project brunel presentation 26th february 2016 · 2016-03-01 · finalproposal submission to dclg...
TRANSCRIPT
Project Brunel Presentation
26th February 2016
Investment Pooling
Local Government Pension Scheme pooled investments –
The government will work with Local Government Pension
Scheme administering authorities to ensure that they pool
investments to significantly reduce costs, while maintaining
overall investment performance. The government will invite
local authorities to come forward with their own proposals to
meet common criteria for delivering savings. A consultation
to be published later this year will set out those detailed
criteria as well as backstop legislation which will ensure that
those administering authorities that do not come forward
with sufficiently ambitious proposals are required to pool
investments.
July Budget Statement:
Government Timetable
Date Requirement
19th February
Initial submission:
• Should include a commitment to pooling.
• A description of progress towards formalising their arrangements with other authorities.
• Can be joint with pool or an individual submission.
15th July
Detailed submission: • For each pool, a joint proposal setting out detail
of governance structures, decision-making processes and implementation timetable.
• For each authority, an individual return detailing commitment to, and expectations of, the pool, including profile of costs and savings, the transition profile for their assets, and rationale for any assets they intend to hold outside of the pool in the long term.
Government Criteria
Issue Description Summary of Requirements
A. Scale of assets under management
• The size of pool once fully operational, and its legal type.
• Assets outside of pool and rationale.
• Internal work and services to be hired.
• Timetable for establishment and asset transition.
B.
Strong governance and decision making
• Accountability between pool and elected members, external scrutiny.
• Mechanisms for Authorities to hold pool to account.
• The process for decision making at all stages of investment.
• Resourcing
• Net performance publication, benchmark usage.
Government Criteria
Issue Description Summary of Requirements
C. Substantial cost savings
• An estimate of investment costs for the year to 31 March 2013 and the current level investment costs.
• Detail on cost savings over 15 years.
• Estimate of implementation and transition costs.
• Proposals for reporting against forecasts.
D. Improved infrastructure capability
• The existing proportion of Fund allocated to infrastructure.
• Proposals to acquire capacity and capability to assess infrastructure projects with reduced costs via pooling.
• Future proportion of Fund to be allocated and how derived.
Current Pooling Proposals
Brunel Pool
Brunel Timetable
Item Date
Project Brunel appoints financial and legal advisors August 2015
Options feasibility report (PwC) September 2015
Development of governance and business case models (PwC) October to December 2015
Work on new Sub-Fund requirements (Fund representatives) Ongoing
Meeting of Committee Chairs and feedback from Funds 7 January 2016
Review initial draft of proposal document for DCLG 18 January 2016
Pension Committee meetings to approve initial proposalLate January/early February
2016
Initial proposal submission to DCLG 19 February 2016
Feedback from DCLG on initial proposal March 2016?
Development of final proposal March to June 2016
Pension Committee meetings to approve final proposal Late June 2016
Final proposal submission to DCLG 15 July 2016
Legal StructureOption Description
1.
Collective Asset Pool governed by a Joint Committee
• with Oversight Group, Operations Groups and Portfolio Construction Groups
• Commercial organisation provides unitisation service
2.
Authorised Contractual Scheme (ACS)
Commercial organisation rented as ACS Operator
• The service enables Brunel people to influence investment appointments
3.
Authorised Contractual Scheme (ACS)
Commercial organisation rented as ACS Operator
• The service is fiduciary, leading on investment management appointments
4.
Authorised Contractual Scheme (ACS)
ACS Operator would be built by Brunel Founder Funds
• A longer term option, following Option 1 or 2?
Comparison between Options 1 and 2
CAP/Joint Committee ACS, rented Operator
Comparison between Options 1 and 2
CAP/Joint Committee ACS, rented OperatorChallenges, resourcing and operations
Operational simplicity
A secretariat for the IOp Joint Committee would be required. Clusters of IMAs.
The Operator would aim at simplicity. Its expertise would be available. Single IMAs.
External entity appointments
The Custodian would be required to deliver unitisation as an additional service.
The rented Operator would deliver unitisation.
Control of unit pricing policy
A pricing policy would be possible, with clarity on potentially contentious situations.
The Operator should be open to pricing policy inputs in some areas.
Retain existing experience
Extensive knowledge from investment teams required by the IOp. Keyman risk is avoidable.
Some reduction in the inputs now made by investment teams possible, depends on Operator approach.
Regulatory capital No regulatory capital required.
Regulatory capital costs likely to be included in Operator fee structures.
Pooling internally managed assets
Possible if internal staff placed in a new, FCA authorised, entity.
Possible if internal staff placed in a new, FCA authorised, entity. Operator approval also needed.
Operational cost control
Focus required on internal cost control.
Focus required on Operator costs and terms of business.
Ownership of assets Founder Funds retain legal as well as beneficial ownership.
Founder Funds retain beneficial but not legal ownership.
Investment manager procurement
OJEU processes not required for existing managers, but likely for new managers.
OJEU processes not applicable, but would still have to demonstrate value for money.
Operations
Group
Oversight
Group
Board reports to Participating
Funds on Operator performance
Recommendations
LGPS Fund
LGPS Fund
LGPS Fund
Founder Funds
LGPS Fund
LGPS Fund
LGPS Fund
LGPS Fund
LGPS Fund
• Manager selection
<-------------------------------------------------------------Investment Managers-------------------------------------------------------->
Sub-fund 1
UK Equities
Sub-fund 2
..
Sub-fund 3
…
Sub-fund …
…
Sub-fund …
..
Sub-fund …
..
Sub-fund 20
…
Each
Investment
Manager
contracts
with
individual
LGPS Funds
Administrator
Depositary(Third Party)
Global Custodian (Third Party)
Resourcing:
Pension Committee
Chairs
Resourcing:
Section 151
Officers,
Investment
Officers
Manager
selection
Unitisation
• Oversight and
ratification
Portfolio Construction
Groups
PCG 1 Growth Liquid
PCG 2 Infrastructure, other
growth, Illiquid
PCG 3 Stabilising, Liquid
PCG 4 Stabilising, Illiquid
PCG 5 LDI
Local pension board
Local
oversight Administering Authority
Pensions Committee
Investment sub-committee
Delegation
Delegation
• Funding strategy
• Asset Allocation
• Manager Selection
• MiFID II compliance
required
• Manager
appointment
• Meeting and
reporting
• Selects the range of
Sub-funds
Resourcing:
Investment Officers
Option 1: Collective Asset Pool (Joint Committee)
Portfolio Construction Groups
and Sub Funds
Growth - Illiquid
Infrastructure
Private Equity
Property
Stabilising - Liquid
Gilts
Index Linked
Corporate Bonds
Multi Asset Credit
Absolute Return Bonds
Overseas Sovereign Debt
Stabilising - Illiquid
Infrastructure Debt
Private Debt
Secured Loans Liability Driven
Investment
Growth - Liquid
Developed Equities - Core
(index + 1-2%)
Developed Equities - High Alpha
(index + 3% or more)
Emerging Market Equities
(index + 1-2%)
Frontier Market Equities
(index + 1-2%)
Sustainable Equities
(index + 1-2%)
Passive Equities
(index tracker)
Passive Equites - Smartbeta
(index +)
Multi Asset (DGF)
(cash +)
Hedge Funds
Emerging Market Debt
High Yield
Savings
Year 2026 (if transfer of
unlisted assets complete)
Option 1
(Joint Committee)
Option 2
(Rented ACS)
Option 1 vs
Option 2
Net predictable
performance savings16.0 16.0 0.0
ACS (rented) Operator
Cost- -1.9 1.9
JC Custodian
Unitisation Cost-1.1 - -1.1
Other costs including
Staffing-0.6 -0.3 -0.3
Net savings 14.3 13.8 0.5
• Aspirational target to make further savings
to achieve total savings of £60m - £70m.
Infrastructure
• Already significant commitment from
founder funds of the Brunel CAP.
• Devon Fund has a 4% target, with c. £150m
committed and c. £95m invested.
• Aspiration to support national initiatives.
• Must be the right type of investment to meet
Fund’s fiduciary duty and investment
objectives.
• Consider increase in target allocation for
July submission?