Progress Report Günther Rosner NuPECC, Milano, 9/3/12 1

Upload: evelyn-garrett

Post on 27-Mar-2015

215 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

Progress Report

Günther Rosner NuPECC, Milano, 9/3/12 1

Page 2: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

1st Birthday

Günther Rosner NuPECC, Milano, 9/3/12 2

Signing of the FAIR Convention by representatives of the founding countriesFinland, France, Germany, India, Poland, Romania, Russia, Slovenia and Sweden

in Wiesbaden on 4/10/2010

Page 3: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

OrgChart FAIR Company

Günther Rosner NuPECC, Milano, 9/3/12 3

BFC

FAIR Council

ManagementBoard

Research

APPA

CBM

NuSTAR

PANDA

Expert C‘ttee Experiments

Project OfficeExperiments

Technical

Division

TechnicalServices

In-Kind Coordination

TechnicalFollow-up

Project Office Techn. Division

Site &Building

s

M&E Eng. Automation,

IT

M&E Eng.Power, Mat.

M&E Eng. Thermo, Refrig.

M&E Eng.Liqu., Gases

Constr. Eng.Building, Geo.

Constr. Managem.

Eng.

ReportingProject Office

Site & Buildings

M&E Advisor Civil Eng. Advisor

Admin.

Internal Services

Controlling

Finance

Purchasing

Personnel

Staff Office

LegalAdvisor

CouncilIssues

Secretariat

Internal Auditing

AFCScientifi

c Council

IKRB MAC

Page 4: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

OrgChart FAIR-GSI Collaboration

Günther Rosner NuPECC, Milano, 9/3/12 4

Page 5: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

Modularised Start Version

Günther Rosner NuPECC, Milano, 9/3/12 5

APPA

CBM/HADES

NuSTAR

PANDAExperimentsM1: APPAM1: CBM/HADESM2: NuSTARM3: PANDA

M0

M1

M2M3

M3

Page 6: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

Costs MSV

Günther Rosner NuPECC, Milano, 9/3/12 6

Accelerators and personnel (including Super-FRS) 502 M€

Civil construction (excluding site related costs) 400 M€

FAIR contribution to experimental end stations * 78 M€

FAIR GmbH personnel & running until 2018 (>8 years) 47 M€

Grand Total MSV, Modules 0 - 3 1027 M€

in 2005 € (inflation escalation until 2018: ca. +50%)

* Total experimental end stations (excluding Super-FRS):ca. 210 M€ (2005) = 315 M€ (2018)

Page 7: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

Timeline

Günther Rosner NuPECC, Milano, 9/3/12 7

20122011 2013 201620152014

6

Building permits

Site preparation

Civil construction contracts

Building of accelerator & detector components

Completion of civil construction work

Installation & commissioning of accelerators and detectors

Start Data taking

7 108

2017 2018 2019

12

6

7

8

9

11

12

10

119

Page 8: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

Civil Construction

Günther Rosner NuPECC, Milano, 9/3/12 8

Page 9: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

Applications & Permits

09 / 11 10 / 11 11 / 11 12 / 11 01 / 12

Clearing permit

Building application

Application for afforestation

Permit for site roads

Application for water rights

31.08.11

11.11.11

19.01.12

20.01.12

21./23.11

Günther Rosner NuPECC, Milano, 9/3/12 9

Page 10: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

First Post Drilling 31/8/2011

Günther Rosner NuPECC, Milano, 9/3/12 10

Page 11: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

Clearing Construction Site 6/12/2011

Günther Rosner NuPECC, Milano, 9/3/12 11

Page 12: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

Further Preparatory Work

01 / 12 02 / 12 03 / 12 04 / 12

Stripping of topsoil(area tree felling)

Site roads (Messeler Parkstr.)

Site roads (southern traffic link)

Site roads (northern traffic link)

Günther Rosner NuPECC, Milano, 9/3/12 12

Page 13: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

Planning Activities01 / 12 02 / 12 03 / 12 04 / 12

Checking and approval ofLph 3

Checking of cost calculations(analysis of differences to ZBau)

Technical route planning(Lph 5)

Statics / layout drawings(Lph 5)

Announcement of logistics

Günther Rosner NuPECC, Milano, 9/3/12 13

Page 14: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

Compact & cost effectiveFast cycling superconducting magnets

dB/dt ~ 4T/s

Accelerators• Ordered for SIS100 from

Babcock Noell in Jan. 2012 (German in-kind contribution, BMBF grant to GSI)

• Many other parts of SIS100 and CR in preparation (in-kind or tender)

• HESR ready to go out for tender (BMBF grant offered to FZ Jülich)

• IKRB meeting at FAIR on 28/3/12

• MAC meeting at FZ Jülich on 2/4/12

Günther Rosner NuPECC, Milano, 9/3/12 14

Page 15: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

MSV Experiments

Günther Rosner NuPECC, Milano, 9/3/12 15

Page 16: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

APPA• Board of APPA

Collaborations established

• Spokesman and Deputy elected

• Layout of APPA hall finalised

• Options explored for experiments at– HESR– Cryring @ ESR

Günther Rosner NuPECC, Milano, 9/3/12 16

APPA

Page 17: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

CBM• HADES detector

upgraded• Collaboration with

Dubna (NICA) being considered

• Finishing R&D work

Günther Rosner NuPECC, Milano, 9/3/12 17

CBM

Page 18: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

NuSTAR• Hall LEB being

considered by Collaboration– search for funds

outside of MSV budget

• Exp. @ HESR being considered

Günther Rosner NuPECC, Milano, 9/3/12 18

NuSTAR

Super-FRS

Page 19: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

PANDA• R&D being

finished• Remaining TDRs

being finalised• Premounting @

FZ Jülich being prepared

Günther Rosner NuPECC, Milano, 9/3/12 19

PANDA

Page 20: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

Timeline Experiments• Finish R&D phase 2012

– Deliver prototypes of all essential parts

• Submit complete sets of TDRs 2012

– Take decisions on alternative technical solutions

• Co-ordinate with 2012

– Civil construction requirements & accelerator setup schedule

• Identify critical pathways, submit risk management plan 2012

– Timelines, milestones, deliverables

• Secure funding, negotiate MoUs between Collaborations,Funding Agencies and FAIR 2012/13

• (Europe-wide) tendering 2013

• Build detectors 2013-16

• Commission detectors 2017

• Initial period of data taking 2018-21

Günther Rosner NuPECC, Milano, 9/3/12 20

Page 21: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

Commissioning & Operation• Commissioning MSV, Modules 0-3

– Top priority: Module 0 – SIS100

– Sequence of experiments depends on

• Civil construction

• Progress in – Prototyping & building of accelerators (storage rings)

– Prototyping & building of production targets (RIB & anti-proton targets)

– Prototyping & setting up of large-scale experimental equipment

• Funding (majority from outwith FAIR MSV budget)

• Operation MSV, Modules 0-3– Signing of agreement on financing the FAIR operation budget

three years after project has started (autumn 2013 at the latest)

• Development of model for fair share of costs for operating FAIR

• Explore– Contributions from participating countries that are not shareholders

– Set up common collaboration funds for running the experiments (cf. DESY & CERN)

• Modules 4 & 5, Phase B– Secure funding for civil construction, accelerators and experiments of Modules 4 & 5

– Continue R&D, in particular for SIS300, HESR Electron Cooler and NESR Electron Ring

Günther Rosner NuPECC, Milano, 9/3/12 21

Page 22: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

FAIR Open Space Planning

Günther Rosner NuPECC, Milano, 9/3/12 2222

Page 23: Progress Report Günther RosnerNuPECC, Milano, 9/3/121

Thank you very much