progress report aanamitra as on 07-06-2014
TRANSCRIPT
-
8/12/2019 Progress Report AANAMITRA as on 07-06-2014
1/5
Sl no. Description
1 Administrative Sanction
2 Technical sanction
3 Details of Package works
4 Total no. of houses proposed
5No. of houses taken up in 1st
phase
8 Name of the Agency
9 Agreement no.
10 Agt Date
11 Estimate Contract Value
12 TP quoted
13 Tender Contract Value
14 Phasing of Works
15 Prirotized buildings
16 EOAT granted upto
17 Progress of worksAs On Date Progress
Num of Houses
To Be
Executed% Of work
As On Date
Progress Num of
Houses
To Be Executed % Of work
As On Date
Progress
Num of
Houses
To Be
Executed
a) Earth work 8 - 100% 11 - 100% 17 -
b) PCC 8 - 100% 11 - 100% 17 -
c) Footings/Pedastals 8 - 100% 11 - 100% 17 -
d) Up to Plinth Beam 8 - 100% 11 - 100% 17 -
e) Plinth Beam level 8 - 100% 11 - 100% 17 -
f) GF Level 8 - 100% 11 - 100% 17 3
g) GF Slab laid 8 - 100% 11 - 100% 17 3
h) FF Level 8 - 100% 11 1 91% 17 3
i) FF Slab laid 8 - 100% 11 1 91% 17 3
j) G.F Masonery 8 - 100% 11 1 91% 17 3
k) F.F Masonery 8 - 100% 11 1 91% 17 3
i) Civil Works
Rs. 225 crores dt:- 14.11.2008
Rs.172 crores dt:- 14.11.2008
Package III
(Basic)
Package II
(Intrinsic)
Package I
(Classic+Dev)
Name of the Project:- ANAMITHRA Township at SRIKAKULAM , Progress Report as on 07.06.2014
Rs 47539170/-
2.7.2010
06/ 2010-11/APRSCL/Dated 2.07.2010
M/s SVC Projects P
Ltd.,Visakhapatna
07/ 2010-11/APRSCL/Dated
Classic+Dev works Intrinsic Basic
172
60
M/s SVC Projects Pvt. Ltd.,Visakhapatnam.
51/ 2008-09/APRSCL/Dated 17.02.2009
M/s SVC Projects Pvt. Ltd.,Visakhapatnam.
466
40
442
60
@ 5.22% Less @ 5.22% Less @ 5.22% Less
Rs 268502066/-
Rs.283289793/- Rs.40644916/-
2.7.201017.2.2009
60
30.06.2014
40
Rs.38523252/- Rs 45057625/-
60
30.06.2014 30.06.2014
8 11 17
-
8/12/2019 Progress Report AANAMITRA as on 07-06-2014
2/5
l) Internal Plasterings 8 - 100% 11 1 91% 17 3
m) External Plasterings 8 - 100% 11 1 91% 17 3
n) Internal Electrification 1 7 13% 1 10 9% 1 16
o) Internal Watersupply &
Sanitary8 - 100% 11 - 100% 15 2
p) Paintings 1 7 13% 1 10 9% 1 16
q) Tiles 1 7 13% 1 10 9% 1 16
r)Internal Finishes &Miscellenous 1 7 13% 1 10 9% 1 16
s)Model Houses completed - 100% completed - 100% completed -
a) Development works
b) Retaining walls
a) Compound wall
b) Entrance gate
c) OHSR & Sump
d) Roads
e) External sewarage and
water supply
f) External Electrification
Started,South side boundry completed.
ii)Site Development Works
iii)Infrasturucture Works
Work In Progress Date of Completion 20-06-2014
Work In Progress Date of Completion 30-06-2014.
OHSR is completed with railing work and vertical connections to be done . For Sump top slab is completed and Pump room is completed .
Pumps & Motors. Work In progress Date of Completion 30-06-2014
Formation work 90% completed, kerb walls for median and foot paths Done. Work I Progress Date of Completion 30-06-2014
Sewerage works in Classic and Intrinsic zonesand Civic are in progress and nearly completion. Date of Completion 30-06-2014
Agreement for street lighting is concluded with S.R. Communications, Hyderabad. External electri fication agreemented to SERVO MAX,
Progress
Asst.General Manager Deputy General ManagerAPRSCL,Srikakulam APRSCL,Srikakulam
Civil structure and steel fabrication work completed. Finishing with ACP panneling work to be done. Work In Progress Date of Completion
-
8/12/2019 Progress Report AANAMITRA as on 07-06-2014
3/5
1725292
15046746 41640498 34794353 71580085
2086671 3701842 3927847 4097678
1126573 2196830 1922715 5314330
12561431 47539170 40644915 108811838
44652869 87320722
6875877 4439848
70049013
4741934 283289793
6482759
163623873
-
8/12/2019 Progress Report AANAMITRA as on 07-06-2014
4/5
% Of
work
As On Date
Progress
Num of
Houses
To Be
Executed% Of work
100% 18 - 100%
100% 18 1 94%
100% 18 1 94%
100% 18 1 94%
100% 18 1 94%
82% 18 2 89%
82% 18 2 89%
82% - - -
82% - - -
82% 18 2 89%
82% _ - -
30-Jun-14
30-Jun-14
30-Jun-14
30-Jun-14
30-Jun-14
30-Jun-14
30-Jun-14
30-Jun-14
30-Jun-14
30-Jun-14
Package IV
(Civic & Infrastructure)
2.7.2010
Rs.163623876/-
40
30.06.201418
t.
.M/s SVC Projects Pvt. Ltd.,Visakhapatnam.
.07.2010 08/ 2010-11/APRSCL/Dated 2.07.2010
Civic & Infrastructure
389
40
@ 1.80% Less
Rs 160678647-
Date Of
Completion
For All
Packages
Total
1469
200
-
8/12/2019 Progress Report AANAMITRA as on 07-06-2014
5/5
82% 18 2 89%
82% 18 2 89%
6% 4 14 22%
88% 18 - 100%
6% 1 17 6%
6% 5 13 28%
6% 4 14 22%
100% completed - 100%
30-Jun-14
30-Jun-14
30-Jun-14
30-Jun-14
ork entrusted for
, Hyderabad. Work In
30-Jun-14
30-Jun-14
30-Jun-14
General ManagerAPRSCL,Srikakulam
30-06-2014
-