project cost management
DESCRIPTION
spmTRANSCRIPT
![Page 1: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/1.jpg)
![Page 2: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/2.jpg)
“The processes involved in planning, estimating, budgeting, and controlling costs so that the budget can be completed within the approved budget”
![Page 3: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/3.jpg)
Profits are revenues minus expenses Life cycle costing is estimating the cost
of a project plus the maintenance costs of the products it produces
Cash flow analysis is determining the estimated annual costs and benefits for a project
Benefits and costs can be tangible or intangible, direct or indirect.
![Page 4: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/4.jpg)
Part of triple constraint, can’t manage one without the others (scope, time, and quality)
Plots of cost and scope against plan can help spot problems early
Cumulative Value
Time
Planned Value (PV)
Actual Costs (AC)
Earned Value (EV)
Today
Is this project over/under budget?
Is it ahead of/behind schedule?
![Page 5: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/5.jpg)
PV - Planned Value, estimated value of the planned work
EV – Earned Value, estimated value of work done AC – Actual Cost, what you paid BAC – Budget at Completion, the budget for the
total job EAC –Estimate at Completion, what is the total job
expected to cost? ETC – Estimate to Complete, forecasted costs to
complete job VAC – Variance at Completion, how much
over/under budget do we expect to be?
![Page 6: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/6.jpg)
Three processes› Estimate Costs› Determine Budget› Control Costs
Estimate
Costs
Determine Budget
Control
Costs
![Page 7: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/7.jpg)
Enterprise Environmental Factors
Organizational Process Assets
Project Scope Statement
Analogous estimating
Determine resource cost rates
Bottom up estimating
Parametric estimating
Project management software
Vendor bid analysis
Reserve analysis
Cost of quality
Inputs OutputsTools & Techniques
Work Breakdown Structure
WBS Dictionary
Project Management Plan
•Schedule Mgmt Pln
•Staffing Mgmt Pln
•Risk Register
Activity Cost Estimates
Activity Cost Estimates Supporting Detail
Requested Changes
Cost Management Plan Updates
Estimate
Costs
Determine Budget
Control
Costs
![Page 8: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/8.jpg)
Analogous (Top Down) estimating – Managers use expert judgment or similar project costs [quick, less accurate]
Bottom-Up estimating – People doing work estimate based on WBS, rolled up into project estimate [slow, most accurate]
Parametric estimating – Use mathematical model (i.e. cost per sq ft). [accuracy varies] Two types:
Regression analysis – based on analysis of multiple data points
Learning Curve – The first unit costs more than the 100th, forecasts efficiency gains
![Page 9: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/9.jpg)
Vendor Bid Analysis – Estimating using bids + allowances for gaps in bid scope [slow, accuracy depends on gaps]
Reserve Analysis – Adding contingency to each activity cost estimates as zero duration item [slow, overstates cost]
![Page 10: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/10.jpg)
Barry Boehm helped develop the COCOMO models for estimating software development costs
Parameters include source lines of code or function points
COCOMO II is a computerized model available on the Web
Boehm suggests that only parametric models do not suffer from the limits of human decision-making
![Page 11: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/11.jpg)
Project Scope StatementCost aggregation
Reserve analysis
Parametric estimating
Funding limit reconciliationInputs
OutputsTools & Techniques
Cost Baseline
Project Funding Requirements
Cost Management Plan Updates
Requested Changes
Work Breakdown Structure
WBS Dictionary
Activity Cost Estimates
Activity Cost Estimates Supporting Detail
Project Schedule
Resource Calendars
Contract
Cost Management Plan
Estimate
Costs
Determine Budget
Control
Costs
![Page 12: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/12.jpg)
Budgeting is allocating costs to work packages to establish a cost baseline to measure project performance
Remember Contingency items are for unplanned but required changes it is not to cover things such as:› Price escalation› Scope & Quality Changes
Funding Limit Reconciliation – Smoothing out the project spend to meet management expectations
![Page 13: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/13.jpg)
Cost Baseline
Project Funding Requirements
Performance Reports
Cost change control system
Performance measurement analysis
Forecasting
Project performance reviews
Project management software
Variance management
Inputs OutputsTools & Techniques
Work Performance Information
Approved Change Requests
Project Management Plan
Cost Estimate Updates
Cost Baseline UpdatesPerformance Measurements
Forecasted Completion
Requested Changes
Recommended Corrective Actions
Organizational Process Assets Updates
Project Management Plan Updates
Estimate
Costs
Determine Budget
Control
Costs
![Page 14: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/14.jpg)
Progress is compared against the baseline to determine whether project is ahead of or behind plan
Percent complete can be difficult to measure, some managers use rules › 50/50 Rule – Assumed 50%
complete when task started, final 50% at completion
› 20/80 Rule – 20% at start› 0/100 Rule – No credit until
complete
Planned Value Planned Value (PV) – Budgeted (PV) – Budgeted CostCost
Earned Value Earned Value (EV) – Actual (EV) – Actual work completedwork completed
Actual Cost (AC) Actual Cost (AC) – Costs incurred– Costs incurred
Estimate to Estimate to Complete (ETC) Complete (ETC) – What’s Left– What’s Left
Estimate at Estimate at Completion (EAC) Completion (EAC) – What final cost – What final cost will bewill be
![Page 15: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/15.jpg)
Variance at Completion
(VAC)
Target Cost &
Schedule
Schedule Variance (Time)
Planned Value (PV)
Earned Value (EV)
![Page 16: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/16.jpg)
NAMENAME FORMULAFORMULA NOTESNOTESCost Variance (CV)Cost Variance (CV) EV-ACEV-AC Negative = Over budget Negative = Over budget
Positive = Under budgetPositive = Under budget
Schedule Variance Schedule Variance (SV)(SV)
EV-PVEV-PV Negative = Behind Schedule Negative = Behind Schedule
Positive = Ahead of SchedulePositive = Ahead of Schedule
Cost Performance Cost Performance Index (CPI)Index (CPI)
EV/ACEV/AC How much are we getting for every How much are we getting for every dollar we spend?dollar we spend?
Schedule Perform Schedule Perform Index (SPI)Index (SPI)
EV/PVEV/PV Progress as % against planProgress as % against plan
Estimate to Complete Estimate to Complete (ETC)(ETC)
EAC-ACEAC-AC How much more do we have to How much more do we have to spend?spend?
Variance at Variance at Completion (VAC)Completion (VAC)
BAC-EACBAC-EAC At the end of the day, how close will At the end of the day, how close will we be to plan?we be to plan?
Estimate at Estimate at Completion (EAC)Completion (EAC)
See following slideSee following slide
![Page 17: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/17.jpg)
NAMENAME FORMULAFORMULA NOTESNOTESEstimate at Estimate at Completion (EAC)Completion (EAC)
BAC/CPIBAC/CPI Use if no variancesUse if no variances from from BAC have occurredBAC have occurred
AC+ATCAC+ATC Use when original Use when original estimate was bad. Actuals estimate was bad. Actuals + New estimate+ New estimate
AC+BAC-EVAC+BAC-EV Use when current Use when current variances are not expected variances are not expected to be there in the futureto be there in the future
AC+(BAC-EV)/CPIAC+(BAC-EV)/CPI Use when current Use when current variances are expected to variances are expected to continuecontinue
![Page 18: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/18.jpg)
Spreadsheets are a common tool for resource planning, cost estimating, cost budgeting, and cost control
Many companies use more sophisticated and centralized financial applications software for cost information
Project management software has many cost-related features
![Page 19: Project Cost Management](https://reader034.vdocuments.us/reader034/viewer/2022051621/55cf8f5a550346703b9b76f8/html5/thumbnails/19.jpg)