Ladybird House(FP 3-1999) PROJECT CHARTER
Project start date Project end date
1st of May 2002 31st of July 2003
Project objectives Project non-objectives
Refitting plan accomplished
Building authorisation signed
House refitted
House entirely equipped with kindergartenfurniture
Kindergarten curricula prepared
Administrative personnel selected
Educators and social assistants selected
Project phases Project costs Project income
Project Management
Contracting
Refitting design
Permits
Refitting execution
Furniture procurement
Garden & yard decoration
Curricula development
160.000 € Not the case
Project sponsor Project manager
Liviu Crainic – General Manager of the PestalozziFoundation
Ruxandra Enache
Project team members
Monica Borasteanu –project manager assistant (authorisation responsible)
Andrei Manolescu – refitting responsible
Mihai Trinca – procurement responsible
Mihaela Cozarescu – curricula development co-ordinator
Relationships to other projects
Synergies with “ Help for poor families” project
Synergies with “Social Pedagogy ” training program
Conflicts with “Orientation for life” and “Ladybird Day Centre for youths”
Relevant project environments
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 3/17
Community with many very poor families with an great number pre-school children /family –interestedin the project
Child Protection Department should face many social problems concerning the pre-school children (lackof children watch, abuse, lack of basic education, etc) – – should be interested in the project
Local authorities interested to solve the problem for pre-school children – should be interested in theproject because of:
o many pre-school children in the communityo
lack of sufficient kindergartenso lack of financial possibilities for the families to send pre-school children to
kindergarten
The main Pestalozzi Foundation’s sponsor wants diversification of projects and clients - interested in theproject
The actual trend to be involved in child protection filed - other potential donors and sponsors may beinterested in the project
Project manager Project owner (team)
Ruxandra Enache Liviu Crainic –General Manager of the PestalozziFoundation
Version 1.0 Date: 1st of May 2002 Author: Ruxandra Enache
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 4/17
Ladybird House(FP 3-1999) PROJECT OBJECTIVES PLAN
Main objectives
Refitting plan accomplished
Building authorisation signed
House and garden refitted
House entirely equipped with kindergarten furniture
Kindergarten curricula prepared
Additional objectives
Accumulation of experience in developing similar programs
Accumulation of legal information in educational programmes
Partnerships local authorities in child protection filed
Non-objectives
Selection of the administrative personnel
Selection of the educators and social assistants
Selection the kids form poor families
Version 1.0 Date: 1st of May 2002
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 5/17
Ladybird House(FP 3-1999)
PROJECT OBJECTS BREAKDWONSTRUCTURE
Object of Consideration Type Object of Consideration Adapted per…
Contracts Design of the building refitting contract
Execution of the building refitting contract
Utilities contracts (water, electricity, heating, garbagecollecting)
Furniture procurement contract
Permits Urbanism certificate
Sanitary notice, electricity notice, gas notice, water and
canalization notice
Building refit authorisation
Health-care authorisation
Refitting plans Architectural plan and structural plans
Electric wires, plumbing, sewerage and heating systemplans
Procurement Furniture
Internal decorations
Air-conditioning equipment
Gardening decorations
Child swings
Personnel Construction specialist
Curricula specialist
Contracting specialist
Procurement specialist
Kindergarten curricula Educational curricula
Vocational curricula
Long-life skills curricula
Version 1.0 Date: 1st of May 2002 Author: Ruxandra Enache
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 6/17
Ladybird House(FP 3-1999) PROJECT WORK BREAKDOWN STRUCTURE
Version 1.0 Date: 1st of May 2002 Author: Ruxandra Enache
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 7/17
Ladybird House(FP 3-1999) WORK PACKAGE DETAILS
WBS-code:
1.4.1. WP-label: CONTRACTING REFITTING EXECUTION ANDUTILITIES
WP-content Adapted per …
Negotiation for the refitting execution
Preparing documentation for utilities permits
WP resultsWP Progress Measurement(in % or verbally)
Adapted per …
Refitting execution contract
Water supply contract Electricity supply contract
Gas supply contract
Garbage collecting contract
WBS-Code:
1.6.4 WP label: CHILDREN
PLAYGROUND SETTING UP
WP content Adapted per …
Enclosing playground
Transporting sand
Laying down the sand
Buying child swings
Mounting child swings
WP resultsWP Progress Measurement(in % or verbally)
Adapted per …
Children playground finished
Sand place finished
Sand toys procured
Child swings in place
Version 1.0 Date: 1st of May 2002 Author: Ruxandra Enache
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 8/17
Ladybird House(FP 3-1999) BAR CHART
Version 1.0 Date: 1st of May 2002 Author: Ruxandra Enache
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 9/17
Ladybird House(FP 3-1999) PROJECT MILESTONE PLAN
WP-code Milestone Planned date
Planneddateadaptedper …
Actual date
1.1.1.1 Project assigned 1st of May 2002
1.2.5.1. Refitting design approved 4th of November2002
1.3.3.1. Construction authorisation signed 17th of February 2003
1.1.3.2.1. Interim project report approued 26th of Febryary 2003
1.4.5.1. Refitting execution approved 18th of June 2003
1.7.4.1. Curricula signed by authorities 19th of May 2003
1.5.5.1. Furnishing house finished 27th of June 2003
1.4.6.1. Healthcare authorisation signed 9th of July 2003
1.1.3.4.1. Final project report approved 8th of August 2003
1.1.4.1 Project approved 31st of July 2003
Version 1.0 Date: 1st of May 2002 Author: Ruxandra Enache
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 10/17
Ladybird House
(FP 3-1999) PROJECT COST PLAN
WP Code WP Label Cost typePlannedquantity
PricePlanned
costs
TOTAL € 146,800
Phase1.1
Project management € 5,100
1.1.1 Project start Personnel 6PD € 150 € 900
1.1.2 Project coordination Personnel 10PD € 150 € 1,500
Material € 100
1.1.3Project controlling (meetings andreports)
Personnel 8PD € 150 € 1,200
Material € 500
1.1.4 Project close-down Personnel 4PD € 150 € 600
Material € 200
1.1 Project organization risk (see projectrisk analysis) Risk costs
€ 100
Phase1.2
Refitting design € 6,900
1.2.1 Contracting refitting design Material € 100
1.2.2 Technical investigation Contract € 5,000
1.2.3 Architectural design Contract € 900
1.2.4 Structural design Contract € 550
1.2.5Water, electricity,
heating refittingContract € 350
Phase1.3
Permits € 800
1.3.1 Urbanism certificate Material € 100
1.3.2 Utilities permits Material € 350
1.3.3 Construction authorization Material € 200
1.3 Delay of permits approval Risk costs € 150 Phase
1.4Refitting execution € 121,200
1.4.1Contracting refitting execution
and utilitiesMaterial € 100
1.4.2 Structural refitting Contract € 66,000
1.4.3 Water, electricity, heating refitting Contract € 12,000
1.4.4 Carpentry assembling Contract € 12,000
1.4.5 Internal and external finishing Contract € 30,000
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 11/17
1.4.6 Healthcare authorization Material € 250
1.4 Refitting execution risks Risk costs € 850
Phase1.5
Furniture procurement € 6,900
1.5.1 Furniture selection Material € 100
1.5.2Contracting furniture
procurementMaterial € 100
1.5.3 Furniture procurement Contract € 6,500
1.5.4 Furniture transport Contract € 100
1.5.5 Furniture assembling Material € 100
Phase1.6
Garden and yard decoration € 1,900
1.6.1 Cleaning the garden Material € 50
Personnel 2PD € 50 € 100
1.6.2 Fence construction Material € 500
Personnel 2PD € 100 € 200
1.6.3 Landscape gardening Material € 50
Personnel 2PD € 50 € 100
1.6.4 Children playground setting up Material € 500
Personnel 2PD € 50 € 100
1.6.5 Flower seeds planting Material € 200
Personnel 2PD € 50 € 100
Phase1.7
Curricula development € 4,000
1.7.1 Preparing educational curricula Personnel 3PD € 300 € 900
1.7.2 Preparing vocational curricula Personnel 3PD € 300 € 900
1.7.3 Preparing life-long skills curricula Personnel 3PD € 300 € 900
1.7.4Curricula approving
Material € 200
Risk costs 1PD € 500 € 500
1.7.5 Kindergarten curricula assembling Personnel 2PD € 300 € 600
Version 1.0 Date: 1st of May 2002 Author: Ruxandra Enache
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 12/17
Ladybird House(FP 3-1999) PROJECT RESPONSIBILITY MATRIX
Project roles and relevant environments
WBS- code WB label P r o j e c t o w n e r ( t e a m )
P r o j e c t m a n a g e r
P T M
1 ( p r o j e c t m a n a g e r
a s s i s t a n t )
P T M
2 ( r e f i t t i n g r e s p o n s i b l e )
P T M
3 ( p r o c u r e m e n t
r e s p o n s i b l e )
P T M
4 ( c u r r i c u l a d e v e l o p m n e t c o -
o r d i n a t o r )
S u n t e a m 1 ( s o c i a l p e d a g o g y
t r a i n i n g d e p a r t m e n t r e p r e s e n t a t i v e )
S u b t e a m 2 ( d i r e c t p r o j e c t s w t h
c h i l d r e n d e p a r t m e n t r e p r e s e t n t a i v e )
S u b t e a m 3 ( S . C . S t i l D e s i g n S . R .
L . ) –
r e f i t t i n g d e s i g n
S u b t e a m 4 ( S . C . B e s t C o n s t r u c t
S . R . L .
- r e f i t t i n g e x a c u t i o n )
S u n t e a m 3 ( F i n a n c i a l D e p a r t m e
n t )
E n v i r o n m e n t 1 ( a u t h o r i t i e s )
E n v i r o n m e n t 2 ( S u p p l i e r s )
E n v i r o n m e n t 3 ( C o m m u n i t y )
1.1.1 Project start D C1 I I
1.1.2 Project coordination I C1
1.1.4 Project controlling I C1
1.1.5 Project close-down D C1 I I
1.2.1 Contracting refitting design D I P P C1
1.2.2 Technical investigation C,I C P
1.2.3 Architectural design C,I C P
1.2.4 Structural design C,I C P
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 13/17
1.2.5Water, electricity,
heating refittingC,I C P
1.3.1 Urbanism certificate C P C1 C1,D
1.3.2 Legal permits C P C1
1.3.3 Construction authorization I C P C1 C1,D
1.4.1Contracting refittingexecution
and utilities
D C PP
C1
1.4.2 Structural refitting C,I C P
1.4.3Water, electricity, heating
refittingC,I C P
1.4.4 Carpentry assembling C,I C P
1.4.5Internal and externalfinishing
C,I C P
1.4.6 Healthcare authorization I C,I P C1 C1,D
1.5.1 Furniture selection C C1 P
1.5.2Contracting furnitureprocurement
D C P C1 P
1.5.3 Furniture procurement C,I P P
1.5.4 Furniture transport C,I P P
1.5.5 Furniture assembling C,I P P
1.6.1 Cleaning the garden C,I C1 P
1.6.2 Fence construction C,I C1 P P
1.6.3 Landscape gardening C C1 P
1.6.4Children playground setting
upC,I C1 P P
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 14/17
Version 1.0 Date: 1st of May 2002 Author: Ruxandra Enache
Legend: C… coordination, initialisation; P… performance; C1… contribution, consulting; D… decision; I … information
1.6.5 Flower seeds planting C,I C1 P P
1.7.1Preparing educationalcurricula
C,I C,P P P C1
1.7.2Preparing vocational
curriculaC,I C,P P P C1
1.7.3Preparing life-long skills
curriculaC,I C,P P P C1
1.7.4 Curricula approving I C,I C,PC1,D
1.7.5 Kindergarten curriculaassembling C,I C,P P P I I
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 15/17
Ladybird House(FP 3-1999) PROJECT ORGANISATION CHART
Project role Person performing role Telefon e-mail
Project sponsor Liviu Crainic
Project manager Ruxadra Enache
Project Team Member 1 Monica Borasteanu
Project Team Member 2 Andrei Manolescu
Project Team Member 3 Mihai Trinca
Project Team Member 4 Mihaela Cozarescu
S.C. Stil Design S.R.L. Chief Architect - Ileana Petcu
S.C. Best Construct S.R.L. Chief Engineer – Ilie Moraru
Version 1.0 Date: 1st of May 2002 Author: Ruxandra Enache
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 16/17
Ladybird House(FP 3-1999)
PROJECT COMMUNICATIONSTRUCTURES
(other than project status meetings)
Meeting Content Participants Frequency Adapted per …
Project start
workshop Information on the projectobjectives, the projectstructures, strategies,organisation, developingthe “big project picture”
Project team 1x in the projectstart process
Project sponsormeeting
Project status and projectpreview, contextinformation, currentproblems, strategicdecisions
Project owner,project manager,selected projectteam members
Every 2-3 weeks
Project teammeeting
Project status and project
preview, review, definitionof project strategies,
operational decisions
All project team
members,possibly selected
representativesof environments
Every 2-3 weeks
Sub-teammeeting
Problem-solving Sub-teammembers,possibly project
manager andselectedrepresentativesof environments
1x per week
Project close-
downworkshop
Reflection, feedback,dissolving the socialsystem, clarifyingremaining tasks
Project team andproject owner 1x in the projectclose-down process
Version 1.0 Date: 1st of May 2002 Author: Ruxandra Enache
7/21/2019 Project 1.pdf
http://slidepdf.com/reader/full/project-1pdf-56da1736abcfa 17/17
Ladybird House(FP 3-1999) PROJECT RISK ANALYSIS
WBS-code
WP / phase RiskCharacteristic/description
Riskevaluation
MeasureAdaptedper …
1.1.
Projectmanagement
Projectorganization
(Negative
risk)
Unclear roles, lackof experience forthe project’s type,lack of commonunderstanding inwhat co-operationconsists
10% x 30=3 Workshop with theproject team,contributors andproject owner toclarify each oneroles in theproject.
Documentationand information
about otherexperiences insimilar projects
1.3.
Permits Delay for the
approvals
(Negativerisk)
Bureaucracy andlow level ofinterest for the
project
50% x80=40
Lobby
Information
Improvingrelationship withthe authorities
1.4
Refittingexecution
Low qualityof thematerials for
theexecution
(Negativerisk)
Few founds toprocure highquality materials
for refitting
20% x50=10
Lobby for donationand sponsorshipsto buy good quality
materials
1.5.1
Furnituresuppliersselection
FavourableVAT low forNGOs
(Positiverisk)
Finding furnituresuppliers acceptingto not include VATin the furnitureprice
15% x50=7.5
Identification ofthe supplierswilling to help.
1.7.4
Curriculaapproval
Be notapproved by
theauthorities
(Negativerisk)
Not accepted or tomany modifications
required for thecurricula content
80% x80=64
Implication (oneChild Protection
Department’sexpert workingwith project team)
Version 1.0 Date: 1st of May 2002