Project Contingency Chris Vizzuett

If you wish a transcript of the presentation email me at [email protected]

Page 2: Project Contingency sanitised

An assessed cost to cover project risk (known / unknowns)

and uncertainties based on an established scope of work.

Contingency is not intended to cover Client Change Orders

and out of scope changes.

If you wish a transcript of the presentation email me at [email protected]

Page 3: Project Contingency sanitised

An assessed cost to cover project risk (known / unknowns)

and uncertainties based on an established scope of work.

Contingency is not intended to cover Client Change Orders

and out of scope changes.

guesstimate mostly

our understanding

of the

The Client will try to

use the project’s

If you wish a transcript of the presentation email me at [email protected]

Page 4: Project Contingency sanitised

An assessed cost to cover project risk (known / unknowns)

and uncertainties based on an established scope of work.

Contingency is not intended to cover Client Change Orders

and out of scope changes.

guesstimate mostly

our understanding

of the

The Client will try to

use the project’s

Your Business Unit Manager expects you not to spend

it and to give it back in order to improve the Unit’s

profit this quarter.If you wish a transcript of the presentation email me at [email protected]

Page 5: Project Contingency sanitised

If you wish a transcript of the presentation email me at [email protected]

Page 6: Project Contingency sanitised

If you wish a transcript of the presentation email me at [email protected]

Page 7: Project Contingency sanitised

Schedule contingency

CostcontingencyIf you wish a transcript of the presentation email me at

[email protected]

Page 8: Project Contingency sanitised

CARMICHAEL COAL PROJECT

Mine• Underground (2x) and open-cut 60Mtpa• Coal handling processing plant• Associated infrastructure

Railway• 388 km standard railway• 24 k tonnes per load

Coal Terminal• Adjacent to existing terminal• Jetty, wharf, transfer towers, shiploaders

If you wish a transcript of the presentation email me at [email protected]

Page 9: Project Contingency sanitised

SCOPE

Bankable Feasibility Study (3x)

Three separate packages• Design• Procurement• Construction• Class 3 estimate (OPEX and CAPEX)

• Class 3 execution schedule• Investment model

If you wish a transcript of the presentation email me at [email protected]

Page 10: Project Contingency sanitised

SCOPE

Bankable Feasibility Study (3x)

Three separate packages• Design• Procurement• Construction• Class 3 estimate• Class 3 execution schedule• Investment model

If you wish a transcript of the presentation email me at [email protected]

Page 11: Project Contingency sanitised

SCOPE

Bankable Feasibility Study (3x)

Three separate packages• Design• Procurement• Construction• Class 3 estimate• Class 3 execution schedule• Investment model

If you wish a transcript of the presentation email me at [email protected]

Page 12: Project Contingency sanitised

Schedule• Build execution schedule• Produce mini-schedule

Risks • Identify discrete risks• Preliminary schedule confidence ranging

Workshop

Build model • Primavera risk analysis

Run model • Monte Carlo simulation

Contingency • P10 to P90• Days and dollars

If you wish a transcript of the presentation email me at [email protected]

Page 13: Project Contingency sanitised

Schedule

If you wish a transcript of the presentation email me at [email protected]

Page 14: Project Contingency sanitised

Schedule Risks

Sch. uncertainty

Discrete risk

Expected weather

If you wish a transcript of the presentation email me at [email protected]

Page 15: Project Contingency sanitised

Schedule Risks Sch. uncertainty

Discrete risk

Expected weather

If you wish a transcript of the presentation email me at [email protected]

Page 16: Project Contingency sanitised

Schedule Risks Sch. uncertainty

Discrete risk

Expected weather

If you wish a transcript of the presentation email me at [email protected]

Page 17: Project Contingency sanitised

Schedule Risks Sch. uncertainty

Discrete risk

Expected weather

If you wish a transcript of the presentation email me at [email protected]

Page 18: Project Contingency sanitised

Schedule Risks Sch. uncertainty

Discrete risk

Expected weather

If you wish a transcript of the presentation email me at [email protected]

Page 19: Project Contingency sanitised

Schedule Risks Workshop

If you wish a transcript of the presentation email me at [email protected]

Page 20: Project Contingency sanitised

Schedule Risks Workshop Build model

If you wish a transcript of the presentation email me at [email protected]

Page 22: Project Contingency sanitised

Schedule Risks Workshop Build model Run model Contingency

30-Mar-18 22-Jun-18 13-Sep-18 05-Dec-18 27-Feb-19 21-May-19

Distribution (start of interval)

0

200

400

600

800

1000

1200

Hits

0% 24-Mar-18

5% 03-May-18

10% 14-May-18

15% 22-May-18

20% 29-May-18

25% 04-Jun-18

30% 11-Jun-18

35% 17-Jun-18

40% 23-Jun-18

45% 30-Jun-18

50% 07-Jul-18

55% 13-Jul-18

60% 20-Jul-18

65% 28-Jul-18

70% 04-Aug-18

75% 14-Aug-18

80% 25-Aug-18

85% 08-Sep-18

90% 30-Sep-18

95% 22-Nov-18

100% 14-Jul-19

Cum

ulat

ive

Freq

uenc

y

Carmichael Coal Mine Risk Assessment Programme 140711 v2 (Post-mitigated)475 - Mine Practical Completion : Finish Date

P10 P50 P70 P 90

Practical Completion 51 105 133 190

If you wish a transcript of the presentation email me at [email protected]

Page 23: Project Contingency sanitised

Schedule Risks Workshop Build model Run model Contingency

14%14%

14%

14%

14%14%

14%

14%

14%

40%42%

73%82%82%

84%

84%86%

86%

86%

86%

100%475 - Mine Practical Completion

905 - Lonw all 2 Development

935 - Longw all 2 Installation

945 - Lonw all 2 - No Load/Load Commissioning

405 - Underground - Longw all 2 First Coal875 - Pit Wall and f loor bottom Stabilisation

885 - Box Cut complete

305 - Mine Lease Granted

865 - Box Cut Excavation

515 - Mining Lease (ML)

835 - Construct temporary access through to Underground Mine855 - Flood Protection Levee

435 - CHPP complete

1115 - Wet Commissioning

315 - Financial Close complete

395 - Underground - Longw all 1 First Coal425 - CHP A complete

1095 - ROM and RAW Coal handling

505 - Financial Close process

1075 - Contractor Mobilisation

1085 - Civil and earthw orks

Carmichael Coal Mine Risk Assessment Programme 140711 v2 (Post-mitigated)Criticality Index

Page 24: Project Contingency sanitised

Useful tipsUseful tips

Page 25: Project Contingency sanitised

Do not underestimate the time required to explain:- process - meaning of P10…- importance of inputs- evidence-based risk assessment

Page 26: Project Contingency sanitised

Quality of the Schedule PRM READINESS GUIDELINES FOR P6 SCHEDULE

• Activity Relationships.• Lags.• Constraints or Imposed Dates.• The objective is for the critical path(s) to

be the result of pure logic and durations from beginning to end. In any case, there should be minimal date constraints in the logic network.

• Other Concerns for P6:Out-of-Sequence LogicAll actual dates must be earlier than the data date;Before the P6 schedule is loaded into PRA, all WBS, Hammocks and level-of-effort activities should be deleted.

• Ensure there is no negative float in the schedule.

Page 27: Project Contingency sanitised

Attitudes towards risk

One World, different views…

Past experiences

Organisational culture

Local knowledge

Page 28: Project Contingency sanitised

Client already has an expected outcome in mind

Page 29: Project Contingency sanitised

These are only tools…

Page 30: Project Contingency sanitised