Progress Report
Günther Rosner NuPECC, Milano, 9/3/12 1
1st Birthday
Günther Rosner NuPECC, Milano, 9/3/12 2
Signing of the FAIR Convention by representatives of the founding countriesFinland, France, Germany, India, Poland, Romania, Russia, Slovenia and Sweden
in Wiesbaden on 4/10/2010
OrgChart FAIR Company
Günther Rosner NuPECC, Milano, 9/3/12 3
BFC
FAIR Council
ManagementBoard
Research
APPA
CBM
NuSTAR
PANDA
Expert C‘ttee Experiments
Project OfficeExperiments
Technical
Division
TechnicalServices
In-Kind Coordination
TechnicalFollow-up
Project Office Techn. Division
Site &Building
s
M&E Eng. Automation,
IT
M&E Eng.Power, Mat.
M&E Eng. Thermo, Refrig.
M&E Eng.Liqu., Gases
Constr. Eng.Building, Geo.
Constr. Managem.
Eng.
ReportingProject Office
Site & Buildings
M&E Advisor Civil Eng. Advisor
Admin.
Internal Services
Controlling
Finance
Purchasing
Personnel
Staff Office
LegalAdvisor
CouncilIssues
Secretariat
Internal Auditing
AFCScientifi
c Council
IKRB MAC
OrgChart FAIR-GSI Collaboration
Günther Rosner NuPECC, Milano, 9/3/12 4
Modularised Start Version
Günther Rosner NuPECC, Milano, 9/3/12 5
APPA
CBM/HADES
NuSTAR
PANDAExperimentsM1: APPAM1: CBM/HADESM2: NuSTARM3: PANDA
M0
M1
M2M3
M3
Costs MSV
Günther Rosner NuPECC, Milano, 9/3/12 6
Accelerators and personnel (including Super-FRS) 502 M€
Civil construction (excluding site related costs) 400 M€
FAIR contribution to experimental end stations * 78 M€
FAIR GmbH personnel & running until 2018 (>8 years) 47 M€
Grand Total MSV, Modules 0 - 3 1027 M€
in 2005 € (inflation escalation until 2018: ca. +50%)
* Total experimental end stations (excluding Super-FRS):ca. 210 M€ (2005) = 315 M€ (2018)
Timeline
Günther Rosner NuPECC, Milano, 9/3/12 7
20122011 2013 201620152014
6
Building permits
Site preparation
Civil construction contracts
Building of accelerator & detector components
Completion of civil construction work
Installation & commissioning of accelerators and detectors
Start Data taking
7 108
2017 2018 2019
12
6
7
8
9
11
12
10
119
Civil Construction
Günther Rosner NuPECC, Milano, 9/3/12 8
Applications & Permits
09 / 11 10 / 11 11 / 11 12 / 11 01 / 12
Clearing permit
Building application
Application for afforestation
Permit for site roads
Application for water rights
31.08.11
11.11.11
19.01.12
20.01.12
21./23.11
Günther Rosner NuPECC, Milano, 9/3/12 9
First Post Drilling 31/8/2011
Günther Rosner NuPECC, Milano, 9/3/12 10
Clearing Construction Site 6/12/2011
Günther Rosner NuPECC, Milano, 9/3/12 11
Further Preparatory Work
01 / 12 02 / 12 03 / 12 04 / 12
Stripping of topsoil(area tree felling)
Site roads (Messeler Parkstr.)
Site roads (southern traffic link)
Site roads (northern traffic link)
Günther Rosner NuPECC, Milano, 9/3/12 12
Planning Activities01 / 12 02 / 12 03 / 12 04 / 12
Checking and approval ofLph 3
Checking of cost calculations(analysis of differences to ZBau)
Technical route planning(Lph 5)
Statics / layout drawings(Lph 5)
Announcement of logistics
Günther Rosner NuPECC, Milano, 9/3/12 13
Compact & cost effectiveFast cycling superconducting magnets
dB/dt ~ 4T/s
Accelerators• Ordered for SIS100 from
Babcock Noell in Jan. 2012 (German in-kind contribution, BMBF grant to GSI)
• Many other parts of SIS100 and CR in preparation (in-kind or tender)
• HESR ready to go out for tender (BMBF grant offered to FZ Jülich)
• IKRB meeting at FAIR on 28/3/12
• MAC meeting at FZ Jülich on 2/4/12
Günther Rosner NuPECC, Milano, 9/3/12 14
MSV Experiments
Günther Rosner NuPECC, Milano, 9/3/12 15
APPA• Board of APPA
Collaborations established
• Spokesman and Deputy elected
• Layout of APPA hall finalised
• Options explored for experiments at– HESR– Cryring @ ESR
Günther Rosner NuPECC, Milano, 9/3/12 16
APPA
CBM• HADES detector
upgraded• Collaboration with
Dubna (NICA) being considered
• Finishing R&D work
Günther Rosner NuPECC, Milano, 9/3/12 17
CBM
NuSTAR• Hall LEB being
considered by Collaboration– search for funds
outside of MSV budget
• Exp. @ HESR being considered
Günther Rosner NuPECC, Milano, 9/3/12 18
NuSTAR
Super-FRS
PANDA• R&D being
finished• Remaining TDRs
being finalised• Premounting @
FZ Jülich being prepared
Günther Rosner NuPECC, Milano, 9/3/12 19
PANDA
Timeline Experiments• Finish R&D phase 2012
– Deliver prototypes of all essential parts
• Submit complete sets of TDRs 2012
– Take decisions on alternative technical solutions
• Co-ordinate with 2012
– Civil construction requirements & accelerator setup schedule
• Identify critical pathways, submit risk management plan 2012
– Timelines, milestones, deliverables
• Secure funding, negotiate MoUs between Collaborations,Funding Agencies and FAIR 2012/13
• (Europe-wide) tendering 2013
• Build detectors 2013-16
• Commission detectors 2017
• Initial period of data taking 2018-21
Günther Rosner NuPECC, Milano, 9/3/12 20
Commissioning & Operation• Commissioning MSV, Modules 0-3
– Top priority: Module 0 – SIS100
– Sequence of experiments depends on
• Civil construction
• Progress in – Prototyping & building of accelerators (storage rings)
– Prototyping & building of production targets (RIB & anti-proton targets)
– Prototyping & setting up of large-scale experimental equipment
• Funding (majority from outwith FAIR MSV budget)
• Operation MSV, Modules 0-3– Signing of agreement on financing the FAIR operation budget
three years after project has started (autumn 2013 at the latest)
• Development of model for fair share of costs for operating FAIR
• Explore– Contributions from participating countries that are not shareholders
– Set up common collaboration funds for running the experiments (cf. DESY & CERN)
• Modules 4 & 5, Phase B– Secure funding for civil construction, accelerators and experiments of Modules 4 & 5
– Continue R&D, in particular for SIS300, HESR Electron Cooler and NESR Electron Ring
Günther Rosner NuPECC, Milano, 9/3/12 21
FAIR Open Space Planning
Günther Rosner NuPECC, Milano, 9/3/12 2222