![Page 1: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/1.jpg)
Chico Urban Area Nitrate Compliance Program
Project Area 1S Neighborhood MeetingNovember 14, 2011
![Page 2: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/2.jpg)
WELCOME
Larry WahlButte County Supervisor, District 2
![Page 3: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/3.jpg)
Agenda• Nitrate Compliance Program Information• Construction Update• Planned County Road Improvements• Benefits of Connection• Application Process• How to Connect to Sewer• Available Assistance• Questions
![Page 4: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/4.jpg)
NITRATE COMPLIANCE PROGRAM
Casey HatcherProgram Development ManagerButte County Administration
![Page 5: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/5.jpg)
Nitrate Compliance Program
• 1990 Regional Water Quality Control Board adopts Prohibition Order No. 90-126– Prohibits installation of new septic systems after July
1990.– Eliminates existing septic systems on lots of less than 1
acre by July 1995.– City and County agreed to review Prohibition Order and
develop responses and propose alternatives to the State.
![Page 6: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/6.jpg)
Nitrate Compliance Program
• 2000 Nitrate Compliance Plan Adopted– Plan included proposed solutions to nitrate
problem as proposed by a technical team and Citizen’s Nitrate Advisory Committee.
– Plan stated 7,800 dwelling units to be connected to City sewer.
– Today that number is closer to 5,600.
![Page 7: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/7.jpg)
Nitrate Compliance Program
• 2008 State Revolving Loan Fund– City and County create mechanism for property
owners to more cost effectively comply with Prohibition Order.
– City and County worked together to secure financing for the public improvements.
• Sewer main• Sewer laterals to the edge of the property line
![Page 8: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/8.jpg)
Nitrate Compliance Program
• 2009 First Phase of Public Improvements– Project Area 1N – Lassen Avenue Area
• Esplanade, Lassen, Cohasset
• 2010 Second Phase of Public Improvements– Project Area 1S – Chapman/Mulberry Area
• Humboldt, Chapman, Mulberry, Pomona
![Page 9: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/9.jpg)
CONSTRUCTION UPDATEPROJECT AREA 1SCHAPMAN, HUMBOLDT, MULBERRY AND POMONA
Tamara Miller, P.E.MPM Engineering
![Page 10: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/10.jpg)
Overview – What Was Included• Sewer mains• Sewer laterals within public right-of-way• Manholes• Repair of trench including replacement of
curb, gutter and sidewalks to match pre-existing conditions
10
![Page 11: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/11.jpg)
Overview – What Was Not Included • Storm drains and drainage systems• Road improvements
– Only repair of backfill trench• New curb, gutter & sidewalks
– Only repair to match pre-existing conditions• Installation of sewer laterals on private property or
septic tank decommissioning– This is “on-site” work, responsibility of property owner
11
![Page 12: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/12.jpg)
Construction Process
• Lions, Tigers, and Bears Oh My!or
• Laterals, Trenches, and Manholes, Oh My!
![Page 13: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/13.jpg)
Step 1 in Construction: Potholing
![Page 14: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/14.jpg)
Step 2 in Construction: Trenching
![Page 15: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/15.jpg)
Step 2 in Construction: Trenching
![Page 16: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/16.jpg)
Step 3 in Construction: Install Pipe
![Page 17: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/17.jpg)
Step 3 in Construction: Install Pipe
![Page 18: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/18.jpg)
Step 4 in Construction: Cold-Patch
![Page 19: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/19.jpg)
Step 5 in Construction: Install Laterals
![Page 20: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/20.jpg)
Step 5 in Construction: Install Laterals
![Page 21: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/21.jpg)
Step 5 in Construction: Install Laterals
![Page 22: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/22.jpg)
Step 5 in Construction: Install Laterals
![Page 23: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/23.jpg)
Step 5 in Construction: Install Laterals
![Page 24: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/24.jpg)
Step 6 in Construction: Test
![Page 25: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/25.jpg)
Step 7 in Construction: Hot Mix Paving
![Page 26: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/26.jpg)
Step 8 in Construction: Manholes to grade
![Page 27: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/27.jpg)
Step 9 in Construction: Striping corrected
![Page 28: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/28.jpg)
And of course… there’s conflict
![Page 29: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/29.jpg)
And of course… there’s conflict
![Page 30: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/30.jpg)
And of course… there’s conflict
![Page 31: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/31.jpg)
Project Area C-8, Humboldt
Contractor: R&R HornConstruction Began: June 23, 2011Construction Ended: October 20, 2011Working Days: 75Sewer: 4,518 ft.Laterals: 148 lateralsManholes: 24
![Page 32: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/32.jpg)
Construction Area C-9, Chapman
Contractor: Visinoni BrothersConstruction Began: June 7, 2011Construction Ending: December 9, 2011Working Days: 120Sewer: 15,405 ft.Laterals: 278 lateralsManholes: 52
![Page 33: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/33.jpg)
Project Areas C-10 and C-11, Mulberry
Contractor: Duke Sherwood Contracting Inc.Construction Began: July 18, 2011Construction Ended: October 20, 2011Working Days: 60Sewer: 1,769 ft.Laterals: 102 lateralsManholes: 9
![Page 34: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/34.jpg)
Project Areas W-9 and W-10, Pomona
Contractor: RJ Heuton ConstructionConstruction Began: August 30, 2011Construction Ending: December 6, 2011Working Days: 60Sewer: 2,027 ft.Laterals: 73 lateralsManholes: 11
![Page 35: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/35.jpg)
COUNTY ROAD IMPROVEMENTS
Mike CrumpPublic Works DirectorButte County
![Page 36: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/36.jpg)
Future County Road Improvements
• Cape Seal for all unincorporated roads in the Chapman and Mulberry neighborhoods.
• Road improvements planned for Summer 2012
![Page 37: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/37.jpg)
Cape Seal
• Combination of chip seal followed in a few days by a slurry of microsurfacing.
![Page 38: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/38.jpg)
Cape Seal Application• Prepare roadway.• Apply chip seal.• Chip seal cures (48 hrs.+).• Apply slurry seal.
![Page 39: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/39.jpg)
Cape Seal Duration
• Lasts longer than chip seal or slurry alone.
• Smoother for pedestrians and bicycles.
![Page 40: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/40.jpg)
BENEFITS OF CONNECTION
Casey HatcherProgram Development ManagerButte County Administration
![Page 41: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/41.jpg)
Benefits of Connection
• Provides a means for property owners to comply with Prohibition Order.
• Reduces septic tank maintenance issues and costs.
• Increases re-sale value of the home.• Construction costs potentially lower now due
to downturn of the economy.(Continued…)
![Page 42: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/42.jpg)
Benefits of Connection• Ability to cooperate with your neighbors to
hire a single contractor which could lower construction costs and save time.
• Current fee savings for properties within project area of approximately $5,650.
• Through sewer connections in Project Area 1S, approximately 2.4 tons of nitrate load will be eliminated.
![Page 43: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/43.jpg)
SEWER FEES & APPLICATION PROCESS
Matt ThompsonSenior Civil EngineerCity of Chico Building & Development Services Department
![Page 44: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/44.jpg)
Typical Sewer FeesLateral $29.81/ft.Main Line $47.80/ft.WPCP $2,251/unitTrunk Line $1,693/unit
Project Area 1S FeesLateral $0/ft.Main Line $0/ft.WPCP $0/unitTrunk Line $1,693/unit
Approximate Fee Savings for Property Owners within Nitrate Compliance Program Boundaries:
$5,600
![Page 45: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/45.jpg)
Sewer Application Process
• Submit a Sewer Application– Application is only one sheet– Application fee is $100.00
• Sign LAFCO covenant regarding future annexation (requirement of interim sewer agreement).
• You will receive a letter indicating connection fees and the steps to sewer connection.
![Page 46: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/46.jpg)
Payment of Sewer Fees
• Pay at issuance of plumbing permit, or• In-lieu payment
– In-lieu process allows fee to be paid over ten year period.– Application for in-lieu is $338 (fee can be financed). – A recent title report or lot book guarantee is required. Title
companies do charge for these documents.
![Page 47: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/47.jpg)
Permits RequiredPermit Issuing Agency Fee
Plumbing Permit City of Chico $131
Septic Abandonment Butte County $117
![Page 48: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/48.jpg)
HOW TO CONNECT TO SEWER
Tamara Miller, PEMPM Engineering
![Page 49: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/49.jpg)
How to Connect to Sewer
After application completed, the steps for sewer connection include:• Plumbing Permit• Hire a Contractor• Locate Lateral
(Continued…)
![Page 50: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/50.jpg)
How to Connect to Sewer
Steps to sewer connection continued:• Dig a Trench• Place a pipe and connect • Inspection• Fill in the Trench• Empty and crack Septic Tank• Final Approval
![Page 51: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/51.jpg)
How to Connect to Sewer
• Do I hire a contractor?• How much time will the construction take?
– Estimated time is 2 days.• What are the costs?
– Estimated cost for improvements, permits and fees is $5,000 to $6,000.
![Page 52: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/52.jpg)
AVAILABLE ASSISTANCE
Casey HatcherProgram Development ManagerButte County Administration
![Page 53: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/53.jpg)
Available Assistance
• Reduction in Fees– Current fee savings approximately $5,600
• Fees – Assessment in-Lieu– Contact City of Chico 530-879-6950
(Continued…)
![Page 54: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/54.jpg)
Available Assistance• Butte County Housing Rehabilitation
– Loan to qualifying low/moderate income property owners.• Typically 3% interest for 15 year term.• Qualifying income for a family of 4 currently $46,300 or below.
– Loans also available to owners of rental property.• Must sign agreement to rent to low/moderate income individuals.
– Eligible improvements:• Application, permit and connection fees• Sewer lateral construction (including abandonment of septic)• Other housing rehabilitation improvements
![Page 55: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/55.jpg)
Available Assistance• City of Chico Housing Rehabilitation
– Grant provided to qualifying low-moderate income property owners where costs are less than $10,000.
– Loan provided to qualifying low-moderate income property owners where costs are $10,000 or more. (payments may be deferred until sale, transfer or rental)
– Loans not available to owners of rental property.– Eligible improvements:
• Application, permit and connection fees• Sewer lateral construction (including abandonment of septic)
![Page 56: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/56.jpg)
Information and Resources
• Citizens Guide to Sewer Connection• Quarterly Newsletters• www.NitrateCompliance.org
![Page 57: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/57.jpg)
THANK YOU
![Page 58: Project Area 1S Neighborhood Meeting November 14, 2011...How to Connect to Sewer • Do I hire a contractor? • How much time will the construction take? – Estimated time is 2 days](https://reader033.vdocuments.us/reader033/viewer/2022052009/601f1b8a7fd68358bd2195ad/html5/thumbnails/58.jpg)
QUESTIONS