Int)

D2.8 EC Best Practice Manual and Protocol for Wave Simulations HMRC

D2.27 Manual of Wave Instrumentation AaU

D2.9 EC Standards for Wave Data Analysis Archival and presentation, WAVEC

D2.28 Protocol for Model Construction HMRC

D2.10 EC Best Practice Protocol for Off-shore Wind System Fluid-Structure Interaction Testing ECNeth

D2.29 Report on Comparative Testing of Tidal Devices UoS

D2.11 EC Best Practice Manual for PTO Testing TECNALIA

Some of the main highlights of these activities are presented (with Task and associated Deliverables) in the

following section in graphic format with explanatory notes.

Page 9: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

The graphs below show close agreement between the key parameters ascertained at each of the test tanks

D2.29 Report on Comparative Testing of Tidal Devices. Key features are:

Informing infrastructure testing programs to enable comparative evaluation: test environment,

instrumentation, test set-up and execution, processing and production of data and evaluation and

interpretation of performance parameters

Builds on Equimar protocol for tidal device testing

Robustness checking against Round Robin tidal turbine testing program & TNA activity (INSEAN June

2015)

Page 10: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

Task 2.3 Off-Shore Wind Energy Standardisation, D2.6 – Report on Offshore Wind System Monitoring Practice

and Normalisation Procedures

Practices for experimental testing and measurement campaigns elaborated as references for harmonized testing standards in international facilities

Detailed assessment practice recommendations elaborated for: ▫ Fatigue of steel components and structures ▫ Pile foundations under cyclic loading ▫ Scour development and protection

Further practical references given for: ▫ Wind field analysis ▫ Airfoil design ▫ Full scale model testing and measurements ▫ Wind tunnel model tests

Involved partners: LUH, USTUTT, ECNeth, CRIACIV, DTU, NTNU

Page 11: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated
Page 12: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

Task 2.4 - Power Take-off, Electrical Power Conversion Systems and other cross cutting issues. The approach

was to undertake a global review of existing PTO concepts in renewable energy generation industry (wind,

tidal, wave) to identify requirements for PRO testing and standardisation. This was designed in order:

To support dynamic tests required for the Power take-off (PTO) components to be used in Marine Renewable Energy (MRE) converters

To establish and dedicate standard PTO testing procedures

Page 13: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated
Page 14: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

4.1.3.2 WP3 Networking and Transnational Access to World Class Ocean

Energy Test Infrastructures

Introduction

The group of partners who came together under MaRINET to provide access to their testing infrastructures

all have a long track record in performing research related to the ocean energy sector. They all have suitable

facilities and appropriately trained expert staff on hand the expertise to manage and enable a wide variety of

devices, testing scenarios and database access across each of the key sectors for a range of technology

readiness levels (TRLs). In this way WP3 is effectively where the main operational elements of the project

were undertaken, and it was very effectively led by IFREMER. WP 3 was also the focal point for coordinating

networking and interchange of staff between infrastructures in order to promote knowledge exchange and

transfer of good practice.

The listed objectives of WP3 were to:

Provide access to shared relevant Research Infrastructure related to marine renewable energy research. to Promote focused research activity in order to speed up development within the Ocean Energy Sector which is growing rapidly in Europe.

Foster Networking between researchers in Europe through trans-national access to the Infrastructures.

Promote Networking between the Infrastructures for training to improve capabilities of individual staff members.

Encourage interchange of research results through the User Workshop meetings

The key features of the MaRINET Transnational Access Programme were:

Facilitating and encouraging access to infrastructures located outside the users home country

Providing free-of-charge access to 45 facilities

Wave Energy

Tidal Energy

Offshore-Wind Energy & Environmental Data

Cross-Cutting Areas (electrical, moorings, materials etc.)

Facility costs are paid by the EC:

o ranging from €1,500-€30,000/week

Open to all –companies any size, research groups etc. (Uptake was predominantly SME).

Visiting group must be majority-based in EU

Over the lifetime of the project MaRINET TNA delivered:

6 calls for access 178 selected projects

315 Applications for access ~696 weeks of access

308 Eligible projects ~€3.5M costs granted

Page 15: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

The entire process from initial dissemination of an access call through submission of the final access report

by a User in respect of the findings generated was handled via the Marinet website with a specialised User

Portal section. This was set up at the start of the project with advanced functionality to manage the detailed

requirements associated with operating the access programme and enabled different levels of access

depending on role (user, facility manager, coordinator, User Selection Board etc.).

The main elements of the selection procedure used to filter applications received was as follows:

Technical assessment (Infrastructure Managers) : Technical feasibility – Level of preparedness – Schedule and planning

Scientific assessment (Internal & External Experts): Quality of Scientific content – Relevance of outcome

Selection Committee o Eligibility criteria o Technical feasibility according to Infrastructure managers assessment o Experts ranking and comments o Management of the requested time in regard of the total allocated time per infrastructure

Page 16: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

Summary of outcomes of the TNA Programme

Page 17: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated
Page 18: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

Summary of Networking activities

Staff Exchange programme:

Transnational exchange programme for personnel working within existing research infrastructures is

offered to share knowledge and experience, train new people for the sector and achieve

harmonization of procedures/practices.

This exchange programme involves training at another Infrastructure for a minimum of one week

and is for both experienced and new staff at the individual locations.

~7 Exchanges were organised , including WP2 Round Robin activity

Infrastructure benefiting from the

staff exchange programme

Hosting Infrastructure Objectives

AAU PU COaST large-scale setups in Large Lab

AAU UCC-Beaufort Management of TA access cost reporting

UCC-Beaufort Strathclyde Round Robin WP2

Ifremer wave-current flume Strathclyde Round Robin WP2

Ifremer wave-current flume CNR-INSEAN Circulating water

channel

Round Robin WP2

Tecnalia PTO Lab UCC-Beaufort Learning about Tank Testing facilities

Tecnalia PTO Lab UNEXE SWMTF Moorings testing and procedures

Page 19: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

4.1.3.3 WP4 Research to innovate and improve infrastructures technologies

and techniques

The work programme conducted under WP4 involved 23 partners and was designed to address a number of

unsolved issues that are specific to ocean energy technologies and required further research. The transition

of wind energy offshore required specific infrastructure capabilities which were different from techniques

onshore. The relevant Infrastructures also identified some key issues related to improvement of capabilities

in this area. Advantages gained from the joint research approach were:

a whole range of methods and techniques was available to bring together best available instrumentation

and data analysis methods for comparative studies for and validation of different new methods

feedback during development process from simulation and modelling, through model testing to the final

full scale field test

the different highly interdisciplinary skills from the leading research teams throughout Europe were

brought together to maximise synergies in complex generic topics such as wave current interaction and

others

techniques and methods which have in the past been used independently and were combined for testing

e.g. in hardware in the loop test combining controlled operation and real numerical modelling, water to

wire test of complete models instead of individual component tests

joint activity enabled the harmonisation of different methods in order to make results comparable e.g.

by introducing common instrumentation and data processing methods

joint activity enabled the identification of the differences and limitations of methods and techniques and

to combine the best available ones for the benefit of the whole research community.

The different activities described under this work package are consequently a combination of the

optimisation of existing instrumentation, the development of new instrumentation and the required data

processing, the development of new test methods and the introduction and validation of new theoretical

approaches from numerical modelling through tank tests to full scale field tests.

The research work was broken down into six tasks as follows:

Task 4.1: Wave Energy Infrastructure Related Research

This task investigated new methods related to remote underwater motion measurement, non-intrusive

wave field measurement, and real time estimation of incident waves. It is led by ECN (Ecole Centrale de

Nantes, France).

Task 4.2: Tidal Energy Infrastructure Related Research

This task investigated improvements in the determination of the current velocity field over a Tidal Energy

Converter’s swept area, focusing on dynamic effects from turbulence and waves and the resulting dynamic

forces in the rotor blades by improving the use of existing (as well as designing new) instrumentation, and

was led by QUB (Queen’s University Belfast, UK).

Task 4.3: Offshore-Wind Energy Infrastructure Related Research

Offshore wind turbine technology today is based on upgraded turbine concepts from onshore technologies.

This task investigated the two main areas of uncertainty remaining in this process. First was the

Page 20: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

characterisation of offshore wind at rotor scale in order to determine the dynamic performance of the

converter and the 2nd was the foundation performance analysis under different geological conditions.

Task 4.4: Cross-Cutting – Electrical Related Research

This task dealt with engineering aspects related to dynamic testing of electrical components and systems and

new analysis tools for the integration in the electrical grid. It is led by Tecnalia, Spain.

Task 4.5: Cross-Cutting – Environmental Monitoring Related Research

This task supported the understanding of the environmental effects of ocean energy devices and offshore

wind turbines on the marine environment by expanding the knowledge of environmental effects and

monitoring methods. It was led by EMEC (European Marine Energy Research Center).

Task 4.6: Cross-Cutting – Station-Keeping Related Research

This task addressed the considerable engineering challenges of finding economical mooring solutions for

marine energy converters, vital for the successful development of the sector. This requires a strong

investigation on introduced mooring dynamics, especially concerning closely packed devices in array

formations. It was led by UNEXE (University of Exeter).

The following deliverables were produced in association with the tasks listed above.

Deliverable No. (related

Task)

Deliverable Title

D4.1 EC (T4.1) Report on tank test related instrumentation and best practice

D4.2 EC (T4.4) Report on dynamic test procedures

D4.3 EC (T4.4) Report on grid integration and power quality testing

D4.4 EC (T4.6) Report on low frequency response and moorings

D4.5 (T4.1) Report on “Non-intrusive wave field measurement

D4.6 EC (T4.3) Data Reports and Data Bases on coastal and offshore wind measurements

D4.7 EC (T4.5) Best practice report on environmental monitoring and new study

techniques

D4.8 EC (T4.5) Database for environmental monitoring techniques and equipment

D4.9 EC (T4.1) Report on “Remote underwater motion measurement”

D4.10 EC (T4.1) Report on “Real Time Estimation of Incident Waves”

D4.11 EC (T4.2) Report new instrumentation and field measuring technology for tidal

currents

D4.12 EC (T4.3) Report on design and accuracy of the sensor and SHM-system

D4.13 EC (T4.6) Report on field test buoy research

D4.14 (T4.4) Report on demand-side grid compatibility

D4.15 (T4.4) Report on numerical methods for PTO systems

D4.16 (T4.3) Report on options for full scale wind resource surveying

D4.17 (T4.5) Report on environmental monitoring protocols

Some of these key results and findings are illustrated graphically to expand and explain their relevance in

the following section.

Page 21: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated
Page 22: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

The following presents some of the key outputs from work conducted during the production of D4.11 “New

instrumentation and field measuring technology for tidal currents” which was led by Pal Schmitt at QUB.

Review of ADV/ADP Technology (Acoustic Doppler Velocimetry/Profiling) which is a fast evolving field

with new methods and equipment coming available frequently.

• Industry standard to measure flow velocity and turbulence

Page 23: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

• Different methods proposed to differentiate turbulence from Doppler/instrument noise, (still issues

remaining)

• Wave affected flows challenging to assess. Currently the requirements are:

▫ Wave orbital phase should be constant along the water column,

▫ Kinematics decay with depth is based on the linear theory

▫ Kinematics decay should be similar for the 2 opposing beams

Review of Radar Use in Tidal Measurements

• European Marine Energy Centre (EMEC) has installed two OceanWaves GmbH WaMoS®II Wave

Monitoring systems

• The X-band radar signal is reflected by Bragg scattering from surface capillary roughness

• FFT analysis provides wavelength/period pairs of estimates.

• When these pairs are fitted at multiple frequencies to the dispersion relationship (𝜎 + 𝑘)2 = 𝑔. 𝑘.

tanh(𝑘. ℎ) current speed in the water can be estimated.

• The HRC software package has the potential for retrieval of more detailed temporal and spatial

current measurements from the X-band radar images on a fine grid of 150m x 150m at Billia Croo

and a coarser 600m x 600m grid at the Fall of Warness and is being evaluated.

• Satisfactory large scale validation with numerical models, but ongoing improvements

Review of procedures/expertise in field tests of marine energy technologies-impact for field testing of

tidal energy devices.

• Potential of Remotely Operated Vehicle:

▫ The maximum speed of the vehicle (usually up to 2 knots), makes it time consuming to

collect a series of data over a survey site

▫ These types of devices commonly have difficulties with station keeping in strong currents

which is a major challenge for the successful application of the technology to sites identified

for tidal energy developments

▫ Many systems use video cameras as feedback sensors making them ill-suited to sites with

low visibility

▫ Vehicles often need a dedicated deployment craft which increases the operation costs

• Optical techniques such as LDV and PIV, and large-scale particle image velocimetry (LSPIV)

Application of real /field conditions to tank /model scale testing produced a listing of facilities and

operational limits in respect of:

▫ flow turbulence

▫ interaction between current and surface waves

▫ bathymetry-induced flow deviations

▫ periodicity between ebb and flood phases in case of tidal (bi-directional) streams

Measuring turbulence upstream of a floating tidal energy converter and wake measurement of full scale

tidal turbines

• Current and Turbulence Measurement with Co-located ADP and Turbulence Profiler Data (2015

IEEE/OES Eleventh Current, Waves and Turbulence Measurement Workshop (CWTM))

• Measurement technology developed and tested on the Schottel STG turbine, Strangford Lough

during MaRINET campaign. Initial flow characterisation ustilising turbine and seabed installed

acoustic sensor arrays.

Page 24: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated
Page 25: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

WP 4 Results: Best practice report on environmental monitoring and new study techniques(D4.07, D4.8

and D4.17).

• Database for environmental monitoring techniques and equipment:

http://wiki.fp7-marinet.eu/index.php/D4.8:_Instrumentation_Database

• D4.17 Report on Environmental Monitoring Protocols

• D4.7 EC Best Practice report on environmental monitoring and new study techniques (based on the

above achieved results)

Page 26: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

4.1.4 Impact, Dissemination and Exploitation of Results (10p)

4.1.4.1 Scientific Impact

Some of the most notable scientific outcomes from the Marinet project can be appreciated with reference to

Special issue of International Journal of Marine Energy Volume 12 (2015). This journal issue contains 7 articles

which cover a wide range of topics in marine energy. The articles span wave & tidal energy and cover particular

approaches to the experimental modelling of tidal turbines as well as wave energy covering a wide domain

from instrumentation reliability for wave measurements to characterisation of power take-off systems

efficiency.

Quote from IJOME editor in chief AbuBakr S. Bahaj University of Southampton, United Kingdom

“The articles in this special issue of IJOME contain valuable experimental data that has assisted

in the development of the marine energy technologies and in some case provided validation

datasets for further numerical model development, pushing these industries ever closer to

commercialisation. It is clear that MaRINET has been successful in fulfilling its goal to promote

the R&D of marine renewable energy through offering free-of-charge access to world class

research facilities throughout Europe. The articles published here contain a snapshot of some

of the high quality research that has been undertaken through the MaRINET programme with

other work supported under the programme were submitted to IJOME as contributed articles.”

Jeffcoate et al. presented field testing results of a full-scale commercial tidal turbine in timeaveraged flows up to

2.1 m/s. A vessel-mounted testing method for field studies of medium and full-scale tidal devices has been used

to investigate the performance of a full-scale device in tidal flows under the IEC standards of data processing.

Nielsen et al. concerns experiments on a ship shaped wave energy converter in order to investigate the power

attenuation efficiency of the system in a range of regular and irregular wave conditions.

Rolland et al. addressed the need of experimental validation for numerical model developments. Both

performance and flow measurements have been used to validate the design process of a vertical axis turbine.

Armstrong et al. presented a methodology of integrating a Wave Energy Converter (WEC) into an electrical test

infrastructure incorporating Hardware-In-the-Loop (HIL). The work was aimed at demonstrating the efficiency of

the use of electrical research test infrastructures incorporating HIL simulation instead of the use of real electrical

equipment and measured signals, in combination with the simulated numerical model.

Liu et al. investigated whether the wave characteristics can be accurately measured using the wave buoys. Wave

measurements using three wave buoy models were compared to the measured waves using reference wave

gauges.

Maisondieu et al. presented the MaRINET Transnational Access program and provided a good overview of the

current research activity, as well as evidence of the requirement for specialised research facilities, in marine

energy field. Statistics on the MaRINET applications and completed projects were also presented which gave a

further overview of the development progress of different offshore renewable energy conversion technologies at

a European level.

Gaurier et al. proposed an evaluation of the efficiency of different kind of experimental infrastructures for classical

tidal turbines performance characterisation. Based on the use of a generic tribladed horizontal axis turbine in four

experimental basins, the wok presented the level of confidence on performance assessment carried out in towing

as well as in circulating tanks.

Standarisation and Best Practice

Key outputs were sets of guidelines and manuals of good practice most of which were contractual

deliverables as described in the precious section.

Page 27: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

A crucial step in arriving at a standardised set of best practises has been the success in ‘round robin’ testing

using a standardised scale model tidal device. The process enabled cross comparison between the

performances of a device, irrespective of the environment in which it was being tested. To achieve this, the

scale tidal device developed by the French Research Institute for Exploitation of the Sea (Ifremer) was tested

in two recirculating flume tanks in France and Italy and two tow-tanks in Italy and the UK. Implementing an

identical test programme at all four facilities, the round robin was the first of its kind to analyse tidal energy

and quantify the effects that different environments can have on test device performance. Consequently,

MaRINET will be able to produce a test tank calibration factor to enable the desired cross comparison.

A broad variety of research fields have been highlighted in the Research WP of Marinet, and new approaches

for offshore wave climate / tidal current / wind site assessments have been investigated and documented.

Technical research with direct impact to the offshore industry development has been performed (standardised

PTO testing methods and advanced mooring concepts), and scientific results have been successfully

introduced to the Marine Energy research Community in various paper publications and conference

presentations. The environmental impact of Marine Energy has been quantitatively evaluated and monitoring

techniques have been documented in a comprehensive data base.

The following reports (specific deliverables) are noted in terms of their potential for use and applicability

beyond the duration of the project.

List of measuring techniques frequently used; List of working sensor implementation;

Electrical/PTO test facility improvements

Database of constituent material properties determined; direct impact on commercial development

of tether; Project D-TET, Durability testing of the Exeter Tether (a novel mooring tether designed to

reduce peak loads and fatigue damage)

Database for environmental monitoring techniques and equipment

Page 28: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

4.1.4.2 Socio-economic and wider societal implications

Conspicuous societal imperatives and the associated policy landscape concerning energy autonomy and

reduction of carbon will continue to drive rapid development of renewables for the foreseeable future, and in

this context there are strong expectations of major developments in the marine renewables area. As progress

is made towards higher TRLs, cost and scale increase accordingly meaning that international collaboration

becomes increasingly more important to maintain competitiveness. MaRINET has been at the forefront in

ensuring that Europe continues to maintain a leading position, and has developed sufficient reach and critical

mass to ensure that Europe has not missed opportunities for the establishment of radical new technologies.

Owing to it’s diverse range of facility types and scale, MaRINET has fostered R&D across a broad range of TRL

levels which is recognised as being highly relevant in the context of an overarching aim to supply society with

new practically and economically viable large-scale renewable energy supply solutions in coming years.

Spanning many technologies and TRL levels is also a potent attractant for a broad range of researchers and

Institutions, which in turn provides enhanced scope for return on the very significant infrastructural

investments that have been made at Member State level.

MaRINET has also provided a cohesive coordination role which is an important enabler in the context of the

broad range of scientific and technical disciplines involved across multiple TRLs. The project’s broad

perspective in terms of geographical coverage, TRL and technologies has also provided an important platform

for highly relevant trans-disciplinary training, and international staff exchange with formal courses and more

hands-on activities being developed and delivered at key facilities. It is noteworthy that demand far

outstripped supply in these areas, a factor that will be taken into account in future initiatives.

MARiNET has also acted as a focal point for broader international collaboration, and the “brand” is now well

established internationally with very satisfactory levels of visibility and recognition among relevant

stakeholders and actors on the global stage.

The success of the MaRINET’s transnational access programme (TNA) can be regarded in the light of the key

statistics as outlined below:

Over 300 applications received from industrial and academic research groups right across the EU.

From these, 178 high quality projects were selected and granted a more than 700 weeks of access across the range of testing facilities

+/- 1.9m Euro in costs granted

These numbers provide a solid indication of the size of the direct interface that exists between individuals that

are part of the MaRINET operational community and members of external user groups drawn mainly from

SME’s and academia. It also illustrates the scale of funds involved which create economic benefits not only to

the facilities themselves, but in most cases have provided a critical opportunity for the individual research

teams to address otherwise insurmountable technological issues and development obstacles. This was a factor

repeatedly borne out in acknowledgments given in testimonies and accounts presented by facility Users during

various workshop sessions in Rome and Nantes, and can also be appreciated by reference to the post access

reports returned by users after each access period.

The great majority of testing facilities involved in MaRINET are medium to large operations in their own right,

which owe their existence to significant and investment programmes from national governments. These

facilities can have considerable fixed operational costs (staff, services etc) meaning that access to users

Page 29: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

applying through MaRINET is an important way to help ensure that spare capacity is not wasted. This

underlines the importance and value of MaRINET tank time in terms of economic contribution to the ongoing

operational feasibility of testing infrastructures. The direct and indirect socio-economic impact of research

infrastructures in their local and regional geographical context has been poorly studied to date and hence

sources of quantitative data are few. One such study is available for Orkney which identified a very significant

positive contribution to the Islands ecomomy with 10,s to 100’s of FTE equivalent jobs being directly and

indirect associated with the extensive European Marine Energy Centre testing facilitates located there.

It is clear that offshore and related research can be logistically complex and expensive, and all the more so at

the higher TRLs, in this context the pooling effect of MaRINET on European resources for renewable energy

research has positive socio-economic consequences, particularly in cases where some facilities may not have

been operating at their full capacity.

MaRINET has also provided the first opportunity to build up a strategic overview of the key features,

operational practices and other defining characteristics of the principal EU infrastructures currently operating

in the marine renewables space. In this light, the potential for adoption onto the European Strategic Forum

for Research Infrastructures (ESFRI) roadmap was identified by several of the key players in the later stages of

the project. With the name Marinerg-I, this concept was adopted and developed under the leadership of the

coordinating partner UCC, by MaRINET partners in five countries; Ireland, UK, France, Spain and Portugal into

a bid for inclusion on the 2016 ESFRI roadmap as a distributed infrastructure.

Following a stringent review process the ESFRI evaluation committee issued their final set of recommendations

on 10th November 2015 in which Marinerg-I was given “medium” as an overall score of maturity, and

designation of “emerging” as the recommended status, with the following final comment:

“Marinerg‐I is evaluated `high` for the scientific case and `medium` for its maturity. The development and provision of practical and cost‐effective renewable energy is of outmost strategic importance and Marinerg‐I building upon Marinet concerns a very promising initiative. In particular, the project would profit a lot from an immediate Design Study. Marinerg‐i is highly recommended as `emerging` project for the 2016 ESFRI Roadmap.”

In general this can be interpreted as an extremely positive outcome from a highly respected and objective source, which clearly recognises the value of MaRINET in terms of the preparatory work that has been carried out. In this regard it should be noted that nearly all other ESFRI candidates would have completed bespoke design studies in preparation for their bid based on specific multi-million Euro investments e.g. under INFRADEV, whereas MaRINET was able to build a credible case purely on the basis of what has been attained under the I3 programme.

Page 30: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated
Page 31: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

Organisation Name Email

1-Tech Jan Erik Hansen [email protected]

1-Tech Lucia Margheritini [email protected]

AAU Amélie Tetu [email protected]

AAU Peter Frigaard [email protected]

CNR-INSEAN Fabio DI Felice [email protected]

CNR-INSEAN Francesco Salvatore [email protected]

CNR-INSEAN Mario Felli [email protected]

CNR-INSEAN Roberto Penna [email protected]

DTU Helene Danielsen [email protected]

DTU Henrik Bredmose [email protected]

DTU Karen Hyllested Thielsen [email protected]

DTU Lars Nielsen [email protected]

DTU Michael Courtney [email protected]

DTU Poul Hummelshøj [email protected]

DTU Soren Larsen [email protected]

ECN Jean-Marc Rousset [email protected]

ECN Pierre Ferrant [email protected]

ECNETH Johan Peeringa [email protected]

ECNETH Peter Eecen [email protected]

ECNETH Regina Heddes [email protected]

EMEC Jennifer Norris [email protected]

EMEC John Lawrence [email protected]

EMEC Matthew Finn [email protected]

EVE Dorleta Marina [email protected]

EVE Joserra Lopez [email protected]

EVE Joserra Lopez [email protected]

EVE Yago Torre-Enciso [email protected]

FH-IWES Hanno Schnars [email protected]

FH-IWES Jochen Bard [email protected]

FH-IWES Jochen Giebhardt [email protected]

FH-IWES Mario Hornig [email protected]

FH-IWES Annegret Peters [email protected]

FH-IWES Julia Gottschall [email protected]

IFREMER Bruno Raguenes [email protected]

IFREMER Christophe Maisondieu [email protected]

IFREMER Delphine Rousic [email protected]

IFREMER Gregory Germain [email protected]

IFREMER Marc Le Boulluec [email protected]

IFREMER Peter Davies [email protected]

IFREMER Yvon Le Guen [email protected]

IPT Gilder Nader [email protected]

LUH Karsten Schröder [email protected]

Page 32: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

Organisation Name Email

LUH Khalid Abdel-Rahman [email protected]

LUH Maike Paul [email protected]

LUH Mauyumi Wilms [email protected]

LUH Niklas Scholle [email protected]

LUH Rasmus Eichstaedt [email protected]

LUH Stefan Schimmels [email protected]

LUH Stephen Lochte-Holtgreven [email protected]

NAREC Tony Robinson [email protected]

NTNU Lars Bardal [email protected]

NTNU Lars Saetran [email protected]

PU

Barbara Da Louraco Rocha De Azevedo Proença

[email protected]

PU Daniel Conley [email protected]

PU Davide Magagna [email protected]

PU Deborah Greaves [email protected]

QUB Bjoern Elsaesser [email protected]

QUB Brian O' Prey [email protected]

SEAI Graham Brennan [email protected]

SEAI Diarmaid O Connor [email protected]

SEAI John Breslin [email protected]

SEAI Brendan Cahill [email protected]

SEAI Paula Tracy [email protected]

SINTEF Atsede Endegnanew [email protected]

SINTEF Ole Christian Spro [email protected]

SINTEF Salvatore D'Arco Salvatore.D'[email protected]

TECNALIA Eider Robles [email protected]

TECNALIA Salvador Ceballos [email protected]

TTC Fred Gardner [email protected]

TTC Luc Hamilton [email protected]

TTC Peter Scheijgrond [email protected]

UCC-HMRC Brian Holmes [email protected]

UCC-HMRC Emma Knowles [email protected]

UCC-HMRC Florent Thiebaut [email protected]

UCC-HMRC Tony Lewis [email protected]

UEDIN Bill Bruce [email protected]

UEDIN Delphine Perret [email protected]

UEDIN Jennifer Mills [email protected]

UEDIN Tom Davey [email protected]

UEDIN David ingram [email protected]

UEDIN Stuart Brown [email protected]

UEDIN Jamie Grimwade [email protected]

UNEXE Lars Johanning [email protected]

Page 33: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

Organisation Name Email

UNEXE Ruth Banyard [email protected]

UNEXE Violette Harnois [email protected]

UNIFI-CRIACIV Claudio Borri [email protected]

UNIFI-CRIACIV Enzo Marino [email protected]

UNIFI-CRIACIV Lorenzo Cappietti [email protected]

UNIFI-CRIACIV Luca Facchini [email protected]

UNIFI-CRIACIV Mauro Paoli [email protected]

UNIFI-PIN Enrico Banchelli [email protected]

UNIFI-PIN Raffaele Tripodo [email protected]

UNI-STRATH Linda MacKay [email protected]

UNI-STRATH Cameron Johnstone [email protected]

UNI-STRATH Sandy Day [email protected]

UNITUS Maximo Peviani [email protected]

UNITUS Sergio Scanu [email protected]

USTUTT Andreas Rettenmeier [email protected]

USTUTT Denis Matha [email protected]

USTUTT Oliiver Bischoff [email protected]

WAVEC Carla Bacelar [email protected]

WAVEC Jose Candido [email protected]

WAVEC Miguel Lopes [email protected]

Page 34: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

4.2 4d

4.2.1 . Initial Marinet Plan for Use and Dissemination of Foreground

An important aspect of the marine renewable energy industry is the sensitivity in relation to knowledge

of device designs, data, technology etc. Ultimately, only a small number of successful designs will

prevail and reap the associated rewards, and for this reason, current technology developers are

extremely sensitive about protecting their intellectual property (IP). This industry, and the academic

research associated with it, is therefore unlike most traditional scientific endeavours whereby

knowledge is shared and advanced for the common good and advancement of science. In this industry,

knowledge and designs are generally very closely protected, similar for example to the pharmaceutical

industry which develops proprietary drug formulations.

The MaRINET Transnational Access programme operates in this context, and therefore must honour

competing EC obligations in terms of ensuring that generated foreground is publishable, while at the

same time protecting the IP of that generated foreground. In order to do this, the Project Manager

continued to operate in keeping with the previously produced MaRINET-specific rules incorporating

the EC obligations which each User-Group accepts upon making an application. This includes a user-

access report template which outlines how foreground and the testing experience should be reported,

and a suggested Access Provider/User-Group agreement which can be modified by the Access

Provider as desired.

Figure 4.2.1: Publishing foreground and protecting IP: (1) Access report template, (2) Transnational Access rules

& conditions document and (3) suggested Access Provider/User-Group Agreement

Page 35: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

Section A

Publications Uploaded directly into ECAS

Page 36: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

Section A (public)

This section includes two templates

Template A1: List of all scientific (peer reviewed) publications relating to the foreground of the project.

Template A2: List of all dissemination activities (publications, conferences, workshops, web sites/applications, press releases, flyers,

articles published in the popular press, videos, media briefings, presentations, exhibitions, thesis, interviews, films, TV clips, posters).

Page 37: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

Section B (Confidential2 or public: confidential information to be marked clearly)

N/A for Marinet

Part B1

The applications for patents, trademarks, registered designs, etc. shall be listed according to the template B1 provided hereafter.

The list should, specify at least one unique identifier e.g. European Patent application reference. For patent applications, only if applicable,

contributions to standards should be specified. This table is cumulative, which means that it should always show all applications from the beginning

until after the end of the project.

TEMPLATE B1: LIST OF APPLICATIONS FOR PATENTS, TRADEMARKS, REGISTERED DESIGNS, ETC.

Type of IP Rights3:

Confidential Click on YES/NO

Foreseen embargo date dd/mm/yyyy

Application reference(s)

(e.g. EP123456) Subject or title of application

Applicant (s) (as on the application)

2 Note to be confused with the "EU CONFIDENTIAL" classification for some security research projects.

3 A drop down list allows choosing the type of IP rights: Patents, Trademarks, Registered designs, Utility models, Others.

Page 38: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

Part B2

Please complete the table hereafter:

N/A for MARINET

Type of Exploitable Foreground4

Description of

exploitable foreground

Confidential Click on YES/NO

Foreseen embargo

date dd/mm/yyyy

Exploitable product(s) or measure(s)

Sector(s) of application5

Timetable, commercial or any other use

Patents or other IPR exploitation (licences)

Owner & Other Beneficiary(s) involved

Ex: New superconductive Nb-Ti alloy

MRI equipment

1. Medical 2. Industrial inspection

2008 2010

A materials patent is planned for 2006

Beneficiary X (owner) Beneficiary Y, Beneficiary Z, Poss. licensing to equipment manuf. ABC

In addition to the table, please provide a text to explain the exploitable foreground, in particular:

Its purpose

How the foreground might be exploited, when and by whom

IPR exploitable measures taken or intended

Further research necessary, if any

Potential/expected impact (quantify where possible)

19 A drop down list allows choosing the type of foreground: General advancement of knowledge, Commercial exploitation of R&D results, Exploitation of R&D results via standards,

exploitation of results through EU policies, exploitation of results through (social) innovation. 5 A drop down list allows choosing the type sector (NACE nomenclature) : http://ec.europa.eu/competition/mergers/cases/index/nace_all.html

Page 39: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

4.3 Report on societal implications

Data Uploaded directly to ECAS

Replies to the following questions will assist the Commission to obtain statistics and indicators

on societal and socio-economic issues addressed by projects. The questions are arranged in a

number of key themes. As well as producing certain statistics, the replies will also help identify

those projects that have shown a real engagement with wider societal issues, and thereby

identify interesting approaches to these issues and best practices. The replies for individual

projects will not be made public.

A General Information (completed automatically when Grant Agreement number is

entered.

Grant Agreement Number:

Title of Project:

Name and Title of Coordinator:

B Ethics

1. Did your project undergo an Ethics Review (and/or Screening)?

If Yes: have you described the progress of compliance with the relevant Ethics

Review/Screening Requirements in the frame of the periodic/final project reports?

Special Reminder: the progress of compliance with the Ethics Review/Screening Requirements should be

described in the Period/Final Project Reports under the Section 3.2.2 'Work Progress and Achievements'

0Yes 0No

2. Please indicate whether your project involved any of the following issues (tick

box) :

YES

RESEARCH ON HUMANS

Did the project involve children?

Did the project involve patients?

Did the project involve persons not able to give consent?

Did the project involve adult healthy volunteers?

Did the project involve Human genetic material?

Did the project involve Human biological samples?

Did the project involve Human data collection?

RESEARCH ON HUMAN EMBRYO/FOETUS

Did the project involve Human Embryos?

Did the project involve Human Foetal Tissue / Cells?

Did the project involve Human Embryonic Stem Cells (hESCs)?

Did the project on human Embryonic Stem Cells involve cells in culture?

Did the project on human Embryonic Stem Cells involve the derivation of cells from Embryos?

PRIVACY

Did the project involve processing of genetic information or personal data (eg. health, sexual

lifestyle, ethnicity, political opinion, religious or philosophical conviction)?

Did the project involve tracking the location or observation of people?

RESEARCH ON ANIMALS

Did the project involve research on animals?

Page 40: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

Were those animals transgenic small laboratory animals?

Were those animals transgenic farm animals?

Were those animals cloned farm animals?

Were those animals non-human primates?

RESEARCH INVOLVING DEVELOPING COUNTRIES

Did the project involve the use of local resources (genetic, animal, plant etc)?

Was the project of benefit to local community (capacity building, access to healthcare, education

etc)?

DUAL USE

Research having direct military use 0 Yes 0 No

Research having the potential for terrorist abuse

C Workforce Statistics

3. Workforce statistics for the project: Please indicate in the table below the number of

people who worked on the project (on a headcount basis).

Type of Position Number of Women Number of Men

Scientific Coordinator

Work package leaders

Experienced researchers (i.e. PhD holders)

PhD Students

Other

4. How many additional researchers (in companies and universities) were

recruited specifically for this project?

Of which, indicate the number of men:

Page 41: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

D Gender Aspects

5. Did you carry out specific Gender Equality Actions under the project?

Yes

No

6. Which of the following actions did you carry out and how effective were they?

Not at all

effective

Very

effective

Design and implement an equal opportunity policy Set targets to achieve a gender balance in the workforce Organise conferences and workshops on gender Actions to improve work-life balance Other:

7. Was there a gender dimension associated with the research content – i.e. wherever people were

the focus of the research as, for example, consumers, users, patients or in trials, was the issue of gender

considered and addressed?

Yes- please specify

No

E Synergies with Science Education

8. Did your project involve working with students and/or school pupils (e.g. open days,

participation in science festivals and events, prizes/competitions or joint projects)?

Yes- please specify

No

9. Did the project generate any science education material (e.g. kits, websites, explanatory

booklets, DVDs)?

Yes- please specify

No

F Interdisciplinarity

10. Which disciplines (see list below) are involved in your project?

Main discipline6:

Associated discipline6: Associated discipline6:

G Engaging with Civil society and policy makers

11a Did your project engage with societal actors beyond the research

community? (if 'No', go to Question 14)

Yes

No

11b If yes, did you engage with citizens (citizens' panels / juries) or organised civil society

(NGOs, patients' groups etc.)?

No

Yes- in determining what research should be performed

Yes - in implementing the research

Yes, in communicating /disseminating / using the results of the project

6 Insert number from list below (Frascati Manual).

Page 42: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

11c In doing so, did your project involve actors whose role is mainly to

organise the dialogue with citizens and organised civil society (e.g.

professional mediator; communication company, science museums)?

Yes

No

12. Did you engage with government / public bodies or policy makers (including international

organisations)

No

Yes- in framing the research agenda

Yes - in implementing the research agenda

Yes, in communicating /disseminating / using the results of the project

13a Will the project generate outputs (expertise or scientific advice) which could be used by

policy makers?

Yes – as a primary objective (please indicate areas below- multiple answers possible)

Yes – as a secondary objective (please indicate areas below - multiple answer possible)

No

13b If Yes, in which fields?

Agriculture Audiovisual and Media

Budget

Competition Consumers

Culture

Customs Development Economic and

Monetary Affairs

Education, Training, Youth Employment and Social Affairs

Energy Enlargement

Enterprise

Environment External Relations

External Trade

Fisheries and Maritime Affairs Food Safety

Foreign and Security Policy

Fraud Humanitarian aid

Human rights Information Society

Institutional affairs

Internal Market Justice, freedom and security

Public Health

Regional Policy Research and Innovation

Space

Taxation Transport

Page 43: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

13c If Yes, at which level?

Local / regional levels

National level

European level

International level

H Use and dissemination

14. How many Articles were published/accepted for publication in

peer-reviewed journals?

To how many of these is open access7 provided?

How many of these are published in open access journals?

How many of these are published in open repositories?

To how many of these is open access not provided?

Please check all applicable reasons for not providing open access:

publisher's licensing agreement would not permit publishing in a repository

no suitable repository available

no suitable open access journal available

no funds available to publish in an open access journal

lack of time and resources

lack of information on open access

other8: ……………

15. How many new patent applications (‘priority filings’) have been made? ("Technologically unique": multiple applications for the same invention in different

jurisdictions should be counted as just one application of grant).

16. Indicate how many of the following Intellectual

Property Rights were applied for (give number in

each box).

Trademark

Registered design

Other

17. How many spin-off companies were created / are planned as a direct

result of the project?

Indicate the approximate number of additional jobs in these companies:

18. Please indicate whether your project has a potential impact on employment, in comparison

with the situation before your project: Increase in employment, or In small & medium-sized enterprises

Safeguard employment, or In large companies

Decrease in employment, None of the above / not relevant to the project

Difficult to estimate / not possible to quantify

19. For your project partnership please estimate the employment effect

resulting directly from your participation in Full Time Equivalent (FTE =

one person working fulltime for a year) jobs:

Difficult to estimate / not possible to quantify

Indicate figure:

Page 44: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

I Media and Communication to the general public

20. As part of the project, were any of the beneficiaries professionals in communication or

media relations?

Yes No

21. As part of the project, have any beneficiaries received professional media / communication

training / advice to improve communication with the general public?

Yes No

22 Which of the following have been used to communicate information about your project to

the general public, or have resulted from your project?

Press Release Coverage in specialist press

Media briefing Coverage in general (non-specialist) press

TV coverage / report Coverage in national press

Radio coverage / report Coverage in international press

Brochures /posters / flyers Website for the general public / internet

DVD /Film /Multimedia Event targeting general public (festival, conference,

exhibition, science café)

23 In which languages are the information products for the general public produced?

Language of the coordinator English

Other language(s)

Question F-10: Classification of Scientific Disciplines according to the Frascati Manual 2002 (Proposed

Standard Practice for Surveys on Research and Experimental Development, OECD 2002):

FIELDS OF SCIENCE AND TECHNOLOGY

1. NATURAL SCIENCES

1.1 Mathematics and computer sciences [mathematics and other allied fields: computer sciences and other

allied subjects (software development only; hardware development should be classified in the

engineering fields)]

1.2 Physical sciences (astronomy and space sciences, physics and other allied subjects)

1.3 Chemical sciences (chemistry, other allied subjects)

1.4 Earth and related environmental sciences (geology, geophysics, mineralogy, physical geography and

other geosciences, meteorology and other atmospheric sciences including climatic research,

oceanography, vulcanology, palaeoecology, other allied sciences)

1.5 Biological sciences (biology, botany, bacteriology, microbiology, zoology, entomology, genetics,

biochemistry, biophysics, other allied sciences, excluding clinical and veterinary sciences)

2 ENGINEERING AND TECHNOLOGY

2.1 Civil engineering (architecture engineering, building science and engineering, construction engineering,

municipal and structural engineering and other allied subjects)

2.2 Electrical engineering, electronics [electrical engineering, electronics, communication engineering and

systems, computer engineering (hardware only) and other allied subjects]

2.3. Other engineering sciences (such as chemical, aeronautical and space, mechanical, metallurgical and

materials engineering, and their specialised subdivisions; forest products; applied sciences such as

geodesy, industrial chemistry, etc.; the science and technology of food production; specialised

7 Open Access is defined as free of charge access for anyone via Internet. 8 For instance: classification for security project.

Page 45: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

technologies of interdisciplinary fields, e.g. systems analysis, metallurgy, mining, textile technology

and other applied subjects)

3. MEDICAL SCIENCES

3.1 Basic medicine (anatomy, cytology, physiology, genetics, pharmacy, pharmacology, toxicology,

immunology and immunohaematology, clinical chemistry, clinical microbiology, pathology)

3.2 Clinical medicine (anaesthesiology, paediatrics, obstetrics and gynaecology, internal medicine, surgery,

dentistry, neurology, psychiatry, radiology, therapeutics, otorhinolaryngology, ophthalmology)

3.3 Health sciences (public health services, social medicine, hygiene, nursing, epidemiology)

4. AGRICULTURAL SCIENCES

4.1 Agriculture, forestry, fisheries and allied sciences (agronomy, animal husbandry, fisheries, forestry,

horticulture, other allied subjects)

4.2 Veterinary medicine

5. SOCIAL SCIENCES

5.1 Psychology

5.2 Economics

5.3 Educational sciences (education and training and other allied subjects)

5.4 Other social sciences [anthropology (social and cultural) and ethnology, demography, geography

(human, economic and social), town and country planning, management, law, linguistics, political

sciences, sociology, organisation and methods, miscellaneous social sciences and interdisciplinary ,

methodological and historical S1T activities relating to subjects in this group. Physical anthropology,

physical geography and psychophysiology should normally be classified with the natural sciences].

6. HUMANITIES

6.1 History (history, prehistory and history, together with auxiliary historical disciplines such as

archaeology, numismatics, palaeography, genealogy, etc.)

6.2 Languages and literature (ancient and modern)

6.3 Other humanities [philosophy (including the history of science and technology) arts, history of art, art

criticism, painting, sculpture, musicology, dramatic art excluding artistic "research" of any kind,

religion, theology, other fields and subjects pertaining to the humanities, methodological, historical and

other S1T activities relating to the subjects in this group]

Page 46: PROJECT FINAL REPORT - CORDIS · concept model through to prototype testing, technical deployment and its final implementation as a commercial unit. Each of these stages is correlated

11. FINAL REPORT ON THE DISTRIBUTION OF THE

EUROPEAN UNION FINANCIAL CONTRIBUTION

This report shall be submitted to the Commission within 30 days after receipt of the final

payment of the European Union financial contribution.

Report on the distribution of the European Union financial contribution

between beneficiaries

Name of beneficiary Final amount of EU contribution per

beneficiary in Euros

1.

2.

n

Total